Fabricated comprehensive pipe gallery multi-section tensioning construction method

Through the multi-stage tensioning method and the use of limiters, the problems of uneven tensioning of pipe sections and large prestressed line losses in the prefabricated comprehensive pipeline corridor are solved, the strength and overall performance of pipe sections are improved, and the project cost is reduced .

CN118997222APending Publication Date: 2024-11-22MCC REAL ESTATE CHONGQING CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411374960.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-30
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

In the existing prefabricated integrated pipe gallery, uneven tensioning of the pipe sections leads to poor connection strength, and high prestress line loss and high cost.

Method used

The multi-stage tensioning method is adopted to control the casting of prefabricated pipe sections through the formwork, and the stoppers and water stops are installed on site, and prestressed lines are applied along the longitudinal direction to ensure uniform displacement of the pipe sections and seals are filled at the joints to reduce gaps.

Benefits of technology

The problem of uneven tensioning of the pipe joints is solved, which significantly reduces the loss of the prestressed line, improves the longitudinal connection strength between the pipe joints, optimizes the overall performance, and saves engineering investment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997222A_ABST
    Figure CN118997222A_ABST
Patent Text Reader

Abstract

The invention discloses an assembly type comprehensive pipe rack multi-section tensioning construction method which comprises the following construction steps that S1, when pipe rack pipe joints are prefabricated, a tensioning pipe joint of the prefabricated pipe rack pipe joints and a common pipe joint of the prefabricated pipe rack pipe joints are formed through formwork control pouring; s2, according to the size of the pipe joints of the pipe gallery, the number of the pipe joints which are tensioned jointly is determined, and meanwhile the length of a pre-stress line needed by tensioning is determined; s3, when the pipe gallery is installed on site, the common pipe joint is inserted between the two tensioning pipe joints, a water stop piece and a limiting stopper are arranged, tensioning is conducted through a prestress line, and in the tensioning process, the displacement of the prefabricated pipe gallery pipe joints is made to be uniform through the limiting stopper; and S4, after tensioning is completed, gaps of the overlapping surfaces are filled with sealing pieces at the overlapping surfaces of the pipe gallery joints. The construction method not only solves the problem of non-uniform tensioning of the pipe joints, but also greatly reduces the loss of the steel strands compared with a traditional tensioning mode, optimizes the overall performance, and saves the project investment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of municipal engineering, and in particular to a multi-segment tensioning construction method for an assembled integrated pipe gallery. Background Art

[0002] A comprehensive pipeline corridor is a tunnel space built under the municipal road, which integrates various engineering pipelines such as water supply and drainage, heat, gas, electricity, communications, radio and television, and is equipped with special inspection ports, feeding ports and other facilities. It unifies construction and management, eliminates the independent structures and earth excavation of the pipelines themselves, and can effectively and intensively utilize urban space resources.

[0003] Among them, underground integrated pipe corridors can effectively solve problems such as road zippers, and are of great significance to the intensive use of underground space. With the promotion of green construction technology, more and more underground pipe corridors are beginning to adopt prefabricated structures. For the connection between pipe sections of small-section integrated pipe corridors, the method of tensioning between pipe sections is now basically adopted. The longitudinal connection strength between pipe sections is increased by applying prestress, and the gap between pipe sections is reduced. However, the following problems were found in the above method: 1. The tensioning of pipe sections is uneven, resulting in gaps between pipe sections and poor connection strength; 2. The loss of prestressed wire is large, and a large number of prestressed wires are required, resulting in high costs.

[0004] Therefore, solving the uneven tensioning of pipe segments and reducing the loss of prestressed lines and increasing the connection strength are technical issues that need to be solved urgently. Summary of the invention

[0005] In view of this, the present invention provides a multi-segment tensioning construction method for an assembled integrated pipeline corridor, which solves the problem of uneven tensioning of pipe segments through multi-stage tensioning. Compared with traditional tensioning methods, it greatly reduces the loss of prestressed lines and has better overall performance.

[0006] The present invention provides a multi-segment tensioning construction method for an assembled integrated pipe gallery, which adopts the following technical solution:

[0007] A multi-segment tensioning construction method for an assembled integrated pipe gallery comprises the following construction steps:

[0008] S1: When prefabricating pipe gallery pipe sections, the tensioned pipe sections of the prefabricated pipe gallery pipe sections and the common pipe sections of the prefabricated pipe gallery pipe sections are respectively formed by pouring controlled by the template;

[0009] S2: According to the pipe gallery pipe segment size, determine the number of pipe segments to be tensioned together, and determine the length of the prestressed wire required for tensioning;

[0010] S3: When installing the pipe gallery on site, insert the common pipe section between the two tensioned pipe sections, set the water stop and the stopper, and tension the pipe section through the prestressed wire. During the tensioning process, the displacement of the prefabricated pipe gallery pipe section is uniform through the stopper;

[0011] S4: After the tensioning is completed, the gaps at the overlapping surfaces of the corridor joints are filled with seals.

