System isolation method for network construction type microgrid, control equipment and storage medium

By monitoring the electrical volume of the grid-connected points in real time and starting the diesel generator, combining the state of energy storage and photovoltaic power generation devices, the system isolation of the network-type microgrid is realized, solving the problem of unstable power supply in the isolated network operation mode, and improving the System security and reliability.

CN118944176APending Publication Date: 2024-11-12SHENZHEN ENERGY INNOVATION TECHNOLOGY CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202410922846.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-09
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In the isolated network operation mode, the equipment and load may be affected by unstable voltage and frequency, resulting in reduced power supply reliability and affecting the stability and safety of the system.

Method used

By monitoring the electrical volume of the network connection point in real time, determine whether it enters the isolated network operation mode, cut off the AC bus line input switch, start the diesel generator, and determine the control strategy based on the status of the energy storage device, V2G and photovoltaic power generation device, and complete the source load according to the status of the energy storage device, V2G and photovoltaic power generation device. Matched system isolation.

Benefits of technology

The state judgment efficiency and emergency response capabilities of network-type micronets in the isolated network operation mode are improved, the stable operation of the system is ensured, and safety and reliability are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118944176A_ABST
    Figure CN118944176A_ABST
Patent Text Reader

Abstract

The invention provides a system isolation method for a network construction type micro-grid, control equipment and a storage medium. The method comprises the following steps: judging whether the network construction type micro-grid runs in an isolated network; if it is judged that the grid-forming type micro-grid enters the isolated grid operation, an alternating current bus incoming switch is controlled to be cut off, and a diesel generator is started; and determining a control strategy according to the power difference before and after the alternating current bus switch is switched off of the grid-forming type micro-grid and by combining the SOC and short-time overload capacity of an energy storage battery of the energy storage device at the current moment, the power generation condition of the photovoltaic power generation device, the discharge condition of the V2G and the power consumption condition of the load at the current moment, and completing source-load matched system isolation based on the control strategy. According to the method, the source load matching precision is improved, the efficiency of identifying the isolated network of the constructed micro-grid is improved, stable construction of the micro-grid is ensured, and the safety and reliability of a power supply system are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of electric power technology, and in particular to a system isolation method, control equipment and storage medium for a meshed microgrid. Background Art

[0002] In modern power systems, microgrids are an important distributed power system architecture. Microgrids are usually composed of distributed power generation equipment (such as solar panels, wind turbines) and energy storage devices (such as battery packs), and are connected to the main grid. Microgrids are flexible and can be connected to the main grid when the main grid is operating normally, and can operate in an isolated grid mode when the main grid fails or is unstable.

[0003] However, when the main grid fails or loses voltage, the microgrid faces the possibility that its equipment and loads may be affected by unstable voltage and frequency in the isolated grid operation mode, and the reliability of power supply will be reduced, which will seriously affect the stability of the microgrid and the safety and reliability of the system. Summary of the invention

[0004] The main purpose of this application is to provide a system isolation method, control equipment and storage medium for a meshed microgrid, aiming to solve the difficulty of state judgment of a meshed microgrid in an isolated grid operation mode, improve the efficiency of emergency response and resource scheduling, ensure the stable operation of the meshed microgrid, and improve the safety and reliability of the system.

[0005] In order to solve the above problems, the embodiments of the present invention mainly provide the following technical solutions:

[0006] In a first aspect, an embodiment of the present application provides a system isolation method for a meshed microgrid, wherein the meshed microgrid includes a diesel generator, an energy storage device, a V2G, and a photovoltaic power generation device; the method includes:

[0007] Monitor the electrical quantity of the grid connection point in real time, and judge whether the grid-connected microgrid has entered the isolated grid operation mode based on the electrical quantity;

[0008] If it is determined that the microgrid has entered the isolated grid operation mode, the AC busbar incoming switch is controlled to be cut off and the diesel generator is started;

[0009] According to the power difference of the grid-type microgrid before and after the AC bus switch is disconnected, combined with the SOC of the energy storage battery and its short-term overload capacity at the current moment, the power generation of the photovoltaic power generation device, the discharge of the V2G system, and the power consumption of the load at the current moment, the control strategy is determined, and the system isolation of source-load matching is completed based on the control strategy.

[0010] In a second aspect, an embodiment of the present application provides a control device, including: a storage device and a controller; the storage device is used to store a computer program; the controller is used to execute the computer program and, when executing the computer program, implement the steps of the coordinated control method of the meshed microgrid as described in the first aspect above.

