Reservoir box dam filling and compacting construction method

By monitoring the soil moisture content and compaction degree in real time, adjusting the rolling parameters, and laying geogrids in the dam filling, the bearing capacity and stability control problems in the dam rolling and filling of the reservoir dam are solved, and the construction quality is improved and dam body strength.

CN118958265APending Publication Date: 2024-11-15POWERCHINA MUNICIPAL CONSTR GRP CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411366475.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-29
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

During the rolling and filling process of reservoir dams, it is difficult for the existing technology to accurately control the bearing capacity and stability of the dam body. It is greatly disturbed by human factors and has a large post-test error, which affects the construction quality.

Method used

The soil temperature and humidity sensor is used to monitor the moisture content of the filling soil in real time, and the excavation area is determined through the PLC control system. The intelligent roller press monitors the compaction and moisture content in real time, adjusts the rolling parameters, and combines the laying of geogrids. Ensure that the quality and compaction of the filling soil are within the allowable deviation range.

Benefits of technology

It improves construction efficiency and quality stability, reduces the influence of human factors, enhances the mechanical strength of the dam's compressive and shear resistance, and improves the overall bearing capacity and stability of the dam body.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958265A_ABST
    Figure CN118958265A_ABST
Patent Text Reader

Abstract

The invention provides a reservoir box dam filling and compacting construction method, which relates to the field of geotechnical engineering and comprises the following steps: S1, monitoring the water content of filling soil materials in real time, determining an excavation area according to the water content of the filling soil materials, and taking soil and transporting the soil to a box dam filling area; s2, soil materials are filled for paving; s3, after paving of the filling soil material is completed, an intelligent rolling machine is used for rolling, the compaction rate, the water content and the compaction path of the filling soil material are monitored in real time in the rolling process, and the working state of the intelligent rolling machine is adjusted in real time according to the monitoring condition; s4, geogrids are laid on the compacted filling soil materials; and S5, repeating the steps S2-S4 until filling and forming, and then carrying out subsequent work. According to the construction method, the water content and the compactness are monitored through the PLC control system, the influence of human factors on the construction quality is reduced, and the overall bearing capacity and stability of the dam are improved through the geogrids.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of geotechnical engineering, and in particular to a reservoir dam filling and compaction construction method. Background Art

[0002] Reservoir dams are usually built by rolling fill soil, specifically by rolling the earth materials in layers. This method has the characteristics of using local materials, saving costs, simple construction, and easy to meet construction quality requirements. It is the most widely used and fastest-growing dam construction method in water conservancy project construction in the world today.

[0003] In the rolling construction of earth dams, the issues that the project is concerned about are the bearing capacity and stability of the dam body. Different moisture contents and compaction degrees will cause different bearing capacities and stability of the dam body. According to the current construction specifications, the quality of earth-rock dam filling rolling is mostly detected and controlled by combining the in-process control of rolling parameters (such as the number of rolling passes, rolling speed, exciting force, vibration frequency and amplitude, etc.) with post-process in-situ tests (test pit method to monitor compaction standards). However, the in-process control of rolling parameters is easily affected by human factors, and the post-process in-situ tests use a limited number of test pit test results to reflect the rolling quality of the entire construction unit warehouse surface, which often results in large errors.

[0004] Therefore, we propose a construction method for reservoir dam filling and compaction. Summary of the invention

[0005] In view of the shortcomings of the prior art, the present invention provides a reservoir dam filling and compaction construction method.

[0006] To achieve the above object, the present invention adopts the following technical solutions:

[0007] The present invention provides a reservoir dam filling and compaction construction method, comprising the following steps:

[0008] S1: Use soil temperature and humidity sensors to monitor the moisture content of the filling soil in real time, determine the excavation area based on the moisture content of the filling soil, and then transport the soil to the dam filling area;

[0009] S2: The filling soil materials transported to the dam filling area are paved, and the paving is carried out by the advance occupation method;

[0010] S3: After the filling soil is paved, the filling soil is compacted by the intelligent roller. During the compaction process, the compaction rate, moisture content and compaction path of the filling soil are monitored in real time, and the working state of the intelligent roller is adjusted in real time according to the monitoring situation;

[0011] S4: Lay geogrid on compacted fill soil;

[0012] S5: Repeat steps S2-S4 until the filling is completed, and then measure the dam axis and elevation, trim the slope, construct slope protection, and clean up and accept the work.

