Building EPC project budgeting method based on BOM management and storage medium thereof
Through the BOM management method combined with the BIM model, the problems of cumbersome cost calculations and poor data sharing in the traditional construction industry are solved, and the precise cost calculation and management of building EPC projects are realized, which improves resource utilization efficiency and cost control capabilities.
Patent Information
- Application Number
- CN202411175150.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-26
- Publication Date
- 2024-11-22
AI Technical Summary
The traditional construction industry faces cumbersome cost accounting, inaccurate data, poor data sharing among departments, and disconnection between design costs and procurement calculations in cost calculations, resulting in waste of resources, cost overruns and decline in operating efficiency, and the cost of traditional engineering The logic is difficult to adapt to the new EPC service.
Using the building EPC project budget method based on BOM management, by obtaining module information in the BIM model, matching the corresponding materials, processing technology and installation technology, calculating the project quantity and generating a project project budget list, and performing materials and processing technology when necessary and replacement of installation processes to control costs.
It improves the accuracy and efficiency of cost calculations, reduces manual calculations, realizes clear correlation of resource requirements and precise cost control, and ensures that project costs are within the budget range.
Smart Images

Figure CN119005442A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of construction EPC engineering cost budgeting and project target cost control, and in particular to a construction EPC engineering budgeting method based on BOM management and a storage medium thereof. Background Art
[0002] In response to the current downward pressure on the construction industry, construction companies are actively seeking digital transformation to cope with market challenges and find new growth points. However, with the continuous improvement of digital construction, the transformation strategy of a single enterprise can no longer cover the broad needs of enterprise transformation and industrial chain development. Accurate cost calculation and effective collaborative management and control have become the key to industry development. In order to break through this bottleneck, cross-functional and cross-organizational collaboration has become particularly important. It is urgent to reimagine the digital industry collaboration model from a macro perspective to achieve collaborative optimization of the industrial chain and improve overall efficiency.
[0003] However, the traditional construction industry faces many challenges in the cost calculation and management of construction projects, such as cumbersome cost accounting, inaccurate data, poor data sharing between departments, and disconnected design cost procurement calculation. These problems not only affect the cost calculation and management efficiency of the construction industry, but may also lead to waste of resources, cost overruns and decline in operating efficiency, restricting the development of the industry. Therefore, the construction industry urgently needs to seek effective solutions to these challenges.
[0004] At the same time, the traditional engineering cost logic is not sufficient to adapt to the new type of construction EPC business. This business integrates the delivery and implementation of demand design, procurement and processing, construction and installation in a manufacturing manner. The fees, calculation methods, and calculation rules that need to be involved in the management are different from the traditional engineering cost and traditional quotation methods. The industry urgently needs a new budgeting method that is suitable for EPC business. Summary of the invention
[0005] The first object of the present invention is to provide a construction EPC project budgeting method based on BOM management, which has the technical effect of improving the cost calculation accuracy and efficiency.
[0006] The above-mentioned object of the present invention is achieved through the following technical solutions: A method for building EPC project budgeting based on BOM management, the method comprising: obtaining a BIM model, the BIM model comprising modules; matching corresponding module information according to a unique identification code of the module, the module information comprising component attributes; matching corresponding selected materials, selected processing techniques and selected installation techniques from the BOM model according to the component attributes; matching a measurement template according to the selected materials, selected processing techniques and selected installation techniques, calculating the engineering quantity and matching the price in a calculation method of the measurement template, and generating a project engineering budget list.
[0007] The present application is further configured as follows: the component attributes include inter-component relationships, initial materials, initial processing technology, and initial installation technology; the inter-component relationships are used to determine the initial processing technology and initial installation technology.
[0008] The present application is further configured as follows: the matching of the selected material, the selected processing technology and the selected installation technology according to the component attributes includes: Match the corresponding selected materials according to the initial materials, match the corresponding selected processing technology according to the initial processing technology, and match the corresponding selected installation technology according to the initial installation technology; the matching principle is to give priority to matching the selected materials that are the same as the initial materials, the selected processing technology that is the same as the initial processing technology, and the selected installation technology that is the same as the initial installation technology in the BOM model, otherwise match the selected materials that are similar to the initial materials, the selected processing technology that is similar to the initial processing technology, and the selected installation technology that is similar to the initial installation technology in the BOM model.