[0011] In a third aspect, an embodiment of the present application provides a computer-readable storage medium, which stores a computer program. When the computer program is executed by a processor, the steps of the coordinated control method of the meshed microgrid described in the first aspect above are implemented.

[0012] The present application provides a system isolation method, control device and storage medium for a grid-type microgrid, wherein the grid-type microgrid includes a diesel generator, an energy storage device, V2G and a photovoltaic power generation device; the system isolation method for the grid-type microgrid includes: real-time monitoring of the electrical quantity of the grid connection point, judging whether the grid-type microgrid is operating in an isolated grid based on the electrical quantity; if it is determined that the grid-type microgrid enters an isolated grid operation, controlling to cut off the AC bus incoming line switch and starting the diesel generator; according to the power difference of the grid-type microgrid before and after the AC bus switch is disconnected, combined with the SOC of the energy storage battery of the energy storage device at the current moment and its short-term overload capacity, the power generation of the photovoltaic power generation device, the discharge of the V2G system, and the power consumption of the load at the current moment, determining the control strategy, and completing the source-load matching system isolation based on the control strategy. It solves the difficulty of state judgment of the grid-type microgrid in the isolated grid operation mode, improves the efficiency of emergency response and resource scheduling, ensures the stable operation of the grid-type microgrid, and improves the safety and reliability of the system. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0014] Figure 1 A schematic diagram of a process flow of a system isolation method for a meshed microgrid provided in an embodiment of the present application;

[0015] Figure 2 A schematic diagram of the structure of a meshed microgrid provided in an embodiment of the present application;

[0016] Figure 3 A schematic diagram of the structure of a control system provided in an embodiment of the present application;

[0017] Figure 4 A schematic diagram of the structure of a control device provided in an embodiment of the present application.

[0018] The realization of the purpose, functional features and advantages of this application will be further explained in conjunction with embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION

[0019] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0020] In conjunction with the accompanying drawings, some embodiments of the present application are described in detail below. In the absence of conflict, the following embodiments and features in the embodiments can be combined with each other.

[0021] See also Figure 1 , Figure 1 A schematic flow chart of a system isolation method for a meshed microgrid provided in an embodiment of the present application.

[0022] The system isolation method of the meshed microgrid is completed by a control device, which is also called an end edge and is communicatively connected to the meshed microgrid, including a terminal device, a computer device, or a server.

[0023] Depend on Figure 1 It can be seen that the system isolation method of the meshed microgrid provided in the embodiment of the present application includes steps S101 to S103. The details are as follows:

[0024] S101: monitor the electrical quantity of the grid connection point in real time, and determine whether the grid-connected microgrid has entered the isolated grid operation mode based on the electrical quantity.

[0025] The electrical quantities at the grid connection point include voltage, frequency, and power. When the power supply circuit of the main grid is abnormal, such as loss of voltage or overload, the voltage and frequency will be detected to rise or fall at the grid connection point, and abnormal voltage and frequency will lead to unstable power. By real-time monitoring of the voltage, frequency, power and other electrical quantities at the grid connection point, it is possible to promptly determine whether the power supply circuit of the main grid is abnormal. When the power supply circuit of the main grid is abnormal, in order to reduce the impact of the power supply of the equipment in the microgrid, the grid-forming microgrid will enter the isolated grid operation state, and the grid-forming microgrid will continue to supply power to users alone.

[0026] S102: If it is determined that the microgrid enters the isolated grid operation mode, the AC busbar incoming switch is controlled to be cut off and the diesel generator is started.

[0027] When a main grid fault is detected, such as voltage drop, frequency fluctuation or grid power outage, the grid-type microgrid can no longer obtain power supply from the main grid. The grid-type microgrid will enter an isolated grid operation state and rely only on the power supply inside the grid-type microgrid to maintain power supply. In this embodiment, when the main grid fails, in order to isolate the connection with the main grid, the AC bus incoming line switch is first controlled to cut off to ensure that the problem of the main grid will not affect the inside of the grid-type microgrid, protect the equipment in the grid-type microgrid, and maintain continuous power supply to users. At the same time, the diesel generator is started, and after the diesel generator meets the synchronization conditions with the grid-type microgrid, the diesel generator is controlled to be incorporated into the grid-type microgrid as needed to achieve power output to ensure the stable operation of the grid-type microgrid. Among them, the diesel generator meeting the synchronization conditions means that the voltage, frequency and phase of the diesel generator outlet and the voltage, frequency and phase difference of the AC bus meet the fixed value requirements.

