Power system load scheduling method, device and equipment and storage medium
By setting up a monitoring platform in the power system, combining historical data and environmental parameters to predict load demand, calculating regulation parameters, and conducting scientific load scheduling, the problem of unstable power supply in the existing technology is solved, and the supply and demand balance and stability of the power system is improved. sex.
Patent Information
- Application Number
- CN202411057334.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-02
- Publication Date
- 2024-11-12
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing load scheduling methods of power systems fail to effectively consider the changing trends and importance of load demand, resulting in unstable power supply.
By setting up a monitoring platform in the power system, the power consumption of power generation nodes, regulation nodes and load nodes is monitored in real time, the power demand of load nodes on each regulation node is obtained, and future demand is predicted based on historical power consumption data and environmental parameters, and the calculation and control are calculated and controlled. parameters, carry out scientific load scheduling.
It has achieved an accurate grasp of the load demand of the power system, formulated a scientific and reasonable scheduling plan, improved supply and demand balance and system stability, enhanced the intelligence and optimization of the power system, and ensured the stability and economical power supply.
Smart Images

Figure CN118944107A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of power system monitoring, and in particular to a power system load scheduling method, device, equipment and storage medium. Background Art
[0002] Power system load dispatch is an important part of power system operation and management. Its main goal is to ensure the stability and reliability of power supply while maximizing the efficiency of system operation.
[0003] In the prior art, load dispatching of power systems usually relies on real-time power demand data, and then uses certain algorithms to calculate the power dispatching parameters of each control node and load node. However, the above method does not take into account the changing trend and importance of load demand, and the dispatching results are unscientific, which may eventually lead to unstable power supply in the power system. Summary of the invention
[0004] The present application provides a power system load scheduling method, device, equipment and storage medium for formulating a scientific scheduling plan to ensure the stability of power supply in the power system.
[0005] In the first aspect, the present application provides a method for load scheduling of an electric power system, which is applied to a monitoring platform, wherein the monitoring platform is used to monitor the electric power system, wherein the electric power system includes a power generation node, a control node and a load node, wherein a plurality of the control nodes are connected to the power generation node, and each of the control nodes is connected to a plurality of load nodes, and the method includes: obtaining a first total power demand required for the load nodes currently running on each of the control nodes; calculating a first control parameter of each of the control nodes based on the first total power demand required for the load nodes currently running on each of the control nodes; predicting the total power demand required for the load nodes running on each of the control nodes after a preset period of time in combination with historical power consumption data, environmental parameters and the first total power demand, and obtaining a second total power demand; calculating a second control parameter of each of the control nodes after the preset period of time based on the second total power demand and the first control parameter; and performing load scheduling on the electric power system based on the current power output of the power generation node, the second total power demand and the second control parameter.
[0006] By adopting the above technical solution, by setting up a monitoring platform in the power system, the power consumption of each power generation node, control node and load node is monitored in real time, and the first total power demand of the load node on each control node is obtained, and the first control parameter is calculated on this basis. Then, the second total power demand after the preset time is predicted by combining environmental parameters, historical data and the first total power demand. Then, according to the second total power demand and the first control parameter, the second control parameter after the preset time is calculated. Finally, according to the power output of the power generation node, the predicted second total power demand and the calculated second control parameter, the power system is load dispatched. By comprehensively analyzing and predicting various data, the accurate grasp of the load demand of the power system is achieved, and then a scientific and reasonable dispatching plan is formulated. Compared with the traditional method of simple dispatching based only on real-time load monitoring results, this method can better balance the supply and demand relationship of the power system, ensure the stability and economy of the system operation, improve the intelligence and optimization of the load dispatching of the power system, and ensure the stability of the power supply of the power system by formulating a scientific dispatching plan.
[0007] Optionally, the load nodes include important load nodes and ordinary load nodes, and the first control parameters of each control node are calculated based on the first total power demand required by the load nodes currently running on each control node, including: obtaining the important power demand required by the important load nodes on each control node and the ordinary power demand required by the ordinary load nodes on each control node; arithmetically adding the important power demand and the ordinary power demand to obtain the first total power demand; arithmetically dividing the important power demand of each control node by the first total power demand to obtain the first control parameter of each control node.
[0008] By adopting the above technical solution, the load nodes include two types: important load nodes and ordinary load nodes. When calculating the first total power demand, the important power demand of the important load nodes on each control node and the ordinary power demand of the ordinary load node are obtained respectively, and the two are arithmetically added to obtain the first total power demand. When calculating the first control parameter, the important power demand on each control node is arithmetically divided by the first total power demand to obtain the first control parameter. This calculation method that distinguishes important loads from ordinary loads enables the control parameters to reflect the importance of different load nodes. When the load is subsequently dispatched according to the control parameters, important loads are given priority, which improves the stability of the power supply to important loads and avoids the impact of power outages on important electricity users. The pertinence and effectiveness of the dispatching scheme of this application are further improved, the power supply reliability of the power system is enhanced, and the optimal dispatching of the power system load is better realized.
[0009] Optionally, the combination of historical power consumption data, environmental parameters and the first total power demand, predicting the total power demand required by the load nodes running on each of the control nodes after a preset period of time, and obtaining a second total power demand, includes: determining the change in the number of load nodes running on each of the control nodes after a preset period of time according to the historical power consumption data of the load nodes of each of the control nodes in each time period; calculating the average power consumption of the load nodes of each of the control nodes under different environmental parameters; predicting the total power demand required by the load nodes running on each of the control nodes after a preset period of time according to the change in the number of load nodes running on each of the control nodes and the average power consumption of the load nodes of each of the control nodes under different environmental parameters, and obtaining the second total power demand.