[0009] The present application is further configured as follows: the engineering quantity includes processing engineering quantity and installation engineering quantity, the processing technology includes processing procedures, the installation technology includes installation procedures, the processing procedures correspond to processing procedure engineering quantities, the installation procedures correspond to installation procedure engineering quantities, the processing engineering quantity includes the processing procedure engineering quantities, and the installation engineering quantity includes the installation procedure engineering quantities.
[0010] The present application is further configured as follows: the price includes a unit price of engineering quantity and a unit price of materials, the unit price of engineering quantity includes a processing unit price and an installation unit price, the processing unit price includes a processing procedure unit price, the installation unit price includes an installation procedure unit price, the processing procedure unit price corresponds to the processing procedure engineering quantity one-to-one, the installation procedure unit price corresponds to the installation procedure engineering quantity one-to-one, each processing procedure corresponds to a processing procedure material consumption, each installation procedure corresponds to an installation procedure material consumption, the corresponding processing procedure cost is calculated by combining the processing procedure unit price, the processing procedure engineering quantity, the processing procedure material consumption and the material unit price, and the corresponding installation procedure cost is calculated by combining the installation procedure unit price, the installation procedure engineering quantity, the installation procedure material consumption and the material unit price.
[0011] The present application is further configured as follows: the method also includes, after generating the project engineering budget list, obtaining a user's correction operation, wherein the correction operation includes replacing one or more of the selected materials, the selected processing technology, and the selected installation technology.
[0012] The present application is further configured as follows: the engineering budget list includes budget costs, and when the budget costs exceed a preset cost threshold, materials are selected from the BOM model according to a preset replacement logic to replace the selected materials.
[0013] The present application is further configured as follows: the replacement logic includes sorting the replacement order of different types of materials, replacing the selected material ranked first in the material type, and replacing materials with lower unit prices than the selected materials until the budget cost is lower than the cost threshold.
[0014] The present application is further configured as follows: when the selected material ranked first has been replaced by the material with the lowest unit price and the budget cost is still higher than the cost threshold, the selected material is restored and the selected material ranked next is selected for replacement according to the order of priority until the budget cost is lower than the cost threshold.
[0015] A second objective of the present invention is to provide a computer-readable storage medium.
[0016] The second object of the present invention is achieved through the following technical solutions: A computer-readable storage medium stores a computer program, which, when executed by a processor, implements the steps of the above-mentioned construction project budgeting method based on BOM management.
[0017] In summary, the beneficial technical effects of the present invention are: 1. Using BOM model and BIM model to automate engineering quantity calculation and cost budgeting greatly reduces the cumbersome manual calculation and secondary modeling calculation in traditional methods; 2. By associating information such as materials, processing technology and installation technology in the BIM model, you can have a clearer understanding of the various resource requirements in the project. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the component BOM model of this application; Figure 2 It is a schematic diagram of BIM model analysis and conversion of this application; Figure 3 It is a schematic diagram of the overall system architecture of BOM model construction and BIM model parsing and conversion in this application. DETAILED DESCRIPTION
[0019] The present invention is further described in detail below in conjunction with the accompanying drawings.
[0020] In traditional construction projects, designers often only focus on the aesthetics and functionality of the building and ignore cost-effectiveness considerations; while cost personnel only focus on cost data and lack an in-depth understanding of architectural design, resulting in a disconnect between project design and cost calculation. This makes it impossible to fully consider cost factors in the design stage, making subsequent cost control and optimization difficult.
[0021] In construction projects, many companies do not have a strong sense of full participation and system control in cost accounting, and only stay at plugging loopholes such as material and equipment procurement, engineering subcontracting, labor subcontracting, and non-productive expenses. There is a lack of deep understanding of factors that potentially affect the cost of engineering projects, such as technological innovation, construction deployment, and construction organization. In cost calculation, costs are often simply and crudely allocated to various departments or stages, resulting in the company's inability to accurately evaluate the profitability of each part, affecting the company's strategic decision-making and resource allocation, and making it impossible to allocate resources to where they are most needed, thereby affecting project quality and delivery progress.
[0022] Based on the many problems existing in the above-mentioned construction projects, in order to improve the accuracy and efficiency of construction project cost calculation, this application proposes a construction project budgeting method based on BOM management. Through the combination of BOM model and BIM model, the management efficiency and accuracy of cost data are further improved, providing a strong guarantee for the successful implementation of the project.
[0023] To realize BOM-based construction project cost budgeting, it is necessary to build a BOM model and realize the conversion from BIM to BOM.
