Assembled foundation pit retaining wall structure

By setting up prefabricated water barrier and tube structure at the edge of the foundation pit, combined with the water pump and liquid level sensor, the problem of water seepage of the foundation pit is solved, the waterproof effect and stability of the retaining wall structure are improved, and the low humidity at the bottom of the foundation pit edge is ensured. and construction safety.

CN119021268AActive Publication Date: 2024-11-26SHANGHAI CONSTRUCTION FOURTH CONSTRUCTION GROUP CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411506694.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-28
Publication Date
2024-11-26
Estimated Expiration
2044-10-28

AI Technical Summary

Technical Problem

The existing foundation pit retaining wall structure cannot effectively prevent water seepage inside the foundation pit, resulting in loose soil and insufficient support, which may cause downfall or tilt.

Method used

The prefabricated water barrier and cannula structures are adopted under the ground layer of the edge of the foundation pit. The seepage water is extracted through the water pump and the pump pump in the cannula, and concrete piles are poured on the bottom plate and the lower layer of the prefabricated water barrier to enhance the fixation. It combines liquid level sensor monitoring and fine pore mesh to enhance the waterproof effect.

Benefits of technology

Effectively prevent water seepage from the ground at the edge of the foundation pit, reduce the risk of construction in the rainy season, ensure low humidity at the bottom of the edge of the foundation pit, and enhance the stability and waterproof effect of the retaining wall structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021268A_ABST
    Figure CN119021268A_ABST
Patent Text Reader

Abstract

The invention discloses a split mounting type foundation pit retaining wall structure, and belongs to the technical field of foundation pit retaining wall structures, and the split mounting type foundation pit retaining wall structure is characterized in that a prefabricated water baffle is arranged to block seepage water of a foundation pit wall surface and surface water of a foundation pit ground, so that underground water seepage at the edge of a foundation pit is avoided, and water seepage of a stratum at the edge of the foundation pit is reduced; and water is pumped through the water pump, water blocking the upper portion of the prefabricated water baffle is pumped out, the waterproof effect is improved, it is guaranteed that the bottom layer of the edge of the foundation pit is low in humidity, and it is guaranteed that foundation pit construction can still be conducted smoothly in rainy days.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of foundation pit retaining wall structures, and in particular relates to an assembled foundation pit retaining wall structure. Background Art

[0002] A retaining wall structure needs to be built on the walls around the foundation pit to reinforce the foundation pit and prevent water seepage. The wall can be reinforced by setting steel plates or prefabricated panels. The existing wall reinforcement structure is only a retaining wall structure for the wall. Accidental water seepage on the wall can still penetrate into the foundation pit through the bottom of the retaining wall structure. Moreover, the water seepage inside the foundation pit during the rainy season will also penetrate into the bottom layer below the retaining wall structure. Long-term water seepage will cause the soil below the retaining wall structure to become loose and the supporting force to be insufficient, causing problems such as collapse or even tilt of the retaining wall structure. Summary of the invention

[0003] In view of this, the purpose of the present invention is to provide an assembled foundation pit retaining wall structure, which is simple and reasonable to install and improves the water seepage problem below the stratum of the retaining wall structure.

[0004] In order to achieve the above object, the present invention provides the following technical solutions: The present invention includes a prefabricated water retaining plate embedded under the ground layer at the edge of a foundation pit, and the ground at the edge of the foundation pit is provided with a plurality of retaining wall structures arranged along the edge of the foundation pit, and the retaining wall structure includes wall panels and insert pipes spliced ​​at intervals, the wall panels are vertically arranged, and a bottom plate is provided on the bottom side of the wall panels, and casting holes are downwardly opened at the bottom plate, which sequentially pass through the bottom plate, the ground, the prefabricated water retaining plate and the lower soil layer of the prefabricated water retaining plate, and also include a pre-positioning cylinder placed on the inner side of the top of the casting hole and a steel cage inside the casting hole, concrete is poured in the casting hole, and slots spliced ​​with the edges of the wall panels are provided on both sides of the insert pipe, the soil at the bottom end of the insert pipe is hollowed out and a pumping pipe is provided, and the pumping pipe extends along the insert pipe to the outside of the foundation pit and is connected to a pumping pump.

[0005] Furthermore, the pumping pipes are arranged at intervals in the arranged insert pipes, and liquid level sensors are provided at the bottom ends of the other insert pipes. The liquid level sensors are arranged along the extension direction of the pumping pipes, the lower ends of the liquid level sensors contact the prefabricated water retaining plate, and the upper ends are higher than the ground at the edge of the foundation pit.

