Gangue blocking sealing supporting device suitable for gob-side entry retaining and using method

By using spaced rigid brackets and flexible sealing walls in the lane-stayed lane technology, combined with metal mesh and retractable U-shaped steel, the problems of support and sealing of the goaf side tunnel are solved, and effective support and sealing are achieved , reduces the risk of air leakage and construction costs, and supports the recycling and utilization of equipment.

CN118959052APending Publication Date: 2024-11-15CHINA COAL TECH & ENG GRP SHENYANG ENG CO +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411027683.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

In the technology of retention of the tunnel along the goaf, there are serious air leakage and complex support processes. Especially when mining coal seams with spontaneous combustion hazards, air leakage in the goaf increases the risk of natural fire in the goaf, and The support equipment is subject to rock-falling thrust after the roof collapses, which is not conducive to recycling.

Method used

Using spaced rigid brackets and flexible sealing walls, combined with metal mesh and retractable U-shaped steel, support and sealing are achieved through telescopic columns, upper and lower telescopic arms, upper and lower gangue stops and clamping fin joints. The flexible sealing wall is injected through medium Close to the top and bottom of the tunnel, and set up a wind window to adjust the air volume for easy recycling and reuse.

Benefits of technology

Effectively block the thrust of rockfall in the goaf, reduce the risk of air leakage in the goaf, achieve stable support of the tunnel roof, simplify construction steps, reduce costs, and be recycled to avoid natural fire in the goaf.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118959052A_ABST
    Figure CN118959052A_ABST
Patent Text Reader

Abstract

The invention provides a waste rock blocking sealing supporting device suitable for gob-side entry retaining. The waste rock blocking sealing supporting device comprises a plurality of rigid supports and a plurality of flexible sealing walls, wherein the rigid supports are sequentially arranged in a roadway at intervals, and the flexible sealing walls are installed between every two adjacent rigid supports. The rigid support comprises a support base, a support top beam, two telescopic stand columns, two upper telescopic arms, two lower telescopic arms, an upper gangue blocking plate and a lower gangue blocking plate. And the left side and the right side of the flexible sealing wall are respectively connected with the upper waste rock blocking plate and the lower waste rock blocking plate of two adjacent rigid brackets. The invention further provides a using method of the gangue blocking sealing supporting device suitable for gob-side entry retaining. According to the gangue blocking sealing supporting device for gob-side entry retaining, supporting and sealing of the gob side of a roadway are achieved together with the telescopic U-shaped steel and the metal net, using steps are simple, meanwhile, the workload is small, construction of workers is facilitated, the whole device can be recycled and reused, and then the overall cost of gob-side entry retaining supporting is effectively reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of gob-side tunneling in mining, and in particular relates to a gangue retaining and sealing support device suitable for gob-side tunneling and a use method thereof. Background Art

[0002] In order to effectively alleviate the tension of mine excavation and succession and improve the recovery rate of mineral resources, the technology of retaining lanes along the goaf is widely used in the field of mining, especially in the coal mining industry. By adopting the technology of retaining lanes along the goaf, the coal pillars between adjacent working faces can be eliminated, thereby improving the recovery rate of coal; and the previous lanes can be used as the lanes of adjacent working faces, thereby greatly reducing the amount of lane excavation; in addition, when conditions permit, the ventilation method of the coal mining face can be changed to eliminate the upper corner gas. Therefore, the technology of retaining lanes along the goaf is widely used in the coal mining industry. At the same time, there are also certain problems with the technology of retaining lanes along the goaf, which mainly focus on the support and sealing of the side lanes in the goaf area.

[0003] At present, the method of grouting and filling the wall on the goaf side of the goaf is generally used for sealing support; or metal mesh + single hydraulic support + shotcrete is used for sealing support; and goaf gangue is used to make gangue wall for sealing support. Although the above-mentioned several sealing support methods can meet the support requirements to a certain extent, there are still problems such as serious air leakage in the goaf and complicated support procedures. Especially when mining coal seams with the risk of spontaneous combustion, air leakage in the goaf will greatly increase the risk of spontaneous combustion in the goaf. In addition, after the roof of the goaf collapses, the horizontal thrust exerted by the falling rocks in the goaf on the currently used support equipment is constantly changing as the coal mining face continues to advance, which is very likely to push the support and is extremely unfavorable for the recovery of the support equipment. Summary of the invention

[0004] In order to solve the above technical problems, the present invention provides a rock retaining sealing support device suitable for gob-side tunnelling and a use method thereof.

[0005] In order to achieve the above object, the present invention adopts the following technical scheme: a sealing support device for retaining gangue along the gob, comprising a plurality of rigid supports sequentially arranged in the gob and a plurality of flexible sealing walls installed between two adjacent rigid supports;

[0006] The rigid support comprises a support base, a support top beam, two telescopic columns, two upper telescopic arms, two lower telescopic arms, an upper rock baffle plate and a lower rock baffle plate; two telescopic columns are symmetrically arranged on the support base in a vertical direction, the top ends of the two telescopic columns are fixed to the support top beam, two upper telescopic arms are installed on the support top beam, two lower telescopic arms are installed on the support base, the two upper telescopic arms and the two lower telescopic arms are arranged in parallel on the same side, the two upper telescopic arms are additionally fixed to the upper rock baffle plate, the two lower telescopic arms are additionally fixed to the lower rock baffle plate, the upper rock baffle plate and the lower rock baffle plate have the same structure and are symmetrically arranged up and down;

[0007] A telescopic column controller, an upper telescopic arm controller and a lower telescopic arm controller are also provided on the support base, which are used to control the actions of the two telescopic columns, the two upper telescopic arms and the two lower telescopic arms respectively;

[0008] The left and right sides of the flexible sealing wall are respectively connected to the upper rock retaining plate and the lower rock retaining plate of two adjacent rigid supports.

