Transformation method for connection of existing large-span column-free station and newly-built structure

By dividing the large-span column-free station into multiple construction sections and using the warehouse jump method to open holes in stages, supporting beams and support columns are set up to connect with the new structure one by one, the structural strength after opening the side wall of the large-span column-free station is solved. The weakened problem has achieved stable connection with the newly built structure.

CN118958738APending Publication Date: 2024-11-15CHINA RAILWAY MAJOR BRIDGE RECONNAISSANCE & DESIGN INSTITUTE CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411241936.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-05
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The structural strength of the large span column-free station weakens after the side wall is opened, making it difficult to meet the requirements of bearing capacity and normal use limit status, affecting the construction of the new structure connection.

Method used

The station is divided into multiple construction sections, the warehouse jump method is used to open holes in stages, and support beams and support columns are set up in each section to connect to the new structure, and the construction is completed one by one to avoid the direct weakening of the structure by large-scale holes.

Benefits of technology

Through phase-by-stage construction and phase-breaking holes, the strength of the large-span column-free station structure is reduced, the stability of the structure is ensured, and the connection with the new structure is facilitated, and the requirements of bearing capacity and use limit status are met.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958738A_ABST
    Figure CN118958738A_ABST
Patent Text Reader

Abstract

The invention relates to a transformation method for connection of an existing large-span column-free station and a newly-built structure, and belongs to the technical field of rail transit structures. Comprising the steps that an existing station is divided into a plurality of construction sections in the length direction for section-by-section construction, and first top plates of the construction sections are subjected to soil unloading; an enclosure is arranged in the existing station, and a part of an enclosure structure of the existing station is dismantled from the side where the newly-built structure is located; a large hole needing to be formed is planned in the position of the side wall of the existing station, the large hole is planned into a plurality of small holes in the length direction of the side wall of the existing station, each small hole is divided into a first-stage hole and a second-stage hole, and skip bay hole forming construction is carried out; a first-stage supporting beam and a supporting column are arranged at the opening of the first-stage hole and connected with a second top plate and a bottom plate of the newly-built structure; and a second-stage supporting beam is arranged at the opening of the second-stage hole, and the first-stage supporting beam and the second-stage supporting beam are connected and connected with a second top plate and a bottom plate of the newly-built structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of rail transit structure technology, and in particular to a method for modifying an existing large-span column-free station to connect with a new structure. Background Technology

[0002] In recent years, with the development of rail transit, there has been an increasing number of renovations to connect existing stations with surrounding stations or ancillary facilities and properties. When renovating existing stations, openings in the side walls of the first basement level often lead to an increase in the mid-span bending moment of the roof slab and the side walls of the second basement level, while reducing the bending moment at the supports of the side walls and roof slab. Since the span of columns in columns is moderate, most of the vertical load in the middle of the roof slab is transferred to the foundation through the central column. Therefore, the impact of openings in the side walls on the station structure is limited, often only affecting the roof slab and side walls on the side with the opening. Thus, openings can be carried out according to conventional construction methods. After the opening, the beams and columns at the opening are constructed, and the structural bearing capacity and serviceability limit state of the station meet the design requirements.

[0003] However, large-span column-free stations differ from column-supported stations. They lack support, and after the opening in the side wall of the first basement level, the vertical load of the top slab is transferred through the slab to the side walls on both sides, and then down to the foundation. The internal forces at the slab supports and mid-span are very large. After the mid-span bending moment of the top slab increases, it does not meet the requirements of bearing capacity and normal serviceability limit state. After the large-area opening in the side wall of the large-span column-free station, it will significantly weaken the structure and make it difficult to connect with the new structure. Summary of the Invention

[0004] This application provides a method for modifying the connection between an existing large-span column-free station and a new structure, in order to solve the problem in related technologies that when constructing a large-span column-free station and a new structure, making large openings in the side wall of the large-span column-free station will significantly weaken the structure and make it difficult to connect with the new structure.

[0005] This application provides a method for modifying an existing long-span column-free station to connect with a newly constructed structure, including:

[0006] The existing station was divided into multiple construction sections along its length and constructed section by section. Soil was removed from the first roof slab of each construction section.

