Road engineering earthwork resource allocation method and device and electronic equipment
By obtaining construction progress information and using the BIM system to determine resource requirements and transportation routes, the problem of low transportation efficiency in the allocation of earth resources in road engineering is solved, and the precise deployment of resources and cost reduction is achieved.
Patent Information
- Application Number
- CN202410893785.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-04
- Publication Date
- 2024-11-12
AI Technical Summary
In the prior art, the allocation of earthwork resources in road engineering lacks systematic optimization methods, resulting in low transportation efficiency, waste of resources and high costs.
By obtaining the construction progress information entered by the construction manager, using the preset BIM system to determine the resource requirements and optimal transportation routes of the construction site, we can realize the intelligent allocation of earth resources.
It improves construction management efficiency and accuracy, reduces resource transportation time and cost, realizes accurate placement of earth resources, and avoids resource waste and backlog.
Smart Images

Figure CN118940921A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of engineering planning, and specifically to a method, device and electronic equipment for allocating earthwork resources for road engineering. Background Art
[0002] With the rapid development of my country's economy and society and the continuous advancement of urbanization, the scale of road construction has continued to expand and the number of engineering projects has increased. Road construction involves a large amount of earthwork excavation, transportation, backfilling and other work. The efficient allocation of earthwork resources is directly related to the quality, progress and cost of the project. Reasonable allocation of earthwork resources can reduce resource waste, shorten construction period and reduce costs, which is of vital importance to the smooth implementation and completion acceptance of road projects.
[0003] At present, the allocation of earthwork resources in road projects mainly relies on the experience of construction management personnel to determine the transportation routes, lacking systematic optimization methods, resulting in low transportation efficiency.
[0004] Therefore, there is an urgent need for a method, device and electronic equipment for allocating earthwork resources in road engineering. Summary of the invention
[0005] The present application provides a method, device and electronic equipment for allocating earthwork resources for road engineering projects, which can determine the optimal transportation route according to the location of the construction site and resource requirements, thereby improving transportation efficiency.
[0006] In a first aspect of the present application, a method for allocating earthwork resources for road engineering is provided, the method comprising: obtaining construction progress information entered by construction management personnel, the construction progress information comprising a construction point, a construction progress corresponding to the construction point, and a work point location corresponding to the construction point; obtaining the resource type required for the construction point in a preset BIM system according to the work point location; calculating the resource demand for the construction point according to the construction progress and the resource type; and determining the transportation route corresponding to each of the construction points according to the work point location and the resource demand.
[0007] By adopting the above technical solution, by obtaining the construction progress information such as construction points, construction progress, and work point locations entered by construction management personnel, the resource types required for the construction points are obtained in the preset BIM system according to the work point locations, and then the resource requirements of the construction points are calculated according to the construction progress and resource types. Finally, the transportation routes of each construction point are determined according to the work point locations and resource requirements, thereby realizing the intelligent allocation of earthwork resources for road projects. This method can accurately obtain the resource requirements of each construction point, optimize the transportation routes, and reduce the time and cost of resource transportation. Construction management personnel only need to enter the construction progress information to automatically complete the demand calculation and transportation routes of earthwork resources, greatly improving the efficiency and accuracy of construction management. At the same time, the resource requirements are matched with the construction progress, and the transportation routes are adapted to the work point locations, so that the precise placement of earthwork resources can be achieved to avoid resource waste and backlog. According to the work point locations and resource requirements of the construction points, the optimal transportation routes are planned to improve transportation efficiency.
[0008] Optionally, before obtaining the resource type required for the construction point in a preset BIM system according to the construction point location, the method also includes: obtaining the construction mileage range for the construction point entered by the construction management personnel; judging whether the construction mileage range is within the preset planned mileage range; if it is determined that the construction mileage range is within the preset planned mileage range, obtaining a first construction mileage range of a first construction point and a second construction mileage range of a second construction point, the first construction point being any one of the multiple construction points, and the second construction point being any one of the multiple construction points except the first construction point; judging whether there is an overlapping part between the first construction mileage range and the second construction mileage range; if it is determined that there is an overlapping part between the first construction mileage range and the second construction mileage range, sending a prompt message to remind the construction management personnel to modify the first construction mileage range or the second construction mileage range.
[0009] By adopting the above technical solution, by judging whether the construction mileage range entered by the construction management personnel is within the preset planned mileage range, it is possible to promptly discover the situation where the construction mileage range plan does not match the actual preset planned mileage range. If it is determined that the construction mileage range is within the preset planned mileage range, the construction mileage ranges of different construction points are further obtained to determine whether there is overlap. If the construction mileage ranges of different construction points overlap, it means that there is a conflict in the construction plan, which may lead to confusion in resource allocation and delays in construction. By sending prompt information in a timely manner to remind construction management personnel to modify the construction mileage range, plan conflicts can be eliminated before construction and the operating scope of different construction points can be reasonably divided. This pre-warning and error correction mechanism can avoid resource contention and process conflicts during construction and ensure that construction activities are carried out in an orderly manner within the predetermined plan.
[0010] Optionally, the resource type required for the construction point is obtained in a preset BIM system according to the work point location, specifically including: if it is determined that the construction mileage range is within the preset planned mileage range, and there is no overlapping part between the first construction mileage range and the second construction mileage, then according to the construction mileage range and the work point location, the resource type required for the corresponding construction point is obtained in the preset BIM system.
