Construction method for reconstructing and expanding four-arch tunnel into double-layer tunnel

Through the construction method of the four-continuous arch tunnel reconstruction into a double-layer tunnel, combined with temporary reinforcement and advanced support, the site restrictions and construction disturbances in the reconstruction and expansion of urban tunnels have been solved, the construction efficiency and safety have been improved, and the surrounding areas have been reduced. Environmental impact.

CN118979764AActive Publication Date: 2024-11-19CHINA RAILWAY 18TH BUREAU GRP CO LTD +3
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411218392.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-02
Publication Date
2024-11-19
Estimated Expiration
2044-09-02

AI Technical Summary

Technical Problem

Urban tunnel renovation and expansion projects face problems such as site restrictions, difficulty in controlling construction disturbances, large traffic impacts and reinforcement of old tunnels. The existing technology lacks comprehensive solutions, which can easily lead to construction failure or safety hazards.

Method used

The construction method of the four-continuous arch tunnel is adopted to expand into a double-layer tunnel. By temporarily reinforcing the existing tunnel, advanced support and tunnel excavation parallel, and using support piles, combining the closed construction on one side and traffic on the other side. When passing, first dig the upper tunnel and then the lower tunnel, and apply a middle partition to make full use of the three-dimensional space.

Benefits of technology

It effectively solves the problems of site restrictions, construction deformation control and traffic impact, improves the construction efficiency of lower tunnels, prevents the development of tunnel diseases, and reduces the impact of construction disturbances on the surrounding environment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979764A_ABST
    Figure CN118979764A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of tunnel engineering, in particular to a construction method for reconstructing and expanding a four-arch tunnel into a double-layer tunnel, which comprises the following steps of: performing traffic closing construction on a third tunnel and a fourth tunnel, and using a first tunnel and a second tunnel as traffic during construction; temporary reinforcement measures are constructed in the first tunnel and the second tunnel; excavating the third tunnel to form an upper-layer tunnel; a reinforced concrete plate and a second support pile of a lower step on the right side of the tunnel are constructed for the upper-layer tunnel; a short side wall and an upper-layer tunnel secondary lining are constructed, so that the upper-layer tunnel is completely communicated; a lower-layer tunnel is excavated, and a lower-layer tunnel lining structure is constructed; and the tunnel middle partition plate is poured, and construction of the double-layer tunnel is completed. The technical problem that in the prior art, a technological method capable of achieving construction from the four aspects of surrounding site limitation, construction deformation control, construction organization arrangement and old tunnel reinforcement measures does not exist is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel engineering, and in particular to a construction method for remodeling and expanding a four-arch tunnel into a double-layer tunnel. Background Art

[0002] The tunnel renovation and expansion project refers to the reconstruction of an existing tunnel that has been in operation for many years. On the basis of the original tunnel, the tunnel cross-section is widened and its span is increased to meet the growing traffic demand in the city.

[0003] The reconstruction and expansion of urban tunnels face the following technical difficulties: (1) There are existing buildings on both sides of urban tunnels, and the site is limited, making it difficult to increase traffic capacity by widening or adding tunnels. (2) There are many buildings and dense underground pipelines around urban tunnels, so construction disturbances should be strictly controlled to reduce the impact of tunnel construction on the surrounding environment. (3) Urban tunnels have important traffic functions, and interrupting traffic for construction will have an impact on the city's economy. Therefore, roads need to be reserved during the construction process to ensure traffic operation. (4) Existing tunnels have serious diseases, which are easy to develop further under the influence of construction disturbances. Existing tunnels need to be reinforced during the construction process. However, the existing technology can only be constructed by combining traditional tunnel construction methods, and does not have a process method that can meet the four aspects of surrounding site restrictions, construction deformation control, construction organization arrangements, and old tunnel reinforcement measures. It is very easy to cause construction that does not meet the requirements or cause safety problems. Summary of the invention

[0004] The purpose of the present invention is to provide a construction method for the reconstruction and expansion of a four-arch tunnel into a double-deck tunnel, so as to solve the technical problem that the prior art does not have a process method that can meet the four aspects of surrounding site restrictions, construction deformation control, construction organization arrangement and old tunnel reinforcement measures. The specific technical scheme is as follows:

[0005] The present invention provides a construction method for renovating and expanding a four-arch tunnel into a double-layer tunnel. The existing four-arch tunnels are, from left to right, a first tunnel, a second tunnel, a third tunnel and a fourth tunnel. The construction of a single-side expansion double-layer tunnel includes the following steps:

[0006] S1: Close the third and fourth tunnels for traffic during construction, and use the first and second tunnels for traffic during the construction period;

[0007] S2: Temporary reinforcement measures are constructed in the first and second tunnels, and anchors are installed on the top of the third tunnel, the first support piles are installed on the bottom of the third tunnel, and a middle partition wall is installed on the left side of the third tunnel;

[0008] S3: Excavate the third tunnel and the fourth tunnel to form the upper tunnel, and carry out initial support and temporary support for the upper tunnel;

[0009] S4: Construct the reinforced concrete slab and the second supporting piles for the lower step on the right side of the upper tunnel;

[0010] S5: Remove the temporary support of the upper tunnel, construct the low side wall and the secondary lining of the upper tunnel, so that the upper tunnel is fully connected;

[0011] S6: excavate the lower tunnel and construct the lower tunnel lining structure;

[0012] S7: Cast the tunnel diaphragm to complete the construction of the double-deck tunnel.

[0013] A further improvement of the construction method for renovating and expanding a four-arch tunnel into a double-deck tunnel of the present invention is that, when constructing temporary reinforcement measures in the first tunnel and the second tunnel, steel supports and carbon fiber cloth protective measures are constructed on the inner wall of the second tunnel; and carbon fiber cloth is constructed on the inner wall of the first tunnel.

[0014] A further improvement of the construction method for expanding and renovating a four-arch tunnel into a double-deck tunnel of the present invention is that when the first supporting pile is constructed at the bottom of the third tunnel, a reinforced concrete pile is cast per meter at the bottom of the third tunnel, and anchoring steel bars are reserved at the pile heads of the concrete piles and supporting beams are cast.

[0015] A further improvement of the construction method for the reconstruction and expansion of a four-arch tunnel into a double-deck tunnel of the present invention is that, when performing S3, before excavating the third tunnel and the fourth tunnel to form an upper tunnel, step S301 is performed, a plurality of support pipes are inserted at intervals along the axial direction of the tunnel above the top surface of the upper tunnel to be constructed to form a pipe shed, a steel cage is inserted into the support pipe, and cement slurry is injected into the support pipe.

[0016] A further improvement of the construction method for the reconstruction and expansion of a four-arch tunnel into a double-deck tunnel of the present invention is that, when performing initial support and temporary support of the upper tunnel, step S302 is performed to excavate the right pilot pit of the upper tunnel. When the right pilot pit has advanced 15 to 20 m, the lining structure of the fourth tunnel within the right pilot pit is removed, and a second initial support is performed, and temporary support is performed in the upper tunnel.

[0017] A further improvement of the construction method for the reconstruction and expansion of a four-arch tunnel into a double-deck tunnel of the present invention is that, when performing the initial support, step S303 is performed to excavate the left pilot pit of the upper tunnel, and when the right pilot pit advances 15 to 20 m, the lining structure of the third tunnel within the left pilot pit is removed, and the third initial support is performed; step S304 is performed to excavate the lower step of the right pilot pit and perform the fourth initial support of the area around the lower step.

[0018] A further improvement of the construction method of the four-arch tunnel reconstruction and expansion into a double-layer tunnel of the present invention is that when constructing the low side wall and the secondary lining of the upper tunnel, the low side wall is constructed at a distance of no more than 35m from the heading face, and the secondary lining of the upper tunnel adopts reinforced waterproof concrete with a thickness of 70cm to 150cm.

[0019] A further improvement of the construction method of the present invention for renovating and expanding a four-arch tunnel into a double-layer tunnel is that when excavating the lower tunnel, step S601 is performed, the lower tunnel is excavated in the order of upper, middle and lower layers, and initial support and temporary support of the lower tunnel are performed.

[0020] A further improvement of the construction method of the present invention for remodeling and expanding a four-arch tunnel into a double-layer tunnel is that, when constructing the lower tunnel lining structure, step S602 is performed to dismantle the temporary support of the lower tunnel in sections; and then step S603 is performed to cast the lower tunnel invert and secondary lining.

