Membrane bag sand blowing shortcut main body structure and construction method
By incorporating a screw and worm gear transmission system and a sliding sleeve locking mechanism, the problem of difficult geomembrane bag splicing was solved, enabling efficient construction of access roads.
Patent Information
- Application Number
- CN202411168945.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-23
- Publication Date
- 2024-11-26
AI Technical Summary
The lack of effective splicing and installation structures for existing geomembrane bags leads to low construction efficiency.
The design incorporates a combination of screw and worm gear transmission system, sliding sleeve and locking mechanism, insert block and pin structure, and guide rod positioning mechanism to achieve rapid longitudinal and transverse connection of geomembrane bags.
This increased the stacking speed of geomembrane bags and improved the efficiency of access road construction.
Smart Images

Figure CN119021059A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of geomembrane bags, and in particular to a main structure of a geomembrane bag sand-blowing access road and a construction method. Background Art
[0002] Geomembrane bags are large-area continuous bag-shaped materials made of two layers of geotextiles. The bags are filled with concrete or cement mortar, and after solidification, they form an integral concrete slab, which is suitable for slope protection. The upper and lower layers of the membrane bag are connected by a certain length of nylon rope to control the thickness during filling.
[0003] Geomembrane bags are continuous (or single) bag-shaped products made of a double-layer polymer fiber synthetic material. Concrete or cement mortar is poured into the membrane bag with a high-pressure pump. The thickness of the concrete or cement mortar is controlled by the length of the suspension bag and the suspension rope (polymer such as nylon, etc.) in the bag. After the concrete or cement mortar solidifies, a plate-like structure or other structure with a certain strength is formed to meet the needs of the project. Geomembrane bags are mainly used for slope protection, along the coast, river slopes, etc., and the mutual accumulation between the geomembrane bags forms a passage for walking, i.e. a road.
[0004] However, the existing geomembrane bags have a relatively simple structure, and the outside of the geomembrane bags lacks a certain splicing and installation structure, which results in the geomembrane bags being unable to be quickly spliced and adjusted during the process of being stacked into a walkway, thereby affecting the construction efficiency of the walkway. Summary of the invention
[0005] 1. Technical problems to be solved
[0006] The purpose of the present invention is to solve the problem that the outside of the geomembrane bag in the prior art lacks a certain splicing and installation structure, and to propose a main structure and construction method of a membrane bag sand blowing access road.
[0007] 2. Technical solution
[0008] In order to achieve the above object, the present invention adopts the following technical solutions:
[0009] A main structure of a walkway for film bag sand blowing, comprising a plurality of geomembrane bags, both ends of the geomembrane bags being fixedly connected to a first connecting plate, one of the first connecting plates being provided with a cavity, a screw being rotatably inserted in the cavity, a worm wheel being fixedly sleeved on the screw, a worm being rotatably inserted in the cavity and meshing with the worm wheel, one end of the worm passing through the inner wall of the cavity and being fixedly connected to a knob, one end of the knob being threadedly inserted with a fastening bolt, and a plurality of thread grooves corresponding to the fastening bolts being arranged around the first connecting plate;
[0010] One end of the screw rod passes through the inner wall of the cavity and extends outward, and the first connecting plate is provided with a mounting groove corresponding to the screw rod, and one end of the screw rod located in the mounting groove is threadedly sleeved with two symmetrically arranged transmission blocks, and the first connecting plate is fixedly connected to a side of the first connecting plate close to the mounting groove with two symmetrically arranged sliding rods, and a sliding sleeve is slidably sleeved on the sliding rod, and the two sliding sleeves are fixedly connected by a connecting rod, and the connecting rod and the transmission block are rotatably connected by the transmission rod, and the other first connecting plate is provided with a sliding groove corresponding to the sliding sleeve, and the outer wall of the first connecting plate is provided with a locking groove corresponding to the sliding groove, and a locking mechanism is fixedly connected in the locking groove;
[0011] A second connecting plate is provided on both sides of the geomembrane bag away from the first connecting plate, and both ends of the second connecting plate are fixedly connected with an insertion block, the first connecting plate is provided with a slot corresponding to the insertion block, a latch is slidably inserted in the slot, and a through hole corresponding to the latch is provided on the plug block, an arc-shaped fixing rod is rotatably connected to the first connecting plate through a pin shaft, the latch is provided with a fixing hole corresponding to the arc-shaped fixing rod, a torsion spring is sleeved on the pin shaft, and the two ends of the torsion spring are respectively against the arc-shaped fixing rod and the first connecting plate, one of the second connecting plates is fixedly connected with a guide rod on one side, and the other second connecting plate is provided with a guide cavity corresponding to the guide rod, a positioning mechanism is slidably inserted in the guide cavity, and a plurality of positioning grooves corresponding to the positioning mechanism are provided on the guide rod.