[0024] The method of building a BOM model is as follows: Figure 1 As shown in the figure, first of all, standardized component attributes are the basis for building a BOM model. It is necessary to clarify and unify the attributes of all components in a construction project, such as name, specification, material, etc., to ensure data consistency and accuracy. This helps to quickly and accurately reference and manage these component attributes in subsequent cost calculations.
[0025] Secondly, clarifying the composition relationship of components is crucial for the construction of BOM model. By clearly sorting out the hierarchical structure and dependency relationship between components and the processing and installation process, clarifying the composition relationship of components and the processing and installation process, and establishing a cost quota model for each processing and installation process, the costs required for other cost consumption, except material costs, are allocated to each process in a certain proportion to ensure that the BOM model can truly reflect the actual structure of the project, thus providing a reliable basis for cost calculation.
[0026] Next, standardized measurement rules are the key to ensuring the accuracy of cost calculation. It is necessary to analyze the measurement rules for the procurement, production, processing and construction of each component according to industry standards and project requirements, clarify the engineering quantity calculation rules for procurement, production, processing and construction technology, and ensure that these rules are uniformly applied and understood in the project.
[0027] Based on the construction of the above BOM model, when designing the BIM model through BIM technology, the component attributes in the BOM model are associated with the components of the BIM model, so that there is a mapping relationship between the component attributes in the BIM model and the component attributes in the BOM model.
[0028] BIM model analysis and conversion, such as Figure 2 As shown, the following steps are included: S101: Acquire a BIM model, where the BIM model includes modules.
[0029] Among them, the BIM model is composed of multiple modules, each module corresponds to a unique identification code, and the component properties in the module can be read through the unique identification code. The component properties include the relationship between components, initial materials, initial processing technology and initial installation technology. The relationship between components is used to determine the initial processing technology and initial installation technology.
[0030] S102: matching corresponding module information according to the unique identification code of the module, where the module information includes component attributes; S103: matching corresponding selected materials, selected processing technology and selected installation technology from the BOM model according to component attributes; In the above step S103, the component attributes include initial materials, initial processing technology and initial installation technology. Initial materials refer to materials selected when designing the BIM model, and materials may include information such as brand, material, weight, size, etc. The matching process is to match the corresponding selected materials according to the initial materials, match the corresponding selected processing technology according to the initial processing technology, and match the corresponding selected installation technology according to the initial installation technology; the matching principle is to give priority to matching the selected materials that are the same as the initial materials, the selected processing technology that is the same as the initial processing technology, and the selected installation technology that is the same as the initial installation technology in the BOM model, otherwise matching the selected materials that are similar to the initial materials, the selected processing technology that is similar to the initial processing technology, and the selected installation technology that is similar to the initial installation technology in the BOM model. Take matching the corresponding selected materials according to the initial materials as an example. If the initial material is a material of brand A, if brand A material exists in the BOM model, brand A material will be used as the selected material. If brand A material does not exist in the BOM model, brand B material with similar parameters such as material material, weight or size can be selected as the selected material instead.
[0031] S104: Match the calculation template according to the selected materials, the selected processing technology and the selected installation technology, calculate the engineering quantity and match the price by the calculation method of the calculation template, and generate a project engineering budget list.
[0032] In the above step S104, the engineering quantity includes the processing engineering quantity and the installation engineering quantity, the processing technology includes the processing procedures, the installation technology includes the installation procedures, the processing procedures correspond to the processing procedure engineering quantity, the installation procedures correspond to the installation procedure engineering quantity, the processing engineering quantity includes the processing procedure engineering quantity, and the installation engineering quantity includes the installation procedure engineering quantity. The price includes the engineering quantity unit price and the material unit price, the engineering quantity unit price includes the processing unit price and the installation unit price, the processing unit price includes the processing procedure unit price, the installation unit price includes the installation procedure unit price, the processing procedure unit price corresponds to the processing procedure engineering quantity, the installation procedure unit price corresponds to the installation procedure engineering quantity, each processing procedure corresponds to the processing procedure material consumption, each installation procedure corresponds to the installation procedure material consumption, the corresponding processing procedure cost is calculated by combining the processing procedure unit price, the processing procedure engineering quantity, the processing procedure material consumption and the material unit price, and the corresponding installation procedure cost is calculated by combining the installation procedure unit price, the installation procedure engineering quantity, the installation procedure material consumption and the material unit price. The calculation template is determined based on three factors: material, selected processing technology and selected installation technology. These three factors mainly affect the calculation of material consumption in the calculation template.