[0021] A further improvement of the construction method for remodeling and expanding a four-arch tunnel into a double-deck tunnel of the present invention is that step S6 also includes: S604, pouring the lower tunnel invert filling; S605, pouring the lower tunnel side wall.

[0022] The application of the technical solution of the present invention has the following beneficial effects:

[0023] The construction method for renovating and expanding a four-arch tunnel into a double-deck tunnel of the present invention makes full use of the three-dimensional space by renovating and expanding the existing four-arch tunnel in the city into a double-deck tunnel, solves the site limitation problem in the renovation and expansion of the urban tunnel, and prevents the continued development of the disease of the existing tunnel by temporarily reinforcing the existing tunnel; and in the renovation and expansion construction, the use of advance support and tunnel excavation in parallel, the use of support piles as support and other methods well controls the disturbance of the construction and the impact on the surrounding environment; by simultaneously carrying out closed construction on one side and traffic on the other side, the impact of tunnel closure on urban traffic during the renovation and expansion construction of the urban tunnel is solved; by the method of first excavating the upper tunnel, then excavating the lower tunnel, and then applying the middle partition, the working space for excavation of the lower tunnel is increased, and the construction efficiency of the lower tunnel is improved.

[0024] In addition to the above-described purposes, features and advantages, the present invention has other purposes, features and advantages. The present invention will be further described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] The drawings constituting a part of this application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:

[0026] Figure 1It is a flow chart of the construction method of the present invention for remodeling and expanding a four-arch tunnel into a double-deck tunnel;

[0027] Figure 2 It is a schematic diagram of temporary reinforcement measures and anchor bolt construction in the construction method of the present invention for remodeling and expanding a four-arch tunnel into a double-deck tunnel;

[0028] Figure 3 It is a schematic diagram of a middle partition wall of a construction method for remodeling and expanding a four-arch tunnel into a double-deck tunnel according to the present invention;

[0029] Figure 4 It is a schematic diagram of a pipe shed of a construction method for remodeling and expanding a four-arch tunnel into a double-deck tunnel according to the present invention;

[0030] Figure 5 It is a schematic diagram of excavating a right pilot pit in the construction method of the present invention for remodeling and expanding a four-arch tunnel into a double-deck tunnel;

[0031] Figure 6 It is a schematic diagram of excavating a left pilot pit in the construction method of the present invention for remodeling and expanding a four-arch tunnel into a double-deck tunnel;

[0032] Figure 7 It is a schematic diagram of applying the fourth initial support of the construction method of the invention for remodeling and expanding a four-arch tunnel into a double-deck tunnel;

[0033] Figure 8 It is a schematic diagram of the construction of a reinforced concrete slab in the construction method of the present invention for remodeling and expanding a four-arch tunnel into a double-deck tunnel;

[0034] Fig. 9 It is a schematic diagram of constructing the second supporting piles in the construction method of the invention for remodeling and expanding a four-arch tunnel into a double-deck tunnel;

[0035] Fig.10 It is a schematic diagram of removing the temporary support of the upper tunnel in the construction method of the present invention for remodeling and expanding a four-arch tunnel into a double-layer tunnel;

[0036] Fig.11 It is a schematic diagram of constructing a low side wall in the construction method of the invention for remodeling and expanding a four-arch tunnel into a double-deck tunnel;

[0037] Fig.12 It is a schematic diagram of the construction of secondary lining of the construction method of the present invention for remodeling and expanding a four-arch tunnel into a double-layer tunnel;

[0038] Fig.13 It is a schematic diagram of excavating a lower tunnel in the construction method of the present invention for remodeling and expanding a four-arch tunnel into a double-deck tunnel;

[0039] Fig.14 It is a schematic diagram of the construction invert of the construction method of the present invention for remodeling and expanding a four-arch tunnel into a double-deck tunnel;

[0040] Fig.15 It is a schematic diagram of the construction invert filling of the construction method of the invention for remodeling and expanding a four-arch tunnel into a double-layer tunnel;

[0041] Fig.16 It is a schematic diagram of the construction side wall of the construction method of the present invention for remodeling and expanding a four-arch tunnel into a double-deck tunnel;

[0042] Fig.17 It is a schematic diagram of a partition plate during construction of a construction method for remodeling and expanding a four-arch tunnel into a double-deck tunnel according to the present invention;

[0043] Fig.18 It is a schematic diagram of the construction method of the present invention for converting and expanding a four-arch tunnel into a double-deck tunnel after the construction is completed.

