By setting up a front expander and a backpressure regulating fan in the gas turbine combined cycle unit, adjusting the compressor flow rate and gas turbine back pressure, the problem of low efficiency under partial load is solved, and more efficient gas turbine operation and wider The load regulation range improves the unit's economy and thermoelectric ratio.
Patent Information
- Application Number
- CN202411058147.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-02
- Publication Date
- 2024-11-22
AI Technical Summary
The efficiency of the gas turbine combined cycle unit decreases under partial load, which restricts the economicality of its peak-shaving operation. The existing variable load regulation strategy is relatively low, especially the increase in the gas turbine intake temperature (TIT) is difficult to achieve.
By setting up a front expander in front of the compressor and setting up a back pressure adjustment fan behind the waste heat boiler, adjusting the compressor intake air flow and gas turbine back pressure, the efficient operation of the gas turbine within a wider load range is achieved. The specific method includes adjusting the expansion ratio of the front expander and the back pressure to adjust the pressure ratio of the fan, and adjusting the fuel quantity to keep the TIT and TET constant.
It significantly improves the operating efficiency and peak-shaving performance of the gas turbine under partial load, expands the thermoelectric ratio, and improves the heating capacity and operational economy of the unit.
Smart Images

Figure CN118997919A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of gas turbine combined cycle, and in particular to a variable load operation control system and method for a gas turbine combined cycle unit. Background Art
[0002] Guided by the "dual carbon" goal, my country's energy utilization mode and energy structure are undergoing profound changes, and the proportion of renewable energy is increasing, posing a challenge to the peak-shaving capacity of the power grid. Gas turbine combined cycle units are becoming increasingly important in the energy system due to their high efficiency, strong peak-shaving capacity and low emissions. However, their efficiency varies widely, and their efficiency drops rapidly under partial load, which restricts the economy of their peak-shaving operation. Improving the efficiency of combined cycle units under partial load is crucial to improving energy utilization efficiency.
[0003] The gas turbine inlet temperature (TIT) is the key factor affecting the performance of the gas turbine combined cycle. Improving TIT helps to improve thermal efficiency. At present, there are three main variable load regulation strategies for heavy-duty gas turbines: 1) Adjustment according to the law of constant gas turbine inlet temperature (TIT). This strategy follows the law of constant TIT and reduces the air flow by gradually closing the opening of the compressor inlet guide vanes (IGV) to achieve the purpose of reducing power generation. Under this regulation law, the compressor pressure ratio decreases as the flow rate decreases, the gas turbine expansion ratio decreases, and the gas turbine exhaust temperature (TET) increases when TIT remains unchanged. In order to ensure the safety of the operation of the steam bottom cycle equipment, the load regulation range of this regulation method is relatively narrow; 2) Adjustment according to the law of constant gas turbine exhaust temperature (TET). This strategy follows the law of constant TET. The air flow rate is reduced by gradually closing the IGV opening. Under this regulation law, the compressor pressure ratio also decreases with the decrease in flow rate, the gas turbine expansion ratio decreases, and the gas turbine inlet temperature (TIT) decreases when TET remains unchanged. The efficiency is slightly lower than the equal TIT regulation strategy; 3) Pure fuel quantity regulation strategy. This strategy does not rely on IGV to adjust the air flow rate. The air flow rate remains almost unchanged under different loads. The unit power is reduced by reducing the amount of fuel entering the combustion chamber. Due to the operating characteristics of the compressor and gas turbine, when this strategy is adopted, both TIT and TET show a downward trend. The efficiency is the worst among the three strategies. It is generally used for load regulation when the IGV reaches the minimum opening at low load. Through the comparison of the above three regulation strategies, it can be found that how to improve TIT under partial load is the key to improving unit efficiency. Summary of the invention
[0004] The object of the present invention is to provide a gas turbine combined cycle unit that can increase the gas turbine intake temperature, and can adjust the compressor intake flow and intake pressure by compressor intake expansion, and adjust the gas turbine expansion ratio and exhaust temperature by gas turbine back pressure, so as to solve the problems raised in the above background technology.