[0013] Furthermore, the step S1 includes the following steps:

[0014] S11: According to the excavation depth and width, soil temperature and humidity sensors are buried in the dam filling material field, and the soil temperature and humidity sensors are arranged at intervals according to the width and length of the dam filling material field. The buried soil temperature and humidity sensors at least cover the entire dam filling material field;

[0015] S12: The buried soil temperature and humidity sensors monitor the moisture content of the filling soil in the entire dam filling field in real time. The soil temperature and humidity sensors transmit the moisture content data to the PLC control system, and the PLC control system analyzes and processes the received data to determine the excavation area;

[0016] S13: After the excavation area is determined, an excavator is used to excavate the filling soil, and then the filling soil is transported to the dam filling area using a transport vehicle.

[0017] Furthermore, in step S12, construction parameters are preset in the PLC control system, and the construction parameters include the optimal moisture content of the fill soil and the preset compaction degree of the fill soil. The PLC control system compares the received moisture content data of the fill soil with the preset optimal moisture content of the fill soil, and determines that the area where the moisture content of the fill soil is within the allowable deviation range of the optimal moisture content is the excavation area.

[0018] Furthermore, the soil temperature and humidity sensor is electrically connected to a data acquisition unit, the data acquisition unit is electrically connected to the solar panel, and the data acquisition unit transmits the data monitored by the soil temperature and humidity sensor to the PLC control system.

[0019] Furthermore, in step S4, a geogrid containing magnesium acrylate, an oxidizing agent sodium persulfate and a cross-linking agent sodium thiosulfate is used.

[0020] Furthermore, the step S3 includes the following steps:

[0021] S31: After the filling soil is paved, the intelligent rollers are arranged to allow the intelligent rollers to roll the filling soil along a predetermined path;

[0022] S32: During the rolling process, the compaction sensor on the intelligent roller monitors the compaction of the filling soil in real time, the near-infrared moisture meter monitors the moisture content of the filling soil in real time, and the directional positioning antenna locates the position of the intelligent roller in real time and determines the compaction path of the intelligent roller;

[0023] S33: The compaction sensor sends the monitored compaction rate data to the PLC control system in real time, and the near-infrared moisture meter sends the monitored moisture content data to the PLC control system in real time. The PLC control system compares the received compaction rate data with the preset compaction rate, and compares the received moisture content data with the optimal moisture content. If both are within the allowable deviation range, the PLC control system does not adjust the working state of the intelligent roller. If at least one of the two is not within the allowable deviation range, the PLC control system sends a command to the intelligent roller to adjust the working state of the intelligent roller.

[0024] Furthermore, in step S3, the intelligent roller is equipped with a compaction sensor, a near-infrared moisture meter, an airborne data transmission unit, a directional positioning antenna and a vehicle-mounted tablet computer. The compaction sensor, the near-infrared moisture meter and the directional positioning antenna are all electrically connected to the airborne data transmission unit, and the airborne data transmission unit is electrically connected to the vehicle-mounted tablet computer. The airborne data transmission unit sends the monitoring data to the PLC control system in real time. The PLC control system processes the monitoring data and sends instructions to the intelligent roller according to the analysis results to adjust the working state of the intelligent roller.

[0025] Furthermore, in step S4, when laying the geogrid on the compacted backfill material, the geogrid is laid every 3 m of backfill material.

