Steel structure construction period prediction method and system based on digital twinning

Through digital twin technology and sensor network monitoring of the construction site, combined with computer vision and evolutionary computing algorithms, accurate prediction and optimization of the construction period is achieved, and the problem of insufficient accuracy and flexibility of construction period calculation in traditional methods is solved, and the construction is improved Management security and efficiency.

CN119005394AActive Publication Date: 2024-11-22STATE GRID JIANGSU ELECTRIC POWER CO LTD NANJING POWER SUPPLY COMPANY +1

Patent Information

Application Number
CN202411005798.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-25
Publication Date
2024-11-22
Estimated Expiration
2044-07-25

AI Technical Summary

Technical Problem

The traditional construction period calculation method has insufficient accuracy for construction boundary conditions, which cannot reflect the actual situation on the construction site in real time, and lacks accurate monitoring of personnel and equipment distribution, resulting in deviations in the calculation results of the construction period, making it difficult to find the optimal solution in complex environments. And there is a lack of an effective risk warning mechanism.

Method used

Using digital twin technology, by monitoring construction site data, using sensor networks and computer vision analysts and equipment distribution, combining genetic algorithms and particle swarm optimization algorithms for iterative optimization of construction periods, dynamically adjusting construction plans, and combining historical data and current conditions for accurate construction periods. predict.

Benefits of technology

It improves the accuracy and reliability of construction progress identification, promptly detects inefficient or abnormal behaviors, enhances the flexibility and adaptability of construction management, promptly discovers potential problems and risks, saves construction costs, and ensures the smooth progress of the project.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119005394A_ABST
    Figure CN119005394A_ABST
Patent Text Reader

Abstract

The invention discloses a steel structure construction period prediction method and system based on digital twinning, and the method comprises the following steps: 1, carrying out the real-time monitoring of a construction site, collecting data, comparing the actual construction condition with a digital model through a digital twinning model, and recognizing the existing progress of a project, personnel and equipment distribution and working efficiency of a construction site are monitored and analyzed in real time through a sensor network and computer vision; 2, based on the data of the existing progress and the working efficiency in the step 1, iterative optimization of the construction period is carried out through an optimization algorithm, and an optimal construction period scheme is found; and step 3, based on the optimized construction period scheme, predicting the construction period of the steel structure combined with digital twinning according to historical data and current construction conditions. The digital twinborn technology is combined with construction period calculation, real-time states of a physical model of an engineering project and digital simulation of the physical model are reflected in real time, comprehensive monitoring and management of the construction process are achieved, and the construction period of the engineering project is accurately predicted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of construction project management, and more specifically, relates to a steel structure construction period prediction method and system based on digital twins. Background Art

[0002] Traditional construction duration calculation methods have limitations to a certain extent, one of the most important problems is the accurate grasp of construction boundary conditions. Construction duration calculation usually relies on project plans and empirical estimates, but these estimates are often affected by many factors, such as human errors, unconsidered risk factors, etc., which may lead to deviations in the calculation results of the construction period. In addition, the traditional construction period calculation formula lacks accuracy for actual construction conditions and cannot fully consider the various changes and complexities in the construction process.

[0003] Traditional methods cannot reflect the actual situation of the construction site in real time, and lack accurate monitoring of the distribution of personnel and equipment. Work efficiency evaluation is often based on manual observation and subjective judgment, and it is difficult to objectively and accurately identify inefficient or abnormal behavior. Construction period optimization and adjustment mainly rely on experience and static data, and it is difficult to find the best solution in a complex and changing construction environment. In addition, traditional methods have deficiencies in processing the combination of historical data and current construction conditions, making it difficult to make accurate construction period predictions. There is a lack of effective risk warning mechanisms, and it is impossible to timely discover and respond to potential problems and risks in the construction process.

[0004] These limitations are particularly prominent in the substation reconstruction project carried out by the power supply company. Accurate calculation of the construction period is crucial to the smooth progress of the project, and traditional methods are difficult to meet this requirement.

[0005] Prior art document 1 (CN115809856A) discloses a method for engineering progress deduction based on digital twins and knowledge graphs, which involves a method for applying digital twin technology to the deduction of construction progress management of construction projects, and specifically involves a method for engineering progress deduction based on digital twins and knowledge graphs. It is achieved through the following technical solutions: according to the actual project progress plan, a knowledge graph of logical data on project consumables, equipment, tasks, people, environment, and weather is established; a twin digital model of the overall project progress is established; the twin digital model of the overall project progress is set as the input quantity of the knowledge graph parameters for each time node; the twin digital model of the overall project progress is mapped with the actual project construction progress, the time progress of the actual construction process is input into the time node input quantity corresponding to the twin digital model of the overall project progress, and the project progress supervision is set; the construction period lag time period and the abnormal factor A in the project progress are input; the twin digital model of the overall project progress calculates the actual construction progress according to the construction progress. When the actual project has a progress deviation, the twin digital model of the overall project progress automatically adjusts the digital model according to the current lag time and its own algorithm, adjusts the overall project progress, readjusts the construction progress, and calculates a new construction schedule.

