Wind-pressure-resistant aluminum plate suspended ceiling system for large-space top surface and mounting construction method of wind-pressure-resistant aluminum plate suspended ceiling system
By adopting wind-resistant aluminum plate ceiling system in typhoon buildings, using rigid fixing and fine-tuning technology of angle steel and connecting accessories, the problem of deformation and fall off of aluminum alloy plates under wind pressure is solved, and the stability of the ceiling system is improved. Security.
Patent Information
- Application Number
- CN202411356650.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-27
- Publication Date
- 2024-11-19
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In buildings in typhoon areas, the lightweight and beautiful aluminum alloy plate ceiling is prone to deform and fall off under wind pressure, and the existing hook-and-up connection method poses safety hazards and economic losses.
Design a wind-resistant aluminum plate ceiling system, adopting direct fixing and fine-adjustable connection, fixing the aluminum plate to the conversion layer through angle steel and connecting accessories structures, and using serrated grooves and bolts to achieve rigid connection and height adjustment of the aluminum plate, and During the construction process, BIM design and angle codes are used for precise installation.
It effectively avoids deformation and fall off of aluminum plates caused by wind pressure, improves the installation and service life of the ceiling system, ensures flatness and aesthetics, and adapts to the settlement deformation of the building.
Smart Images

Figure CN118979584A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of building construction, and in particular to a wind pressure resistant aluminum plate ceiling system for a large space top surface and an installation construction method of the aluminum plate ceiling system. Background Art
[0002] Suspended ceiling is a common ceiling decoration form in building decoration projects. According to the environment and climate characteristics of the building, choosing suspended ceiling forms of different materials can reflect different decorative styles, create different interior styles and atmospheres, and reflect the characteristics of decorative design.
[0003] Luxury resort hotels are often built in beautiful locations, relying on the beautiful natural environment to blend in with the surroundings, providing a good and comfortable environment for vacation and leisure. Among them, islands or peninsulas have become more preferred locations. For islands in the south, if they are in the path of typhoons, adaptive design and adjustment of buildings and interior decoration are necessary. Especially for large indoor space ceilings, if lightweight and beautiful aluminum alloy plates are selected as ceiling materials, it is necessary to consider how to avoid deformation and falling off caused by wind pressure after the decorative aluminum plates are installed as ceilings.
[0004] In the prior art, in order to facilitate the construction of aluminum alloy plates as suspended ceilings, the decorative aluminum plates are often hung in a hooking manner. The aluminum alloy decorative plates are processed in the factory and transported to the construction site for hooking and connection, and then installed piece by piece on the conversion layer on the top surface of the interior space of the building to form a suspended ceiling. However, this hooking and connection method will cause safety hazards for large spaces in the typhoon belt. In typhoon weather, wind will blow into the interior space through the gaps and doors and windows of the building, resulting in a pressure difference between the front and back of the aluminum plate ceiling inside the building, thereby forming a large positive and negative wind pressure problem. The long strips of aluminum plates are easily blown down due to the hooking installation method, causing safety hazards and economic losses. Summary of the invention
[0005] The purpose of the present invention is to overcome the deficiencies in the above-mentioned prior art and provide a wind-resistant aluminum plate ceiling system for large space ceilings and an installation and construction method of the aluminum plate ceiling system. The wind-resistant ceiling system and its installation method of the present invention are specially designed for large indoor space ceilings of buildings in typhoon zones. Through direct fixed installation and fine-tunable connection, it is required to have rigid resistance to avoid falling off when a typhoon comes, and to be able to adapt to the slight deformation caused by the settlement of the building itself.