[0026] Compared with the prior art, the present invention has the following technical effects:

[0027] The present invention provides a reservoir dam filling and compaction construction method. In the excavation stage of filling soil, the moisture content of the filling soil is monitored in real time by a soil temperature and humidity sensor, and then a PLC control system determines the excavation area according to the moisture content. In the rolling and compaction stage, the compaction degree of the filling soil is monitored in real time by a compaction sensor on an intelligent roller, and the moisture content of the filling soil is monitored in real time by a near-infrared moisture meter, and then the PLC control system adjusts the working state of the intelligent roller according to the monitoring situation. This construction method uses a PLC control system to accurately monitor the moisture content of the fill material during the excavation stage of the fill material, thereby ensuring the quality requirements of the fill material from the beginning, and ensuring that the subsequent rolling and compaction work is carried out within the optimal moisture content range of the fill material; in the rolling and compaction stage, the PLC control system accurately monitors the moisture content and compaction degree of the fill material, and the PLC control system processes and analyzes the monitoring data. According to the analysis results, the PLC control system can timely adjust the working parameters of the intelligent roller, such as increasing or decreasing the number of compaction passes, adjusting the compaction path, changing the compaction speed, etc., to ensure that the moisture content and compaction degree of the fill material are always within the allowable deviation range. At the same time, through the automated PLC control system, the influence of human factors on the construction quality is reduced, the possibility of human errors is reduced, and the construction efficiency and the stability of the construction quality are improved.

[0028] In addition, geogrids are laid during the dam filling and compaction process, so that a layer of geogrid is placed between every two layers of compacted filling soil, which enhances the dam's mechanical strength such as compression and shear resistance, thereby improving the compaction degree and the overall bearing capacity and stability of the dam. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 It is a flow chart of a reservoir dam filling and compaction construction method according to an embodiment of the present invention;

[0030] Figure 2 A schematic diagram of the structure of an intelligent roller compactor according to an embodiment of the present invention;

[0031] Figure 3 A schematic diagram of the buried soil temperature and humidity sensor according to an embodiment of the present invention;

[0032] Figure 4 A schematic diagram of the arrangement of soil temperature and humidity sensors in a dam filling site according to an embodiment of the present invention;

[0033] Figure 5 Schematic diagram of laying the geogrid according to an embodiment of the present invention.

[0034] Explanation of the reference numerals in the accompanying drawings: 1. Intelligent roller compactor, 2. Vehicle-mounted tablet computer, 3. Near-infrared moisture meter, 4. Compaction sensor, 5. Positioning directional antenna, 6. PLC control system, 7. Remote monitoring system, 8. XHS-WS soil temperature and humidity sensor, 9. Dam filling site, 10. Solar panel, 11. Data acquisition unit, 12. Filling soil, 13. Geogrid. DETAILED DESCRIPTION

[0035] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.

[0036] It should be noted that the following detailed descriptions are exemplary and are intended to provide further explanation of the present application. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present application belongs.

[0037] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprise" and / or "include" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.

[0038] See also Figures 1 to 5 This embodiment provides a reservoir dam filling and compaction construction method. Before the construction begins, preparatory work is performed. First, the dam filling material field 9 and the dam filling area are leveled, measured and staked out. Then, the dam filling material field 9 is cleared, and the dam foundation is cleared and compacted. After the preparatory work is completed, the construction begins, including the following steps:

[0039] S1: Use the soil temperature and humidity sensor to monitor the moisture content of the filling soil 12 in real time. The soil temperature and humidity sensor sends the monitoring data to the PLC control system 6. The PLC control system 6 determines the excavation area according to the moisture content of the filling soil 12, and then transports the soil to the dam filling area.

[0040] The specific steps include:

[0041] S11: According to the excavation depth and width, soil temperature and humidity sensors are buried in the dam filling material field 9. The soil temperature and humidity sensors are arranged at intervals according to the width and length of the dam filling material field 9. The buried soil temperature and humidity sensors at least cover the entire dam filling material field 9;

[0042] S12: The buried soil temperature and humidity sensor monitors the moisture content of the filling soil 12 of the entire dam filling material field 9 in real time. The soil temperature and humidity sensor transmits the moisture content data to the PLC control system 6. The PLC control system 6 analyzes and processes the received data to determine the excavation area;

[0043] S13: After the excavation area is determined, an excavator is used to excavate the filling soil 12, and then the filling soil 12 is transported to the dam filling area using a transport vehicle.