[0010] By adopting the above technical scheme, firstly, according to the historical power consumption data, the change in the number of load nodes on each control node after the preset time is determined. Then, the average power consumption of the load nodes of each control node under different environmental parameters is calculated. Finally, combined with the change in the number of load nodes and the average power consumption under different environmental parameters, the second total power demand after the preset time is predicted. This prediction method not only takes into account the changes in the number of load nodes, but also takes into account the influence of environmental parameters, such as temperature, humidity and other factors that affect power consumption. Compared with simple predictions based on historical data alone, this scheme conducts a comprehensive analysis of multiple factors, which can more accurately predict the total power demand at future times, improve the prediction effect, and then formulate a more scientific and reasonable scheduling plan. The advancement of the present application scheme is further enhanced, making the load scheduling of the power system more accurate and efficient, which helps to ensure the safe and stable operation of the power system.
[0011] Optionally, the second control parameter of each control node after the preset time period is calculated based on the second total power demand and the first control parameter, including: calculating the difference between the second total power demand of each control node and the first total power demand corresponding to each control node to obtain a growth rate; arithmetically multiplying the growth rate of each control node by the first control parameter of each control node to obtain a power demand regulation coefficient of each control node; adding the power demand regulation coefficients of each control node and taking the average value to obtain a comprehensive power demand regulation coefficient of the power system; arithmetically dividing the power demand regulation coefficient of each control node by the comprehensive power demand regulation coefficient of the power system to obtain a power demand growth trend of each control node; and determining the second control parameter of each control node according to the power demand growth trend of each control node.
[0012] By adopting the above technical solution, the difference between the second total power demand and the first total power demand of each control node is first calculated to obtain the growth rate of the control node. Then the growth rate is multiplied by the first control parameter to obtain the power demand adjustment coefficient. Then the average value of the power demand adjustment coefficients of all control nodes is calculated as the comprehensive power demand adjustment coefficient of the power system. After that, the power demand adjustment coefficient of each control node is divided by the system comprehensive power demand adjustment coefficient to obtain the power demand growth trend of each control node. Finally, according to the difference in the power demand growth trend of each control node, its second control parameter is determined. This calculation method takes into account the difference in load growth rate of different control nodes within a preset time, and allocates a higher second control parameter to the control node with a faster load growth trend. Thereby realizing the differentiated regulation of the power supply capacity of the control node, and improving the power supply capacity of the area with rapid load growth in a targeted manner. This further improves the operability and pertinence of the scheme of the present application, and realizes the precise regulation of the load of the power system.
[0013] Optionally, the load scheduling of the power system according to the current power output of the power generation node, the second total power demand and the second control parameter includes: sorting the load nodes on each control node according to the second control parameter value of each control node to obtain a first sequence; comparing the power output and the sum of the second total power demands of the load nodes on all control nodes; if the power output is greater than the sum of the second total power demands of the load nodes on all control nodes, reducing the power supply of the load nodes at the front end of the first sequence; if the power output is not greater than the sum of the second total power demands of the load nodes on all control nodes, increasing the power supply of the load nodes at the back end of the first sequence until the power output and the sum of the second total power demands of the load nodes on all control nodes reach a balance.
[0014] By adopting the above technical solution, the load nodes on each control node are first sorted according to the second control parameter to obtain a sorting sequence. Then, the total power output of the power generation node is compared with the sum of the second total power demand of all control node load nodes. If the output is greater than the sum of the demand, the power supply of the load node at the front end of the sorting sequence is reduced; if the output is less than the sum of the demand, the power supply of the load node at the back end of the sorting sequence is increased until the supply and demand balance is reached. This scheduling method fully considers the importance of different load nodes and ensures that important loads are given priority. At the same time, by dynamically adjusting the power supply of different load nodes, the load demand of the entire system is met.
[0015] Optionally, after the load scheduling of the power system, it also includes: judging whether the power generation of the power generation node is equal to the economic power generation after the load scheduling of the power system; if the power generation of the power generation node is not equal to the economic power generation, calculating the excess power generation or lack of power generation that needs to be adjusted to make the power generation node operate at the economic power generation; and adjusting the power supply of the load nodes arranged at the front end or the back end in the first sequence according to the excess power generation or the lack of power generation, until the power generation node operates at the economic power generation.
[0016] By adopting the above technical solution, first determine whether the power generation of the dispatched power generation node reaches the economic power generation. If not, calculate the amount of excess power generation or lack of power generation that needs to be adjusted to make the power generation node reach the economic power generation. Then, according to the excess or lack of power generation, continue to fine-tune the power supply of the load node at the front or back end of the sorting sequence until the power generation of the power generation node is adjusted to the economic power generation. This adjustment method further optimizes the economic operation of the power generation node on the basis of ensuring that the load demand is met. Allowing the power generation node to operate at an economic power generation capacity can reduce system power consumption, reduce power loss, and effectively save energy use. At the same time, it also ensures that the supply and demand balance relationship after dispatch is not destroyed. Therefore, it not only improves the economy of the power system itself, but also makes the entire dispatch plan more scientific and reasonable, achieving multi-objective optimization of the environment, economy and power supply and demand.
[0017] Optionally, after the load scheduling of the power system, it also includes: monitoring the power transmission amount on the power transmission lines of the power generation nodes and each of the control nodes; determining whether the power transmission amount on the power transmission lines of each of the control nodes exceeds the upper limit of the transmission capacity; if exceeded, reducing the power supply of one or more control nodes whose power transmission amount on the power transmission lines exceeds the upper limit of the transmission capacity and / or increasing the power supply of the control nodes connected to other power transmission lines.
[0018] By adopting the above technical solution, the real-time power transmission volume on the power transmission line between the power generation node and each control node is monitored to determine whether the transmission volume exceeds the upper limit of the line transmission capacity. If the upper limit is exceeded, the power supply of the control node connected to the over-limit line is reduced accordingly, and / or the power supply of the control node connected to other lines is increased.