[0028] Specifically, the power source of the microgrid provided in the embodiment of the present application includes: a diesel generator, an energy storage device, a V2G and a photovoltaic power generation device. Figure 2 As shown, Figure 2 A schematic diagram of the structure of a meshed microgrid provided in an embodiment of the present application. The power supply of the meshed microgrid 201 includes: a diesel generator 202, an energy storage device 203, a photovoltaic power generation device 204, and a V2G system 204. The power supply of the meshed microgrid 201 is used to provide power to the meshed microgrid in an isolated grid operation state according to demand and maintain the frequency and voltage stability of the isolated grid.

[0029] Exemplarily, when the grid-type microgrid enters the isolated grid operation mode, in order to ensure the stable operation of the grid-type microgrid, after the diesel generator is incorporated into the grid-type microgrid, the grid-type inverter that controls the energy storage device and the photovoltaic power generation device automatically maintains the voltage and frequency stability of the grid-type microgrid. The diesel generator is used as a newly incorporated power source to provide power to the grid-type microgrid. In the isolated grid, each power generation unit enters the voltage droop and frequency droop control state. The energy storage and V2G systems dynamically adjust the droop coefficient according to the battery's state of charge, that is, the percentage of available energy in the battery, the battery's health, that is, the battery's remaining life and performance attenuation. The diesel engine and photovoltaic optimize the active and reactive outputs of each power generation unit according to the preset droop curve, smooth the frequency fluctuation and voltage fluctuation of the isolated grid, and maintain the stable operation of the isolated grid.

[0030] S103: According to the power difference at the isolation point before and after the AC bus switch is disconnected in the grid-type microgrid, combined with the SOC of the energy storage battery of the energy storage device at the current moment and its short-term overload capacity, the power generation of the photovoltaic power generation device, the discharge of the V2G system, and the power consumption of the load at the current moment, the control strategy is determined, and the system isolation of source-load matching is completed based on the control strategy.

[0031] According to the power difference at the isolation point before and after the AC bus switch of the grid-forming microgrid is disconnected, combined with the SOC of the energy storage battery of the energy storage device at the current moment and its short-term overload capacity, the power generation of the photovoltaic power generation device, the discharge of the V2G, and the operation of each load at the current moment, the power outage range control strategy is determined to complete the source-load matching system isolation, including: if the power difference is positive, according to the power difference, the SOC of the energy storage battery of the energy storage device at the current moment and its short-term overload capacity, the power generation of the photovoltaic power generation device, the power consumption of each load at the current moment and the priority of each load, the corresponding load is selectively cut off, and / or the power consumption of the load is dynamically adjusted; a diesel generator grid connection instruction is issued, and the diesel generator is connected to the grid-forming microgrid after the diesel generator meets the synchronous grid connection conditions, and the diesel generator supplies power to the load of the grid-forming microgrid; if the power difference is negative, the diesel generator is not started, and the power supply is adjusted downward according to the power supply of the energy storage device, the photovoltaic power generation device and the V2G system and their respective priorities, so as to achieve source-load matching system isolation and stable operation.

[0032] Preferably, if the power difference is positive, the corresponding load is selectively cut off and / or the power consumption of the load is dynamically adjusted according to the power difference, the SOC and short-term overload capacity of the energy storage battery of the energy storage device at the current moment, the power generation situation of the photovoltaic power generation device, the power consumption of each load at the current moment and the priority of each load, including: sending the SOC and short-term overload capacity of the energy storage battery of the energy storage device at the current moment, the power generation situation of the photovoltaic power generation device to the edge, receiving the predicted values ​​of each load, the maximum photovoltaic output predicted value and the remaining battery capacity predicted value sent by the edge, and according to the predicted values ​​of each load, the maximum photovoltaic output predicted value and the remaining battery capacity predicted value, combining the SOC and short-term overload capacity of the energy storage battery of the energy storage device at the current moment and the power generation situation of the photovoltaic power generation device Short-term overload capacity, power generation of photovoltaic power generation devices, power difference, current power consumption of each load and priority of each load, real-time determination of the system's stable isolation strategy, and completion of system isolation based on the isolation strategy in the coordinated controller; the predicted value of each load is obtained by the edge side based on a pre-trained load prediction model and the load power collected in real time by the end side; the photovoltaic maximum output prediction value is obtained by the edge side based on a pre-trained photovoltaic power generation prediction model and the weather information collected in real time by the end side; the battery remaining capacity prediction value is obtained by the edge side based on a pre-trained battery remaining capacity prediction model and the battery charging and discharging power, battery terminal voltage, battery current and battery temperature collected in real time by the end side.

