Composite beam segment construction method and cable-stayed bridge composite beam construction method
By using precast steel box girders and connecting structures, combined with the hoisting of concrete slabs, rapid and economical construction of composite beams for cable-stayed bridges was achieved, solving the problems of long construction cycles and high costs, simplifying the construction process, and reducing operational difficulty and the probability of errors.
Patent Information
- Application Number
- CN202411409356.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-10
- Publication Date
- 2024-11-22
AI Technical Summary
In existing technologies, the construction method of composite beams for cable-stayed bridges requires the separate fabrication and installation of multiple separate steel boxes, crossbeams and longitudinal beams on site, which results in a complicated construction process, long construction period, high cost, and high requirements for construction organization and management.
By prefabricating the first steel box girder, the second steel box girder, and the connecting structure in advance, and combining the prefabrication and hoisting of concrete slabs, the construction of the composite beam segment is completed in one hoisting operation, which simplifies on-site operations and reduces the probability of human error.
It shortened the construction period, reduced construction costs and personnel requirements, improved construction efficiency, simplified the construction process, and reduced operational difficulty and the probability of errors.
Smart Images

Figure CN118997015A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of construction of composite beams of cable-stayed bridges, and in particular to a composite beam segment construction method and a composite beam construction method for cable-stayed bridges. Background Art
[0002] A cable-stayed bridge is a bridge structure that relies on cables on the bridge tower to support the bridge deck. Its design allows for a larger span. In the design of cable-stayed bridges, the composite beam structure is popular because it combines the high strength of steel with the compressive properties of concrete. In order to reduce the weight of the structure and improve construction efficiency, the composite beams of modern cable-stayed bridges usually use separate steel boxes and are connected by cross beams to enhance integrity. For specific structures, please refer to Figure 1 .
[0003] This design brings a series of challenges during the construction process. As the span of the cable-stayed bridge increases, the number of composite beam segments and cables required also increases. In addition, the increase in the number of crossbeams significantly increases the complexity of construction. At present, the construction process of composite beams includes the installation of steel box girders, the installation of crossbeams in sequence, the installation of bridge decks, and the final tensioning of the cable stays. This process places higher demands on construction machinery and personnel. As the scale of the project expands, the number of construction machinery and personnel required also increases. As the number of construction links increases, the coordination work during the construction process becomes more complicated, requiring more sophisticated construction planning and management, which not only increases the construction cost, but also places higher demands on construction organization and management.
[0004] Moreover, the large number of composite beam segments and cable stays that need to be installed, coupled with the increase in the number of crossbeams, significantly extends the construction period, which may lead to delays in the construction project and cost overruns.
[0005] Therefore, it is necessary to seek a safe, applicable, economical, fast and efficient composite beam construction method to effectively shorten the composite beam construction period of cable-stayed bridges, reduce construction equipment and personnel, and reduce construction costs. Summary of the invention
[0006] The purpose of the present invention is to provide a method for constructing a segment of a composite beam and a method for constructing a composite beam of a cable-stayed bridge, so as to solve the technical problem in the prior art that when the composite beam of the cable-stayed bridge adopts a structure in which a separate steel box is adopted and connected by a cross beam, the traditional construction method requires on-site production and installation of multiple separate steel boxes, multiple cross beams, and longitudinal beams for connecting the multiple cross beams, which results in a cumbersome construction process and a long construction period.
[0007] In order to solve the above technical problems, the present invention adopts the following technical solutions:
[0008] In a first aspect, based on the technical problems solved above, the present invention discloses a method for constructing a composite beam segment, wherein the composite beam segment comprises a first steel box beam and a second steel box beam, wherein the first steel box beam and the second steel box beam are fixedly connected by a connecting structure; during construction, the method comprises the following steps:
[0009] S1. Prefabricate the first steel box girder, the second steel box girder and the connecting structure in advance and transport them to the construction site;
[0010] S2. Lift and fix the first steel box girder and the second steel box girder to the designed positions respectively;
[0011] S3, hoisting the connection structure between the first steel box girder and the second steel box girder, and fixing the two sides of the connection structure to the first steel box girder and the second steel box girder respectively;
[0012] S4, installing the stay cables on the composite beam segment and performing the first tensioning operation;
[0013] S5, prefabricate the overlying concrete slab of the composite beam segment, and hoist the concrete slab to the position corresponding to the composite beam segment;
[0014] S6. Perform a second tensioning operation on the inclined cable to complete the construction of the composite beam segment.
