Intelligent anti-error system and method for electronic work ticket of power line
Through the three-level anti-miss error verification and bundling technology of the intelligent anti-missile system, the problem of insufficient security and information integration capabilities of electronic work tickets for power lines is solved, and a more efficient and safer work ticket licensing process is achieved.
Patent Information
- Application Number
- CN202411034400.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-07-30
AI Technical Summary
The safety and error prevention capabilities of electronic work tickets for power lines are insufficient and the information integration capabilities are weak, resulting in risks and hidden dangers in the licensing process of power lines work tickets.
An intelligent anti-error system was designed, including work ticket management module and work ticket anti-error module. Through technical means such as three-level anti-error verification, bundle establishment and real-time interaction, multiple security for electronic work tickets of power lines can be achieved. Verification and information integration, establish a strong lockdown relationship, and improve the safety and integration efficiency of work tickets.
It has improved the safety and error prevention level of electronic work tickets for power lines, improved information integration capabilities, reduced the risk of missed associations in manual reviews, and improved the work efficiency of work permit holders.
Smart Images

Figure CN119005896A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of technical error prevention of power systems, and in particular relates to an intelligent error prevention system and method for electronic work tickets of power lines. Background Art
[0002] The power line work permit system is a fundamental organizational measure to ensure the safety of power line maintenance work. The overall process involves the issuer of a work permit, who then signs for it. Once grid safety measures are met, the permit issuer approves the work permit from the person in charge. Only after completing the permitting procedures can the person in charge organize on-site operations. Upon completion of on-site work, the person in charge completes the work permit closure process with the permit issuer.
[0003] Existing technology has realized the electronic flow of the entire process of power line work tickets. Traditional paper work tickets are gradually being replaced by electronic work tickets, but the two remain basically consistent in business processes. Both divide the work ticket links into four links: waiting for receipt, waiting for permission, waiting for termination and terminated. Through these four links, a closed loop of power line work ticket licensing work is realized.
[0004] Existing technical solutions simply convert power line work permits from paper to electronic form, that is, from offline to online. While this helps save paper, it does not directly improve safety. Therefore, electronic power line work permits still face the following problems:
[0005] 1. Inadequate security and error prevention capabilities. The security of electronic work permits for power lines still relies on the professional expertise and meticulousness of the permit issuer, the person in charge of the work, and the person issuing the permit. Technical measures are not applied to implement multiple security checks on work permits. This is particularly true for partial work on the same line, such as when voltage is applied to the power line. Multiple work permits are mutually exclusive. These work permits effectively have a strong locking relationship, but the current lack of technical error prevention means they rely solely on the approval of the permit issuer.
[0006] 2. Weak information integration capabilities. Currently, electronic power line work tickets involving the same line are integrated and linked by the work permit holder, without sufficient technical means to efficiently bundle them. This heavy workload not only brings the risk of missing links, but also poses a risk to the authorization of power line work tickets. Summary of the Invention
[0007] The present invention aims to address the aforementioned issues by providing an intelligent error-prevention system and method for electronic work permits for power lines. This system implements multiple intelligent safety checks on work permits, further integrating information such as the work route, work location, work content, and safety measures within the electronic work permits. This system then intelligently associates multiple work permits related to the same power line. Furthermore, a strong locking relationship is established for specific work permits that could pose a personal risk to power line workers, thereby improving the technical error-prevention capabilities of electronic work permits for power lines.
[0008] To achieve the above purpose, the technical solution of the present invention is: an intelligent error-proofing system for electronic work tickets of power lines, comprising a work ticket management module and a work ticket error-proofing module; wherein,
[0009] The work ticket management module includes a waiting-for-receipt unit, a waiting-for-approval unit, a bundling unit, a waiting-for-termination unit, and an archiving unit; the waiting-for-receipt unit is used for pre-signing for the electronic work ticket for the power line and pushing it to the self-inspection unit; the waiting-for-approval unit is used for opening the permission function for the electronic work ticket for the power line that has passed the self-inspection unit and has been signed; the bundling unit is used for bundling multiple electronic work tickets for the power line with overlapping safety measures to form a work ticket bundle; the waiting-for-termination unit is used for opening the termination function for the approved electronic work ticket for the power line; and the archiving unit is used for archiving the terminated electronic work ticket for the power line;
[0010] The work ticket error prevention module includes a self-check unit, a real-time error prevention unit, a data service unit, a real-time interaction unit and an associated error prevention unit; the self-check unit is used to perform a three-level error prevention check on the ticket information of the electronic work ticket for the power line; the real-time error prevention unit is used to perform a real-time error prevention safety check on the permitted electronic work ticket for the power line; the data service unit is used to receive and parse the data of the real-time error prevention unit and the real-time interaction unit, and perform comparison; the real-time interaction unit is used to read data with the EMS system in real time, and transmit the read data to the data service unit; the associated error prevention unit is used to receive the bundled information of the electronic work ticket for the power line pushed by the bundling unit, and retrieve the key fields to establish an associated error prevention lock.
