Underground large-scale hole tank system and nitrogen replacement method thereof

By setting up distributed oil and gas pipes and nitrogen injection pipes in large underground oil storage tanks, and monitoring and adjusting flow using oxygen content analyzer, the problems of long nitrogen replacement cycle and insufficient replacement in the prior art are solved, and the further development is achieved. Safe and efficient nitrogen replacement effect.

CN118934039AActive Publication Date: 2024-11-12CHINA NAT OFFSHORE OIL CORP +2
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411022175.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-29
Publication Date
2024-11-12
Estimated Expiration
2044-07-29

AI Technical Summary

Technical Problem

The existing large underground oil storage tank has a long period of nitrogen replacement and insufficient replacement, which poses safety hazards.

Method used

A large underground cave tank system was designed. By setting up multiple oil storage cave chambers between the oil storage cave chambers and connecting them through multiple connecting tunnels, distributed oil and gas pipes and nitrogen injection pipes were set up, and monitoring was performed using an oxygen content analyzer. Gas oxygen content, adjust flow control, and ensure sufficient nitrogen replacement.

Benefits of technology

It significantly reduces the nitrogen replacement cycle, avoids safety hazards caused by insufficient replacement, and achieves safer and more efficient nitrogen replacement.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118934039A_ABST
    Figure CN118934039A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of underground oil storage cave tank construction, in particular to an underground large cave tank system and a nitrogen replacement method thereof. The invention provides an underground large-scale cavern system. The underground large-scale cavern system comprises a vertical shaft, an oil storage cavern, a connecting roadway, an oil-gas pipe and a nitrogen injection pipe, the multiple oil storage caverns are arranged at intervals, all the oil storage caverns are communicated through the multiple connecting roadways, and the vertical shafts are communicated with the oil storage caverns; an oil gas pipe and a nitrogen injection pipe are arranged at the intersection of each oil storage cavern and the connecting roadway, a distributed arrangement mode is adopted, gas short circuit of a nitrogen inlet and a gas outlet is avoided, the duration of a nitrogen replacement period can be obviously shortened, meanwhile, replacement is sufficient through the arrangement mode, and potential safety hazards are avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of underground oil storage cavern construction, and in particular to a large underground cavern system and a nitrogen replacement method thereof. Background Art

[0002] Before the first oil filling of a large underground oil storage cave tank, the original air in the cave tank needs to be discharged through nitrogen replacement to avoid the formation of an explosive mixture between the volatilized oil gas and the oxygen in the air after the oil is filled.

[0003] Traditionally, nitrogen injection and air discharge are carried out by vertically inserting nitrogen pipes and oil and gas pipes into a vertical shaft. Due to the large space of the cavern, a large amount of nitrogen is required for replacement. For the millions of cubic meters in the cavern, the density of nitrogen and air is almost the same, and a long time of diffusion is required. As a result, the nitrogen replacement cycle is long. At the same time, there are safety hazards caused by insufficient replacement. Summary of the invention

[0004] The purpose of the present invention is to provide a large underground cavern system and a nitrogen replacement method thereof, so as to solve the technical problems in the prior art that the nitrogen replacement cycle is long and there is also the potential safety hazard caused by insufficient replacement.

[0005] The present invention provides an underground large cavern system, comprising: a vertical shaft, an oil storage cavern, a connecting tunnel, an oil and gas pipe and a nitrogen injection pipe;

[0006] The oil storage caverns are arranged in multiple intervals, and all the oil storage caverns are connected through multiple connecting tunnels, and the vertical shaft is connected to the oil storage caverns;

[0007] Each of the oil storage caverns is provided with a plurality of the oil and gas pipes, and the oil and gas pipes correspond to the connecting lanes one by one, one end of each of the oil and gas pipes extends to the intersection of the corresponding connecting lane and the oil storage cavern, and the other end extends to the vertical shaft for exhaust;

[0008] Each of the oil storage caverns is provided with a plurality of nitrogen injection pipes corresponding one-to-one with the oil and gas pipes, and the nitrogen injection pipes correspond one-to-one with the connecting lanes. The outlet end of each nitrogen injection pipe extends to the intersection of the corresponding connecting lane and the oil storage cavern, and the inlet end extends to the vertical shaft for introducing nitrogen.

