River channel barrage and construction method thereof

By dividing the river weir into multiple prefabricated sections, processing them in the factory, and assembling them on site, the problems of difficult and time-consuming on-site pouring construction were solved, achieving rapid and efficient construction and excellent waterproofing and seepage prevention effects.

CN118997069APending Publication Date: 2024-11-22SHANGHAI INVESTIGATION DESIGN & RES INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411394423.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-08
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The on-site pouring construction of existing river weirs and dams is difficult, has a long construction period, and is severely affected by geographical, hydrological, and climatic factors.

Method used

The river weir is divided into multiple sections. The prefabricated dam body is processed in the factory and assembled on site through connecting structures, including connectors and concrete structures. Wing walls are set on both sides of the prefabricated dam body to improve its seepage prevention performance.

Benefits of technology

It saves on-site pouring time, shortens the construction cycle, improves construction efficiency and waterproofing and seepage prevention effects, adapts to various geographical environments, and reduces production costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997069A_ABST
    Figure CN118997069A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of water conservancy projects, and discloses a river channel barrage and a construction method thereof.The river channel barrage comprises a dam body assembly, the dam body assembly comprises a plurality of prefabricated dam bodies arranged in the direction perpendicular to the water flow direction of a river channel, and the adjacent prefabricated dam bodies are connected through connecting structures. According to the method, the whole dam body is divided into multiple sections, and then the situation that all the sections of the prefabricated dam body need to be subjected to cast-in-place construction in the construction process of the dam body is avoided through the mode that the prefabricated dam body is prefabricated, machined and produced in advance. And the cast-in-place construction time is saved. And when the concrete prefabricated dam body is prefabricated in a factory, the influence caused by climatic factors of a construction area does not need to be considered, and the problem faced by cast-in-place construction is solved. Therefore, the construction time can be greatly saved and the construction period can be shortened when the river channel barrage is built.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of water conservancy engineering, and in particular to a river channel dam and a construction method thereof. Background Art

[0002] A weir is an obstacle across a river that can change the characteristics of water flow. It is often used to divert water into irrigation canals, prevent floods, measure flow, and increase water depth to facilitate navigation. A dam is a barrier built on a river to prevent flooding, produce hydroelectric power, or store water for food or irrigation. People usually set up straight or arched dams on rivers, which can meet the basic function of river water storage and can also release water during floods. In river management, river weirs are usually built across the river.

[0003] At present, these river dams are usually made of reinforced concrete structures, and are basically cast on site. The structure of the dam is complex, and the construction is also affected by many factors such as geography, hydrology, and climate. The on-site construction is difficult and the construction period is generally long. Summary of the invention

[0004] In view of this, the present invention provides a river channel weir and a construction method thereof to solve the problem that on-site casting of the weir is difficult and the construction period is long.

[0005] In a first aspect, the present invention provides a river weir, including a dam body assembly, wherein the dam body assembly includes: a plurality of prefabricated dam bodies arranged perpendicular to a direction of water flow in the river, and adjacent prefabricated dam bodies are connected by a connecting structure.

[0006] Beneficial Effects

[0007] The whole dam body is divided into multiple sections, and then each section is prefabricated and processed in advance to avoid the need for on-site pouring of the dam body during construction. This saves time for on-site pouring construction. Moreover, when prefabricating the concrete prefabricated dam body in the factory, there is no need to consider the impact of climate factors in the construction area, which overcomes the difficulties faced by on-site pouring construction. Therefore, the construction of this kind of river channel dam can greatly save construction time and shorten the construction period.

[0008] In an optional embodiment, the connection structure includes: a connecting piece and a concrete structure, a plurality of the connecting pieces are provided on both sides of the prefabricated dam body, and the connecting pieces on two adjacent prefabricated dam bodies are correspondingly connected, the concrete structure is located between two adjacent prefabricated dam bodies, and the outer wall surface of the concrete structure is flush with the outer wall surface of the prefabricated dam body.