[0011] By adopting the above technical solution, when it is determined that the construction mileage range is within the preset planned mileage range and the construction mileage ranges of different construction points do not overlap, the resource types required for the corresponding construction point can be accurately obtained in the preset BIM system according to the construction mileage range and the work point location. By matching the construction mileage range and the work point location with the preset BIM system, the types of resources such as earthwork required for a specific construction area can be accurately extracted. This BIM-based resource demand analysis can make full use of engineering design data and automatically generate resource types that meet design requirements.
[0012] Optionally, the transportation routes corresponding to the construction points are determined according to the resource requirements, specifically including: determining the type of earthwork required for each construction point and the amount of earthwork corresponding to the type of earthwork according to the resource requirements; calculating the first transportation distance between each construction point and the second transportation distance between the construction point and the material yard according to the work point location corresponding to the construction point; determining the transportation route for each construction point according to the earthwork type, the amount of earthwork, the first transportation distance and the second transportation distance.
[0013] By adopting the above technical solution, the type and quantity of earthwork required for each construction site are determined according to resource requirements, and the transportation distance between construction sites and between construction sites and material yards is calculated. On this basis, factors such as earthwork type, earthwork quantity, and transportation distance are comprehensively considered to optimize the transportation route for each construction site.
[0014] Optionally, the transportation route of each of the construction points is determined according to the earthwork type, the earthwork volume, the first transportation distance and the second transportation distance, specifically including: constructing a transportation network diagram; taking the material yard as the source point of the transportation network diagram, and taking the construction site location as the confluence point of the transportation network diagram; connecting the source point and the confluence point by lines to obtain multiple connection paths; using a preset shortest path algorithm to calculate the shortest connection path among the multiple connection paths, and taking the shortest connection path as the transportation route for the construction point.
[0015] By adopting the above technical solution, by constructing a transportation network diagram, taking the material yard as the source point and the construction site location as the confluence point, multiple alternative connection paths from the material yard to the construction site are obtained by connecting lines, and then the shortest path algorithm is used to select the shortest connection path as the final transportation route. This networked transportation organization method can intuitively reflect the topological relationship between the material yard, construction site, and road, which is convenient for analysis and optimization. By abstracting the transportation problem into a mathematical model for solution, the blindness and limitations of empirical planning are overcome, and the scientific optimization of transportation routes is achieved.
[0016] Optionally, after calculating the resource demand of the construction site according to the construction progress and the resource type, the method further includes: classifying and summarizing the earthwork quantities according to the earthwork types to obtain the total demand for each earthwork type; obtaining the existing inventory of each earthwork type; judging the relationship between the total demand and the existing inventory; and if it is determined that the total demand is greater than the existing inventory, issuing a material preparation notice, the material preparation notice including the difference between the total demand and the existing inventory.
[0017] By adopting the above technical solution, after calculating the resource requirements of each construction site, the earthwork volume is summarized by type to obtain the total demand, and compared with the existing inventory. If the total demand is greater than the existing inventory, a material preparation notice is issued to indicate the difference quantity that needs to be prepared. This demand summary and inventory early warning mechanism can help construction management personnel accurately grasp the supply and demand relationship of earthwork, take replenishment measures in advance and in a timely manner, and ensure the normal progress of construction.
[0018] Optionally, after calculating the resource requirements of the construction site according to the construction progress and the resource type, the method further includes: generating a summary table, and presenting the summary table to the construction management personnel, the summary table including the construction site, the construction mileage range, the resource category and the resource requirements.
[0019] By adopting the above technical solutions, through information aggregation and visualization, construction managers can fully and intuitively understand the resource demand distribution of the construction site, and grasp the material type, quantity, schedule and other elements of each construction point. The summary table provides a "resource map" of the road section construction, which is convenient for construction managers to coordinate and dispatch resources and scientifically formulate material demand plans.
[0020] In a second aspect of the present application, a road engineering earthwork resource allocation device is provided, which includes: an acquisition module and a processing module, wherein: the acquisition module is used to obtain construction progress information entered by construction management personnel, the construction progress information includes a construction point, a construction progress corresponding to the construction point, and a work point location corresponding to the construction point; the acquisition module is also used to obtain the resource type required for the construction point in a preset BIM system according to the work point location; the processing module is used to calculate the resource demand of the construction point according to the construction progress and the resource type; the processing module is also used to determine the transportation route corresponding to each of the construction points according to the work point location and the resource demand.
[0021] In the third aspect of the present application, an electronic device is provided, including a processor, a memory, a user interface and a network interface, the memory is used to store instructions, the user interface and the network interface are both used to communicate with other devices, and the processor is used to execute the instructions stored in the memory so that the electronic device executes any one of the methods described above.
[0022] In a fourth aspect of the present application, a computer-readable storage medium is provided, wherein the computer-readable storage medium stores instructions, and when the instructions are executed, any of the methods described above is executed.