[0009] As a further technical solution, each of the oil and gas pipes is provided with a first flow meter, a first control valve, a sampling pipe and a sampling valve provided on the sampling pipe, wherein the first flow meter is used to monitor the flow in the oil and gas pipe, the first control valve is used to adjust the flow in the oil and gas pipe, the sampling pipe is connected to an oxygen content analyzer and is used to sample the oxygen content analyzer, and the sampling valve is used to open or close the sampling pipe;

[0010] Each of the nitrogen injection pipes is provided with a second flow meter and a second control valve, wherein the second flow meter is used to monitor the flow in the nitrogen injection pipe, and the second control valve is used to adjust the flow in the nitrogen injection pipe.

[0011] As a further technical solution, it further comprises a nitrogen main pipe, which is arranged in the vertical shaft, and the air inlet ends of all the nitrogen injection pipes are connected to the nitrogen main pipe;

[0012] and / or;

[0013] It also includes an oil and gas main pipe, which is arranged in the vertical shaft, and the exhaust ends of all the oil and gas pipes are connected to the oil and gas main pipe.

[0014] As a further technical solution, three connecting lanes are provided, namely a first connecting lane, a second connecting lane and a third connecting lane;

[0015] Along the length direction of the oil storage cavern, the distance between the first connecting tunnel and the vertical shaft is D1, the distance between the second connecting tunnel and the vertical shaft is D2, the distance between the third connecting tunnel and the vertical shaft is D3, and D1<D2<D3.

[0016] As a further technical solution, the height of the oil storage cavern is H, the first connecting lane is located at 2 / 3H-H of the oil storage cavern, the second connecting lane is located at 1 / 3H-2 / 3H of the oil storage cavern, and the third connecting lane is located at 0-1 / 3H of the oil storage cavern.

[0017] As a further technical solution, the length of the oil storage cavern is L, the height of the oil storage cavern is H, the width of the oil storage cavern is W, and L≥15×H, 0.5H≤W≤H.

[0018] As a further technical solution, the portion of the nitrogen injection pipe located in the oil storage cavern and the portion of the oil and gas pipe located in the oil storage cavern are both located at the top of the oil storage cavern.

[0019] The present invention provides a nitrogen replacement method for a large underground cavern system, which is used for the large underground cavern system. The nitrogen replacement method comprises the following steps:

[0020] S1, close the sampling tube on each oil and gas pipe through the sampling valve, and introduce nitrogen into all nitrogen injection pipes;

[0021] S2, opening the sampling tube on each oil and gas pipe through the sampling valve to start sampling, and detecting the oxygen content of the gas in each sampling tube through the oxygen content analyzer;

[0022] S3, calculating the average oxygen content of the gas in all sampling tubes;

[0023] S4, when the average oxygen content of the gas in all sampling tubes is between 2% and 5%, stop introducing nitrogen into all nitrogen injection tubes.

[0024] As a further technical solution, a judgment and adjustment step is also included, and the judgment and adjustment step includes:

[0025] Compare the oxygen content of the gas in each sampling tube with the average oxygen content of the gas in all the sampling tubes. If the oxygen content of the gas in a sampling tube exceeds 10% of the average oxygen content of the gas in all the sampling tubes, increase the opening of the first control valve on the oil and gas pipe corresponding to the sampling tube and increase the opening of the second control valve on the nitrogen injection pipe corresponding to the oil and gas pipe;

[0026] The sampling tube whose oxygen content exceeds 10% of the average value of the oxygen content of the gas in all the sampling tubes is tested by an oxygen content analyzer. When the oxygen content of the gas in this sampling tube is within ±10% of the average value of the oxygen content of the gas in all the sampling tubes, the opening of the first control valve on the oil and gas pipe corresponding to the sampling tube is restored, and the opening of the second control valve on the nitrogen injection pipe corresponding to the oil and gas pipe is restored.

[0027] As a further technical solution, step S2 also includes: obtaining the total amount of nitrogen introduced into all the oil storage caverns through the second flow meter on each nitrogen injection pipe, and when the total amount of nitrogen introduced accounts for 70%-99% of the total volume of all the oil storage caverns, opening the sampling tube on each oil and gas pipe through the sampling valve to start sampling, and detecting the oxygen content of the gas in each sampling tube through the oxygen content analyzer.