[0012] Preferably, a cross bar is fixedly connected in the installation groove, and a through opening corresponding to the cross bar is provided on the transmission block.
[0013] Preferably, one end of the sliding rod located in the sliding sleeve is fixedly connected to a limiting block.
[0014] Preferably, the locking mechanism comprises a support rod, an L-shaped locking rod is slidably sleeved on the support rod, a first spring is sleeved on the support rod, and two ends of the first spring are respectively fixedly connected to the L-shaped locking rod and the inner wall of the locking groove.
[0015] Preferably, the two second connecting plates in the same pair are fixedly connected via a plurality of elastic bands.
[0016] Preferably, the first connecting plate is provided with a plurality of fastening openings.
[0017] Preferably, the positioning mechanism comprises a positioning rod, one end of the positioning rod close to the guide rod is fixedly sleeved with a clamping sleeve, and one end of the positioning rod away from the clamping sleeve is fixedly connected with a pull rod.
[0018] Preferably, a second spring is sleeved on the positioning rod, and two ends of the second spring are fixedly connected to the pull rod and the outer wall of the second connecting plate respectively.
[0019] The present invention also proposes a construction method for a main structure of a membrane bag sand blowing access road, comprising the following steps:
[0020] S1: First, turn the knob to drive the worm to rotate, and through the meshing action between the worm and the worm wheel, drive the screw to rotate, and through the transmission action between the transmission block and the transmission rod, drive the connecting rod to move, adjust the distance between the sliding sleeve and the first connecting plate, and then fix the knob with the fastening bolt;
[0021] S2: then inserting the sliding sleeve into the sliding groove on another first connecting plate, and then fixing the sliding sleeve by using a locking mechanism to achieve the longitudinal connection of the geomembrane bag;
[0022] S3: Then insert the guide rod into the guide cavity of the second connecting plate on the adjacent geomembrane bag, adjust the gap as needed, and then fix the guide rod by the positioning mechanism to achieve the lateral connection of the geomembrane bag.
[0023] 3. Beneficial effects
[0024] Compared with the prior art, the advantages of the present invention are:
[0025] (1) In the present invention, by setting up the adjustment structure and the splicing structure, multiple geomembrane bags can be spliced and adjusted, which improves the stacking speed of the geomembrane bags and effectively improves the construction efficiency of the access road.
[0026] (2) In the present invention, the setting of the plug block and the latch can facilitate the connection and fixation of the first connecting plate to the first connecting plate. At the same time, the arc-shaped fixing rod can facilitate the fixation of the latch. The torsion spring can provide a certain torsional support for the arc-shaped fixing rod. At the same time, the setting of the fastening port can facilitate the reinforcement of the first connecting plate.
[0027] (3) In the present invention, the limit block can prevent the sliding rod from falling off the sliding sleeve, the first spring can provide a certain elastic support for the L-shaped locking rod, the second spring can provide a certain elastic support for the positioning rod, the setting of the elastic belt can reinforce and protect the outside of the geomembrane bag, and the setting of the cross bar can prevent the transmission block from shaking. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 This is a schematic structural diagram of the main structure of a membrane bag sand blowing access road proposed by the present invention;
[0029] Figure 2 This is a schematic diagram of the side view of the worm gear of the main structure of a membrane bag sand blowing walkway proposed by the present invention;
[0030] Figure 3 for Figure 1 A schematic diagram of the structure at A;
[0031] Figure 4 for Figure 1 Schematic diagram of the structure at point B.
