Method for realizing automatic affiliation and installation of subitem projects based on system codes and equipment codes
By designing system code and equipment code in complex projects, decomposing the project into multi-level coding, and using artificial intelligence to optimize progress, the problem of inability to reflect installation relationships and responsibility traceability in the existing technology is solved, and scientific, efficient and safe Sub-project construction.
Patent Information
- Application Number
- CN202410959128.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-17
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-07-17
AI Technical Summary
The existing technology cannot effectively reflect the installation relationship between the subsystems within complex engineering systems, cannot realize sub-projects with sufficient responsibilities, and cannot carry out scientific and reasonable construction methods and construction personnel responsibilities traceability, and cannot realize over-the-air download technology (OTA) Optimize sub-projects.
By designing three-dimensional model drawings, system codes and equipment codes are built, the project is decomposed into sub-engines, branch projects, parts projects and detailed projects, and the corresponding codes are given to each engineering equipment, materials and personnel, and the time code is built, and the design order is carried out. Install simulation and actual comparison, and use artificial intelligence models to optimize project progress.
It has achieved scientific, traceable and safe project progress design, optimized the construction sequence of sub-projects, achieved responsibility traceability and cost savings, and improved the efficiency and reliability of the project.
Smart Images

Figure CN118941231A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method for installing a sub-project, and in particular to a method for automatically installing a sub-project based on a system code and a device code. Background Art
[0002] The installation process of large-scale projects, such as automobiles, aviation, aerospace, nuclear power plants, etc., is complex and involves tens of thousands of components. Therefore, how to complete the installation of the project systematically, traceably and on time has become a scientific problem. The existing technology sets attributes for the components, mounts the attributes to the installation sub-projects, and associates them with the cost analysis, system code and equipment code to obtain the sub-projects. It only associates part of the project with the construction method and cost, and does not sort out a complete and reasonable construction method for the whole project. Therefore, it is impossible to reflect the scientific order from bottom to top between the various parts, nor can it reflect the construction personnel of the project, and it is impossible to realize the real-name responsibility traceability of the detailed processes of the project. It is also impossible to improve and update the existing methods of attributing the installation of sub-projects. Although automation can be achieved, over-the-air download technology (OTA) cannot be realized to complete the practical optimization of sub-projects.
[0003] Therefore, how to reflect the installation relationship between subsystems within a complex engineering system and arrange the sub-projects reasonably and with due responsibility has become a difficult problem that needs to be solved urgently. Summary of the invention
[0004] In order to solve the problem that the existing technology cannot solve the installation sequence of a full set of projects, the present invention provides a method for automatically assigning installation sub-projects based on system codes and equipment codes, including designing a three-dimensional model drawing of the project, constructing the first code of each sub-project of the project, further decomposing the sub-project into the next-level branch project, constructing the branch code of the branch project, and then further decomposing the branch project into parts project, constructing the part code of the parts project, and finally decomposing the parts project into detail project, constructing the detail code of the detail project, setting the corresponding second code for the equipment, materials, and engineering personnel required for the sub-project, branch project, parts project, and detail project, and constructing the time code of each sub-project, branch project, parts project, and detail project to correspond to the time node when each project is expected to be completed, constructing three-dimensional models of equipment, materials, and engineering personnel, and assigning corresponding second codes to each.
[0005] Detail codes are assigned to the three-dimensional models of detail components in the detail project according to the optional contact position after installation or the designed close distance position, and then at least one of the three-dimensional models of the part project, the three-dimensional models of the branch project, and the three-dimensional models of the sub-project are assigned at least one detail code, part code, branch code, first code at the contact position after installation or at the designed close distance position, and / or, with the three-dimensional models of the four types of projects, namely, detail project, part project, branch project, and sub-project, as the core assignment object, each type of project and at least one other project three-dimensional model are assigned at least one detail code, part code, branch code, first code at the contact position after installation or at the designed close distance position.
[0006] For example, if detail engineering is assigned as the core object, then detail engineering and part engineering that are in contact with or close to detail engineering in part engineering will be assigned detail codes respectively. Similarly, if there is contact between part engineering and branch engineering, then part engineering will be assigned as the core object, and part codes will be assigned to part engineering and branch engineering respectively.
[0007] And the time code and the second code are assigned to at least one of the detail project, the part project, the branch project, and the sub-project, and the codes assigned to the above-mentioned contact positions or close distance positions in the detail project, the part project, the branch project, and the sub-project are associated.