[0005] To achieve the above object, the present invention provides the following solutions:
[0006] A variable load operation control system for a gas turbine combined cycle unit comprises an air intake filter, a compressor, a combustion chamber, a gas turbine, a waste heat boiler and a chimney connected in sequence, a pre-expander is arranged between the compressor and the air intake filter, and a back pressure regulating fan is arranged between the waste heat boiler and the chimney;
[0007] The variable load operation method of the variable load operation control system of the gas turbine combined cycle unit is: the air flow of the gas turbine is regulated by adjusting the expansion ratio of the pre-expander, and the pressure ratio of the back pressure regulating fan is adjusted to achieve the regulation of the turbine inlet and the exhaust gas temperature of the gas turbine. The two cooperate to achieve efficient operation of the combined cycle under variable load.
[0008] Further, the air intake filter is connected to the compressor through the pre-expander main air flow channel and the pre-expander bypass air flow channel respectively;
[0009] The pre-expander main air flow passage is provided with a pre-expander main air flow passage guide vane, a pre-expander main air flow passage guide vane driving mechanism and the pre-expander, and the pre-expander main air flow passage guide vane driving mechanism is used to adjust the pre-expander main air flow passage guide vane to be in an open or closed state;
[0010] The front expander bypass air flow passage is provided with a front expander bypass air flow passage guide vane and a front expander bypass air flow passage guide vane driving mechanism inside, and the front expander bypass air flow passage guide vane driving mechanism is used to adjust the front expander bypass air flow passage guide vane to be in an open or closed state;
[0011] The waste heat boiler is connected to the chimney through a back pressure regulating fan main flue and a back pressure regulating fan bypass flue respectively;
[0012] The main flue of the back pressure regulating fan is provided with a main flue damper valve of the back pressure regulating fan and the back pressure regulating fan;
[0013] The back pressure regulating fan bypass flue is provided with a back pressure regulating fan bypass flue damper valve;
[0014] The inlet of the back pressure regulating fan is provided with a fan inlet guide vane;
[0015] The pre-expander is provided with a nozzle with adjustable nozzle size.
[0016] The present invention also discloses a variable load operation control method for a gas turbine combined cycle unit, which is applied to the variable load operation control system for the gas turbine combined cycle unit, and comprises:
[0017] Compressor intake flow and pressure control: closing the pre-expander air bypass flow guide vane through the pre-expander air flow guide vane actuator, and opening the pre-expander air flow guide vane through the pre-expander air flow guide vane actuator, so that air enters the compressor from the pre-expander main air flow passage (3), adjusting the nozzle size of the pre-expander nozzle or the rotation speed of the pre-expander to adjust the intake flow and expansion ratio of the pre-expander, thereby achieving the adjustment of the compressor intake flow and intake pressure;
[0018] as well as,
[0019] Gas turbine back pressure control: By adjusting the speed of the back pressure regulating fan or the fan inlet guide vanes at the inlet of the back pressure regulating fan to adjust the back pressure of the gas turbine, the gas turbine back pressure reduction control or gas turbine back pressure increase control is performed to achieve continuous adjustment of the gas turbine back pressure between a certain negative pressure and a certain positive pressure.
[0020] Furthermore, the gas turbine back pressure control includes two situations: gas turbine back pressure reduction control and gas turbine back pressure increase control;
[0021] When it is necessary to reduce the back pressure of the gas turbine, the following methods are included:
[0022] Close the flue damper valve of the back pressure regulating fan bypass, and open the flue damper valve of the back pressure regulating fan main flue, so that the flue gas enters the chimney from the back pressure regulating fan main flue;
[0023] Increase the opening degree of the fan inlet guide vane at the inlet of the back pressure regulating fan, increase the pressure ratio of the back pressure regulating fan, or increase the speed of the back pressure regulating fan, increase the pressure ratio of the back pressure regulating fan, and achieve the reduction regulation of the gas turbine back pressure;
[0024] When it is necessary to regulate the back pressure of the gas turbine, the following methods are included:
[0025] Close the flue damper valve of the back pressure regulating fan bypass, and open the flue damper valve of the back pressure regulating fan main flue, so that the flue gas enters the chimney from the back pressure regulating fan main flue;
[0026] Reduce the opening degree of the fan inlet guide vane at the inlet of the back pressure regulating fan, reduce the pressure ratio of the back pressure regulating fan, or reduce the speed of the back pressure regulating fan, reduce the pressure ratio of the back pressure regulating fan, or make the back pressure regulating fan rotate in the opposite direction to increase the flow resistance of the flue gas and achieve the increase regulation of the back pressure of the gas turbine.