[0015] In this solution, the first steel box girder and the second steel box girder, the connecting structure and the concrete slab are all prefabricated in advance, which is conducive to shortening the construction period on site. Moreover, the installation is simple, and only one lifting machine is needed to complete the construction of the entire composite beam segment. The operator only needs to perform simple lifting and fixing work on site, which reduces the construction difficulty of the operator and the probability of error of the operator, which is conducive to saving construction costs.
[0016] Preferably, in step S3, the connection structure comprises a plurality of cross beams, both ends of each cross beam are respectively fixedly connected to the first steel box beam and the second steel box beam on the opposite side, and a longitudinal beam is fixed between each cross beam;
[0017] During construction, first arrange the beams in parallel according to the designed intervals, and then fix the longitudinal beams between the beams to keep the intervals between the beams relatively unchanged.
[0018] This enables prefabrication of the connecting structure and on-site hoisting, which is beneficial to shortening the construction period on site, reducing the complexity of construction, reducing the probability of operator error, and helping to save construction costs.
[0019] In order to facilitate the fixed connection of the two ends of each cross beam with the opposite side of the first steel box beam and the second steel box beam, preferably, a plurality of reserved parts are fixed on the opposite side of the first steel box beam and the second steel box beam, and the two ends of each cross beam are fixedly connected with the corresponding reserved parts fixed on the first steel box beam and the second steel box beam;
[0020] During construction, firstly, each reserved part is fixed to the opposite side of the first steel box girder and the second steel box girder according to the designed interval, and then both ends of each cross beam are fixedly connected to the corresponding reserved part.
[0021] During construction, hoisting multiple cross beams and longitudinal beams as a whole can also help shorten the construction period on site. The installation is simple and the construction of the connecting structure can be completed using the same hoisting machine. Operators only need to perform simple hoisting and fixing work on site, which reduces the construction difficulty and error probability of operators and helps save construction costs.
[0022] In a second aspect, the present invention further discloses a method for constructing a cable-stayed bridge composite beam, wherein the composite beam comprises a plurality of composite beam segments, and the composite beam segment construction method is used to sequentially construct the composite beam segments in accordance with the sequence of the composite beam segments, comprising the following steps:
[0023] A1. Operate the hoisting machine to lift the first composite beam segment in the composite beam, i=1, and perform composite beam segment construction of the i-th segment;
[0024] A2. After completing the construction of the i-th section, operate the hoisting machinery to move forward to the predetermined position and hoist the first steel box girder of the i+1-th section to the designed position;
[0025] A3. After the hoisting of the first steel box girder of the i+1th section is completed, the first steel box girder of the i+1th section and the first steel box girder of the ith section are welded;
[0026] A4. Operate the hoisting machinery to continue hoisting the second steel box girder of the i+1th section to the designed position, and connect the second steel box girder of the i+1th section with the second steel box girder of the ith section by welding;
[0027] A5. Operate the lifting machinery to lift the connection structure of the i+1 segment, and weld it to the first steel box girder and the second steel box girder of the i+1 segment respectively, and carry out the composite beam segment construction of the i+1 segment;
[0028] A6. Carry out the first tensioning operation of the cable corresponding to the i+1th segment;
[0029] A7. Use a lifting machine to lift the concrete slab corresponding to the i+1th section, and perform wet joint pouring between the concrete slabs of the i+1th section and the ith section;
[0030] A8. Carry out the second tensioning operation of the corresponding inclined cable of the i+1 segment. After reaching the designed tensioning stress, complete the construction of the composite beam segment of the i+1 segment;
[0031] A9, taking the composite beam of the i+1th segment as the new composite beam of the ith segment, i.e., setting i=i+1, and returning to step A2;
[0032] A10. Repeat steps A2 to A9 until all composite beam segments are constructed.
[0033] When the composite beam of the cable-stayed bridge adopts a structure in which a separate steel box is connected by a crossbeam, the first steel box beam and the second steel box beam of each segment, the connection structure and the concrete slab are prefabricated in advance, which is beneficial to shorten the construction period on site. The installation is simple, and only one lifting machine is needed to complete the construction of the entire composite beam segment. The operator only needs to perform simple lifting and fixing work on site, which reduces the construction difficulty of the operator and the probability of error of the operator, which is beneficial to saving construction costs.
[0034] This solution not only solves the problem of complex construction steps and heavy workload of composite beams of this structural form, but also saves the number of workers, costs and construction period.
