Vertical shaft large-section pressure steel pipe mounting device and method
By designing a device including a frame, indexing platform and pressure steel pipe installation bridge in the vertical shaft, the problems of many node alignment times, large welding volume and safety risks in large pressure steel pipe installation are solved, and efficient installation and Quality assurance.
Patent Information
- Application Number
- CN202411043058.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-31
- Publication Date
- 2024-11-15
AI Technical Summary
In large-scale water conservancy and hydropower projects in alpine canyons, the installation of large pressure steel pipes in the vertical shaft has problems such as space limitations, many node alignment times, difficulty in accuracy control, many welds, difficulty in quality assurance, large safety risks and long cycles.
A large-segment pressure steel pipe installation device of vertical shaft is designed, including frame, indexing platform, transfer trolley, pressure steel pipe installation bridge machine and indexing mechanism, and short-term through pressure steel pipe limit holding device and roller welding trolley The clamping, adjustment, welding and indexing of segments reduces the amount of welding and improves installation efficiency.
It effectively solves the problems of many short sections, long cycles, large welding workload, difficult quality control and high safety risks, reduces installation costs, optimizes construction management, and improves installation efficiency and safety.
Smart Images

Figure CN118951252A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of installation of large-scale pressure steel pipes for water conservancy and hydropower under environmental conditions of construction sites, and particularly relates to a device and method for installing large-segment pressure steel pipes in a vertical shaft. Background Art
[0002] There are many large-scale water conservancy and hydropower projects built in high mountain valleys. In the tunnels where the water diversion penstocks are arranged, there are technical difficulties in installing large penstocks in the shaft. Affected by the tunnel working environment, large penstocks can usually only be transported to the turning position of the shaft in short sections (or tiles), and then transferred and hoisted to the assembly position by the shaft hoisting equipment. At the shaft assembly position, the short-section penstocks are assembled as a whole. Since the length of the shaft section ranges from tens of meters to hundreds of meters, or even thousands of meters, the installation method of the shaft penstock has the problems of limited installation space, many pipe section alignment times, high difficulty in precision control, many horizontal welds, high difficulty in quality assurance, high safety risks and long installation period. In view of the characteristics and difficulties of the installation of large penstock shafts, it is necessary to study a shaft penstock installation method and device to solve the construction technical problems and ensure the construction quality, construction period and safety. Summary of the invention
[0003] In view of the technical problems to be solved by the present invention, the present invention provides a large-segment pressure steel pipe device and method for a vertical shaft, which can effectively solve the technical problems of short-section vertical shaft pressure steel pipe installation with many sections, long cycle, large welding workload at unfavorable welding positions, great difficulty in quality control, and great safety risks, thereby reducing installation costs and optimizing construction management.
[0004] The objective of the present invention is achieved through the following technical solutions: A large-section pressure steel pipe installation device for a vertical shaft comprises a frame, a transfer platform, a transfer trolley, a pressure steel pipe installation bridge crane and a transfer mechanism, wherein the transfer platform is arranged at the entrance of the vertical shaft, the frame is arranged on the transfer platform, a roller welding trolley, a welding machine, a sliding trolley, an adjustable roller and a pressure steel pipe limiting and holding device are arranged on the transfer platform, the pressure steel pipe limiting and holding device and the roller welding trolley are arranged at intervals, the transfer trolley is arranged in a straight section of the tunnel, the pressure steel pipe installation bridge crane is slidably arranged in the straight section of the tunnel, the pressure steel pipe limiting and holding device is used for clamping and fixing a short section of the pressure steel pipe, the pressure steel pipe installation bridge crane is used for the X, Y and Z three-axis movement of the short section of the pressure steel pipe in the straight section of the tunnel and the lowering or lifting of the long section of the pressure steel pipe after welding; the transfer mechanism is used for the transfer of the transfer platform.