[0033] In the generated project purchase list, the processing quantity can correspond to the processing unit price, the installation quantity can correspond to the installation unit price, and the material consumption can correspond to the material unit price, and then the budget cost can be calculated.
[0034] In the embodiment of the present application, after the project engineering budget list is generated, the user's correction operation can be obtained, and the correction operation includes replacing one or more of the selected materials, selected processing technology and selected installation technology. This operation can be performed by the user when the budget cost does not meet expectations, that is, the user can replace one or more of the multiple materials to achieve the purpose of reducing costs, improving quality, etc. The same can be applied to the replacement of installation technology and processing technology. The budget cost expectation can be lower than the user's psychological cost. A cost threshold can be set in the system. When the budget cost is higher than When the cost threshold is reached, the value of the budget cost will be marked in red in the project budget list. When the budget cost is lower than the cost threshold, Highlight the budget cost value in green.
[0035] The above is a manual replacement operation for selected materials, etc. In another embodiment of the present application, a cost threshold can also be preset. When the budget cost is higher than the cost threshold, the replacement of the selected materials, selected processing technology and selected installation technology is automatically triggered.
[0036] The specific replacement method requires pre-setting of replacement logic, such as giving priority to replacing selected materials among selected materials, selected processing techniques, and selected installation techniques. The different types of materials are sorted in order of replacement, and the selected materials ranked first in material type are replaced, and materials with lower unit prices than the selected materials are replaced until the budget cost is lower than the cost threshold. When the selected material ranked first has been replaced with the material with the lowest unit price and the budget cost is still higher than the cost threshold, the selected materials are restored, and the selected materials ranked next in order are selected for replacement according to the order of priority until the budget cost is lower than the cost threshold. When replacing the selected processing technology and the selected installation technology, only one of the processing procedures or installation procedures can also be replaced. The above replacement logic is only one of the replacement logics disclosed in this application, and it can also be, for example, to screen out one or more selected materials, selected installation processes, and selected processing technologies with the highest total price for replacement. Since the higher the total price, the higher the weight affecting the budget cost, the replacement logic will be more efficient.
[0037] like Figure 3 The following is the overall system architecture for BOM model construction and BIM model parsing and conversion, including: First layer: base layer Preparation of basic data: define the basic properties of all components (such as parts, assemblies, modules, etc.) and materials and bills in the system, such as size, material, project characteristics, etc. These properties are the basis for subsequent calculations and decisions.
[0038] Construction of BOM model: clarify the hierarchical relationship and assembly relationship between components, clarify the content and calculation rules of each component based on industry or enterprise custom rules, and set predefined quotation templates according to project type and customer needs to accurately track and calculate the cost of the overall project.
[0039] Second layer: Execution layer Model quality inspection: Check the quality of the design model to see if it meets the company's design standards, parse and match the company's modules, parse and obtain component attribute values, provide a basis for procurement, and prepare for the calculation of engineering quantities.
[0040] DBOM generation: Based on project requirements, clarify the materials, labor and machinery to be purchased, and clarify the specific processes and procedures for production, processing, installation and construction.
[0041] Cost estimation: Match the estimation template, calculate the engineering quantity of each part, such as area, volume, weight, etc. based on the project model and design, and obtain the project engineering budget list based on information such as engineering quantity and material price.
[0042] Third layer: Management Cost monitoring: Supports multi-stage cost calculation of projects, monitors and controls project costs at different stages to ensure that they do not exceed the budget.
[0043] Decision support: Based on the data from the basic layer and the execution layer, it provides decision support to the management, such as selecting the best suppliers, formulating procurement strategies, etc., helping the management understand the project status and market trends, and providing direction for product iteration and optimization.
[0044] In one embodiment, a computer readable storage medium is provided, on which a computer program is stored, and when the computer program is executed by a processor, the following steps are implemented: Acquire a BIM model, where the BIM model includes modules; Matching corresponding module information according to the unique identification code of the module, wherein the module information includes component attributes; Matching corresponding selected materials, selected processing technology and selected installation technology from the BOM model according to the component attributes; According to the selected materials, selected processing technology and selected installation technology, the measurement template is matched, the engineering quantity is calculated and the price is matched by the calculation method of the measurement template, and the project engineering budget list is generated.
[0045] Those of ordinary skill in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be implemented by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to memory, storage, database or other media used in the embodiments provided in this application may include non-volatile and / or volatile memory. Non-volatile memory may include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM) or flash memory. Volatile memory may include random access memory (RAM) or external cache memory. By way of illustration and not limitation, RAM is available in many forms, such as static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double data rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM), etc.