[0033] It should be noted that the end side is the main body that executes the system isolation method of the meshed microgrid in the embodiment of the present application, and the edge side is a device that is connected to the end side for communication and has higher computing power than the end side.

[0034] In one implementation, based on the predicted value of each load, the predicted value of the maximum photovoltaic output, and the predicted value of the remaining battery capacity, combined with the SOC of the energy storage battery of the energy storage device at the current moment and its short-term overload capacity, the power generation of the photovoltaic power generation device, the power difference, the current power consumption of each load and the priority of each load, a stable isolation strategy for the system is determined in real time, including: the predicted value of each load, the predicted value of the maximum photovoltaic output, the predicted value of the remaining battery capacity, the short-term overload capacity of the energy storage battery, the power generation of the photovoltaic power generation device, the power difference, the current power consumption of each load and the priority of each load are input into a preset matching objective function for analysis, and the stable isolation strategy for the system is determined according to the analysis results.

[0035] Specifically, the analysis results include: a list of loads that need to be removed and loads that need to dynamically adjust power consumption and their adjustment amounts.

[0036] Among them, the preset matching objective function is expressed as:

[0037]

[0038] The constraints are expressed as:

[0039] P main (t)+P PV (t)+P bat.D (t) = ∑ i P load,i(t) +P bat.C (t)

[0040]

[0041] D rate (t)≤β(t)D rated

[0042] SOC estd (t)≤SOH(t)·SOC reted (t)

[0043]

[0044] P main (t)≥0

[0045] n=i+j

[0046] Among them, the objective function ΔJ represents the power matching situation after considering the current power of each load and its priority, the power prediction value of each load and its adjustment degree, and the maximum photovoltaic power generation prediction value, so as to complete the optimized isolation and the minimum power outage scope after the system is quickly isolated. The objective function value is the expected minimum power difference.

[0047] w iIndicates the power adjustment weight of the i-th load to be adjusted, which is the percentage of the corresponding load power; δ j It represents the priority of the jth load to be cut, which is 1 when it is cut in this round, otherwise it is 0; n represents the total number of loads.

[0048] P load,i(t) represents the real-time power of the i-th load at time t; P PV (t) represents the power generation of photovoltaic power at time t; P main (t) represents the power of the AC bus switch at time t; P bat.C (t) represents the charging power of the energy storage battery at time t, and is 0 when the battery is in a discharging state; P bat.D (t) represents the discharge power of the energy storage battery at time t, and is 0 when the battery is in a charging state.

[0049] represents the load forecast value of the i-th load to be adjusted; Indicates the current maximum photovoltaic output forecast value; Indicates the maximum predicted discharge power of the energy storage battery at time t; SOC estd (t) represents the estimated value of the remaining capacity of the energy storage battery at time t; SOC rated (t) represents the original estimated value of the remaining capacity of the energy storage battery at time t.

[0050] D rate (t) is the overcurrent multiple corresponding to the discharge power of the energy storage battery at time t, D rated is the rated discharge overcurrent multiple of the energy storage battery, β(t) is the overcurrent capacity attenuation factor of the energy storage battery, SOH(t) is the attenuation factor of the energy storage battery capacity, SOH(t)·SOC rated (t) represents the maximum state of charge of the energy storage battery at time t. Through the above constraints, the goal is to minimize the power difference.

[0051] In one embodiment, the priority of the energy storage device is higher than that of the V2G system, and the priority of the V2G system is higher than that of the photovoltaic power generation device; according to the power supply conditions of the energy storage device, the photovoltaic power generation device and the V2G system and their respective priorities, the power supply is adjusted downward to achieve system isolation with source-load matching, including: if the power difference is negative and it is determined that the power of the energy storage device is sufficient, power is released from the energy storage device to make up for the power difference, and the output power of the energy storage device is automatically adjusted to reduce the power supply to predetermined non-critical loads; when the energy storage device is insufficient to make up for the power difference, the V2G system is enabled to control the electric vehicle to feed back power from the battery to the power grid, and the fed-back power is adjusted to further reduce the power supply to non-critical loads; if the V2G system is still insufficient to make up for the power difference, it is monitored whether there is sunlight, and if there is sunlight, the photovoltaic power generation device is controlled to increase the power output and terminate the power supply to non-critical loads.