[0035] Preferably, in step A5, the connection structure of the i+1th segment includes a plurality of cross beams, a plurality of reserved parts are respectively fixed on opposite sides of the first steel box beam and the second steel box beam of the i+1th segment, two ends of each cross beam of the i+1th segment are respectively fixedly connected to the corresponding reserved parts fixed on the first steel box beam and the second steel box beam of the i+1th segment, and a longitudinal beam is fixed between each cross beam of the i+1th segment;
[0036] The steps of prefabricating the connection structure of the i+1 segment are: firstly arranging the cross beams of the i+1 segment in parallel according to the designed intervals, and then fixing the longitudinal beams of the i+1 segment between the cross beams of the i+1 segment to keep the intervals between the cross beams of the i+1 segment relatively unchanged, and at the same time, fixing the reserved parts to the opposite sides of the first steel box beam and the second steel box beam of the i+1 segment according to the designed intervals;
[0037] During on-site construction, after using a lifting machine to lift the connection structure of the i+1th segment to the designed position, the two ends of each beam of the i+1th segment are welded to the corresponding reserved parts, so as to realize the welding of the connection structure of the i+1th segment with the first steel box girder and the second steel box girder of the i+1th segment.
[0038] The present invention has the following beneficial effects: in the present invention, the first steel box girder, the second steel box girder and the connecting structure, as well as the concrete slab in the composite beam segment are all prefabricated in advance, which is beneficial to shortening the construction period on site, and the installation is simple, and only one lifting machine is needed to complete the construction work of the entire composite beam segment. The operator only needs to perform simple lifting and fixing work on site, which reduces the construction difficulty of the operator, and also reduces the probability of error of the operator, which is beneficial to saving construction costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] In order to make the purpose, technical solution and advantages of the invention more clear, the present invention will be further described in detail below with reference to the accompanying drawings, in which:
[0040] Figure 1 It is a structural schematic diagram of a separated steel box-concrete composite beam cable-stayed bridge in the prior art.
[0041] Figure 2 It is a top view of a composite beam segment of the present invention.
[0042] Figure 3 It is a cross-sectional view of a composite beam segment of the present invention.
[0043] Figure 4 This is a schematic diagram of a preferred structure of the connection structure of the present invention.
[0044] Figure 5 It is a schematic diagram of the construction process of the composite beam of the present invention.
[0045] Figure 6 It is a schematic diagram of the construction process of the composite beam of the present invention.
[0046] Explanation of the reference numerals: 100, composite beam; 101, composite beam segment; 102, first steel box beam; 103, second steel box beam; 104, connection structure; 105, inclined cable; 106, concrete slab; 107, lifting machinery; 108, cross beam; 109, longitudinal beam; 110, reserved parts. DETAILED DESCRIPTION
[0047] To make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0048] It should be noted that similar numbers and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in the subsequent drawings. In the description of the present invention, it should be noted that the orientation or position relationship indicated by the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. is based on the orientation or position relationship shown in the drawings, or the orientation or position relationship in which the invention product is usually placed when used, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation of the present invention. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance. In addition, the terms "horizontal", "vertical", etc. do not mean that the components are absolutely horizontal or suspended, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted. In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0049] The invention can be applied to the construction of composite beams of cable-stayed bridges, and is particularly suitable for the construction of composite beams of cable-stayed bridges when the composite beams adopt a structure in which separated steel boxes are used and connected by cross beams.
[0050] The present invention solves the technical problem in the prior art that when the composite beams of the cable-stayed bridge adopt a structure in which separate steel boxes are used and connected by cross beams, the traditional construction method requires on-site production and installation of multiple separate steel boxes, multiple cross beams, and longitudinal beams for connecting the multiple cross beams, which makes the construction process complicated and leads to a long construction period.
[0051] See also Figure 1 , is a schematic diagram of a separated steel box-concrete composite beam 100 cable-stayed bridge, including a composite beam 100 and a cable 105. The composite beam 100 includes a plurality of composite beam segments 101, and each composite beam segment 101 is respectively fixed with a cable 105; a concrete slab 106 is paved on the top surface of the composite beam 100.
[0052] Based on the technical problems solved above, the present invention discloses a composite beam segment construction method and a construction method for composite beams of cable-stayed bridges using the composite beam segment construction method.
[0053] See also Figure 2 and Figure 3 The composite beam segment 101 includes a first steel box beam 102 and a second steel box beam 103 , and the first steel box beam 102 and the second steel box beam 103 are fixedly connected via a connecting structure 104 .
