Prefabricated guardrail turtle back backfilling greening structure for medial strip and construction method of prefabricated guardrail turtle back backfilling greening structure

By employing a closed waterproof structure, intelligent sprinkler system, and standardized compaction device in the central median strip of the highway, the problems of low vegetation survival rate and low construction efficiency were solved, achieving efficient and environmentally friendly greening construction and improving driving safety and road stability.

CN118997040AInactive Publication Date: 2024-11-22CHINA FIRST HIGHWAY ENGINEERING CO LTD +2
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411129615.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-11-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing greening of the median strip on highways suffers from problems such as low vegetation survival rate, impaired visibility and safety for drivers, and increased maintenance costs. Furthermore, the efficiency and quality of construction need to be improved.

Method used

The system employs a closed, waterproof central median structure, an intelligent sprinkler irrigation system for greening maintenance, a raised baffle structure to prevent road pollution, and a standardized, leak-proof, turtle-back shaped compaction device. Combined with a side-opening backfill soil placement structure for transport vehicles, it creates a stable greening environment and improves construction efficiency.

Benefits of technology

It improved the survival rate of green plants and construction efficiency, reduced environmental pollution, lowered costs, improved driving visibility and safety, and extended the service life of roads.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997040A_ABST
    Figure CN118997040A_ABST
Patent Text Reader

Abstract

The invention relates to a medial strip prefabricated guardrail turtleback backfilling greening structure and a construction method thereof. The construction method comprises a closed waterproof medial strip technology, a greening maintenance intelligent sprinkling irrigation technology, a transport vehicle side door opening backfilling soil distribution technology, a road surface pollution preventing, baffle heightening and hilling technology and a shaped soil leakage preventing turtleback-shaped compaction device. The invention belongs to the field of highway engineering construction, not only can improve the soil filling and compaction construction efficiency, the structural strength, the anti-seepage quality, the green plant survival rate and the sprinkling irrigation safety, but also reduces the pollution to the surrounding environment, saves manpower and cost, and can obtain better technical and economic benefits when being applied to actual engineering.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of highway engineering, is suitable for the construction of a central dividing strip, and mainly relates to a central dividing strip prefabricated assembled guardrail turtleback backfill greening structure and a construction method thereof. Background Art

[0002] Most of the existing central dividers on expressways use assembled guardrails, which play a major role in preventing out-of-control vehicle collisions and effectively reduce the occurrence of serious accidents. However, with the continuous development of the economy, the use of various types of vehicles (especially high-end cars, luxury buses, and container freight vehicles, etc.) is growing rapidly, and the greening of the central divider of the guardrail has gradually revealed some defects and deficiencies in protecting vehicles with high speeds and large masses. The vegetation survival rate of the current guardrail greening method is not high, which seriously affects the driving vision and safety, and increases the cost of later maintenance and replacement.

[0003] In view of this, in order to address the shortcomings in the previous prefabricated box culvert construction, a new construction method for the central median prefabricated assembled guardrail turtleback backfill greening structure is urgently needed to improve construction efficiency, construction quality and green plant survival rate, and ensure the safety and reliability of the construction process. Summary of the invention

[0004] The purpose of the present invention is to provide a central dividing strip prefabricated assembled guardrail turtleback backfill greening structure and its construction method which can effectively improve the filling and compaction construction efficiency, structural strength and anti-seepage quality, green plant survival rate, and sprinkler irrigation safety, while reducing pollution to the surrounding environment, saving manpower and costs, and having the characteristics of environmental protection and energy saving, convenient construction, and simple operation.

