Intelligent micro-grid dispatching system

By dividing the intelligent microgrid system into multiple partitions and deploying sub-controllers, and generating scheduling plan signals in combination with weather prediction information and environmental parameters, the problems of low measurement data accuracy and communication transmission rate in the smart grid are solved, and the system is improved Automatic decision-making ability and signal reliability achieve faster scheduling signal generation and stable system operation.

CN118944172APending Publication Date: 2024-11-12INNER MONGOLIA UNIV OF TECH
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202310528414.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-05-11
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing smart grid technology has problems such as unknown accuracy of measurement data, low communication transmission rate, and signal masking or loss during transmission, making it difficult for the central control system to formulate accurate control strategies, increasing the difficulty of smart microgrid scheduling.

Method used

An intelligent microgrid scheduling system was designed. By dividing the system into a power generation area, an energy storage area, a load area and a central control area, and deploying sub-controllers in each area, reducing the types of information that the controller needs to process, and using multiple uses This communication method realizes two-way transmission of signals, combines meteorological prediction information and environmental parameters to generate scheduling planning signals, reducing the burden on the central controller.

Benefits of technology

It improves the automatic decision-making ability of the intelligent microgrid system, enhances the reliability and computing power of the signal, can generate scheduling signals faster, maintains the stable operation of the system, and reduces the burden on the central controller.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118944172A_ABST
    Figure CN118944172A_ABST
Patent Text Reader

Abstract

The invention discloses an intelligent micro-grid dispatching system, and relates to the technical field of intelligent power grids. The system comprises: a power generation module; the power generation side sub-controller is used for generating a first power parameter according to the first power related parameter sent by the power generation module; an energy storage module; the energy storage side sub-controller is used for generating a second electric power parameter according to a second electric power related parameter sent by the energy storage module; a user load module; the load side sub-controller is used for generating load parameters according to the load related parameters sent by the user load module; and a main control. The main controller is used for generating power generation prediction information according to the weather prediction information and the first electric power parameters, generating load prediction information according to the load parameters, generating scheduling plan signals according to the power generation prediction information and the load prediction information, and sending the scheduling plan signals to the corresponding sub-controllers. According to the invention, the smart grid is partitioned and linked with other systems, so that the burden of the central controller is reduced, and the signal feasibility and the stability and scheduling efficiency of the micro-grid system are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of smart grid technology, and in particular to a smart microgrid dispatching system. Background Art

[0002] Microgrid systems often utilize the natural complementarity of wind and solar resources and use wind and solar complementarity to generate electricity, which can solve the problem of randomness of wind and solar output to a certain extent. The dispatch of microgrid systems is usually achieved in combination with smart grid technology.

[0003] Smart grids should have the characteristics of self-healing, reliability, compatibility, high efficiency, interactivity, etc., and have high requirements for communication technology. The construction of smart grids requires the addition of sensor measurement technology, integrated communication technology and advanced control methods to the existing power grids, and the Internet of Things itself is an organic combination of these three. Therefore, the Internet of Things technology can be highly integrated with the smart grid, and the two complement each other.

[0004] On the one hand, the smart grid collects electrical information and environmental information from the source side through various sensors, and transmits the signals to the signal control unit through wired / wireless methods. The control unit preliminarily screens the transmitted information, then compares the signal with the preset control scheme to generate a control signal, which is transmitted to the control unit to control the device action and maintain the operation of the smart microgrid. However, due to the development of sensor measurement technology and communication technology, the existing smart grid technology has problems such as unknown measurement data accuracy, low communication transmission rate, and information being blocked or lost during transmission. Signal loss and errors will increase the difficulty of the central control system to screen signals, leading to its formulation of incorrect control strategies and affecting the dispatch of the smart grid. At the same time, with the increase of various types of equipment in the smart grid and the increasingly frequent interaction with the user end, the smart grid needs to process more and more data, which puts higher requirements on the computing power of the central control system.