[0008] When the sub-projects are then installed, the progress of the project is simulated in the order of detail project, parts project, branch project, sub-project or the order of the designed association, and compared with the actual progress to analyze the progress of the project.
[0009] Optionally, in one embodiment, the simulation project progress includes calling detail codes and corresponding time codes, completing the simulation of the detailed installation of all detail components according to the association between the detail codes and the time codes required for the installation of each detail component, and then continuing to call the part code, branch code, first code and corresponding time codes in sequence, and completing the simulation project progress of the installation of all parts, branches and sub-projects according to the association between the part code, branch code, first code and corresponding time codes.
[0010] It can be understood that the setting of each code and the physical assignment and association of the three-dimensional model can be simulated under the time code in the three-dimensional engineering progress without errors and in an orderly manner.
[0011] In another embodiment, the simulation project progress includes different engineers using a remote server to perform the attribution installation operations of the three-dimensional model respectively, and record the associations of the detail code, part code, branch code, and first code assigned during the operation, and record the order of different associations completed by different engineers, assign a time code to each association, and simulate the project progress through the remote server according to the order of different associations, record the total completion time, establish an artificial intelligence model, use the total completion time as a label, learn the order of associations, and thus obtain an intelligent project progress simulation model. The engineering personnel input the designed order of associations into the intelligent project progress simulation model to obtain the corresponding total completion time prediction.
[0012] By sampling the order of associations among different engineers, we can gain different schools of thought’s understanding of the overall installation of the project, and use artificial intelligence to learn and optimize the best project schedule.
[0013] Specifically, the artificial intelligence model includes a convolutional neural network, which pixelates each pair of associations, arranges multiple pixels in sequence according to the order of association to form a two-dimensional image, and uses the convolutional neural network to train the image and classify the total completion time by corresponding the two-dimensional image and the corresponding total completion time.
[0014] For complex projects, there are many types of associated sequences, which are very suitable for predicting the total completion time through the conversion of two-dimensional images.
[0015] Optionally, the method of association is that after the engineer drags the corresponding parts of each project into place during the attribution installation operation, when the corresponding code on the corresponding core assignment object flashes, the engineer stops dragging, and the flashing code is associated with the code on the parts of this project or other projects. Specifically, an association table can be established to complete the mapping of the associated codes in the table.
[0016] Optionally, the code K on the core-assigned object and the code C on the associated component in the project are uniformly represented by (K, C), indicating that the code K is associated with the code C, and the representation (K, C) is marked on the sequential node of the association of the design, and the core-assigned object is used as the node. Thus, the installation operation is visualized.
[0017] Optionally, the actual engineering progress is completed in the following steps:
[0018] S1 allocates engineering personnel, arranges electronic tags for each engineering personnel, and enters the second code corresponding to the engineering personnel into the electronic tag;
[0019] S2 engineering personnel, according to the simulated engineering schedule, execute (can be executed sequentially) the corresponding detail engineering, parts engineering, branch engineering, sub-engineering, and record equipment and materials;
[0020] S3 engineers record the completion progress of each working day, and when the assigned project is completed or the completion progress is recorded, they communicate with the remote server through the electronic tag to confirm the completion of the assigned project or upload the record and completion progress of the equipment and materials. The remote server records the second code of the engineer and associates the detail code, part code, branch code and the first code corresponding to the engineer.
[0021] Optionally, the recording equipment and materials are obtained by scanning equipment and materials with electronic tags.
[0022] Optionally, the materials include various profiles, fasteners, structural accessories, electronic accessories, other materials involved in physical and chemical processes, etc., and the equipment includes mechanical equipment, instruments, etc.
[0023] Optionally, the engineering progress according to the simulation is specifically input into the artificial intelligence model in the order of association of the design, and then the design optimization is cyclically performed and the artificial intelligence model predicts the optimal design in the order of association, specifically downloading the artificial intelligence model from the remote server to complete the optimal design association order.
[0024] The analysis of project progress includes analysis of the completion progress of each working day, analysis of the completion time of detail projects, parts projects, branch projects, and sub-projects, and analysis of the total completion time.