[0027] Furthermore, it also includes: compressor intake expansion + fuel quantity regulation + gas turbine back pressure regulation:
[0028] When reducing the load, reduce the nozzle size of the pre-expander nozzle, reduce the air flow entering the pre-expander and compressor, and reduce the compressor inlet pressure, gradually increase the opening degree of the fan inlet guide vane at the inlet of the back pressure regulating fan or increase the speed of the back pressure regulating fan to reduce the gas turbine back pressure, and adjust the fuel amount to keep TIT and TET constant at the design value;
[0029] When the load is increased, the nozzle size of the pre-expander nozzle is increased to increase the air flow entering the pre-expander and the compressor, and the opening degree of the fan inlet guide vane at the inlet of the back pressure regulating fan is gradually reduced or the speed of the back pressure regulating fan is reduced to increase the gas turbine back pressure, and the fuel amount is adjusted to keep TIT and TET constant at the design value.
[0030] Furthermore, it also includes: compressor IGV + fuel quantity + gas turbine back pressure adjustment:
[0031] When reducing the load, close the compressor IGV opening, reduce the air flow entering the compressor, adjust the fuel amount to keep TIT constant at the design value, gradually increase the back pressure to adjust the opening degree of the fan inlet guide vane at the fan inlet or increase the back pressure to adjust the fan speed to reduce the gas turbine back pressure and keep TET constant;
[0032] When the load is increased, the compressor IGV opening is increased to increase the air flow entering the compressor, the fuel amount is adjusted to keep TIT constant at the design value, and the back pressure is gradually reduced to adjust the opening degree of the fan inlet guide vanes at the fan inlet or reduce the back pressure to adjust the fan speed to increase the gas turbine back pressure and keep TET constant.
[0033] Furthermore, it also includes: fuel quantity + gas turbine back pressure regulation:
[0034] When the load is reduced, the IGV opening remains unchanged, and the back pressure is gradually reduced to adjust the opening degree of the fan inlet guide vane at the fan inlet, or the back pressure is reduced to adjust the fan speed to increase the gas turbine back pressure, and the TET is controlled to be constant in combination with the fuel quantity adjustment;
[0035] When the load is increased, the IGV opening remains fixed, and the opening degree of the fan inlet guide vane at the back pressure regulating fan inlet is gradually increased or the back pressure regulating fan speed is increased to reduce the gas turbine back pressure, and the TET is controlled constant in combination with the fuel quantity adjustment.
[0036] It can be seen from the above technical solution that, compared with the prior art, the beneficial effects of the present invention are:
[0037] 1. A pre-expander is installed before the compressor of the gas turbine to assist the compressor in adjusting the flow rate, inlet pressure and pressure ratio. A back-pressure regulating fan is installed after the waste heat boiler. Through the cooperation of the expander and the back-pressure regulating fan, the gas turbine is assisted to achieve a wide range of flow regulation under variable operating conditions, so that the total pressure ratio and TIT of the gas turbine are maintained at the design operating level within a wider partial load range, thereby achieving better peak-shaving performance.
[0038] 2. The present invention can significantly increase the turbine inlet temperature under all operating conditions, significantly improve the operating performance under all operating conditions, and help improve the operating economy of the gas turbine combined cycle unit when participating in peak load regulation.
[0039] 3. The present invention can realize continuous adjustment of the back pressure of the gas turbine within a range from a certain negative pressure to a certain positive pressure. In the heating season, the exhaust pressure of the gas turbine can be increased to increase the temperature of the flue gas entering the waste heat boiler, thereby increasing the power ratio of the steam low cycle in the combined cycle, which is beneficial to improving the heating capacity of the unit and expanding the thermal power ratio. BRIEF DESCRIPTION OF THE DRAWINGS
[0040] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0041] Figure 1 It is a flow chart of a variable load operation control system of a gas turbine combined cycle unit in an embodiment of the present invention;
[0042] Figure 2 A graph showing a comparison between the operating performance of the variable load operation control system of the gas turbine combined cycle unit in an embodiment of the present invention and the efficiency of the gas turbine in a traditional control scheme;
[0043] Figure 3 It is a comparative relationship diagram of the operating performance of the variable load operation control system of the gas turbine combined cycle unit in the embodiment of the present invention and the combined cycle efficiency of the traditional control scheme.