[0009] Beneficial Effects

[0010] First, the connectors on the two adjacent prefabricated dam bodies are connected accordingly, and then concrete is poured on site to form a concrete structure. The concrete structure can be connected to the two prefabricated dam bodies on both sides as a whole, with good waterproof and anti-leakage effects. Moreover, the steel bars at the connection of the two prefabricated dam bodies can improve the strength of the concrete structure, making it firm and reliable.

[0011] In an optional embodiment, the connection structure further includes: wing walls arranged on both sides of the prefabricated dam body.

[0012] In an optional embodiment, a plurality of the wing walls are arranged at intervals along the water flow direction of the river channel.

[0013] Beneficial Effects

[0014] After wing walls are set on both sides of the prefabricated dam body, the length of the seepage path can be increased, which can improve the anti-seepage performance of the connecting structure.

[0015] In an optional implementation, the prefabricated dam body is a straight-segment prefabricated dam body or a curved-segment prefabricated dam body.

[0016] Beneficial Effects

[0017] By combining straight-segment prefabricated dam bodies or curved-segment prefabricated dam bodies, weirs of different shapes can be constructed. The weirs have a variety of shapes and can adapt to a variety of geographical environments.

[0018] In an optional implementation, the prefabricated dam body includes: a foundation section and a wall section, and the wall section is arranged on the foundation section.

[0019] In an optional embodiment, the wall segment is provided with holes.

[0020] Beneficial Effects

[0021] Setting holes can reduce the weight of the prefabricated dam body, and can also save some materials and reduce production costs.

[0022] In an optional embodiment, stepping stones are provided at intervals on the top surface of the dam body assembly.

[0023] Beneficial Effects

[0024] After setting up the stepping stones, pedestrians will not slip when walking on the dam surface, which is safer and the dam surface is more beautiful.

[0025] In an optional embodiment, boulders are provided on the backwater side of the dam assembly.

[0026] Beneficial Effects

[0027] Setting up boulders can increase the overall stability of the dam and also effectively prevent erosion.

[0028] In a second aspect, the present invention further provides a river channel dam construction method, comprising:

[0029] Prefabricate and process the prefabricated dam body;

[0030] Arrange a plurality of the prefabricated dam bodies perpendicular to the direction of water flow in the river;

[0031] Two adjacent prefabricated dam bodies are connected by a connecting structure, and the two prefabricated dam bodies at both ends are respectively connected to the soil on both sides of the river bank.

[0032] Beneficial Effects

[0033] By prefabricating these prefabricated dam bodies in the factory, various adverse weather factors such as temperature and humidity in the construction area can be overcome, and these prefabricated dam bodies can be directly constructed after being transported to the site, greatly speeding up the construction progress and improving construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0035] Figure 1 It is a schematic diagram of a prefabricated dam body in a river channel weir of the present invention;

[0036] Figure 2 A top view of a prefabricated dam body in a river channel weir of the present invention;

[0037] Figure 3 is a side cross-sectional view of a river channel weir of the present invention;

[0038] Figure 4 It is a top view schematic diagram of the river channel weir of the present invention.

[0039] Description of reference numerals:

[0040] 1. Dam body components;

[0041] 101, prefabricated dam body, 1011, foundation section, 1012, wall section;

[0042] 102, connection structure, 1021, connection piece, 1022, wing wall;

[0043] 2. Tingbu;

[0044] 3. Driftwood. DETAILED DESCRIPTION

[0045] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0046] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0047] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0048] In addition, the technical features involved in the different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0049] River dams have the functions of irrigation, power generation, slope adjustment, sediment consolidation and flood control. They are facilities dedicated to river management in water conservancy projects. Specifically, the irrigation function is to provide a stable water source for farmland by adjusting the water level to ensure the smooth progress of agricultural production. The power generation function is to use the potential energy generated when water flows through the dam to drive the turbine to generate electricity and provide power support for the local or regional area. The slope adjustment function is to control the speed and direction of water flow to slow down the slope of the river or canal and prevent the water flow from eroding the river bank or canal. The sediment consolidation function is to adjust the water flow so that the sediment is deposited in the appropriate position, thereby consolidating the riverbed or riverbank and preventing soil erosion. The flood control function refers to reducing the flood control pressure in the downstream area by adjusting the water storage and flood discharge of the reservoir during the flood season.