[0019] In a second aspect, the present application provides a load dispatching device for an electric power system, the device comprising: an acquisition module, a first calculation module, a combination module, a second calculation module and a dispatching module; wherein the acquisition module is used to acquire the first total power demand required by the load nodes currently running on each of the control nodes; the first calculation module is used to calculate the first control parameter of each of the control nodes based on the first total power demand required by the load nodes currently running on each of the control nodes; the combination module is used to combine historical power consumption data, environmental parameters and the first total power demand, predict the total power demand required by the load nodes running on each of the control nodes after a preset time period, and obtain the second total power demand; the second calculation module is used to calculate the second control parameter of each of the control nodes after the preset time period based on the second total power demand and the first control parameter; the dispatching module is used to perform load dispatch on the electric power system according to the current power output of the power generation node, the second total power demand and the second control parameter.
[0020] By adopting the above technical solution, by setting up a monitoring platform in the power system, the power consumption of each power generation node, control node and load node is monitored in real time, and the first total power demand of the load node on each control node is obtained, and the first control parameter is calculated on this basis. Then, the second total power demand after the preset time is predicted by combining environmental parameters, historical data and the first total power demand. Then, according to the second total power demand and the first control parameter, the second control parameter after the preset time is calculated. Finally, according to the power output of the power generation node, the predicted second total power demand and the calculated second control parameter, the power system is load dispatched. By comprehensively analyzing and predicting various data, the accurate grasp of the load demand of the power system is achieved, and then a scientific and reasonable dispatching plan is formulated. Compared with the traditional method of simple dispatching based only on real-time load monitoring results, this method can better balance the supply and demand relationship of the power system, ensure the stability and economy of the system operation, improve the intelligence and optimization of the load dispatching of the power system, and ensure the stability of the power supply of the power system by formulating a scientific dispatching plan.
[0021] In a third aspect, the present application provides an electronic device, which adopts the following technical solution: it includes a processor, a memory, a user interface and a network interface, the memory is used to store instructions, the user interface and the network interface are used to communicate with other devices, and the processor is used to execute the instructions stored in the memory so that the electronic device executes a computer program such as any of the above-mentioned power system load scheduling methods.
[0022] In a fourth aspect, the present application provides a computer-readable storage medium, which adopts the following technical solution: storing a computer program that can be loaded by a processor and execute any of the above-mentioned power system load scheduling methods.
[0023] In summary, the present application includes at least one of the following beneficial technical effects: 1. Better balance the supply and demand relationship of the power system, ensure the stability and economy of the system operation, improve the intelligence and optimization of the load dispatching of the power system, and ensure the stability of the power supply of the power system by formulating a scientific dispatching plan; 2. Making the power generation nodes operate at economic power generation can reduce system power consumption, reduce power loss, effectively save energy use, and at the same time ensure that the supply and demand balance after scheduling is not destroyed. Therefore, it not only improves the economy of the power system itself, but also makes the entire scheduling plan more scientific and reasonable, achieving multi-objective optimization of the environment, economy and power supply and demand. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a flow chart of a method for load dispatching of a power system provided in an embodiment of the present application; Figure 2 It is a structural schematic diagram of a power system load dispatching device provided in an embodiment of the present application; Figure 3 It is a structural schematic diagram of an electronic device provided in an embodiment of the present application.
[0025] Description of reference numerals: 1000, electronic device; 1001, processor; 1002, communication bus; 1003, user interface; 1004, network interface; 1005, memory. DETAILED DESCRIPTION
[0026] In order to enable those skilled in the art to better understand the technical solutions in this specification, the technical solutions in the embodiments of this specification will be clearly and completely described below in conjunction with the drawings in the embodiments of this specification. Obviously, the described embodiments are only part of the embodiments of this application, not all of the embodiments.
[0027] In the description of the embodiments of the present application, words such as "illustrative", "for example" or "for example" are used to indicate examples, illustrations or descriptions. Any embodiment or design described as "illustrative", "for example" or "for example" in the embodiments of the present application should not be interpreted as being more preferred or more advantageous than other embodiments or designs. Specifically, the use of words such as "illustrative", "for example" or "for example" is intended to present related concepts in a concrete way.
[0028] Figure 1is a flow chart of a method for dispatching loads in a power system provided in an embodiment of the present application. It should be understood that although Figure 1 The steps in the flowchart are shown in sequence as indicated by the arrows, but the steps are not necessarily executed in the order indicated by the arrows; unless otherwise specified in this document, there is no strict order restriction for the execution of the steps, and the steps may be executed in other orders; and Figure 1 At least part of the steps may include multiple sub-steps or multiple stages. These sub-steps or stages are not necessarily executed at the same time, but can be executed at different times. The execution order of these sub-steps or stages is not necessarily sequential, but can be executed in turn or alternately with other steps or at least part of the sub-steps or stages of other steps.
[0029] The present application discloses a method for dispatching loads in a power system. Figure 1 As shown, the method includes S101-S105.
[0030] S101, obtaining a first total power demand required by load nodes currently running on each control node.
[0031] In one example, a control node refers to a voltage regulating and control device node in a power system such as a transformer, which can adjust the power supply at the node. A control node is usually connected to multiple load nodes. Load node refers to a node in a power system that is connected to various types of power loads, such as factories, shopping malls and other units that need electricity. Multiple load nodes are usually connected to one control node. The first total power demand refers to the total power demand of all load nodes connected to each control node at a certain moment, which is obtained by summing the power demand of each load node.
[0032] The load monitoring subsystem in the monitoring platform will detect the real-time effective power of all load nodes connected to each control node in real time, and sum the effective power of each load node to obtain the total effective power of all load nodes on the control node as the first total power demand of the control node. The reason why the total power demand of each control node needs to be monitored is that in the subsequent power system load dispatching, it is necessary to reasonably allocate power resources according to the power demand of each control node. Directly monitoring the total demand of each control node can simplify the calculation and reflect the overall power demand of the control node.
[0033] By obtaining the first total power demand of each control node, when performing load dispatch, according to the total power demand of each control node, it is possible to intuitively judge whether the power supply of the control node needs to be increased or decreased, which helps to make the dispatch result reasonable. Obtaining the first total power demand of each current control node can provide key input data support for subsequent power load forecasting and power dispatching, and is the basis for power load dispatching.
[0034] S102: Calculate a first control parameter of each control node according to a first total power demand required by load nodes currently running on each control node.