[0025] Optionally, the analysis of the completion progress of each working day includes using a pre-established prediction model to predict the time when the detailed projects, parts projects, branch projects, and sub-projects described in the working day can be completed using the uploaded multiple completion progresses. The analysis of the completion time of the detailed projects, parts projects, branch projects, and sub-projects includes comparing the time that can be completed with the corresponding time code of each project. If it exceeds a first positive threshold, it indicates that the progress is slow; if it is less than a first negative threshold, it indicates that there is a probability of early completion; if it is between the first positive threshold and the first negative threshold, it indicates on-time completion. The analysis of the total completion time includes comparing the prediction result of the convolutional neural network with the actual total completion time. If it exceeds a second positive threshold, it indicates that the completion is slow; if it is less than the first negative threshold, it indicates that it has been completed ahead of schedule; if it is between the second positive threshold and the second negative threshold, it indicates that it is completed on schedule.
[0026] Optionally, the remote server confirms the human cause analysis of slow or early completion of the construction period based on the analysis results of the project progress and the second code of the engineering personnel, records the completion progress record corresponding to the early completion, analyzes the reasons for the early completion, and optimizes the time code based on this.
[0027] It is easy to understand that the mathematical method of overall arrangement can optimize the construction period from the time code, and the design of artificial intelligence model can optimize the order of association, that is, the order of each project. The human reasons for the early and delayed completion of the construction period can be analyzed by using electronic tags and records of completion progress. The multi-level process, time arrangement, and human factors are used to complete the installation sub-projects from bottom to top.
[0028] Preferably, in the process of attributing and installing sub-projects from the bottom up, a remote server is used to adjust the order of design associations, and the artificial intelligence model is continuously retrained using optimized time codes to achieve the updating of the artificial intelligence model.
[0029] It should be understood that through remote OTA of the remote server, the download of the artificial intelligence model used for optimization of the order of design associations is achieved, and the order of design associations is performed locally during engineering construction.
[0030] Optionally, the remote server also has a cost calculation module for engineering personnel to download and calculate the cost of each detail project, part project, branch project, and sub-project.
[0031] Beneficial effect: the project is divided and various codes are assigned to realize both manual and intelligent progress simulation of the three-dimensional model, so that the sub-projects can be continuously optimized and a scientific, efficient, safe and responsible project progress design can be achieved. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 The overall flow chart of the method for realizing automatic attribution of installation sub-projects based on system code and equipment code of the present invention,
[0033] Figure 2 The assignment of each code in the sub-project method in the example of automobile assembly and the associated state diagram,
[0034] Figure 3 for Figure 2 Schematic diagram of the assignment of time code and second code in the three branch projects of the electronic control system sub-project.
[0035] Figure 4 by Figure 3 Taking the Zhongsan branch project as an example, the engineer performs the attribution installation operation and the schematic diagram before and after the association of branch code 6 and branch code 7.
[0036] Figure 5A bottom-up design of the associated sequence diagram, in which the associated code is marked,
[0037] Figure 6 Diagram of the process of constructing a 2D image.
[0038] Figure 7 Another flowchart of the simulation schedule modeling, showing the iterative design solution for optimizing the sequence of design associations.
[0039] Figure 8 Actual engineering progress flow chart. In which, the reference numerals 1-17 are the sequence numbers of each code. DETAILED DESCRIPTION
[0040] like Figure 1 As shown, a method for automatically assigning installation sub-projects based on system codes and equipment codes includes designing a three-dimensional model drawing of the project, constructing the first code of each sub-project of the project, further decomposing the sub-project into the next-level branch project, constructing the branch code of the branch project, further decomposing the branch project into parts project, constructing the parts code of the parts project, and finally decomposing the parts project into detail project, constructing the detail code of the detail project, setting the corresponding second code for the equipment, materials, and engineering personnel required for the sub-project, branch project, parts project, and detail project, and constructing the time code of each sub-project, branch project, parts project, and detail project to correspond to the time node when each project is expected to be completed, constructing three-dimensional models of equipment, materials, and engineering personnel, and assigning corresponding second codes to each of them.