[0050] In the related technology, most of the river dams and other dams are concrete structures, so they are mostly cast on site during construction. Dam construction is a complex project, which is affected by geography, hydrology, climate and other factors. In the early stage of construction, it is necessary to conduct a detailed geological survey of the construction area to understand the shape of the mountains, the hardness of the rocks, the situation of the river and the groundwater level. When pouring the dam body, it will also be restricted by climatic factors such as regional temperature and humidity, which will bring a series of difficulties to the on-site pouring of concrete construction. For example, in a high temperature environment, the hydration reaction inside the concrete will accelerate, generating more heat, resulting in an increase in the temperature difference between the inside and outside of the concrete, thereby increasing the risk of cracks. At the same time, high temperature will accelerate the evaporation of water on the surface of the concrete, making it more prone to shrinkage cracks. If the humidity is too low, the concrete surface will dry quickly, causing the internal water to evaporate too quickly and produce shrinkage cracks. Therefore, it is necessary to select appropriate construction conditions for dam construction, which also leads to a longer construction period.

[0051] To this end, this embodiment provides a river channel weir, as shown below Figures 1 to 4 The embodiment of the present invention is described. The river channel dam mainly includes: a dam body assembly. The dam body assembly includes: a plurality of prefabricated dam bodies 101 arranged perpendicular to the direction of the river flow, and adjacent prefabricated dam bodies 101 are connected by a connecting structure 102 .

[0052] Specifically, the dam body assembly connects the two sides of the river channel, and its two ends are connected to the soil at both ends of the river channel. The main part is set on the river channel, and stands stably in the river channel to play its water control function. The dam body assembly includes a plurality of prefabricated dam bodies 101 arranged at intervals from one side of the river channel to the other, that is, the prefabricated dam bodies 101 are prefabricated concrete structural parts. During construction, it can be directly pulled to the site for arrangement, and then the adjacent prefabricated dam bodies 101 are connected through the connecting structure 102 to complete the construction of the weir.

[0053] The entire dam body is divided into multiple sections, and then each section of the prefabricated dam body 101 is produced by prefabrication in advance, which avoids the need for on-site pouring of the dam body during construction. The steps of on-site pouring of concrete, vibrating concrete, concrete setting, and curing concrete are saved. Moreover, although the prefabricated dam body 101 produced in the factory also needs to be poured with concrete, the impact of climatic factors in the construction area does not need to be considered, which overcomes the difficulties faced by on-site pouring construction. Therefore, the construction of this river channel dam can greatly save construction time and shorten the construction period.

[0054] In one embodiment, the connection structure 102 includes: a connection piece 1021 and a concrete structure. A plurality of connection pieces 1021 are provided on both sides of the prefabricated dam body 101, and the connection pieces 1021 on two adjacent prefabricated dam bodies 101 are correspondingly connected, the concrete structure is located between the two adjacent prefabricated dam bodies 101, and the outer wall surface of the concrete structure is flush with the outer wall surface of the prefabricated dam body 101.

[0055] Specifically, the connecting member 1021 is preferably a steel bar, and one end of the steel bar can be embedded in the prefabricated dam body 101 when the prefabricated dam body 101 is prefabricated. After the prefabricated dam body 101 is formed, one end of the steel bar is fixed in the prefabricated dam body 101. Steel bars are embedded in both sides of the prefabricated dam body 101, and the number of embedded steel bars can be adaptively selected according to the volume of the prefabricated dam body 101. This embodiment does not limit the number of steel bars.