[0005] On the other hand, the cloud computing-based smart grid system uses cloud computing to enhance the computing power of the system, and uses edge computing technology to allocate some computing resources to edge controllers. However, due to the immaturity of edge computing technology, higher requirements are placed on the controller, which increases the cost, and the reliability of signal screening through a single controller is also poor. Summary of the invention

[0006] In order to solve at least one of the above problems existing in the prior art, an embodiment of the present application provides a smart microgrid dispatching system, the system comprising: a power generation module, a power generation side sub-controller corresponding to the power generation module, an energy storage module, an energy storage side sub-controller corresponding to the energy storage module, a user load module, a load side sub-controller corresponding to the user load module, and a main controller;

[0007] The power generation side sub-controller receives the first power related parameter of the power generation module, processes the first power related parameter, generates a first power parameter, and sends the first power parameter to the main controller;

[0008] The energy storage side sub-controller receives the second power-related parameter of the energy storage module, processes the second power-related parameter, generates a second power parameter, and sends the second power parameter to the main controller;

[0009] The load-side sub-controller receives the load-related parameters of the user load module, processes the load-related parameters, generates load parameters, and sends the load parameters to the main controller;

[0010] The main controller generates power generation forecast information according to the meteorological forecast information and the first power parameter, generates load forecast information according to the load parameter, generates a scheduling plan signal according to the power generation forecast information and the load forecast information, and sends it to the corresponding sub-controller.

[0011] In one embodiment, the system further comprises:

[0012] A sensor module, which is used to obtain environmental parameters and send the environmental parameters to the power generation side sub-controller and / or the energy storage side sub-controller;

[0013] The power generation side sub-controller compares the first power-related parameter with the environmental parameter to generate the first power parameter, and / or the energy storage side sub-controller compares the second power-related parameter with the environmental parameter to generate the second power parameter;

[0014] The environmental parameters include wind speed, light irradiance, photovoltaic panel temperature, and temperature and humidity of the working environment of the electrical equipment.

[0015] In one embodiment, the power generation module includes a wind power generation module and / or a photovoltaic power generation module, and the power generation side sub-controller includes a wind power generation side sub-controller corresponding to the wind power generation module and / or a photovoltaic power generation side sub-controller corresponding to the photovoltaic power generation module.

[0016] In one embodiment, the user load module includes at least two types of load modules with different importance levels.

[0017] In one embodiment, the main controller also generates a scheduling modification signal based on the scheduling plan signal and the first power-related parameters and / or the second power-related parameters and / or the load-related parameters collected in real time, and sends it to the corresponding sub-controller.

[0018] In one embodiment, when the power of the power generation module and the energy storage module does not meet the load demand of the user load module, the main controller cuts off the power supply of the load module with the lowest importance level.

[0019] In one embodiment, the main controller determines whether the power generation module and / or the energy storage module is operating safely based on the environmental parameters, and generates an alarm signal when it is determined that the power generation module and / or the energy storage module is not operating safely.

[0020] In one embodiment, the scheduling plan signal includes: a signal for adjusting the predicted power generation of the power generation module, a signal for adjusting the power consumption of the user load module and / or a signal for controlling the charging and discharging of the energy storage module.

[0021] In one embodiment, the first power parameter and / or the second power parameter includes at least one parameter of generated power, generated electricity, generated voltage, generated current, and generated frequency.

[0022] In one embodiment, the main controller generates real-time electricity price information and user electricity usage behavior suggestion information, and sends them to the user load module.

[0023] The smart microgrid dispatching system of the present application improves the wind, solar, diesel and storage multi-energy complementary system, makes the microgrid system intelligent, and improves its automatic decision-making ability. It improves the feasibility of signals by zoning the smart grid and linking with other systems, reduces the burden on the central controller, improves computing power, and can generate dispatching signals faster, maintaining a more stable operation of the smart microgrid system. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the prior art descriptions. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. In the drawings:

[0025] Figure 1 A schematic diagram of the structure of the smart microgrid dispatching system provided in this application.

[0026] Figure 2 Another structural schematic diagram of the smart microgrid dispatching system provided in this application.

[0027] Figure 3A This is the control flow chart of the energy storage side sub-controller during the charging process.

[0028] Figure 3B This is the control flow chart of the energy storage side sub-controller during the discharge process.

[0029] Figure 4A This is a schematic diagram of the structure of the power generation module in the power generation area provided in this application.

[0030] Figure 4B A schematic diagram of the structure of the energy storage module in the energy storage area provided in this application.

[0031] Figure 4C This is a schematic diagram of the structure of the load module in the load zone provided in this application.

[0032] Figure 4D Schematic diagram of the deployment structure of the central control area provided for this application.