[0006] In order to achieve the above invention purpose, the technical solution provided by the present invention is as follows:
[0007] A wind-pressure-resistant aluminum plate ceiling system for the top surface of a large space, a conversion layer is provided on the internal top surface of the large space, the ceiling system includes an aluminum plate, a connecting accessory structure and an angle steel, a plurality of the angle steels are in the conversion layer, a base layer in the conversion layer is welded to the internal top surface of the large space of the building to form a horizontal plane, a plurality of the aluminum plates are adjustably fixed to the angle steels through the connecting accessory structure, the direction of the aluminum plates is perpendicular to the angle steels; the connecting accessory structure includes a plurality of connecting accessories connected to each aluminum plate, the connecting accessory composition includes an upper connecting piece, a lower connecting piece and a plastic pad, the side surface of the upper connecting piece is in an inverted L-shape, including an upper vertical plate and a top plate with edges vertically connected, a plurality of serrated grooves are provided on the inner side of the lower vertical plate, the plurality of serrated grooves are arranged in parallel, the side surface of the lower connecting piece is in an L-shape, including a lower vertical plate and a bottom plate with edges vertically connected, A plurality of serrated grooves are provided on the inner side, and the plurality of serrated grooves are arranged in parallel. The upper connecting piece and the lower connecting piece are buckled with each other and the serrated grooves are relatively connected. The serrated grooves at different positions are fitted to achieve distance adjustment between the top plate and the bottom plate. The plastic pad is fitted on the top of the top plate, and a transverse long hole is provided in the middle of the top plate and the plastic pad. The direction of the transverse long hole is parallel to the upper vertical plate, and vertical long holes are respectively provided in the middle of the upper vertical plate and the lower vertical plate. The upper connecting piece and the lower connecting piece are fixed together at an adjustable height by bolts passing through the vertical long holes; the connecting accessories are connected to the angle steel by bolts, and the plastic pad is between the upper connecting piece and the angle steel. The bolts pass through the transverse long holes of the plastic pad and the upper connecting piece respectively. The aluminum plate is connected to the bottom plate of the connecting accessories at the corresponding position by screws, and a plurality of the aluminum plates are spliced to form a suspended ceiling on the top surface of a large space.
[0008] In the wind pressure resistant aluminum plate ceiling system for the top surface of a large space of the present invention, a card slot is provided at the bottom of the lower connecting member, and the card slot is two parallel raised strips, and the edges of adjacent strip-shaped aluminum plates are arranged in the card slot.
[0009] In the wind-resistant aluminum plate ceiling system for the top surface of a large space of the present invention, the serrated grooves are horizontally arranged to form a wave shape, and the upper and lower vertical plates relative to each other are interlocked and tightly fitted to form an integrated connection accessory to prevent sliding through the serrated grooves.
[0010] In the wind pressure resistant aluminum plate ceiling system for the top surface of a large space of the present invention, a plurality of the connection accessories are fixed on the same angle steel at the same intervals, and each connection accessory is connected to the protrusion of the edge of the aluminum plate.
[0011] In the wind pressure resistant aluminum plate ceiling system for the top surface of a large space of the present invention, the aluminum plate is an aluminum alloy flat plate with 90-degree folded edges on both sides, and decorative wood grain is provided on the surface of the aluminum alloy flat plate. Adjacent aluminum plates are tightly attached by folding edges to achieve seamless splicing.
[0012] In the wind pressure resistant aluminum plate ceiling system for the top surface of a large space of the present invention, an angle code is provided on the aluminum alloy flat plate, one side of a plurality of the angle codes is fixed to the same side fold of the aluminum alloy flat plate with screws, and the top of the angle code is fixed to the bottom plate.
[0013] A method for installing and constructing a wind-resistant aluminum plate ceiling system for a large space top surface, the method comprising the following steps:
[0014] The first step is to weld the base layer of the conversion layer. An aluminum plate ceiling system is designed on the top surface of the large space inside the typhoon belt building. The ceiling system uses angle brackets to adjustably fix the aluminum plate on the conversion layer. The conversion layer is welded and fixed on the top of the building as the base layer to form a construction surface. The size of a single aluminum plate is designed using BIM, and the order drawings of the aluminum plate for processing operations are output. According to the order drawings of the aluminum plate, the installation position of the angle bracket is designed, and the angle bracket is positioned at a height of 7 cm above the finished surface of the vertical high conversion layer of the aluminum plate;
[0015] The second step is to position and punch holes. According to the order drawing of the aluminum plate, the aluminum plate is processed and a hole opener is used to punch holes on the top surface according to the approximate position of the aluminum plate corner code, with a left and right deviation of 2 cm.