[0056] After the prefabricated dam bodies 101 are set in the river channel, the free ends of the corresponding connecting members 1021 (ie, steel bars) on two adjacent prefabricated dam bodies 101, ie, the ends of the steel bars not connected to the prefabricated dam bodies 101, can be tied together by steel wires.

[0057] After the connecting pieces 1021 on two adjacent prefabricated dam bodies 101 are tied together, concrete is poured between the two adjacent prefabricated dam bodies 101, that is, the concrete structure is formed by on-site casting. The two adjacent prefabricated dam bodies 101 are connected together by the concrete structure. And the structural shape of the concrete structure and the prefabricated dam body 101 are the same, and they only differ in size. After the concrete structure is connected to the prefabricated dam body 101, the corresponding top surface and side wall surface are flat and smooth, so as to ensure that the final dam body assembly has good integrity and good aesthetics.

[0058] All parts of other prefabricated buildings are prefabricated and then assembled on site. However, due to the special working conditions of the weir dam in the river channel, the water-proof performance of the prefabricated dam body 101 must be considered. Conventional connectors 1021 or connecting structures 102 cannot achieve leakage prevention after connecting the two prefabricated dam bodies 101. However, the connection structure 102 of the present application is first connected by steel bar binding, and then concrete is poured on site to form a concrete structure. The concrete structure can be connected to the two prefabricated dam bodies 101 on both sides as a whole, and the waterproof and anti-leakage effects are better. Moreover, the steel bars at the connection of the two prefabricated dam bodies 101 can improve the strength of the concrete structure, which is strong and reliable.

[0059] In one embodiment, the connection structure 102 further includes: wing walls 1022 disposed on both sides of the prefabricated dam body 101. The number of wing walls 1022 can be one or more. When multiple wing walls 1022 are provided, the multiple wing walls 1022 are spaced apart along the direction of the water flow in the river channel.

[0060] Specifically, the wing wall 1022 can be prefabricated along with the prefabricated dam body 101, that is, the wing wall 1022 is also cast with concrete. The thickness of the wing wall 1022 is relatively thin, and its height is close to the height of the prefabricated dam body 101. In this embodiment, two wing walls 1022 are arranged on each side of the prefabricated dam body 101, and the sizes of the two wing walls 1022 are the same. Moreover, the wing wall 1022 is embedded in the concrete structure and solidified with the concrete after the concrete is cast on site, just like the connecting piece 1021. The wing walls 1022 on the river bank side of the two prefabricated dam bodies 101 at both ends of the dam body assembly are embedded in the river bank soil.

[0061] After the wing walls 1022 are arranged on both sides of the prefabricated dam body 101 , the length of the seepage path can be increased, and the water-proof performance of the connection structure 102 can be improved.

[0062] In other embodiments, when multiple wing walls 1022 are provided, the lengths of the wing walls 1022 may also be different, so that the water seepage path in the connection structure 102 is more complex and the water seepage prevention performance is better.

[0063] In one embodiment, the prefabricated dam body 101 is a straight-segment prefabricated dam body 101 or a curved-segment prefabricated dam body 101 .

[0064] Specifically, although the weir dam set in the river channel is a whole, it may be straight or curved, or a combination of straight and curved segments, depending on the terrain shape. During the design stage of the weir dam construction, the entire weir dam can be divided into multiple sections, and when processing the prefabricated dam body 101, a corresponding mold can be made according to the specific shape of each section, and then prefabrication work can be carried out. Figure 3 As shown, in this embodiment, some of the dam body components are prefabricated dam bodies 101 in straight sections and some are prefabricated dam bodies 101 in curved sections.

[0065] By combining the straight-segment prefabricated dam body 101 or the curved-segment prefabricated dam body 101 , dams of different shapes can be constructed. The dams have various shapes and can adapt to various geographical environments.

[0066] In one embodiment, the prefabricated dam body 101 includes: a foundation section 1011 and a wall section 1012 , and the wall section 1012 is disposed on the foundation section 1011 .