[0005] Preferably, the pressure steel pipe limiting and holding device includes two vertical clamping parts and a horizontal part. The two vertical clamping parts are hinged to the horizontal part. The vertical clamping part is connected to the horizontal part through a locking cylinder. The locking cylinder drives the vertical clamping part to rotate to achieve clamping or loosening of the short section of the pressure steel pipe.
[0006] Preferably, both sides of the transfer platform are arranged at the entrance of the shaft through platform locking devices.
[0007] Preferably, the transfer mechanism includes a transfer drive gear, a transfer drive rack and a transfer drive cylinder, the front end of the transfer drive cylinder is connected to the transfer drive rack, the transfer drive rack is meshed with the transfer drive gear, the transfer drive cylinder drives the transfer drive gear to rotate, and the transfer drive gear is fixedly arranged on the frame.
[0008] Preferably, the roller welding trolley includes a roller welding base, and roller welding assemblies are hinged on the left and right sides of the roller welding base. The roller welding assembly includes a rotating member, and the rotating member is rotatably connected to the roller welding base. Rollers are provided on the upper and lower sides of the rotating member, and the lower roller is connected to the rotating drive member through a connecting member.
[0009] Preferably, a plurality of adjustable rollers are provided, and the adjustable rollers are arranged between the frame and the horizontal portion or between the frame and the roller welding base.
[0010] Preferably, the frame is provided with a plurality of sets of adjustable electric push rods.
[0011] Preferably, it also includes a hydraulic control system, which is used to control the start and stop of the locking cylinder and the indexing drive cylinder.
[0012] A method for installing a large-segment pressure steel pipe in a vertical shaft comprises the following steps: Step 1: Transfer the first pressure steel pipe short section to the adjustable roller, and adjust the verticality of the end face of the first pressure steel pipe short section; Step 2: The second penstock section is transferred to the adjustable roller, and the first penstock section and the second penstock section are adjusted and assembled; Step 3: Weld the welds of the penstock short section 1 and the penstock short section 2, and perform nondestructive testing; Step 4: After nondestructive testing, repeat steps 1 to 3 to complete the welding of the long section pressure steel pipe; Step 5: The long section pressure steel pipe is locked with the transfer platform, the adjustable roller is retracted, and then the transfer platform is opened and locked; Step 6: The transfer platform is transferred, the pressure steel pipe installation bridge crane is connected to the long-section pressure steel pipe, the lifting system is pre-tightened, the pressure steel pipe locking mechanism of the transfer platform is released, and the long-section pressure steel pipe is lowered or lifted; Step 7: Adjust and assemble to meet the requirements, and weld the vertical sections; Step 8. Repeat steps 5 to 7 until the shaft pressure steel pipe is installed.
[0013] Preferably, in step one and step two, pressure steel pipe short section one is placed on a pressure steel pipe limiting and holding device, and pressure steel pipe short section two is placed on a roller welding trolley. The pressure steel pipe is first installed by a bridge crane to lift pressure steel pipe short section two and pressure steel pipe short section one, and then the pressure steel pipe limiting and holding device is used to adjust the verticality of the end face of short section one. The coaxiality of pressure steel pipe short section two and pressure steel pipe short section one in the horizontal direction is adjusted by adjustable rollers and adjusting electric push rods.
[0014] Preferably, in the step three, after the connected pressure steel pipe pup sections are fixed by manual spot welding, the pressure steel pipe limiting holding device is released, and the submerged arc welding machine mounting bracket and the submerged arc welding machine are installed on the transfer platform; the roller welding trolley drives the pressure steel pipe pup section one and the pressure steel pipe pup section two to rotate, and the submerged arc welding machine automatically welds the annular seam between the pressure steel pipe pup section one and the pressure steel pipe pup section two.
[0015] Preferably, in step five, the frame is connected and fixed to the long-segment pressure steel pipe, the electric push rod is adjusted to retract, so that the telescopic end of the electric push rod is disengaged from the horizontal part or the roller welding base, and the locking electric push rod retracts the locking beam and moves away from the locking beam fixing pin of the civil engineering, thereby completing the unlocking of the transfer platform.