[0044] Specifically, the excavation depth and width of the filling soil 12 are affected by many factors, including the design requirements of the specific project, terrain conditions, soil properties, and the configuration of construction machinery. In actual construction, the actual excavation depth and width of the filling soil 12 should be determined according to the design requirements of the specific project, the geological survey report, and the construction organization design. The construction personnel should comprehensively consider various factors and formulate a reasonable excavation plan to ensure the quality and safety of the construction. In addition, during the construction process, it is also necessary to make flexible adjustments according to the actual situation on site to ensure the quality and safety of the construction.

[0045] Specifically, in this embodiment, the soil temperature and humidity sensor adopts the XHS-WS soil temperature and humidity sensor 8, the XHS-WS soil temperature and humidity sensor 8 is electrically connected to the data acquisition unit 11, the data acquisition unit 11 is electrically connected to the solar panel 10, the XHS-WS soil temperature and humidity sensor 8 is used to monitor the moisture content of the filling soil 12 in real time, the data acquisition unit 11 is used to receive the monitoring data of the XHS-WS soil temperature and humidity sensor 8 and send the monitoring data to the PLC control system 6 in real time, and the solar panel 10 is used to provide power support for the data acquisition unit 11 and the XHS-WS soil temperature and humidity sensor 8. When working, the XHS-WS soil temperature and humidity sensor 8 is inserted into the filling soil 12 to a certain depth, the XHS-WS soil temperature and humidity sensor 8 monitors the moisture content of the filling soil 12 in the area in real time, and the data monitored in real time by the XHS-WS soil temperature and humidity sensor 8 is transmitted to the data acquisition unit 11, and the data acquisition unit 11 sends the monitoring data to the PLC control system 6 in real time.

[0046] Specifically, the arrangement of soil temperature and humidity sensors in the dam filling site 9 is as follows: Figure 4 As shown, when soil temperature and humidity sensors are arranged in the dam filling yard 9, a soil temperature and humidity sensor is arranged every 3m along the width direction of the dam filling yard 9, and a soil temperature and humidity sensor is arranged every 3m along the length direction of the dam filling yard 9. The arranged soil temperature and humidity sensors at least cover the entire dam filling yard 9.

[0047] Specifically, in step S12, the PLC control system 6 is an open architecture, and the operator can program and adjust the construction parameters in the system according to the construction requirements. The PLC control system 6 is also wirelessly connected to the remote monitoring system 7, and the operator can view the operation status of the PLC control system 6 and related equipment in real time through the remote monitoring system 7. In this embodiment, the PLC control system 6 is preset with two construction parameters: the optimal moisture content of the filling soil 12 and the preset compaction degree of the filling soil 12. The preset optimal moisture content value is 16.7%, and the preset compaction value is 96%. The set construction parameters continue to be used in the rolling stage of the dam. In the excavation stage of the filling soil 12, the PLC control system 6 compares the moisture content data of the filling soil 12 received in real time with the preset optimal moisture content of the filling soil 12, and determines that the area where the moisture content of the filling soil is within the allowable deviation range of the optimal moisture content is the excavation area, wherein the allowable deviation range of the optimal moisture content is 15.0%-18.4%.

[0048] S2: The filling soil material 12 transported to the dam filling area is paved, and the paving is carried out using the advance occupation method.

[0049] Specifically, the advance method is a method of unloading in earth filling. The process is as follows: the transport vehicle starts unloading on the edge of the filling area on the high platform (i.e. the surface of the soil layer that has just been laid and has not yet been rolled), and the unloading is spread forward and then leveled with a bulldozer, and sometimes manual cooperation is required. During the construction process of the advance method, transport vehicles are not allowed to drive into the area where the previous layer has been rolled to avoid disturbing the foundation surface. In addition, the paving direction is parallel to the axis of the dam. In addition, in order to ensure the uniform thickness of the paving, the paving thickness of each layer should be strictly paved and leveled according to the virtual paving thickness determined by the rolling test.