[0052] Prioritize the use of energy storage devices, then enable the V2G system, and finally use photovoltaic power generation to form a multi-level response mechanism to ensure stable power supply. According to the actual status of the energy storage device and the V2G system, dynamically adjust the output power and feedback power to ensure optimal power distribution. By real-time monitoring of system status and environmental conditions (such as light conditions), intelligently control the output of each power source to maximize the use of available resources. By gradually reducing and terminating the power supply to non-critical loads, ensure that critical loads can still operate stably when power is insufficient.

[0053] Through the above analysis, it can be known that the system isolation method of the grid-type microgrid provided in the embodiment of the present application includes: real-time monitoring of the electrical quantity of the grid-connected point, judging whether the grid-type microgrid is operating in an isolated grid based on the electrical quantity; if it is determined that the grid-type microgrid is in an isolated grid operation, controlling the AC bus to be cut off for switching, and starting the diesel generator; according to the power difference of the grid-type microgrid before and after the AC bus switch is disconnected, combined with the SOC of the energy storage battery of the energy storage device at the current moment and its short-term overload capacity, the power generation of the photovoltaic power generation device, the discharge of V2G, and the power consumption of the load at the current moment, determine the control strategy, and complete the source-load matching system isolation based on the control strategy. It solves the difficulty of state judgment of the grid-type microgrid in the isolated grid operation mode, improves the efficiency of emergency response and resource scheduling, ensures the stable operation of the grid-type microgrid, and improves the safety and reliability of the system.

[0054] See also Figure 3 , Figure 3 A schematic diagram of the structure of a control system provided in an embodiment of the present application.

[0055] like Figure 3 As shown, the control system 20 includes: a meshed microgrid 201 and a control device 202. The meshed microgrid 201 and the control device 202 are in communication connection, and the control device 202 includes but is not limited to a cloud server, a local server or a server cluster.

[0056] See also Figure 4 , Figure 4 A schematic diagram of the structure of a control device provided in an embodiment of the present application.

[0057] like Figure 4As shown, the control device 202 includes: a controller 401, a memory 402, and a computer program 403 stored in the memory 402 and executable on the controller 401, such as a system isolation program for a meshed microgrid. When the controller 401 executes the computer program 403, the steps of the system isolation method for the meshed microgrid are implemented. In a specific implementation, the process of implementing the steps of the system isolation method for the meshed microgrid when the controller 401 executes the computer program 403 can be implemented by hardware or software modules with the same functions. Exemplarily, the computer program 403 can be divided into one or more modules, one or more modules are stored in the memory 402, and executed by the controller 403 to complete the present application. One or more units can be a series of computer program instruction segments capable of completing a specific function, and the instruction segment is used to describe the execution process of the computer program 403 in the control device 401.

[0058] It should be understood that the control device 401 includes but is not limited to the controller 401 and the memory 402. Those skilled in the art can understand that Figure 4 It is only an example of the control device 202 and does not constitute a limitation of the control device 202. It may include more or fewer components than shown in the figure, or a combination of certain components, or different components. For example, the control device 202 may also include input and output devices, network access devices, buses, etc.

[0059] The controller 401 may be a central processing unit (CPU), or other general controllers, digital signal processors (DSP), application specific integrated circuits (ASIC), field-programmable gate arrays (FPGA), or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. The general controller may be a microcontroller or any conventional controller, etc.

[0060] The memory 402 may be an internal storage unit of the control device 202, such as a hard disk or memory of the control device 202. The memory 402 may also be an external storage device of the control device 202, such as a plug-in hard disk, a smart memory card (Smart Media Card, SMC), a secure digital (Secure Digital, SD) card, a flash card (FlashCard), etc. equipped on the control device 202. Further, the memory 402 may also include both an internal storage unit of the control device 202 and an external storage device. The memory 402 is used to store computer programs and other programs and data required by the control device 202. The memory 402 may also be used to temporarily store data that has been output or is to be output, etc. Specifically, the present application will not describe in detail the various components included in the control device.

[0061] It should be understood that the terms used in this application specification are only for the purpose of describing specific embodiments and are not intended to limit the application. As used in this application specification and the appended claims, unless the context clearly indicates otherwise, the singular forms "a", "an" and "the" are intended to include plural forms.