[0033] Figure 5 This is a schematic diagram of the structure of the main controller provided in this application.

[0034] Figure 6 A schematic diagram of the steps for the main controller provided in this application to generate a scheduling plan signal. DETAILED DESCRIPTION

[0035] To make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the embodiments of the present invention are further described in detail below in conjunction with the accompanying drawings. Here, the exemplary embodiments of the present invention and their descriptions are used to explain the present invention, but are not intended to limit the present invention.

[0036] The acquisition, storage, use, and processing of data in the technical solution of this application comply with the relevant provisions of laws and regulations.

[0037] In order to solve at least one of the above problems existing in the prior art, the present application embodiment provides a smart microgrid dispatching system, such as Figure 1 As shown, according to the different functions to be implemented, the present application divides the smart microgrid dispatching system into multiple partitions, namely power generation area, energy storage area, load area and central control area.

[0038] Among them, a functional module is deployed in each partition, and a sub-controller is deployed corresponding to each functional module, and the sub-controller is not necessarily deployed in the corresponding partition. Specifically, a power generation module is deployed in the power generation area, and a power generation side sub-controller is deployed corresponding to the power generation module; an energy storage module is deployed in the energy storage area, and an energy storage side sub-controller is deployed corresponding to the energy storage module; an energy storage module is deployed in the energy storage area, and an energy storage side sub-controller is deployed corresponding to the energy storage module; a user load module is deployed in the load area, and a load side sub-controller is deployed corresponding to the user load module; a main controller is deployed in the central control area. In some embodiments, the central control area can also deploy a backup controller with a similar structure to the main controller and the same function.

[0039] Through the data line, the main controller is connected to the sub-controllers of each partition, and the sub-controllers of each partition are connected to the functional modules of the partition to which they belong, so as to realize the two-way transmission of signals. Among them, the data line includes wired communication lines and wireless communication lines. The wireless communication line can adopt long-distance wireless transmission technologies such as GPRS / CDMA wireless communication technology, digital radio communication technology, spread spectrum microwave communication technology, satellite communication technology, and short-distance wireless communication technologies such as Bluetooth, wireless broadband, Zig-Bee, and ultra-wideband. When actually installing and deploying data lines, one or more appropriate communication methods can be selected according to different ground conditions to meet most working conditions. For example, for areas where power lines are laid, the power lines with the widest coverage can be used as the carrier of high-speed data communication, which can realize the user's data terminal access to the broadband communication network without wiring and at low cost; for areas where no power lines are laid, optical cables can be laid to realize fast and reliable transmission of signals, and so on.

[0040] The sub-controller of each partition is only used to process the signals within the partition to which it belongs, so the types of signals that each sub-controller needs to process can be reduced, which is conducive to simplifying the algorithm and improving the calculation speed. Specifically, the sub-controller on the power generation side receives and processes the first power-related parameters of the power generation module, generates the first power parameters, and then sends the first power parameters to the main controller through the data line; the sub-controller on the energy storage side receives and processes the second power-related parameters of the energy storage module, generates the second power parameters, and then sends the second power parameters to the main controller through the data line; the sub-controller on the load side receives and processes the load-related parameters of the user load module, generates the load parameters, and then sends the load parameters to the main controller through the data line. Among them, the first power parameter and the second power parameter include but are not limited to parameters such as power generation power, power generation amount, power generation voltage, power generation current, power generation frequency, etc., and the load parameters include but are not limited to load curves. The sub-controllers of each partition are also used to receive the scheduling plan signal issued by the main controller through the data line, and control the corresponding functional modules according to the scheduling plan signal.

[0041] The main controller is used to receive data processed by each sub-controller and send a scheduling plan signal to each sub-controller. Specifically, the main controller generates power generation forecast information based on meteorological forecast information and the first power parameter sent by the power generation side sub-controller, generates load forecast information based on the load parameter sent by the load side sub-controller, and generates a scheduling plan signal based on the power generation forecast information and the load forecast information, and sends the scheduling plan signal to the sub-controller of the corresponding partition.