[0046] Those skilled in the art can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional units and modules is used as an example. In actual applications, the above-mentioned functions can be distributed and completed by different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above.
[0047] The embodiments described above are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention, and should all be included in the protection scope of the present invention.
Claims
1. A construction EPC project budgeting method based on BOM management, characterized in that: The method comprises: Acquire a BIM model, where the BIM model includes modules; Matching corresponding module information according to the unique identification code of the module, wherein the module information includes component attributes; Matching corresponding selected materials, selected processing technology and selected installation technology from the BOM model according to the component attributes; According to the selected materials, selected processing technology and selected installation technology, the measurement template is matched, the engineering quantity is calculated and the price is matched by the calculation method of the measurement template, and the project engineering budget list is generated.
2. The construction EPC project budgeting method based on BOM management as claimed in claim 1 is characterized in that: The component attributes include inter-component relationships, initial materials, initial processing technology, and initial installation technology. The inter-component relationships are used to determine the initial processing technology and initial installation technology.
3. The construction EPC project budgeting method based on BOM management as claimed in claim 2 is characterized in that: The matching of the selected material, the selected processing technology and the selected installation technology according to the component attributes includes: Match the selected materials according to the initial materials, match the selected processing technology according to the initial processing technology, and match the selected installation technology according to the initial installation technology; The matching principle is to give priority to matching the selected materials that are the same as the initial materials, the selected processing technology that is the same as the initial processing technology, and the selected installation technology that is the same as the initial installation technology in the BOM model; otherwise, match the selected materials that are similar to the initial materials, the selected processing technology that is similar to the initial processing technology, and the selected installation technology that is similar to the initial installation technology in the BOM model.
4. The construction EPC project budgeting method based on BOM management as claimed in claim 1 is characterized in that: The EPC project quantity includes processing project quantity and installation project quantity. The processing technology includes processing procedures, and the installation technology includes installation procedures. The processing procedures correspond to processing procedure project quantities, and the installation procedures correspond to installation procedure project quantities. The processing project quantity includes the processing procedure project quantities, and the installation project quantity includes the installation procedure project quantities.
5. The construction EPC project budgeting method based on BOM management as claimed in claim 4 is characterized in that: The price includes the unit price of engineering quantity and the unit price of materials. The unit price of engineering quantity includes the processing unit price and the installation unit price. The processing unit price includes the processing procedure unit price. The installation unit price includes the installation procedure unit price. The processing procedure unit price corresponds to the processing quantity of the processing procedure. The installation procedure unit price corresponds to the installation quantity of the installation procedure. Each processing procedure has a corresponding processing procedure material consumption. Each installation procedure has a corresponding installation procedure material consumption. The corresponding processing procedure cost is calculated by combining the processing procedure unit price, the processing quantity of the processing procedure, the processing procedure material consumption and the material unit price. The corresponding installation procedure cost is calculated by combining the installation procedure unit price, the installation quantity of the installation procedure, the installation procedure material consumption and the material unit price.
6. The construction EPC project budgeting method based on BOM management as claimed in claim 1 is characterized in that: The method further includes, after generating the project engineering budget list, obtaining a user's correction operation, wherein the correction operation includes replacing one or more of the selected material, the selected processing technology, and the selected installation technology.
7. The construction EPC project budgeting method based on BOM management as claimed in claim 1 is characterized in that: The engineering budget list includes the budget cost. When the budget cost exceeds a preset cost threshold, a material is selected from the BOM model according to a preset replacement logic to replace the selected material.
8. The construction EPC project budgeting method based on BOM management as claimed in claim 7 is characterized in that: The replacement logic includes sorting the replacement order of different types of materials, replacing the selected material ranked first in the material type, and replacing the material with a lower unit price than the selected material until the budget cost is lower than the cost threshold.
9. The construction EPC project budgeting method based on BOM management as claimed in claim 8 is characterized in that: When the first-ranked selected material has been replaced by the material with the lowest unit price and the budget cost is still higher than the cost threshold, the selected materials are restored and the next-ranked selected materials are selected for replacement according to the order of priority until the budget cost is lower than the cost threshold.
10. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of the construction EPC engineering budgeting method based on BOM management as described in any one of claims 1 to 9 are implemented.
Citation Information
Cited By
Product automatic quotation method and system based on multi-source data
CN122492297A
A product automatic pricing method and system based on multi-source data
CN122492297B