[0023] In summary, one or more technical solutions provided in the embodiments of the present application have at least the following technical effects or advantages: 1. By obtaining the construction progress information such as construction points, construction progress, and work point locations entered by construction management personnel, the resource types required for the construction points are obtained in the preset BIM system according to the work point locations, and then the resource requirements of the construction points are calculated according to the construction progress and resource types. Finally, the transportation routes of each construction point are determined according to the work point locations and resource requirements, realizing the intelligent allocation of earthwork resources for road projects. This method can accurately obtain the resource requirements of each construction point, optimize the transportation routes, and reduce the time and cost of resource transportation. Construction management personnel only need to enter the construction progress information to automatically complete the demand calculation and transportation routes for earthwork resources, greatly improving the efficiency and accuracy of construction management. At the same time, the resource requirements are matched with the construction progress, and the transportation routes are adapted to the work point locations, which can achieve accurate delivery of earthwork resources and avoid resource waste and backlogs.
[0024] 2. By judging whether the construction mileage range entered by the construction management personnel is within the preset planned mileage range, it is possible to promptly discover situations where the construction mileage range plan does not match the actual preset planned mileage range. If it is determined that the construction mileage range is within the preset planned mileage range, the construction mileage ranges of different construction points are further obtained to determine whether there is overlap. If the construction mileage ranges of different construction points overlap, it means that there is a conflict in the construction plan, which may lead to confusion in resource allocation and delays in construction. By sending prompt information in a timely manner to remind construction management personnel to modify the construction mileage range, plan conflicts can be eliminated before construction and the operating scope of different construction points can be reasonably divided. This pre-warning and error correction mechanism can avoid resource contention and process conflicts during construction and ensure that construction activities are carried out in an orderly manner within the predetermined plan.
[0025] 3. When it is determined that the construction mileage range is within the preset planned mileage range and the construction mileage ranges of different construction points do not overlap, the resource types required for the corresponding construction points are accurately obtained in the preset BIM system according to the construction mileage range and the work point location. By matching the construction mileage range and the work point location with the preset BIM system, the types of resources such as earthwork required for a specific construction area can be accurately extracted. This BIM-based resource demand analysis can make full use of engineering design data and automatically generate resource types that meet design requirements. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a flow chart of a method for allocating earthwork resources in a road engineering project disclosed in an embodiment of the present application; Figure 2 It is a module schematic diagram of a road engineering earthwork resource allocation device disclosed in an embodiment of the present application; Figure 3 It is a structural schematic diagram of an electronic device disclosed in an embodiment of the present application.
[0027] Explanation of the reference numerals: 201, acquisition module; 202, processing module; 300, electronic device; 301, processor; 302, communication bus; 303, user interface; 304, network interface; 305, memory. DETAILED DESCRIPTION
[0028] In order to enable technicians in this field to better understand the technical solutions in this specification, the technical solutions in the embodiments of this specification will be clearly and completely described below in conjunction with the drawings in the embodiments of this specification. Obviously, the described embodiments are only part of the embodiments of this application, not all of the embodiments.
[0029] In the description of the embodiments of the present application, words such as "for example" or "for example" are used to indicate examples, illustrations or explanations. Any embodiment or design described as "for example" or "for example" in the embodiments of the present application should not be interpreted as being more preferred or more advantageous than other embodiments or designs. Specifically, the use of words such as "for example" or "for example" is intended to present related concepts in a specific way.
[0030] In the description of the embodiments of the present application, the meaning of the term "multiple" refers to two or more. For example, multiple systems refer to two or more systems, and multiple screen terminals refer to two or more screen terminals. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the indicated technical features. Thus, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. The terms "include", "comprise", "have" and their variations all mean "including but not limited to", unless otherwise specifically emphasized.
[0031] This application provides a method for allocating earthwork resources in a road engineering project. Figure 1 , Figure 1 1 is a flow chart of a method for allocating earthwork resources in a road engineering project provided in an embodiment of the present application. The method is applied to a server and includes steps S101 to S104, which are as follows: Step S101: Acquire construction progress information entered by a construction management personnel, wherein the construction progress information includes a construction point, a construction progress corresponding to the construction point, and a construction point location corresponding to the construction point.
[0032] In step S101, the server provides a variety of information entry methods so that construction managers can flexibly choose according to actual conditions. One way is to associate existing data, that is, to use the existing BIM platform or other types of data files (such as xtx files) to directly import construction progress information. For example, if the project is already using the BIM platform, the existing construction progress data on the platform can be directly associated with the server, avoiding the workload of repeated entry. At the same time, the BIM platform can also use GPS positioning technology to automatically identify and locate the work site location of the construction site, further improving the efficiency and accuracy of data entry.
[0033] Another way is real-time data entry and positioning. This method is suitable for situations where there is no ready-made data for association, and construction managers need to manually enter information on the platform provided by the server. The server provides a user interface and input process to guide construction managers to enter data in the order of construction points, construction progress, and work point locations. When entering construction progress information, construction managers need to specify the name or number of each construction point to uniquely identify each construction point. For the construction progress, you can enter information such as the current construction stage of each construction point, the amount of work completed, and the estimated completion time. The location of the work point can be obtained in a variety of ways, such as using GPS positioning, manually marking on the map, and entering longitude and latitude coordinates.
[0034] Step S101 is the data basis for the rapid deployment method of earthwork resources in the entire road project. The server ensures that high-quality construction progress information can be obtained in subsequent steps by providing a flexible information entry method, data inspection and storage, and provides a reliable basis for optimizing resource deployment.
[0035] Step S102: Acquire the resource type required for the construction point in a preset BIM system according to the location of the construction point.