[0016] Preferably, in step six, the frame on the transfer platform is hinged to the ground through an axis, and the transfer platform is transferred by pushing and pulling a set of hydraulic cylinders arranged on both sides of the transfer platform; the long-segment pressure steel pipe is connected to the pressure steel pipe installation bridge crane, the pressure steel pipe installation bridge crane pre-tightens the pull rope, and the long-segment pressure steel pipe is lowered or lifted by the pressure steel pipe installation bridge crane.
[0017] Preferably, in step seven, the bridge crane is installed by means of a pressure steel pipe; and the circumferential butt welding is performed manually.
[0018] The beneficial effects of this technical solution are as follows: 1. The present invention provides a method and device for installing large-segment pressure steel pipes in a vertical shaft. The device has the functions of assembling short-segment steel pipes, clamping and positioning, inter-segment adjustment, steel pipe rotation drive, inter-segment weld welding, long-segment pressure steel pipe transfer, transfer process and locking and holding of pressure steel pipes in a vertical state, and can cooperate with the lifting system to complete the installation of vertical section pressure steel pipes.
[0019] 2. The invention provides a method for installing large-segment pressure steel pipes in a vertical shaft, which can effectively solve the technical problems of short-section vertical shaft pressure steel pipes, such as many sections for assembly, long cycle, large welding workload at unfavorable welding positions, great difficulty in quality control, and great safety risks, thereby reducing installation costs and optimizing construction management.
[0020] 3. The present invention provides a method for installing a large-segment pressure steel pipe in a vertical shaft. A welding transfer platform is set near the interface between the straight section and the vertical bend of the tunnel. On the transfer platform, short sections of the pressure steel pipe are assembled into long sections of the pressure steel pipe, and submerged arc welding is used to weld the long-segment pressure steel pipe. The long-segment pressure steel pipe is positioned on the installation axis by rotating hinge displacement, lowered or lifted into place by steel pipe lifting equipment, and butt-welded with the front section pressure steel pipe. This method decomposes the serial installation work into parallel work of two workstations, and can significantly reduce the number of assembly times and welding amount of the vertical pressure steel pipe (calculated based on at least two short sections, the workload of unfavorable workstations can be reduced by 50%), thereby achieving the purpose of reducing construction difficulty, ensuring installation quality, reducing labor intensity, improving efficiency, reducing costs, shortening construction period and improving safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a structural schematic diagram of the present invention; Figure 2 It is a structural schematic diagram of the pressure steel pipe limiting and holding device in the present invention; Figure 3 It is a structural schematic diagram of the roller welding trolley in the present invention; Figure 4 It is a structural schematic diagram of step 1 of the installation method of the present invention; Figure 5 It is a structural schematic diagram of step three of the installation method of the present invention; Figure 6 It is a structural schematic diagram of step 4 of the installation method of the present invention; Figure 7 This is a structural schematic diagram of step five of the installation method of the present invention; Figure 8 The structure of step 6 of the installation method of the present invention is shown in FIG. Figure 1 ; Fig. 9 The structure of step 6 of the installation method of the present invention is shown in FIG. Figure 2 ; Fig.10 It is a structural schematic diagram of step seven of the installation method of the present invention; Fig.11 It is a structural schematic diagram of step eight of the installation method of the present invention; Among them: 1. Frame; 2. Transfer platform; 3. Pressure steel pipe limit holding device; 31. Vertical clamping part; 32. Horizontal part; 34. Locking cylinder; 4. Transfer trolley; 6. Pressure steel pipe installation bridge crane; 7. Transfer mechanism; 71. Transfer drive gear; 72. Transfer drive cylinder; 8. Adjustable roller; 9. Platform locking device; 11. Roller welding trolley; 111. Roller welding base; 113. Roller welding assembly; 114. Rotating part; 115. Roller; 13. Adjustment electric push rod. DETAILED DESCRIPTION
[0022] The present invention is further described in detail below in conjunction with examples, but the embodiments of the present invention are not limited thereto.