[0005] To achieve the above technology, the present invention adopts the following technical solutions:

[0006] The central median prefabricated guardrail turtleback backfill greening structure includes:

[0007] It includes a closed waterproof central dividing strip structure, an intelligent sprinkler irrigation system for greening maintenance, and a raised baffle and earth-building structure to prevent road pollution;

[0008] The closed waterproof central dividing strip structure includes a subbase, a base layer, a surface layer, waterproof concrete, emulsified asphalt, assembled guardrails, backfill soil, and green plants. The base layer is arranged on the subbase, the surface layer is arranged on the base layer, the assembled guardrails are arranged under the subbase, the waterproof concrete is arranged on the subbase between the assembled guardrails, the emulsified asphalt is arranged on the waterproof concrete, the backfill soil is arranged between the assembled guardrails, and the green plants are arranged on the backfill soil;

[0009] The greening maintenance intelligent sprinkler irrigation system includes a water pump, a water pipe, a nozzle, a water pipe fixing ring, a horizontal fixing frame, a vertical fixing frame, a sensor, and a water tank. The water tank is arranged on the surface layer at both ends of the central dividing strip, the water pump is arranged in the water tank, the vertical fixing frame is arranged on the central dividing strip, the horizontal fixing frame is arranged on the vertical fixing frame, the water pipe is connected to the water pump and fixed on the horizontal fixing frame through the water pipe fixing ring, the nozzle is arranged on the water pipe, and the sensor is arranged in the central dividing strip;

[0010] The raised baffle earth-building structure for preventing road pollution includes a raised baffle, a hook, a rope, and fixed ribs. The raised baffle is arranged on the assembled guardrail, the hook is arranged on the raised baffle, one end of the rope is fixed on the hook, and the other end is fixed on the transport vehicle, and one end of the fixed rib is fixed on the raised baffle, and the other end is fixed on the assembled guardrail.

[0011] Furthermore, it also includes a transport vehicle side door opening backfill soil spreading structure, which includes a transport vehicle, a transport vehicle side door, and a triangular retaining plate. The transport vehicle is arranged on one side of the central dividing strip, the upper side of the transport vehicle side door is fixed on the assembled guardrail, and the triangular retaining plates are arranged at both ends of the transport vehicle side door.

[0012] Furthermore, it also includes a standardized anti-leakage soil turtle-back compaction device, which includes an excavator, an excavator arm, fixing holes, fixing screws, a fixing frame, a flat plate, and side plates. The excavator is arranged on one side of the central dividing strip, the excavator arm is arranged on the excavator, the fixing holes are arranged on the fixing frame, the fixing frame is arranged on the flat plate, the fixing frame is connected and fixed to the excavator arm by fixing screws, and the side plates are arranged at the bottom of the flat plate.

[0013] The construction method of the central dividing strip prefabricated assembled guardrail turtleback backfill greening structure includes the following steps:

[0014] Step 1: Construction preparation: Be familiar with the construction drawings and related technical requirements. On the basis of fully understanding the construction drawings, carry out positioning and layout according to the plane dimensions of the design drawings.

[0015] Step 2: Construction of closed waterproof central dividing strip: the base layer is set on the subbase layer, the surface layer is set on the base layer, the assembled guardrail is inserted under the subbase layer, the waterproof concrete is set on the subbase layer between the assembled guardrails, and the emulsified asphalt is set on the waterproof concrete;

[0016] Step 3: Soil cultivation: The transport vehicle transports soil to the construction site and stops on one side of the central dividing strip. The upper side of the side door of the transport vehicle is fixed on the assembled guardrail. The triangular retaining plates are set at both ends of the side door of the transport vehicle. The heightened baffle is set on the assembled guardrail. The hook is set on the heightened baffle. One end of the rope is fixed on the hook and the other end is fixed on the transport vehicle. One end of the fixing rib is fixed on the heightened baffle and the other end is fixed on the assembled guardrail. The soil is unloaded from the transport vehicle.

[0017] Step 4: Pressing: The excavator is moved to one side of the central dividing strip, the excavator arm is set on the excavator, the fixing holes are set on the fixing frame, the fixing frame is set on the flat plate, the fixing frame is connected and fixed to the excavator arm through the fixing screw, the side plate is set at the bottom of the flat plate, and the flat plate is controlled by the excavator arm to perform pressing;

[0018] Step 5: Intelligent sprinkler irrigation construction for greening maintenance: water tanks are installed on the surface layers at both ends of the central dividing strip, water pumps are installed in the water tanks, vertical fixed frames are installed on the central dividing strip, horizontal fixed frames are installed on the vertical fixed frames, water pipes are connected to the water pumps and fixed on the horizontal fixed frames through water pipe fixing rings, sprinklers are installed on the water pipes, humidity sensors are buried in the soil in the central dividing strip, and watering is controlled by computer by sensing the soil humidity;

[0019] Step 6. Planting construction of seedlings: Lay out and dig planting holes on the backfill soil, plant the green plants, and water them in time after planting to ensure that the seedlings grow well.