[0009] Furthermore, two tunnel top beam placement openings are arranged above the support top beam for placing the tunnel top beam.

[0010] Furthermore, the upper and lower rock baffle plates each include a "T"-shaped plate body, a plurality of splicing plate grooves are provided at the bottom of one side of the "T"-shaped plate body facing the telescopic column, and a plurality of splicing plate bolt holes are provided on each splicing plate groove;

[0011] The left and right outer sides of the "T"-shaped plate body are respectively provided with fin slits and plate slots, and the two ends of the end surface of the "T"-shaped plate body facing the telescopic column are respectively provided with a plurality of buckle bolt holes from top to bottom, and the bottom of the two ends of the end surface of the "T"-shaped plate body facing the telescopic column are respectively provided with a plurality of plate bolt holes at the plate slots;

[0012] The end face of the "T"-shaped plate body facing away from the telescopic column is provided with multiple pressure box mounting grooves, a wire groove is provided under each pressure box mounting groove, two fixing bolt holes are provided in the pressure box mounting groove, and a pressure box is installed in the pressure box mounting groove to detect the horizontal thrust of falling rocks in the goaf.

[0013] Furthermore, the flexible sealing wall includes a flexible bag body, and side fins are respectively provided on the left and right side facades of the flexible bag body, and a plurality of buckle rings are provided on the side fins, and the buckle rings match the buckle ring bolt holes; two tunnel top beam reserved openings are provided on the top of the flexible bag body for the tunnel top beam to pass through; a medium injection port is also provided at the bottom of the flexible bag body for injecting medium into the interior thereof, so that the flexible sealing wall expands and fits tightly against the top and bottom of the tunnel.

[0014] Furthermore, a plurality of wind windows are provided in the middle of the flexible bag body, and wind window covers are installed in the wind windows through wind window zippers. The wind window covers are opened or closed through the wind window zippers to adjust the air volume entering the goaf.

[0015] Furthermore, a plurality of safeguard holes are provided at the bottom of the flexible bag body, and safeguard hole cover cloths are installed in the safeguard holes through safeguard hole zippers.

[0016] The present invention also provides a method for using a rock retaining sealing support device suitable for gob-side tunneling, which is implemented by using the rock retaining sealing support device for gob-side tunneling, and comprises the following steps:

[0017] S1. Tunnel support design;

[0018] Determine the size of the rigid support and flexible sealing wall of the rock retaining sealing support device used for the side support of the goaf area of ​​the tunnel, and use metal mesh and retractable U-shaped steel between two adjacent rigid supports to support the tunnel;

[0019] S2, rigid support to support the goaf side of the tunnel;

[0020] The first rigid support is placed at the supporting position in the tunnel and installed. The installation method is as follows: first, the telescopic column controller is controlled to extend the telescopic column, so that the support top beam rises until a gap of 10cm-20cm width is left between the upper and lower rock baffles, and the upper and lower rock baffles are respectively controlled by the upper telescopic arm controller and the lower telescopic arm controller to extend to the side away from the telescopic column, so that the upper and lower rock baffles are located on the same plane and close to the goaf. In this process, one end of the two tunnel top beams is placed in the tunnel top beam placement opening of the support top beam, and the other end of the tunnel top beam is supported by a single hydraulic support.

[0021] Continue to control the telescopic column controller to make the support top beam contact the tunnel roof and support it. At this time, the tunnel top beam also supports the tunnel roof under the joint action of the single hydraulic support and the rigid support; then, respectively place splicing plates in the splicing plate grooves at each group of corresponding upper and lower positions of the upper and lower baffle plates, and fix the splicing plates by installing splicing plate bolts in the splicing plate bolt holes in the splicing plate grooves, and at the same time, place plug-in plates in the plug-in plate grooves at the corresponding positions on the left and right sides of the upper and lower baffle plates, and fix the plug-in plates by installing plug-in plate bolts in the plug-in plate bolt holes, so that the upper and lower baffle plates are connected as one;

[0022] S3, metal mesh and retractable U-shaped steel support tunnel goaf side;

[0023] As the coal mining working face continues to advance, along the advancing direction of the working face, a first retractable U-shaped steel is installed on the right side of the upper and lower rock retaining plates of the first rigid support and close to the goaf, and a tunnel top beam is installed above the first retractable U-shaped steel. The other end of the tunnel top beam is supported by a single hydraulic support, and the tunnel top beam is contacted with the tunnel roof and supported by controlling the extension of the first retractable U-shaped steel and the single hydraulic support; then, along the advancing direction of the working face, a second retractable U-shaped steel is arranged on the right side of the first retractable U-shaped steel, and a tunnel top beam is installed above the second retractable U-shaped steel. The other end of the tunnel top beam is supported by a single hydraulic support, and the tunnel top beam is contacted with the tunnel roof and supported by controlling the extension of the second retractable U-shaped steel and the single hydraulic support; then, along the advancing direction of the working face, the next rigid support is installed on the right side of the second retractable U-shaped steel using the installation method of the first rigid support in step S2;