[0050] Specifically, after the filling soil material 12 is paved, the filling soil material 12 should be rolled in time to prevent the filling soil material 12 from being dried out.

[0051] S3: After the filling material 12 is paved, the intelligent roller 1 is used to compact the filling material 12. During the compaction process, the sensor carried by the intelligent roller 1 monitors the compaction rate, moisture content and compaction path of the filling material 12 in real time. The sensor sends the real-time monitoring data to the PLC control system 6, and the PLC control system 6 adjusts the working state of the intelligent roller 1 in real time according to the monitoring situation.

[0052] The specific steps include:

[0053] S31: After the filling soil material 12 is paved, the plurality of intelligent rollers 1 are arranged to allow the intelligent rollers 1 to roll the filling soil material 12 along a predetermined path;

[0054] S32: During the rolling process, the compaction sensor 4 carried by the intelligent roller 1 monitors the compaction of the filling soil 12 in real time, the near-infrared moisture meter 3 monitors the moisture content of the filling soil 12 in real time, and the directional positioning antenna 5 locates the position of the intelligent roller 1 and determines the compaction path of the intelligent roller 1 in real time;

[0055] S33: The compaction sensor 4 sends the monitored compaction rate data to the PLC control system 6 in real time, and the near-infrared moisture meter 3 sends the monitored moisture content data to the PLC control system 6 in real time. The PLC control system 6 compares the received compaction rate data with the preset compaction rate, and compares the received moisture content data with the optimal moisture content. If both are within the allowable deviation range, the PLC control system 6 does not adjust the working state of the intelligent roller 1. If at least one of the two is not within the allowable deviation range, the PLC control system 6 sends an instruction to the intelligent roller 1 to adjust the working state of the intelligent roller 1.

[0056] Specifically, during the rolling stage, the PLC control system 6 compares the moisture content data received in real time with the preset optimal moisture content, and the PLC control system 6 compares the compaction rate data received in real time with the preset compaction rate. If the moisture content and the compaction degree are both within the allowable deviation range, the compaction parameters of the intelligent roller 1 will not change. If at least one of the moisture content and the compaction degree is not within the allowable deviation range, the PLC control system 6 will automatically adjust the compaction parameters of the intelligent roller 1, such as increasing or decreasing the number of compaction passes, adjusting the compaction path, changing the compaction speed, etc., wherein the allowable deviation range of the optimal moisture content is 15.0%-18.4%, and the allowable deviation range of the preset compaction degree is greater than or equal to 96%.

[0057] Specifically, in step S3, the intelligent roller compactor 1 is installed with a compaction sensor 4, a near-infrared moisture meter 3, an airborne data transmission unit, a directional positioning antenna 5 and a vehicle-mounted tablet computer 2. The compaction sensor 4, the near-infrared moisture meter 3 and the directional positioning antenna 5 are all electrically connected to the airborne data transmission unit, and the airborne data transmission unit is electrically connected to the vehicle-mounted tablet computer 2. The compaction sensor 4 is used to monitor the compaction of the filling material 12 in real time, the near-infrared moisture meter 3 is used to monitor the moisture content of the filling material 12 in real time, the directional positioning antenna 5 is used to locate the position of the intelligent roller compactor 1 in real time and determine the compaction path of the intelligent roller compactor 1, the airborne data transmission unit is used to send the monitoring data to the PLC control system 6 in real time, and the vehicle-mounted tablet computer 2 is used to provide the operator with real-time data display and system operation interface to ensure the transparency and controllability of the construction process.

[0058] Specifically, in this embodiment, the compaction sensor 4 adopts the TJS01 compaction sensor, which is adsorbed on the intelligent roller compactor 1 through a magnetic base, and the near-infrared moisture meter 3 adopts the WKT-R-50ZS near-infrared moisture meter, which is installed on the front anti-collision beam of the intelligent roller compactor 1.

[0059] S4: laying the geogrid 13 on the compacted filling soil 12 (thickness is 3m), that is, laying the geogrid 13 is carried out every 3m of filling soil 12.