[0028] Compared with the prior art, the large underground cavern system and nitrogen replacement method provided by the present invention have the following technical advantages:

[0029] The large underground cave tank system provided by the present invention comprises: a vertical shaft, an oil storage cavern, a connecting tunnel, an oil and gas pipe and a nitrogen injection pipe; a plurality of oil storage caverns are arranged at intervals, and all the oil storage caverns are connected through a plurality of connecting tunnels, and the vertical shaft is connected with the oil storage caverns; a plurality of oil and gas pipes are arranged in each oil storage cavern, and the oil and gas pipes correspond to the connecting tunnels one by one, one end of each oil and gas pipe extends to the intersection of the corresponding connecting tunnel and the oil storage cavern, and the other end extends to the vertical shaft for exhaust; a plurality of nitrogen injection pipes corresponding to the oil and gas pipes are arranged in each oil storage cavern, and the nitrogen injection pipes correspond to the connecting tunnels one by one, the gas outlet end of each nitrogen injection pipe extends to the intersection of the corresponding connecting tunnel and the oil storage cavern, and the gas inlet end extends to the vertical shaft for nitrogen introduction.

[0030] Oil and gas pipes and nitrogen injection pipes are installed at the intersection of each oil storage cavern and the connecting tunnel. A distributed setting is adopted to avoid gas short circuit between the nitrogen inlet and the gas outlet, and can significantly reduce the duration of the nitrogen replacement cycle. At the same time, this setting method ensures sufficient replacement and avoids safety hazards.

[0031] The nitrogen replacement method for the underground large cavern system provided by the present invention is used for the above-mentioned underground large cavern system. Therefore, the technical advantages and effects achieved by it include the technical advantages and effects achieved by the above-mentioned underground large cavern system, which will not be elaborated in detail here.

[0032] Other features and advantages of the present invention will be described in detail in the following detailed description. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0034] Figure 1 A schematic diagram of a large underground cave tank system provided by an embodiment of the present invention;

[0035] Figure 2 A cross-sectional view of a large underground cave tank system provided by an embodiment of the present invention;

[0036] Figure 3 A cross-sectional view of an oil storage cavern provided in an embodiment of the present invention;

[0037] Figure 4 A schematic diagram of an oil and gas pipeline provided in an embodiment of the present invention;

[0038] Figure 5A schematic diagram of a nitrogen injection pipeline provided in an embodiment of the present invention.

[0039] Icons: 1-vertical shaft; 2-oil storage cavern; 3-pipeline group; 4-oil and gas pipe; 5-nitrogen injection pipe; 6-first flow meter; 7-first control valve; 8-sampling tube; 9-oxygen content analyzer; 10-second flow meter; 11-second control valve; 12-first connecting tunnel; 13-second connecting tunnel; 14-third connecting tunnel; 15-nitrogen main pipe; 16-oil and gas main pipe; 17-sampling valve. DETAILED DESCRIPTION

[0040] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0041] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0042] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0043] In addition, the technical solutions between the various embodiments can be combined with each other, but it must be based on the fact that ordinary technicians in the field can implement it. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such combination of technical solutions does not exist and is not within the scope of protection required by the present invention.

[0044] The present invention is further described in detail below through specific implementation examples in conjunction with the accompanying drawings.

[0045] Specific structure such as Figures 1 to 5 shown.

[0046] The present embodiment provides an underground large cave tank system, comprising: a vertical shaft 1, an oil storage cavern 2, a connecting tunnel, an oil and gas pipe 4 and a nitrogen injection pipe 5; the oil storage cavern 2 is arranged with a plurality of intervals, and all the oil storage caverns 2 are connected through a plurality of the connecting tunnels, and the vertical shaft 1 is connected with the oil storage cavern 2; each of the oil storage cavern 2 is provided with a plurality of the oil and gas pipes 4, and the oil and gas pipes 4 correspond to the connecting tunnels one by one, one end of each of the oil and gas pipes 4 extends to the intersection of the corresponding connecting tunnel and the oil storage cavern 2, and the other end extends to the vertical shaft 1 for exhaust; each of the oil storage cavern 2 is provided with a plurality of the nitrogen injection pipes 5 corresponding to the oil and gas pipes 4 one by one, and the nitrogen injection pipes 5 correspond to the connecting tunnels one by one, the outlet end of each of the nitrogen injection pipes 5 extends to the intersection of the corresponding connecting tunnel and the oil storage cavern 2, and the inlet end extends to the vertical shaft 1 for nitrogen introduction.