[0024] A metal mesh is installed between the first rigid support, the first retractable U-shaped steel, the second retractable U-shaped steel and the second rigid support, the metal mesh is placed in front of the first retractable U-shaped steel and the second retractable U-shaped steel and close to the goaf, and the metal mesh is tied and fixed to the first retractable U-shaped steel and the second retractable U-shaped steel;

[0025] S4, flexible sealing wall closes the goaf side of the tunnel;

[0026] Place the side fins on both sides of the flexible sealing wall in the fin gaps of the upper and lower baffle plates of the two rigid supports respectively, the buckles correspond to the buckle bolt holes, and the buckle bolts are installed in the buckle bolt holes to fix the side fins on the upper and lower baffle plates of the two rigid supports, so that the flexible sealing wall is fixed to the two adjacent rigid supports, and the two roadway top beams above the first retractable U-shaped steel and the second retractable U-shaped steel are respectively placed in the two roadway top beam reserved openings of the flexible sealing wall, and then connect the air supply pipeline in the roadway with the medium injection port of the flexible sealing wall, and inject the medium into the flexible sealing wall to expand it, until the top and bottom of the two rigid supports are close to the roadway top plate and the roadway bottom plate, and the roadway top beam is tightly wrapped;

[0027] When the wind flow in the goaf needs to be adjusted, it can be achieved by opening and closing the wind windows on the flexible sealing wall;

[0028] S5, repeating steps S3 and S4 until the support of the entire tunnel is completed;

[0029] S6, reclaim the rigid support and the flexible sealing wall;

[0030] When the supporting tunnel is no longer used with the recovery of its coal mining face, the rigid support and flexible sealing wall can be recycled for reuse; the recycling should be carried out under sufficient ventilation conditions;

[0031] Recycling of rigid supports: first remove the splicing plates, plug plates and buckling bolts on the two rigid supports to disconnect the upper rock baffle, the lower rock baffle and the flexible sealing wall; then synchronously lower the support top beam and the two single hydraulic pillars that support the tunnel top beam with it, and the lowering degree needs to be enough to make the upper rock baffle detach from the tunnel top plate and shrink; then shrink the upper telescopic arm so that the upper and lower rock baffles are not in the same plane; then synchronously lower the support top beam and the two single hydraulic pillars that support the tunnel top beam with it until it is convenient to remove the tunnel top beam; then control the shrinkage of the lower telescopic arm until the lower rock baffle contacts the upper rock baffle;

[0032] Recycling of the flexible sealing wall: After disconnecting the flexible sealing wall from the rigid supports on both sides thereof, release the medium inside the flexible sealing wall through the medium injection port, and then fold the flexible sealing wall.

[0033] Furthermore, in step S2, when it is necessary to detect the horizontal thrust of falling rocks in the goaf on the rigid support, the pressure box is installed in the pressure box installation groove on the upper rock retaining plate and the lower rock retaining plate, and the pipeline of the pressure box is placed in the wire groove and extends into the tunnel through the gap between the upper rock retaining plate and the lower rock retaining plate.

[0034] Furthermore, the single hydraulic prop is installed close to the tunnel wall.

[0035] Compared with the prior art, the present invention has the following beneficial effects:

[0036] (1) The rock-blocking sealing support device for gob-side lane retaining of the present invention can support the lane while preventing the horizontal squeezing of falling rocks in the goaf. The rigid support is provided with an upper rock-blocking plate and a lower rock-blocking plate structure, which can reduce the horizontal thrust of the falling rocks in the goaf on the rigid support, making it easier for the rigid support to support the lane and recover it later. In addition, the top beam of the rigid support is provided with a lane top beam opening, which can work in coordination with a single hydraulic support to support the top plate of the lane.

[0037] (2) The flexible sealing wall of the present invention can be tightly connected with the rigid support, and the flexible sealing wall can seal the goaf side of the tunnel after the medium is injected into the interior; the flexible sealing wall is also provided with a measure hole and a wind window, which is convenient for taking measures against the goaf and adjusting the air volume entering the goaf;

[0038] (3) The rock-blocking sealing support device for retaining a tunnel along the goaf of the present invention, together with the retractable U-shaped steel and the metal mesh, realizes the support and sealing of the goaf side of the tunnel. The use steps are simple, and the workload is small, which is convenient for workers to construct. In addition, the entire device can be recycled and reused, thereby effectively reducing the overall cost of supporting the tunnel along the goaf. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] Figure 1 It is a structural schematic diagram of a rigid support of a rock retaining sealing support device suitable for gob-side tunnel retaining of the present invention;

[0040] Figure 2 is a schematic diagram of a rigid bracket;

[0041] Figure 3 It is a three-dimensional structural schematic diagram of a flexible sealing wall;

[0042] Figure 4 This is a structural diagram of a flexible sealing wall (without installing a windshield cover cloth and a measure hole cover cloth);

[0043] Figure 5 It is a schematic diagram of the installation cross section of the rigid support in the tunnel.