[0067] Specifically, the foundation section 1011 is the load-bearing foundation of the prefabricated dam body 101. Generally speaking, the foundation section 1011 in each prefabricated dam body 101 is also the load-bearing foundation of the entire dam body assembly. The wall section 1012 is the main part of the dam body assembly to achieve various functions. The height of the wall section 1012 is much greater than the height of the foundation section 1011.

[0068] In one embodiment, the wall segment 1012 is provided with holes.

[0069] Specifically, the holes can reduce the weight of the prefabricated dam body 101, and can also save some materials and reduce production costs. In this embodiment, the holes provided in the wall section 1012 are square, and the square hole structure is simple, and the mold of the prefabricated dam body 101 is easy to process and manufacture.

[0070] In other embodiments, the hole may also be in other shapes, such as circular, semicircular, etc.

[0071] In one embodiment, the top surface of the dam body assembly is provided with stepping stones 2 at intervals.

[0072] Specifically, the stepping stone 2 is a stepping stone arranged on the top surface of the dam body assembly. Commonly used stepping stones 2 include processed stones made from natural stones, artificial stones produced by cement, concrete, etc., and wooden stepping stones 2. The shapes of the stepping stones 2 are naturally varied. The artificial stepping stones 2 are mostly regular shapes such as square and round, while the stepping stones 2 produced by processing natural stone materials are mostly irregular shapes. In this embodiment, stone stepping stones 2 are used, and the shapes of the stepping stones 2 are all approximately circular or elliptical, of different sizes, and are arranged at intervals on the top surface of the dam body assembly.

[0073] After installing Stepping Stone 2, pedestrians will not slip when walking on the dam surface, which is safer and the dam surface is more beautiful.

[0074] In one embodiment, boulders 3 are provided on the backwater side of the dam assembly.

[0075] Along the extension direction of the dam body assembly, at the bottom of the backwater side of the dam body assembly, that is, at the bottom of the dam body assembly close to the downstream side of the river, a certain height of boulders 3 are laid. The particle size of the boulders 3 can be 0.6 to 1.2 meters.

[0076] The arrangement of the boulders 3 can increase the overall stability of the weir and dam, and also effectively prevent erosion.

[0077] On the other hand, this embodiment also provides a river channel weir construction method, which is applied to the construction of river channel weirs. The structure of the river channel weir is as described in the above embodiment and will not be repeated here.

[0078] The river channel dam construction method includes the following steps:

[0079] Step 1: prefabricate and process a prefabricated dam body 101;

[0080] According to the exploration data before the construction of the weir, the overall parameters of the weir are designed, and then the entire weir is divided into multiple sections, each of which is a prefabricated dam body 101. At the same time, the relevant size data of the prefabricated dam body 101 are given, and the parameters of the straight section prefabricated dam body 101 can be the same, so that the straight section prefabricated dam body 101 can be produced by one mold, while the curved section prefabricated dam body 101 may have different parameters due to its own shape characteristics, so different molds need to be made accordingly. And when making the mold, the dam body 101 and the wing walls 1022 on both sides must be prefabricated so that the prefabricated dam body 101 and the wing walls 1022 can be cast and formed at one time.

[0081] The straight section prefabricated dam body 101 and the curved section prefabricated dam body 101 are both cast by concrete. During casting, connectors 1021 (rebars) can be embedded on both sides of the prefabricated dam body 101. After the prefabricated dam body 101 is manufactured, one end of the connector 1021 is fixed in the prefabricated dam body 101.

[0082] By prefabricating these prefabricated dam bodies 101 in factories, various adverse weather factors such as temperature and humidity in the construction area can be overcome, and these prefabricated dam bodies 101 can be directly constructed after being transported to the site, which greatly speeds up the construction progress and improves the construction efficiency.