[0044] Description of reference numerals:
[0045] 1. Air intake filter; 2. Guide vane of main air flow channel of pre-expander; 3. Main air flow channel of pre-expander; 4. Guide vane of bypass air flow channel of pre-expander; 5. Bypass air flow channel of pre-expander; 6. Drive mechanism of guide vane of air flow channel of pre-expander; 7. Drive mechanism of guide vane of bypass air flow channel of pre-expander; 8. Pre-expander; 9. First generator; 10. Compressor; 11. Combustion chamber; 12. Gas turbine; 13. , the second generator; 14. waste heat boiler; 15. main flue of back-pressure regulating fan; 16. damper valve of main flue of back-pressure regulating fan; 17. back-pressure regulating fan; 18. electric motor; 19. bypass flue of back-pressure regulating fan; 20. damper valve of bypass flue of back-pressure regulating fan; 21. chimney; 22. high-pressure cylinder of steam turbine; 23. intermediate-pressure cylinder of steam turbine; 24. low-pressure cylinder of steam turbine; 25. condenser; 26. the third generator. DETAILED DESCRIPTION
[0046] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0047] In the description of the present application, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0048] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, unless otherwise specified, "plurality" means two or more.
[0049] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0050] In order to better understand the purpose, structure and function of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings.
[0051] Example
[0052] See also Figure 1 As shown, a variable load operation control system for a gas turbine combined cycle unit comprises an air intake filter 1, a compressor 10, a combustion chamber 11, a gas turbine 12, a waste heat boiler 14 and a chimney 21 which are connected in sequence, a pre-expander 8 is arranged between the compressor 10 and the air intake filter 1, and a back pressure regulating fan 17 is arranged between the waste heat boiler 14 and the chimney 21;
[0053] The variable load operation method of the variable load operation control system of the gas turbine combined cycle unit is: the air flow of the gas turbine is regulated by adjusting the expansion ratio of the pre-expander 8, and the pressure ratio of the back pressure regulating fan 7 is adjusted to achieve the regulation of the turbine inlet and the exhaust gas temperature of the gas turbine. The two cooperate to achieve efficient operation of the combined cycle under variable load.
[0054] Specifically, the air intake filter is connected to the compressor 10 through the pre-expander main air flow channel 3 and the pre-expander bypass air flow channel 5 respectively;
[0055] The pre-expander main air flow passage 3 is provided with a pre-expander main air flow passage guide vane 2, a pre-expander main air flow passage guide vane driving mechanism 6 and a pre-expander 8. The pre-expander main air flow passage guide vane driving mechanism 6 is used to adjust the pre-expander main air flow passage guide vane 2 to be in an open or closed state.
[0056] The front expander bypass air flow passage 5 is provided with a front expander bypass air flow passage guide vane 4 and a front expander bypass air flow passage guide vane driving mechanism 7. The front expander bypass air flow passage guide vane driving mechanism 7 is used to adjust the front expander bypass air flow passage guide vane 4 to be in an open or closed state.
[0057] The waste heat boiler 14 is connected to the chimney 21 through the back pressure regulating fan main flue 15 and the back pressure regulating fan bypass flue 19 respectively;
[0058] The back pressure regulating fan main flue 15 is provided with a back pressure regulating fan main flue damper valve 16 and a back pressure regulating fan 17;
[0059] A back-pressure regulating fan bypass flue damper valve 20 is provided on the back-pressure regulating fan bypass flue 19 .
[0060] Specifically, the present invention arranges a pre-expander 8 before the compressor 10 of the gas turbine to assist the compressor 10 in regulating the flow rate, inlet pressure and pressure ratio, and arranges a back-pressure regulating fan 17 after the waste heat boiler 14. Through the cooperation of the pre-expander 8 and the back-pressure regulating fan 17, the auxiliary gas turbine can achieve a wide range of flow rate regulation under variable operating conditions, so that the total pressure ratio and the gas turbine inlet temperature of the gas turbine are maintained at the design operating level within a wider partial load range, thereby achieving more excellent peak-shaving performance.
[0061] It should be noted that the inlet of the back pressure regulating fan 17 is provided with a fan inlet guide vane, and the pressure ratio of the back pressure regulating fan 17 is adjusted by controlling the opening degree of the fan inlet guide vane.
[0062] It should be noted that the pre-expander 8 is provided with a nozzle with an adjustable nozzle size, and the intake flow rate and expansion ratio of the pre-expander 8 are adjusted by adjusting the nozzle size of the nozzle.