[0035] In one example, the first total power demand refers to the total power consumption of each control node, i.e., the load node at the rear end of the transformer, at a certain moment. The first control parameter refers to the proportion of power consumption of each control node, i.e., the important load node at the rear end of the transformer, to the first total power demand. The first control parameter reflects the proportion and importance of important loads on each control node. The higher the value, the greater the power demand of the important loads on the control node. When the power supply is tight, the power consumption on the control node should be prioritized. The purpose of calculating the first control parameter is to provide a basis for subsequent load scheduling. When the power supply is short, the power distribution can be adjusted according to the parameters of each control node to ensure that important loads receive priority power supply.
[0036] On the basis of obtaining the first total power demand of each control node, the load assessment subsystem in the monitoring platform will distinguish between the important load nodes and ordinary load nodes on each control node, and calculate the total demand of the important load nodes on each control node, that is, the important power demand, and the total demand of the ordinary load nodes on each control node, that is, the ordinary power demand. Then, the ratio of the important power demand of each control node to the first total power demand is calculated to obtain the first control parameter of each control node. The reason why the first control parameter needs to be calculated is that in the case of tight power supply and demand, it is necessary to ensure that the power demand of important loads is given priority. The first control parameter can intuitively reflect the proportion and importance of important loads on each control node.
[0037] By calculating the first control parameter, when performing load dispatch, the power demand of important loads on the control nodes with higher importance can be preferentially met according to the parameter values of each control node. At the same time, the first control parameter also provides a basis for calculating the second control parameter. Calculating the first control parameter is the basis for reasonable load dispatching. It can evaluate the proportion of important loads on each control node, guide subsequent load dispatching to optimize power configuration, and ensure important power demand.
[0038] Based on the above embodiment, as an optional embodiment, the load node includes an important load node and a common load node, and in S102: according to the first total power demand required by the load nodes currently running on each control node, calculating the first control parameter of each control node specifically includes: Obtain the important power demand required by the important load nodes on each current control node, and the ordinary power demand required by the ordinary load nodes on each current control node; arithmetically add the important power demand and the ordinary power demand to obtain a first total power demand; arithmetically divide the important power demand of each control node by the first total power demand to obtain a first control parameter of each control node.
[0039] In one example, the load monitoring subsystem in the monitoring platform distinguishes between important load nodes and ordinary load nodes connected to each control node. Important load nodes include users with high electricity requirements such as hospitals and governments, and ordinary load nodes include users with general electricity requirements such as shopping malls and residences. Then, the total effective power of all important load nodes of each control node in the current period is counted to obtain the important power demand of the control node; at the same time, the total effective power of all ordinary loads of each control node is counted to obtain the ordinary power demand. The important power demand is added to the ordinary power demand to obtain the first total power demand of the control node. Finally, the important power demand of each control node is divided by its first total power demand to calculate the first control parameter of the control node. The load monitoring subsystem of the monitoring platform monitors the operating status of each load node in real time to determine whether it is in an enabled state. For load nodes whose operating status is enabled, their real-time effective power is detected and summed and counted. For load nodes whose operating status is stopped, their effective power is recorded as 0. The effective power sum of important load nodes in real-time enabled state is respectively counted to obtain important power demand, and the effective power sum of common load nodes is counted to obtain common power demand. The subsequent calculation of the first total power demand and the first control parameter is the same as the above process.
[0040] In this way, the power demand data of important loads and ordinary loads can be obtained to more carefully reflect the actual power consumption of each control node, and the first control parameter can be calculated to provide a basis for the subsequent reasonable allocation of power resources. When the power supply is short, the power supply of important loads can be prioritized according to the first control parameter. At the same time, the importance of different control nodes can be measured to guide power dispatching. By distinguishing important loads from ordinary loads and accurately calculating the first control parameter, it can better serve the power load dispatching, so that limited power resources can be reasonably divided and efficiently used, and the power supply quality of important power users can be ensured.
[0041] S103, combining historical power consumption data, environmental parameters and the first total power demand, predicting the total power demand required by the load nodes running on each control node after a preset period of time, and obtaining a second total power demand.
[0042] In an example, historical electricity consumption data refers to the electricity consumption data of the load nodes connected to each control node (transformer) in different time periods in the past, including electricity consumption data on weekdays, holidays, peak hours and off-peak hours, which can reflect the electricity consumption habits and patterns of each load node in different time periods.
[0043] Environmental parameters: mainly refer to data on environmental factors that affect electricity consumption, including: temperature - when the temperature is too high or too low, the electricity consumption of air conditioning or heating will increase; humidity - high humidity will increase the air conditioning load, thus affecting electricity consumption; weather - in rainy weather, the electricity consumption of shopping malls and entertainment venues will decrease; air quality - when the air quality is poor, ventilation equipment will be turned off to reduce electricity consumption; sunshine - the intensity of sunshine affects the lighting electricity consumption.
[0044] The load forecasting subsystem in the monitoring platform collects historical power consumption data of each control node at different time periods, such as power consumption patterns on weekdays, holidays, and under different weather conditions. At the same time, relevant environmental parameter information is obtained, such as temperature, humidity, weather and other data. Then, combined with the first total power demand of each control node at the current moment, according to the algorithm model, after calculating the preset time (such as the next 24 hours), considering the load growth and environmental impact, the expected power demand of each control node, that is, the second total power demand, is calculated.
[0045] The purpose of such prediction is to prepare for subsequent power dispatching. Dispatching based only on the current power load situation may lead to a mismatch between supply and demand. Combining historical data and environmental parameters can improve the accuracy of the prediction and take various influencing factors into account. Predicting the power demand after a preset period of time can guide the dispatching center to prepare for power dispatching in advance, which will help to ensure the power supply of important loads at each control node and ensure the reliable and stable operation of the power grid. By predicting future power demand, the power department can formulate a dispatching plan in advance to cope with the growth of power demand, meet the load demand as much as possible, and ensure the safe and stable operation of the power system.