[0036] Before step S102, the method also includes: obtaining the construction mileage range for the construction point entered by the construction management personnel; judging whether the construction mileage range is within the preset planned mileage range; if it is determined that the construction mileage range is within the preset planned mileage range, obtaining a first construction mileage range of the first construction point and a second construction mileage range of the second construction point, wherein the first construction point is any one of the multiple construction points, and the second construction point is any one of the multiple construction points except the first construction point; judging whether there is an overlapping part between the first construction mileage range and the second construction mileage range; if it is determined that there is an overlapping part between the first construction mileage range and the second construction mileage range, sending a prompt message to remind the construction management personnel to modify the first construction mileage range or the second construction mileage range.
[0037] Specifically, the server provides a user interface that allows construction managers to enter the construction mileage range information for each construction site. The construction mileage range is usually given in the form of starting mileage and ending mileage, such as "K10+200 to K10+500". Construction managers can submit these data to the server by filling out a form or uploading a file. After receiving the data, the server will store it in the database and associate it with the corresponding construction site. At the same time, the server will perform a rationality check on the entered construction mileage range data. Specifically, the server will compare the construction mileage range of each construction site with the preset planned mileage range to determine whether there is a situation that exceeds the preset planned mileage range. The preset planned mileage range is usually determined at the beginning of the project and represents the starting and ending points of the entire road project. If the construction mileage range of a construction site exceeds the planned range, it means that there may be errors in the entered data and the manager needs to be prompted to correct it.
[0038] For example, suppose the planned mileage range of a road project is K0+000 to K20+000. If the construction manager enters the construction mileage range of a construction point as K25+000 to K26+000, the server will find that this construction mileage range exceeds the preset planned mileage range, and will send a prompt message to the manager, asking him to modify the entered data.
[0039] After confirming that the construction mileage ranges of all construction sites are within the preset planned mileage range, the server also needs to check whether the construction mileage ranges of different construction sites overlap. Since the construction tasks responsible for each construction site should be relatively independent and continuous, if the construction mileage ranges overlap, it may lead to conflicts and waste in the allocation of construction resources.
[0040] In order to check for overlap, the server will randomly select two different construction points (called the first construction point and the second construction point) from the input data and obtain their respective construction mileage ranges (called the first construction mileage range and the second construction mileage range). Furthermore, the server compares the two construction mileage ranges to determine whether they overlap. If there is an overlap, the management personnel needs to be prompted to adjust the construction mileage range of one or both construction points.
[0041] For example, suppose the first construction mileage range of the first construction point is K5+000 to K6+000, and the second construction mileage range of the second construction point is K5+500 to K7+000. The server will find through comparison that the two construction mileage ranges overlap between K5+500 and K6+000. Therefore, the server sends a prompt message to the construction management personnel, prompting the construction management personnel to adjust the construction mileage range of one or both construction points.
[0042] The server will traverse all possible construction point combinations and perform the above overlap check process for each pair of construction points. Only when there is no overlap in the construction mileage range between all construction points will the server determine that the entered data is completely reasonable and consistent and can proceed to the next step of the processing flow.
[0043] In step S102, if it is determined that the construction mileage range is within the preset planned mileage range, and there is no overlap between the first construction mileage range and the second construction mileage range, the resource type required for the corresponding construction point is obtained in the preset BIM system according to the construction mileage range and the construction point location.
[0044] Specifically, when the server confirms that the construction mileage range entered by the construction manager is within the preset planned mileage range and that the construction mileage ranges of different construction sites do not overlap, it can start to obtain the resource types required for each construction site in the preset BIM system based on this information. The following is a detailed description of how the server implements this process.
[0045] First, the server sends the verified construction mileage range and the corresponding work site location to the preset BIM system. The preset BIM system refers to a digital platform that has been established at the beginning of the project and integrates various design and construction information of the project. It contains the 3D visualization model of the project, as well as various attribute data and resource information. The work site location can be a GPS coordinate, which is used to accurately locate the construction point in the preset BIM system.
[0046] For example, suppose the location of a construction site is (X=120, Y=30) and the construction mileage range is K15+000 to K15+500. The server will search for the location with coordinates (120, 30) in the preset BIM system and extract all model elements within the range of K15+000 to K15+500, such as roadbed, pavement, bridges and culverts.
[0047] Next, the preset BIM system analyzes the extracted model elements and identifies the resource types associated with each element. Different engineering locations and construction processes require different resource types. For example, for roadbed construction, materials such as sand and gravel, geogrids, etc. are usually required, while pavement construction requires materials such as asphalt and cement. By analyzing the attributes of each element and the associated resource type information, the preset BIM system can accurately derive the various resource types required for the construction site at different construction stages.
[0048] These resource type information usually exist in the form of classification codes in the preset BIM system, such as "SGCC" for sand and gravel, "LQPT" for asphalt, etc. Each code corresponds to a specific material, equipment or personnel. The preset BIM system will organize the identified resource type codes into a list and associate them with the corresponding construction points.
[0049] Step S103: Calculate the resource demand of the construction point according to the construction progress and the resource type.