[0063] The embodiment of the present invention also provides a method for regulating the gas turbine expansion ratio and exhaust temperature of the variable load operation control system of the gas turbine combined cycle unit as described above, including two situations: gas turbine back pressure reduction control and gas turbine back pressure increase control;
[0064] When it is necessary to reduce the back pressure of the gas turbine, the following methods are included:
[0065] Close the flue damper valve 20 of the back pressure regulating fan bypass, and open the flue damper valve 16 of the back pressure regulating fan main flue, so that the flue gas enters the chimney 21 from the back pressure regulating fan main flue 15;
[0066] Increase the opening degree of the fan inlet guide vane at the inlet of the back pressure regulating fan 17, increase the pressure ratio of the back pressure regulating fan 17, or increase the speed of the back pressure regulating fan 17, increase the pressure ratio of the back pressure regulating fan 17, and achieve the lowering regulation of the back pressure of the gas turbine 12;
[0067] When it is necessary to regulate the back pressure of the gas turbine, the following methods are included:
[0068] Close the flue damper valve 20 of the back pressure regulating fan bypass, and open the flue damper valve 16 of the back pressure regulating fan main flue, so that the flue gas enters the chimney 21 from the back pressure regulating fan main flue 15;
[0069] Reduce the opening degree of the fan inlet guide vane at the inlet of the back pressure regulating fan 17, reduce the pressure ratio of the back pressure regulating fan 17, or reduce the rotation speed of the back pressure regulating fan 17, reduce the pressure ratio of the back pressure regulating fan 17, or make the back pressure regulating fan 17 rotate in the opposite direction, increase the flow resistance of the flue gas, and realize the increase regulation of the back pressure of the gas turbine 12.
[0070] The embodiment of the present invention further provides a method for regulating the compressor intake flow and intake pressure of the variable load operation control system of the gas turbine combined cycle unit as described above, including the following method:
[0071] The pre-expander air bypass flow channel guide vane actuator 7 is used to close the pre-expander air bypass flow channel guide vane 4, and the pre-expander air flow channel guide vane actuator 6 is used to open the pre-expander air flow channel guide vane 2, so that air enters the compressor 10 from the pre-expander main air flow channel 3, and the nozzle size of the nozzle or the rotation speed of the pre-expander is adjusted to adjust the intake flow rate and expansion ratio entering the pre-expander 8, thereby realizing the adjustment of the intake flow rate and intake pressure of the compressor 10.
[0072] It should be noted that the variable load operation control system of the gas turbine combined cycle unit in this embodiment also includes a first generator 9, a second generator 13, an electric motor 18, a steam turbine high pressure cylinder 22, a steam turbine intermediate pressure cylinder 23, a steam turbine low pressure cylinder 24, a condenser 25 and a third generator 26, and the specific connection relationship is as follows: Figure 1 As shown, no more details are given here.
[0073] It should be noted that the air compressed by the compressor 10 enters the combustion chamber 11 and the high-temperature combustion gas generated by the combustion of the fuel enters the gas turbine 12. The combustion gas expands and does work in the gas turbine 13 and then enters the waste heat boiler 14. A back-pressure regulating fan main flue 15 and a back-pressure regulating fan bypass flue 19 connected in parallel are arranged at the outlet of the waste heat boiler. A back-pressure regulating fan main flue damper valve 16 and a back-pressure regulating fan 17 are arranged in the back-pressure regulating fan main flue 15. A back-pressure regulating fan bypass flue damper valve 20 is arranged in the back-pressure regulating fan bypass flue 19. By adjusting the back-pressure regulating fan main flue damper valve 16 and the back-pressure regulating fan bypass flue damper valve 20, the flue gas at the outlet of the waste heat boiler 14 can be controlled to enter the chimney 21 through the back-pressure regulating fan main flue 15 or the back-pressure regulating fan bypass flue 19.