[0007] An enclosure is set up inside the existing station, and part of the existing station's enclosure structure is removed from the side where the new structure is located;

[0008] A large opening to be made is planned at the side wall of the existing station, and it is further divided into multiple small openings along the length of the side wall of the existing station. Using the skip-opening method, each small opening is divided into a first-phase opening and a second-phase opening, and the skip-opening construction is carried out.

[0009] After the first-stage opening is set, a first-stage support beam and support column are set at the opening of the first-stage opening and connected to the second top plate and bottom plate of the newly built structure;

[0010] A second-phase opening is constructed, and a second-phase support beam is installed at the opening of the second-phase opening. The first-phase support beam and the second-phase support beam are connected, and then connected to the second top plate and the bottom plate of the newly constructed structure to complete the construction of this section. Subsequently, each construction section is constructed in sequence to complete the connection between the existing station and the newly constructed structure.

[0011] In some embodiments, after the first-stage support beam and the support column are installed at the first-stage opening, a support member is used to temporarily support the bottom of the first-stage support beam.

[0012] In some embodiments, a second-phase support beam is installed at the second-phase opening, the first-phase support beam and the second-phase support beam are connected, and then connected to the second top plate and the bottom plate of the newly built structure, and the support member is removed.

[0013] In some embodiments, the first-phase opening is provided, and the first-phase support beam and the support column are provided at the opening of the first-phase opening. After being connected to the second top plate and the bottom plate of the newly built structure, the remaining enclosure structure of the existing station is anchored into the bottom plate for anti-buoyancy.

[0014] In some embodiments, the first-stage opening is provided, and the first-stage support beam and the support column are provided at the opening of the first-stage opening. After being connected to the second top plate and the bottom plate of the newly built structure, a joint for the second-stage support beam is reserved on the first-stage support beam.

[0015] In some embodiments, construction is carried out on each construction section, and after the connection between the existing station and the new structure is completed, lightweight material is backfilled on the first roof slab.

[0016] In some embodiments, before construction is carried out on each construction section, the drainage holes of the base plate of the newly constructed structure are used to maintain pressure relief.

[0017] In some embodiments, after the soil is unloaded from the first top slab of the construction section, a water collection ditch is set in the middle of the soil covering the upper part of the first top slab, and a necessary construction width is left on one side of the newly built structure.

[0018] In some embodiments, the support member is a steel section.

[0019] In some embodiments, the first-stage opening and the second-stage opening are arranged adjacent to each other.

[0020] The beneficial effects of the technical solution provided in this application include:

[0021] This application provides a method for modifying an existing long-span column-free station to connect with a new structure. The method includes dividing the existing station into multiple construction sections along its length and constructing each section sequentially; unloading soil from the first roof slab of the construction section; setting up enclosures within the existing station and demolishing part of the existing station's enclosure structure from the side where the new structure is located; planning a large opening to be made in the side wall of the existing station, and dividing it into multiple smaller openings along the length of the side wall; using a skip-opening method, dividing each smaller opening into first-phase and second-phase openings and performing skip-opening construction; after setting the first-phase opening, setting first-phase support beams and support columns at the opening of the first-phase opening and connecting them to the second roof and bottom slabs of the new structure; setting the second-phase opening, setting second-phase support beams at the opening of the second-phase opening, connecting the first-phase support beams and the second-phase support beams, and connecting them to the second roof and bottom slabs of the new structure to complete the construction of this construction section; then, constructing each construction section sequentially to complete the connection between the existing station and the new structure.

[0022] In practice, to ensure that the structural strength of the existing long-span column-free station is not significantly weakened, the existing station is first divided into multiple construction sections along its length for sequential construction. Construction proceeds segment by segment only after one section is completed. When constructing the first section, the first slab of that section is unloaded. Enclosures are set up within the existing station to facilitate construction. Part of the existing station's retaining structure is removed from the side where the new structure is located; at this stage, only a portion of the existing station's retaining structure needs to be removed.