[0006] The inadequacy of the prior art document 1 is that it mainly relies on static knowledge graphs to establish the logical relationship of engineering parameters, and fails to fully achieve real-time response and adaptation to dynamic changes on the construction site. In addition, when dealing with actual construction progress deviations, the adjustment mechanism is too simplified and lacks the intelligent processing capability of comprehensive consideration of multiple construction factors; in terms of resource optimization and allocation, the most efficient allocation strategy is not implemented, resulting in suboptimal resource utilization. Summary of the invention

[0007] In order to solve the deficiencies in the prior art, the present invention provides a method and system for predicting the construction period of a steel structure based on digital twins.

[0008] In view of the limitations and problems of traditional construction period calculation methods, a more accurate and intelligent construction period calculation method is proposed using digital twin technology. This method aims to solve the problems of traditional methods in terms of accuracy of construction boundary conditions and accuracy of construction period calculation formulas, thereby improving the safety management level and construction efficiency of the original site reconstruction project.

[0009] The present invention adopts the following technical solution.

[0010] A first aspect of the present invention provides a method for predicting steel structure construction period based on digital twin, comprising the following steps:

[0011] Step 1: By monitoring the construction site and collecting data, the digital twin model is used to compare the actual construction situation with the digital model to identify the current progress of the project;

[0012] Step 2: Based on the current progress obtained, the distribution of personnel and equipment and work efficiency at the construction site are monitored and analyzed through sensor networks and computer vision;

[0013] Step 3: Based on the current progress of step 1 and the work efficiency data of step 2, the construction period is iteratively optimized through an algorithm to find the optimal construction period solution;

[0014] Step 4: Based on the optimized construction schedule, the construction schedule of the steel structure combined with the digital twin is predicted according to historical data and current construction conditions.

[0015] Preferably, step 1 specifically includes the following steps:

[0016] Step 1.1, configure sensors and monitoring equipment, install cameras and RFID tags at the construction site to cover all areas; cameras are used for video monitoring, and RFID tags are used to track personnel and equipment;

[0017] Step 1.2, based on the sensors and monitoring equipment configured in step 1.1, collect multi-dimensional data of the construction site, including personnel location, equipment status, and material usage;

[0018] Step 1.3: Input the collected data into the digital twin model, compare the actual construction progress with the planned progress, and generate progress comparison results.

[0019] Preferably, in step 1.3, comparing the actual construction progress with the planned progress includes:

[0020] Step 1.3.1, preprocess the collected data and transmit it to the central processing through the communication protocol; preprocessing includes data cleaning and data formatting; data formatting includes converting the data format into a standard format for digital twin model processing data;

[0021] Step 1.3.2, input the preprocessed real-time construction data into the digital twin model, and load and initialize the planned progress data in the digital twin model in preparation for comparison;

[0022] Step 1.3.3, identify and record the location and status of each construction worker and equipment, and match them with the location and status in the planned schedule; compare the start and end time of the actual and planned tasks to calculate the time deviation; calculate the task completion ratio by comparing the actual workload with the planned workload to obtain the actual progress; based on the comparison results, update the planned schedule data in the digital twin model in real time to synchronize the digital twin model with the actual construction situation.

[0023] Preferably, step 2 specifically includes the following steps:

[0024] Step 2.1, use computer vision and RFID to process the video of the construction site, identify the location of personnel and equipment on the construction site, and detect their movements and operating status;

[0025] Step 2.2: Analyze the actions and postures of personnel through posture estimation algorithms to determine their working status, including operating equipment, moving materials, and resting; identify the work efficiency of personnel and equipment through behavioral analysis to determine whether there is inefficient or abnormal behavior;

[0026] Step 2.3, quantify the analysis results and display them through 3D visualization, calculate the work efficiency of each type of work and equipment, and identify the factors affecting work efficiency;

[0027] Step 2.4, generate a work efficiency analysis report, including the working status of personnel and equipment, efficiency data and the identification results of inefficient or abnormal behaviors.