[0032] In the figure: 1 geomembrane bag, 2 first connecting plate, 3 screw, 4 worm gear, 5 worm, 6 knob, 7 fastening bolt, 8 mounting groove, 9 transmission block, 10 sliding rod, 11 sliding sleeve, 12 connecting rod, 13 transmission rod, 14 locking groove, 15 second connecting plate, 16 plug block, 17 latch, 18 pin shaft, 19 arc-shaped fixing rod, 20 guide rod, 21 cross bar, 22 limit block, 23 support rod, 24 L-shaped locking rod, 25 first spring, 26 elastic band, 27 fastening port, 28 positioning rod, 29 ferrule, 30 pull rod, 31 second spring. DETAILED DESCRIPTION
[0033] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0034] Embodiment 1:
[0035] Reference Figure 1-4 , a main structure of a membrane bag sand blowing access road, comprising a plurality of geomembrane bags 1, both ends of the geomembrane bags 1 are fixedly connected with a first connecting plate 2, the first connecting plate 2 is provided with a plurality of fastening openings 27, one of the first connecting plates 2 is provided with a cavity, a screw 3 is rotatably inserted in the cavity, used to drive a transmission block 9 to slide, a worm wheel 4 is fixedly sleeved on the screw 3, used to drive the screw 3 to rotate, a worm 5 meshing with the worm wheel 4 is rotatably inserted in the cavity, one end of the worm 5 passes through the inner wall of the cavity and is fixedly connected with a knob 6, used to drive the worm 5 to rotate, a fastening bolt 7 is threadedly inserted at one end of the knob 6, convenient for fixing the knob 6, and a plurality of thread grooves corresponding to the fastening bolts 7 are arranged around the first connecting plate 2;
[0036] In the present invention, one end of the screw rod 3 passes through the inner wall of the cavity and extends outward, and the first connecting plate 2 is provided with a mounting groove 8 corresponding to the screw rod 3, and one end of the screw rod 3 located in the mounting groove 8 is threadedly sleeved with two symmetrically arranged transmission blocks 9, which are used to drive the connecting rod 12 to slide up and down through the transmission rod 13, and a cross bar 21 is fixedly connected in the mounting groove 8, and a through hole corresponding to the cross bar 21 is provided on the transmission block 9, which is used to support the transmission block 9, and the first connecting plate 2 is fixedly connected with two symmetrically arranged sliding rods 10 on one side close to the mounting groove 8, and a sliding sleeve 11 is slidably sleeved on the sliding rod 10, and one end of the sliding rod 10 located in the sliding sleeve 11 is fixedly connected with a limiting block 22 to prevent the sliding rod 10 from falling off from the sliding sleeve 11;
[0037] In the present invention, the two sliding sleeves 11 are fixedly connected by a connecting rod 12, and the connecting rod 12 and the transmission block 9 are rotationally connected by a transmission rod 13. A sliding groove corresponding to the sliding sleeve 11 is provided on the other first connecting plate 2, and a locking groove 14 corresponding to the sliding groove is provided on the outer wall of the first connecting plate 2. A locking mechanism is fixedly connected in the locking groove 14 for fixing the sliding sleeve 11.
[0038] In the present invention, the locking mechanism includes a support rod 23, on which an L-shaped locking rod 24 is slidably sleeved, for fixing the sliding sleeve 11, and a first spring 25 is sleeved on the support rod 23, and the two ends of the first spring 25 are respectively fixedly connected to the L-shaped locking rod 24 and the inner wall of the locking groove 14, so as to provide a certain elastic support for the L-shaped locking rod 24;
[0039] In the present invention, the second connecting plates 15 are provided on both sides of the geomembrane bag 1 away from the first connecting plate 2. The two second connecting plates 15 are fixedly connected by a plurality of elastic bands 26, which provide a certain elastic protection for the geomembrane bag 1. The two ends of the second connecting plates 15 are fixedly connected with plug blocks 16. The first connecting plate 2 is provided with a slot corresponding to the plug block 16, which is used to connect the first connecting plate 2 and the second connecting plate 15. A latch 17 is slidably inserted in the slot, and a through hole corresponding to the latch 17 is provided on the plug block 16, which is used to fix the plug block 16.