[0011] In one embodiment of the present invention, the self-checking unit performs a three-level error prevention check on the ticket information of the power line electronic work ticket in the following specific implementation methods:
[0012] The work line and work location fields in the electronic work tickets for power lines that are waiting to be signed are compared in pairs, and the two parts of the field content "**kVxx line" are extracted. If the two parts of the field content are completely consistent, it is judged that the first level of error prevention verification has passed; the "**" characters are Arabic numerals, and the "xx" characters are not restricted;
[0013] Compare the work line and work content fields of the electronic work tickets for power lines that are waiting to be signed for in pairs, extract the two parts of the field content "**kVxx line", and if the two parts of the field content are completely consistent, it is determined that the second-level anti-error verification has passed;
[0014] For the electronic work tickets for power lines that are waiting to be signed, the contents of the fields "Working Line" and "Name of Line Interval to be Switched to Maintenance" for safety measures are compared in pairs. The contents of the two fields "**kVxx line" are extracted. If the contents of the two fields are completely consistent, the third-level error prevention check is considered to have passed.
[0015] After passing the three-level error prevention check, the electronic work ticket for the power line will open the signing function. After the electronic work ticket for the power line is signed, the electronic work ticket process for the power line will be transferred to the unit awaiting permission. When any level of error prevention check fails, the system will lock the signing and issue an alarm.
[0016] In one embodiment of the present invention, the bundling unit bundles multiple electronic power line work tickets with overlapping safety measures to form a work ticket bundle package. The specific implementation method is as follows:
[0017] The bundling unit obtains the field content "**kVxx line" of the safety measures "name of the line interval that should be turned into maintenance status" of all the electronic work tickets for power lines of the units to be signed, the units to be permitted, and the units to be terminated, and compares them; a bundle package is generated for each electronic work ticket for power lines with completely non-overlapping safety measures. When the field content "**kVxx line" in the safety measures "name of the line interval that should be turned into maintenance status" of multiple electronic work tickets for power lines overlaps, they are bundled together, and the bundle package associates multiple electronic work tickets for power lines; when the process of the electronic work ticket for power lines is transferred to the archiving unit, the corresponding electronic work ticket for power lines is removed from the bundle package.
[0018] In one embodiment of the present invention, the permission-pending unit opens the permission function for the electronic work ticket for the power line that has passed the self-inspection unit and has been signed for. That is, when the permission is clicked on the electronic work ticket for the power line that is pending permission, the work ticket management module will push the safety measures information of the electronic work ticket for the power line to the real-time error prevention unit of the work ticket error prevention module. The real-time error prevention unit will parse the information on the safety measures including the substation name, voltage level, line name, and line status, and request the above information from the data service unit.
[0019] In one embodiment of the present invention, the data service unit reads the substation name, voltage level, and line name, and pushes them to the real-time interaction unit; the real-time interaction unit interacts with the EMS system in real time, reads the status information of the corresponding equipment through the substation name, voltage level, and line name, and returns the status information to the real-time interaction unit; the real-time interaction unit further transmits the status information to the data service unit, and the data service unit compares the line status received from the real-time error prevention unit and the data service unit respectively. If the line status information is consistent, the real-time error prevention check passes, and the power line electronic work ticket is pushed to the associated error prevention unit; if the status information is inconsistent, the real-time error prevention check fails, the system will issue an alarm prompt, and the power line electronic work ticket licenser will forcibly unlock it or return the power line electronic work ticket to the unit to be permitted.