[0023] Then, the large opening to be created at the existing station side wall is planned, and further divided into multiple smaller openings along the length of the existing station side wall. Using a skip-section method, each smaller opening is divided into a first-phase opening and a second-phase opening, and construction is carried out in a skip-section manner. Depending on the actual situation, the opening can be divided into two phases. Using the skip-section method, the first-phase opening is constructed first, followed by the second-phase opening. The first-phase and second-phase openings are arranged adjacent to each other, and also interspersed; that is, a second-phase opening is placed between two first-phase openings, and vice versa. The first-phase and second-phase openings together form a large-area opening in the side wall of the large-span, column-free station. This method avoids directly creating a large-area opening in the side wall at the same time, and can reduce the weakening of the structural strength of the existing large-span, column-free station during construction. Attached Figure Description

[0024] To more clearly illustrate the technical solutions in the embodiments of this application, the accompanying drawings used in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of this application. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0025] Figure 1 A sectional view of the renovation of an existing large-span column-free station structure provided in this application embodiment;

[0026] Figure 2 A schematic diagram of the first-stage opening provided in an embodiment of this application;

[0027] Figure 3 This is a schematic diagram of the construction status during the first phase of tunnel opening;

[0028] Figure 4 This is a schematic diagram of the second phase of the excavation.

[0029] Figure 5 This is a schematic diagram of the construction status during the second phase of tunnel opening;

[0030] Figure 6 This is a schematic diagram of the structure after construction is completed.

[0031] Figure label:

[0032] 1. First roof slab; 2. First phase support beam; 3. Support column; 4. Enclosure structure; 5. Second roof slab; 6. Bottom slab; 7. Enclosure; 8. Drainage ditch; 10. First phase opening; 11. Second phase opening; 12. Joint; 13. Support component; 14. Second phase support beam; 20. Existing station; 30. New structure. Detailed Implementation

[0033] To make the objectives, technical solutions, and advantages of the embodiments of this application clearer, the technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, not all embodiments. Based on the embodiments of this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.

[0034] This application provides a method for modifying the connection between an existing large-span column-free station and a new structure. This method can solve the problem in related technologies where, when constructing a large-span column-free station and a new structure, making large openings in the side wall of the large-span column-free station will significantly weaken the structure and make it difficult to connect with the new structure.

[0035] See Figures 1 to 6As shown in the figure, this application provides a method for modifying the connection between an existing long-span column-free station and a newly constructed structure, including:

[0036] S1. Divide the existing station 20 into multiple construction sections along its length and carry out construction section by section. Unload the soil from the first roof slab 1 of the construction section.

[0037] S2. Set up enclosure 7 within the existing station 20 and demolish part of the enclosure structure 4 of the existing station 20 from the side where the new structure 30 is located.

[0038] S3. Plan the large opening to be made at the side wall of the existing station 20, and plan it into multiple small openings along the length of the side wall of the existing station 20. Using the skip-opening method, divide each small opening into the first phase opening 10 and the second phase opening 11, and carry out the skip-opening construction.

[0039] S4. After setting the first-stage opening 10, set the first-stage support beam 2 and support column 3 at the opening of the first-stage opening 10, and connect them with the second top plate 5 and bottom plate 6 of the newly built structure 30.

[0040] S5. Set up a second-phase opening 11, and set up a second-phase support beam 14 at the opening of the second-phase opening 11. Connect the first-phase support beam 2 and the second-phase support beam 14, and connect them with the second top plate 5 and bottom plate 6 of the new structure 30 to complete the construction of this construction section. Then, carry out construction on each construction section in sequence to complete the connection between the existing station 20 and the new structure 30.

[0041] In practice, to ensure that the structural strength of the existing long-span column-free station is not significantly weakened, the existing station 20 is first divided into multiple construction sections along its length for sequential construction. Construction proceeds section by section only after one section is completed. When constructing the first section, the soil is first removed from the first roof slab 1 of that section. An enclosure 7 is then set up within the existing station 20 to facilitate construction. Part of the retaining structure 4 of the existing station 20 is removed from the side where the new structure 30 is located; at this point, only a portion of the retaining structure 4 of the existing station 20 needs to be removed.