[0020] Compared with the prior art, the present invention has the following characteristics and beneficial effects:

[0021] 1) The closed waterproof central dividing strip structure of the present invention provides a stable and suitable growth environment for green plants, reduces water loss and soil erosion, and helps to improve the survival rate of green plants. The greening maintenance intelligent sprinkler irrigation system can accurately control watering according to soil humidity, ensure that green plants receive an appropriate amount of water supply, avoid the problem of insufficient or excessive watering, and thus improve the growth quality and survival rate of green plants.

[0022] 2) Through the construction of greening maintenance intelligent sprinkler irrigation system, irrigation is convenient and highly intelligent, which can effectively reduce the risk factor of greening watering operations in the central dividing strip, reduce the impact of factors such as weather and personnel deployment on irrigation operation efficiency, and improve driving safety.

[0023] 3) The soil filling construction is carried out by using a transport vehicle with a side-opening door to backfill the soil and a baffle to prevent road pollution. The operation is simple, the construction efficiency is high, and the pollution to the surrounding ground is reduced.

[0024] 4) A standardized anti-leakage turtle-back compaction device is used for compaction construction to form a turtle-back structure, which reduces the risk of uneven soil settlement. The survival rate of seedlings reaches 100%, achieving zero gaps in greening and reducing the cost of replacing seedlings in the later stage.

[0025] 5) The setting of waterproof concrete and emulsified asphalt enhances the waterproof performance of the central median, reduces the damage to the road structure caused by water penetration, and increases the service life of the road. Reasonable structural design and material selection make the entire central median prefabricated guardrail turtleback backfill greening structure have higher strength and stability.

[0026] 6) The high survival rate of green plants and the reasonable layout of greening effectively improve the driving sight, reduce the visual fatigue of the driver, and improve driving safety. The heightened baffle and earth-building structure can prevent the soil from polluting the road surface during the filling process, keeping the road clean and safe.

[0027] 7) The high survival rate and good growth condition of green plants reduce the frequency of later maintenance and replacement, and reduce related costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is a schematic diagram of the structure of the closed waterproof central dividing strip of the present invention;

[0029] Figure 2 It is a schematic diagram of the system structure of the greening maintenance intelligent sprinkler irrigation system of the present invention;

[0030] Figure 3 It is a schematic diagram of the structure of the transport vehicle with side-opening doors for backfilling soil and distributing materials according to the present invention;

[0031] Figure 4 It is a front view of the raised baffle and earth-raising structure for preventing road pollution according to the present invention;

[0032] Figure 5 It is a schematic structural diagram of the standardized anti-leakage soil turtle-back compacting device of the present invention.

[0033] In the figure: 1. subbase; 2. base layer; 3. surface layer; 4. waterproof concrete; 5. emulsified asphalt; 6. assembled guardrail; 7. backfill soil; 8. green plants; 9. central dividing strip; 10. water pump; 11. water pipe; 12. sprinkler; 13. water pipe fixing ring; 14. horizontal fixing frame; 15. vertical fixing frame; 16. sensor; 17. water tank; 18. transport vehicle; 19. transport vehicle side door; 20. heightened baffle; 21. pull hook; 22. rope; 23. fixing rib; 24. triangular retaining plate; 25. excavator; 26. excavator arm; 27. fixing hole; 28. fixing screw; 29. ​​fixing frame; 30. flat plate; 31. side panel. DETAILED DESCRIPTION

[0034] The present invention will be further described in detail below with reference to the accompanying drawings and by way of examples, but the description is not limited to the following examples.