[0016] The third step is to install the connection accessories, design and process the connection accessories, which are composed of an upper connection piece, a lower connection piece and a plastic pad. The side of the upper connection piece is in an inverted L-shape, including an upper vertical plate and a top plate whose edges are vertically connected, and a plurality of sawtooth grooves are provided on the inner side of the upper vertical plate, and the plurality of sawtooth grooves are arranged in parallel. The side of the lower connection piece is in an L-shape, including a lower vertical plate and a bottom plate whose edges are vertically connected, and a plurality of sawtooth grooves arranged in parallel are provided on the inner side of the lower vertical plate. The upper connection piece and the lower connection piece are buckled with each other and the sawtooth grooves are relatively connected, and the plastic pad is fitted on the top of the top plate as a vibration damping pad; during the installation of the connection accessories, the vibration damping pad is positioned upward so that the plastic pad can be fixed to the angle steel on the conversion layer during subsequent installation;
[0017] Step 4: Level adjustment: Before the aluminum plate arrives at the site, the bottom of the aluminum alloy profile needs to be leveled with a level to meet the installation requirements after the aluminum plate arrives at the site;
[0018] Step 5: Install and adjust the aluminum plate. Before installing the aluminum plate, verify the position of the angle code on the aluminum plate on site. If the angle code is offset, reinstall the angle code on site to determine the position of the top aluminum plate. After confirming, fix one piece first and then insert and fix it later.
[0019] Step 6. Complete and inspect the ceiling system. After all the aluminum panels are spliced together to form a large-area ceiling, the ceiling is adjustably fixed to the transfer layer using rigid connections. Inspect its flatness and tightness of fit to ensure that the flatness is less than 0.1 / 100 and the maximum gap between adjacent aluminum panels is less than 5 cm.
[0020] In the fifth step, when installing the aluminum plate, first fix the aluminum plate at the edge by fixing it on both sides, insert one side of the adjacent aluminum plate into the edge of the fixed aluminum plate so that the folded edges are aligned and connected horizontally with screws, and fix the folded edges on the other side to the angle steel of the conversion layer with angle codes, and then use one side of screws to horizontally connect the adjacent aluminum plates and fix them, and use one side of the angle code to fix the angle steel to achieve aluminum plate splicing.
[0021] Based on the above technical solution, the wind pressure resistant aluminum plate ceiling system for large space top surface and the installation and construction method of the aluminum plate ceiling system of the present invention have achieved the following technical effects through practical application:
[0022] 1. The wind-pressure-resistant aluminum plate ceiling system for the ceiling of a large space of the present invention analyzes the different wind pressure differences between the upper and lower parts of the ceiling inside the building caused by typhoon weather, analyzes the causes of deformation and falling off of the ceiling, and proposes a rigid connection method for fixing the aluminum plate ceiling. By designing special connection accessories, the connection accessories can be used to rigidly fix the profile aluminum plate on the angle steel of the conversion layer, thereby avoiding large-area deformation of the aluminum plate caused by excessive wind pressure, and avoiding deformation and falling off caused by overlap connection in the prior art, thereby maintaining the installability of the ceiling system and increasing its service life.
[0023] 2. The wind-pressure-resistant aluminum plate ceiling system for the large space ceiling of the present invention takes into account the shortcomings brought by rigid connection and fully considers the deformation problem during the construction and use of the aluminum plate ceiling, and makes the connection accessory structure adjustable. On the one hand, in conjunction with the size adjustment of the ceiling installation construction, the height position and the left and right position can be adjusted within a certain range, so that the flatness and reliability of the ceiling system installation are guaranteed. Plastic pads are also designed on the connection accessory structure as buffers, which provide a certain buffer during the construction process to avoid abnormal noise caused by slight deformation due to wind pressure, and to avoid deformation of the connection parts caused by rigid connection and affecting the appearance, and can make subsequent adjustments to the deformation of the building caused by settlement to maintain the flatness and aesthetics of the aluminum plate ceiling system.