[0042] Subsequently, a large opening was planned to be created at the side wall of the existing station 20, and then divided into multiple smaller openings along the length of the existing station 20 side wall. Using the skip-section method, each smaller opening was divided into a first-phase opening 10 and a second-phase opening 11, and construction was carried out in a skip-section manner. Depending on the actual situation, the opening can be divided into two phases, and the skip-section method is used to construct the first-phase opening 10 first, and then the second-phase opening 11 after the first-phase opening 10 is completed. The first-phase opening 10 and the second-phase opening 11 are set up adjacent to each other, and they are also interleaved. That is, the second-phase opening 11 is set up between two first-phase openings 10, and similarly, the first-phase opening 10 is set up between two second-phase openings 11. The first-phase openings 10 and the second-phase opening 11 together form a large-area opening in the side wall of the large-span column-free station. This method avoids directly creating a large-area opening in the side wall at the same time. It can reduce the weakening of the structural strength of the existing large-span column-free station during construction.

[0043] Specifically, such as Figure 2 and Figure 3 After the first-stage opening 10 is constructed, i.e., after the construction of the first-stage opening 10 is completed, a first-stage support beam 2 and a support column 3 are installed at the opening of the first-stage opening 10 to ensure structural strength and to connect with the second top slab 5 and bottom slab 6 of the newly built structure 30; then the second-stage opening 11 is constructed, as follows... Figure 4 and Figure 5 A second-phase support beam 14 is installed at the entrance of the second-phase opening 11, connecting the first-phase support beam 2 and the second-phase support beam 14. This beam is then connected to the second top slab 5 and bottom slab 6 of the newly constructed structure 30, completing the construction of this section. Subsequently, each construction section is constructed sequentially using the same method, thus completing the connection between the existing station 20 and the newly constructed structure 30. During this process, small-scale enclosure can be implemented within the station, eliminating the need for excessive temporary supports, thus not affecting station operation and ensuring the structural strength of the existing large-span column-free station.

[0044] In some alternative embodiments, such as Figures 2 to 5 After installing the primary support beam 2 and support column 3 at the opening of the primary opening 10, temporary support member 13 is used at the bottom of the primary support beam 2 for support. That is, in step 4, temporary support member 13 can be used at the bottom of the primary support beam 2 for support to ensure the structural strength during construction. In some applicable cases, the support member 13 is a steel section. A secondary support beam 14 is installed at the opening of the secondary opening 11. The primary support beam 2 and the secondary support beam 14 are connected, and then connected to the second top plate 5 and bottom plate 6 of the newly built structure 30. After this connection, the temporary support member 13 is removed.

[0045] In some alternative embodiments, such as Figure 2 and Figure 3A first-phase opening 10 is set up, and a first-phase support beam 2 and support column 3 are set at the opening of the first-phase opening 10. After connecting with the second top plate 5 and bottom plate 6 of the new structure 30, in step 4, the remaining retaining structure 4 of the existing station 20 can be anchored into the bottom plate 6 for anti-buoyancy. When performing step 2, a enclosure 7 is set up inside the existing station 20, and part of the retaining structure 4 of the existing station 20 is removed from the side where the new structure 30 is located. At this time, only part of the retaining structure 4 of the existing station 20 that affects construction is removed. In step 4, the remaining retaining structure 4 of the existing station 20 can be anchored into the bottom plate 6 for anti-buoyancy. By using the remaining retaining structure 4 of the existing station 20 to anchor into the plate of the new structure 30 and using the new structure 30 to participate in anti-buoyancy, other additional anti-buoyancy measures are avoided, which can save investment during construction.

[0046] In some optional embodiments, a first-stage opening 10 is set up, and a first-stage support beam 2 and a support column 3 are set at the opening of the first-stage opening 10. After being connected to the second top plate 5 and bottom plate 6 of the newly built structure 30, that is, in step 4, a joint 12 for the second-stage support beam 14 is reserved on the first-stage support beam 2 to facilitate the connection of the first-stage support beam 2 and the second-stage support beam 14 during subsequent construction.

