Power grid distribution line real-time monitoring and analyzing system

By introducing computer vision video image processing module in the power grid video surveillance system, intelligent identification and automatic alarm of transmission lines are realized, and the problems of low manual monitoring efficiency and poor alarm accuracy in the existing technology are solved, which improves the power grid Safety and reliability.

CN119010324APending Publication Date: 2024-11-22HEFEI SWITCH FACTORY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410893676.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-04
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The existing power grid video surveillance system relies on manual monitoring, resulting in low efficiency, poor alarm accuracy, many false alarms and missed reports, and it is difficult to detect transmission line failures in a timely manner, which increases the safety and reliability challenges of power grid operation.

Method used

The video image processing module in computer vision is introduced, and the real-time video images are analyzed using object detection, classification and recognition algorithms to realize intelligent identification and automatic judgment, filter abnormal situations, and issue intelligent alarms through the monitoring and management system.

Benefits of technology

It improves the real-time monitoring efficiency of transmission lines, reduces the time cost of manual monitoring, enhances the grasp of the operating status of the power grid, promptly detects faults, reduces the number of power outages, and improves the safety and reliability of the power grid.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119010324A_ABST
    Figure CN119010324A_ABST
Patent Text Reader

Abstract

The invention provides a power grid distribution line real-time monitoring and analysis system, which comprises a client and a terminal, and is characterized in that the client and the terminal transmit internal information to each other; wherein the terminal further comprises a data acquisition front-end module and a video image processing module, and the data acquisition front-end module comprises a video acquisition unit; the video image processing module analyzes the acquired real-time video image by adopting target detection, target classification and a recognition mode recognition algorithm, and relates to the technical field of line real-time monitoring, in which whether a target exists in a view field and the position of the target are determined through an image processing technology; and on the basis of completing target detection, target tracking, intelligent identification and automatic judgment of monitoring on-site abnormal states, and filtering of abnormal conditions in an on-site environment are realized, so that management personnel can master the condition of a power transmission line conveniently, and an alarm signal is sent out through a monitoring management system when necessary, thereby realizing intelligent alarm.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of line real-time monitoring, and in particular to a real-time monitoring and analysis system for power distribution lines in a power grid. Background Art

[0002] In recent years, with the accelerating pace of China's power development, China's power grid has also developed rapidly, the operating voltage level of the power grid system has been continuously improved, and the network scale has been continuously expanded. The country has formed six large-scale cross-provincial regional power grids, namely the Northeast Power Grid, North China Power Grid, Central China Power Grid, East China Power Grid, Northwest Power Grid and Southern Power Grid, and has basically formed a complete long-distance transmission power grid framework. The power grid is a whole composed of substations and transmission and distribution lines of various voltages in the power system, which is called the power grid, which includes three units: substation, transmission and distribution.

[0003] The power facilities deployed by the power grid company are damaged during the large-scale mechanical construction process, which not only brings huge losses to the State Grid Corporation every year, but also the efficiency of manually adjusting the monitoring screen to find the accident screen is very low, and the manual real-time monitoring consumes a huge time cost. In order to timely discover the hidden dangers of transmission line faults, reduce the number of power outages, ensure the safe and stable operation of transmission lines, and improve the safety and reliability of the power grid, it is necessary to strengthen the online monitoring of transmission lines. The current video surveillance system mainly relies on manual monitoring by monitoring personnel. Since the monitoring system collects a large number of videos, the monitoring personnel are prone to fatigue, it is difficult to monitor each video in real time, the alarm accuracy is poor, and there are many false alarms and missed alarms. Summary of the invention

[0004] In order to overcome the existing problems, the embodiment of the present application provides a real-time monitoring and analysis system for power grid distribution lines, which introduces a video image processing module in computer vision into video monitoring. The video image processing module adopts target detection, target classification and recognition pattern recognition algorithms to analyze the collected real-time video images, and determines whether there is a target and the position of the target in the field of view through image processing technology, and realizes target tracking on the basis of completing target detection, monitors abnormal conditions on site for intelligent identification and automatic judgment, filters abnormal conditions in the on-site environment, and facilitates management personnel to grasp the transmission line conditions. When necessary, an alarm signal is issued through the monitoring management system to realize intelligent alarm.