[0035] Figure 1 It is a schematic diagram of the closed waterproof central dividing strip structure. Figure 2 This is a schematic diagram of the intelligent sprinkler irrigation system architecture for greening maintenance. Figure 3 This is a schematic diagram of the transport vehicle's side-opening door backfilling soil distribution structure. Figure 4 It is a front view of the structure of raising the baffle to prevent road pollution. Figure 5 It is a schematic diagram of the structure of a standardized anti-leakage soil turtle-back compaction device.

[0036] Example 1

[0037] like Figures 1 to 5 As shown, the central median prefabricated assembled guardrail turtleback backfill greening structure includes a closed and waterproof central median structure, an intelligent sprinkler system for greening maintenance, a transport vehicle side door backfill soil distribution structure, a raised baffle soil-building structure to prevent road pollution, and a standardized anti-leakage turtleback compaction device.

[0038] The closed waterproof central dividing strip structure includes a subbase layer 1, a base layer 2, a surface layer 3, waterproof concrete 4, emulsified asphalt 5, an assembled guardrail 6, backfill soil 7, and green plants 8. The base layer 2 is arranged on the subbase layer 1, the surface layer 3 is arranged on the base layer 2, the assembled guardrail 6 is arranged under the subbase layer 1, the waterproof concrete 4 is arranged on the subbase layer 1 between the assembled guardrails 6, the emulsified asphalt 5 is arranged on the waterproof concrete 4, the backfill soil 7 is arranged between the assembled guardrails 6, and the green plants 8 are arranged on the backfill soil 7.

[0039] As an improved specific implementation method, it also includes a greening maintenance intelligent sprinkler irrigation system, which includes a water pump 10, a water pipe 11, a nozzle 12, a water pipe fixing ring 13, a horizontal fixing frame 14, a vertical fixing frame 15, a sensor 16, and a water tank 17. The water tank 17 is arranged on the surface layer 3 at both ends of the central dividing strip 9, the water pump 10 is arranged in the water tank 17, the vertical fixing frame 15 is arranged on the central dividing strip 9, the horizontal fixing frame 14 is arranged on the vertical fixing frame 15, the water pipe 11 is connected to the water pump 10 and fixed on the horizontal fixing frame 14 through the water pipe fixing ring 13, the nozzle is arranged on the water pipe 11, and the sensor 16 is arranged in the central dividing strip 9.

[0040] As an improved specific implementation method, it also includes a transport vehicle side door opening backfill soil spreading structure, the transport vehicle side door opening backfill soil spreading structure includes a transport vehicle 18, a transport vehicle side door 19, and a triangular retaining plate 24. The transport vehicle is arranged on one side of the central dividing strip 9, the upper side of the transport vehicle side door 19 is fixed on the assembled guardrail 6, and the triangular retaining plates 24 are arranged at both ends of the transport vehicle side door 19.

[0041] As an improved specific implementation method, it also includes a raised baffle and earth-building structure for preventing road pollution. The raised baffle and earth-building structure for preventing road pollution includes a raised baffle 20, a hook 21, a rope 22, and a fixing rib 23. The raised baffle 20 is arranged on the assembled guardrail 6, the hook 21 is arranged on the raised baffle 20, one end of the rope 22 is fixed to the hook 21, and the other end is fixed to the transport vehicle 18, and one end of the fixing rib 23 is fixed to the raised baffle 20, and the other end is fixed to the assembled guardrail 6.

[0042] As an improved specific implementation method, it also includes a standardized anti-leakage soil turtle-back compaction device, which includes an excavator 25, an excavator arm 26, a fixing hole 27, a fixing screw 28, a fixing frame 29, a flat plate 30, and a side plate 31. The excavator 25 is arranged on one side of the central dividing strip 9, the excavator arm 26 is arranged on the excavator 25, the fixing hole 27 is arranged on the fixing frame 29, the fixing frame 29 is arranged on the flat plate 30, the fixing frame 29 is connected and fixed to the excavator arm 26 by a fixing screw 28, and the side plate 31 is arranged at the lower part of the flat plate 30.

[0043] Example 2

[0044] The construction method of the central dividing strip prefabricated assembled guardrail turtleback backfill greening structure includes the following steps:

[0045] Step 1: Construction preparation: Familiarize yourself with the construction drawings and related technical requirements. Based on a full understanding of the construction drawings, carry out positioning and layout according to the plane dimensions of the design drawings.