[0044] Figure 6 It is a schematic diagram of the support positions of the rigid bracket, the retractable U-shaped steel and the metal mesh;

[0045] Figure 7 It is a schematic diagram of the connection structure between the rigid support and the flexible sealing wall;

[0046] Figure 8 It is a top view of the installation of two rigid supports and the first retractable U-shaped steel between the two rigid supports, the second retractable U-shaped steel, the metal mesh and the support top beam.

[0047] Markings in the figure:

[0048] 1. Rigid support; 1001. Telescopic column; 1002. Support base; 10021. Rectangular block; 10022. Protrusion; 1003. Support top beam; 1004. Laneway top beam placement opening; 1005. Telescopic column controller; 1006. Upper telescopic arm controller; 1007. Lower telescopic arm controller; 1008. Lower telescopic arm; 1009. Lower gangue baffle; 1010. Plate bolt hole; 1011 , splicing plate groove; 1012, plug-in plate groove; 1013, splicing plate bolt hole; 1014, upper slag plate; 1015, retaining ring bolt hole; 1016, fin seam; 1017, upper telescopic arm; 1018, pressure box installation groove; 1019, wire trough; 1020, fixing bolt hole; 1021, plug-in plate bolt; 1022, splicing plate; 1023, retaining ring bolt; 1024, splicing plate bolt; 1025, plug-in plate;

[0049] 2. Flexible sealing wall; 2001. Side fin; 2002. Buckle; 2003. Wind window; 2004. Measure hole; 2005. Reserved opening for tunnel top beam; 2006. Wind window zipper; 2007. Wind window cover cloth; 2008. Measure hole zipper; 2009. Measure hole cover cloth; 2010. Medium injection port;

[0050] 3. Tunnel top beam; 4. Single hydraulic support;

[0051] 5. Laneway; 5001. Laneway roof; 5002. Laneway floor; 5003. Laneway wall;

[0052] 6. Rockfall in goaf; 7. Retractable U-shaped steel; 8. Metal mesh. DETAILED DESCRIPTION

[0053] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0054] Embodiment 1

[0055] Reference Figure 1-Figure 8 , a rock-blocking sealing support device suitable for gob-side tunneling, comprising a plurality of rigid supports 1 sequentially arranged in a tunnel 5 and a plurality of flexible sealing walls 2 installed between two adjacent rigid supports 1; the number of the rigid supports 1 is not less than two, and the number of the flexible sealing walls 2 is not less than one;

[0056] The rigid support 1 includes a support base 1002, a support top beam 1003, two telescopic columns 1001, two upper telescopic arms 1017, two lower telescopic arms 1008, an upper slag baffle 1014 and a lower slag baffle 1009; two telescopic columns 1001 are symmetrically arranged on the support base 1002 in a vertical direction, the top ends of the two telescopic columns 1001 are fixed to the support top beam 1003, two upper telescopic arms 1017 are installed on the support top beam 1003, and two lower telescopic arms 1017 are installed on the support base 1002. The upper telescopic arm 1008, the two upper telescopic arms 1017 and the two lower telescopic arms 1008 are arranged in parallel on the same side, the two upper telescopic arms 1017 are additionally fixed to the upper rock baffle 1014, and the two lower telescopic arms 1008 are additionally fixed to the lower rock baffle 1009, the upper rock baffle 1014 and the lower rock baffle 1009 have the same structure and are symmetrically arranged up and down; the upper rock baffle 1014 and the lower rock baffle 1009 can reduce the horizontal thrust of the rockfall 6 in the goaf area on the rigid support, which is convenient for the rigid support 1 to support the tunnel 5 and the later recovery;

[0057] A telescopic column controller 1005, an upper telescopic arm controller 1006 and a lower telescopic arm controller 1007 are also provided on the support base 1002, which are used to control the actions of the two telescopic columns 1001, the two upper telescopic arms 1017 and the two lower telescopic arms 1008 respectively;

[0058] The left and right sides of the flexible sealing wall 2 are respectively connected to the upper rock baffle plate 1014 and the lower rock baffle plate 1009 of two adjacent rigid supports 1 .

[0059] Two tunnel top beam placement openings 1004 are provided above the support top beam 1003 for placing the tunnel top beam 3 .

[0060] The upper baffle plate 1014 and the lower baffle plate 1009 both include a "T"-shaped plate body, and a plurality of splicing plate grooves 1011 (three splicing plate grooves 1011 in this embodiment) are provided at the bottom of one side of the "T"-shaped plate body facing the telescopic column 1001, and a plurality of splicing plate bolt holes 1013 (two splicing plate bolt holes 1013 in each splicing plate groove 1011 in this embodiment) are provided on each splicing plate groove 1011;

[0061] Fin slits 1016 and plate slots 1012 are respectively provided on the outer facades of the left and right ends of the “T”-shaped plate body, and multiple buckle bolt holes 1015 are respectively provided from top to bottom at the two ends of the end surface of the “T”-shaped plate body facing the telescopic column 1001, and two plate bolt holes 1010 are respectively provided at the bottom of the two ends of the end surface of the “T”-shaped plate body facing the telescopic column 1001 at the plate slots 1012;

[0062] The end face of the "T"-shaped plate body facing away from the telescopic column 1001 is provided with multiple pressure box mounting grooves 1018 (two in this embodiment), a wire groove 1019 is provided under each pressure box mounting groove 1018, and two fixing bolt holes 1020 are provided in the pressure box mounting groove 1018. A pressure box is installed in the pressure box mounting groove 1018 to detect the horizontal thrust of the fallen rocks 6 in the goaf.