[0046] The combining of historical power consumption data, environmental parameters and the first total power demand to predict the total power demand required by the load nodes running on each of the control nodes after a preset period of time to obtain the second total power demand includes: Based on the above embodiment, as an optional embodiment, in S103: combining historical power consumption data, environmental parameters and the first total power demand, predicting the total power demand required by the load nodes running on each control node after a preset time, and obtaining the second total power demand, includes: According to the historical power consumption data of the load nodes of each control node in each time period, the change in the number of load nodes running on each control node after a preset time period is determined; the average power consumption of the load nodes of each control node under different environmental parameters is calculated; according to the change in the number of load nodes running on each control node, and the average power consumption of the load nodes of each control node under different environmental parameters, the total power demand required for the load nodes running on each control node after a preset time period is predicted to obtain a second total power demand.
[0047] In one example, the load forecasting subsystem in the monitoring platform collects the historical power consumption data of each control node in different time periods, determines the number of load nodes enabled on each control node in each time period, and analyzes its changing rules. At the same time, according to historical statistics, the average power consumption data of each load node under different environmental parameters of each control node is calculated. Then, combined with the first total power demand of each control node at the current moment, according to the expected change in the number of load nodes and the average power consumption corresponding to the environmental parameters, the second total power demand of each control node can be predicted after the preset time, considering the load growth and environmental impact. This prediction takes into account a variety of factors, which can make the results more accurate and reliable. The historical power consumption data reflects the power consumption rules, the impact of environmental parameters on the applied power, the current demand reflects the real-time basis, and considers the changes in the number of loads in the future time period. Combining all factors, a more accurate estimate of future power demand can be made, providing a scientific basis for power grid dispatching. The comprehensive prediction of multiple factors can better guide the power grid to formulate dispatching plans, reasonably allocate power resources, meet load demand, and ensure the safe and stable operation of the power grid. At the same time, it can also provide a reference for the development planning of the power sector.
[0048] S104: Calculate the second control parameter of each control node after a preset time period according to the second total power demand and the first control parameter.
[0049] In one example, the prediction subsystem can calculate the total power demand growth rate of each control node after a preset time period, that is, the ratio of the second total power demand to the first total power demand, based on the second total power demand, and then multiply the power demand growth rate of each control node by its corresponding first control parameter (reflecting the proportion of important loads) to obtain the power demand adjustment coefficient of the control node. Then take the average value of the adjustment coefficients of all control nodes to calculate the comprehensive power demand adjustment coefficient of the system. Finally, the adjustment coefficient of each control node is divided by the comprehensive adjustment coefficient of the system to obtain the power demand growth trend of the control node as the second control parameter of the control node.
[0050] The purpose of calculating the second control parameter in this way is to guide the subsequent load dispatching. When the power supply is expected to be relatively tight, the power distribution of each node should be adjusted according to the size of the second control parameter, and the power demand of the control nodes with a large growth trend in power demand and a high first control parameter (i.e., a large proportion of important loads) should be guaranteed first. By calculating the second control parameter, the power supply and demand situation in the future period can be better applied, and the dispatching plan can be reasonably guided, so that the dispatching results can not only meet the priority power demand of important loads, but also take into account the growth demand of the loads of each control node, and optimize the dispatching of the power system.
[0051] Assuming there are control nodes A, B, and C, the first total power demand of each node at the current moment is: A: 100MW, B: 80MW, C: 50MW; the first control parameters corresponding to the current moment (reflecting the proportion of important loads) are: A: 0.6, B: 0.7, C: 0.4; the second total power demand forecast after a period of time in the future is: A: 120MW, B: 100MW, C: 70MW, then: A node demand growth rate: (120-100) / 100=0.2, B node demand growth rate: (100-80) / 80=0.25, C node demand growth rate: (70-50) / 50=0.4; multiply the growth rate by the first control parameter to obtain the power demand adjustment coefficient: A: 0.2*0.6=0.12, B: 0.25*0.7=0.175, C: 0.4*0.4=0.16; take the average value of the three node adjustment coefficients, 0.152, as the system comprehensive power demand adjustment coefficient. Then the adjustment coefficient of each node is divided by the average value to obtain the second control parameter, that is, the power demand growth trend: A: 0.12 / 0.152=0.79, B: 0.175 / 0.152=1.15, C: 0.16 / 0.152=1.05. In this way, by calculating the second control parameter, the future power demand growth trend and importance of each control node can be evaluated, providing a basis for subsequent load scheduling.
[0052] Based on the above embodiment, as an optional embodiment, in S104: calculating the second control parameter of each control node after the preset time according to the second total power demand and the first control parameter specifically includes: Calculate the difference between the second total power demand of each control node and the first total power demand corresponding to each control node to obtain the growth rate; arithmetically multiply the growth rate of each control node by the first control parameter of each control node to obtain the power demand adjustment coefficient of each control node; add the power demand adjustment coefficients of each control node and take the average value to obtain the comprehensive power demand adjustment coefficient of the power system; arithmetically divide the power demand adjustment coefficient of each control node by the comprehensive power demand adjustment coefficient of the power system to obtain the power demand growth trend of each control node; determine the second control parameter of each control node according to the power demand growth trend of each control node.
[0053] In one example, after the load forecasting subsystem predicts the second total power demand, it will calculate the expected growth in power demand for each control node, that is, the difference between the second total power demand and the first total power demand, and obtain the power demand growth rate of each control node. Then multiply the growth rate by the first control parameter (reflecting the proportion of important loads) to obtain the power demand adjustment coefficient of each control node. Take the average of the power demand adjustment coefficients of all control nodes to calculate the comprehensive power demand adjustment coefficient of the power system. Finally, divide the adjustment coefficient of each control node by the comprehensive coefficient to obtain the power demand growth trend of the control node as the second control parameter of the node. The purpose of calculating the second control parameter in this way is to reasonably determine the power dispatch priority of each node. Taking into account the two factors of growth rate and important load proportion, the dispatch can meet both important power demand and the growth of ordinary load power demand. Sorting according to the second control parameter can guide the subsequent optimization of power dispatch strategy.