[0020] In one embodiment of the present invention, the associated error prevention unit obtains the field content of the work content in all the electronic work tickets for power lines in all the bundled packages. When the field content of the work content of a certain electronic work ticket for power lines contains a field including "parameter testing" or "pressurization", an error prevention locking relationship is established for the electronic work ticket for power lines: when the electronic work ticket for power lines in any bundled package is in the to-be-terminated unit, the electronic work ticket for power lines whose work content contains a field including "parameter testing" or "pressurization" will not be able to pass the safety check of the associated error prevention unit, and an alarm prompt will be given to the work permit holder.
[0021] In one embodiment of the present invention, when the electronic work ticket for a power line whose work content includes fields such as "parameter testing" or "pressurization" is in the stage of pending termination, the electronic work ticket for a power line in the corresponding bundle that is in the stage of pending permission will not be able to pass the safety check of the associated anti-error unit, and an alarm will be given to the work permit holder.
[0022] In one embodiment of the present invention, the system locking library supports manual addition of key fields to perform the power line electronic work ticket permission locking function, and the power line electronic work ticket permission locking function has the function of supporting manual release after review by the work permit holder.
[0023] In one embodiment of the present invention, the method for obtaining the field content in the electronic work ticket of the power line adopts the OCR text recognition technology.
[0024] The present invention also provides an intelligent error-prevention method for electronic work tickets for power lines, comprising:
[0025] S1. The electronic work tickets for power lines to be signed for are subject to three-level error prevention verification. The electronic work tickets that pass the three-level error prevention verification will be able to open the signing function; specifically,
[0026] The work line and work location fields in the electronic work tickets for power lines that are waiting to be signed are compared in pairs, and the two parts of the field content "**kVxx line" are extracted. If the two parts of the field content are completely consistent, it is judged that the first level of error prevention verification has passed; the "**" characters are Arabic numerals, and the "xx" characters are not restricted;
[0027] Compare the work line and work content fields of the electronic work tickets for power lines that are waiting to be signed for in pairs, extract the two parts of the field content "**kVxx line", and if the two parts of the field content are completely consistent, it is determined that the second-level anti-error verification has passed;
[0028] For the electronic work tickets for power lines that are waiting to be signed, the contents of the fields "Working Line" and "Name of Line Interval to be Switched to Maintenance" for safety measures are compared in pairs. The contents of the two fields "**kVxx line" are extracted. If the contents of the two fields are completely consistent, the third-level error prevention check is considered to have passed.
[0029] After passing the three-level error prevention check, the electronic work ticket for the power line will open the sign-off function. After the electronic work ticket for the power line is signed, step S2 is executed. If any level of error prevention check fails, the system will lock the sign-off and issue an alarm.
[0030] S2. Obtain the field content "**kVxx line" of the safety measure "line interval name to be transferred to maintenance status" of all power line electronic work tickets and compare them to establish the mutual correlation relationship of the power line electronic work tickets; specifically,
[0031] Obtain the "**kVxx line" field content of the "Name of the line interval that should be transferred to the maintenance state" safety measure of all power line electronic work tickets and compare them; generate a bundle package for each power line electronic work ticket with completely non-overlapping safety measures. When the "**kVxx line" field content of the "Name of the line interval that should be transferred to the maintenance state" safety measure of multiple power line electronic work tickets overlap, they are bundled together, and the bundle package is associated with multiple power line electronic work tickets; when the power line electronic work ticket process flows to the terminated stage, the corresponding power line electronic work ticket is removed from the bundle package;
[0032] S3. Obtain the field contents of the work contents in all the electronic work tickets for power lines in all the bundles. When the field contents of the work contents of a certain electronic work ticket for power lines contain a field including "parameter testing" or "pressurization", an anti-error locking relationship is established for the electronic work ticket for power lines: when the electronic work ticket for power lines in any bundle is in the pending termination stage, the electronic work ticket for power lines with work contents containing fields including "parameter testing" or "pressurization" will not be able to pass the safety check of the associated anti-error unit, and an alarm will be given to the work permit holder; and, when the electronic work ticket for power lines with work contents containing fields including "parameter testing" or "pressurization" is in the pending termination stage, the electronic work tickets for power lines in the corresponding bundle that are in the pending permission stage will not be able to pass the safety check of the associated anti-error unit, and an alarm will be given to the work permit holder.
[0033] Compared with the prior art, the present invention has the following beneficial effects:
[0034] 1. Improve the security and error prevention level of electronic work permits for power lines. By applying technical means to establish a multi-level error prevention lockout safety check for a single electronic work permit for power lines and multiple electronic work permits with overlapping safety measures, an additional layer of technical protection is added to the large number of work permits that only pass manual review.