[0060] Specifically, in step S4, the geogrid 13 used is made of magnesium acrylate, oxidant sodium persulfate and cross-linking agent sodium thiosulfate. The specific process is: 1% of the mass of the magnesium acrylate solution is added to the magnesium acrylate solution in batches. The magnesium acrylate solution is quickly connected into polymer chains under the action of the oxidant and the cross-linking agent to form a gel with high toughness. Then, a co-extrusion casting machine is used to process the prepared gel to prepare the geogrid 13 product required for the project.

[0061] Specifically, when laying the geogrid 13, it is necessary to ensure that the geogrid 13 is intact, without bending or breaking, and then use bamboo stakes or wooden stakes to mark the scope of laying the geogrid 13, and then lay it. During the laying process, the flatness and straightness of the geogrid 13 should be ensured. In addition, the longitudinal and transverse joints of the geogrid 13 can be connected as a whole by nylon rope or polyester sewing or U-shaped nails, and the geogrids 13 overlap each other by no less than 20cm. After the geogrid 13 is laid, the filling soil 12 should be spread and compacted within 24 hours. The filling should be spread according to the principle of "first the two sides, then the middle", and it is strictly forbidden to fill the middle first.

[0062] S5: Steps S2-S4 are then repeated until the filling is completed, and then the dam axis and elevation are measured, the slope is trimmed, the slope protection is constructed, and the cleaning and acceptance work is carried out. Finally, a layer of geogrid 13 is separated between every two layers of compacted filling soil 12 of the built enclosure dam.

[0063] Specifically, the present construction method uses the PLC control system 6 to accurately monitor the moisture content of the filling material 12 during the excavation stage of the filling material, thereby ensuring the quality requirements of the filling material 12 from the very beginning, and ensuring that the subsequent rolling work is carried out within the optimal moisture content range of the filling material 12. In addition, the PLC control system 6 is used to accurately monitor the moisture content and compaction degree of the filling material 12 during the rolling and compaction stage. The PLC control system 6 processes and analyzes the monitoring data. According to the analysis results, the PLC control system 6 can timely adjust the compaction parameters of the intelligent roller 1, such as increasing or decreasing the number of compaction passes, adjusting the compaction path, changing the compaction speed, etc., to ensure that the moisture content and compaction degree of the filling material 12 are always within the allowable deviation range. At the same time, through the automated PLC control system 6, the influence of human factors on the construction quality is reduced, the possibility of human errors is reduced, and the construction efficiency and the stability of the construction quality are improved. Furthermore, geogrids 13 are laid during the rolling process of the dam, so that a layer of geogrid 13 is placed between every two layers of compacted filling soil 12, thereby enhancing the mechanical strength of the dam such as compression and shear resistance, thereby improving the compaction degree and the overall bearing capacity and stability of the dam.

[0064] The above description is only a preferred embodiment of the present disclosure and is not intended to limit the present disclosure. For those skilled in the art, the present disclosure may have various changes and variations. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present disclosure should be included in the protection scope of the present disclosure. Although the specific implementation methods of the present disclosure are described above in conjunction with the accompanying drawings, it is not a limitation on the protection scope of the present disclosure. Those skilled in the art should understand that on the basis of the technical solution of the present disclosure, various modifications or deformations that can be made by those skilled in the art without creative labor are still within the protection scope of the present disclosure.

Claims

1. A reservoir dam filling and compaction construction method, characterized in that: The following steps are involved: S1: Use soil temperature and humidity sensors to monitor the moisture content of the filling soil in real time, determine the excavation area based on the moisture content of the filling soil, and then transport the soil to the dam filling area; S2: The filling soil materials transported to the dam filling area are paved, and the paving is carried out by the advance occupation method; S3: After the filling soil is paved, the filling soil is compacted by the intelligent roller. During the compaction process, the compaction rate, moisture content and compaction path of the filling soil are monitored in real time, and the working state of the intelligent roller is adjusted in real time according to the monitoring situation; S4: Lay geogrid on compacted fill soil; S5: Repeat steps S2-S4 until the filling is completed, and then measure the dam axis and elevation, trim the slope, construct slope protection, and clean up and accept the work.