[0028] Preferably, step 3 specifically includes the following steps:

[0029] Step 3.1, taking the identified existing progress data and working conditions as the initial solution, the initial construction schedule is represented as individuals or particles, each of which represents a construction schedule, including the start and end time of each task and resource allocation;

[0030] Step 3.2, simulating natural selection, crossover and mutation operations through genetic algorithms to gradually optimize the construction schedule;

[0031] Step 3.3, using the particle swarm optimization algorithm to simulate group behavior, optimize the construction schedule, and find the optimal or near-optimal solution;

[0032] Step 3.4, evaluate the pros and cons of each new solution based on comprehensive indicators of construction period, cost, and resource utilization;

[0033] Step 3.5: In each iteration, the optimal solution is selected based on the evaluation results, and crossover and mutation operations are performed to generate new candidate solutions;

[0034] Step 3.6, continue iterating until the preset stopping condition is reached. When the stopping condition is met, output the current optimal solution as the final construction schedule.

[0035] Preferably, in step 3.2, the selection operation includes selecting individuals with better performance from the initial solution set, and preferentially retaining the duration solutions with high fitness;

[0036] The crossover operation involves exchanging part of the duration schedule of the selected individuals to generate a new duration plan;

[0037] The mutation operation involves randomly mutating some individuals, changing the start time of the task or the allocation of resources.

[0038] Preferably, step 4 specifically includes the following steps:

[0039] Step 4.1, input construction boundary conditions including the number of construction personnel, number of mechanized equipment shifts, and weather factors;

[0040] Step 4.2, establish a construction period calculation model based on historical data and experience;

[0041] Step 4.3, based on the input boundary conditions, automatically calculate the duration of the sub-projects, arrange the daily construction volume, mechanized equipment and operator location distribution and work content;

[0042] Step 4.4, apply the construction period calculation formula to calculate the estimated construction period.

[0043] Preferably, step 4.2 specifically includes:

[0044] Based on historical data, the construction period including hoisting and riveting and welding of floor decking is estimated with a set number of cranes and construction workers.

[0045] The number of cranes is proportional to the lifting efficiency. Compared with 1 crane, the lifting efficiency improvement rate is estimated according to the set ratio for each additional crane.

[0046] The number of construction workers is directly proportional to the efficiency of riveted and welded floor decking laying. The efficiency improvement ratio is estimated according to the increase in the number of people.

[0047] Preferably, in step 4.4, the construction period calculation formula is as follows:

[0048]

[0049] Where:

[0050] X represents the number of cranes;

[0051] Y represents the number of construction workers;

[0052] Z represents the number of downtime days;

[0053] D represents the construction period in days.

[0054] A second aspect of the present invention provides a steel structure construction duration prediction system based on digital twins, comprising: a data acquisition and monitoring module, a digital twin and progress identification module, a work efficiency analysis and evaluation module, and a construction period optimization and prediction module;

[0055] The data collection and monitoring module collects multi-dimensional data, including personnel location, equipment status, and material usage, by installing high-resolution cameras, RFID tags, and sensor networks at the construction site, providing basic data support for subsequent analysis and model comparison;

[0056] The digital twin and progress identification module uses the digital twin model to compare the actual construction data with the planned progress, adjusts the model parameters through a real-time update mechanism, generates progress comparison results, and identifies the current progress of the project;

[0057] The work efficiency analysis and evaluation module uses computer vision and sensor networks to monitor and analyze the distribution and working status of personnel and equipment on the construction site in real time, evaluate work efficiency, and identify inefficient and abnormal behaviors;

[0058] The construction period optimization and prediction module uses genetic algorithms and particle swarm optimization algorithms to iteratively optimize the construction period based on the existing progress and work efficiency data. It generates the optimal construction period plan by evaluating the comprehensive indicators of construction period, cost and resource utilization, and predicts the construction period of the steel structure by combining historical data and current construction conditions.

[0059] Compared with the prior art, the beneficial effects of the present invention include at least:

[0060] (1) Through the digital twin model, the actual construction data is compared with the planned progress, the current progress of the project is effectively identified, and the accuracy and reliability of progress identification are improved;

[0061] (2) Through posture estimation algorithms and behavior analysis, the work efficiency of construction personnel and equipment can be identified, inefficient or abnormal behaviors can be discovered in a timely manner, and overall work efficiency can be improved;

[0062] (3) Dynamically adjust the construction plan based on real-time monitoring data and optimization results to improve the flexibility and adaptability of construction management;

[0063] (4) Through real-time monitoring and predictive analysis, potential problems and risks in construction can be discovered in a timely manner, early warning information can be provided, construction costs can be saved, and the smooth progress of the project can be ensured. BRIEF DESCRIPTION OF THE DRAWINGS

[0064] Figure 1 The present invention provides a flowchart for predicting construction period. DETAILED DESCRIPTION

[0065] In order to make the purpose, technical scheme and advantages of the present invention clearer, the technical scheme of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. The embodiments described in this application are only part of the embodiments of the present invention, not all of them. Based on the spirit of the present invention, other embodiments obtained by ordinary technicians in this field without creative work are all within the scope of protection of the present invention.