[0024] 3. The present invention specially designs an installation and construction method to complete the construction of a wind-resistant aluminum plate ceiling system for the top surface of a large space. First, a processing drawing of the aluminum plate is given in a BIM manner, and the aluminum plate profile is processed according to the drawing. Then holes are punched on the aluminum plate and angle codes are installed as connecting transition parts, and then connecting accessories are processed. Each connecting accessory has the same structure and can achieve left-right adjustment and up-and-down adjustment within a certain range. A special splicing method is used at the installation site. The aluminum plate at the edge is first fixed on both sides, and one side of the adjacent aluminum plate is inserted into the edge of the fixed aluminum plate so that the folded edges are aligned and connected horizontally with screws. The folded edge on the other side is fixed to the angle steel of the conversion layer with an angle code, and the adjacent aluminum plates are fixed horizontally with screws on one side, and the angle steel is fixed on one side to achieve aluminum plate splicing, thereby achieving construction convenience and safety of the aluminum plate ceiling system installation, so that the installed aluminum plate can resist typhoons and avoid falling off. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 This is a schematic diagram of the difference in wind pressure inside and outside a building in a typhoon-covered area.
[0026] Figure 2 The invention is a side view of the installation of a wind pressure resistant aluminum plate ceiling system for a large space top surface.
[0027] Figure 3 The present invention is a schematic diagram of a connecting accessory structure in a wind pressure resistant aluminum plate ceiling system for a large space top surface.
[0028] Figure 4 The diagram is a schematic diagram of the connection state of a wind pressure resistant aluminum plate ceiling system for a large space top surface according to the present invention.
[0029] Figure 5 The invention is a schematic flow chart of an installation and construction method of a wind pressure resistant aluminum plate ceiling system for a large space top surface. DETAILED DESCRIPTION
[0030] Below we will further elaborate on the wind pressure resistant aluminum plate ceiling system for the ceiling of a large space and the installation and construction method of the aluminum plate ceiling system in combination with the accompanying drawings and specific embodiments, in order to more clearly understand its structural composition and installation and construction method, but this cannot be used to limit the protection scope of the present invention.
[0031] Example 1
[0032] A hotel is located on the sea, on the path of typhoons all year round. According to the design requirements, our lobby is decorated with aluminum panels. The original hanging method is hook-type, such as Figure 2 As shown in the figure, the bottom is a wood grain aluminum plate 1, and a 50 angle steel 2 is set on the top to hold the wood grain aluminum plate. The adjacent wood grain aluminum plates 1 are connected in a hooking manner, which poses a hidden danger to the top surface of a large space and cannot resist large deformation. Figure 1 The wind pressure analysis shown in the figure found that it would cause a great impact on the suspended ceiling. According to our previous analysis of the aluminum ceiling panels of the adjacent hotel, the island faces typhoon weather. We need to consider that when a typhoon comes, the poor sealing of the building will lead to a difference in wind force between the front and back of the aluminum ceiling panels, resulting in a large positive and negative wind pressure problem. If the original hook-up connection is used, the strip-shaped wood-grain aluminum panels are very easy to blow off due to the hook-up installation, which will cause safety hazards and economic losses.
[0033] like Figure 4 As shown, the present invention is a wind pressure resistant aluminum plate ceiling system for the top surface of a large space, and a conversion layer is provided on the internal top surface of the large space building. The ceiling system includes an aluminum plate, a connection accessory structure and an angle steel, a plurality of the angle steels are in the conversion layer, the base layer in the conversion layer is welded on the internal top surface of the large space of the building to form a horizontal construction surface, and a plurality of the aluminum plates are adjustably fixed on the angle steel through the connection accessory structure, and the adjustable means that the height and horizontal position of the aluminum plate can be adjusted within a small range as needed. The direction of the aluminum plate is perpendicular to the angle steel, so that multiple parallel aluminum plates can be spliced and connected to the same angle steel; the connection accessory structure includes a plurality of connection accessories connected to each aluminum plate, and the plurality of connection accessories are located at different positions to form a connection accessory structure, the purpose is to combine multiple aluminum plates into a body and connect them to the conversion layer, and its function is required to be a physical connection on the one hand, to improve the connection strength to resist the damage to the ceiling caused by different wind pressures caused by typhoons, and on the other hand, it can be fine-tuned as needed to avoid deformation of the ceiling due to building settlement.