[0041] like Figure 2 As shown, the order of assigning each code and design association is constructed, taking automobile assembly as an example, Figure 2 The corresponding contact or proximity positions in the center frame, chassis, transmission shaft, control panel, vehicle electronic system, headrest, backrest, seat adjustment, console, axle, and wheel are assigned codes 1 to 17, among which red is the detail code, cyan is the part code, and green and brown are the branch codes. Detail code 8 and detail code 9 are respectively assigned to the headrest and backrest as detail parts in the seat part project. The frame, chassis, control panel, and seat are several branch projects belonging to the support component system sub-project, and are assigned part code 1, part code 2, part code 4, part code 5, and part code 12; the vehicle electronic system, seat adjustment, and console are three branch projects belonging to the electronic control system sub-project, and are respectively assigned green branch code 6, branch code 10, and branch code 13; and in the control panel, seat, door ( Figure 2The corresponding branch codes 7, 11, and 14 are set on the subprojects (not shown); the transmission shaft, axle, and wheel belong to another branch project of the transmission system subproject, and are assigned brown branch codes 2, 16, and 15. The supporting component system subproject, the electronic control system subproject, and the transmission system subproject are each assigned a first code. However, no subproject is assigned, because the detail code, part code, and branch code are sufficient to support the sub-item attribution of the automobile assembly project. Therefore, through the multi-level code assignment design, it can also be flexibly selected according to the size of the engineering system.
[0042] Figure 3 Given Figure 2 The second code and time code of a three-branch project in the electronic control system sub-project are shown in the figure. The three-dimensional models of equipment, materials, and engineering personnel are assigned corresponding second codes respectively. Figure 3 A gives the process of assigning the second code to engineering personnel and equipment. Figure 3 B gives the second coding assignment of the two materials of the wheel hub and the tire, and the assignment is completed on the remote server by associating the second coding and the one-third engineering.
[0043] After the assignment of codes to the components of each project is completed, the engineer can associate the codes. One implementation method is to do this by Figure 2 The spatial coordinate system established in the three-dimensional model of the contact and proximity positions shown in the figure is used to find the spatial coordinate correspondence of each code and realize the association. Call the time code, detail code, part code, and branch code to complete all parts, branches, and sub-projects. Figure 1 Simulation engineering progress of the attribute installation as described in.
[0044] For example, according to the assigned and associated detail code and the time code assigned to the installation of the headrest and backrest in the detail project, the installation process of the detail project is simulated, and the time required for the process corresponds to the time code to achieve the progress simulation of the detail project. Other types of projects are simulated in the same way. The simulation process can be fast-forwarded through the remote server.
[0045] Another implementation is the attribution installation operation of the 3D model on the remote server, such as Figure 4 Mouse pair Figure 2 Drag the vehicle electronic system in the vehicle, and when the associated position is reached, the core assigns the code on the object. Figure 4 In Figure 2 The branch code 6 in the diagram will flash. Release the mouse and stop dragging to automatically complete the association. Engineers mark the association according to the designed sequence of nodes.
[0046] Figure 5The engineer is given a bottom-up design sequence, starting with the frame and installing it with the chassis, based on Figure 2 , mark (1,2) on the frame. Part code 1 represents the core assigned object frame, and part code 2 represents the chassis. Figure 4 After dragging the car frame into place, the part code 1 flashes, and the dragging stops, the association is completed, and the node of the car frame assigned to the core is marked with (1,2). Similarly, the drive shaft, control panel, vehicle electronic system, headrest backrest, seat adjustment, seat and chassis, control panel, axle, and wheel are marked with (2,3), (4,5), (6,7), (8,9), (10,11), (12,2), (13,14), (16,17), (15,16). The order of association is thus recorded (2,3), (4,5), (6,7), (8,9), (10,11), (12,2), (13,14), (16,17), (15,16). Follow Figure 6 The two-dimensional array is arranged in the row and column order directions. After pixelation, a two-dimensional image is formed. The two-dimensional image is represented by three points in the row and column directions to represent the pixels of the other nodes in the order of pixelation.
[0047] Therefore, if Figure 7 As shown, different engineers, through the above-mentioned attribution installation operation, obtain different associated orders, thereby obtaining corresponding different multiple two-dimensional images, thereby training in the convolutional neural network CNN, taking the total completion time as the label, and obtaining the total completion time (classification) predicted by the training. The engineering progress simulation model (that is, the trained CNN) is obtained. Therefore, the engineering progress simulation model is input in the designed associated order to obtain the predicted total completion time, and then the design optimization is continuously cycled, the engineering progress simulation model is input, and the new total completion time is predicted. Until the optimal design associated order is obtained.
[0048] The actual progress of the project is as follows: Figure 8 The following steps are completed:
[0049] S1 allocates engineering personnel, arranges electronic tags for each engineering personnel, and enters the second code corresponding to the engineering personnel into the electronic tags;
[0050] S2 engineering personnel, in accordance with the simulated engineering schedule, carry out the corresponding detail engineering, parts engineering, branch engineering, and sub-engineering in sequence, and record equipment and materials;
[0051] S3 engineers record the completion progress of each working day, and when the assigned project is completed or the completion progress is recorded, they communicate with the remote server through the electronic tag to confirm the completion of the assigned project or upload the record and completion progress of the equipment and materials. The remote server records the second code of the engineer and associates the detail code, part code, branch code and the first code corresponding to the engineer.