[0035] 2. Improve the ability to integrate information from electronic power line work tickets. By identifying electronic power line work tickets with overlapping safety measures and creating bundled packages, this system efficiently integrates work ticket information, making it easier for work permit holders to review and improving their work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] Figure 1 This is a system block diagram of the present invention.
[0037] Figure 2 Showcases an example UI for the bundle.
[0038] Figure 3 This is a work ticket for a unit waiting to be signed for.
[0039] Figure 4 For Figure 3 Work tickets for units with the same work line and to be terminated. DETAILED DESCRIPTION
[0040] The technical solution of the present invention will be described in detail below with reference to the accompanying drawings.
[0041] Reference Figure 1 This example provides an intelligent error prevention system for electronic work tickets of power lines, which mainly includes: a work ticket management module and a work ticket error prevention module.
[0042] The work ticket management module includes a waiting-for-receipt unit, a waiting-for-approval unit, a bundling unit, a waiting-for-termination unit, and an archiving unit. The waiting-for-receipt unit is used for pre-signing for the electronic work ticket for the power line and pushing it to the self-inspection unit. The waiting-for-approval unit is used for opening the permission function for the electronic work ticket for the power line that has passed the self-inspection unit and has been signed. The bundling unit is used for bundling multiple electronic work tickets for the power line with overlapping safety measures to form a work ticket bundle. The termination unit is used for opening the termination function for the approved electronic work ticket for the power line. The archiving unit is used for archiving the terminated electronic work ticket for the power line.
[0043] The work ticket error prevention module includes a self-check unit, a real-time error prevention unit, a data service unit, a real-time interaction unit and an associated error prevention unit. The self-check unit is used to perform a three-level error prevention check on the ticket information of the electronic work ticket for the power line. The real-time error prevention unit is used to perform a real-time error prevention safety check on the electronic work ticket for the power line to be approved. The data service unit is used to receive and parse the data of the real-time error prevention unit and the real-time interaction unit, and perform comparisons. The real-time interaction unit is used to read data from the EMS system in real time and transmit the read data to the data service unit. The associated error prevention unit is used to receive the work ticket bundling information pushed by the bundling unit, and retrieve the key fields to establish an associated error prevention lock.
[0044] The self-check unit for electronic power line work tickets uses a three-level error prevention check. First, the work line and work location fields in the pending receipt phase are compared pairwise. The two fields, "**kVxx line" ("**" represents Arabic numerals, and "xx" is not a restriction, similarly below), are extracted. If the two fields match, the first level error prevention check is considered passed.
[0045] Furthermore, the work route and work content fields of the work ticket are compared in pairs. The two content fields "**kVxx line" are extracted. If the contents of the two fields are completely consistent, the second level error prevention check is considered to have passed.
[0046] Furthermore, the work line and safety measure fields "Name of line interval to be switched to maintenance" on the work ticket are compared pairwise. The two fields "**kVxx line" are extracted. If the two fields are identical, the third-level error prevention check is considered passed.
[0047] After passing the three-level self-checking unit, the electronic work ticket for the power line will be available for signing. Once the work ticket is signed, the work ticket process will be transferred to the unit for approval. If any level of error prevention verification fails, the system will lock the sign-off and issue an alarm.
[0048] Furthermore, the bundling unit obtains the field content "**kVxx line" of the safety measures "name of the line interval that should be turned into maintenance status" of all work tickets for units to be signed, to be authorized, and to be terminated, and compares them. A bundle package is generated for each work ticket with completely non-overlapping safety measures. When the field content "**kVxx line" in the safety measures "name of the line interval that should be turned into maintenance status" of multiple work tickets overlaps, they are bundled together, and the bundle package associates multiple work tickets. The mutual relationship between multiple work tickets is identified through the bundle package. An example of the bundle package display interface is as follows: Figure 2 When the work ticket process flows to the archiving unit, the work ticket is removed from the bundle.
[0049] When a work ticket pending approval is clicked, the work ticket management module pushes the work ticket's safety measures to the real-time error prevention unit in the work ticket error prevention module. The real-time error prevention unit parses the safety measures, including substation name, voltage level, line name, and line status, and requests this information from the data service unit.