[0046] Step 2, construction of a closed waterproof central dividing strip: the base layer 2 is arranged on the subbase layer 1, the surface layer 3 is arranged on the base layer 2, the assembled guardrail 6 is inserted under the subbase layer 1, the waterproof concrete 4 is arranged on the subbase layer 1 between the assembled guardrails 6, and the emulsified asphalt 5 is arranged on the waterproof concrete 4.

[0047] Step three, soil construction: the transport vehicle transports soil to the construction site and stops on one side of the central dividing strip 9. The upper side of the side door 19 of the transport vehicle is fixed on the assembled guardrail 6. The triangular retaining plates 24 are arranged at both ends of the side door 19 of the transport vehicle. The heightened baffle 20 is arranged on the assembled guardrail 6. The hook 21 is arranged on the heightened baffle 20. One end of the rope 22 is fixed on the hook 21, and the other end is fixed on the transport vehicle 18. One end of the fixing rib 23 is fixed on the heightened baffle 20, and the other end is fixed on the assembled guardrail 6. The soil is unloaded from the transport vehicle 18.

[0048] Step 4: Pressing construction: the excavator 25 is moved to one side of the central dividing strip 9, the excavator arm 26 is arranged on the excavator 25, the fixing hole 27 is arranged on the fixing frame 29, the fixing frame 29 is arranged on the flat plate 30, the fixing frame 29 is connected and fixed to the excavator arm 26 by the fixing screw 28, the side plate 31 is arranged at the lower part of the flat plate 30, and the flat plate 30 is controlled by the excavator arm 26 to perform pressing construction.

[0049] Step 5, construction of intelligent sprinkler irrigation for greening maintenance: water tank 17 is installed on the surface layer 3 at both ends of the central dividing strip 9, water pump 10 is installed in the water tank 17, vertical fixing frame 15 is installed on the central dividing strip 9, horizontal fixing frame 14 is installed on the vertical fixing frame 15, water pipe 11 is connected to water pump 10, and fixed on the horizontal fixing frame 14 through water pipe fixing ring 13, sprinkler head is installed on water pipe 11, humidity sensor 16 is buried in the soil in the central dividing strip 9, and watering is controlled by computer by sensing soil humidity.

[0050] Step six, seedling planting construction: mark out and dig planting holes on the backfill soil 7, plant green plants 8, and water them in time after planting to ensure that the seedlings grow well.

[0051] For example, in a certain highway reconstruction project, the central median prefabricated assembled guardrail turtleback backfill greening structure of the present invention was used. During the construction process, the side-opening backfill soil distribution structure of the transport vehicle increased the filling efficiency by 30% compared with the traditional method, and the use of a standardized anti-leakage turtleback compaction device shortened the compaction construction time by 25%. The application of the greening maintenance intelligent sprinkler irrigation system has increased the survival rate of green plants to more than 95%, greatly reducing the subsequent replanting work. At the same time, the structure effectively prevents rainwater infiltration, and the service life of the road is expected to be extended by more than 5 years, with a significant reduction in the overall cost.

[0052] For example, in another section of expressway, the central dividing strip had poor greening effect in the past, which often affected the driving sight and brought hidden dangers to traffic safety. After adopting the present invention, the green plants grew luxuriantly, the sight obstruction problem was effectively solved, and there was no obvious road seepage in the rainy season, and the stability and safety of the road were greatly improved.

[0053] Example 3

[0054] The working principle of the greening maintenance intelligent sprinkler irrigation system in the present invention is as follows:

[0055] First, sensors are buried in the soil within the central dividing strip, which can monitor the soil moisture in real time. The sensors transmit the monitored moisture data to the computer control system.

[0056] When the soil moisture is lower than the set threshold, the computer control system will issue a command to start the water pump in the water tank. After the water pump starts working, the water in the water tank will be pumped out.

[0057] The pumped water is transported through a water pipe connected to the water pump. The water pipe is fixed to a horizontal fixing frame through a water pipe fixing ring, and the horizontal fixing frame is installed on a vertical fixing frame, thereby ensuring the stability and position fixation of the water pipe.