[0005] The technical solution adopted by the embodiment of the present application to solve the technical problem is:

[0006] A real-time monitoring and analysis system for power distribution lines, comprising a client and a terminal, wherein the client and the terminal transmit information to each other, and the main function of the terminal is to collect and monitor the operation data of power system equipment, and transmit this data information to the main station module of the control center, and then execute the remote operation instructions sent by the main station module of the control center;

[0007] Wherein, the terminal also includes a data acquisition front-end module and a video image processing module;

[0008] The data acquisition front-end module includes a video acquisition unit, which includes an analog camera, a network camera, a video storage device, a front-end control and management device, and an auxiliary device. The video signal is collected according to the control signal sent by a pre-set program, and the data is transmitted to the background control center by wireless transmission;

[0009] The video image processing module adopts target detection, target classification and recognition pattern recognition algorithms to analyze the collected real-time video images, determines whether there is a target and the position of the target in the field of view through image processing technology, and realizes target tracking on the basis of completing target detection, monitors the abnormal state of the scene for intelligent identification and automatic judgment, filters abnormal conditions in the scene environment, and facilitates management personnel to grasp the situation of the transmission line. When necessary, an alarm signal is issued through the monitoring management system to realize intelligent alarm.

[0010] Preferably, the terminal further comprises a monitoring center backend module, which manages and controls the data acquisition frontend module and is used to provide software and hardware equipment for providing services;

[0011] Among them, after the back-end module of the monitoring center receives the real-time video image data from the data acquisition front-end module, it analyzes and processes it, and issues alarm information in time when fault information is found. It also uses a database to store relevant data, predicts its changing trend based on historical data and real-time data, and evaluates the operating status of the line, so that managers can understand the status of the transmission line and issue alarm signals through the monitoring management system when necessary.

[0012] Preferably, the client is used to provide to on-duty personnel and management personnel of the production monitoring center;

[0013] Among them, the on-duty personnel of the monitoring center can use the browsing function of video monitoring, and professional managers and relevant supervisors of production, safety supervision, scheduling and other departments can browse the on-site video images through laptops and mobile phones via wireless networks.

[0014] Preferably, the terminal also includes a control center master station module;

[0015] Among them, the control center main station module is used to actively extract different types of data and information collected by each data terminal as needed. The control center main station module and the terminal adopt a question-and-answer type of data communication. The control center main station module actively extracts different types of data and information collected by each data terminal as needed. This communication method enables the dispatcher to use flexible and changeable methods to dispatch and control the power grid according to the characteristics of different information.

[0016] Preferably, the data acquisition front-end module includes a data collection unit and a data preprocessing unit, and the data collection unit transmits the collected data to the data preprocessing unit.

[0017] Preferably, the data collection unit collects power grid operation status data information in real time through various information detection devices, and exchanges information with the control center master station module, and the data preprocessing unit includes checking switch position reliability, testing data rationality and data filtering;

[0018] Among them, after the terminal collects the displacement switch information, it transmits the data information to the control center main station module multiple times. The control center main station module verifies and corrects the multiple data information received by comparing them, thereby reducing errors in information transmission.

[0019] The advantages of the embodiments of the present application are:

[0020] The present invention introduces a video image processing module in computer vision into video monitoring. The video image processing module adopts target detection, target classification and recognition pattern recognition algorithms to analyze the collected real-time video images, determines whether there is a target and the position of the target in the field of view through image processing technology, and realizes target tracking on the basis of completing target detection, monitors the abnormal state of the scene for intelligent recognition and automatic judgment, filters abnormal situations in the scene environment, and facilitates management personnel to grasp the situation of the power transmission line. When necessary, an alarm signal is sent through the monitoring management system to realize intelligent alarm. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 This is a flow chart of the real-time monitoring and analysis system for power grid distribution lines of the present invention;

[0022] Figure 2 It is a schematic diagram of the flow of the data acquisition front-end module in the real-time monitoring and analysis system of the power grid distribution line of the present invention.