[0006] Furthermore, a connection flange fixedly connected to the bottom plate is provided at the upper end of the pre-positioning cylinder.

[0007] Furthermore, a reinforcing rib plate is fixedly connected between the wall plate and the bottom plate.

[0008] Furthermore, the bottom end of the cannula is a sharpened structure.

[0009] Furthermore, the bottom end of the insert pipe is against the top side of the prefabricated water retaining plate, and a plurality of through grooves are provided on the wall surface of the bottom end of the insert pipe, and a layer of fine mesh is covered on the through grooves.

[0010] Furthermore, the bottom surface of the prefabricated water retaining plate is horizontal, and the two sides extend obliquely outward and upward to form an inverted trapezoidal structure. The wall panel is located above the middle of the prefabricated water retaining plate, and the wall panel is filled with soil on one side of the foundation pit wall. The beneficial effects of the present invention are: The present invention is arranged on the ground at the edge of the foundation pit and is in the form of a wall structure. The construction method is as follows: first, a ditch is dug under the ground at the edge of the foundation pit, and then a prefabricated water retaining plate is laid in the ditch. The prefabricated water retaining plate is a steel plate structure. After the paving is completed, the ditch is filled and leveled, and the wall panels and the plugging plates are installed. The wall panels and the plugging plates are arranged at intervals, and the wall panels are vertically placed on the ground through the bottom plate structure. The plugging plates are plugged into the wall panels through slots, so that the retaining wall structure is a continuous and sealed water-proof wall surface. The wall panels are arranged against the wall surface of the foundation pit. After the retaining wall structure is arranged, a casting hole is drilled by a drilling rig, and the bottom plate, the ground, the prefabricated water retaining plate and the soil layer under the prefabricated water retaining plate are drilled at one time to form a casting hole, and then a pre-positioning tube is arranged at the bottom plate drilling hole. The steel cage is then poured with concrete. The pre-positioning cylinder is used to limit the vertical position of the wall panel. After the concrete solidifies, the steel cage forms a fixed pile body connecting the prefabricated water retaining plate, the wall panel and the ground. The pile body serves as the anchor structure of the retaining wall structure to prevent the wall panel from tilting. The retaining wall structure, by setting a prefabricated water retaining plate, blocks the seepage water of the foundation pit wall and the surface water of the foundation pit ground, avoids the penetration of underground water at the edge of the foundation pit, and reduces the seepage of the stratum at the edge of the foundation pit. By setting a pumping pipe in the insert pipe and pumping water through a pump, the water blocked above the prefabricated water retaining plate is pumped out, thereby improving the waterproof effect, ensuring a lower humidity at the bottom layer of the foundation pit edge, and ensuring that the foundation pit construction can proceed smoothly on rainy days.

[0011] Other advantages, objectives and features of the present invention will be described in the following description and will be apparent to those skilled in the art to some extent, or those skilled in the art may be taught from the practice of the present invention. The objectives and other advantages of the present invention may be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] In order to make the purpose, technical solution and beneficial effects of the present invention clearer, the present invention provides the following drawings for illustration: Figure 1 This is a schematic diagram of assembling a foundation pit retaining wall according to an embodiment of the present invention; Figure 2 A cross-sectional view of a casting hole in an embodiment of the present invention; Figure 3 This is a schematic diagram of the structure of the cannula end in an embodiment of the present invention; Figure 4 This is a schematic diagram of the splicing of wall panels and pipes according to an embodiment of the present invention; Figure 5This is a schematic diagram of the internal structure of the cannula in an embodiment of the present invention; The markings in the attached drawings are as follows: 1. Prefabricated water retaining plate; 2. Retaining wall structure; 21. Wall panel; 211. Reinforcing rib plate; 22. Insert pipe; 221. Slot; 222. Through groove; 223. Fine mesh; 23. Bottom plate; 24. Casting hole; 25. Pre-positioning cylinder; 251. Connecting flange; 26. Steel cage; 27. Pumping pipe; 28. Liquid level sensor. DETAILED DESCRIPTION