[0042] This application divides the smart microgrid system into multiple partitions and deploys controllers in the partitions, which can reduce the types of information that the controller needs to process and reduce the burden on the controller. At the same time, by deploying a main controller and multiple sub-controllers, multi-system linkage of the power generation system, energy storage system, and load system is realized, the feasibility of the signal is improved, the burden on the main controller of the central control area is reduced, the computing power is improved, the dispatching signal can be generated faster, and the smart microgrid system can be maintained in a more stable operation.

[0043] In one embodiment, if Figure 2 As shown, the smart microgrid dispatching system also includes:

[0044] The sensor module is used to obtain environmental parameters. There are two types of environmental parameters: one is wind speed, light irradiance, photovoltaic panel temperature and other environmental parameters related to power generation; the other is temperature, humidity and other environmental parameters related to the working environment of electrical equipment such as generators.

[0045] The sensors are deployed in multiple areas and are connected to the corresponding power generation side sub-controller or energy storage side sub-controller or main controller through data lines to send environmental parameters.

[0046] The power generation side sub-controller compares, analyzes and processes the environmental parameters sent by the sensor and the first power related parameters sent by the power generation module to generate the first power parameters;

[0047] Similarly, the energy storage-side sub-controller compares, analyzes and processes the environmental parameters sent by the sensor and the second power-related parameters sent by the energy storage module to generate the second power parameters.

[0048] Specifically, Figure 2 In the invention, the sub-controller on the power generation side receives the environmental parameters collected by the sensor module of the power generation area and the electrical parameters of the power generation module, and transmits the electrical parameters to the main controller; the sub-controller on the energy storage side receives the environmental parameters collected by the energy storage sensor module of the energy storage area and the electrical parameters of the energy storage module, and transmits the electrical parameters to the main controller; the sub-controller on the load side receives the electrical parameters of the user load module of the load area, and transmits the electrical parameters to the main controller.

[0049] The main controller receives electrical parameters sent by the power generation side sub-controller, the energy storage side sub-controller and the load side sub-controller, as well as environmental parameters such as temperature and humidity of the main control room sent by the sensor module installed in the central control area.

[0050] In addition, the energy storage side sub-controller also needs to monitor the charge state of the battery and take corresponding control measures based on the charge state to provide over-limit protection. Figure 3A This is the control flow chart of the energy storage side sub-controller during the charging process. Figure 3BThis is the control flow chart of the energy storage side sub-controller during the discharge process.

[0051] like Figure 3A As shown, during charging:

[0052] (1) The energy storage side sub-controller monitors the battery's state of charge in real time;

[0053] (2) Determine whether the state of charge of the battery exceeds 90%; if so, execute step (3); if not, return to step (1);

[0054] (3) Reduce the battery charging current;

[0055] (4) Determine whether the state of charge of the battery exceeds 98%; if so, execute step (5); if not, repeat step (4);

[0056] (5) Stop charging the battery;

[0057] (6) Determine whether the energy storage system can store electrical energy; if so, execute step (7); if not, execute step (8);

[0058] (7) charging the supercapacitor with excess electricity;

[0059] (8) Increasing load-side demand, such as charging electric vehicles or curtailing wind and solar power operations.

[0060] like Figure 3B As shown, during the discharge process:

[0061] (1) The energy storage side sub-controller monitors the battery's state of charge in real time;

[0062] (2) Determine whether the state of charge of the battery is less than 20%; if so, execute step (3); if not, return to step (1);

[0063] (3) Reduce the discharge current of the battery;

[0064] (4) Determine whether the state of charge of the battery is less than 10%; if so, execute step (5); if not, repeat step (4);

[0065] (5) Stop discharging the battery;

[0066] (6) Determine whether the energy storage system has sufficient power; if so, execute step (7); if not, execute step (8);

[0067] (7) Controlling the supercapacitor to charge the battery;

[0068] (8) Cut off the loads in order according to their importance.

[0069] The power generation side sub-controller and the energy storage side sub-controller preliminarily process the received power-related parameters and environmental parameters, filter out the correct signals, and then generate parameters such as wind, solar and energy storage resource curve power, power generation, power generation voltage, power generation current and power generation frequency based on the filtered signals, and transmit them to the main controller.