[0063] Reference Figure 3 and Figure 4 The flexible sealing wall 2 includes a flexible bag body, and side fins 2001 are respectively provided on the left and right side facades of the flexible bag body, and multiple buckle rings 2002 are provided on the side fins 2001; two tunnel top beam reserved openings 2005 are provided on the top of the flexible bag body for the tunnel top beam 3 to pass through; a medium injection port 2010 is also provided at the bottom of the flexible bag body for injecting a medium (the medium is air or liquid medium) into it, so that the flexible sealing wall 2 expands and fits tightly against the top and bottom of the tunnel 5.

[0064] A plurality of wind windows 2003 are also provided in the middle of the flexible bag body. The number of wind windows 2003 is not less than two, and in this embodiment, the number is three. A wind window cover 2007 is installed in the wind window 2003 through a wind window zipper 2006. The wind window cover 2007 is opened or closed through the wind window zipper 2006 to adjust the air volume entering the goaf.

[0065] A plurality of measure holes 2004 are provided at the bottom of the flexible bag body, the number of the measure holes 2004 being no less than two, and the number being three in this embodiment, and a measure hole cover cloth 2009 is installed in the measure hole 2004 through a measure hole zipper 2008, and the measure hole 2004 is used for the pipeline to pass through when nitrogen or other media is injected into the goaf;

[0066] In the present invention, the support base 1002 includes a rectangular block 10021 and two rectangular protrusions 10022 arranged above the rectangular block 10021 at intervals along the width direction of the rectangular block 10021 , and the telescopic columns 1001 are fixed above the two protrusions 10022 respectively.

[0067] Embodiment 2

[0068] Reference Figure 1-Figure 8 A method for using a rock retaining sealing support device for gob-side tunneling is implemented by using the rock retaining sealing support device for gob-side tunneling in the first embodiment, and includes the following steps:

[0069] S1. Tunnel support design;

[0070] Determine the size of the rigid support 1 and the flexible sealing wall 2 of the rock-blocking sealing support device used for the side support of the goaf of the tunnel, and use the metal mesh 8 and the retractable U-shaped steel 7 between two adjacent rigid supports 1 to support the tunnel 5; the specific size of the rigid support 1, the flexible sealing wall 2, the retractable U-shaped steel 7 and the metal mesh 8 is determined according to the tunnel conditions;

[0071] S2, rigid support 1 supports the goaf side of tunnel 5;

[0072] The first rigid support 1 is placed at the supporting position in the tunnel 5 and installed. The installation method is as follows: first, the telescopic column 1001 is extended by controlling the telescopic column controller 1005, so that the support top beam 1003 rises until a gap of 10cm-20cm width is left between the upper gangue baffle 1014 and the lower gangue baffle 1009, and the upper telescopic arm controller 1006 and the lower telescopic arm controller 1007 are used to control the upper gangue baffle 1014 and the lower gangue baffle 1009 to extend to the side away from the telescopic column 1001, so that the upper gangue baffle 1014 and the lower gangue baffle 1009 are located on the same plane and close to the goaf. In this process, one end of the two tunnel top beams 3 is placed in the tunnel top beam placement opening 1004 of the support top beam 1003, and the other end of the tunnel top beam 3 is supported by a single hydraulic support 4;

[0073] Continue to control the telescopic column controller 1005 to make the support top beam 1003 contact the tunnel roof 5001 and support it. At this time, the tunnel top beam 3 also supports the tunnel roof 5001 under the joint action of the single hydraulic support 4 and the rigid support 1; then place the splicing plates 1022 in the splicing plate grooves 1011 of each group of corresponding upper and lower positions of the upper and lower baffle plates 1014 and the lower baffle plates 1009, and The splicing plate bolts 1024 are installed in the splicing plate bolt holes 1013 in 1011 to fix the splicing plate 1022, and the inserting plates 1025 are placed in the inserting plate grooves 1012 at the corresponding positions on the left and right sides of the upper baffle plate 1014 and the lower baffle plate 1009, and the inserting plate bolts 1021 are installed in the inserting plate bolt holes 1010 to fix the inserting plate 1025, so that the upper baffle plate 1014 and the lower baffle plate 1009 are connected as a whole;

[0074] In step S2, when it is necessary to detect the horizontal thrust of the rockfall 6 in the goaf on the rigid support 1, the pressure box is installed in the pressure box installation groove 1018 on the upper rock baffle plate 1014 and the lower rock baffle plate 1009, and the pipeline of the pressure box is placed in the wire groove 1019 and extends into the tunnel 5 through the gap between the upper rock baffle plate 1014 and the lower rock baffle plate 1009;

[0075] S3, metal mesh 8 and retractable U-shaped steel 7 support the goaf side of the tunnel;