[0013] like Figure 1~Figure 5 As shown, the present invention discloses an assembled foundation pit retaining wall structure, such as Figure 1 , Figure 2 As shown, it includes a prefabricated water retaining plate 1 embedded in the ground layer at the edge of the foundation pit, and the ground at the edge of the foundation pit is provided with a plurality of retaining wall structures 2 arranged along the edge of the foundation pit, and the retaining wall structure 2 includes a wall panel 21 and a plug pipe 22 spliced ​​at intervals, the wall panel 21 is vertically arranged, and a bottom plate 23 is provided at the bottom side of the wall panel 21, and a casting hole 24 is downwardly opened at the bottom plate 23, which passes through the bottom plate 23, the ground, the prefabricated water retaining plate 1 and the soil layer under the prefabricated water retaining plate 1 in sequence, and also includes a pre-positioning cylinder 25 placed on the inner side of the top of the casting hole 24 and a steel cage 26 inside the casting hole 24, and concrete is poured in the casting hole 24, refer to Figure 4 , slots 221 spliced ​​with the edges of the wall panel 21 are provided on both sides of the insert pipe 22, the bottom end of the insert pipe 22 is against the top side of the prefabricated water retaining plate 1, and a plurality of through grooves 222 are provided on the bottom wall of the insert pipe 22, and a layer of fine mesh 223 is covered on the through grooves 222. The soil at the bottom end of the insert pipe 22 is hollowed out and a pumping pipe 27 is provided. The pumping pipe 27 extends along the insert pipe 22 to the outside of the foundation pit and is connected to a pumping pump.

[0014] This structure is set on the ground at the edge of the foundation pit and is a wall structure. Its construction method is to first dig a ditch under the ground at the edge of the foundation pit, and then lay a prefabricated water retaining plate 1 in the ditch. The prefabricated water retaining plate 1 is a steel plate structure. After paving, fill the ditch, and implement the installation of wall panels 21 and plug pipes 22. The wall panels 21 and the plug plates are arranged at intervals. The wall panels 21 are vertically placed on the ground through the bottom plate 23 structure. The plug pipe 22 is plugged with the wall panel 21 through the slot 221, so that the retaining wall structure 2 is a continuous and sealed waterproof wall surface. The wall panel 21 is set against the foundation pit wall surface. After the retaining wall structure 2 is arranged, the casting hole 24 is drilled by a drilling rig, and the bottom plate 23, the ground, the prefabricated water retaining plate 1 and the lower soil layer of the prefabricated water retaining plate 1 are drilled once to form a casting hole 24, and then set at the bottom plate 23 drilling hole The pre-positioning cylinder 25 anticipates the steel cage 26, and finally the concrete is poured. The pre-positioning cylinder 25 is used to vertically limit the wall panel 21. After the concrete solidifies, the steel cage 26 forms a fixed pile body connecting the prefabricated water retaining plate 1, the wall panel 21 and the ground. The pile body serves as an anchoring structure of the retaining wall structure 2 to prevent the wall panel 21 from tilting. The retaining wall structure, by setting the prefabricated water retaining plate 1, blocks the infiltration water of the foundation pit wall and the surface water of the foundation pit ground, avoids the penetration of underground water at the edge of the foundation pit, and reduces the seepage of the stratum at the edge of the foundation pit. By setting a pumping pipe 27 in the insert pipe 22 and pumping water through a pump, the water blocked above the prefabricated water retaining plate 1 is pumped out, thereby improving the waterproof effect, ensuring a lower humidity at the bottom layer of the foundation pit edge, and ensuring that the foundation pit construction can proceed smoothly on rainy days.

[0015] In a further solution, Figure 5 As shown, the pumping pipes 27 are arranged at intervals in the arranged inserts 22, and the bottom ends of the other inserts 22 are provided with liquid level sensors 28. The liquid level sensors 28 are arranged along the extension direction of the pumping pipes 27. The lower ends of the liquid level sensors 28 contact the prefabricated water retaining plate 1, and the upper ends are higher than the ground at the edge of the foundation pit.

[0016] In this structure, the liquid level sensor 28 can sense the depth of the liquid level in the infiltration tube 22. By setting the liquid level sensor 28, the degree of water seepage at the edge of the foundation pit can be determined to control the switch of the water pump and save energy. The intervally arranged water pumping pipes 27 and liquid level sensors 28 can not only ensure the rapid and uniform extraction of water seepage at the edge of the foundation pit, but also ensure the real-time data recording of the water seepage depth at the edge of the foundation pit.

[0017] In a further solution, Figure 1 and Figure 4 As shown, the upper end of the pre-positioning cylinder 25 is provided with a connection flange 251 fixedly connected to the bottom plate 23. By setting the flange, the pre-positioning cylinder 25 is fixed to the position of the bottom plate 23, thereby improving the fixing ability of the pre-positioning cylinder 25 and ensuring the vertical limiting of the wall panel 21 by the pre-positioning cylinder 25.