[0052] The red underlined lines follow the simulated engineering progress, including Figure 7 The loop optimization method realizes the sequential execution of the associated optimization design.
[0053] The analysis of the completion progress of each working day includes using a pre-established prediction model to predict the time when the detailed projects, parts projects, branch projects, and sub-projects described in the working day can be completed using the uploaded multiple completion progresses. The analysis of the completion time of the detailed projects, parts projects, branch projects, and sub-projects includes comparing the time that can be completed with the corresponding time code of each project. If it exceeds the first positive threshold, it means that the progress is slow; if it is less than the first negative threshold, it means that there is a probability of early completion; if it is between the first positive threshold and the first negative threshold, it means that it is completed on time; the analysis of the total completion time includes comparing the prediction result of the convolutional neural network with the actual total completion time. If it exceeds the second positive threshold, it means that the completion is slow; if it is less than the first negative threshold, it means that it has been completed ahead of schedule; if it is between the second positive threshold and the second negative threshold, it means that it is completed on schedule.
[0054] The remote server confirms the human cause analysis of slow or early completion of the construction period based on the analysis results of the project progress and the second code of the engineering personnel, records the completion progress record corresponding to the early completion, analyzes the reasons for the early completion, and optimizes the time code based on this.
[0055] The remote server also has a cost calculation module for engineers to download and calculate the cost of each detail project, parts project, branch project, and sub-project, so different project association code designs and sequence designs can save different costs. Therefore, through the method of the present invention for automatically assigning installation sub-projects based on system codes and equipment codes, the scientific, traceable, and safe implementation of installation sub-projects is achieved.
Claims
1. A method for automatically assigning installation sub-projects based on system codes and equipment codes, characterized in that: It includes designing the three-dimensional model drawings of the project, constructing the first codes of the sub-projects of the project, further decomposing the sub-projects into the next-level branch projects, constructing the branch codes of the branch projects, further decomposing the branch projects into parts projects, constructing the parts codes of the parts projects, and finally decomposing the parts projects into detail projects, constructing the detail codes of the detail projects, setting the corresponding second codes for the equipment, materials, and engineering personnel required for the sub-projects, branch projects, parts projects, and detail projects, and constructing the time codes of each sub-project, branch project, parts project, and detail project to correspond to the time nodes expected to be completed for each project, constructing the three-dimensional models of the equipment, materials, and engineering personnel, and assigning the corresponding second codes respectively; Assign detail codes to the three-dimensional models of detail parts in detail engineering according to the optional contact position after installation or the designed close distance position, and then assign at least one detail code, part code, branch code, and first code to at least one of the three-dimensional models of part engineering, three-dimensional models of branch engineering, and three-dimensional models of sub-engineering in the contact position after installation or the designed close distance position, and / or, with the three-dimensional models of four types of engineering, namely, detail engineering, part engineering, branch engineering, and sub-engineering, as the core assignment object, assign at least one detail code, part code, branch code, and first code to the contact position after installation between each type of engineering and at least one other engineering three-dimensional model or the designed close distance position; And assign the time code and the second code to at least one of the detail project, the part project, the branch project, and the sub-project, and associate the codes assigned to the above-mentioned contact position or proximity distance position in the detail project, the part project, the branch project, and the sub-project; When the sub-projects are then installed, the progress of the project is simulated in the order of detail project, parts project, branch project, sub-project or the order of the designed association, and compared with the actual progress to analyze the progress of the project.
2. The method according to claim 1, characterized in that The simulation project progress includes calling the detail code and the corresponding time code, completing the simulation of the detailed installation of all detail components according to the association between the detail codes and the time code required for the installation of each detail component, and then continuing to call the part code, branch code, first code and each corresponding time code in sequence, and completing the simulation project progress of the installation of all parts, branches and sub-projects according to the association between the part code, branch code, first code and each corresponding time code.