[0054] The construction of the composite beam segment 101 includes the following steps:
[0055] S1, prefabricate the first steel box girder 102, the second steel box girder 103 and the connection structure 104 in advance and transport them to the construction site;
[0056] S2, hoisting and fixing the first steel box girder 102 and the second steel box girder 103 to the designed positions respectively;
[0057] S3, hoisting the connection structure 104 between the first steel box girder 102 and the second steel box girder 103, and fixing both sides of the connection structure 104 to the first steel box girder 102 and the second steel box girder 103 respectively;
[0058] See also Figure 2 The connection structure 104 includes a plurality of cross beams 108, and the two ends of each cross beam 108 are respectively fixedly connected to the first steel box beam 102 and the second steel box beam 103 on the opposite side, and a longitudinal beam 109 is fixed between each cross beam 108; during construction, each cross beam 108 is first arranged in parallel according to the designed interval, and then the longitudinal beam 109 is fixed between each cross beam 108 to keep the interval position between each cross beam 108 relatively unchanged; in this way, the connection structure 104 can be prefabricated and hoisted on site, which is conducive to shortening the construction period on site, reducing the complexity of construction, reducing the probability of operator error, and saving construction costs;
[0059] S4, installing the stay cable 105 on the composite beam segment 101, and performing the first tensioning operation;
[0060] S5, prefabricate the overlying concrete slab 106 of the composite beam segment 101, and hoist the concrete slab 106 to a position corresponding to the composite beam segment 101;
[0061] S6. Perform a second tensioning operation on the stay cable 105 to complete the construction of the composite beam segment 101.
[0062] In this solution, the first steel box girder 102 and the second steel box girder 103, the connecting structure 104 and the concrete slab 106 are all prefabricated in advance, which is beneficial to shortening the construction period on site and is easy to install. Only one lifting machine 107 is needed to complete the construction of the entire composite beam segment 101. The operator only needs to perform simple lifting and fixing work on site, which reduces the construction difficulty of the operator and the probability of error of the operator, and is beneficial to saving construction costs.
[0063] Specifically, the design interval is provided by the design data of the cable-stayed bridge.
[0064] See also Figure 4 In order to facilitate the fixed connection between the two ends of each cross beam 108 and the opposite side of the first steel box beam 102 and the second steel box beam 103, a plurality of reserved parts 110 are fixed on the opposite side of the first steel box beam 102 and the second steel box beam 103, and the two ends of each cross beam 108 are fixedly connected to the corresponding reserved parts 110 fixed on the first steel box beam 102 and the second steel box beam 103;
[0065] During construction, firstly, each reserved part 110 is fixed to the opposite side of the first steel box girder 102 and the second steel box girder 103 according to the designed interval, and then both ends of each cross beam 108 are fixedly connected to the corresponding reserved part 110. Specifically, the designed interval is provided by the design data of the cable-stayed bridge.
[0066] During construction, multiple cross beams 108 and longitudinal beams 109 are hoisted as a whole, which is also conducive to shortening the construction period on site. The installation is simple. The construction of the connecting structure 104 can be completed using the same hoisting machine 107. The operator only needs to perform simple hoisting and fixing work on site, which reduces the construction difficulty of the operator and the probability of error of the operator, which is conducive to saving construction costs.
[0067] See also Figures 5 and 6 The composite beam 100 includes a plurality of composite beam segments 101. The composite beam segment construction method is adopted to sequentially construct the composite beam segments 101 in sequence. The composite beam construction method for a cable-stayed bridge disclosed in the present invention includes the following steps:
[0068] A1. Operate the hoisting machine to lift the first composite beam segment in the composite beam, i=1, and perform composite beam segment construction of the i-th segment;
[0069] A2. After completing the construction of the i-th section, operate the hoisting machinery to move forward to the predetermined position and hoist the first steel box girder of the i+1-th section to the designed position;
[0070] A3. After the hoisting of the first steel box girder of the i+1th section is completed, the first steel box girder of the i+1th section and the first steel box girder of the ith section are welded;
[0071] A4. Operate the hoisting machinery to continue hoisting the second steel box girder of the i+1th section to the designed position, and connect the second steel box girder of the i+1th section with the second steel box girder of the ith section by welding;
[0072] A5. Operate the lifting machinery to lift the connection structure of the i+1 segment, and weld it to the first steel box girder and the second steel box girder of the i+1 segment respectively, and carry out the composite beam segment construction of the i+1 segment;
[0073] A6. Carry out the first tensioning operation of the cable corresponding to the i+1th segment;
[0074] A7. Use a lifting machine to lift the concrete slab corresponding to the i+1th section, and perform wet joint pouring between the concrete slabs of the i+1th section and the ith section;
[0075] A8. Carry out the second tensioning operation of the corresponding inclined cable of the i+1 segment. After reaching the designed tensioning stress, complete the construction of the composite beam segment of the i+1 segment;
[0076] A9, taking the composite beam of the i+1th segment as the new composite beam of the ith segment, i.e., setting i=i+1, and returning to step A2;
[0077] A10. Repeat steps A2 to A9 until all composite beam segments are constructed.