[0050] After the data service unit reads the substation name, voltage level, and line name, it pushes it to the real-time interaction unit. The real-time interaction unit interacts with the EMS system in real time, reads the status of the equipment through the substation name, voltage level, and line name, and returns the status information to the real-time interaction unit. The real-time interaction unit then further transmits the status information to the data service unit, which compares the line status received from the real-time anti-error unit and the data service unit respectively. If the line status information is consistent, the real-time anti-error check passes, and the work ticket is pushed to the associated anti-error unit. If the status information is inconsistent, the real-time anti-error check fails, the system will issue an alarm, and the work ticket permitter will forcibly unlock it or return the work ticket to the unit awaiting permission.
[0051] Furthermore, the associated error prevention unit retrieves the work content field contents of all work tickets within all bundles. If a work ticket's work content fields include fields such as "parameter test" or "pressurization," an error prevention lockout relationship is established for that work ticket: If a work ticket in any bundle is in the pending termination unit, any work ticket containing "parameter test" or "pressurization" will fail the associated error prevention unit's safety check, and a warning will be issued to the work permit holder.
[0052] Furthermore, when a work ticket containing the "parameter test" or "pressurization" field is in the pending termination stage, the work tickets in the bundle that are in the pending permission stage will not be able to pass the associated anti-error safety check and an alarm will be given to the work permit holder.
[0053] The system lock library supports manual addition of key fields for work ticket permission locking function.
[0054] Furthermore, the locking function of the electronic work ticket for the power line has the function of supporting manual release after review by the work permit holder.
[0055] The method for obtaining the field content of the electronic work ticket of the power line adopts OCR text recognition technology. The technical process includes image input, preprocessing, layout analysis, character cutting, character feature extraction, character recognition, layout recovery, post-processing and proofreading.
[0056] The present invention also provides an intelligent error-prevention method for electronic work tickets for power lines, comprising:
[0057] S1. The electronic work tickets for power lines to be signed for are subject to three-level error prevention verification. The electronic work tickets that pass the three-level error prevention verification will be able to open the signing function; specifically,
[0058] The work line and work location fields in the electronic work tickets for power lines that are waiting to be signed are compared in pairs, and the two parts of the field content "**kVxx line" are extracted. If the two parts of the field content are completely consistent, it is judged that the first level of error prevention verification has passed; the "**" characters are Arabic numerals, and the "xx" characters are not restricted;
[0059] Compare the work line and work content fields of the electronic work tickets for power lines that are waiting to be signed for in pairs, extract the two parts of the field content "**kVxx line", and if the two parts of the field content are completely consistent, it is determined that the second-level anti-error verification has passed;
[0060] For the electronic work tickets for power lines that are waiting to be signed, the contents of the fields "Working Line" and "Name of Line Interval to be Switched to Maintenance" for safety measures are compared in pairs. The contents of the two fields "**kVxx line" are extracted. If the contents of the two fields are completely consistent, the third-level error prevention check is considered to have passed.
[0061] After passing the three-level error prevention check, the electronic work ticket for the power line will open the sign-off function. After the electronic work ticket for the power line is signed, step S2 is executed. If any level of error prevention check fails, the system will lock the sign-off and issue an alarm.
[0062] S2. Obtain the field content "**kVxx line" of the safety measure "line interval name to be transferred to maintenance status" of all power line electronic work tickets and compare them to establish the mutual correlation relationship of the power line electronic work tickets; specifically,
[0063] Obtain the "**kVxx line" field content of the "Name of the line interval that should be transferred to the maintenance state" safety measure of all power line electronic work tickets and compare them; generate a bundle package for each power line electronic work ticket with completely non-overlapping safety measures. When the "**kVxx line" field content of the "Name of the line interval that should be transferred to the maintenance state" safety measure of multiple power line electronic work tickets overlap, they are bundled together, and the bundle package is associated with multiple power line electronic work tickets; when the power line electronic work ticket process flows to the terminated stage, the corresponding power line electronic work ticket is removed from the bundle package;
[0064] S3. Obtain the field contents of the work contents in all the electronic work tickets for power lines in all the bundles. When the field contents of the work contents of a certain electronic work ticket for power lines contain a field including "parameter testing" or "pressurization", an anti-error locking relationship is established for the electronic work ticket for power lines: when the electronic work ticket for power lines in any bundle is in the pending termination stage, the electronic work ticket for power lines with work contents containing fields including "parameter testing" or "pressurization" will not be able to pass the safety check of the associated anti-error unit, and an alarm will be given to the work permit holder; and, when the electronic work ticket for power lines with work contents containing fields including "parameter testing" or "pressurization" is in the pending termination stage, the electronic work tickets for power lines in the corresponding bundle that are in the pending permission stage will not be able to pass the safety check of the associated anti-error unit, and an alarm will be given to the work permit holder.