[0047] In some alternative embodiments, construction is carried out on each construction section. After the connection between the existing station 20 and the new structure 30 is completed, lightweight material is backfilled on the first top slab 1. At this time, the lightweight material can be lightweight concrete. The density of the backfill material and the backfill height are determined according to the stress and buoyancy calculations.

[0048] In some alternative embodiments, before construction of each construction section, the drainage holes of the bottom slab 6 of the new structure 30 are used to maintain pressure relief. After the soil is unloaded from the first top slab 1 of the construction section, a water collection ditch 8 is set in the middle of the soil cover on the top of the first top slab 1, leaving the necessary construction width on one side of the new structure 30.

[0049] In summary, during construction, the existing station 20 is divided into multiple construction sections along its length for segmented construction. Soil is unloaded from the first top slab 1 of the construction section. Before construction of each construction section, the drainage holes of the bottom slab 6 of the new structure 30 can be used to maintain pressure relief. After unloading the soil from the first top slab 1 of the construction section, a water collection ditch 8 is set in the middle of the soil covering the first top slab 1. The necessary construction width is left on one side of the new structure 30.

[0050] Within the existing station 20, an enclosure 7 is set up, and part of the existing station 20's retaining structure 4 is demolished from the side where the new structure 30 is located. A large opening to be made is planned at the side wall of the existing station 20, and it is planned as multiple small openings along the length of the side wall of the existing station 20. Using the skip-opening method, each small opening is divided into a first-phase opening 10 and a second-phase opening 11, and skip-opening construction is carried out.

[0051] Specifically, after setting up the first-phase opening 10, a first-phase support beam 2 and a support column 3 are set at the opening of the first-phase opening 10. At this time, a support member 13 is used to temporarily support the bottom of the first-phase support beam 2. The support member 13 can be a steel section. After setting up the first-phase support beam 2 and the support column 3 at the opening of the first-phase opening 10, they are connected to the second top plate 5 and the bottom plate 6 of the newly built structure 30. The remaining enclosure structure 4 of the existing station 20 is anchored into the bottom plate 6 for anti-buoyancy. A joint 12 is reserved on the first-phase support beam 2 for connection with the second-phase support beam 14.

[0052] Next, a second-phase opening 11 is constructed, and a second-phase support beam 14 is installed at the opening of the second-phase opening 11. The first-phase support beam 2 and the second-phase support beam 14 are connected, and then connected to the second top slab 5 and bottom slab 6 of the newly constructed structure 30. The temporary support components 13 are then removed, completing the construction of this section. The construction of each section is then carried out sequentially in the same manner to complete the connection between the existing station 20 and the newly constructed structure 30. After completing the construction of each section and connecting the existing station 20 and the newly constructed structure 30, lightweight materials, such as lightweight concrete, are backfilled onto the first top slab 1, thus completing the overall construction process. This method ensures that the structural strength of the existing large-span column-free station is not significantly weakened while simultaneously connecting the existing large-span column-free station to the newly constructed structure 30.

[0053] In the description of this application, it should be noted that the terms "upper," "lower," etc., indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this application. Unless otherwise expressly specified and limited, the terms "installed," "connected," and "linked" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; they can refer to the internal communication between two elements. For those skilled in the art, the specific meaning of the above terms in this application can be understood according to the specific circumstances.

[0054] It should be noted that in this application, relational terms such as "first" and "second" are used merely to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such a process, method, article, or apparatus. Without further limitations, an element defined by the phrase "comprising one..." does not exclude the presence of other identical elements in the process, method, article, or apparatus that includes said element.

[0055] The above description is merely a specific embodiment of this application, enabling those skilled in the art to understand or implement this application. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of this application. Therefore, this application is not to be limited to the embodiments shown herein, but is to be accorded the widest scope consistent with the principles and novel features claimed herein.