[0078] When the composite beam of the cable-stayed bridge adopts a structure in which a separate steel box is connected by a crossbeam, the first steel box beam and the second steel box beam of each segment, the connection structure and the concrete slab are prefabricated in advance, which is beneficial to shorten the construction period on site. The installation is simple, and only one lifting machine is needed to complete the construction of the entire composite beam segment. The operator only needs to perform simple lifting and fixing work on site, which reduces the construction difficulty of the operator and the probability of error of the operator, which is beneficial to saving construction costs.
[0079] In step A5, please refer to Figure 4 , the connection structure 104 of the i+1 segment includes a plurality of cross beams 108, and a plurality of reserved parts 110 are fixed on opposite sides of the first steel box beam 102 and the second steel box beam 103 of the i+1 segment, and both ends of each cross beam 108 of the i+1 segment are fixedly connected to the corresponding reserved parts 110 fixed on the first steel box beam 102 and the second steel box beam 103, respectively, and a longitudinal beam 109 is fixed between each cross beam 108 of the i+1 segment;
[0080] The steps of prefabricating the connection structure 104 of the i+1 segment are: firstly arranging the cross beams 108 of the i+1 segment in parallel according to the designed intervals, and then fixing the longitudinal beams 109 of the i+1 segment between the cross beams 108 of the i+1 segment to keep the intervals between the cross beams 108 of the i+1 segment relatively unchanged, and at the same time, fixing the reserved parts 110 to the opposite sides of the first steel box beam 102 and the second steel box beam 103 of the i+1 segment according to the designed intervals;
[0081] During on-site construction, after using a lifting machine 107 to lift the connection structure 104 of the i+1th segment to the designed position, the two ends of each beam 108 of the i+1th segment are welded to the corresponding reserved parts 110, respectively, to achieve the welding of the connection structure 104 of the i+1th segment with the first steel box girder 102 and the second steel box girder 103 of the i+1th segment.
[0082] The composite beam segment construction method and the composite beam construction method for cable-stayed bridge disclosed in the present invention have the following technical effects: In the present invention, the first steel box beam, the second steel box beam and the connecting structure, as well as the concrete slab in the composite beam segment are all prefabricated in advance, and the composite beam is constructed segment by segment, which is conducive to shortening the construction period on site, and the installation is simple, only one hoisting machine is needed to complete the construction of the entire composite beam segment, and the operator only needs to perform simple hoisting and fixing work on site, which reduces the construction difficulty of the operator, and also reduces the error probability of the operator, which is conducive to saving construction costs. The present invention not only solves the problem of complex construction steps and large workload of composite beams of this structural form, but also saves the number of workers, costs and construction period.
[0083] It is understood that the present invention is described by some embodiments, and those skilled in the art are aware that various changes or equivalent substitutions may be made to these features and embodiments without departing from the spirit and scope of the present invention. Under the teachings of the present invention, these features and embodiments may be modified to adapt to specific circumstances and materials without departing from the spirit and scope of the present invention. The embodiments described in the present invention are part of the embodiments of the present invention, rather than all of the embodiments. The components of the embodiments of the present invention generally described and shown in the drawings herein may be arranged and designed in various different configurations. Therefore, the following detailed description of the embodiments of the present invention provided in the drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed herein, and all other embodiments obtained by ordinary technicians in the art without creative work based on the embodiments in the present invention belong to the scope of protection of the present invention.