[0018] In a further solution, Figure 1 The wall panel 21 and the bottom plate 23 are fixedly connected with a reinforcing rib plate 211. By providing the reinforcing rib plate 211, the verticality between the bottom plate 23 and the vertical plate is ensured, and the supporting capacity of the wall panel 21 is also ensured after the construction is completed.

[0019] In a further solution, Figure 3 As shown, the bottom end of the insert tube 22 is a sharpened structure. By providing the insert tube 22 with a sharpened structure, it is easy to insert the insert tube 22 into the ground, thereby improving the convenience of construction operation.

[0020] In a further solution, the bottom surface of the prefabricated water retaining plate 1 is horizontal, and the two sides extend obliquely outward and upward, forming an inverted trapezoidal structure. The wall panel 21 is located above the middle of the prefabricated water retaining plate 1, and the wall panel 21 is filled with soil toward the side of the foundation pit wall. This structure is conducive to the collection and diversion of seepage water.

[0021] Finally, it should be noted that the above preferred embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail through the above preferred embodiments, those skilled in the art should understand that various changes can be made in form and details without departing from the scope defined by the claims of the present invention.

Claims

1. An assembled foundation pit retaining wall structure, characterized in that: The invention comprises a prefabricated water retaining plate (1) pre-buried under the ground layer at the edge of a foundation pit, the ground layer at the edge of the foundation pit is provided with a plurality of retaining wall structures (2) arranged along the edge of the foundation pit, the retaining wall structure (2) comprises wall panels (21) spliced ​​at intervals and a plug pipe (22), the wall panels (21) are arranged vertically, a bottom plate (23) is provided at the bottom side of the wall panels (21), and a pipe is downwardly opened at the bottom plate (23) and passes through the bottom plate (23), the ground, the prefabricated water retaining plate (1) and the lower layer of the prefabricated water retaining plate (1) in sequence. The pouring hole (24) of the soil layer also includes a pre-positioning tube (25) placed inside the top of the pouring hole (24) and a steel cage (26) inside the pouring hole (24). Concrete is poured in the pouring hole (24). Slots (221) are provided on both sides of the insert pipe (22) to be spliced ​​with the edge of the wall panel (21). The soil at the bottom end of the insert pipe (22) is hollowed out and provided with a pumping pipe (27). The pumping pipe (27) extends along the insert pipe (22) to the outside of the foundation pit and is connected to a pumping pump.

2. The assembled foundation pit retaining wall structure according to claim 1 is characterized in that: The water pumping pipes (27) are arranged at intervals in the arranged insert pipes (22), and the bottom ends of the other insert pipes (22) are provided with liquid level sensors (28). The liquid level sensors (28) are arranged along the extending direction of the water pumping pipes (27), and the lower ends of the liquid level sensors (28) contact the prefabricated water retaining plate (1), and the upper ends are higher than the ground at the edge of the foundation pit.

3. The assembled foundation pit retaining wall structure according to claim 2 is characterized in that: The upper end of the pre-positioning cylinder (25) is provided with a connecting flange (251) fixedly connected to the bottom plate (23).

4. The assembled foundation pit retaining wall structure according to claim 3 is characterized in that: A reinforcing rib plate (211) is fixedly connected between the wall plate (21) and the bottom plate (23).

5. The assembled foundation pit retaining wall structure according to claim 4 is characterized in that: The bottom end of the insertion tube (22) is a sharpened structure.

6. The assembled foundation pit retaining wall structure according to claim 5 is characterized in that: The bottom end of the insert pipe (22) is against the top side of the prefabricated water retaining plate (1), and a plurality of through grooves (222) are provided on the wall surface of the bottom end of the insert pipe (22), and a layer of fine mesh (223) is covered on the through grooves (222).

7. The assembled foundation pit retaining wall structure according to claim 6 is characterized in that: The bottom surface of the prefabricated water retaining plate (1) is horizontal, and the two sides extend obliquely outward and upward, forming an inverted trapezoidal structure. The wall panel (21) is located above the middle of the prefabricated water retaining plate (1), and the wall panel (21) is filled with soil on one side of the foundation pit wall.

Citation Information

Patent Citations

  • Retaining wall with drainage function

    CN212427187U

  • Foundation pit support with stable structure

    CN212742566U

  • Fabricated two-stage retaining wall structure

    CN212866031U

  • Cast-in-place pile reinforcement cage positioning device

    CN215329887U

  • Deep foundation pit supporting composite retaining wall with water pumping and recharging functions

    CN215948204U