[0023] Description of main reference numerals:

[0024] 1. Client; 2. Terminal; 3. Data acquisition front-end module; 4. Video image processing module; 5. Monitoring center back-end module; 6. Data collection unit; 7. Data pre-processing unit. DETAILED DESCRIPTION

[0025] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. In addition, for the convenience of description below, the referenced "upper", "lower", "left", and "right" are the same as the upper, lower, left, and right directions of the drawings themselves. The "first", "second", etc. below are distinguished for the description and have no other special meanings.

[0026] The embodiment of the present application solves the problems in the prior art by providing a real-time monitoring and analysis system for power grid distribution lines, introduces a video image processing module in computer vision into video monitoring, and uses target detection, target classification and recognition pattern recognition algorithms to analyze the collected real-time video images, determines whether there is a target and the position of the target in the field of view through image processing technology, and realizes target tracking on the basis of completing target detection, monitors abnormal conditions on site for intelligent identification and automatic judgment, filters abnormal conditions in the on-site environment, and facilitates management personnel to grasp the status of transmission lines. When necessary, an alarm signal is issued through the monitoring management system to realize intelligent alarm.

[0027] The technical solution in the embodiment of the present application is to solve the above problems, and the overall idea is as follows:

[0028] Example

[0029] This embodiment provides a real-time monitoring and analysis system for power distribution lines. Figure 1-2 As shown, the real-time monitoring and analysis system for power distribution lines includes a client 1 and a terminal 2. The internal information of the client 1 and the terminal 2 is transmitted to each other. The main function of the terminal 2 is to collect and monitor the operation data of the power system equipment, and transmit this data information to the control center master station module 8, and then execute the remote operation instructions sent by the control center master station module 8;

[0030] The terminal 2 also includes a data acquisition front-end module 3 and a video image processing module 4;

[0031] The data acquisition front-end module 3 includes a video acquisition unit, which includes an analog camera, a network camera, etc., a video storage device, a front-end control and management device, and auxiliary equipment. The video signal is collected according to the control signal sent by the pre-set program, and the data is transmitted to the background control center through wireless transmission;

[0032] The video image processing module 4 adopts target detection, target classification and recognition pattern recognition algorithms to analyze the collected real-time video images, and determines whether there is a target and the position of the target in the field of view through image processing technology, and realizes the tracking of the target on the basis of completing the target detection, and realizes the tracking of the target on the basis of completing the target detection, monitors the abnormal state of the scene for intelligent identification and automatic judgment, filters the abnormal situation in the scene environment, and facilitates the management personnel to grasp the situation of the transmission line. When necessary, an alarm signal is issued through the monitoring management system to realize intelligent alarm.

[0033] By adopting the above technical solution:

[0034] Through image processing technology, it is determined whether there is a target and the position of the target in the field of view, and the target is tracked on the basis of completing target detection. It is also possible to track the target on the basis of completing target detection, monitor the abnormal status of the site for intelligent identification and automatic judgment, filter out abnormal situations in the on-site environment, and facilitate managers to understand the situation of the transmission line. When necessary, an alarm signal is issued through the monitoring management system to realize intelligent alarm.

[0035] The terminal 2 also includes a monitoring center back-end module 5, which manages and controls the data acquisition front-end module 3 and is used to provide service software and hardware equipment. After receiving the real-time video image data from the data acquisition front-end module 3, the monitoring center back-end module 5 analyzes and processes it, and promptly issues an alarm message when fault information is found, and uses a database to store relevant data. According to historical data and real-time data, its change trend is predicted, and the operating status of the line is evaluated, so that management personnel can grasp the status of the transmission line and send an alarm signal through the monitoring management system when necessary.