Claims
1. A composite beam segment construction method, characterized in that: The composite beam segment comprises a first steel box beam and a second steel box beam, and the first steel box beam and the second steel box beam are fixedly connected by a connecting structure; during construction, the following steps are included: S1. Prefabricate the first steel box girder, the second steel box girder and the connecting structure in advance and transport them to the construction site; S2. Lift and fix the first steel box girder and the second steel box girder to the designed positions respectively; S3, hoisting the connection structure between the first steel box girder and the second steel box girder, and fixing the two sides of the connection structure to the first steel box girder and the second steel box girder respectively; S4, installing the stay cables on the composite beam segment and performing the first tensioning operation; S5, prefabricate the overlying concrete slab of the composite beam segment, and hoist the concrete slab to the position corresponding to the composite beam segment; S6. Perform a second tensioning operation on the inclined cable to complete the construction of the composite beam segment.
2. The composite beam segment construction method according to claim 1, characterized in that: In step S3, the connection structure includes a plurality of cross beams, both ends of each cross beam are respectively fixedly connected to the opposite side of the first steel box beam and the second steel box beam, and a longitudinal beam is fixed between each cross beam; During construction, first arrange the beams in parallel according to the designed intervals, and then fix the longitudinal beams between the beams to keep the intervals between the beams relatively unchanged.
3. The composite beam segment construction method according to claim 2, characterized in that: In order to facilitate the fixed connection of the two ends of each cross beam with the opposite side of the first steel box beam and the second steel box beam, a plurality of reserved parts are respectively fixed on the opposite side of the first steel box beam and the second steel box beam, and the two ends of each cross beam are respectively fixedly connected with the corresponding reserved parts fixed on the first steel box beam and the second steel box beam; During construction, firstly, each reserved part is fixed to the opposite side of the first steel box girder and the second steel box girder according to the designed interval, and then both ends of each cross beam are fixedly connected to the corresponding reserved part.
4. A method for constructing a cable-stayed bridge composite beam, characterized in that: The composite beam comprises a plurality of composite beam segments, and the composite beam segment construction method according to claim 1 is used to sequentially construct the composite beam segments in order, including the following steps: A1. Operate the hoisting machine to lift the first composite beam segment in the composite beam, i=1, and perform composite beam segment construction of the i-th segment; A2. After completing the construction of the i-th section, operate the hoisting machinery to move forward to the predetermined position and hoist the first steel box girder of the i+1-th section to the designed position; A3. After the hoisting of the first steel box girder of the i+1th section is completed, the first steel box girder of the i+1th section and the first steel box girder of the ith section are welded; A4. Operate the hoisting machinery to continue hoisting the second steel box girder of the i+1th section to the designed position, and connect the second steel box girder of the i+1th section with the second steel box girder of the ith section by welding; A5. Operate the lifting machinery to lift the connection structure of the i+1 segment, and weld it to the first steel box girder and the second steel box girder of the i+1 segment respectively, and carry out the composite beam segment construction of the i+1 segment; A6. Carry out the first tensioning operation of the cable corresponding to the i+1th segment; A7. Use a lifting machine to lift the concrete slab corresponding to the i+1th section, and perform wet joint pouring between the concrete slabs of the i+1th section and the ith section; A8. Carry out the second tensioning operation of the corresponding inclined cable of the i+1 segment. After reaching the designed tensioning stress, complete the construction of the composite beam segment of the i+1 segment; A9, taking the composite beam of the i+1th segment as the new composite beam of the ith segment, i.e., setting i=i+1, and returning to step A2; A10. Repeat steps A2 to A9 until all composite beam segments are constructed.
5. The cable-stayed bridge composite beam construction method according to claim 4, characterized in that: In step A5, the connection structure of the i+1th segment includes a plurality of cross beams, a plurality of reserved parts are respectively fixed on opposite sides of the first steel box beam and the second steel box beam of the i+1th segment, two ends of each cross beam of the i+1th segment are respectively fixedly connected to the corresponding reserved parts fixed on the first steel box beam and the second steel box beam of the i+1th segment, and a longitudinal beam is fixed between each cross beam of the i+1th segment; The steps of prefabricating the connection structure of the i+1 segment are: firstly arranging the cross beams of the i+1 segment in parallel according to the designed intervals, and then fixing the longitudinal beams of the i+1 segment between the cross beams of the i+1 segment to keep the intervals between the cross beams of the i+1 segment relatively unchanged, and at the same time, fixing the reserved parts to the opposite sides of the first steel box beam and the second steel box beam of the i+1 segment according to the designed intervals; During on-site construction, after using a lifting machine to lift the connection structure of the i+1th segment to the designed position, the two ends of each beam of the i+1th segment are welded to the corresponding reserved parts, so as to realize the welding of the connection structure of the i+1th segment with the first steel box girder and the second steel box girder of the i+1th segment.