[0062] It should also be understood that the term "and / or" used in the specification of this application and the appended claims refers to any combination of one or more of the associated listed items and all possible combinations, including these combinations. It should be noted that, in this article, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or system including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or system. In the absence of further restrictions, an element defined by the sentence "including a..." does not exclude the presence of other identical elements in the process, method, article or system including the element.

[0063] The serial numbers of the embodiments of the present application are for description only and do not represent the advantages and disadvantages of the embodiments. The above description is only a specific implementation mode of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can easily think of various equivalent modifications or replacements within the technical scope disclosed in the present application, and these modifications or replacements should be included in the protection scope of the present application. Therefore, the protection scope of the present application shall be based on the protection scope of the claims.

Claims

1. A system isolation method for a meshed microgrid, It is characterized in that The grid-type microgrid includes a diesel generator, an energy storage device, a V2G system and a photovoltaic power generation device; the method includes: Real-time monitoring of the electrical quantity of the grid connection point, and judging whether the grid-connected microgrid has entered an isolated grid operation mode based on the electrical quantity; If it is determined that the grid-type microgrid enters the isolated grid operation mode, the AC busbar incoming line switch is controlled to be cut off, and the diesel generator is started; According to the power difference of the grid-type microgrid before and after the AC bus switch is disconnected, combined with the SOC of the energy storage battery of the energy storage device at the current moment and its short-term overload capacity, the power generation of the photovoltaic power generation device, the discharge of the V2G system, and the power consumption of the load at the current moment, a control strategy is determined, and the system isolation of source-load matching is completed based on the control strategy.

2. The system isolation method of the meshed microgrid according to claim 1, It is characterized in that The control strategy is determined based on the power difference of the grid-type microgrid before and after the AC bus switch is disconnected, combined with the SOC of the energy storage battery of the energy storage device at the current moment and its short-term overload capacity, the power generation of the photovoltaic power generation device, the discharge of the V2G system, and the power consumption of the load at the current moment, and the system isolation of source-load matching is completed based on the control strategy, including: If the power difference is positive, the corresponding load is selectively cut off, and / or the power consumption of the load is dynamically adjusted according to the power difference, the SOC of the energy storage battery of the energy storage device at the current moment and its short-term overload capacity, the power generation of the photovoltaic power generation device, the power consumption of each load at the current moment and the priority of each load; During the process of cutting off the load and / or adjusting the load power consumption, if it is detected that the energy storage battery of the energy storage device is insufficient, the diesel generator is connected to the grid-forming microgrid after meeting the synchronous grid-connection conditions, and the diesel generator supplies power to the load of the grid-forming microgrid; If the power difference is negative, the diesel generator is not started, and the power supply is adjusted downward according to the power supply conditions of the energy storage device, the photovoltaic power generation device and the V2G system and their respective priorities to achieve system isolation with source-load matching.

3. The system isolation method of the meshed microgrid according to claim 2, It is characterized in that The selective removal of corresponding loads and / or dynamic adjustment of load power consumption according to the power difference, the SOC of the energy storage battery of the energy storage device at the current moment and its short-term overload capacity, the power generation of the photovoltaic power generation device, the power consumption of each load at the current moment and the priority of each load, includes: The predicted value of each load, the predicted value of the maximum photovoltaic output and the predicted value of the remaining battery capacity sent by the receiving side are determined in real time according to the predicted value of each load, the predicted value of the maximum photovoltaic output and the predicted value of the remaining battery capacity, in combination with the SOC of the energy storage battery of the energy storage device at the current moment and its short-term overload capacity, the power generation status of the photovoltaic power generation device, the power difference, the current power consumption status of each load and the priority of each load, and the system isolation is completed in the coordination controller based on the isolation strategy; the predicted value of each load is obtained by the side based on the load prediction model completed in advance and the load power collected in real time by the end side; the predicted value of the maximum photovoltaic output is obtained by the side based on the photovoltaic power generation prediction model completed in advance and the weather information collected in real time by the end side; the predicted value of the remaining battery capacity is obtained by the side based on the battery remaining capacity prediction model completed in advance and the battery charging and discharging power, battery terminal voltage, battery current and battery temperature collected in real time by the end side.