[0074] The air enters the main air flow passage 3 of the pre-expander, expands and performs work in the pre-expander 8, and the air pressure is reduced. The expansion effect of the pre-expander 8 is used to reduce the pressure and flow of the air inlet of the compressor 10;
[0075] The flue gas at the outlet of the waste heat boiler 14 enters the back pressure regulating fan 17 in the main flue 15 of the back pressure regulating fan. The back pressure regulating fan 17 can reduce the pressure of the waste heat boiler 14 by continuously sucking and discharging the flue gas and maintain it at a certain vacuum degree, thereby achieving the regulation of the outlet pressure of the gas turbine 12;
[0076] When the pre-expander 8 is not enabled or the equipment in the pre-expander main air flow passage 3 needs to be repaired, the pre-expander main air flow passage guide vane 2 is closed by adjusting the pre-expander main air flow passage guide vane actuator 6, and the pre-expander bypass air flow passage guide vane actuator 7 is adjusted to open the pre-expander bypass air flow passage guide vane 4, and the air enters the compressor 10 through the pre-expander bypass air flow passage 5;
[0077] When the back pressure regulating fan 17 is not enabled or the equipment in the back pressure regulating fan main flue 15 needs to be repaired, the back pressure regulating fan main flue damper valve 16 is closed, the back pressure regulating fan bypass flue damper valve 20 is opened, and the flue gas enters the chimney 21 through the back pressure regulating fan bypass flue 19.
[0078] It should be noted that the above-mentioned method for adjusting the gas turbine expansion ratio and exhaust temperature of the variable load operation control system of the gas turbine combined cycle unit and the method for adjusting the compressor intake flow and intake pressure of the variable load operation control system of the gas turbine combined cycle unit can be combined with the compressor inlet adjustable guide vane IGV and fuel amount adjustment method to realize the gas turbine combined cycle power control:
[0079] ① Compressor intake expansion + fuel quantity regulation + gas turbine back pressure regulation: In this combined regulation mode, the load operation range of equal TIT and TET can be expanded. When the load is reduced, the nozzle size of the nozzle of the pre-expander 8 is reduced, the air flow entering the pre-expander 8 and the compressor 10 is reduced, and the inlet pressure of the compressor 10 is reduced. The opening degree of the fan inlet guide vane set at the inlet of the back pressure regulating fan 17 is gradually increased or the speed of the back pressure regulating fan 19 is increased to reduce the back pressure of the gas turbine, and the fuel quantity is adjusted to keep TIT and TET constant at the design value; when the load is increased, the nozzle size of the nozzle of the pre-expander 8 is increased, the air flow entering the pre-expander 8 and the compressor 10 is increased, the opening degree of the fan inlet guide vane set at the inlet of the back pressure regulating fan 17 is gradually reduced or the speed of the back pressure regulating fan 17 is reduced to increase the back pressure of the gas turbine, and the fuel quantity is adjusted to keep TIT and TET constant at the design value.
[0080] ② Compressor IGV + fuel quantity + gas turbine back pressure regulation: In this combined regulation mode, equal TIT and equal TET regulation can be achieved. When reducing the load, close the compressor IGV opening, reduce the air flow entering the compressor, adjust the fuel quantity to keep TIT constant at the design value, gradually increase the opening degree of the fan inlet guide vane set at the inlet of the back pressure regulating fan 17 or increase the speed of the back pressure regulating fan 19 to reduce the gas turbine back pressure and keep TET constant; when increasing the load, increase the compressor IGV opening, increase the air flow entering the compressor, adjust the fuel quantity to keep TIT constant at the design value, gradually reduce the opening degree of the fan inlet guide vane set at the inlet of the back pressure regulating fan 17 or reduce the speed of the back pressure regulating fan 17 to increase the gas turbine back pressure and keep TET constant.
[0081] ③ Fuel quantity + gas turbine back pressure regulation: In this combined regulation mode, in the low load area, equal TET regulation can be achieved by increasing the gas turbine back pressure. When the load is reduced, the IGV opening remains unchanged, and the opening degree of the fan inlet guide vane set at the inlet of the back pressure regulating fan 17 is gradually reduced, or the speed of the back pressure regulating fan 17 is reduced to increase the gas turbine back pressure, and the fuel quantity regulation is combined to control the TET constant; when the load is increased, the IGV opening remains unchanged, and the opening degree of the fan inlet guide vane set at the inlet of the back pressure regulating fan 17 is gradually increased, or the speed of the back pressure regulating fan 17 is increased to reduce the gas turbine back pressure, and the fuel quantity regulation is combined to control the TET constant.