[0066] In view of the limitations and problems of traditional construction period calculation methods, a more accurate and intelligent construction period calculation method is proposed using digital twin technology. This method aims to solve the problems of traditional methods in terms of accuracy of construction boundary conditions and accuracy of construction period calculation formulas, thereby improving the safety management level and construction efficiency of the original site reconstruction project.

[0067] Specifically, the system will use advanced sensor networks to collect real-time data on the construction site, including but not limited to soil conditions, meteorological conditions, equipment operating status, worker activities, etc. These data will be transmitted to the digital twin system center through the network for digital modeling and synchronized operation with the actual site to achieve real-time monitoring and simulation of the construction process.

[0068] The digital twin system center will be equipped with high-performance computers and intelligent algorithms, and use advanced machine learning and data mining technologies to analyze and process the large amount of data collected. By reviewing and comparing historical data, the system can identify regular changes and potential risk factors in the construction process, providing an accurate basis for calculating the construction period.

[0069] In terms of construction period calculation, the system will use advanced mathematical modeling methods such as multiple regression analysis and neural network models to take various factors in the construction process into consideration, thereby establishing a more accurate and detailed construction period calculation model. These models will be able to comprehensively consider various changes and uncertain factors in the construction process, and realize intelligent prediction and optimization adjustment of the construction period.

[0070] In addition, the digital twin system will also be equipped with an intelligent decision support system that can automatically propose adjustment suggestions for the construction plan based on real-time monitoring data and construction period calculation models, and assist project managers in making decisions. Such a digital twin system that integrates real-time monitoring, data analysis, construction period calculation and decision support will provide a full range of intelligent construction management solutions for the original site reconstruction project, improving the project's safety management level and construction efficiency.

[0071] like Figure 1 As shown, Example 1 of the present invention provides a steel structure construction period prediction method based on digital twin, comprising the following steps:

[0072] Step 1: By monitoring the construction site and collecting data, the digital twin model is used to compare the actual construction situation with the digital model to identify the current progress of the project;

[0073] First, the progress of the current construction project is identified through real-time monitoring and data collection of the construction site. Using digital twin technology, more real-time data and monitoring indicators are introduced to compare the actual construction situation with the digital model, so as to accurately determine the current status of the project and improve the accuracy and reliability of the construction period calculation model.

[0074] Preferably, step 1 specifically includes the following steps:

[0075] Step 1.1, configure sensors and monitoring equipment, install high-resolution cameras and RFID tags at the construction site to cover all areas; cameras are used for video monitoring, and RFID tags are used to track personnel and equipment;

[0076] Step 1.2, based on the configured equipment, collect multi-dimensional data of the construction site, including personnel location, equipment status, and material usage;

[0077] Step 1.3: Input the collected data into the digital twin model, compare the actual construction progress with the planned progress, and generate progress comparison results.

[0078] Preferably, in step 1.3, comparing the actual construction progress with the planned progress includes:

[0079] Step 1.3.1, preprocessing the collected data and transmitting it to the central processing through the communication protocol; the preprocessing includes data cleaning and data formatting; the data formatting includes uniformly converting the data format into a standard format for digital twin model processing data;

[0080] Step 1.3.2, input the preprocessed real-time construction data into the digital twin model, and load and initialize the planned progress data in the digital twin model in preparation for comparison;

[0081] Step 1.3.3, identify and record the location and status of each construction worker and equipment through sensor and RFID tag data, and match them with the location and status in the planned schedule; compare the start and end time of the actual and planned tasks to calculate the time deviation; calculate the task completion ratio by comparing the actual workload with the planned workload to obtain the actual progress; based on the comparison results, update the planned schedule data in the digital twin model in real time to synchronize the digital twin model with the actual construction situation.