[0044] Among them, 1.1, steel support and carbon fiber cloth protection measures; 1.2, carbon fiber cloth; 2, anchor rod; 3.1, first support pile; 3.2, second support pile; 4, support beam; 5, middle partition wall; 6, initial support of upper tunnel; 6.1, first initial support; 6.2, second initial support; 6.3, third initial support; 6.4, fourth initial support; 7, pipe shed; 8, temporary support of upper tunnel; 9, reinforced concrete slab; 10, low side wall; 11, secondary lining; 12, initial support of lower tunnel; 13, invert; 14, invert filling; 15, side wall; 16, middle partition; 17, right pilot pit; 18, left pilot pit; 19, upper tunnel; 20, lower tunnel; 21, soil. DETAILED DESCRIPTION

[0045] The embodiments of the present invention are described in detail below with reference to the accompanying drawings.

[0046] See also Figures 1 to 18 As shown, a construction method for converting and expanding a four-arch tunnel into a double-deck tunnel, the existing four-arch tunnels are, from left to right, the first tunnel, the second tunnel, the third tunnel and the fourth tunnel, and the construction of the single-side expansion double-deck tunnel includes the following steps:

[0047] S1: Close the third and fourth tunnels for traffic during construction, and use the first and second tunnels for traffic during the construction period;

[0048] S2: Figure 1 and Figure 2 As shown, temporary reinforcement measures are constructed in the first tunnel and the second tunnel, and anchor rods 2 are installed on the top of the third tunnel, first support piles 3.1 are installed on the bottom of the third tunnel, and a middle partition wall 5 is installed on the left side of the third tunnel;

[0049] S3: Figure 5As shown, the third tunnel and the fourth tunnel are excavated to form an upper tunnel 19, and initial support and temporary support 8 for the upper tunnel are implemented;

[0050] S4: Figure 8 and Fig. 9 As shown, the upper tunnel is constructed with a reinforced concrete slab 9 and a second support pile 3.2 for the lower step on the right side of the tunnel;

[0051] S5: Figure 10 to Figure 12 As shown, the temporary support 8 of the upper tunnel is removed, and the low side wall 10 and the secondary lining 11 of the upper tunnel are constructed, so that the upper tunnel 19 is completely connected;

[0052] S6: Fig.13 As shown, the lower tunnel 20 is excavated and the lower tunnel lining structure is constructed;

[0053] S7: Fig.17 As shown, the tunnel diaphragm 16 is poured to complete the construction of the double-deck tunnel.

[0054] Specifically, step S1 also includes: separating the construction area from the traffic area by construction fencing, establishing a traffic diversion channel, and directing the traffic flow into the first tunnel and the second tunnel for temporary passage. The anchor rod 2 adopts a hollow grouting anchor rod with a diameter of 25 mm and a length of 350 mm. After the anchor rod is installed, grouting is performed. The number of anchor rods 2 is multiple, and the multiple anchor rods 2 are arranged in a divergent manner in the circumferential direction and longitudinally with a spacing of 100 mm. Through the setting of the anchor rod 2, temporary support and the first support pile 3.1, the third tunnel can be kept stable during the construction process to avoid problems such as tunnel deformation or collapse.