[0047] In this embodiment, a plurality of pipeline groups 3 are arranged in each of the oil storage caverns 2, and the pipeline groups 3 correspond to the connecting tunnels one by one, one end of each pipeline group 3 extends to the intersection of the corresponding connecting tunnel and the oil storage cavern 2, and the other end extends to the vertical shaft 1; wherein each pipeline group 3 includes oil and gas pipes 4 and nitrogen injection pipes 5 corresponding to each other.

[0048] In this embodiment, an oil and gas pipe 4 and a nitrogen injection pipe 5 are arranged at the intersection of each oil storage cavern 2 and the connecting tunnel, and a distributed arrangement is adopted to avoid gas short circuit between the nitrogen inlet and the gas outlet, and can significantly reduce the duration of the nitrogen replacement cycle. At the same time, this arrangement method can fully replace the gas and avoid safety hazards.

[0049] In the optional technical solution of this embodiment, each of the oil and gas pipes 4 is provided with a first flow meter 6, a first control valve 7, a sampling tube 8 and a sampling valve 17 arranged on the sampling tube 8, the first flow meter 6 is used to monitor the flow in the oil and gas pipe 4, the first control valve 7 is used to adjust the flow in the oil and gas pipe 4, the sampling tube 8 is connected to the oxygen content analyzer 9 and is used to sample the oxygen content analyzer 9, and the sampling valve 17 is used to open or close the sampling tube 8; each of the nitrogen injection pipes 5 is provided with a second flow meter 10 and a second control valve 11, the second flow meter 10 is used to monitor the flow in the nitrogen injection pipe 5, and the second control valve 11 is used to adjust the flow in the nitrogen injection pipe 5.

[0050] In this embodiment, the flow rate in the oil and gas pipe 4 is monitored by the first flow meter 6, and the flow rate in the nitrogen injection pipe 5 is monitored by the second flow meter 10. When the value monitored by the second flow meter 10 is significantly greater than the value monitored by the first flow meter 6, it means that the pressure at the corresponding part of the oil storage cavern is relatively large and there is a danger. At this time, the opening of the first control valve 7 can be increased and / or the opening of the second control valve 11 can be reduced. If there is no improvement, it means that the oil and gas pipe 4 is blocked and needs to be repaired in time. At the same time, the total amount of nitrogen introduced into all the oil storage caverns 2 can be obtained through the values ​​monitored by all the second flow meters 10. One end of the sampling tube 8 is connected to the oil and gas pipe 4, and the other end is connected to the oxygen content analyzer 9. By opening the sampling valve 17, the sampling tube 8 can obtain the flow rate in the oil and gas pipe 4, so as to realize sampling for the oxygen content analyzer 9.

[0051] The optional technical solution of this embodiment further includes a nitrogen main pipe 15, which is arranged in the vertical shaft 1, and the air inlet ends of all the nitrogen injection pipes 5 are connected to the nitrogen main pipe 15; one end of the nitrogen main pipe 15 extends out of the vertical shaft 1, and the other end is connected to all the nitrogen injection pipes 5, so as to avoid confusion of the pipelines in the vertical shaft 1. And / or; an oil and gas main pipe 16 is also included, which is arranged in the vertical shaft 1, and the exhaust ends of all the oil and gas pipes 4 are connected to the oil and gas main pipe 16. One end of the oil and gas main pipe 16 extends out of the vertical shaft 1, and the other end is connected to all the oil and gas pipes 4, so as to avoid confusion of the pipelines in the vertical shaft 1.

[0052] The present embodiment is not limited thereto, and all of the nitrogen injection pipes 5 may extend out of the vertical shaft 1 , or all of the oil and gas pipes 4 may extend out of the vertical shaft 1 .