[0082] Step 2: Based on the current progress obtained, the distribution of personnel and equipment and work efficiency at the construction site are monitored and analyzed through sensor networks and computer vision;

[0083] Preferably, step 2 specifically includes the following steps:

[0084] Step 2.1, use computer vision and RFID to process the video of the construction site, identify the location of personnel and equipment on the construction site, and detect their movements and operating status;

[0085] Step 2.2: Analyze the actions and postures of personnel through posture estimation algorithms to determine their working status, including operating equipment, moving materials, and resting; identify the work efficiency of personnel and equipment through behavioral analysis to determine whether there is inefficient or abnormal behavior;

[0086] Step 2.3, quantify the analysis results and display them through 3D visualization, calculate the work efficiency of each type of work and equipment, and identify the factors affecting work efficiency;

[0087] Step 2.4, generate a work efficiency analysis report, including the working status of personnel and equipment, efficiency data and the identification results of inefficient or abnormal behaviors.

[0088] By deploying a sensor network to monitor the distribution of personnel and equipment at the construction site in real time, including cameras, RFID tags, etc., accurate real-time data can be obtained. Then, computer vision technology is used to analyze the monitored video to identify the location, quantity and operation status of personnel and equipment. At the same time, the system can also classify different types of work and equipment in combination with intelligent recognition algorithms to further improve the accuracy of recognition.

[0089] In terms of work efficiency identification, the system uses data analysis and machine learning technology to process and analyze real-time monitoring data to quantify work efficiency and identify influencing factors. By building a model, the system can dynamically adjust the relevant parameters in the construction period calculation model, such as staffing ratio, equipment utilization rate, etc., according to actual conditions to reflect the actual situation on the construction site.

[0090] Step 3: Based on the current progress of step 1 and the work efficiency data of step 2, the construction period is iteratively optimized through an algorithm to find the optimal construction period solution;

[0091] Preferably, step 3 specifically includes the following steps:

[0092] Step 3.1, taking the identified existing progress data and working conditions as the initial solution, the initial construction schedule is represented as individuals or particles, each of which represents a construction schedule, including the start and end time of each task and resource allocation;

[0093] Step 3.2, simulating natural selection, crossover and mutation operations through genetic algorithms to gradually optimize the construction schedule;

[0094] Preferably, in step 3.2, the selection operation is: selecting individuals with better performance from the initial solution set, and preferentially retaining the duration solutions with high fitness;

[0095] Crossover operation: exchange part of the schedule of the selected individuals to generate a new schedule plan;

[0096] Mutation operation: Randomly mutate some individuals to change the start time of the task or resource allocation.

[0097] Step 3.3, using the particle swarm optimization algorithm to simulate group behavior, optimize the construction schedule, and find the optimal or near-optimal solution;

[0098] Step 3.4, evaluate the pros and cons of each new solution based on comprehensive indicators of construction period, cost, and resource utilization;

[0099] Step 3.5: In each iteration, the optimal solution is selected based on the evaluation results, and crossover and mutation operations are performed to generate new candidate solutions;

[0100] Step 3.6, continue iterating until the preset stopping condition is reached. When the stopping condition is met, output the current optimal solution as the final construction schedule.

[0101] Iterative optimization algorithm based on evolutionary computation:

[0102] This algorithm imitates the process of biological evolution in nature, and gradually optimizes the solution to the problem by simulating operations such as selection, crossover and mutation. The system uses evolutionary computing algorithms such as Genetic Algorithm (GA) and Particle Swarm Optimization (PSO) to achieve iterative optimization of the construction period.

[0103] In the process of calculating and adjusting the construction period, the system first inputs the identified existing progress and working conditions as the initial solution into the optimization algorithm. Then, the evolutionary computing algorithm is used to iteratively adjust the construction period, generate new solutions, and evaluate the new solutions through the evaluation function to determine their quality. The evaluation function usually includes comprehensive indicators that consider factors such as construction period, cost, and resource utilization.

[0104] In each iteration, the optimization algorithm selects the better solution based on the evaluation results, and performs operations such as crossover and mutation to generate new candidate solutions. This process will continue for multiple iterations until the preset stopping condition is reached, such as reaching the maximum number of iterations or finding the optimal solution that meets the requirements.

[0105] Through continuous iterative optimization, the system can find the best construction schedule to meet project requirements and maximize construction efficiency. The advantage of evolutionary computing algorithms is that they can find global optimal solutions or solutions close to the optimal solution in a complex search space, and they have good adaptability and can cope with different types of engineering projects and construction environments.

[0106] Step 4: Based on the optimized construction schedule, the construction schedule of the steel structure combined with the digital twin is predicted according to historical data and current construction conditions.

[0107] By inputting common construction boundary conditions such as the number of construction personnel, the number of mechanized equipment shifts, weather factors, etc., the duration of each part of the project can be automatically calculated, and the daily construction volume, the location distribution of mechanized equipment and operators, and the work content can be precisely arranged.