[0036] Client 1 is used for use by on-duty personnel and managers of the production monitoring center. Among them, on-duty personnel of the monitoring center can use the browsing function of video monitoring, and professional managers and relevant supervisors of production, safety supervision, scheduling and other departments can browse on-site video images through laptops and mobile phones through wireless networks.

[0037] The terminal 2 also includes a control center main station module 8;

[0038] Among them, the control center main station module 8 is used to actively extract different types of data and information collected by each data terminal as needed. The control center main station module 8 and the terminal 2 adopt a question-and-answer type of data communication. The control center main station module 8 actively extracts different types of data and information collected by each data terminal as needed. This communication method enables the dispatcher to use flexible and changeable methods to dispatch and control the power grid according to the characteristics of different information.

[0039] By adopting the above technical solution:

[0040] The main function of the terminal 2 is to collect and monitor the operation data of the power system equipment, and transmit this data information to the control center master station module 8, and then execute the remote operation instructions sent by the control center master station module 8.

[0041] The data acquisition front-end module 3 includes a data collection unit 6 and a data preprocessing unit 7 . The data collection unit 6 transmits the collected data to the data preprocessing unit 7 .

[0042] The data collection unit 6 collects the power grid operation status data information in real time through various information detection equipment, and exchanges information with the control center main station module 8. The data preprocessing unit 7 includes checking the switch change reliability, checking the rationality of the data and filtering the data. After the terminal 2 collects the change switch information, it transmits the data information to the control center main station module 8 for multiple times. The control center main station module 8 compares the received multiple data information for verification and error correction, thereby reducing errors in information transmission.

[0043] By adopting the above technical solution:

[0044] After collecting the position switch information, terminal 2 transmits the data information to the control center master station module 8 for multiple times. The control center master station module 8 performs verification and error correction by comparing the received multiple data information, thereby reducing errors in information transmission.

[0045] Finally, it should be noted that: Obviously, the above embodiments are only examples for clearly explaining the present invention, and are not intended to limit the implementation methods. For ordinary technicians in the relevant field, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived from this are still within the scope of protection of the present invention.

Claims

1. A real-time monitoring and analysis system for power distribution lines, characterized in that: The real-time monitoring and analysis system for power grid distribution lines comprises a client (1) and a terminal (2), wherein internal information of the client (1) and the terminal (2) is transmitted to each other; Wherein, the terminal (2) also includes a data acquisition front-end module (3) and a video image processing module (4); The data acquisition front-end module (3) includes a video acquisition unit, which acquires video signals according to control signals sent by a preset program and transmits the data to a background control center via wireless transmission; The video image processing module (4) adopts target detection, target classification and recognition pattern recognition algorithms to analyze the collected real-time video images.

2. A real-time monitoring and analysis system for power distribution lines according to claim 1, characterized in that: The terminal (2) also includes a monitoring center backend module (5), which manages and controls the data acquisition frontend module (3) and is used to provide software and hardware equipment for providing services.

3. A real-time monitoring and analysis system for power distribution lines according to claim 1, characterized in that: The client (1) is used for use by on-duty personnel and management personnel of a production monitoring center.

4. A real-time monitoring and analysis system for power distribution lines according to claim 1, characterized in that: The terminal (2) also includes a control center master station module (8); The control center master station module (8) is used to actively extract different types of data and information collected by each data terminal as needed.

5. A real-time monitoring and analysis system for power distribution lines according to claim 4, characterized in that: The data acquisition front-end module (3) comprises a data collection unit (6) and a data preprocessing unit (7), and the data collection unit (6) transmits the collected data to the data preprocessing unit (7).

6. A real-time monitoring and analysis system for power distribution lines according to claim 5, characterized in that: The data collection unit (6) collects power grid operation status data information in real time through various information detection devices, and exchanges information with the control center master station module (8).

7. A real-time monitoring and analysis system for power distribution lines according to claim 1, characterized in that: The data preprocessing unit (7) includes checking the reliability of switch displacement, checking the rationality of data and filtering the data.