[0040] In the present invention, an arc-shaped fixing rod 19 is rotatably connected to the first connecting plate 2 through a pin shaft 18, a fixing hole corresponding to the arc-shaped fixing rod 19 is provided on the latch 17, a torsion spring is sleeved on the pin shaft 18, and the two ends of the torsion spring are respectively against the arc-shaped fixing rod 19 and the first connecting plate 2, so as to provide a certain torsional support for the arc-shaped fixing rod 19, a guide rod 20 is fixedly connected to one side of one of the second connecting plates 15, and a guide cavity corresponding to the guide rod 20 is provided on the other second connecting plate 15, a positioning mechanism is slidably inserted in the guide cavity, and a plurality of positioning grooves corresponding to the positioning mechanism are provided on the guide rod 20, so as to fix the position of the guide rod 20;
[0041] In the present invention, the positioning mechanism includes a positioning rod 28, one end of the positioning rod 28 close to the guide rod 20 is fixedly sleeved with a clamping sleeve 29, and the end of the positioning rod 28 away from the clamping sleeve 29 is fixedly connected to a pull rod 30. A second spring 31 is sleeved on the positioning rod 28, and the two ends of the second spring 31 are respectively fixedly connected to the pull rod 30 and the outer wall of the second connecting plate 15, thereby providing a certain elastic support for the positioning rod 28.
[0042] In the present invention, a construction method for a main structure of a membrane bag sand blowing access road comprises the following steps:
[0043] S1: First, turn the knob 6 to drive the worm 5 to rotate, and through the meshing action between the worm 5 and the worm wheel 4, drive the screw 3 to rotate, and through the transmission action between the transmission block 9 and the transmission rod 13, drive the connecting rod 12 to move, adjust the distance between the sliding sleeve 11 and the first connecting plate 2, and then fix the knob 6 with the fastening bolt 7;
[0044] S2: Then insert the sliding sleeve 11 into the sliding groove on the other first connecting plate 2, and then fix the sliding sleeve 11 by using the locking mechanism to realize the longitudinal connection of the geomembrane bag 1;
[0045] S3: Then, the guide rod 20 is inserted into the guide cavity of the second connecting plate 15 on the adjacent geomembrane bag 1, and the gap is adjusted as needed, and then the guide rod 20 is fixed by the positioning mechanism to achieve the transverse connection of the geomembrane bag 1.
[0046] In the present invention, by setting the adjustment structure and the splicing structure, multiple geomembrane bags can be spliced and adjusted, which improves the stacking speed of the geomembrane bags and effectively improves the construction efficiency of the access road.
[0047] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A main structure of a membrane bag sand blowing access road, comprising a plurality of geomembrane bags (1), characterized in that: Both ends of the geomembrane bag (1) are fixedly connected with a first connecting plate (2), one of the first connecting plates (2) is provided with a cavity, a screw (3) is rotatably inserted in the cavity, a worm wheel (4) is fixedly sleeved on the screw (3), a worm (5) meshing with the worm wheel (4) is rotatably inserted in the cavity, one end of the worm (5) passes through the inner wall of the cavity and is fixedly connected with a knob (6), one end of the knob (6) is threadedly inserted with a fastening bolt (7), and a plurality of thread grooves corresponding to the fastening bolts (7) are arranged around the first connecting plate (2); One end of the screw rod (3) passes through the inner wall of the cavity and extends outwards, the first connecting plate (2) is provided with a mounting groove (8) corresponding to the screw rod (3), one end of the screw rod (3) located in the mounting groove (8) is threadedly sleeved with two symmetrically arranged transmission blocks (9), the first connecting plate (2) is fixedly connected with two symmetrically arranged sliding rods (10) on one side close to the mounting groove (8), the sliding rod (10) is slidably sleeved with a sliding sleeve (11), the two sliding sleeves (11) are fixedly connected by a connecting rod (12), the connecting rod (12) and the transmission block (9) are rotationally connected by a transmission rod (13), the other first connecting plate (2) is provided with a sliding groove corresponding to the sliding sleeve (11), the outer wall of the first connecting plate (2) is provided with a locking groove (14) corresponding