[0108] The determinants of construction boundary conditions include the number of mechanized equipment shifts (cranes) and the number of construction workers, while the uncertainties of construction boundary conditions include weather (such as heavy rain, typhoons, high temperatures, etc.) and holidays.

[0109] Preferably, in step 4.1, inputting construction boundary conditions includes the number of construction personnel, the number of mechanized equipment shifts, and weather factors;

[0110] Step 4.2, establish a construction period calculation model based on historical data and experience;

[0111] Preferably, step 4.2 specifically includes:

[0112] Based on historical data, the construction period including hoisting and riveting and welding of floor decking is estimated with a set number of cranes and construction workers.

[0113] The number of cranes is proportional to the lifting efficiency. Compared with 1 crane, the lifting efficiency improvement rate is estimated according to the set ratio for each additional crane.

[0114] The number of construction workers is directly proportional to the efficiency of riveted and welded floor decking laying. The efficiency improvement ratio is estimated according to the increase in the number of people.

[0115] For example:

[0116] According to historical data, when there are 2 cranes and 25 construction workers, the estimated complete construction period is 60 days, with 24 days for hoisting accounting for 40% and 36 days for riveting and welding floor decking accounting for 60%;

[0117] The number of cranes directly affects the lifting efficiency. Compared with one crane, the lifting efficiency increases by 30% to 40% with each additional crane. The lifting efficiency improvement rate is estimated at 35%.

[0118] The number of construction workers is directly proportional to the efficiency of riveting and welding floor decking. The efficiency of 40 construction workers is twice that of 20 workers.

[0119] Uncertain factors will cause downtime days, and the construction period will be increased by as many days as entered.

[0120] Step 4.3, based on the input boundary conditions, automatically calculate the duration of the sub-projects, arrange the daily construction volume, mechanized equipment and operator location distribution and work content;

[0121] Step 4.4, apply the construction period calculation formula to calculate the estimated construction period.

[0122] Preferably, in step 4.4, the construction period calculation formula is as follows:

[0123]

[0124] Where:

[0125] X represents the number of cranes;

[0126] Y represents the number of construction workers;

[0127] Z represents the number of downtime days;

[0128] D represents the construction period in days.

[0129] The significant difference between the present invention and the prior art is that it provides a digital twin model that combines real-time monitoring data and a dynamic adjustment algorithm. The model can not only be updated in real time to reflect the current status of the construction site, but also accurately predict and optimize the construction progress through advanced algorithms. The present invention uses computer vision and sensor network technology to monitor personnel and equipment on the construction site, and improves the accuracy of understanding construction activities through behavior analysis and posture estimation algorithms. At the same time, the present invention uses genetic algorithms and particle swarm optimization algorithms to achieve automation and optimization of construction schedule scheduling.

[0130] The beneficial effect achieved by the present invention compared with the prior art is that, through the integration and analysis of real-time data, the accuracy and reliability of construction period prediction are significantly improved; the dynamic parameter adjustment and intelligent progress adjustment mechanism enable the present invention to quickly adapt to any changes in the construction process and effectively reduce construction delays; the intelligent resource optimization and scheduling further improve the construction efficiency and resource utilization; the present invention also provides a user-friendly interactive interface and three-dimensional visualization technology, so that construction managers can monitor the construction progress and manage the construction site more intuitively and conveniently.

[0131] A second aspect of the present invention provides a steel structure construction duration prediction system based on digital twins, comprising: a data acquisition and monitoring module, a digital twin and progress identification module, a work efficiency analysis and evaluation module, and a construction period optimization and prediction module;

[0132] The data collection and monitoring module collects multi-dimensional data, including personnel location, equipment status, and material usage, by installing high-resolution cameras, RFID tags, and sensor networks at the construction site, providing basic data support for subsequent analysis and model comparison;

[0133] The digital twin and progress identification module uses the digital twin model to compare the actual construction data with the planned progress, adjusts the model parameters through a real-time update mechanism, generates progress comparison results, and identifies the current progress of the project;

[0134] The work efficiency analysis and evaluation module uses computer vision and sensor networks to monitor and analyze the distribution and working status of personnel and equipment on the construction site in real time, evaluate work efficiency, and identify inefficient and abnormal behaviors;

[0135] The construction period optimization and prediction module uses genetic algorithms and particle swarm optimization algorithms to iteratively optimize the construction period based on the existing progress and work efficiency data. It generates the optimal construction period plan by evaluating the comprehensive indicators of construction period, cost and resource utilization, and predicts the construction period of the steel structure by combining historical data and current construction conditions.