3. The method according to claim 1, characterized in that The simulation project progress includes that different engineers use the remote server to perform the attribution installation operations of the three-dimensional model respectively, and record the association of the detail code, part code, branch code, and first code assigned during the operation, and record the order of different associations completed by different engineers, assign a time code to each association, and simulate the project progress through the remote server according to the order of different associations, record the total completion time, establish an artificial intelligence model, use the total completion time as a label, learn the order of associations, and thus obtain an intelligent project progress simulation model. The engineering personnel input the designed order of associations into the intelligent project progress simulation model to obtain the corresponding total completion time prediction.
4. The method according to claim 3, characterized in that The artificial intelligence model includes a convolutional neural network, which pixelates each pair of associations and arranges multiple pixels in sequence according to the order of association to form a two-dimensional image. The convolutional neural network is used to train the image and classify the total completion time by corresponding the two-dimensional image and the corresponding total completion time.
5. The method according to claim 4, characterized in that The method of association is that after the engineer drags the corresponding components of each project into place during the attribution installation operation, when the corresponding code on the corresponding core assigned object flashes, stop dragging, and the flashing code can be associated with the code on the components of this project or other types of projects.
6. The method according to claim 5, characterized in that The code K on the core assigned object and the code C on the component in the associated project are uniformly represented by (K, C), indicating that code K is associated with code C, and the representation (K, C) is marked on the sequential node of the designed association, with the core assigned object as the node.
7. The method according to any one of claims 1 to 6, characterized in that The actual engineering progress is completed according to the following steps: S1 assigns engineering personnel, arranges electronic tags for each engineering personnel, and enters the second code corresponding to the engineering personnel into the electronic tag; S2 engineering personnel, according to the simulated engineering schedule, perform corresponding detail engineering, parts engineering, branch engineering, sub-engineering, and record equipment and materials; S3 engineering personnel record the completion progress of each working day, and when the assigned project is completed or the completion progress is recorded, the electronic tag communicates with the remote server to confirm the completion of the assigned project or upload the record and completion progress of the equipment and materials. The remote server records the second code of the engineering personnel and associates the detail code, part code, branch code and the first code corresponding to the engineering personnel.
8. The method according to claim 7, characterized in that The recording equipment and materials are obtained by scanning the equipment and materials with electronic tags; the engineering progress according to the simulation is specifically carried out in the order of the association of the design after the artificial intelligence model is input, and then the design optimization is cyclically performed and the artificial intelligence model predicts the optimal design in the order of association, specifically downloading the artificial intelligence model from the remote server to complete the optimal design association sequence; the analysis of the engineering progress includes the analysis of the completion progress of each working day, the analysis of the completion time of the detail project, parts project, branch project and sub-project, and the analysis of the total completion time.
9. The method according to claim 8, characterized in that The analysis of the completion progress of each working day includes using a pre-established prediction model to predict the time when the detailed engineering, parts engineering, branch engineering, and sub-engineering described in the working day can be completed by using the uploaded multiple completion progress. The analysis of the completion time of the detailed engineering, parts engineering, branch engineering, and sub-engineering includes comparing the time that can be completed with the corresponding time code of each project. If it exceeds the first positive threshold, it means that the progress is slow, and if it is less than the first negative threshold, it means that there is a probability of early completion. If it is between the first positive threshold and the first negative threshold, it means that it is completed on time; the analysis of the total completion time includes comparing the prediction result of the convolutional neural network with the actual total completion time. If it exceeds the second positive threshold, it means that the completion is slow, and if it is less than the first negative threshold, it means that it has been completed ahead of schedule. If it is between the second positive threshold and the second negative threshold, it means that it is completed on schedule; The remote server confirms the human cause analysis of slow or early completion of the construction period based on the analysis results of the project progress and the second code of the engineering personnel, records the completion progress record corresponding to the early completion, analyzes the reasons for the early completion, and optimizes the time code based on this; in the process of attributing the installation sub-projects from bottom to top, the remote server is used to adjust the order of design associations, and the optimized time code is used to continuously retrain the artificial intelligence model to achieve the update of the artificial intelligence model.
10. The method according to claim 8 or 9, characterized in that: The remote server also has a cost calculation module for engineering personnel to download and calculate the cost of each detail project, part project, branch project, and sub-project.
Citation Information
Patent Citations
System and method for multi-code-in-one digital management system
CN109636156A
Method for realizing automatic attribution installation subentry engineering based on system codes and equipment codes
CN111680985A
Engineering construction progress plan management and control system and method based on BIM model
CN111754138A
Rail transit engineering verification coding method, system, equipment and medium
CN116486032A
Tunnel engineering progress and metering linkage management method and system based on BIM technology
CN118261748A