[0055] In this embodiment, Figure 2 As shown, the second tunnel and the third tunnel are the main tunnels of the existing tunnel, and the first tunnel and the fourth tunnel are the auxiliary tunnels of the existing tunnel. Figure 2 and Figure 5As shown, the first tunnel, the second tunnel, the third tunnel and the fourth tunnel are surrounded by soil 21. Since the diameter of the double-layer tunnel after expansion will increase, a part of the surrounding soil 21 needs to be excavated during the expansion process. When constructing the middle partition wall 5, the middle partition wall 5 is first built on the left side of the main hole of the third tunnel, and the first initial support 6.1 is applied to the outside of the middle partition wall 5, and C25 plain concrete is filled inside the middle partition wall 5. The first initial support 6.1 adopts the form of shotcrete + steel mesh + steel support + anchor rod 2. First, 4 cm thick shotcrete is wet sprayed, steel mesh is hung, steel support is erected, anchor rod 2 is constructed, and finally, concrete is sprayed layer by layer to the designed thickness. The initial support of each stage is closed into a ring in time after construction. The shotcrete is early-strength wet shotcrete C25 shotcrete with a thickness of 31 cm; the steel support is I-beam with a longitudinal spacing of 0.5 m; the anchor rod 2 is a hollow grouting anchor rod 22 with a diameter of 25 mm and a length of 350 cm, with a circumferential spacing of 100 cm and a longitudinal spacing of 50 cm, arranged in a divergent manner.

[0056] Preferably, Figure 2 and Figure 3 As shown, when temporary reinforcement measures are constructed in the first tunnel and the second tunnel, steel support and carbon fiber cloth protective measures 1.1 are constructed on the inner wall of the second tunnel; and carbon fiber cloth 1.2 is constructed on the inner wall of the first tunnel. Carbon fiber cloth 1.2 can fix the structure of the tunnel into a whole, so that the first tunnel and the second tunnel are respectively stressed as a whole. The steel support can further enhance the strength of the main tunnels of the first tunnel and the second tunnel, avoiding deformation of the tunnel and potential safety hazards during the construction of the double-layer tunnel.

[0057] Preferably, when the first support pile 3.1 is constructed at the bottom of the third tunnel, one reinforced concrete pile is cast per meter at the bottom of the third tunnel, and anchoring steel bars are reserved at the pile heads of the concrete piles and a joist 4 is cast. The joist 4 fixes all the reinforced concrete piles into a force-bearing whole, so that they have a certain strength to support the tunnel. In this embodiment, the diameter of the reinforced concrete pile is 800 mm. When constructing the joist 4, it should be constructed section by section and formed as soon as possible to ensure the safety and stability of the initial support of the tunnel. The meter is an engineering measurement used to count or describe irregular strip or linear projects.

[0058] Preferably, Figure 5 and Figure 6 As shown, step S3 includes:

[0059] S301. Insert multiple support pipes at intervals along the axial direction of the tunnel above the top surface of the upper tunnel 19 to be constructed to form a pipe shed 7, insert a steel cage into the support pipe, and inject cement slurry into the support pipe. Specifically, the form of the pipe shed 7 is that a hot-rolled seamless steel pipe with a diameter of 159 mm is used at the entrance of the tunnel, and a hot-rolled seamless steel pipe with a diameter of 89 mm is used after entering the tunnel. After the steel pipe is in place, a steel cage is placed and cement slurry is injected.

[0060] S302, excavate the right pilot pit 17 of the upper tunnel 19. When the right pilot pit 17 advances 15 to 20 meters, remove the lining structure of the fourth tunnel within the right pilot pit 17, and implement the second initial support 6.2, and implement temporary support in the upper tunnel 19. The temporary support adopts the form of I-beam + shotcrete. The shotcrete adopts early strength wet spray C25 shotcrete with a thickness of 22 cm. The steel support adopts I-beam with a longitudinal spacing of 0.5 m.

[0061] S303, excavate the left pilot pit 18 of the upper tunnel 19, when the right pilot pit 17 advances 15-20m, remove the lining structure of the third tunnel within the left pilot pit 18, and implement the third initial support 6.3;

[0062] S304, excavate the lower step of the right pilot pit 17 and construct the fourth initial support 6.4 in the area around the lower step. The tunnel excavation method can adopt the non-explosive excavation method, strictly control the under-excavation and minimize the over-excavation. The three links of excavation, support and concrete spraying in the construction process should be closely followed, and the initial support should be implemented in time to form a closed circle in the tunnel body as soon as possible. The method of dismantling the lining structure of the existing tunnel can adopt the mechanical crushing method or the mechanical cutting method. The demolition should be as flat as possible to provide a tunnel trolley walking surface for the subsequent upper tunnel lining construction. The upper tunnel initial support 6 includes the first initial support 6.1, the second initial support 6.2, the third initial support 6.3 and the fourth initial support 6.4.