[0050] In step S103, the server reads the construction progress and resource type of each construction point. The construction progress information includes the actual progress percentage, etc., which is used to measure the progress of the construction point. The resource type is obtained through the preset BIM system in step S102, including various materials required for the construction point. Further, the server starts to calculate the resource demand for each construction point. Earthwork is an important part of road construction and requires a large amount of excavation and filling operations. Therefore, accurately calculating the type and quantity of earthwork required for each construction point is crucial for the rational allocation of resources and cost control. The server first identifies the type code related to earthwork, such as "SGCC" (sand and gravel), "LQPT" (asphalt), etc., based on the resource type information of the construction point. The server extracts the design drawings and engineering quantity information of the construction point from the preset BIM system or other engineering database. This information usually exists in the form of a three-dimensional model or a two-dimensional drawing, including detailed dimensioning and material descriptions. The server calculates the theoretical engineering quantity of various types of earthwork required by the construction point at the current stage based on the design drawings and construction progress.
[0051] During the calculation process, the server also needs to consider the actual progress of the construction site. For example, if a construction site is scheduled to last 30 days and 50% of the work has been completed, the server only needs to consider the earthwork demand corresponding to the remaining 50% of the work when calculating resource requirements. This can avoid resource waste and over-purchasing. The server stores the calculated and optimized resource requirements in the database and associates them with the corresponding construction sites. Resource requirements include the various types of earthwork required for each construction site, as well as the actual demand.
[0052] In a possible implementation, after step S103, the method further includes: after calculating the resource demand of the construction point according to the construction progress and the resource type, the method further includes: classifying and summarizing the earthwork volume according to the earthwork type to obtain the total demand of each earthwork type; obtaining the existing inventory of each earthwork type; judging the relationship between the total demand and the existing inventory; if it is determined that the total demand is greater than the existing inventory, issuing a material preparation notice, the material preparation notice including the difference between the total demand and the existing inventory.
[0053] Specifically, after completing the resource demand calculation for each construction point in step S103, the server needs to perform a series of summary analysis to ensure that the earthwork resources required for construction can be supplied in time to avoid affecting the construction period due to material shortage. The following describes in detail how the server implements these subsequent steps.
[0054] The server classifies and summarizes the earthwork demand of each construction site according to the earthwork type. Earthwork types usually include sand, clay, silt, etc. The server can obtain the total demand of each earthwork type at all construction sites by querying and grouping the demand data. For example, it can be obtained through statistics that under the current construction progress, all construction sites require a total of 10,000 cubic meters of sand and 5,000 cubic meters of clay. These summary data can help managers quickly understand the earthwork resource demand of the entire project and formulate procurement and deployment plans accordingly. Furthermore, the server needs to obtain the existing inventory of each earthwork type in order to compare it with the total demand. The existing inventory is usually stored in the warehouse management system or ERP system, and the server can obtain this data through the API interface or data synchronization mechanism. Continuing the above example, the server queries from the warehouse management system that the current inventory of sand is 8,000 cubic meters and the inventory of clay is 6,000 cubic meters. After obtaining the total demand and existing inventory data, the server conducts comparative analysis to determine whether a material preparation notice needs to be issued. The server will make a judgment for each type of earthwork: if the total demand is greater than the existing inventory, it means that the current inventory is insufficient to meet the construction needs and materials need to be replenished in time; conversely, if the total demand is less than or equal to the existing inventory, it means that the current inventory is sufficient and no additional purchase is required. In the above example, the total demand for sand (10,000 cubic meters) is greater than the existing inventory (8,000 cubic meters), so the server will issue a material preparation notice for sand. The notification content includes the demand gap for sand, that is, the difference between the total demand and the existing inventory (10,000 - 8,000 = 2,000 cubic meters). This difference is the amount of sand that needs to be replenished through procurement or transfer. For clay, the total demand (5,000 cubic meters) is less than the existing inventory (6,000 cubic meters), and the server determines that the current inventory is sufficient and will not issue a material preparation notice.
[0055] In a possible implementation, after step S103, the method further includes generating a summary table and presenting the summary table to the construction management personnel, wherein the summary table includes the construction point, the construction mileage range, the resource category and the resource demand.
[0056] Specifically, the server needs to extract data related to resource requirements from the database, including construction site information, construction mileage range, resource category, and specific demand. These data may be scattered in different tables or collections, and the server needs to associate them through SQL queries to form a complete data set. The server needs to generate a structured summary table according to a certain format and layout of the data set. This table is usually presented in the form of rows and columns, with each row corresponding to a construction site and each column corresponding to an information item. The summary table generated by the server may include the following columns: construction site number, construction site name, starting mileage, ending mileage, earthwork type, earthwork demand, etc. The server fills the data set according to the definitions of these columns to form a complete summary table. After generating the summary table, the server needs to display it to the construction management personnel. The server transmits the generated summary table to the front-end application, which is responsible for rendering it into a visual table component. Construction management personnel can access this front-end application through a browser or mobile phone to view the contents of the summary table.
[0057] Through the above steps, the server realizes the automatic aggregation and visual display of construction resource demand data. This method can transform the scattered and original demand data into an intuitive and easy-to-understand table form, providing a global perspective for construction managers to help them quickly grasp the resource demand status of the construction site. Based on the summary table, construction managers can promptly discover problems such as abnormal demand and resource shortages, and take targeted measures to deal with them, such as adjusting the construction plan and coordinating with suppliers. At the same time, through the horizontal and vertical analysis of the table data, managers can also summarize the laws and trends of resource demand, and provide decision support for subsequent construction organization and cost control.