[0053] In the optional technical solution of this embodiment, there are three connecting tunnels, namely the first connecting tunnel 12, the second connecting tunnel 13 and the third connecting tunnel 14; along the length direction of the oil storage cavern 2, the distance between the first connecting tunnel 12 and the vertical shaft 1 is D1, the distance between the second connecting tunnel 13 and the vertical shaft 1 is D2, the distance between the third connecting tunnel 14 and the vertical shaft 1 is D3, and D1<D2<D3.

[0054] In the optional technical solution of this embodiment, the height of the oil storage cavern 2 is H, the first connecting tunnel 12 is located at 2 / 3H-H of the oil storage cavern 2, the second connecting tunnel 13 is located at 1 / 3H-2 / 3H of the oil storage cavern 2, and the third connecting tunnel 14 is located at 0-1 / 3H of the oil storage cavern 2.

[0055] In this embodiment, by providing three connecting tunnels at different heights, effective connectivity between multiple oil storage caverns 2 can be ensured, thereby improving the flexibility of storage and transportation.

[0056] In this embodiment, the number of the oil storage caverns 2 is preferably two or three, but the invention is not limited thereto and may be other numbers.

[0057] In this embodiment, three oil storage caverns 2 are provided as an example. In this case, nine pipeline groups 3 are provided, that is, nine oil and gas pipes 4 and nine nitrogen injection pipes 5 are provided.

[0058] In the optional technical solution of this embodiment, the length of the oil storage cavern 2 is L, the height of the oil storage cavern 2 is H, the width of the oil storage cavern 2 is W, and L≥15×H, 0.5H≤W≤H. Such a setting is convenient for construction and structural design. The reason for the restriction here is that if the oil storage cavern 2 is too short and the cross-sectional area is large, gas replacement is easier, and the effect is better for a relatively slender oil storage cavern 2. The more slender the oil storage cavern 2, the longer the gas circulation path is, and it is more difficult to replace qualified.

[0059] In the optional technical solution of this embodiment, the part of the nitrogen injection pipe 5 located in the oil storage cavern 2 and the part of the oil and gas pipe 4 located in the oil storage cavern 2 are both located at the top of the oil storage cavern 2. This prevents the nitrogen injection pipe 5 and the oil and gas pipe 4 from being submerged after the oil storage cavern 2 is filled with oil.

[0060] The present embodiment provides a nitrogen replacement method for a large underground cavern system, which is used for the above-mentioned large underground cavern system. Therefore, the technical advantages and effects achieved by the nitrogen replacement method for a large underground cavern system include the technical advantages and effects achieved by the above-mentioned large underground cavern system, which will not be repeated here.

[0061] The nitrogen replacement method comprises the steps of:

[0062] S1, close the sampling tube 8 on each oil and gas pipe 4 through the sampling valve 17, and introduce nitrogen into all nitrogen injection pipes 5;

[0063] S2, opening the sampling tube 8 on each oil and gas pipe 4 through the sampling valve 17 to start sampling, and detecting the oxygen content of the gas in each sampling tube 8 through the oxygen content analyzer 9;

[0064] S3, calculating the average oxygen content of the gas in all sampling tubes 8;

[0065] S4, when the average oxygen content of the gas in all the sampling tubes 8 is between 2% and 5%, the nitrogen is stopped from being introduced into all the nitrogen injection tubes 5.

[0066] In this embodiment, the nitrogen replacement method can effectively reduce the replacement time and achieve sufficient replacement.

[0067] The optional technical solution of this embodiment further includes a judgment and adjustment step, which includes:

[0068] The oxygen content of the gas in each sampling tube 8 is compared with the average oxygen content of the gas in all the sampling tubes 8. If the oxygen content of the gas in any sampling tube 8 exceeds 10% of the average oxygen content of the gas in all the sampling tubes 8, the opening of the first control valve 7 on the oil and gas pipe 4 corresponding to the sampling tube 8 is increased, and the opening of the second control valve 11 on the nitrogen injection pipe 5 corresponding to the oil and gas pipe 4 is increased;

[0069] The sampling tube 8 whose oxygen content exceeds 10% of the average value of the oxygen content of the gas in all the sampling tubes 8 is detected by the oxygen content analyzer 9. When the oxygen content of the gas in this sampling tube 8 is within ±10% of the average value of the oxygen content of the gas in all the sampling tubes 8, the opening of the first control valve 7 on the oil and gas pipe 4 corresponding to this sampling tube 8 is restored, and the opening of the second control valve 11 on the nitrogen injection pipe 5 corresponding to this oil and gas pipe 4 is restored.