[0070] For the deployment of sensors, appropriate installation strategies can be developed based on regional differences and the deployment of data lines in the region. For example, in areas where fire / security systems already exist, existing security / fire sensors and central control systems can be used to compare similar signals, filter out erroneous information in a timely manner, and supplement correct and missing information, thereby reducing the workload of the sub / main controller of the system to filter information; combined with the local security / fire system, the reliability of the signal is guaranteed and the burden on the control system is reduced;

[0071] For areas without fire protection / security systems, monitoring equipment such as sensors / smart meters need to be installed;

[0072] For areas where it is difficult to lay lines, you can choose to install wireless sensors and develop appropriate structures and protocols based on actual conditions;

[0073] For areas where it is convenient to lay lines, you can choose to install wired sensors to enhance their anti-interference capabilities, etc.

[0074] In one embodiment, see Figure 4A , the power generation modules deployed in the power generation area further include: at least one of a wind power generation module and a photovoltaic power generation module. When a wind power generation module is deployed, a wind power generation side sub-controller connected thereto needs to be deployed at the same time; when a photovoltaic power generation module is deployed, a photovoltaic power generation side sub-controller connected thereto needs to be deployed at the same time. Both the wind power generation side sub-controller and the photovoltaic power generation side sub-controller belong to the power generation side sub-controller. When wind power generation modules and photovoltaic power generation modules are deployed at the same time, the power generation area can be further divided into a wind power generation area and a photovoltaic power generation area.

[0075] The wind power generation module at least includes a wind turbine, an AC / DC module, and a DC / AC module. These modules establish communication connections with the wind power generation side sub-controller. The power line connection relationship is shown in Figure 4A The photovoltaic power generation module includes at least a photovoltaic array and a DC / AC module, which are respectively connected to the photovoltaic power generation side sub-controller. The power line connection relationship is shown in Figure 4A The wind power generation side sub-controller and the photovoltaic power generation side sub-controller are both communicated with the main controller of the central control area.

[0076] In one embodiment, see Figure 4BThe energy storage modules deployed in the energy storage area include a battery pack and a DC / AC module electrically connected thereto, a supercapacitor and a DC / AC module electrically connected thereto, and these modules respectively establish communication connections with the energy storage side sub-controller.

[0077] The energy storage module of the present application adopts a hybrid energy storage method of batteries and supercapacitors, and utilizes the high energy density of batteries to compensate for large power differences over a long period of time and reduce the frequency of charge and discharge switching; and utilizes the fact that the life of supercapacitors is almost unaffected by the number of charge and discharge times, as well as their fast response speed, to compensate for high-frequency and small power fluctuations in a short period of time.

[0078] In one embodiment, the load area is further divided into at least two types of load areas according to different load importance levels, and the number of load areas and the importance level division can be adjusted according to actual ground conditions. Accordingly, the user load modules deployed in the load area include at least two types of load modules with different importance levels. Figure 4C A type I load module, a type II load module and a type III load module are shown in the figure, among which the type I load module has the highest importance level and the type III load module has the lowest importance level. These three types of user load modules establish communication connections with the load-side sub-controller respectively.

[0079] In one embodiment, if Figure 4D As shown in the figure, in addition to the main controller, the central control area also deploys a backup controller as a hot standby. The backup controller can achieve the same functions as the main controller. The data of the main control needs to be synchronized to the backup controller in real time, so that when the main controller fails, it can be quickly switched to the backup controller to avoid paralysis of the central control system.

[0080] The main controller and the backup controller form a central control system, which is set up in the central control room. At the same time, the central control room is also equipped with display equipment, operating equipment, sound and light alarm equipment, etc. After receiving the signals from each sub-controller, the central control system can display the signal curve or signal diagram through the display device, and provide manual access function through the display device, so that the staff can use the operating equipment to access various signals in real time. When receiving the alarm signal, the central control system controls the sound and light alarm system to send out the sound and light alarm signal to provide the staff with timely viewing.

[0081] Among them, the central control system also needs to store and back up the data it receives and generates for easy review. Therefore, the smart microgrid dispatching system also includes a data storage module, which is divided into three parts: data storage, data processing, and data access. The above-mentioned data storage and processing, staff access signal and other functions must be implemented through the data storage module. The data storage module adopts data parallelism to increase the rate, namely, parallel data loading module, parallel ETL module and parallel storage module. The data storage module can be deployed in the central control room or in other areas.

[0082] Figure 1 It is shown that the smart microgrid dispatching system also includes a backup power supply module. In one embodiment, the present application selects a diesel / gas turbine as a backup power supply. When the smart grid power generation cannot meet the power demand of the primary load and cannot obtain power from the large power grid, the backup power supply can realize uninterrupted power supply to the primary load.