[0023] Example 1 like Figure 1-Figure 3 As shown, a method and device for installing large-section pressure steel pipes in a vertical shaft, and a device for installing large-section pressure steel pipes in a vertical shaft, include a frame 1, a transfer platform 2, a transfer trolley 4, a pressure steel pipe installation bridge machine 6 and a transfer mechanism 7, the transfer platform 2 is arranged at the entrance of the vertical shaft, the frame 1 is arranged on the transfer platform 2, the transfer platform 2 is provided with a roller welding trolley 11, a welding machine, an adjustable roller 8 and a pressure steel pipe limiting and holding device 3, the pressure steel pipe limiting and holding device 3 and the roller welding trolley 11 are arranged at intervals, the transfer trolley 4 is arranged in a straight section of the tunnel, the pressure steel pipe installation bridge machine 6 is slidably arranged in the straight section of the tunnel, the pressure steel pipe limiting and holding device 3 is used for clamping and fixing the pressure steel pipe short section, the pressure steel pipe installation bridge machine 6 is used for the X, Y and Z three-axis movement of the pressure steel pipe short section in the straight section of the tunnel and the lowering or lifting of the welded pressure steel pipe long pipe section; the transfer mechanism 7 is used for the transfer of the transfer platform 2.
[0024] Example 2 The difference between this embodiment and embodiment 1 is that the pressure steel pipe limiting and holding device 3 includes two vertical clamping parts 31 and a horizontal part 32. The two vertical clamping parts 31 are hinged to the horizontal part 32. The vertical clamping part 31 is connected to the horizontal part 32 through a locking cylinder 34. The locking cylinder 34 drives the vertical clamping part 31 to rotate to achieve clamping or loosening of the short section of the pressure steel pipe.
[0025] The two sides of the transfer platform 2 are arranged at the entrance of the shaft through the platform locking device 9. The platform locking device 9 adopts two box beams driven by electric push rods to extend and retract. When the transfer platform 2 needs to be locked, the locking beam is pushed out by the electric push rod and inserted into the locking beam fixing pin of the civil engineering to complete the locking of the transfer platform 2.
[0026] Among them, the indexing mechanism 7 includes an indexing drive gear 71, an indexing drive rack and an indexing drive cylinder 72. The front end of the indexing drive cylinder 72 is connected to the indexing drive rack, the indexing drive rack is engaged with the indexing drive gear 71, and the indexing drive cylinder 72 drives the indexing drive gear 71 to rotate. The indexing drive gear 71 is fixedly set on the frame 1.
[0027] The roller welding trolley 11 includes a roller welding base 111, and the roller welding assembly 113 is hinged on the left and right sides of the roller welding base 111. The roller welding assembly 113 includes a rotating member 114, and the rotating member 114 is rotatably connected to the roller welding base 111. The rotating member 114 is provided with rollers 115 on both the upper and lower sides, and the lower roller 115 is connected to the rotating driving member through a connecting member. The rotating driving member and the connecting member are prior art, and the rotating driving member is a rotating motor, and the connecting member is a chain.
[0028] There are multiple adjustable rollers 8 , and the adjustable rollers 8 are arranged between the frame 1 and the horizontal portion 32 or between the frame 1 and the roller welding base 111 .
[0029] Wherein, the frame 1 is provided with a plurality of sets of adjusting electric push rods 13 .
[0030] It also includes a hydraulic control system, which is used to control the start and stop of the locking cylinder 34 and the indexing drive cylinder 72.