[0034] like Figure 3As shown, the connecting accessory structure includes a plurality of connecting accessories connected to each aluminum plate, and the connecting accessory composition includes an upper connecting member 41, a lower connecting member 42 and a plastic pad 43. The side of the upper connecting member 41 is in an inverted L-shape, including an upper vertical plate and a top plate whose edges are vertically connected, and a plurality of serrated grooves are provided on the inner side of the upper vertical plate, and the plurality of serrated grooves are arranged in parallel. The side of the lower connecting member 42 is in an L-shape, including a lower vertical plate and a bottom plate whose edges are vertically connected, and a plurality of serrated grooves are provided on the inner side of the lower vertical plate, and the plurality of serrated grooves on the lower vertical plate are also arranged in parallel. The upper connecting member and the lower connecting member are buckled with each other and the serrated grooves are relatively connected, and the serrated grooves at different positions are fitted to achieve the distance adjustment of the top plate and the bottom plate. The plastic pad 43 is fitted on the top of the top plate, and a transverse long hole 44 is provided in the middle of the top plate and the plastic pad. The direction of the transverse long hole 44 is parallel to the upper vertical plate, and vertical long holes 45 are provided in the middle of the upper vertical plate and the lower vertical plate, respectively. The upper connecting member and the lower connecting member are fixed together at an adjustable height by bolts passing through the vertical long holes 45. Considering the shortcomings brought by the rigid connection and the deformation problem during the construction and use of the aluminum plate ceiling, the connection accessory structure is made adjustable. On the one hand, in conjunction with the size adjustment of the ceiling installation construction, the height position and the left and right position can be adjusted within a certain range, so that the flatness and reliability of the ceiling system installation are guaranteed. The plastic pad is also designed as a buffer on the connection accessory structure, so that a certain buffer is provided during the construction process to avoid abnormal noise caused by slight deformation due to wind pressure, and to avoid deformation of the connection part caused by the rigid connection and affecting the appearance, and to enable subsequent adjustment of the deformation caused by the settlement of the building to maintain the flatness and beauty of the aluminum plate ceiling system.
[0035] The plastic pad is used as a shock-absorbing pad in the present invention. By arranging the shock-absorbing pad between the connecting piece and the conversion layer, a rigid connection between the connecting piece and the conversion layer is avoided. If it is a rigid connection, even a slight deformation will affect the flatness of the surface layer, resulting in partial or overall deformation affecting the appearance and safety.
[0036] like Figure 3 and Figure 4 As shown, Figure 4 It is a schematic diagram of the connection state of a wind-resistant aluminum plate ceiling system for a large space top surface of the present invention. The connecting fitting 4 is connected to the angle steel 5 by bolts, and the plastic pad 43 is between the upper connecting piece 41 and the angle steel 5. The bolts pass through the plastic pad 43 and the transverse long holes 44 of the upper connecting piece 41 respectively. The aluminum plate 3 is connected to the bottom plate of the connecting fitting 4 at the corresponding position by screws. Multiple aluminum plates 3 are spliced to form a ceiling on the top surface of a large space. In actual connection, an angle code is provided on the right-angled fold 31 of the aluminum plate 3, and screws are passed through the angle code to connect to the bottom plate of the lower connecting piece 42 in the connecting fitting 4.
[0037] By analyzing the different wind pressure differences between the upper and lower parts of the building's ceiling caused by typhoon weather and the causes of deformation and falling off of the ceiling, a rigid connection method is proposed to fix the aluminum plate ceiling. By designing special connection accessories, the connection accessories can rigidly fix the profile aluminum plate on the angle steel of the conversion layer, thereby avoiding large-area deformation of the aluminum plate caused by excessive wind pressure, and avoiding deformation and falling off caused by overlap connection in the existing technology, maintaining the installability of the ceiling system and increasing its service life.