[0063] Preferably, Fig.11 As shown, when constructing the short side wall 10 and the secondary lining 11 of the upper tunnel, the short side wall 10 is constructed at a distance of no more than 35m from the heading face, and the secondary lining 11 of the upper tunnel adopts reinforced waterproof concrete with a thickness of 70cm to 150cm. When constructing the short side wall 10, the lining short side wall 10 should be constructed in a timely manner according to the surrounding rock measurement and monitoring conditions, and after the initial support deformation is stable. And according to the surrounding rock monitoring conditions, the secondary lining 11 of the upper tunnel should be constructed in a timely manner after the initial support deformation of the tunnel is basically stable.

[0064] Step S6 includes:

[0065] S601, excavate the lower tunnel 20 in the order of upper, middle and lower layers, that is, Fig.13 Excavation is carried out in the order of Ⅰ, Ⅱ, and Ⅲ. Fig.14 and Fig.15 As shown, initial support 12 for the lower tunnel and temporary support for the lower tunnel are implemented.

[0066] S602, dismantle temporary support of lower tunnel in sections;

[0067] S603, such as Fig.13 and Fig.14 As shown, the lower tunnel invert 13 and the secondary lining 11 are cast.

[0068] S604, such as Fig.15 As shown, pouring the lower tunnel invert filling 14;

[0069] S605, such as Fig.16 As shown, the lower tunnel side wall 15 is cast.

[0070] The lower tunnel lining structure includes a lower tunnel invert 13, a secondary lining 11, a lower tunnel invert filling 14 and a lower tunnel side wall 15. The invert 13 of the lower tunnel is in the form of 100 cm thick, and the model is C35 reinforced waterproof concrete. The side wall 15 of the lower tunnel is in the form of 80 cm thick, and the model is C35 reinforced waterproof concrete. The middle partition 16 is in the form of 100 cm thick, and the model is C35 reinforced waterproof concrete. After the construction of the middle partition 16 is completed, the right tunnel can be divided into two layers, the upper tunnel 19 and the lower tunnel 20 are completed, and then the left double-layer tunnel is constructed using the same steps, and finally the middle partition walls 5 constructed on both sides are connected to form a complete middle partition wall 5.

[0071] The construction method for renovating and expanding a four-arch tunnel into a double-deck tunnel of the present invention makes full use of the three-dimensional space by renovating and expanding the existing four-arch tunnel in the city into a double-deck tunnel, solves the site limitation problem in the renovation and expansion of the urban tunnel, and prevents the continued development of the disease of the existing tunnel by temporarily reinforcing the existing tunnel; and in the renovation and expansion construction, the use of advance support and tunnel excavation in parallel, the use of support piles as support and other methods well controls the disturbance of the construction and the impact on the surrounding environment; by simultaneously carrying out closed construction on one side and traffic on the other side, the impact of tunnel closure on urban traffic during the renovation and expansion construction of the urban tunnel is solved; by the method of first excavating the upper tunnel, then excavating the lower tunnel 20, and then applying the middle partition 16, the working space for excavation of the lower tunnel is increased, and the construction efficiency of the lower tunnel is improved.

[0072] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A construction method for renovating and expanding a four-arch tunnel into a double-deck tunnel, wherein the existing four-arch tunnels are, from left to right, a first tunnel, a second tunnel, a third tunnel and a fourth tunnel, characterized in that: The construction of a double-deck tunnel with a single-side expansion includes the following steps: S1: Close the third and fourth tunnels for traffic during construction, and use the first and second tunnels for traffic during the construction period; S2: temporary reinforcement measures are constructed in the first tunnel and the second tunnel, anchor rods (2) are installed on the top of the third tunnel, first support piles (3.1) are installed on the bottom of the third tunnel, and a middle partition wall (5) is installed on the left side of the third tunnel; S3: excavating the third tunnel and the fourth tunnel to form an upper tunnel (19), and performing initial support and temporary support for the upper tunnel (8); S4: construct a reinforced concrete slab (9) and a second supporting pile (3.2) on the right side of the tunnel for the upper tunnel; S5: dismantle the temporary support (8) of the upper tunnel, construct the low side wall (10) and the secondary lining (11) of the upper tunnel, and make the upper tunnel (19) completely connected; S6: excavating the lower tunnel (20) and constructing the lower tunnel lining structure; S7: Casting the tunnel middle partition (16) to complete the construction of the double-deck tunnel.