[0031] Example 3 This embodiment adopts a large-segment pressure steel pipe installation device for a vertical shaft in Embodiment 2, such as Figure 4-Figure 11 As shown, a method for installing a large-segment pressure steel pipe in a vertical shaft comprises the following steps: Step 1: The pressure steel pipe short section 1 is transferred to the adjustable roller 8, and the verticality of the end face of the pressure steel pipe short section 1 is adjusted; Step 2: The second penstock section is transferred to the adjustable roller 8, and the first penstock section and the second penstock section are adjusted and assembled; Step 3: Weld the welds of the penstock short section 1 and the penstock short section 2, and perform nondestructive testing; Step 4: After nondestructive testing, repeat steps 1 to 3 to complete the welding of the long section pressure steel pipe; Step 5: The long section pressure steel pipe is fixed to the transfer platform 2, the adjustable roller 8 is retracted, and then the transfer platform 2 is opened and locked; Step 6: The transfer platform 2 is transferred, the pressure steel pipe installation bridge crane 6 is connected to the long-section pressure steel pipe, the lifting system is pre-tightened, the pressure steel pipe locking mechanism of the transfer platform 2 is released, and the long-section pressure steel pipe is lowered or lifted; Step 7: Adjust and assemble to meet the requirements, and weld the vertical sections; Step 8. Repeat steps 5 to 7 until the shaft pressure steel pipe is installed.
[0032] Preferably, in step one and step two, the pressure steel pipe short section one is placed on the pressure steel pipe limiting and holding device 3, and the pressure steel pipe short section two is placed on the roller welding trolley 11. The pressure steel pipe installation bridge crane 6 is first used to lift the pressure steel pipe short section two and the pressure steel pipe short section one to complete the rough positioning, and then the pressure steel pipe limiting and holding device 3 is used to adjust the verticality of the end face of the short section one, and the coaxiality of the pressure steel pipe short section two and the pressure steel pipe short section one in the horizontal direction is adjusted by the adjustable roller 8 and the adjusting electric push rod 13.
[0033] Preferably, in the step three, after the connected pressure steel pipe pup sections are fixed by manual spot welding, the pressure steel pipe limiting holding device 3 is released, and the submerged arc welding machine mounting bracket and the submerged arc welding machine are installed on the transfer platform 2; the roller welding trolley 11 drives the pressure steel pipe pup section 1 and the pressure steel pipe pup section 2 to rotate, and the submerged arc welding machine automatically welds the annular seam between the pressure steel pipe pup section 1 and the pressure steel pipe pup section 2.
[0034] Preferably, in step five, the frame 1 is connected and fixed to the long-section pressure steel pipe, the electric push rod 13 is adjusted to retract, so that the telescopic end of the electric push rod 13 is disengaged from the horizontal part 32 or the roller welding base 111, the long-section pressure steel pipe is connected to the transfer platform 2, and the locking electric push rod retracts the locking beam and moves away from the locking beam fixing pin of the civil engineering, thereby completing the unlocking of the transfer platform 2.
[0035] Preferably, in step six, the frame 1 on the transfer platform 2 is hinged to the ground through an axis, and the transfer platform 2 is transferred by pushing and pulling a set of hydraulic cylinders arranged on both sides of the transfer platform 2; the long-segment pressure steel pipe is connected to the pressure steel pipe mounting bridge crane 6, the pressure steel pipe mounting bridge crane 6 pre-tightens the pull rope, and the long-segment pressure steel pipe is lowered or lifted by the pressure steel pipe mounting bridge crane 6.
[0036] Preferably, in step seven, the bridge crane 6 is lifted and lowered by installing a pressure steel pipe; and the circumferential butt welding is performed manually.
[0037] The beneficial effects of this technical solution are as follows: 1. The present invention provides a method and device for installing large-segment pressure steel pipes in a vertical shaft. The device has the functions of assembling short-segment steel pipes, clamping and positioning, inter-segment adjustment, steel pipe rotation drive, inter-segment weld welding, long-segment pressure steel pipe transfer, transfer process and locking and holding of pressure steel pipes in a vertical state, and can cooperate with the lifting system to complete the installation of vertical section pressure steel pipes.