[0038] Example 2
[0039] like Figure 5 As shown, this embodiment is an installation and construction method of a wind pressure resistant aluminum plate ceiling system for a large space top surface, and the installation and construction method includes the following steps:
[0040] The first step is to weld the base layer of the conversion layer. An aluminum plate ceiling system is designed on the top surface of the large space inside the typhoon belt building. The ceiling system uses angle brackets to adjustably fix the aluminum plate on the conversion layer. The conversion layer is welded and fixed on the top of the building as the base layer to form a construction surface. The size of a single aluminum plate is designed using BIM, and the order drawings of the aluminum plate for processing operations are output. According to the order drawings of the aluminum plate, the installation position of the angle bracket is designed, and the angle bracket is positioned at a height of 7 cm above the finished surface of the vertical high conversion layer of the aluminum plate;
[0041] The second step is to position and punch holes. According to the order drawing of the aluminum plate, the aluminum plate is processed and a hole opener is used to punch holes on the top surface according to the approximate position of the aluminum plate corner code, with a left and right deviation of 2 cm.
[0042] The third step is to install the connection accessories, design and process the connection accessories, which are composed of an upper connection piece, a lower connection piece and a plastic pad. The side of the upper connection piece is in an inverted L-shape, including an upper vertical plate and a top plate whose edges are vertically connected, and a plurality of sawtooth grooves are arranged on the inner side of the upper vertical plate, and the plurality of sawtooth grooves are arranged in parallel. The side of the lower connection piece is in an L-shape, including a lower vertical plate and a bottom plate whose edges are vertically connected, and a plurality of sawtooth grooves arranged in parallel are arranged on the inner side of the lower vertical plate. The upper connection piece and the lower connection piece are buckled with each other and the sawtooth grooves are relatively connected, and the plastic pad is fitted on the top of the top plate as a vibration damping pad; during the installation of the connection accessories, the vibration damping pad is positioned upward and fixed to the angle steel on the conversion layer;
[0043] Step 4: Level adjustment: Before the aluminum plate arrives at the site, the bottom of the aluminum alloy profile needs to be leveled with a level to meet the installation requirements after the aluminum plate arrives at the site;
[0044] The fifth step is to install and adjust the aluminum plate. Before installing the aluminum plate, verify the position of the angle code on the aluminum plate on site. If the position of the angle code is offset, reinstall the angle code on site to determine the laying position of the top aluminum plate. After determination, fix one piece first, and then insert and fix it one by one. When installing the aluminum plate, first fix the aluminum plate at the edge and fix it on both sides. Insert one side of the adjacent aluminum plate into the edge of the fixed aluminum plate so that the folded edges are aligned and connected horizontally with screws. Fix the folded edge on the other side to the angle steel of the conversion layer with an angle code. Use screws on one side to horizontally connect the adjacent aluminum plates and fix them with the angle code on one side to achieve aluminum plate splicing.
[0045] Step 6. Complete and inspect the ceiling system. After all the aluminum panels are spliced together to form a large-area ceiling, the ceiling is adjustably fixed to the transfer layer using rigid connections. Inspect its flatness and tightness of fit to ensure that the flatness is less than 0.1 / 100 and the maximum gap between adjacent aluminum panels is less than 5 cm.
[0046] The construction method of this embodiment first gives the processing drawings of the aluminum plate in a BIM manner, processes the aluminum plate profile according to the drawings, then punches holes on the aluminum plate and installs angle codes as connecting transition parts, and then processes the connecting accessories. Each connecting accessory has the same structure and can achieve left-right adjustment and up-down adjustment within a certain range. In particular, a special splicing method is used at the installation site. The aluminum plate at the edge is first fixed on both sides, and one side of the adjacent aluminum plate is inserted into the edge of the fixed aluminum plate so that the folded edges are aligned and connected horizontally with screws. The folded edges on the other side are fixed to the angle steel of the conversion layer with angle codes, and the adjacent aluminum plates are fixed horizontally with screws on one side, and the angle steel is fixed on one side to achieve aluminum plate splicing, so as to achieve the construction convenience and safety of the aluminum plate ceiling system installation, so that the installed aluminum plate can resist typhoons and avoid falling off.