[0083] As mentioned above, the main controller, or the central control system, generates a scheduling plan based on the weather forecast information and the data sent by each sub-controller in each partition, and sends it to the corresponding sub-controller for execution. This is described here through a specific embodiment.

[0084] First, if Figure 5 As shown, according to the different functions implemented, the main controller is divided into a monitoring and early warning function module, a scheduling and planning function module, a scheduling and management function module and a safety verification function module. The standby controller has the same or similar function modules as the main controller.

[0085] Among them, the monitoring and early warning function module realizes data collection and intelligent alarm functions. It needs to monitor the operating status information and parameter information of the equipment, and realize automatic alarm and on-site protection for abnormal information; and transmit the alarm signal to the sub-controller and the main controller, display the alarm area and alarm information, and send out sound and light alarm signals to facilitate confirmation by the staff.

[0086] Through the monitoring and early warning function module, the main controller realizes linkage with the sound and light alarm and the monitoring system. After receiving the alarm signal, the monitoring and early warning function module controls the action of the sound and light alarm, sends out sound and light alarm information, and controls the monitoring camera to monitor the fault location in real time.

[0087] After receiving the sound and light alarm information, the staff needs to determine whether the alarm part has a fault and turn off the sound and light alarm. For the control command of the malfunction, it is necessary to restore its normal operation in time. After the fault is repaired, the control command is issued in time to restore the operation of the faulty equipment. For the sound and light alarm, the control signal generated by the main controller has a lower priority than the control signal manually generated by the staff, so that the staff can manually turn off the sound and light alarm.

[0088] The dispatch planning module amends the day-ahead dispatch plan based on the real-time information collected to meet the current working conditions. It also regularly formulates maintenance plans to regularly inspect and maintain the equipment and lines in the smart microgrid to avoid large-scale failures. It also notifies the user side of the maintenance plan.

[0089] The scheduling management function module forms a management system based on the scheduling professional portal website and production information intelligent management software, integrating work planning, production control and operation management.

[0090] The safety verification function module needs to determine the static safety index, determine the stability index, and carry out margin correction based on the analysis results.

[0091] The backup controller has the same structure and function as the main controller. Please refer to the description of the main controller and it will not be repeated in this article.

[0092] After describing the structure of the main controller, the present application continues to describe how the main controller implements the process of generating a scheduling plan through the following embodiments.

[0093] In one embodiment, see Figure 6 , the steps for the main controller to generate the scheduling plan signal are as follows:

[0094] Step S1, the main controller collects weather forecast information from the meteorological unit and generates a wind and solar output forecast curve based on the weather forecast information;

[0095] Step S2, the main controller predicts the user's electricity consumption behavior based on historical load data to generate a load prediction curve, generates user electricity consumption behavior recommendation information based on the load prediction curve to perform flexible load scheduling, and generates a scheduled electricity load curve.

[0096] Step S2 also includes sending the user's electricity consumption behavior suggestion information to the user's mobile phone. The user's electricity consumption behavior suggestion information includes electricity consumption behavior suggestions and corresponding preferential policies. For example, if the user uses electricity according to the electricity consumption behavior suggestions, he can enjoy a low electricity price or return part of the electricity fee. Step S2 is conducive to keeping the user's electricity demand curve stable through flexible load scheduling;

[0097] Step S3, the main controller allocates tasks according to the upper and lower limits of the unit output;

[0098] Step S4, adjust the unit output, load, and energy storage charge and discharge until the unit output meets the preset first constraint, the load meets the preset second constraint, and the whole meets the preset balance constraint. Among them, the first constraint, the second constraint, and the balance constraint can be set according to actual conditions, and this application does not make specific restrictions on this.

[0099] Step S5, formulating a scheduling plan signal according to the data when the first constraint, the second constraint and the balance constraint are satisfied at the same time, and sending the signal to the corresponding sub-controller.

[0100] The scheduling plan signal includes a signal for adjusting the predicted power generation of the power generation module, a signal for adjusting the power consumption of the user load module and / or a signal for controlling the charging and discharging of the energy storage module.