Claims

1. A reconstruction method for connecting an existing large-span column-free station with a newly constructed structure, characterized in that: include: Dividing the existing station (20) into a plurality of construction sections along the length direction, carrying out construction section by section, and unloading soil from the first top plate (1) of the construction section; Setting up an enclosure (7) inside the existing station (20), and removing part of the enclosure structure (4) of the existing station (20) from the side where the new structure (30) is located; A large hole to be opened is planned at the side wall of the existing station (20), and it is planned to be divided into a plurality of small holes along the length direction of the side wall of the existing station (20); each small hole is divided into a first-phase opening hole (10) and a second-phase opening hole (11) by using a skipping method, and the skipping opening construction is performed; After the first-stage opening (10) is provided, a first-stage support beam (2) and a support column (3) are provided at the opening of the first-stage opening (10), and are connected to the second top plate (5) and bottom plate (6) of the newly built structure (30); A second-phase opening (11) is provided, and a second-phase support beam (14) is provided at the opening of the second-phase opening (11), the first-phase support beam (2) and the second-phase support beam (14) are connected, and connected with the second top plate (5) and the bottom plate (6) of the newly-built structure (30), to complete the construction of the construction section, and then the construction of each construction section is carried out in turn to complete the connection between the existing station (20) and the newly-built structure (30).

2. A reconstruction method for connecting an existing large-span column-free station with a newly built structure as claimed in claim 1, characterized in that: After the first-stage support beam (2) and the support column (3) are arranged at the opening of the first-stage opening (10), a support member (13) is used to temporarily support the bottom of the first-stage support beam (2).

3. A reconstruction method for connecting an existing large-span column-free station with a newly built structure as claimed in claim 2, characterized in that: The second-phase support beam (14) is arranged at the opening of the second-phase opening (11), the first-phase support beam (2) and the second-phase support beam (14) are connected, and after being connected to the second top plate (5) and the bottom plate (6) of the newly-built structure (30), the support member (13) is removed.

4. A reconstruction method for connecting an existing large-span column-free station with a newly built structure as claimed in claim 2, characterized in that: The first-phase opening (10) is provided, and the first-phase support beam (2) and the support column (3) are provided at the opening of the first-phase opening (10), and after being connected with the second top plate (5) and the bottom plate (6) of the newly-built structure (30), the remaining enclosure structure (4) of the existing station (20) is anchored into the bottom plate (6) for anti-floating.

5. The reconstruction method of connecting an existing large-span column-free station with a newly built structure as claimed in claim 1, characterized in that: The first-stage opening (10) is provided, and the first-stage support beam (2) and the support column (3) are provided at the opening of the first-stage opening (10). After being connected to the second top plate (5) and the bottom plate (6) of the newly-built structure (30), a joint (12) with the second-stage support beam (14) is reserved on the first-stage support beam (2).

6. A reconstruction method for connecting an existing large-span column-free station with a newly built structure as claimed in claim 1, characterized in that: After construction is carried out on each construction section and the connection between the existing station (20) and the newly built structure (30) is completed, lightweight materials are backfilled on the first top plate (1).

7. The reconstruction method of connecting an existing large-span column-free station with a newly built structure as claimed in claim 1, characterized in that: Before construction of each construction section, the drainage holes of the bottom plate (6) of the newly built structure (30) are used to maintain pressure relief.

8. The reconstruction method of connecting an existing large-span column-free station with a newly built structure as claimed in claim 1, characterized in that: After the soil is unloaded from the first top plate (1) in the construction section, a water collection ditch (8) is arranged in the middle of the soil covering the upper part of the first top plate (1), and a necessary construction width is reserved on one side of the newly built structure (30).

9. The reconstruction method of connecting an existing large-span column-free station with a newly built structure as claimed in claim 2, characterized in that: The support member (13) is a steel section.

10. The reconstruction method of connecting an existing large-span column-free station with a newly built structure as claimed in claim 1, characterized in that: The first-stage opening (10) and the second-stage opening (11) are arranged adjacent to each other.

Citation Information

Patent Citations

  • Design and construction method of joining new subway station and existing subway station by holing baseplates

    CN105484287A

  • Method for breaking existing underground station side wall for hole opening reconstruction

    CN109736586A

  • Underground three-layer large-span column-free station structure

    CN113684863A

  • Splicing structure who borders on existing transfer station on a large scale

    CN207032282U

  • Procedure for erection of buildings entails erecting repetitive filigree structures with precast concrete parts produced by concrete mixing plants which may be located at building sites and / or in vicinity of building sites

    DE10233145A1