[0038] 2. The invention provides a method for installing large-segment pressure steel pipes in a vertical shaft, which can effectively solve the technical problems of short-section vertical shaft pressure steel pipes, such as many sections for assembly, long cycle, large welding workload at unfavorable welding positions, great difficulty in quality control, and great safety risks, thereby reducing installation costs and optimizing construction management.
[0039] 3. The present invention provides a method for installing a large-segment pressure steel pipe in a vertical shaft. A welding transfer platform 2 is set near the interface between the straight section and the vertical bend of the tunnel. On the transfer platform 2, short sections of the pressure steel pipe are assembled into long sections of the pressure steel pipe, and submerged arc welding is used to weld the long-segment pressure steel pipe. The long-segment pressure steel pipe is positioned on the installation axis by rotating hinge displacement, lowered or lifted into place by steel pipe lifting equipment, and butt-welded with the front-segment pressure steel pipe. This method decomposes the serial installation work into parallel work of two stations, and can significantly reduce the number of assembly times and welding amount of the vertical pressure steel pipe (calculated based on at least two short sections, the workload of the unfavorable stations can be reduced by 50%), thereby achieving the purpose of reducing construction difficulty, ensuring installation quality, reducing labor intensity, improving efficiency, reducing costs, shortening construction period and improving safety.
[0040] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Any simple modification or equivalent change made to the above embodiment based on the technical essence of the present invention is within the protection scope of the present invention.
Claims
1. A device for installing a large-section pressure steel pipe in a vertical shaft, characterized in that: The invention comprises a frame (1), a transfer platform (2), a transfer trolley (4), a pressure steel pipe installation bridge machine (6) and a transfer mechanism (7), wherein the transfer platform (2) is arranged at the entrance of the shaft, the frame (1) is arranged on the transfer platform (2), and a roller welding trolley (11), a welding machine, a sliding trolley (12), an adjustable roller (8) and a pressure steel pipe limit holding device (3) are arranged on the transfer platform (2). The pressure steel pipe limit holding device (3) and the roller welding trolley (11) are ) are arranged at intervals, the transfer trolley (4) is arranged in the straight section of the tunnel, the pressure steel pipe installation bridge crane (6) is slidably arranged in the straight section of the tunnel, the pressure steel pipe limiting holding device (3) is used to clamp and fix the pressure steel pipe short section, the pressure steel pipe installation bridge crane (6) is used for the X, Y and Z three-axis movement of the pressure steel pipe short section in the straight section of the tunnel and the lowering or lifting of the welded pressure steel pipe long section; the transfer mechanism (7) is used for the transfer of the transfer platform (2).
2. A vertical shaft large-segment pressure steel pipe installation device according to claim 1, characterized in that: The penstock position limiting and holding device (3) comprises two vertical clamping parts (31) and a horizontal part (32). The two vertical clamping parts (31) are hinged to the horizontal part (32). The vertical clamping parts (31) are connected to the horizontal part (32) via a locking oil cylinder (34). The locking oil cylinder (34) drives the vertical clamping parts (31) to rotate to clamp or release the penstock short section.
3. A device for installing a large-segment pressure steel pipe in a vertical shaft according to claim 2, characterized in that: The indexing mechanism (7) comprises an indexing drive gear (71), an indexing drive rack and an indexing drive cylinder (72); the front end of the indexing drive cylinder (72) is connected to the indexing drive rack; the indexing drive rack is meshed with the indexing drive gear (71); the indexing drive cylinder (72) drives the indexing drive gear (71) to rotate; and the indexing drive gear (71) is fixedly arranged on the frame (1).
4. A device for installing a large-segment pressure steel pipe in a vertical shaft according to claim 3, characterized in that: The roller welding trolley (11) comprises a roller welding base (111), and roller welding assemblies (113) are hingedly connected to the left and right sides of the roller welding base (111). The roller welding assembly (113) comprises a rotating member (114), and the rotating member (114) is rotatably connected to the roller welding base (111). The rotating member (114) is provided with rollers (115) on both the upper and lower sides, and the lower roller (115) is connected to the rotating drive member via a connecting member.