[0101] At the same time, the main controller also sends the dispatch plan signal to the dispatcher. The dispatcher formulates user power consumption behavior suggestions based on the dispatch plan signal and sends them to the user's mobile phone to adjust the power consumption time and power consumption behavior of the user's flexible load and other transferable loads, thereby reducing the dispatch difficulty of the smart microgrid. The smart microgrid dispatch system sends the generated dispatch plan and power consumption suggestions formulated by the staff to the user end through the 5G network.

[0102] In one embodiment, the main controller also generates a scheduling modification signal based on the scheduling plan signal and the first power-related parameters and / or the second power-related parameters and / or the load-related parameters collected in real time, and sends it to the corresponding sub-controller.

[0103] Specifically, the main controller collects the wind, solar and load storage signals transmitted by each sub-controller, compares them with the scheduling plan signals, generates real-time scheduling signals according to the preset algorithm, and transmits them to the corresponding sub-controllers to control the actions of equipment at all levels to maintain the stable, efficient and economical operation of the smart grid system.

[0104] In one embodiment, when the power of the power generation module and the energy storage module does not meet the load demand of the user load module, the main controller cuts off the power supply of the load module with the lowest importance level. Specifically, the main controller repeatedly performs the following operations: cuts off the power supply of the load module with the lowest importance level among the load modules being powered, until the power of the power generation module and the energy storage module can meet the load demand of the load modules that have not been cut off.

[0105] Specifically, Figure 4C Taking the load area deployment structure shown as an example, the loads are divided into three categories according to their importance level. When the power generation of the power generation module and the power of the energy storage module do not meet the load demand of the user load module, the power supply of the three types of load modules with the lowest importance level is cut off first, and the second type of load modules is cut off second. According to the above-mentioned embodiment, when the power generation of the smart grid cannot meet the power demand of a type of load and cannot obtain power from the large power grid, the power supply of the load module can be realized by activating the backup power supply.

[0106] In one embodiment, the main controller determines whether the power generation module and / or the energy storage module is operating safely based on the environmental parameters, and generates an alarm signal when it is determined that the power generation module and / or the energy storage module is not operating safely.

[0107] In one embodiment, the scheduling plan signal includes: a signal for adjusting the predicted power generation of the power generation module, a signal for adjusting the power consumption of the user load module and / or a signal for controlling the charging and discharging of the energy storage module.

[0108] In one embodiment, the main controller generates real-time electricity price information and user electricity usage behavior suggestion information, and sends them to the user load module.

[0109] Specifically, the main controller generates real-time electricity prices and user electricity usage behavior recommendations for different stages based on the current wind output and load demand, and synchronizes the current electricity price information and user electricity usage behavior recommendation information to the user in real time, and adjusts the user's electricity usage behavior secondary through the real-time electricity price.

[0110] Users can query real-time electricity prices, maintenance plans, user electricity usage behavior recommendations, load adjustments and other information on their personal electronic devices, adjust their electricity usage behavior in a timely manner, participate in grid dispatch, and reduce the burden on smart microgrids.

[0111] The main controller can also stimulate users' subjective initiative to constrain loads, and then formulate energy storage control strategies based on time constraints.

[0112] Through the above embodiments, this application describes the structure of the smart microgrid dispatching system. From the perspective of the network hierarchy, the smart microgrid dispatching system consists of four layers: perception layer, network layer, platform layer, and application layer. The perception layer is responsible for data collection through sensor technology and transmits it to the sub-controllers of each partition for processing. It also improves the reliability of the signal and reduces the computing pressure of the platform layer server by combining with other power systems.

[0113] The network layer is responsible for transmitting data between the perception layer and the platform layer, using a variety of communication methods to achieve reliable data transmission and flexible scheduling, improve the transmission speed and reliability of information, and avoid signal distortion, loss and other problems.

[0114] The platform layer is responsible for efficient data processing and IoT management through cloud computing technology. It is the basis for realizing advanced applications. It realizes rapid data processing through cloud computing technology, predicts wind and solar power output based on wind and solar information from the Meteorological Bureau, predicts load curves, formulates day-ahead dispatch plans, and adjusts the dispatch plans based on the status of wind and solar load storage.

[0115] The application layer realizes the production operation, business management and related energy services of the power grid, such as microgrid operation management, electric vehicle operation management, and park energy management.