[0012] Optionally, both ends of each pipe gallery pipe segment have socket components that fit together. When assembling at the construction site, a certain number of ordinary pipe segments are inserted before the two tensioning pipe segments. After water stops and limiters are arranged between the two pipe gallery pipe segments, prestress is applied longitudinally through prestressed lines for tensioning, so that the entire tensioning section forms an integral structure.

[0013] Optionally, the tensioning pipe segment includes a pipe segment body and a tensioning connection box, the tensioning connection box is arranged on the pipe segment body for connecting the prestressed wire, the pipe segment body is provided with a tensioning hole for accommodating the prestressed wire along the longitudinal direction, and the tensioning connection box is connected to the tensioning hole.

[0014] Optionally, the prestressed wires are arranged longitudinally at the armpit corners of the prefabricated pipe gallery sections.

[0015] Optionally, limiters are provided between the tensioned pipe sections and the common pipe sections and between adjacent common pipe sections, and the limiters are used to limit the lateral displacement of the pipe sections in the pipe gallery.

[0016] Optionally, the waterstop is a rubber waterstop, which is wrapped between two pipe gallery pipe sections and covers the limiter.

[0017] Optionally, the longitudinal section of the prefabricated pipe gallery segment is rectangular, and the prefabricated pipe gallery segment is a single-compartment pipe gallery or a double-compartment pipe gallery.

[0018] Optionally, the prefabricated pipe gallery pipe sections are cast in one piece.

[0019] Optionally, the limiter includes a connecting sleeve, a connecting rod and a spring. Two connecting rods are provided. The two connecting rods are respectively slidably fitted on both sides of the connecting sleeve. The spring is provided between the two connecting rods to apply a pre-tightening force to the two connecting rods in a direction toward each other. The connecting rods are used to connect to adjacent prefabricated pipe gallery sections.

[0020] Optionally, a fixing rod is arranged between the connecting rods on the same side.

[0021] In summary, the present invention includes at least one of the following beneficial technical effects: the construction method not only solves the problem of uneven tensioning of pipe segments, but also greatly reduces the loss of steel strands compared to traditional tensioning methods, optimizes the overall performance, and saves engineering investment. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0023] Figure 1 It is an overall schematic diagram of a multi-segment tensioning construction method of an assembled integrated pipe gallery according to an embodiment of the present invention;

[0024] Figure 2 is a plan view of the tensioning section of an embodiment of the present invention;

[0025] Figure 3 It is a schematic diagram of the limiter structure of the tensioning section according to an embodiment of the present invention.

[0026] Explanation of the accompanying drawings: 1. tensioning pipe joint; 2. limiter; 21. connecting sleeve; 22. connecting rod; 23. spring; 24. fixing rod; 3. tensioning connection box; 4. tensioning hole; 5. steel strand; 6. ordinary pipe joint. DETAILED DESCRIPTION

[0027] The following describes the embodiments of the present invention through specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention.

[0028] The following is combined with Figure 1-3 The present invention is described in further detail.

[0029] An embodiment of the present invention discloses a multi-segment tensioning construction method for an assembled integrated pipe gallery.

[0030] Reference Figure 1 , Figure 2 , Figure 3 , a multi-segment tensioning construction method for an assembled integrated pipe gallery, comprising the following construction steps:

[0031] S1: When prefabricating pipe gallery pipe segments, the tensioned pipe segments 1 of the prefabricated pipe gallery pipe segments and the common pipe segments 6 of the prefabricated pipe gallery pipe segments are respectively formed by casting controlled by the template;

[0032] S2: According to the pipe gallery pipe segment size, determine the number of pipe segments to be tensioned together, and determine the length of the prestressed wire required for tensioning;

[0033] S3: When installing the pipe gallery on site, insert the common pipe segment 6 between the two tensioned pipe segments 1, and set the water stop and the stopper 2, and tension is performed through the prestressed wire. During the tensioning process, the displacement of the prefabricated pipe gallery pipe segment is uniform through the stopper 2;

[0034] S4: After the tensioning is completed, the gaps at the overlapping surfaces of the corridor joints are filled with seals.

[0035] This construction method not only solves the problem of uneven tensioning of pipe sections, but also greatly reduces the loss of steel strands 5 compared to traditional tensioning methods, optimizes overall performance, and saves project investment. The use of limiters 2 and a multi-stage tensioning method solves the problem of uneven tensioning of pipe sections; compared to traditional tensioning methods, the loss of steel strands 5 is greatly reduced, the overall performance is further enhanced, the longitudinal connection strength between pipe sections of the pipe gallery is improved, and the gap between pipe sections is reduced.