[0136] The beneficial effect of the present invention is that it combines digital twin technology with construction period calculation, innovatively develops a highly intelligent and accurate construction management system, and brings new management concepts and technical means to the field of engineering construction. Through digital twin technology, the system can reflect the real-time status of the physical model of the engineering project and its digital simulation in real time, and realize all-round monitoring and management of the construction process; at the same time, combined with construction period calculation technology, the system can accurately predict the construction period of the engineering project, providing an important basis for the reasonable arrangement of the project progress.

[0137] Through the digital twin model, the actual construction data is compared with the planned progress, the current progress of the project is effectively identified, and the accuracy and reliability of progress identification are improved; through posture estimation algorithms and behavior analysis, the work efficiency of construction personnel and equipment is identified, and inefficient or abnormal behaviors are discovered in time to improve overall work efficiency; according to real-time monitoring data and optimization results, the construction plan is dynamically adjusted to improve the flexibility and adaptability of construction management; through real-time monitoring and predictive analysis, potential problems and risks in construction are discovered in time, early warning information is provided, construction costs are saved, and the smooth progress of the project is ensured.

[0138] The present disclosure may be a system, a method and / or a computer program product. The computer program product may include a computer-readable storage medium carrying computer-readable program instructions for causing a processor to implement various aspects of the present disclosure.

[0139] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, ordinary technicians in the relevant field should understand that the specific implementation methods of the present invention can still be modified or replaced by equivalents, and any modifications or equivalent replacements that do not depart from the spirit and scope of the present invention should be covered within the scope of protection of the claims of the present invention.

Claims

1. A method for predicting steel structure construction period based on digital twin, characterized in that: The following steps are involved: Step 1: By monitoring the construction site and collecting data, the digital twin model is used to compare the actual construction situation with the digital model to identify the current progress of the project; Step 2: Based on the current progress obtained, the distribution of personnel and equipment and work efficiency at the construction site are monitored and analyzed through sensor networks and computer vision; Step 3: Based on the current progress of step 1 and the work efficiency data of step 2, the construction period is iteratively optimized through the optimization algorithm to find the optimal construction period solution; Step 4: Based on the optimized construction schedule, the construction schedule of the steel structure combined with the digital twin is predicted according to historical data and current construction conditions.

2. A method for predicting steel structure construction period based on digital twin according to claim 1, characterized in that: Step 1 specifically includes the following steps: Step 1.1, configure sensors and monitoring equipment, install cameras and RFID tags at the construction site to cover all areas; cameras are used for video monitoring, and RFID tags are used to track personnel and equipment; Step 1.2, based on the sensors and monitoring equipment configured in step 1.1, collect multi-dimensional data of the construction site, including personnel location, equipment status, and material usage; Step 1.3: Input the collected data into the digital twin model, compare the actual construction progress with the planned progress, and generate progress comparison results.

3. A method for predicting steel structure construction period based on digital twin according to claim 2, characterized in that: In step 1.3, the comparison between the actual construction progress and the planned progress includes: Step 1.3.1, preprocess the collected data and transmit it to the central processing through the communication protocol; preprocessing includes data cleaning and data formatting; data formatting includes converting the data format into a standard format for digital twin model processing data; Step 1.3.2, input the preprocessed real-time construction data into the digital twin model, and load and initialize the planned progress data in the digital twin model in preparation for comparison; Step 1.3.3, identify and record the location and status of each construction worker and equipment, and match them with the location and status in the planned schedule; compare the start and end time of the actual and planned tasks to calculate the time deviation; calculate the task completion ratio by comparing the actual workload with the planned workload to obtain the actual progress; based on the comparison results, update the planned schedule data in the digital twin model in real time to synchronize the digital twin model with the actual construction situation.

4. The method for predicting steel structure construction period based on digital twin according to claim 1, characterized in that: Step 2 specifically includes the following steps: Step 2.1, use computer vision and RFID to process the video of the construction site, identify the location of personnel and equipment on the construction site, and detect their movements and operating status; Step 2.2: Analyze the actions and postures of personnel through posture estimation algorithms to determine their working status, including operating equipment, moving materials, and resting; identify the work efficiency of personnel and equipment through behavioral analysis to determine whether there is inefficient or abnormal behavior; Step 2.3, quantify the analysis results and display them through 3D visualization, calculate the work efficiency of each type of work and equipment, and identify the factors affecting work efficiency; Step 2.4, generate a work efficiency analysis report, including the working status of personnel and equipment, efficiency data and the identification results of inefficient or abnormal behaviors.