[0082] It should be noted that in the process of gradually reducing the output power of the gas turbine combined cycle unit from 100% load, the following operation adjustment schemes will obtain better full-condition conversion efficiency: 1) High load area: adopt the combined adjustment method of compressor IGV+fuel amount+gas turbine back pressure, and adjust the unit load according to the equal TIT and equal TET laws; 2) Intermediate load area: adopt the combined adjustment method of compressor intake expansion+fuel amount adjustment, and adjust the unit load according to the equal TET law; 3) Extremely low load area: adopt the combined adjustment method of fuel amount+gas turbine back pressure adjustment, and adjust the unit load according to the equal TET law. Compared with the traditional adjustment scheme (medium and high load area: adopt the combined adjustment scheme of compressor IGV+fuel amount, and adjust the unit load according to the equal TET law; low load area: adopt the pure fuel amount adjustment scheme), this adjustment scheme can maintain a higher TIT in a wider load range, and the thermal efficiency under partial load is higher. The specific comparison relationship is as follows: Figure 2 , 3 shown.
[0083] This article uses specific examples to illustrate the principles and implementation methods of the present invention. The above examples are only used to help understand the method and core ideas of the present invention. At the same time, for those skilled in the art, according to the ideas of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.
Claims
1. A variable load operation control system for a gas turbine combined cycle unit, comprising an air intake filter (1), a compressor (10), a combustion chamber (11), a gas turbine (12), a waste heat boiler (14) and a chimney (21) connected in sequence, characterized in that: A pre-expander (8) is arranged between the compressor (10) and the air inlet filter (1), and a back-pressure regulating fan (17) is arranged between the waste heat boiler (14) and the chimney (21); The variable load operation method of the variable load operation control system of the gas turbine combined cycle unit is as follows: the air flow of the gas turbine is regulated by adjusting the expansion ratio of the pre-expander (8), and the turbine inlet and gas turbine exhaust temperatures are regulated by adjusting the pressure ratio of the back pressure regulating fan (7), and the two cooperate to achieve efficient operation of the combined cycle under variable load.
2. A variable load operation control system for a gas turbine combined cycle unit according to claim 1, characterized in that: The air intake filter (1) is connected to the compressor (10) through the pre-expander main air flow channel (3) and the pre-expander bypass air flow channel (5) respectively; The pre-expander main air flow passage (3) is provided with a pre-expander main air flow passage guide vane (2), a pre-expander main air flow passage guide vane driving mechanism (6) and the pre-expander (8), wherein the pre-expander main air flow passage guide vane driving mechanism (6) is used to adjust the pre-expander main air flow passage guide vane (2) to be in an open or closed state; The front expander bypass air flow passage (5) is provided with a front expander bypass air flow passage guide vane (4) and a front expander bypass air flow passage guide vane driving mechanism (7), and the front expander bypass air flow passage guide vane driving mechanism (7) is used to adjust the front expander bypass air flow passage guide vane (4) to be in an open or closed state; The waste heat boiler (14) is connected to the chimney (21) through a back pressure regulating fan main flue (15) and a back pressure regulating fan bypass flue (19) respectively; The back pressure regulating fan main flue (15) is provided with a back pressure regulating fan main flue damper valve (16) and the back pressure regulating fan (17); The back pressure regulating fan bypass flue (19) is provided with a back pressure regulating fan bypass flue damper valve (20); The inlet of the back pressure regulating fan (17) is provided with a fan inlet guide vane; The pre-expander (8) is provided with a nozzle with an adjustable nozzle size.
3. A variable load operation control method for a gas turbine combined cycle unit, applied to the variable load operation control system for a gas turbine combined cycle unit according to claim 2, characterized in that: include: Compressor intake flow rate and pressure control: closing the pre-expander air bypass flow path guide vane (4) through the pre-expander air flow path guide vane actuator (7), and opening the pre-expander air flow path guide vane (2) through the pre-expander air flow path guide vane actuator (6), so that air enters the compressor (10) from the pre-expander main air flow path (3), adjusting the nozzle size of the pre-expander (8) nozzle or the rotation speed of the pre-expander (8) to adjust the intake flow rate and expansion ratio of the pre-expander (8), thereby realizing the regulation of the intake flow rate and intake pressure of the compressor (10); as well as, Gas turbine back pressure control: by adjusting the rotation speed of the back pressure control fan (17) or the fan inlet guide vane at the inlet of the back pressure control fan (17) to adjust the back pressure of the gas turbine (12), the gas turbine back pressure reduction control or gas turbine back pressure increase control is performed to achieve continuous adjustment of the back pressure of the gas turbine (12) between a certain negative pressure and a certain positive pressure.