[0065] The present invention will be further described below with reference to the accompanying drawings and specific implementations.
[0066] Figure 3 、 Figure 4 These are the front pages of two typical electronic work tickets for power lines with the same work lines. Figure 3 The work ticket shown is in the waiting receipt unit. Figure 4 The work tickets shown are in the unit to be terminated. The work lines of the above two work tickets are already under maintenance, which is consistent with the safety measures on the tickets.
[0067] For items awaiting receipt Figure 3 The electronic work ticket for the power line shown in the figure shows the work line field containing "110kVA B line" and the work location field containing "110kVA B line." If the contents of these two fields are consistent, the self-check unit has passed the first-level error prevention check.
[0068] Furthermore, the work content field "110kVA B line" in the work ticket is obtained and compared with the work line field "110kVA B line". If the two fields are consistent, the self-test unit passes the second level error prevention check.
[0069] Furthermore, the work ticket's safety measure, "Line Interval Name to be Transitioned to Maintenance," field, containing "110kVA B Line," is obtained and compared with the working line field, containing "110kVA B Line." If the two fields match, the self-check unit passes the third-level error prevention check, and the sign-off function is enabled. After sign-off is complete, the process is pushed to the unit awaiting approval.
[0070] Further, obtain Figure 3 、 Figure 4 The safety measure field "Name of line bay to be transferred to maintenance" on the work ticket shown contains "110kVA B line" and "110kVA B line" respectively. It is determined that the two fields overlap. A new bundle is created for the two electronic power line work tickets, establishing a mutual relationship between the two work tickets.
[0071] Furthermore, the field contents of the work contents in all work tickets in the above bundle are obtained. Figure 3 The work content of the electronic work ticket shown contains the content of the "parameter test" field, establishing an anti-error locking relationship.
[0072] When the right Figure 3 When the work permit is issued, the real-time error prevention unit safety check is first carried out. Since the "110kVAB line" has been transferred to maintenance, the real-time error prevention unit safety check has passed.
[0073] Furthermore, the safety check of the associated error prevention unit is carried out. Figure 4 The electronic work ticket shown is in the stage of waiting for completion. Figure 3 The work ticket shown will lock the permission function and issue an alarm prompt.
[0074] The above are preferred embodiments of the present invention. Any changes made according to the technical solution of the present invention, as long as the resulting functions and effects do not exceed the scope of the technical solution of the present invention, shall fall within the scope of protection of the present invention.
Claims
1. An intelligent error-prevention system for electronic work tickets of power lines, characterized in that: It includes work ticket management module and work ticket error prevention module; among which, The work ticket management module includes a waiting-for-receipt unit, a waiting-for-permission unit, a bundling unit, a waiting-for-termination unit and an archiving unit; the waiting-for-receipt unit is used for pre-signing for the electronic work ticket of the power line and pushing it to the self-inspection unit; the waiting-for-permission unit is used for opening the permission function for the electronic work ticket of the power line that has passed the self-inspection unit and has been signed; the bundling unit is used for bundling multiple copies of the electronic work ticket of the power line with overlapping safety measures and forming a work ticket bundle; the waiting-for-termination unit is used for opening the termination function for the permitted electronic work ticket of the power line; the archiving unit is used for archiving the terminated electronic work ticket of the power line; The work ticket error prevention module includes a self-check unit, a real-time error prevention unit, a data service unit, a real-time interaction unit and an associated error prevention unit; the self-check unit is used to perform a three-level error prevention check on the ticket information of the power line electronic work ticket; the real-time error prevention unit is used to perform a real-time error prevention safety check on the permitted power line electronic work ticket; the data service unit is used to receive and parse the real-time error prevention unit and the real-time interaction unit data, and compare them; the real-time interaction unit is used to read data from the EMS system in real time, and transmit the read data to the data service unit; the associated error prevention unit is used to receive the power line electronic work ticket bundling information pushed by the bundling unit, and retrieve the key fields to establish the associated error prevention lock.