[0116] The above perception layer, network layer, platform layer, and application layer can all correspond to the aforementioned embodiments, and can be referred to each other, and will not be described in detail here.

[0117] The smart microgrid dispatching system of the present application improves the wind, solar, diesel and storage multi-energy complementary system, makes the microgrid system intelligent, and improves its automatic decision-making ability. It improves the feasibility of signals by zoning the smart grid and linking with other systems, reduces the burden on the central controller, improves computing power, and can generate dispatching signals faster, maintaining a more stable operation of the smart microgrid system.

[0118] Those skilled in the art will appreciate that the present invention may be implemented in the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Furthermore, the present invention may be implemented in the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program codes.

[0119] The present invention is described with reference to the system flow chart and / or block diagram according to the embodiment of the present invention. It should be understood that each process and / or block in the flow chart and / or block diagram, as well as the combination of the processes and / or blocks in the flow chart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flow chart. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0120] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture including an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0121] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0122] The specific embodiments described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific embodiment of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. A smart microgrid dispatching system, characterized in that: The system comprises: a power generation module, a power generation side sub-controller corresponding to the power generation module, an energy storage module, an energy storage side sub-controller corresponding to the energy storage module, a user load module, a load side sub-controller corresponding to the user load module and a main controller; The power generation side sub-controller receives the first power related parameter of the power generation module, processes the first power related parameter, generates a first power parameter, and sends the first power parameter to the main controller; The energy storage side sub-controller receives the second power-related parameter of the energy storage module, processes the second power-related parameter, generates a second power parameter, and sends the second power parameter to the main controller; The load-side sub-controller receives the load-related parameters of the user load module, processes the load-related parameters, generates load parameters, and sends the load parameters to the main controller; The main controller generates power generation forecast information according to the meteorological forecast information and the first power parameter, generates load forecast information according to the load parameter, generates a scheduling plan signal according to the power generation forecast information and the load forecast information, and sends it to the corresponding sub-controller.

2. The system according to claim 1, characterized in that The system further comprises: A sensor module, which is used to obtain environmental parameters and send the environmental parameters to the power generation side sub-controller and / or the energy storage side sub-controller; The power generation side sub-controller compares the first power-related parameter with the environmental parameter to generate the first power parameter, and / or the energy storage side sub-controller compares the second power-related parameter with the environmental parameter to generate the second power parameter; The environmental parameters include wind speed, light irradiance, photovoltaic panel temperature, and temperature and humidity of the working environment of the electrical equipment.

3. The system according to claim 1, characterized in that The power generation module includes a wind power generation module and / or a photovoltaic power generation module, and the power generation side sub-controller includes a wind power generation side sub-controller corresponding to the wind power generation module and / or a photovoltaic power generation side sub-controller corresponding to the photovoltaic power generation module.

4. The system according to claim 1, characterized in that The user load modules include at least two types of load modules with different importance levels.

5. The system according to claim 1, characterized in that The main controller also generates a scheduling modification signal based on the scheduling plan signal and the first power-related parameters and / or the second power-related parameters and / or the load-related parameters collected in real time, and sends it to the corresponding sub-controller.

6. The system according to claim 4, characterized in that When the power of the power generation module and the energy storage module does not meet the load demand of the user load module, the main controller cuts off the power supply of the load module with the lowest importance level.

7. The system according to claim 2, characterized in that The main controller determines whether the power generation module and / or the energy storage module are operating safely based on the environmental parameters, and generates an alarm signal when it is determined that the power generation module and / or the energy storage module are not operating safely.

8. The system according to claim 1, characterized in that The scheduling plan signal includes: a signal for adjusting the predicted power generation of the power generation module, a signal for adjusting the power consumption of the user load module and / or a signal for controlling the charging and discharging of the energy storage module.

9. The system according to claim 1, characterized in that The first power parameter and / or the second power parameter includes at least one parameter of generated power, generated electricity, generated voltage, generated current, and generated frequency.

10. The system according to claim 1, characterized in that The main controller generates real-time electricity price information and user electricity usage behavior suggestion information, and sends them to the user load module.

Citation Information

Cited By

  • Constructed wetland water treatment method and device based on energy distribution and electronic equipment

    CN120810819A

  • Artificial wetland water treatment method, device and equipment based on anomaly monitoring and medium

    CN121063717A