[0036] In this embodiment, the prefabricated pipe gallery pipe section is integrally cast to ensure its overall mechanical and waterproof properties. The longitudinal section of the prefabricated pipe gallery pipe section is rectangular, and the prefabricated pipe gallery pipe section is a single-compartment pipe gallery or a double-compartment pipe gallery. The double-compartment pipe gallery consists of two parallel pipes, which can carry more lines and has higher fault tolerance and reliability. The single-compartment pipe gallery has only one pipe, with a relatively simple structure and limited carrying capacity.

[0037] Each pipe gallery pipe section has a socket member that fits in with each other at both ends. Specifically, a connection groove is provided at one end of the pipe gallery pipe section and a connection block is provided at the other end. During assembly, the connection block is clamped in the connection groove of the adjacent pipe gallery pipe section to form a socket structure. The socket structure itself has certain waterproofness and good mechanical properties. In combination with the stopper 2 and the waterproof member, the waterproofness and mechanical properties can be further improved. Under the action of the prestressed wire, the connection between the adjacent pipe gallery pipe sections is more stable, the pipe section tensioning is more uniform, the overall performance is further enhanced, the longitudinal connection strength between the pipe gallery pipe sections is improved, and the pipe section gap is reduced. During assembly at the construction site, a certain number of ordinary pipe sections 6 are inserted before the two tensioned pipe sections 1. In this embodiment, four pipe sections are inserted. After the water stop and the stopper 2 are arranged between the two pipe gallery pipe sections, the prestress is applied longitudinally by the prestressed wire for tensioning, so that the entire tensioning section forms an integral structure.

[0038] The tensioning pipe segment 1 includes a pipe segment body and a tensioning connection box 3. The tensioning connection box 3 is arranged on the pipe segment body for connecting the prestressed wire. The pipe segment body is longitudinally provided with a tensioning hole 4 for accommodating the prestressed wire. The tensioning connection box 3 is connected to the tensioning hole 4. The prestressed wire extends from the tensioning hole 4 for connecting the tensioning equipment. When the tensioning equipment is started, the prestressed wire begins to be tensioned, and the pipe segment body begins to move.

[0039] In this embodiment, the pipe segment body includes a side plate, a bottom plate and a top plate, a chamber is formed between the side plate, the bottom plate and the top plate, and an armpit angle is provided at the connection of the side plate, the bottom plate and the top plate. The prestressed wire is arranged at the armpit angle of the prefabricated pipe gallery pipe segment in the longitudinal direction.

[0040] Limiters 2 are provided between the tensioning pipe section 1 and the common pipe section 6 and between adjacent common pipe sections 6. The limiters 2 are used to limit the lateral displacement of the pipe gallery pipe section and ensure the reliability of the connection between the pipe gallery pipe sections. In this embodiment, the limiter 2 includes a connecting sleeve 21, a connecting rod 22 and a spring 23. A receiving groove for receiving the limiter 2 is provided on the side wall of the adjacent pipe gallery pipe section. Two connecting rods 22 are provided. The two connecting rods 22 are respectively slidably matched on both sides of the connecting sleeve 21. The spring 23 is provided between the two connecting rods 22 to apply a pre-tightening force to the two connecting rods 22 in a direction of approaching each other. The connecting rod 22 is used to connect with the receiving groove of the adjacent prefabricated pipe gallery pipe section. A fixing rod 24 is arranged between the connecting rods 22 on the same side, and the fixing rod 24 links the connecting rods 22 on the same side. The connecting rods 22 on the same side are moved by the fixing rod 24 with the same displacement. The setting of the limiter 2 can ensure that the displacement of each pipe gallery segment is uniform, the longitudinal connection strength between the pipe gallery segments is improved, the gap between the pipe gallery segments is reduced, and the overall performance is further enhanced.

[0041] In other embodiments, the limiter 2 is a rectangular block, and a receiving groove for receiving the limiter 2 is opened on the side wall of the adjacent pipe gallery pipe section. The limiter 2 is slidably fitted in the receiving groove. Furthermore, two limiters 2 are spaced apart on each surface.

[0042] The water stop is a rubber water stop, which is wound between two pipe gallery pipe sections and covers the limiter 2.

[0043] In this embodiment, the prestressed wire is a steel strand 5 arranged in the longitudinal direction. The steel strand 5 has excellent tensile strength and strong overload resistance (the strength of the steel strand 5 is often more than twice that of ordinary steel wire), corrosion resistance, wear resistance (the surface of the steel strand 5 is galvanized and coated, and has high corrosion resistance and wear resistance, and can be used for a long time in harsh environments), low production cost and electrical function advantages, and is suitable for small-span transmission lines in special occasions.