[0047] The above embodiments provide detailed technical implementation details, covering the ceiling system and the construction method of the ceiling system, with the purpose of realizing the typhoon-resistant design of a specific area. By combining the fixing and fine-tuning technology, the system can significantly improve the stability and safety of the ceiling system. Users can choose a suitable implementation plan according to actual needs to maximize the use of system functions.
[0048] The contents not described in detail in this specification belong to the prior art known to professional and technical personnel in the field. Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A wind pressure resistant aluminum plate ceiling system for a large space top surface, a conversion layer is provided on the inner top surface of the large space, characterized in that: The ceiling system includes an aluminum plate, a connecting accessory structure and an angle steel, wherein a plurality of the angle steels are located in a conversion layer, wherein a base layer in the conversion layer is welded to an inner top surface of a large space of a building to form a horizontal surface, and a plurality of the aluminum plates are adjustably fixed to the angle steels through a connecting accessory structure, wherein the direction of the aluminum plates is perpendicular to the angle steels; the connecting accessory structure includes a plurality of connecting accessories connected to each aluminum plate, wherein the connecting accessory composition includes an upper connecting piece, a lower connecting piece and a plastic pad, wherein a side surface of the upper connecting piece is in an inverted L-shape, comprising an upper vertical plate and a top plate whose edges are vertically connected, wherein a plurality of sawtooth grooves are provided on the inner side of the upper vertical plate, wherein the plurality of sawtooth grooves are arranged in parallel, and a side surface of the lower connecting piece is in an L-shape, comprising a lower vertical plate and a bottom plate whose edges are vertically connected, wherein a plurality of sawtooth grooves arranged in parallel are provided on the inner side of the lower vertical plate The upper connecting piece and the lower connecting piece are buckled with each other and the serrated grooves are relatively connected. The serrated grooves at different positions are fitted to achieve the distance adjustment of the top plate and the bottom plate. The plastic pad is fitted on the top of the top plate, and a horizontal long hole is provided in the middle of the top plate and the plastic pad. The direction of the horizontal long hole is parallel to the upper vertical plate. Vertical long holes are respectively provided in the middle of the upper vertical plate and the lower vertical plate. The upper connecting piece and the lower connecting piece are fixed together at an adjustable height by bolts passing through the vertical long holes; the connecting accessories are connected to the angle steel by bolts, and the plastic pad is between the upper connecting piece and the angle steel. The bolts pass through the horizontal long holes of the plastic pad and the upper connecting piece respectively. The aluminum plate is connected to the bottom plate of the connecting accessories at the corresponding position by screws, and multiple aluminum plates are spliced to form a suspended ceiling on the top surface of a large space.
2. The wind pressure resistant aluminum plate ceiling system for large space top surface according to claim 1 is characterized in that: A clamping groove is provided at the bottom of the lower connecting piece. The clamping groove is two parallel raised strips, and the edges of adjacent strip-shaped aluminum plates are arranged in the clamping groove.
3. The wind pressure resistant aluminum plate ceiling system for large space top surface according to claim 1 is characterized in that: The serrated grooves are arranged horizontally to form a wave shape, and the upper and lower vertical plates relative to each other are buckled and tightly fitted to each other through the serrated grooves to form an integrated connection accessory that prevents sliding.
4. The wind pressure resistant aluminum plate ceiling system for large space top surface according to claim 1 is characterized in that: A plurality of the connection fittings are fixed on the same angle steel at the same intervals, and each connection fitting is connected to a protrusion on the edge of the aluminum plate.
5. The wind pressure resistant aluminum plate ceiling system for large space top surface according to claim 1 is characterized in that: The aluminum plate is an aluminum alloy flat plate with 90-degree folded edges on both sides, and a decorative wood grain is provided on the surface of the aluminum alloy flat plate. Adjacent aluminum plates are closely attached by the folded edges to achieve seamless splicing.