[0054] S105: Perform load dispatching on the power system according to the power output of the current power generation node, the second total power demand and the second control parameter.
[0055] In one example, the load dispatching subsystem of the monitoring platform obtains the total available power output of the current power generation node, and at the same time obtains the second total power demand calculated by the prediction subsystem. Combined with the calculated second control parameters of each control node, the control nodes are sorted from high to low according to the parameter value to obtain a priority sequence, that is, the first sequence. Then the power generation is compared with the second total power demand. If the power generation is greater than the demand, the power supply of these control nodes is gradually reduced from the front end of the first sequence; if the power generation is less than the demand, the power supply is gradually increased from the back end until the power generation and demand are balanced. The purpose of load dispatching in this way is to achieve a balance between power supply and demand. By determining the priority of the control node through the second control parameter, the power demand of important loads can be met, and the goal of seeking balance can be achieved by gradually adjusting the power distribution.
[0056] This scheduling method not only takes into account the importance of different loads, but also takes into account the supply and demand balance of the system. It not only ensures the power demand of important control nodes, but also meets the power demand of non-important loads to the greatest extent, realizes the optimal allocation of limited power resources, and ensures the safe and stable operation of the power system.
[0057] Based on the above embodiment, as an optional embodiment, in S105: according to the power output of the current power generation node, the second total power demand and the second control parameter, the load dispatching of the power system specifically includes: The load nodes on each control node are sorted according to the second control parameter value of each control node to obtain a first sequence; the power output and the sum of the second total power demands of the load nodes on all control nodes are compared; if the power output is greater than the sum of the second total power demands of the load nodes on all control nodes, the power supply of the load nodes at the front in the first sequence is reduced; if the power output is not greater than the sum of the second total power demands of the load nodes on all control nodes, the power supply of the load nodes at the back in the first sequence is increased until the power output and the sum of the second total power demands of the load nodes on all control nodes reach a balance.
[0058] In one example, the load dispatch subsystem obtains the current total power generation and the sum of the second total power demands of all control nodes calculated by the prediction subsystem. Then, the nodes are sorted from high to low according to the second control parameter values to obtain the priority sequence of the control nodes, i.e., the first sequence. The sum of power generation and demand is compared: if the power generation is greater than the demand, the power supply of these high-priority control nodes is reduced from the front end of the first sequence; if the power generation is less than the demand, the power supply is increased from the back end until the power generation and demand are balanced.
[0059] The purpose of adjusting power distribution in this way is to achieve a balance between supply and demand. By determining the node priority through the second control parameter, the demand of important loads can be met first, and the balance can be gradually achieved by gradually adjusting power distribution. This scheduling method fully considers the importance of different loads and the supply and demand balance goal of the system, ensuring the power supply of important nodes and meeting the power demand of non-important nodes as much as possible, realizing the reasonable and effective allocation of power resources and ensuring the safe and stable operation of the power grid.
[0060] After the load dispatching of the power system, it also includes: judging whether the power generation of the power generation node after the load dispatching of the power system is equal to the economic power generation; if the power generation of the power generation node is not equal to the economic power generation, calculating the excess power generation or lack of power generation required to adjust the power generation node to operate at the economic power generation; according to the excess power generation or lack of power generation, adjusting the power supply of the load nodes arranged at the front or back end of the first sequence until the power generation node operates at the economic power generation.
[0061] In one example, the load dispatch subsystem determines whether the power generation of the power generation node is equal to the economic power generation of the node after the first round of load dispatch. The economic power generation here refers to the power generation with the lowest power generation cost. If the two are not equal, the difference in the amount of electricity that needs to be increased or decreased to adjust to the economic power generation is calculated. Then, according to the difference, the load node priority sequence obtained in the first round of dispatch is adjusted in the second round: if the power generation needs to be increased, the node power consumption is increased from the back end; if the power generation needs to be reduced, the power consumption is reduced from the front end, and the adjustment range is to achieve the goal of power generation equal to economic power generation. The purpose of this operation is to further optimize the economic operation of the system. The first round of dispatching achieves supply and demand balance, and the second round of adjustment enables the power generation end to operate in an economic state, which not only meets the user's load demand, but also minimizes the system operation cost. It comprehensively considers the power supply and demand and economic goals to achieve the optimal configuration of the power system.
[0062] Through two rounds of regulation, the electricity demand of important loads is guaranteed, and the economic efficiency of system operation is improved. Multi-objective constraints are fully considered, the rational and effective use of power resources is achieved, and the operation of the entire power system is more optimized.
[0063] After the load scheduling of the power system, it also includes: monitoring the power transmission amount on the power transmission lines of the power generation nodes and each control node; judging whether the power transmission amount on the power transmission lines of each control node exceeds the upper limit of the transmission capacity; if exceeded, reducing the power supply of one or more control nodes whose power transmission amount on the power transmission lines exceeds the upper limit of the transmission capacity and / or increasing the power supply of the control nodes connected to other power transmission lines.
[0064] In one example, after the load is dispatched, the load dispatch subsystem will continue to monitor the real-time power transmission volume on the power transmission line from the power generation node to each control node. And determine whether the transmission volume of each line exceeds the transmission capacity upper limit of the line. If a line is found to be overloaded, the power supply of the relevant control node will be adjusted accordingly, specifically by reducing the power consumption of the control node that causes the overload, and / or increasing the power consumption of the control nodes connected to other lines, in order to reduce the power flow of the overloaded line and avoid transmission overload. The purpose of monitoring the line transmission volume is to ensure the safety of the dispatching scheme. Because the line capacity is a safety constraint for power transmission, overload may lead to accidents. Through monitoring and timely adjustment, the potential dangers caused by over-limit transmission can be effectively prevented to ensure the safe operation of the system. Comprehensively considering the line transmission capacity constraints, the dispatching scheme not only realizes the load demand, but also takes into account the system safety, avoids the risks brought by blind dispatching, and improves the reliability and stability of the power grid.