[0083] Step 2: Arrange multiple prefabricated dam bodies 101 perpendicular to the direction of river flow;

[0084] A plurality of prefabricated dam bodies 101 are placed at designated positions at intervals according to the designed dam shape, and the interval between two adjacent prefabricated dam bodies 101 is not greater than the total length of the connecting pieces 1021 on the two adjacent prefabricated dam bodies 101 .

[0085] Step 3: connect two adjacent prefabricated dam bodies 101 through the connecting structure 102, and the two prefabricated dam bodies 101 at both ends are respectively connected to the soil on both sides of the river bank.

[0086] Specifically, firstly, the corresponding connectors 1021 on the two adjacent prefabricated dam bodies 101 are tied and connected, and then a mold is set, and concrete is poured on site between the two prefabricated dam bodies 101 to form a concrete structure. Finally, the concrete structure is connected to the prefabricated dam bodies 101 on both sides as a whole, and the connectors 1021 and wing walls 1022 are both located in the concrete structure and solidified with the concrete as a whole. On the side of the two prefabricated dam bodies 101 at both ends of the dam assembly facing the river bank, the connectors 1021 and wing walls 1022 on the prefabricated dam bodies 101 are embedded in the soil for connection.

[0087] The concrete structure and the prefabricated dam body 101 are connected to form a complete dam body assembly, and the connector 1021 in the concrete structure can increase the strength of the concrete structure, and the wing wall 1022 can increase the anti-seepage performance of the concrete structure.

[0088] Step 4: After the construction of the dam body components is completed, stepping stones 2 are set at intervals on the top surface of the dam body components, and boulders 3 are laid on the backwater side of the dam body components.

[0089] The stepping stones 2 are provided to facilitate people to walk on the dam body components. The boulders 3 provided can increase the overall stability of the dam.

[0090] Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.

Claims

1. A river dam, characterized in that: include: A dam body assembly, comprising: a plurality of prefabricated dam bodies (101) arranged perpendicular to the direction of water flow in a river channel, wherein adjacent prefabricated dam bodies (101) are connected via a connecting structure (102).

2. The river channel weir according to claim 1, characterized in that: The connection structure (102) comprises: a connection piece (1021) and a concrete structure; a plurality of the connection pieces (1021) are provided on both sides of the prefabricated dam body (101); the connection pieces (1021) on two adjacent prefabricated dam bodies (101) are correspondingly connected; the concrete structure is located between two adjacent prefabricated dam bodies (101); and the outer wall surface of the concrete structure is flush with the outer wall surface of the prefabricated dam body (101).

3. The river channel weir according to claim 2, characterized in that: The connection structure (102) further comprises: wing walls (1022) arranged on both sides of the prefabricated dam body (101).

4. The river channel weir according to claim 3, characterized in that: The plurality of wing walls (1022) are arranged at intervals along the water flow direction of the river channel.

5. The river channel weir according to claim 1, characterized in that: The prefabricated dam body (101) is a straight-segment prefabricated dam body (101) or a curved-segment prefabricated dam body (101).

6. The river channel weir according to claim 1, characterized in that: The prefabricated dam body (101) comprises: a foundation section (1011) and a wall section (1012), and the wall section (1012) is arranged on the foundation section (1011).

7. The river channel weir according to claim 6, characterized in that: The wall segment (1012) is provided with holes.

8. The river channel weir according to any one of claims 1 to 7, characterized in that: Steps (2) are arranged at intervals on the top surface of the dam body assembly.

9. The river channel weir according to any one of claims 1 to 7, characterized in that: The backwater side of the dam body assembly is provided with boulders (3).

10. A river channel dam construction method, applied to the river channel dam according to any one of claims 1 to 9, characterized in that: include: Prefabricate and process a prefabricated dam body (101); Arranging a plurality of the prefabricated dam bodies (101) perpendicular to the direction of water flow in the river; Two adjacent prefabricated dam bodies (101) are connected via a connection structure (102), and the two prefabricated dam bodies (101) at both ends are respectively connected to soil bodies on both sides of the river bank.