[0070] In this embodiment, the judging and adjusting step is performed after step S3, and the nitrogen replacement effect and safety can be effectively guaranteed by the judging and adjusting step.

[0071] In the optional technical solution of this embodiment, step S2 also includes: obtaining the total amount of nitrogen introduced into all the oil storage caverns 2 through the second flowmeter 10 on each nitrogen injection pipe 5, and when the total amount of nitrogen introduced accounts for 70%-99% of the total volume of all the oil storage caverns 2, the sampling tube 8 on each oil and gas pipe 4 is opened through the sampling valve 17 to start sampling, and the oxygen content of the gas in each sampling tube 8 is detected by the oxygen content analyzer 9.

[0072] In this embodiment, sampling is started after the total amount of nitrogen introduced accounts for 70%-99% of the total volume of the entire oil storage cavern 2, ensuring that there is a certain amount of nitrogen in the oil storage cavern 2. At this time, the sampling data is more accurate, effectively ensuring the reliability of the judgment and adjustment steps. Preferably, sampling is started after the total amount of nitrogen introduced accounts for 80% of the total volume of the entire oil storage cavern 2, which has a better effect.

[0073] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A large underground cavern system, characterized in that: include: A vertical shaft (1), an oil storage cavern (2), a connecting tunnel, an oil and gas pipe (4) and a nitrogen injection pipe (5); The oil storage caverns (2) are arranged in plurality at intervals, and all the oil storage caverns (2) are connected via a plurality of connecting tunnels, and the vertical shaft (1) is connected to the oil storage caverns (2); A plurality of oil and gas pipes (4) are arranged in each of the oil storage caverns (2), and the oil and gas pipes (4) correspond to the connecting tunnels one by one. One end of each of the oil and gas pipes (4) extends to the intersection of the corresponding connecting tunnel and the oil storage cavern (2), and the other end extends to the vertical shaft (1) for exhaust. Each of the oil storage caverns (2) is provided with a plurality of nitrogen injection pipes (5) corresponding one-to-one with the oil and gas pipes (4), and the nitrogen injection pipes (5) correspond one-to-one with the connecting tunnels. The gas outlet end of each nitrogen injection pipe (5) extends to the intersection of the corresponding connecting tunnel and the oil storage cavern (2), and the gas inlet end extends to the vertical shaft (1) for introducing nitrogen.

2. The underground large cave tank system according to claim 1, characterized in that: Each of the oil and gas pipes (4) is provided with a first flow meter (6), a first control valve (7), a sampling pipe (8), and a sampling valve (17) provided on the sampling pipe (8); the first flow meter (6) is used to monitor the flow in the oil and gas pipe (4); the first control valve (7) is used to adjust the flow in the oil and gas pipe (4); the sampling pipe (8) is connected to an oxygen content analyzer (9) and is used to sample the oxygen content analyzer (9); and the sampling valve (17) is used to open or close the sampling pipe (8); Each of the nitrogen injection pipes (5) is provided with a second flow meter (10) and a second control valve (11); the second flow meter (10) is used to monitor the flow rate in the nitrogen injection pipe (5); and the second control valve (11) is used to adjust the flow rate in the nitrogen injection pipe (5).

3. The underground large cavern system according to claim 1, characterized in that: It also includes a nitrogen main pipe (15), which is arranged in the vertical shaft (1), and the air inlet ends of all the nitrogen injection pipes (5) are connected to the nitrogen main pipe (15); and / or; It also comprises an oil and gas main pipe (16), which is arranged in the vertical shaft (1), and the exhaust ends of all the oil and gas pipes (4) are connected to the oil and gas main pipe (16).

4. The underground large cavern system according to claim 1, characterized in that: The connecting lanes are provided with three, namely a first connecting lane (12), a second connecting lane (13) and a third connecting lane (14); Along the length direction of the oil storage cavern (2), the distance between the first connecting tunnel (12) and the vertical shaft (1) is D1, the distance between the second connecting tunnel (13) and the vertical shaft (1) is D2, and the distance between the third connecting tunnel (14) and the vertical shaft (1) is D3, and D1<D2<D3.