[0065] Based on the above method, the present application also discloses a power system load dispatching device, such as Figure 2 As shown, Figure 2 It is a structural schematic diagram of a power system load dispatching device provided in an embodiment of the present application.
[0066] A load dispatching device for an electric power system comprises: an acquisition module, a first calculation module, a combination module, a second calculation module and a dispatching module; wherein the acquisition module is used to acquire a first total power demand required by load nodes currently running on each control node; the first calculation module is used to calculate a first control parameter of each control node according to the first total power demand required by load nodes currently running on each control node; the combination module is used to combine historical power consumption data, environmental parameters and the first total power demand, predict the total power demand required by load nodes running on each control node after a preset time, and obtain a second total power demand; the second calculation module is used to calculate a second control parameter of each control node after a preset time according to the second total power demand and the first control parameter; the dispatching module is used to perform load dispatching on the electric power system according to the power output of the current power generation node, the second total power demand and the second control parameter.
[0067] It should be noted that: when the device provided in the above embodiment realizes its function, only the division of the above functional modules is used as an example. In actual application, the above functions can be assigned to different functional modules as needed, that is, the internal structure of the device is divided into different functional modules to complete all or part of the functions described above. In addition, the device and method embodiments provided in the above embodiment belong to the same concept, and the specific implementation process is detailed in the method embodiment, which will not be repeated here.
[0068] See also Figure 3, is a schematic diagram of the structure of an electronic device provided in an embodiment of the present application. Figure 3 As shown, the electronic device 1000 may include: at least one processor 1001 , at least one network interface 1004 , a user interface 1003 , a memory 1005 , and at least one communication bus 1002 .
[0069] The communication bus 1002 is used to realize the connection and communication between these components.
[0070] The user interface 1003 may include a display screen (Display) and a camera (Camera). Optionally, the user interface 1003 may also include a standard wired interface and a wireless interface.
[0071] The network interface 1004 may optionally include a standard wired interface or a wireless interface (such as a WI-FI interface).
[0072] Among them, the processor 1001 may include one or more processing cores. The processor 1001 uses various interfaces and lines to connect various parts in the entire server, and executes various functions of the server and processes data by running or executing instructions, programs, code sets or instruction sets stored in the memory 1005, and calling data stored in the memory 1005. Optionally, the processor 1001 can be implemented in at least one hardware form of digital signal processing (Digital Signal Processing, DSP), field programmable gate array (Field-Programmable Gate Array, FPGA), and programmable logic array (Programmable Logic Array, PLA). The processor 1001 can integrate one or a combination of a central processing unit (Central Processing Unit, CPU), a graphics processing unit (Graphics Processing Unit, GPU) and a modem. Among them, the CPU mainly processes the operating system, user interface and application programs; the GPU is responsible for rendering and drawing the content to be displayed on the display screen; the modem is used to process wireless communications. It can be understood that the above-mentioned modem may not be integrated into the processor 1001, and it can be implemented separately through a chip.
[0073] Among them, the memory 1005 may include a random access memory (Random Access Memory, RAM) and may also include a read-only memory (Read-Only Memory). Optionally, the memory 1005 includes a non-transitory computer-readable storage medium. The memory 1005 can be used to store instructions, programs, codes, code sets or instruction sets. The memory 1005 may include a program storage area and a data storage area, wherein the program storage area may store instructions for implementing an operating system, instructions for at least one function (such as a touch function, a sound playback function, an image playback function, etc.), instructions for implementing the above-mentioned various method embodiments, etc.; the data storage area may store data involved in the above-mentioned various method embodiments, etc. The memory 1005 may optionally also be at least one storage device located away from the aforementioned processor 1001. As Figure 3 As shown, the memory 1005 as a computer storage medium may include an operating system, a network communication module, a user interface module, and an application program of a power system load scheduling method.
[0074] exist Figure 3 In the electronic device 1000 shown, the user interface 1003 is mainly used to provide an input interface for the user and obtain data input by the user; and the processor 1001 can be used to call an application program storing a power system load scheduling method in the memory 1005. When executed by one or more processors, the electronic device executes one or more methods described in the above embodiments.
[0075] An electronic device readable storage medium stores instructions, which, when executed by one or more processors, enable the electronic device to execute one or more of the methods described in the above embodiments.
[0076] It should be noted that, for the aforementioned method embodiments, for the sake of simplicity, they are all described as a series of action combinations, but those skilled in the art should be aware that the present application is not limited by the order of the actions described, because according to the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required for the present application.
[0077] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0078] In the several embodiments provided in the present application, it should be understood that the disclosed devices can be implemented in other ways. For example, the device embodiments described above are only schematic, such as the division of the units, which is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some service interfaces, and the indirect coupling or communication connection of devices or units can be electrical or other forms.
[0079] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0080] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.
[0081] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable memory. Based on this understanding, the technical solution of the present application, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, which is stored in a memory and includes several instructions for a computer device (which can be a personal computer, server or network device, etc.) to execute all or part of the steps of the method described in each embodiment of the present application. The aforementioned memory includes: various media that can store program codes, such as USB flash drives, mobile hard drives, magnetic disks or optical disks.
[0082] The above is only an exemplary embodiment of the present disclosure, and the scope of the present disclosure cannot be limited thereto. That is, any equivalent changes and modifications made according to the teachings of the present disclosure are still within the scope of the present disclosure. After considering the specification and practicing the disclosure here, those skilled in the art will easily think of other embodiments of the present disclosure. This application is intended to cover any modification, use or adaptation of the present disclosure, which follows the general principles of the present disclosure and includes common knowledge or customary technical means in the technical field not recorded in the present disclosure. The description and examples are only regarded as exemplary, and the scope and spirit of the present disclosure are defined by the claims.