5. The method for predicting steel structure construction period based on digital twin according to claim 1, characterized in that: Step 3 specifically includes the following steps: Step 3.1, taking the identified existing progress data and working conditions as the initial solution, the initial construction schedule is represented as individuals or particles, each of which represents a construction schedule, including the start and end time of each task and resource allocation; Step 3.2, simulating natural selection, crossover and mutation operations through genetic algorithms to gradually optimize the construction schedule; Step 3.3, using the particle swarm optimization algorithm to simulate group behavior, optimize the construction schedule, and find the optimal or near-optimal solution; Step 3.4, evaluate the pros and cons of each new solution based on comprehensive indicators of construction period, cost, and resource utilization; Step 3.5: In each iteration, the optimal solution is selected based on the evaluation results, and crossover and mutation operations are performed to generate new candidate solutions; Step 3.6, continue iterating until the preset stopping condition is reached. When the stopping condition is met, output the current optimal solution as the final construction schedule.

6. A method for predicting steel structure construction period based on digital twin according to claim 5, characterized in that: In step 3.2, the selection operation includes selecting individuals with better performance from the initial solution set, and giving priority to retaining the duration solutions with high fitness; The crossover operation involves exchanging part of the duration schedule of the selected individuals to generate a new duration plan; The mutation operation involves randomly mutating some individuals, changing the start time of the task or the allocation of resources.

7. The method for predicting steel structure construction period based on digital twin according to claim 1, characterized in that: Step 4 specifically includes the following steps: Step 4.1, input construction boundary conditions including the number of construction personnel, number of mechanized equipment shifts, and weather factors; Step 4.2, establish a construction period calculation model based on historical data and experience; Step 4.3, based on the input boundary conditions, automatically calculate the duration of the sub-projects, arrange the daily construction volume, mechanized equipment and operator location distribution and work content; Step 4.4, apply the construction period calculation formula to calculate the estimated construction period.

8. A method for predicting steel structure construction period based on digital twin according to claim 7, characterized in that: Step 4.2 specifically includes: Based on historical data, the construction period including hoisting and riveting and welding of floor decking is estimated with a set number of cranes and construction workers. The number of cranes is proportional to the lifting efficiency. Compared with 1 crane, the lifting efficiency improvement rate is estimated according to the set ratio for each additional crane. The number of construction workers is directly proportional to the efficiency of riveted and welded floor decking laying. The efficiency improvement ratio is estimated according to the increase in the number of people.

9. The method for predicting steel structure construction period based on digital twin according to claim 7, characterized in that: In step 4.4, the calculation formula for the construction period is as follows: Where: X represents the number of cranes; Y represents the number of construction workers; Z represents the number of downtime days; D represents the construction period in days.

10. A steel structure construction period prediction system based on digital twin, comprising: Data collection and monitoring module, digital twin and progress identification module, work efficiency analysis and evaluation module, and construction period optimization and prediction module; its characteristics are: The data collection and monitoring module collects multi-dimensional data, including personnel location, equipment status, and material usage, by installing high-resolution cameras, RFID tags, and sensor networks at the construction site; The digital twin and progress identification module uses the digital twin model to compare the actual construction data with the planned progress, adjusts the model parameters through a real-time update mechanism, generates progress comparison results, and identifies the current progress of the project; The work efficiency analysis and evaluation module uses computer vision and sensor networks to monitor and analyze the distribution and working status of personnel and equipment on the construction site in real time, evaluate work efficiency, and identify inefficient and abnormal behaviors; The construction period optimization and prediction module uses genetic algorithms and particle swarm optimization algorithms to iteratively optimize the construction period based on the existing progress and work efficiency data. It generates the optimal construction period plan by evaluating the comprehensive indicators of construction period, cost and resource utilization, and predicts the construction period of the steel structure by combining historical data and current construction conditions.

Citation Information

Patent Citations

  • Construction process management and control method based on digital twinning

    CN113110313A

  • Project progress deduction method based on digital twinborn and knowledge graph

    CN115809856A

  • Building construction optimization system based on big data and cloud computing

    CN116862199A

  • Intelligent safety management and control method and system for road-related construction project based on BIM (Building Information Modeling)

    CN117829534A

  • Project progress prediction method, progress prediction device, and progress prediction program

    WO2024122049A1

Cited By

  • Manufacturing unit innovation platform building method based on digital twin industrial robot

    CN119328809A

  • Steel structure construction management and control method and equipment based on machine vision

    CN119849002A

  • Building construction site energy consumption prediction supervision method and system

    CN120181334A

  • A method and system for predicting and supervising energy consumption at a construction site

    CN120181334B

  • Fabricated steel structure building construction evaluation system

    CN120316891A