to the sliding groove, and a locking mechanism is fixedly connected in the locking groove (14); The geomembrane bag (1) is provided with a second connecting plate (15) on both sides away from the first connecting plate (2), and both ends of the second connecting plate (15) are fixedly connected with an insert block (16), the first connecting plate (2) is provided with a slot corresponding to the insert block (16), a latch (17) is slidably inserted in the slot, and the insert block (16) is provided with a through hole corresponding to the latch pin (17), and the first connecting plate (2) is rotatably connected with an arc-shaped fixing rod (19) through a pin shaft (18), and the latch pin (17) A fixing hole corresponding to the arc-shaped fixing rod (19) is provided on the pin shaft (18), a torsion spring is sleeved on the pin shaft (18), and the two ends of the torsion spring are respectively against the arc-shaped fixing rod (19) and the first connecting plate (2), one side of one of the second connecting plates (15) is fixedly connected with a guide rod (20), and the other second connecting plate (15) is provided with a guide cavity corresponding to the guide rod (20), a positioning mechanism is slidably inserted in the guide cavity, and the guide rod (20) is provided with a plurality of positioning grooves corresponding to the positioning mechanism.
2. The main structure of the membrane bag sand blowing access road according to claim 1 is characterized in that: A cross bar (21) is fixedly connected in the installation groove (8), and a through opening corresponding to the cross bar (21) is provided on the transmission block (9).
3. The main structure of the membrane bag sand blowing access road according to claim 1 is characterized in that: One end of the sliding rod (10) located inside the sliding sleeve (11) is fixedly connected to a limiting block (22).
4. The main structure of the membrane bag sand blowing access road according to claim 1 is characterized in that: The locking mechanism comprises a support rod (23), an L-shaped locking rod (24) is slidably sleeved on the support rod (23), a first spring (25) is sleeved on the support rod (23), and two ends of the first spring (25) are respectively fixedly connected to the L-shaped locking rod (24) and the inner wall of the locking groove (14).
5. The main structure of the membrane bag sand blowing access road according to claim 1 is characterized in that: The two second connecting plates (15) of the same pair are fixedly connected via a plurality of elastic bands (26).
6. The main structure of the membrane bag sand blowing access road according to claim 1 is characterized in that: The first connecting plate (2) is provided with a plurality of fastening openings (27).
7. The main structure of the membrane bag sand blowing access road according to claim 1 is characterized in that: The positioning mechanism comprises a positioning rod (28), one end of the positioning rod (28) close to the guide rod (20) is fixedly sleeved with a clamping sleeve (29), and one end of the positioning rod (28) away from the clamping sleeve (29) is fixedly connected with a pull rod (30).
8. The main structure of the membrane bag sand blowing access road according to claim 7, characterized in that: The positioning rod (28) is sleeved with a second spring (31), and the two ends of the second spring (31) are respectively fixedly connected to the pull rod (30) and the outer wall of the second connecting plate (15).
9. A construction method for a main structure of a membrane bag sand blowing access road according to any one of claims 1 to 8, characterized in that: The following steps are involved: S1: First, the knob (6) is rotated to drive the worm (5) to rotate, and the screw (3) is driven to rotate through the meshing action between the worm (5) and the worm wheel (4), and the connecting rod (12) is driven to move through the transmission action between the transmission block (9) and the transmission rod (13), and the distance between the sliding sleeve (11) and the first connecting plate (2) is adjusted, and then the knob (6) is fixed by the fastening bolt (7); S2: then inserting the sliding sleeve (11) into the sliding groove on the other first connecting plate (2), and then fixing the sliding sleeve (11) by using a locking mechanism to achieve the longitudinal connection of the geomembrane bag (1); S3: Then, the guide rod (20) is inserted into the guide cavity of the second connecting plate (15) on the adjacent geomembrane bag (1), and the gap is adjusted as needed, and then the guide rod (20) is fixed by a positioning mechanism to achieve the transverse connection of the geomembrane bag (1).