[0076] Reference Figure 7 As the coal mining working face continues to advance, along the advancing direction of the working face, a first retractable U-shaped steel 7 is installed on the right side of the upper gangue retaining plate 1014 and the lower gangue retaining plate 1009 of the first rigid support and close to the goaf, and a tunnel top beam 3 is installed above the first retractable U-shaped steel 7. The other end of the tunnel top beam 3 is supported by a single hydraulic support 4. By controlling the extension of the first retractable U-shaped steel 7 and the single hydraulic support 4, the tunnel top beam 3 contacts the tunnel roof 5001 and supports it; then, along the advancing direction of the working face, a second retractable U-shaped steel 7 is installed on the right side of the first retractable U-shaped steel 7, and a second retractable U-shaped steel 7 is installed on the second retractable U-shaped steel 7. The tunnel top beam 3 is installed, and the other end of the tunnel top beam 3 is supported by a single hydraulic support 4. By controlling the extension of the second retractable U-shaped steel 7 and the single hydraulic support 4, the tunnel top beam 3 contacts the tunnel roof 5001 and supports it; then along the advancing direction of the working face, the next rigid support 1 is installed on the right side of the second retractable U-shaped steel 7 using the installation method of the first rigid support 1 in step S3; the installation positions of the first retractable U-shaped steel 7 and the second retractable U-shaped steel 7 are based on the positions of the two tunnel top beams 3 above them corresponding to the positions of the two tunnel top beam reserved openings 2005 above the pre-installed flexible sealing wall 2;

[0077] A metal mesh 8 is installed between the first rigid support 1, the first retractable U-shaped steel 7, the second retractable U-shaped steel 7 and the second rigid support 1. The metal mesh 8 is placed in front of the first retractable U-shaped steel 7 and the second retractable U-shaped steel 7 and close to the goaf. The metal mesh 8 is tied and fixed to the first retractable U-shaped steel 7 and the second retractable U-shaped steel 7. The mesh of the metal mesh 8 is a diamond or square shape.

[0078] S4, flexible sealing wall 2 closes the goaf side of the tunnel;

[0079] Reference Figure 7 and Figure 8 The side fins 2001 on both sides of the flexible sealing wall 2 are respectively placed in the fin slits 1016 of the upper baffle plate 1014 and the lower baffle plate 1009 of the two rigid brackets 1, and the buckle ring 2002 corresponds to the buckle ring bolt hole 1015, and the buckle ring bolt 1023 is installed in the buckle ring bolt hole 1015 to fix the side fin 2001 on the upper baffle plate 1014 and the lower baffle plate 1009 of the two rigid brackets 1, so that the flexible sealing wall 2 is connected to the two adjacent The first retractable U-shaped steel 7 and the second retractable U-shaped steel 7 are fixed with a rigid bracket 1, and the two tunnel top beams 3 above the first retractable U-shaped steel 7 are respectively placed in the tunnel top beam reserved opening 2005, and then the air supply pipeline in the tunnel 5 is connected to the medium injection port 2010 of the flexible sealing wall 2, and the medium (air or liquid) is injected into it to expand it, until the top and bottom of the flexible sealing wall 2 are closely attached to the tunnel top plate 5001 and the tunnel bottom plate 5002, and the tunnel top beam 3 is tightly wrapped;

[0080] When the wind flow in the goaf needs to be adjusted, it is achieved by opening and closing the wind window 2003 on the flexible sealing wall 2;

[0081] S5, repeating steps S3 and S4 until the support of the entire tunnel 5 is completed;

[0082] S6, recovering the rigid support 1 and the flexible sealing wall 2;

[0083] When the supporting tunnel 5 is no longer used with the recovery of its coal mining face, the rigid support 1 and the flexible sealing wall 2 can be recovered for reuse; the recovery should be carried out under conditions of sufficient ventilation;

[0084] Recycling of the rigid support 1: first remove the splicing plates 1022, the plug plates 1025 and the retaining ring bolts 1023 on the two rigid supports 1 to disconnect the upper gangue baffle 1014, the lower gangue baffle 1009 and the flexible sealing wall 2; then synchronously lower the support top beam 1003 and the two single hydraulic struts 4 that support the tunnel top beam 3 together, and the lowering degree needs to be enough to enable the upper gangue baffle 1014 to be separated from the tunnel top plate 5001 and to be able to shrink; then shrink the upper telescopic arm 1017 so that the upper gangue baffle 1014 and the lower gangue baffle 1009 are not in the same plane; then synchronously lower the support top beam 1003 and the two single hydraulic struts 4 that support the tunnel top beam 3 together with it until it is convenient to remove the tunnel top beam 3; then control the shrinkage of the lower telescopic arm 1008 until the lower gangue baffle 1009 contacts the upper gangue baffle 1014;

[0085] Recycling of the flexible sealing wall 2: After the flexible sealing wall 2 is disconnected from the rigid supports 1 on both sides thereof, the medium inside the flexible sealing wall 2 can be released through the medium injection port 2010 and then folded.

[0086] The single hydraulic prop 4 is installed close to the tunnel wall 5003 .