[0058] The water flows along the water pipe and finally sprays out from the sprinkler head to irrigate the green plants in the central dividing strip.

[0059] The entire process achieves automatic and precise sprinkler irrigation based on the actual humidity conditions of the soil, which can not only meet the water needs of green plants but also avoid waste of water resources.

[0060] For example, if in the hot and dry summer, the soil water evaporates quickly and the humidity drops quickly, the sensor detects that the humidity is below the threshold, and the smart sprinkler system will start in time to replenish water for the green plants to ensure their normal growth. In the rainy season, the soil humidity is high, and the smart sprinkler system will not start, saving water resources.

[0061] For example, in areas with different soil types, due to differences in water retention capacity, sensors can flexibly set humidity thresholds based on actual conditions, thereby achieving more personalized and precise sprinkler irrigation services.

[0062] The parts not described in detail in this application are prior art, so this application does not describe them in detail.

[0063] It is to be understood that the term "one" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element may be one, while in another embodiment, the number of the element may be multiple, and the term "one" should not be understood as a limitation on the quantity.

[0064] Although this article uses more professional terms, it does not exclude the possibility of using other terms. These terms are used only to more conveniently describe and explain the essence of this application; interpreting them as any additional restrictions is contrary to the spirit of this application.

[0065] The present application is not limited to the above-mentioned optimal implementation mode. Anyone can derive other forms of products under the inspiration of this application. However, no matter what changes are made in the shape or structure, all technical solutions that are the same or similar to those of the present application fall within the protection scope of the present application.

Claims

1. The central dividing strip prefabricated assembled guardrail turtleback backfill greening structure is characterized by: It includes a closed waterproof central dividing strip structure, an intelligent sprinkler irrigation system for greening maintenance, and a raised baffle and earth-building structure to prevent road pollution; The closed waterproof central dividing strip structure comprises a subbase (1), a base layer (2), a surface layer (3), waterproof concrete (4), emulsified asphalt (5), an assembled guardrail (6), backfill soil (7), and green plants (8); the base layer (2) is arranged on the subbase (1), the surface layer (3) is arranged on the base layer (2), the assembled guardrail (6) is arranged under the subbase (1), the waterproof concrete (4) is arranged on the subbase (1) between the assembled guardrails (6), the emulsified asphalt (5) is arranged on the waterproof concrete (4), the backfill soil (7) is arranged between the assembled guardrails (6), and the green plants (8) are arranged on the backfill soil (7); The greening maintenance intelligent sprinkler irrigation system comprises a water pump (10), a water pipe (11), a nozzle (12), a water pipe fixing ring (13), a horizontal fixing frame (14), a vertical fixing frame (15), a sensor (16), and a water tank (17). The water tank (17) is arranged on the surface layer (3) at both ends of the central dividing strip (9). The water pump (10) is arranged in the water tank (17). The vertical fixing frame (15) is arranged on the central dividing strip (9). The horizontal fixing frame (14) is arranged on the vertical fixing frame (15). The water pipe (11) is connected to the water pump (10) and fixed to the horizontal fixing frame (14) through the water pipe fixing ring (13). The nozzle is arranged on the water pipe (11). The sensor (16) is arranged in the central dividing strip (9). The raised baffle plate soil-raising structure for preventing road pollution comprises a raised baffle plate (20), a draw hook (21), a rope (22), and a fixing rib (23); the raised baffle plate (20) is arranged on an assembled guardrail (6); the draw hook (21) is arranged on the raised baffle plate (20); one end of the rope (22) is fixed on the draw hook (21) and the other end is fixed on a transport vehicle (18); one end of the fixing rib (23) is fixed on the raised baffle plate (20) and the other end is fixed on the assembled guardrail (6).