2. The reservoir dam filling and compaction construction method according to claim 1 is characterized in that: The step S1 comprises the following steps: S11: According to the excavation depth and width, soil temperature and humidity sensors are buried in the dam filling material field, and the soil temperature and humidity sensors are arranged at intervals according to the width and length of the dam filling material field. The buried soil temperature and humidity sensors at least cover the entire dam filling material field; S12: The buried soil temperature and humidity sensors monitor the moisture content of the filling soil in the entire dam filling field in real time. The soil temperature and humidity sensors transmit the moisture content data to the PLC control system, and the PLC control system analyzes and processes the received data to determine the excavation area; S13: After the excavation area is determined, an excavator is used to excavate the filling soil, and then the filling soil is transported to the dam filling area using a transport vehicle.

3. The reservoir dam filling and compaction construction method according to claim 2 is characterized in that: In step S12, construction parameters are preset in the PLC control system, and the construction parameters include the optimal moisture content of the fill soil and the preset compaction degree of the fill soil. The PLC control system compares the received moisture content data of the fill soil with the preset optimal moisture content of the fill soil, and determines that the area where the moisture content of the fill soil is within the allowable deviation range of the optimal moisture content is the excavation area.

4. The reservoir dam filling and compaction construction method according to claim 2 is characterized in that: The soil temperature and humidity sensor is electrically connected to a data acquisition unit, the data acquisition unit is electrically connected to a solar panel, and the data acquisition unit transmits the data monitored by the soil temperature and humidity sensor to a PLC control system.

5. The reservoir dam filling and compaction construction method according to claim 1, characterized in that: In the step S4, a geogrid is used which is made of magnesium acrylate, an oxidizing agent, sodium persulfate, and a cross-linking agent, sodium thiosulfate.

6. The reservoir dam filling and compaction construction method according to claim 1, characterized in that: The step S3 comprises the following steps: S31: After the filling soil is paved, the intelligent rollers are arranged to allow the intelligent rollers to roll the filling soil along a predetermined path; S32: During the rolling process, the compaction sensor on the intelligent roller monitors the compaction of the filling soil in real time, the near-infrared moisture meter monitors the moisture content of the filling soil in real time, and the directional positioning antenna locates the position of the intelligent roller in real time and determines the compaction path of the intelligent roller; S33: The compaction sensor sends the monitored compaction rate data to the PLC control system in real time, and the near-infrared moisture meter sends the monitored moisture content data to the PLC control system in real time. The PLC control system compares the received compaction rate data with the preset compaction rate, and compares the received moisture content data with the optimal moisture content. If both are within the allowable deviation range, the PLC control system does not adjust the working state of the intelligent roller. If at least one of the two is not within the allowable deviation range, the PLC control system sends a command to the intelligent roller to adjust the working state of the intelligent roller.

7. The reservoir dam filling and compaction construction method according to claim 1, characterized in that: In step S3, the intelligent roller is equipped with a compaction sensor, a near-infrared moisture meter, an airborne data transmission unit, a directional positioning antenna and a vehicle-mounted tablet computer. The compaction sensor, the near-infrared moisture meter and the directional positioning antenna are all electrically connected to the airborne data transmission unit, and the airborne data transmission unit is electrically connected to the vehicle-mounted tablet computer. The airborne data transmission unit sends the monitoring data to the PLC control system in real time. The PLC control system processes the monitoring data and sends instructions to the intelligent roller according to the analysis results to adjust the working state of the intelligent roller.

8. The reservoir dam filling and compaction construction method according to claim 1, characterized in that: In the step S4, when laying the geogrid on the compacted filling soil, the geogrid is laid every 3 m of filling soil.

Citation Information

Cited By

  • Dam rolling construction quality monitoring method and system

    CN119671404A

  • A method and system for monitoring the quality of roller compaction construction of a dam

    CN119671404B