[0058] Step S104: Determine the transportation route corresponding to each of the construction points according to the location of the construction point and the resource demand.
[0059] In step S104, the type of earthwork required for each of the construction points and the amount of earthwork corresponding to the type of earthwork are determined according to the resource demand; the first transportation distance between each of the construction points and the second transportation distance between the construction point and the material yard are calculated according to the work point location corresponding to the construction point; the transportation route of each of the construction points is determined according to the type of earthwork, the amount of earthwork, the first transportation distance and the second transportation distance.
[0060] Specifically, the server needs to determine the type of earthwork and the corresponding amount of earthwork required for each construction point based on the resource demand data obtained in step S103. The server needs to calculate the transportation distance between each construction point and between the construction point and the material yard. There are two distance concepts involved here: the first transportation distance and the second transportation distance. The first transportation distance refers to the distance between the construction points, reflecting the distance of earthwork allocation between different construction points; the second transportation distance refers to the distance between the construction point and the material yard, reflecting the distance of transporting earthwork from the material yard to the construction point. After obtaining the earthwork type, earthwork amount and transportation distance data (the first transportation distance and the second transportation distance), the server can start planning the transportation route.
[0061] In a possible implementation, the transportation route of each of the construction points is determined according to the earthwork type, the earthwork volume, the first transportation distance, and the second transportation distance, specifically including: constructing a transportation network diagram; using the material yard as the source point of the transportation network diagram, and using the construction site location as the confluence point of the transportation network diagram; connecting the source point and the confluence point by connecting lines to obtain multiple connection paths; using a preset shortest path algorithm to calculate the shortest connection path among the multiple connection paths, and using the shortest connection path as the transportation route of the construction point.
[0062] Specifically, the server takes the material yard as the source point and each construction point as the sink point to construct a transportation network diagram. The transportation network diagram is an abstract mathematical model used to describe the starting point, end point and possible paths in the transportation task. In the transportation network diagram, the material yard and the construction point are abstracted as nodes, and the lines between the nodes represent possible transportation paths, and the length of the lines corresponds to the distance of the path. The server traverses each construction point and plans the optimal transportation path for it. For the current construction point, the server starts from the material yard and connects the source point and the sink point through lines to obtain all possible transportation paths. Obviously, there may be multiple different roads from the material yard to the construction point, forming multiple alternative connection paths. It should be noted that when the server constructs the transportation network diagram, for each construction point, only the material yard and transportation path that match the required earthwork type are considered. For example, for construction point A that requires Class A soil, the server only connects the material yard node that provides Class A soil and the roadside that can transport Class A soil in the network diagram, without considering the material yard and road that provide Class B soil.
[0063] The server uses a preset shortest path algorithm to find a shortest path among multiple candidate paths as the optimal transportation route for the current construction point. Preferably, the shortest path algorithm used in this application is the Dijkstra algorithm.
[0064] Reference Figure 2The present application also provides a road engineering earthwork resource allocation device, which is a server, and the server includes an acquisition module 201 and a processing module 202, wherein: the acquisition module 201 is used to obtain the construction progress information entered by the construction management personnel, and the construction progress information includes the construction point, the construction progress corresponding to the construction point, and the work point location corresponding to the construction point; the acquisition module 201 is also used to obtain the resource type required for the construction point in the preset BIM system according to the work point location; the processing module 202 is used to calculate the resource demand of the construction point according to the construction progress and the resource type; the processing module 202 is also used to determine the transportation route corresponding to each of the construction points according to the work point location and the resource demand.
[0065] In a possible implementation, before the acquisition module 201 acquires the resource type required for the construction point in a preset BIM system according to the construction point location, the method further includes: the acquisition module 201 acquires the construction mileage range for the construction point entered by the construction management personnel; the processing module 202 determines whether the construction mileage range is within the preset planned mileage range; if the acquisition module 201 determines that the construction mileage range is within the preset planned mileage range, then acquires a first construction mileage range of a first construction point and a second construction mileage range of a second construction point, wherein the first construction point is any one of the multiple construction points, and the second construction point is any one of the multiple construction points except the first construction point; the processing module 202 determines whether there is an overlap between the first construction mileage range and the second construction mileage range; if the processing module 202 determines that there is an overlap between the first construction mileage range and the second construction mileage range, then a prompt message is sent to remind the construction management personnel to modify the first construction mileage range or the second construction mileage range.
[0066] In a possible implementation, the acquisition module 201 acquires the resource type required for the construction point in the preset BIM system according to the work point location, specifically including: if the acquisition module 201 determines that the construction mileage range is within the preset planned mileage range, and there is no overlapping part between the first construction mileage range and the second construction mileage, then the resource type required for the corresponding construction point is acquired in the preset BIM system according to the construction mileage range and the work point location.
[0067] In a possible implementation, the processing module 202 determines the transportation routes corresponding to each of the construction points according to the resource requirements, specifically including: the processing module 202 determines the earthwork type required for each of the construction points and the earthwork quantity corresponding to the earthwork type according to the resource requirements; the processing module 202 calculates the first transportation distance between each of the construction points and the second transportation distance between the construction point and the material yard according to the work point location corresponding to the construction point; the processing module 202 determines the transportation routes for each of the construction points according to the earthwork type, the earthwork quantity, the first transportation distance and the second transportation distance.