5. A method for installing a large-segment pressure steel pipe in a vertical shaft, characterized in that: The following steps are involved: Step 1: The first penstock short section is transferred to the adjustable roller (8), and the verticality of the end face of the first penstock short section is adjusted; Step 2: The second penstock short section is transferred to the adjustable roller (8), and the first penstock short section and the second penstock short section are adjusted and assembled; Step 3: Weld the welds of the penstock short section 1 and the penstock short section 2, and perform nondestructive testing; Step 4: After nondestructive testing, repeat steps 1 to 3 to complete the welding of the long section pressure steel pipe; Step 5: The long section pressure steel pipe is locked with the transfer platform (2), the adjustable roller (8) is retracted, and then the transfer platform (2) is opened and locked; Step 6: The transfer platform (2) is transferred, the pressure steel pipe installation bridge crane (6) is connected to the long-section pressure steel pipe, the lifting system is pre-tightened, the pressure steel pipe locking mechanism of the transfer platform (2) is released, and the long-section pressure steel pipe is lowered or lifted; Step 7: Adjust and assemble to meet the requirements, and weld the vertical sections; Step 8. Repeat steps 5 to 7 until the shaft pressure steel pipe is installed.
6. A method for installing a large-segment pressure steel pipe in a vertical shaft according to claim 5, characterized in that: In the steps 1 and 2, the pressure steel pipe short section 1 is placed on the pressure steel pipe limiting holding device (3), and the pressure steel pipe short section 2 is placed on the roller welding trolley (11). The pressure steel pipe installation bridge crane (6) is first used to lift the pressure steel pipe short section 2 and the pressure steel pipe short section 1 to complete the rough positioning. After that, the pressure steel pipe limiting holding device (3) is used to adjust the verticality of the end face of the short section 1. The coaxiality of the pressure steel pipe short section 2 and the pressure steel pipe short section 1 in the horizontal direction is adjusted by the adjustable roller (8) and the adjusting electric push rod (13).
7. A method for installing a large-segment pressure steel pipe in a vertical shaft according to claim 6, characterized in that: In the step three, after the connected penstock short sections are fixed by manual spot welding, the penstock limiting holding device (3) is released, and a submerged arc welding machine mounting bracket and a submerged arc welding machine are installed on the transfer platform (2); the roller welding trolley (11) drives the penstock short section one and the penstock short section two to rotate, and the submerged arc welding machine automatically welds the annular seam between the penstock short section one and the penstock short section two.
8. A method for installing a large-segment pressure steel pipe in a vertical shaft according to claim 7, characterized in that: In the step five, the frame (1) is connected and fixed to the long section pressure steel pipe, the electric push rod (13) is adjusted to retract, so that the telescopic end of the electric push rod (13) is disengaged from the horizontal part (32) or the roller welding base (111), and the locking electric push rod retracts the locking beam and moves away from the locking beam fixing pin of the civil engineering, thereby completing the unlocking of the transfer platform (2).
9. A method for installing a large-segment pressure steel pipe in a vertical shaft according to claim 8, characterized in that: In the step six, the frame (1) on the transfer platform (2) is hinged to the ground via an axis, and the transfer platform (2) is transferred by pushing and pulling a set of hydraulic cylinders arranged on both sides of the transfer platform (2); the long-segment pressure steel pipe is connected to the pressure steel pipe installation bridge crane (6), the pressure steel pipe installation bridge crane (6) pre-tightens the pull rope, and the long-segment pressure steel pipe is lowered or lifted by the pressure steel pipe installation bridge crane (6).
10. A method for installing a large-segment pressure steel pipe in a vertical shaft according to claim 9, characterized in that: In the step seven, the bridge crane (6) is raised and lowered by installing a pressure steel pipe; and the circumferential seam butt welding is performed manually.