4. The system isolation method of the meshed microgrid according to claim 3, It is characterized in that According to the predicted value of each load, the predicted value of the photovoltaic maximum output and the predicted value of the remaining battery capacity, combined with the SOC of the energy storage battery of the energy storage device at the current moment and its short-term overload capacity, the power generation of the photovoltaic power generation device, the power difference, the current power consumption of each load and the priority of each load, the isolation strategy for system stability is determined in real time, including: the predicted value of each load, the predicted value of the photovoltaic maximum output, the predicted value of the remaining battery capacity, the short-term overload capacity of the energy storage battery, the power generation of the photovoltaic power generation device, the power difference, the current power consumption of each load and the priority of each load are input into a preset matching objective function for analysis, and the isolation strategy for system stability is determined according to the analysis results.

5. The system isolation method of the meshed microgrid according to claim 4, It is characterized in that The analysis results include: a list of loads that need to be removed and their priorities, a list of loads that need to dynamically adjust power consumption, the adjustment amounts and their priorities.

6. The system isolation method of the meshed microgrid according to claim 4, It is characterized in that The preset matching objective function is expressed as: The constraints are expressed as: P main (t)+P PV (t)+P bat.D (t)=∑ i P load,i(t) +P bat.C (t) D rate (t)≤β(t)D rated SOC estd (t)≤SOH(t)·SOC rated (t) P main (t)≥0 n=t+j Among them, the objective function ΔJ represents the power matching after considering the current power and priority of each load, the power prediction value of each load and its adjustment degree, and the maximum photovoltaic power generation prediction value, so as to complete the optimized isolation and the minimum power outage range after the system is quickly isolated. The objective function value is the expected minimum power difference; w i Indicates the power adjustment weight of the i-th load to be adjusted, which is the percentage of the corresponding load power; δ j It indicates the priority of the jth load to be cut, which is 1 when it is cut in this round, otherwise it is 0; n indicates the total number of loads; P load,i(t) represents the real-time power of the i-th load at time t; P PV (t) represents the power generation of photovoltaic power at time t; P main (t) represents the power of the AC bus switch at time t; P bat.C (t) represents the charging power of the energy storage battery at time t, and is 0 when the battery is in a discharging state; P bat.D (t) represents the discharge power of the energy storage battery at time t, and is 0 when the battery is in a charging state; represents the load forecast value of the i-th load to be adjusted; Indicates the current maximum photovoltaic output forecast value; Indicates the maximum predicted discharge power of the energy storage battery at time t; SOC estd (t) represents the estimated value of the remaining capacity of the energy storage battery at time t; SOC rated (t) represents the original estimated value of the remaining capacity of the energy storage battery at time t; D rate (t) is the overcurrent multiple corresponding to the discharge power of the energy storage battery at time t, D rated is the rated discharge overcurrent multiple of the energy storage battery, β(t) is the overcurrent capacity attenuation factor of the energy storage battery, SOH(t) is the attenuation factor of the energy storage battery capacity, SOH(t)·SOC rated (t) represents the maximum state of charge of the energy storage battery at time t.

7. The system isolation method of the meshed microgrid according to claim 2, It is characterized in that The priority of the energy storage device is higher than that of the V2G system, and the priority of the V2G system is higher than that of the photovoltaic power generation device; According to the power supply conditions of the energy storage device, the photovoltaic power generation device and the V2G system and their respective priorities, the power supply is adjusted downward to achieve system isolation with source-load matching, including: If the power difference is negative, it is determined that the energy storage device has sufficient power, then power is released from the energy storage device to make up for the power difference, and the output power of the energy storage device is automatically adjusted to reduce power supply to a predetermined non-critical load; When the energy storage device is insufficient to make up for the power difference, the V2G system is enabled to control the electric vehicle to feed back power from the battery to the power grid, and the fed-back power is adjusted to further reduce the power supply to the non-critical loads; If the V2G system is still insufficient to make up for the power difference, monitor whether there is sunlight. If there is sunlight, control the photovoltaic power generation device to increase power output and terminate the power supply to the non-critical load.

8. A control device, include: Memory and controller; The memory is used to store computer programs; The controller is used to execute the computer program and implement the steps of the method according to any one of claims 1 to 7 when executing the computer program.

9. A computer-readable storage medium storing a computer program. It is characterized in that When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 7 are implemented.

Citation Information

Cited By

  • Start control method and system suitable for full-direct-current collection network construction type energy storage isolated network

    CN119834300A

  • Fault matching control method and system suitable for network construction type energy storage in isolated network

    CN119965908A