[0068] In a possible implementation, the processing module 202 determines the transportation route of each of the construction points according to the earthwork type, the earthwork volume, the first transportation distance and the second transportation distance, specifically including: the processing module 202 constructs a transportation network diagram; the processing module 202 uses the material yard as the source point of the transportation network diagram, and uses the construction site location as the confluence point of the transportation network diagram; the processing module 202 connects the source point and the confluence point through lines to obtain multiple connection paths; the processing module 202 uses a preset shortest path algorithm to calculate the shortest connection path among the multiple connection paths, and uses the shortest connection path as the transportation route of the construction point.
[0069] In a possible implementation, after the processing module 202 calculates the resource demand of the construction point according to the construction progress and the resource type, the method further includes: the processing module 202 classifies and summarizes the earthwork volume according to the earthwork type to obtain the total demand of each earthwork type; the acquisition module 201 obtains the existing inventory of each earthwork type; the processing module 202 determines the relationship between the total demand and the existing inventory; if it is determined that the total demand is greater than the existing inventory, a material preparation notice is issued, and the material preparation notice includes the difference between the total demand and the existing inventory.
[0070] In a possible implementation, after the processing module 202 calculates the resource requirements of the construction point according to the construction progress and the resource type, the method further includes: the processing module 202 generates a summary table and displays the summary table to the construction management personnel, wherein the summary table includes the construction point, the construction mileage range, the resource category and the resource requirements.
[0071] It should be noted that: when the device provided in the above embodiment realizes its function, only the division of the above functional modules is used as an example. In actual application, the above functions can be assigned to different functional modules as needed, that is, the internal structure of the device is divided into different functional modules to complete all or part of the functions described above. In addition, the device and method embodiments provided in the above embodiment belong to the same concept, and the specific implementation process is detailed in the method embodiment, which will not be repeated here.
[0072] The present application also provides an electronic device. Figure 3 , Figure 3 The electronic device 300 may include: at least one processor 301 , at least one network interface 304 , a user interface 303 , a memory 305 , and at least one communication bus 302 .
[0073] The communication bus 302 is used to realize the connection and communication between these components.
[0074] The user interface 303 may include a display screen (Display) and a camera (Camera). Optionally, the user interface 303 may also include a standard wired interface and a wireless interface.
[0075] The network interface 304 may optionally include a standard wired interface or a wireless interface (such as a WI-FI interface).
[0076] Among them, the processor 301 may include one or more processing cores. The processor 301 uses various interfaces and lines to connect various parts in the entire server, and executes various functions of the server and processes data by running or executing instructions, programs, code sets or instruction sets stored in the memory 305, and calling data stored in the memory 305. Optionally, the processor 301 can be implemented in at least one hardware form of digital signal processing (Digital Signal Processing, DSP), field programmable gate array (Field-Programmable Gate Array, FPGA), and programmable logic array (Programmable Logic Array, PLA). The processor 301 can integrate one or a combination of a central processing unit (Central Processing Unit, CPU), a graphics processing unit (Graphics Processing Unit, GPU) and a modem. Among them, the CPU mainly processes the operating system, user interface and application programs; the GPU is responsible for rendering and drawing the content to be displayed on the display screen; the modem is used to process wireless communications. It can be understood that the above-mentioned modem may not be integrated into the processor 301, and it can be implemented separately through a chip.
[0077] Among them, the memory 305 may include a random access memory (Random Access Memory, RAM) and may also include a read-only memory (Read-Only Memory). Optionally, the memory 305 includes a non-transitory computer-readable storage medium. The memory 305 can be used to store instructions, programs, codes, code sets or instruction sets. The memory 305 may include a program storage area and a data storage area, wherein the program storage area may store instructions for implementing an operating system, instructions for at least one function (such as a touch function, a sound playback function, an image playback function, etc.), instructions for implementing the above-mentioned various method embodiments, etc.; the data storage area may store data involved in the above-mentioned various method embodiments, etc. The memory 305 may optionally also be at least one storage device located away from the aforementioned processor 301. Refer to Figure 3 The memory 305 as a computer storage medium may include an operating system, a network communication module, a user interface module and an application program of a method for allocating earthwork resources in a road engineering project.
[0078] exist Figure 3In the electronic device 300 shown, the user interface 303 is mainly used to provide an input interface for the user and obtain the data input by the user; and the processor 301 can be used to call the application program stored in the memory 305 for a method of allocating earthwork resources for road engineering. When executed by one or more processors 301, the electronic device 300 executes one or more of the methods described in the above embodiments. It should be noted that for the aforementioned method embodiments, for the sake of simple description, they are all expressed as a series of action combinations, but those skilled in the art should be aware that the present application is not limited by the described order of actions, because according to the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required for the present application.
[0079] The present application also provides a computer-readable storage medium, which stores instructions. When executed by one or more processors 301, the electronic device 300 executes one or more of the methods described in the above embodiments.
[0080] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0081] In the several embodiments provided in this application, it should be understood that the disclosed devices can be implemented in other ways. For example, the device embodiments described above are only schematic, such as the division of units, which is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some service interfaces, and the indirect coupling or communication connection of devices or units can be electrical or other forms.
[0082] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0083] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.