2. The central dividing strip prefabricated assembled guardrail turtleback backfill greening structure according to claim 1 is characterized in that: The invention also comprises a transport vehicle side door opening backfill soil distribution structure, the transport vehicle side door opening backfill soil distribution structure comprises a transport vehicle (18), a transport vehicle side door (19), and a triangular retaining plate (24), the transport vehicle is arranged on one side of the central dividing strip (9), the upper side of the transport vehicle side door (19) is fixed on the assembled guardrail (6), and the triangular retaining plate (24) is arranged at both ends of the transport vehicle side door (19).

3. The central dividing strip prefabricated assembled guardrail turtleback backfill greening structure according to claim 2 is characterized in that: The invention also comprises a standardized anti-leakage soil turtle-back compacting device, which comprises an excavator (25), an excavator arm (26), a fixing hole (27), a fixing screw (28), a fixing frame (29), a flat plate (30), and a side plate (31). The excavator (25) is arranged on one side of the central dividing strip (9), the excavator arm (26) is arranged on the excavator (25), the fixing hole (27) is arranged on the fixing frame (29), the fixing frame (29) is arranged on the flat plate (30), the fixing frame (29) is connected and fixed to the excavator arm (26) by a fixing screw (28), and the side plate (31) is arranged at the lower part of the flat plate (30).

4. The construction method of the central median prefabricated assembled guardrail turtleback backfill greening structure according to claim 3 is characterized in that: The following steps are involved: Step 1: Construction preparation: Be familiar with the construction drawings and related technical requirements. On the basis of fully understanding the construction drawings, carry out positioning and layout according to the plane dimensions of the design drawings. Step 2: Construction of a closed waterproof central dividing strip: the base layer (2) is arranged on the subbase layer (1), the surface layer (3) is arranged on the base layer (2), the assembled guardrail (6) is inserted under the subbase layer (1), the waterproof concrete (4) is arranged on the subbase layer (1) between the assembled guardrails (6), and the emulsified asphalt (5) is arranged on the waterproof concrete (4); Step 3, soil construction: the transport vehicle transports soil to the construction site and stops at one side of the central dividing strip (9). The upper side of the transport vehicle side door (19) is fixed on the assembled guardrail (6). The triangular retaining plate (24) is arranged at both ends of the transport vehicle side door (19). The heightened baffle (20) is arranged on the assembled guardrail (6). The hook (21) is arranged on the heightened baffle (20). One end of the rope (22) is fixed on the hook (21) and the other end is fixed on the transport vehicle (18). One end of the fixing rib (23) is fixed on the heightened baffle (20) and the other end is fixed on the assembled guardrail (6). The soil is unloaded from the transport vehicle (18); Step 4: Pressing construction: the excavator (25) is moved to one side of the central dividing strip (9), the excavator arm (26) is arranged on the excavator (25), the fixing hole (27) is arranged on the fixing frame (29), the fixing frame (29) is arranged on the flat plate (30), the fixing frame (29) is connected and fixed to the excavator arm (26) through the fixing screw (28), the side plate (31) is arranged at the lower part of the flat plate (30), and the flat plate (30) is controlled by the excavator arm (26) to perform pressing construction; Step 5: Intelligent sprinkler irrigation construction for greening maintenance: a water tank (17) is arranged on the surface layer (3) at both ends of the central dividing strip (9), a water pump (10) is arranged in the water tank (17), a vertical fixing frame (15) is arranged on the central dividing strip (9), a horizontal fixing frame (14) is arranged on the vertical fixing frame (15), a water pipe (11) is connected to the water pump (10), and is fixed to the horizontal fixing frame (14) through a water pipe fixing ring (13), a sprinkler head is arranged on the water pipe (11), a humidity sensor (16) is buried in the soil in the central dividing strip (9), and watering is controlled by a computer by sensing the soil humidity; Step 6: Planting of seedlings: Stake out and dig planting holes on the backfill soil (7), plant green plants (8), and water them in time after planting to ensure that the seedlings grow well.

Citation Information

Patent Citations

  • Filling, leveling and compacting device

    CN111101528A

  • Closed waterproof type central dividing strip for highway

    CN201865023U

  • Prefabricated central concrete barrier

    CN207419329U

  • Movable hilling trolley for medial strip of anti-collision wall of road

    CN216452158U

  • Road greening maintenance device

    CN220965719U