2. The intelligent error-prevention system for electronic work tickets of power lines according to claim 1 is characterized in that: The specific implementation method of the self-checking unit to perform three-level error prevention verification on the ticket information of the power line electronic work ticket is as follows: The fields of work line and work location in the electronic work ticket of the power line in the stage of waiting for receipt are compared in pairs, and the two parts of the field content "**kVxx line" are extracted. If the two parts of the field content are completely consistent, it is judged that the first level of error prevention check has passed; among them, the "**" characters are Arabic numerals, and the "xx" characters are not restricted; Compare the fields of work line and work content of the electronic work ticket of the power line in the stage of waiting for receipt in pairs, extract the two parts of the field content "**kVxx line", if the two parts of the field content are completely consistent, it is judged that the second level error prevention check has passed; For the electronic work tickets of power lines that are waiting to be signed, the field contents of the safety measures "line interval name that should be transferred to the maintenance state" are compared in pairs, and the two parts of the field contents "**kVxx line" are extracted. If the two parts of the field contents are completely consistent, it is judged that the third-level error prevention check has passed; After passing the three-level error prevention check, the electronic work ticket for the power line will open the signing function. After the electronic work ticket for the power line is signed, the electronic work ticket process for the power line will be transferred to the unit awaiting permission. When any level of error prevention check fails, the system will lock the signing and issue an alarm.
3. The intelligent error-prevention system for electronic work tickets of power lines according to claim 1 is characterized in that: The bundling unit bundles multiple electronic work tickets for power lines with overlapping safety measures and forms a work ticket bundle package. The specific implementation method is as follows: The bundling unit obtains the field content "**kVxx line" of the safety measure "name of the line interval that should be turned into the maintenance state" of all the electronic work tickets for power lines in the units to be signed, the units to be permitted, and the units to be terminated, and compares them; a bundle package is generated for each electronic work ticket for power lines with completely non-overlapping safety measures. When the field content "**kVxx line" in the safety measure "name of the line interval that should be turned into the maintenance state" of multiple electronic work tickets for power lines overlap, they are bundled with each other, and the bundle package is associated with multiple electronic work tickets for power lines; when the process of the electronic work ticket for power lines is transferred to the archiving unit, the corresponding electronic work ticket for power lines is removed from the bundle package.
4. The intelligent error-prevention system for electronic work tickets of power lines according to claim 1 is characterized in that: The unit awaiting permission opens the permission function for the electronic work ticket for the power line that has passed the self-inspection unit and has been signed for. That is, when the permission is clicked for the electronic work ticket for the power line that is awaiting permission, the work ticket management module will push the safety measures information of the electronic work ticket for the power line to the real-time error prevention unit of the work ticket error prevention module. The real-time error prevention unit will parse the information in the safety measures including the substation name, voltage level, line name, and line status, and request the above information from the data service unit.
5. The intelligent error-prevention system for electronic work tickets of power lines according to claim 4 is characterized in that: After the data service unit reads the substation name, voltage level, and line name, it pushes them to the real-time interaction unit; the real-time interaction unit interacts with the EMS system in real time, reads the status information of the corresponding equipment through the substation name, voltage level, and line name, and returns the status information to the real-time interaction unit; the real-time interaction unit further transmits the status information to the data service unit, and the data service unit compares the line status received from the real-time error prevention unit and the data service unit respectively. If the line status information is consistent, the real-time error prevention check is passed, and the electronic work ticket of the power line is pushed to the associated error prevention unit; If the status information is inconsistent, the real-time anti-error verification will fail, and the system will issue an alarm prompt. The power line electronic work ticket permit holder will forcibly unlock the power line electronic work ticket or return the power line electronic work ticket to the unit awaiting permission.
6. The intelligent error-prevention system for electronic work tickets of power lines according to claim 4 is characterized in that: The associated error prevention unit obtains the field content of the work content in all the electronic work tickets for power lines in all the bundles. When the field content of the work content of a certain electronic work ticket for power lines contains fields including "parameter testing" or "pressurization", an error prevention locking relationship is established for the electronic work ticket for power lines: when the electronic work ticket for power lines in any bundle is in the pending termination unit, the electronic work ticket for power lines whose work content contains fields including "parameter testing" or "pressurization" will not be able to pass the safety check of the associated error prevention unit, and an alarm will be given to the work permit holder.