5. The underground large cave tank system according to claim 4, characterized in that: The height of the oil storage cavern (2) is H, the first connecting tunnel (12) is located at 2 / 3H-H of the oil storage cavern (2), the second connecting tunnel (13) is located at 1 / 3H-2 / 3H of the oil storage cavern (2), and the third connecting tunnel (14) is located at 0-1 / 3H of the oil storage cavern (2).

6. The underground large cavern system according to any one of claims 1 to 5, characterized in that: The length of the oil storage cavern (2) is L, the height of the oil storage cavern (2) is H, the width of the oil storage cavern (2) is W, and L≥15×H, 0.5H≤W≤H.

7. The underground large cavern system according to any one of claims 1 to 5, characterized in that: The portion of the nitrogen injection pipe (5) located in the oil storage cavern (2) and the portion of the oil and gas pipe (4) located in the oil storage cavern (2) are both located at the top of the oil storage cavern (2).

8. A nitrogen replacement method for a large underground cavern system, characterized in that: For the underground large cavern system according to any one of claims 1 to 7, the nitrogen replacement method comprises the steps of: S1, closing the sampling tube (8) on each oil and gas pipe (4) through a sampling valve (17), and introducing nitrogen into all nitrogen injection tubes (5); S2, opening the sampling tube (8) on each oil and gas pipe (4) through the sampling valve (17) to start sampling, and detecting the oxygen content of the gas in each sampling tube (8) through the oxygen content analyzer (9); S3, calculating the average oxygen content of the gas in all sampling tubes (8); S4, when the average oxygen content of the gas in all the sampling tubes (8) is between 2% and 5%, the introduction of nitrogen into all the nitrogen injection tubes (5) is stopped.

9. The nitrogen replacement method for underground large cavern system according to claim 8, characterized in that: The method further includes a judgment and adjustment step, wherein the judgment and adjustment step includes: The oxygen content of the gas in each sampling tube (8) is compared with the average oxygen content of the gas in all the sampling tubes (8). If the oxygen content of the gas in a sampling tube (8) exceeds 10% of the average oxygen content of the gas in all the sampling tubes (8), the opening of the first control valve (7) on the oil and gas pipe (4) corresponding to the sampling tube (8) is increased, and the opening of the second control valve (11) on the nitrogen injection pipe (5) corresponding to the oil and gas pipe (4) is increased; A sampling tube (8) whose oxygen content exceeds 10% of the average value of the oxygen content of the gas in all the sampling tubes (8) is detected by an oxygen content analyzer (9). When the oxygen content of the gas in the sampling tube (8) is within ±10% of the average value of the oxygen content of the gas in all the sampling tubes (8), the opening of the first control valve (7) on the oil and gas pipe (4) corresponding to the sampling tube (8) is restored, and the opening of the second control valve (11) on the nitrogen injection pipe (5) corresponding to the oil and gas pipe (4) is restored.

10. The nitrogen replacement method for underground large cavern system according to claim 8, characterized in that: Step S2 also includes: obtaining the total amount of nitrogen introduced into all the oil storage caverns (2) through the second flowmeter (10) on each nitrogen injection pipe (5); when the total amount of nitrogen introduced accounts for 70%-99% of the total volume of all the oil storage caverns (2), opening the sampling pipe (8) on each oil and gas pipe (4) through the sampling valve (17) to start sampling, and detecting the oxygen content of the gas in each sampling pipe (8) through the oxygen content analyzer (9).

Citation Information

Patent Citations

  • Cavern nitrogen displacement method used for underground water-sealed rock cavern oil storages

    CN103121566A

  • Underground water-sealing cave depot system, and oil storage method of underground water-sealing cave depot

    CN108357849A

  • Integrated underground water-sealed stone cavern oil depot process system

    CN115321081A

  • Method for storing mineral oil in underground cavern, involves displacing stored mineral oil by pressure of gas held in adjacent separate cavern during extraction process

    DE102006047036A1

  • Device for brine drainage during the initial gas filling of gas storage caverns

    DE202009016682U1