2. The construction method for remodeling and expanding a four-arch tunnel into a double-deck tunnel according to claim 1, characterized in that: When constructing temporary reinforcement measures in the first tunnel and the second tunnel, it includes constructing steel supports and carbon fiber cloth protection measures (1.1) on the inner wall of the second tunnel; and constructing carbon fiber cloth (1.2) on the inner wall of the first tunnel.

3. The construction method for remodeling and expanding a four-arch tunnel into a double-deck tunnel according to claim 1, characterized in that: When constructing the first supporting pile (3.1) at the bottom of the third tunnel, a reinforced concrete pile is cast per meter at the bottom of the third tunnel, and anchoring steel bars are reserved at the pile heads of the concrete piles and a supporting beam (4) is cast.

4. The construction method for remodeling and expanding a four-arch tunnel into a double-deck tunnel according to claim 1, characterized in that: When performing S3, before excavating the third tunnel and the fourth tunnel to form the upper tunnel, perform step S301, insert a plurality of support pipes at intervals along the axial direction of the tunnel above the top surface of the upper tunnel (19) to be constructed to form a pipe shed (7), insert a steel cage into the support pipe, and inject cement slurry into the support pipe.

5. The construction method for remodeling and expanding a four-arch tunnel into a double-deck tunnel according to claim 4, characterized in that: When the initial support and the temporary support (8) of the upper tunnel are applied, step S302 is performed to excavate the right pilot pit (17) of the upper tunnel (19). When the right pilot pit (17) has advanced 15 to 20 m, the lining structure of the fourth tunnel within the right pilot pit (17) is removed, and the second initial support (6.2) is applied, and temporary support is applied in the upper tunnel (19).

6. The construction method for remodeling and expanding a four-arch tunnel into a double-deck tunnel according to claim 5, characterized in that: When performing the initial support, step S303 is performed to excavate the left pilot pit (18) of the upper tunnel (19). When the right pilot pit (17) has advanced 15 to 20 m, the lining structure of the third tunnel within the left pilot pit (18) is removed and the third initial support (6.3) is performed; step S304 is performed to excavate the lower step of the right pilot pit and perform the fourth initial support (6.4) in the area around the lower step.

7. The construction method for remodeling and expanding a four-arch tunnel into a double-deck tunnel according to claim 4, characterized in that: When constructing the short side wall (10) and the secondary lining (11) of the upper tunnel, the short side wall (10) is constructed at a distance of no more than 35m from the tunnel face, and the secondary lining (11) of the upper tunnel is made of reinforced waterproof concrete with a thickness of 70cm to 150cm.

8. The construction method for remodeling and expanding a four-arch tunnel into a double-deck tunnel according to claim 1, characterized in that: When excavating the lower tunnel (20), step S601 is performed to excavate the lower tunnel (20) in the order of upper, middle and lower layers, and to perform initial support (12) and temporary support for the lower tunnel.

9. The construction method for remodeling and expanding a four-arch tunnel into a double-deck tunnel according to claim 8, characterized in that: When constructing the lower tunnel lining structure, step S602 is performed to dismantle the temporary support of the lower tunnel in sections; then step S603 is performed to cast the lower tunnel invert (13) and the secondary lining (11).

10. The construction method for remodeling and expanding a four-arch tunnel into a double-deck tunnel according to claim 9, characterized in that: Step S6 also includes: S604, pouring the lower tunnel invert filling (14); S605, pouring the lower tunnel side wall (15).

Citation Information

Patent Citations

  • Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel

    CN101737061A

  • Excavation design construction method for four-arch tunnel

    CN114263467A

  • Double-hole tunnel formed by expanding single-hole tunnel and construction method of double-hole tunnel

    CN115199292A

  • In-situ extension construction method for multi-arch tunnel

    CN115653618A

  • Construction method for two arches tunnel

    KR100752285B1