7. The intelligent error-prevention system for electronic work tickets of power lines according to claim 6 is characterized in that: When the electronic work ticket for a power line whose work content includes fields such as "parameter test" or "pressurization" is in the stage of pending termination, the electronic work ticket for a power line in the corresponding bundle that is in the stage of pending permission will not be able to pass the safety check of the associated error prevention unit, and an alarm will be given to the work permit holder.
8. An intelligent error-prevention system for electronic work tickets of power lines according to any one of claims 5 to 7, characterized in that: The system lockout library supports manual addition of key fields for power line electronic work ticket permission locking function. The power line electronic work ticket permission locking function has the function of supporting manual release after review by the work permit holder.
9. The intelligent error-prevention system for electronic work tickets of power lines according to claim 1 is characterized in that: The method for obtaining the field content in the electronic work ticket of the power line adopts OCR text recognition technology.
10. An intelligent error-prevention method for electronic work tickets of power lines, characterized in that: include: S1. The electronic work tickets for power lines to be signed for will be subject to three-level error prevention verification. The electronic work tickets for power lines that have passed the three-level error prevention verification will be open to the signing function; specifically, The fields of work line and work location in the electronic work ticket of the power line in the stage of waiting for receipt are compared in pairs, and the two parts of the field content "**kVxx line" are extracted. If the two parts of the field content are completely consistent, it is judged that the first level of error prevention check has passed; among them, the "**" characters are Arabic numerals, and the "xx" characters are not restricted; Compare the fields of work line and work content of the electronic work ticket of the power line in the stage of waiting for receipt in pairs, extract the two parts of the field content "**kVxx line", if the two parts of the field content are completely consistent, it is judged that the second level error prevention check has passed; For the electronic work tickets of power lines that are waiting to be signed, the field contents of the safety measures "line interval name that should be transferred to the maintenance state" are compared in pairs, and the two parts of the field contents "**kVxx line" are extracted. If the two parts of the field contents are completely consistent, it is judged that the third-level error prevention check has passed; After passing the three-level error prevention check, the electronic work ticket of the power line will open the signing function. After the electronic work ticket of the power line is signed, step S2 is executed. If any level of error prevention check fails, the system will sign and lock and issue an alarm prompt; S2. Obtain the field content "**kVxx line" of the safety measures "line interval name to be transferred to maintenance status" of all power line electronic work tickets and compare them to establish the mutual correlation relationship of the power line electronic work tickets; specifically, Obtain the field content "**kVxx line" of the safety measure "name of the line interval that should be turned into the maintenance state" of all the electronic work tickets for power lines, and compare them; generate a bundle package for each electronic work ticket for power lines with completely non-overlapping safety measures. When the field content "**kVxx line" of the safety measure "name of the line interval that should be turned into the maintenance state" of multiple electronic work tickets for power lines overlap, they are bundled together, and the bundle package is associated with multiple electronic work tickets for power lines; when the process of the electronic work ticket for power lines flows to the terminated stage, the corresponding electronic work ticket for power lines is removed from the bundle package; S3. Obtain the field contents of the work contents in all the electronic work tickets for electric power lines in all the bundles. When the field contents of the work contents of a certain electronic work ticket for electric power lines include the fields of "parameter testing" or "pressurization", establish an anti-error locking relationship for the electronic work ticket for electric power lines: when the electronic work ticket for electric power lines in any bundle is in the pending termination stage, the electronic work ticket for electric power lines whose work contents include the fields of "parameter testing" or "pressurization" will not be able to pass the safety check of the associated anti-error unit, and give an alarm to the work permit holder; and, when the electronic work ticket for electric power lines whose work contents include the fields of "parameter testing" or "pressurization" is in the pending termination stage, the electronic work ticket for electric power lines in the corresponding bundle that is in the pending permission stage will not be able to pass the safety check of the associated anti-error unit, and give an alarm to the work permit holder.
Citation Information
Patent Citations
Cross-platform power grid intelligent program-controlled error-preventing system and operation method and interface communication way
CN102073305A
Monitoring remote control operation intelligent linkage anti-misoperation locking method based on IES700 system
CN113410907A
Method and system for monitoring whole process of patrol and maintenance operation
CN116259117A
Cash letter print streams with audit data
US20060191998A1
Cited By
Operation safety management and control system and management and control method based on multi-source data fusion
CN122415001A