[0084] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable memory. Based on this understanding, the technical solution of the present application, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, which is stored in a memory and includes several instructions for a computer device (which can be a personal computer, server or network device, etc.) to execute all or part of the steps of the various embodiments of the present application. The aforementioned memory includes: various media that can store program codes, such as USB flash drives, mobile hard drives, magnetic disks or optical disks.
[0085] The above is only an exemplary embodiment of the present disclosure and cannot be used to limit the scope of the present disclosure. That is, any equivalent changes and modifications made according to the teachings of the present disclosure are still within the scope of the present disclosure. After considering the disclosure of the specification and the truth of practice, those skilled in the art will easily think of other embodiments of the present disclosure.
[0086] This application is intended to cover any variation, use or adaptation of the present disclosure, which follows the general principles of the present disclosure and includes common knowledge or customary technical means in the art not described in the present disclosure. The description and examples are to be regarded as exemplary only, and the scope and spirit of the present disclosure are defined by the claims.
Claims
1. A method for allocating earthwork resources in road engineering, characterized in that: The method comprises: Acquire construction progress information entered by the construction management personnel, the construction progress information including the construction point, the construction progress corresponding to the construction point, and the construction point location corresponding to the construction point; Acquire the resource type required for the construction point in a preset BIM system according to the location of the construction point; Calculating resource requirements of the construction site according to the construction progress and the resource type; The transportation routes corresponding to the construction sites are determined according to the locations of the construction sites and the resource requirements.
2. The method according to claim 1, characterized in that Before obtaining the resource type required for the construction point in the preset BIM system according to the construction point location, the method further includes: Obtaining the construction mileage range for the construction point entered by the construction management personnel; Determine whether the construction mileage range is within the preset planned mileage range; If it is determined that the construction mileage range is within the preset planned mileage range, a first construction mileage range of a first construction point and a second construction mileage range of a second construction point are obtained, wherein the first construction point is any one of the multiple construction points, and the second construction point is any one of the multiple construction points except the first construction point; Determine whether the first construction mileage range and the second construction mileage range have overlapping parts; If it is determined that the first construction mileage range and the second construction mileage range have overlapping parts, a prompt message is sent to remind the construction management personnel to modify the first construction mileage range or the second construction mileage range.
3. The method according to claim 2, characterized in that The step of obtaining the resource type required for the construction point in the preset BIM system according to the construction point location specifically includes: If it is determined that the construction mileage range is within the preset planned mileage range, and there is no overlap between the first construction mileage range and the second construction mileage range, the resource type required for the corresponding construction point is obtained in the preset BIM system according to the construction mileage range and the construction point location.
4. The method according to claim 1, characterized in that: Determining the transportation routes corresponding to the construction sites according to the construction site locations and the resource requirements specifically includes: Determine the earthwork type required for each construction point and the earthwork volume corresponding to the earthwork type according to the resource demand; Calculate the first transport distance between each of the construction points and the second transport distance between the construction point and the material yard according to the work point position corresponding to the construction point; The transportation route of each of the construction points is determined according to the earthwork type, the earthwork volume, the first transportation distance, and the second transportation distance.
5. The method according to claim 4, characterized in that Determining the transportation route of each construction point according to the earthwork type, the earthwork volume, the first transportation distance, and the second transportation distance specifically includes: Construct a transportation network diagram; The material yard is used as the source point of the transportation network diagram, and the work site location is used as the confluence point of the transportation network diagram; Connecting the source point and the sink point through lines to obtain multiple connection paths; A preset shortest path algorithm is used to calculate the shortest connection path among the multiple connection paths, and the shortest connection path is used as the transportation route of the construction point.
6. The method according to claim 4, characterized in that After calculating the resource demand of the construction point according to the construction progress and the resource type, the method further includes: Classify and summarize the earthwork volume according to earthwork type to obtain the total demand of each earthwork type; Obtaining the current inventory of each of the earthwork types; Determine the relationship between the total demand and the existing inventory; If it is determined that the total demand is greater than the existing inventory, a material preparation notice is issued, where the material preparation notice includes the difference between the total demand and the existing inventory.
7. The method according to claim 1, characterized in that After calculating the resource demand of the construction point according to the construction progress and the resource type, the method further includes: A summary table is generated and displayed to the construction management personnel, wherein the summary table includes the construction site, the construction mileage range, the resource category, and the resource demand.
8. A road engineering earthwork resource allocation device, characterized in that: The device comprises an acquisition module (201) and a processing module (202), wherein: The acquisition module (201) is used to acquire the construction progress information entered by the construction management personnel, wherein the construction progress information includes the construction point, the construction progress corresponding to the construction point, and the construction point location corresponding to the construction point; The acquisition module (201) is further used to acquire the resource type required for the construction point in a preset BIM system according to the location of the construction point; The processing module (202) is used to calculate the resource demand of the construction site according to the construction progress and the resource type; The processing module (202) is further used to determine the transportation route corresponding to each of the construction points according to the location of the construction point and the resource demand.
9. An electronic device, characterized in that: The electronic device (300) comprises a processor (301), a memory (305), a user interface (303) and a network interface (304), wherein the memory (305) is used to store instructions, the user interface (303) and the network interface (304) are used to communicate with other devices, and the processor (301) is used to execute the instructions stored in the memory (305) so that the electronic device (300) executes the method according to any one of claims 1 to 7.
10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores instructions, and when the instructions are executed, the method according to any one of claims 1 to 7 is executed.