4. The variable load operation control method for a gas turbine combined cycle unit according to claim 3, characterized in that: Gas turbine back pressure control includes two situations: gas turbine back pressure reduction control and gas turbine back pressure increase control; When it is necessary to reduce the back pressure of the gas turbine, the following methods are included: The back pressure regulating fan bypass flue damper valve (20) is closed, and the back pressure regulating fan main flue damper valve (16) is opened to allow the flue gas to enter the chimney (21) from the back pressure regulating fan main flue (15); Increasing the opening degree of the fan inlet guide vane at the inlet of the back pressure regulating fan (17) to increase the pressure ratio of the back pressure regulating fan (17), or increasing the rotation speed of the back pressure regulating fan (17) to increase the pressure ratio of the back pressure regulating fan (17), thereby achieving the back pressure reduction regulation of the gas turbine (12); When it is necessary to regulate the back pressure of the gas turbine, the following methods are included: The back pressure regulating fan bypass flue damper valve (20) is closed, and the back pressure regulating fan main flue damper valve (16) is opened to allow the flue gas to enter the chimney (21) from the back pressure regulating fan main flue (15); The opening degree of the fan inlet guide vane at the inlet of the back pressure regulating fan (17) is reduced, the pressure ratio of the back pressure regulating fan (17) is reduced, or the rotation speed of the back pressure regulating fan (17) is reduced, the pressure ratio of the back pressure regulating fan (17) is reduced, or the back pressure regulating fan (17) is made to rotate in the reverse direction, so as to increase the flow resistance of the flue gas and realize the increase regulation of the back pressure of the gas turbine (12).
5. The variable load operation control method for a gas turbine combined cycle unit according to claim 3, characterized in that: Also includes: Compressor intake expansion + fuel quantity regulation + gas turbine back pressure regulation: When the load is reduced, the nozzle size of the nozzle of the pre-expander (8) is reduced, the air flow entering the pre-expander (8) and the compressor (10) is reduced, and the inlet pressure of the compressor (10) is reduced, and the opening degree of the fan inlet guide vane at the inlet of the back pressure regulating fan (17) is gradually increased or the speed of the back pressure regulating fan (19) is increased to reduce the back pressure of the gas turbine, and the fuel amount is adjusted to keep the TIT and TET constant at the design value; When the load is increased, the nozzle size of the nozzle of the pre-expander (8) is increased to increase the air flow rate entering the pre-expander (8) and the compressor (10), the opening degree of the fan inlet guide vane at the inlet of the back pressure regulating fan (17) is gradually reduced or the speed of the back pressure regulating fan (17) is reduced to increase the gas turbine back pressure, and the fuel amount is adjusted to keep the TIT and TET constant at the design value.
6. The variable load operation control method for a gas turbine combined cycle unit according to claim 3, characterized in that: Also includes: Compressor IGV + fuel quantity + gas turbine back pressure regulation: When the load is reduced, the compressor IGV opening is closed to reduce the air flow entering the compressor (10), the fuel amount is adjusted to keep the TIT constant at the design value, and the opening degree of the fan inlet guide vane at the inlet of the back pressure regulating fan (17) is gradually increased or the speed of the back pressure regulating fan (17) is increased to reduce the gas turbine back pressure and keep the TET constant; When the load is increased, the compressor IGV opening is increased to increase the air flow entering the compressor (10), the fuel amount is adjusted to keep the TIT constant at the design value, and the opening degree of the fan inlet guide vane at the inlet of the back pressure regulating fan (17) is gradually reduced or the speed of the back pressure regulating fan (17) is reduced to increase the gas turbine back pressure and keep the TET constant.
7. The variable load operation control method for a gas turbine combined cycle unit according to claim 3, characterized in that: Also includes: Fuel quantity + gas turbine back pressure regulation: When the load is reduced, the IGV opening is fixed, the opening degree of the fan inlet guide vane at the inlet of the back pressure regulating fan (17) is gradually reduced, or the speed of the back pressure regulating fan (17) is reduced to increase the gas turbine back pressure, and the TET is controlled to be constant in combination with the fuel quantity regulation; When the load is increased, the IGV opening is kept constant, the opening degree of the fan inlet guide vane at the inlet of the back pressure regulating fan (17) is gradually increased or the speed of the back pressure regulating fan (17) is increased to reduce the gas turbine back pressure, and the TET is controlled to be constant in combination with the fuel quantity regulation.