[0087] The rigid support 1 of the present invention is provided with an upper rock retaining plate 1014 and a lower rock retaining plate 1009 structure, which can reduce the horizontal thrust of the falling rocks 6 in the goaf on the rigid support 1, and facilitate the support of the tunnel 5 by the rigid support 1 and the subsequent recovery; and the tunnel top beam placement port 1004 is provided on the support top beam 1003, which can cooperate with the single hydraulic support 4 to achieve the support of the tunnel top plate 5001. Through the structural design of the flexible sealing wall 2 and the rigid support 1, a tight connection can be achieved, and after the medium is injected into the flexible sealing wall 2, the goaf side of the tunnel 5 can be sealed to avoid the spontaneous combustion of the goaf caused by air leakage. In addition, the rigid support 1 and the flexible sealing wall 2 of the present invention are both recyclable structures, which effectively reduce the overall cost of supporting the goaf.

[0088] The principles and implementation methods of the present invention are described in this article using specific examples. The description of the above embodiments is only used to help understand the method and core idea of ​​the present invention. At the same time, for those skilled in the art, according to the idea of ​​the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.

Claims

1. A rock retaining sealing support device suitable for gob-side tunnelling, characterized in that: It includes a plurality of rigid supports which are sequentially arranged in the tunnel at intervals and a plurality of flexible sealing walls which are installed between two adjacent rigid supports; The rigid support comprises a support base, a support top beam, two telescopic columns, two upper telescopic arms, two lower telescopic arms, an upper rock baffle plate and a lower rock baffle plate; two telescopic columns are symmetrically arranged on the support base in a vertical direction, the top ends of the two telescopic columns are fixed to the support top beam, two upper telescopic arms are installed on the support top beam, two lower telescopic arms are installed on the support base, the two upper telescopic arms and the two lower telescopic arms are arranged in parallel on the same side, the two upper telescopic arms are additionally fixed to the upper rock baffle plate, the two lower telescopic arms are additionally fixed to the lower rock baffle plate, the upper rock baffle plate and the lower rock baffle plate have the same structure and are symmetrically arranged up and down; A telescopic column controller, an upper telescopic arm controller and a lower telescopic arm controller are also provided on the support base, which are used to control the actions of the two telescopic columns, the two upper telescopic arms and the two lower telescopic arms respectively; The left and right sides of the flexible sealing wall are respectively connected to the upper rock retaining plate and the lower rock retaining plate of two adjacent rigid supports.

2. A rock retaining sealing support device suitable for gob-side tunnelling according to claim 1, characterized in that: Two tunnel top beam placement openings are arranged above the support top beam for placing the tunnel top beam.

3. A rock retaining sealing support device suitable for gob-side tunnelling according to claim 1, characterized in that: The upper and lower rock baffle plates each include a "T"-shaped plate body, a plurality of splicing plate grooves are provided at the bottom of the "T"-shaped plate body facing the telescopic column, and a plurality of splicing plate bolt holes are provided on each splicing plate groove; The left and right outer sides of the "T"-shaped plate body are respectively provided with fin slits and plate slots, and the two ends of the end surface of the "T"-shaped plate body facing the telescopic column are respectively provided with a plurality of buckle bolt holes from top to bottom, and the bottom of the two ends of the end surface of the "T"-shaped plate body facing the telescopic column are respectively provided with a plurality of plate bolt holes at the plate slots; The end face of the "T"-shaped plate body facing away from the telescopic column is provided with multiple pressure box installation grooves, a wire groove is provided under each pressure box installation groove, two fixing bolt holes are provided in the pressure box installation groove, and a pressure box is installed in the pressure box installation groove to detect the horizontal thrust of falling rocks in the goaf.

4. A rock retaining sealing support device suitable for gob-side tunnelling as claimed in claim 1, characterized in that: The flexible sealing wall includes a flexible bag body, on the left and right side facades of the flexible bag body are respectively provided with side fins, and the side fins are provided with a plurality of buckle rings; two tunnel top beam reserved openings are provided on the top of the flexible bag body for the tunnel top beam to pass through, and a medium injection port is also provided at the bottom of the flexible bag body for injecting medium therein, so that the flexible sealing wall expands and fits tightly against the top and bottom of the tunnel.

5. A rock retaining sealing support device suitable for gob-side tunnelling as claimed in claim 4, characterized in that: A plurality of wind windows are also provided in the middle of the flexible bag body, and wind window covers are installed in the wind windows through wind window zippers. The wind window covers are opened or closed through the wind window zippers to adjust the air volume entering the goaf.

6. A rock retaining sealing support device suitable for gob-side tunnelling as claimed in claim 4, characterized in that: A plurality of measure holes are arranged at the bottom of the flexible bag body, and measure hole cover cloths are installed in the measure holes through measure hole zippers.