6. The wind pressure resistant aluminum plate ceiling system for large space top surface according to claim 5 is characterized in that: Angle codes are arranged on the aluminum alloy flat plate, one side of a plurality of the angle codes is fixed to the same side fold of the aluminum alloy flat plate with screws, and the top of the angle code is fixed to the bottom plate.
7. An installation and construction method for a wind-resistant aluminum plate ceiling system for a large space top surface, characterized in that: The installation construction method comprises the following steps: The first step is to weld the base layer of the conversion layer. An aluminum plate ceiling system is designed on the top surface of the large space inside the typhoon belt building. The ceiling system uses angle brackets to adjustably fix the aluminum plate on the conversion layer. The conversion layer is welded and fixed on the top of the building as the base layer to form a construction surface. The size of a single aluminum plate is designed using BIM, and the order drawings of the aluminum plate for processing operations are output. According to the order drawings of the aluminum plate, the installation position of the angle bracket is designed, and the angle bracket is positioned at a height of 7 cm above the finished surface of the vertical high conversion layer of the aluminum plate; The second step is to position and punch holes. According to the order drawing of the aluminum plate, the aluminum plate is processed and a hole opener is used to punch holes on the top surface according to the approximate position of the aluminum plate corner code, with a left and right deviation of 2 cm. The third step is to install the connection accessories, design and process the connection accessories, which are composed of an upper connection piece, a lower connection piece and a plastic pad. The side of the upper connection piece is in an inverted L-shape, including an upper vertical plate and a top plate whose edges are vertically connected. A plurality of sawtooth grooves are provided on the inner side of the upper vertical plate, and the plurality of sawtooth grooves are arranged in parallel. The side of the lower connection piece is in an L-shape, including a lower vertical plate and a bottom plate whose edges are vertically connected. A plurality of sawtooth grooves are arranged in parallel on the inner side of the lower vertical plate. The upper connection piece and the lower connection piece are buckled with each other and the sawtooth grooves are relatively connected. The plastic pad is fitted on the top of the top plate as a vibration damping pad. During the installation of the connection accessories, the shock-absorbing pad is positioned upward and fixed to the angle steel on the transfer layer; Step 4: Level adjustment: Before the aluminum plate arrives at the site, the bottom of the aluminum alloy profile needs to be leveled with a level to meet the installation requirements after the aluminum plate arrives at the site; Step 5: Install and adjust the aluminum plate. Before installing the aluminum plate, verify the position of the angle code on the aluminum plate on site. If the angle code is offset, reinstall the angle code on site to determine the position of the top aluminum plate. After confirming, fix one piece first and then insert and fix it later. Step 6. Complete and inspect the ceiling system. After all the aluminum panels are spliced together to form a large-area ceiling, the ceiling is adjustably fixed to the transfer layer using rigid connections. Inspect its flatness and tightness of fit to ensure that the flatness is less than 0.1 / 100 and the maximum gap between adjacent aluminum panels is less than 5 cm.
8. The installation and construction method of a wind pressure resistant aluminum plate ceiling system for a large space top surface according to claim 7 is characterized in that: In the fifth step, when installing the aluminum plate, first fix the aluminum plate at the edge by fixing it on both sides, insert one side of the adjacent aluminum plate into the edge of the fixed aluminum plate so that the folded edges are aligned and connected horizontally with screws, and fix the folded edges on the other side to the angle steel of the conversion layer with angle codes, and then use one side of screws to horizontally connect the adjacent aluminum plates and fix them, and use one side of the angle code to fix the angle steel to achieve aluminum plate splicing.
Citation Information
Patent Citations
Stone hoisting mounting hanging piece
CN113431252A
Unit assembly type suspended ceiling connection structure
CN202899393U
Suspended ceiling metal plate and suspended ceiling structure
CN209538507U
Close joint suspended ceiling connecting structure
CN211286229U
Perforated aluminum alloy closely-jointed plate connecting structure
CN219690860U