[0044] The construction method of the present invention not only solves the problem of uneven tensioning of pipe sections, but also greatly reduces the loss of steel strands 5 compared to traditional tensioning methods, thereby optimizing overall performance. This innovative solution is not only simple and practical, but also universal, providing an efficient and reliable solution for the tensioning of various prefabricated structures. Whether it is an urban underground integrated pipe gallery or other prefabricated structures, this technology can be used to reduce tensioning consumables and save engineering investment.

[0045] This article uses specific examples to illustrate the principles and implementation methods of the present invention. The description of the above embodiments is only used to help understand the method of the present invention and its core ideas. The above are only preferred implementation methods of the present invention. It should be pointed out that due to the limitations of textual expression, there are objectively infinite specific structures. For ordinary technicians in this technical field, without departing from the principles of the present invention, they can also make several improvements, modifications or changes, and can also combine the above technical features in an appropriate manner; these improvements, modifications, changes or combinations, or the direct application of the inventive concept and technical solution to other occasions without improvement, should be regarded as the protection scope of the present invention.

Claims

1. A multi-segment tensioning construction method for an assembled integrated pipe gallery, characterized in that: The construction steps include: S1: When prefabricating pipe gallery pipe sections, the tensioned pipe sections of the prefabricated pipe gallery pipe sections and the common pipe sections of the prefabricated pipe gallery pipe sections are respectively formed by pouring controlled by the template; S2: According to the pipe gallery pipe segment size, determine the number of pipe segments to be tensioned together, and determine the length of the prestressed wire required for tensioning; S3: When installing the pipe gallery on site, insert the common pipe section between the two tensioned pipe sections, set the water stop and the stopper, and tension the pipe section through the prestressed wire. During the tensioning process, the displacement of the prefabricated pipe gallery pipe section is uniform through the stopper; S4: After the tensioning is completed, the gaps at the overlapping surfaces of the pipe gallery joints are filled with seals.

2. The multi-segment tensioning construction method of the assembled integrated pipe gallery according to claim 1 is characterized in that: Both ends of each pipe gallery pipe segment have socket components that fit together. When assembling at the construction site, a certain number of ordinary pipe segments are inserted before the two tensioning pipe segments. After water stops and limiters are arranged between the two pipe gallery pipe segments, prestress is applied longitudinally through prestressed lines for tensioning, so that the entire tensioning section forms an integral structure.

3. The multi-segment tensioning construction method of the assembled integrated pipe gallery according to claim 2 is characterized in that: The tensioning pipe segment includes a pipe segment body and a tensioning connection box. The tensioning connection box is arranged on the pipe segment body for connecting the prestressed wire. The pipe segment body is longitudinally provided with a tensioning hole for accommodating the prestressed wire. The tensioning connection box is connected to the tensioning hole.

4. The multi-segment tensioning construction method of the assembled integrated pipe gallery according to claim 3 is characterized in that: The prestressed wires are arranged longitudinally at the armpit corners of the prefabricated pipe gallery sections.

5. The multi-segment tensioning construction method of the assembled integrated pipe gallery according to claim 2 is characterized in that: Limiters are arranged between the tensioned pipe joints and ordinary pipe joints, as well as between adjacent ordinary pipe joints. The limiters are used to limit the lateral displacement of the pipe joints and the lateral displacement of the pipe gallery.

6. The multi-segment tensioning construction method of the assembled integrated pipe gallery according to claim 1 is characterized in that: The waterstop is a rubber waterstop, which is wrapped between two pipe gallery sections and covers the limiter.

7. The multi-segment tensioning construction method of the assembled integrated pipe gallery according to claim 1 is characterized in that: The longitudinal section of the prefabricated pipe gallery segment is rectangular, and the prefabricated pipe gallery segment is a single-compartment pipe gallery or a double-compartment pipe gallery.

8. The multi-segment tensioning construction method of the assembled integrated pipe gallery according to claim 7 is characterized in that: The prefabricated pipe gallery pipe sections are cast in one piece.

9. The multi-segment tensioning construction method of the assembled integrated pipe gallery according to claim 5, characterized in that: The limiter includes a connecting sleeve, a connecting rod and a spring. Two connecting rods are provided. The two connecting rods are slidingly fitted on both sides of the connecting sleeve respectively. The spring is provided between the two connecting rods and is used to apply a pre-tightening force to the two connecting rods in a direction of approaching each other. The connecting rods are used to connect with adjacent prefabricated pipe gallery pipe sections.

10. The multi-segment tensioning construction method of the assembled integrated pipe gallery according to claim 9, characterized in that: A fixing rod is arranged between the connecting rods on the same side.