7. A method for using a rock retaining sealing support device for gob-side entry retention, which is implemented by using the rock retaining sealing support device for gob-side entry retention as claimed in any one of claims 1 to 6, characterized in that: The following steps are involved: S1. Tunnel support design; Determine the size of the rigid support and flexible sealing wall of the rock retaining sealing support device used for the side support of the goaf area of ​​the tunnel, and use metal mesh and retractable U-shaped steel between two adjacent rigid supports to support the tunnel; S2, rigid support to support the goaf side of the tunnel; The first rigid support is placed at the supporting position in the tunnel and installed. The installation method is as follows: first, the telescopic column controller is controlled to extend the telescopic column, so that the support top beam rises until a gap of 10cm-20cm width is left between the upper and lower rock baffles, and the upper and lower rock baffles are respectively controlled by the upper telescopic arm controller and the lower telescopic arm controller to extend to the side away from the telescopic column, so that the upper and lower rock baffles are located on the same plane and close to the goaf. In this process, one end of the two tunnel top beams is placed in the tunnel top beam placement opening of the support top beam, and the other end of the tunnel top beam is supported by a single hydraulic support. Continue to control the telescopic column controller to make the support top beam contact the tunnel roof and support it. At this time, the tunnel top beam also supports the tunnel roof under the joint action of the single hydraulic support and the rigid support; then, respectively place splicing plates in the splicing plate grooves at each group of corresponding upper and lower positions of the upper and lower baffle plates, and fix the splicing plates by installing splicing plate bolts in the splicing plate bolt holes in the splicing plate grooves, and at the same time, place plug-in plates in the plug-in plate grooves at the corresponding positions on the left and right sides of the upper and lower baffle plates, and fix the plug-in plates by installing plug-in plate bolts in the plug-in plate bolt holes, so that the upper and lower baffle plates are connected as one; S3, metal mesh and retractable U-shaped steel support goaf side of the tunnel; As the coal mining face continues to advance, along the advancing direction of the working face, a first retractable U-shaped steel is installed on the right side of the upper and lower rock retaining plates of the first rigid support and close to the goaf, and a tunnel top beam is installed above the first retractable U-shaped steel. The other end of the tunnel top beam is supported by a single hydraulic support, and the tunnel top beam is contacted with the tunnel roof and supported by controlling the extension of the first retractable U-shaped steel and the single hydraulic support; then, along the advancing direction of the working face, a second retractable U-shaped steel is arranged on the right side of the first retractable U-shaped steel, and a tunnel top beam is installed above the second retractable U-shaped steel. The other end of the tunnel top beam is supported by a single hydraulic support, and the tunnel top beam is contacted with the tunnel roof and supported by controlling the extension of the second retractable U-shaped steel and the single hydraulic support; then, along the advancing direction of the working face, the next rigid support is installed on the right side of the second retractable U-shaped steel using the installation method of the first rigid support in step S2; A metal mesh is installed between the first rigid support, the first retractable U-shaped steel, the second retractable U-shaped steel and the second rigid support, the metal mesh is placed in front of the first retractable U-shaped steel and the second retractable U-shaped steel and close to the goaf, and the metal mesh is tied and fixed to the first retractable U-shaped steel and the second retractable U-shaped steel; S4, flexible sealing wall closes the goaf side of the tunnel; Place the side fins on both sides of the flexible sealing wall in the fin gaps of the upper and lower baffle plates of the two rigid supports respectively, the buckles correspond to the buckle bolt holes, and the buckle bolts are installed in the buckle bolt holes to fix the side fins on the upper and lower baffle plates of the two rigid supports, so that the flexible sealing wall is fixed to the two adjacent rigid supports, and the two roadway top beams above the first retractable U-shaped steel and the second retractable U-shaped steel are respectively placed in the two roadway top beam reserved openings of the flexible sealing wall, and then connect the air supply pipeline in the roadway with the medium injection port of the flexible sealing wall, and inject the medium into the flexible sealing wall to expand it, until the top and bottom of the two rigid supports are close to the roadway top plate and the roadway bottom plate, and the roadway top beam is tightly wrapped; When the wind flow in the goaf needs to be adjusted, it can be achieved by opening and closing the wind windows on the flexible sealing wall; S5, repeating steps S3 and S4 until the support of the entire tunnel is completed; S6, reclaim the rigid support and the flexible sealing wall; When the supporting tunnel is no longer used with the recovery of its coal mining face, the rigid support and flexible sealing wall can be recycled for reuse; the recycling should be carried out under sufficient ventilation conditions; Recycling of rigid supports: first remove the splicing plates, plug plates and buckling bolts on the two rigid supports to disconnect the upper rock baffle, the lower rock baffle and the flexible sealing wall; then synchronously lower the support top beam and the two single hydraulic pillars that support the tunnel top beam with it, and the lowering degree needs to be enough to make the upper rock baffle detach from the tunnel top plate and shrink; then shrink the upper telescopic arm so that the upper and lower rock baffles are not in the same plane; then synchronously lower the support top beam and the two single hydraulic pillars that support the tunnel top beam with it until it is convenient to remove the tunnel top beam; then control the shrinkage of the lower telescopic arm until the lower rock baffle contacts the upper rock baffle; Recycling of the flexible sealing wall: After disconnecting the flexible sealing wall from the rigid supports on both sides thereof, release the medium inside the flexible sealing wall through the medium injection port, and then fold the flexible sealing wall.

8. The method for using the rock retaining sealing support device for gob-side tunnel retaining as claimed in claim 7, characterized in that: In step S2, when it is necessary to detect the horizontal thrust of falling rocks in the goaf on the rigid support, the pressure box is installed in the pressure box installation groove on the upper and lower rock retaining plates, and the pipeline of the pressure box is placed in the wire groove and extends into the tunnel through the gap between the upper and lower rock retaining plates.

9. The method for using the rock retaining sealing support device for gob-side tunnel retaining as claimed in claim 7, characterized in that: The single hydraulic prop is installed close to the tunnel wall.