Claims
1. A method for load dispatching of a power system, characterized in that: Applied to a monitoring platform, the monitoring platform is used to monitor a power system, the power system includes a power generation node, a control node and a load node, the power generation node is connected to a plurality of the control nodes, each of the control nodes is connected to a plurality of load nodes, the method includes: Obtaining a first total power demand required by the load nodes currently running on each of the control nodes; Calculating a first control parameter of each control node according to a first total power demand required by a load node currently running on each control node; Combined with the historical power consumption data, environmental parameters and the first total power demand, the total power demand required by the load nodes running on each of the control nodes after a preset period of time is predicted to obtain a second total power demand; Calculating the second control parameter of each of the control nodes after the preset time period according to the second total power demand and the first control parameter; The power system is load dispatched according to the current power output of the power generation node, the second total power demand and the second control parameter.
2. The power system load dispatching method according to claim 1, characterized in that: The load nodes include important load nodes and common load nodes, and the first control parameter of each control node is calculated according to the first total power demand required by the load nodes currently running on each control node, including: Obtaining the important power demand required by the important load nodes on each of the current control nodes, and the ordinary power demand required by the ordinary load nodes on each of the current control nodes; arithmetically adding the important power demand and the ordinary power demand to obtain the first total power demand; The important power demand of each of the control nodes is arithmetically divided by the first total power demand to obtain a first control parameter of each of the control nodes.
3. The power system load dispatching method according to claim 1, characterized in that: The combining of historical power consumption data, environmental parameters and the first total power demand to predict the total power demand required by the load nodes running on each of the control nodes after a preset period of time to obtain the second total power demand includes: Determine the change in the number of load nodes running on each of the control nodes after a preset time period according to the historical power consumption data of the load nodes of each of the control nodes in each time period; Calculate the average power consumption of the load nodes of each of the control nodes under different environmental parameters; Based on the change in the number of load nodes running on each of the control nodes and the average power consumption of the load nodes of each of the control nodes under different environmental parameters, the total power demand required by the load nodes running on each of the control nodes after a preset period of time is predicted to obtain a second total power demand.
4. The power system load dispatching method according to claim 1, characterized in that: The calculating, according to the second total power demand and the first control parameter, the second control parameter of each control node after the preset time period includes: Calculate the difference between the second total power demand of each of the control nodes and the first total power demand corresponding to each of the control nodes to obtain a growth rate; Performing arithmetical multiplication of the growth rate of each of the control nodes and the first control parameter of each of the control nodes to obtain a power demand adjustment coefficient of each of the control nodes; The power demand adjustment coefficients of the control nodes are added together and then averaged to obtain a comprehensive power demand adjustment coefficient of the power system; Dividing the power demand adjustment coefficient of each of the control nodes by the comprehensive power demand adjustment coefficient of the power system to obtain the power demand growth trend of each of the control nodes; According to the power demand growth trend of each of the control nodes, a second control parameter of each of the control nodes is determined.
5. The power system load dispatching method according to claim 1, characterized in that: The step of performing load dispatching on the power system according to the current power output of the power generation node, the second total power demand and the second control parameter includes: Sorting the load nodes on each of the control nodes according to the second control parameter value of each of the control nodes to obtain a first sequence; Comparing the power output with the sum of the second total power demands of the load nodes on all the control nodes; If the power output is greater than the sum of the second total power demands of the load nodes on all the control nodes, reducing the power supply of the load nodes at the front in the first sequence; If the power output is not greater than the sum of the second total power demands of the load nodes on all the control nodes, the power supply to the load nodes at the rear end of the first sequence is increased until the power output and the sum of the second total power demands of the load nodes on all the control nodes reach a balance.
6. The power system load dispatching method according to claim 1, characterized in that: After the load dispatching of the power system, the method further includes: Determining whether the power generation of the power generation node is equal to the economic power generation after the load dispatch of the power system; If the power generation of the power generation node is not equal to the economic power generation, then calculating the excess power generation or the lack of power generation that needs to be adjusted to make the power generation node operate at the economic power generation; According to the excess power generation or the shortage of power generation, the power supply of the load node arranged at the front end or the back end in the first sequence is adjusted until the power generation node operates at the economic power generation.
7. The power system load dispatching method according to claim 1, characterized in that: After the load dispatching of the power system, the method further comprises: Monitoring the power transmission amount on the power transmission lines of the power generation node and each of the control nodes; Determining whether the power transmission amount on the power transmission line of each of the control nodes exceeds the upper limit of the transmission capacity; If it exceeds, the power supply to one or more control nodes whose power transmission amount on the power transmission line exceeds the upper limit of the transmission capacity is reduced and / or the power supply to the control nodes connected to other power transmission lines is increased.
8. A power system load dispatching device, characterized in that: The device comprises: an acquisition module, a first calculation module, a combination module, a second calculation module and a scheduling module; wherein, The acquisition module is used to acquire the first total power demand required by the load nodes currently running on each of the control nodes; The first calculation module is used to calculate the first control parameter of each of the control nodes according to the first total power demand required by the load nodes currently running on each of the control nodes; The combining module is used to combine the historical power consumption data, environmental parameters and the first total power demand to predict the total power demand required by the load nodes running on each of the control nodes after a preset period of time to obtain a second total power demand; The second calculation module is used to calculate the second control parameter of each of the control nodes after the preset time period according to the second total power demand and the first control parameter; The scheduling module is used to perform load scheduling on the power system according to the current power output of the power generation node, the second total power demand and the second control parameter.
9. An electronic device, characterized in that: It includes a processor, a memory, a user interface and a network interface, the memory is used to store instructions, the user interface and the network interface are used to communicate with other devices, and the processor is used to execute the instructions stored in the memory so that the electronic device executes the method as described in any one of claims 1-7.
10. A computer-readable storage medium, characterized in that: A computer program is stored which can be loaded by a processor and execute the method according to any one of claims 1 to 7.
Citation Information
Cited By
Detection method, system and equipment for electric power engineering and storage medium
CN119738712A
Power equipment load scheduling method and system based on big data analysis
CN119742795A
Control method and system of power distribution system, storage medium and power distribution system
CN120300876A
A control method, system, storage medium and power distribution system for a power distribution system
CN120300876B