Cross-shaped connecting joint of concrete modular laminated slab and wall and construction method of cross-shaped connecting joint
Through the cross-shaped connection nodes of the concrete modular stacked plate and the wall, the combination of prefabricated grooved bottom plate and cast-in-place top plate is used to cancel the extension steel bars, which solves the problems of construction difficulty and material waste in the existing technology, and achieves efficient and safe Construction and seismic resistance.
Patent Information
- Application Number
- CN202410990237.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-23
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-07-23
AI Technical Summary
In the construction of existing concrete floor slabs, there are problems such as high difficulty in supporting the formwork, high loss of formwork and high cost, and the extended steel bars of the overlapping boards affect the convenience of handling.
The cross-shaped connection nodes of concrete modular laminated plates and walls are adopted. By combining prefabricated grooved bottom plates and cast-in-place top plates, horizontal notches and overlapping steel bars are set, and the extension steel bars are eliminated, which simplifies the structure and improves the connection reliability, which is convenient for module production. , transport and install.
It improves the integrity and safety of modular buildings, shortens the construction process, reduces the building's own weight, reduces material waste and on-site operations, and improves construction efficiency and seismic resistance.
Smart Images

Figure CN119021387A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, in particular to a cross-shaped connection node between a concrete modular composite plate and a wall and a construction method thereof. Background Art
[0002] At present, the reinforced concrete slabs used in China include cast-in-place slabs and precast slabs. Cast-in-place slabs have good integrity, but they require on-site formwork and then pouring concrete. The construction period is difficult, the formwork loss is large, and the cost is high. Precast slabs do not require on-site formwork, have a short construction period, and a low cost. The composite slab is a better structural form that combines precast and cast-in-place concrete.
[0003] In the prior art, the composite slab usually has extended steel bars (such as CN218522059U, a reinforced concrete composite slab for modular buildings) to connect with the wall, etc. The provision of the extended steel bars affects the convenience of transportation. Summary of the invention
[0004] The present invention provides a cross-shaped connection node between a concrete modular composite plate and a wall and a construction method thereof, so as to solve the technical problems raised by the above-mentioned background technology.
[0005] In order to solve the above technical problems, the present invention discloses a cross-shaped connection node between a concrete modular composite plate and a wall, comprising: The slotted composite slab comprises two prefabricated slotted bottom plates and a cast-in-place top plate. The two prefabricated slotted bottom plates are spliced at a certain distance from left to right. A plurality of horizontal slots are arranged at intervals from front to back on one side where the two prefabricated slotted bottom plates are spliced with each other. The connecting piece 1 is connected in the horizontal slots corresponding to the two prefabricated slotted bottom plates. The upper double skin wall and the lower double skin wall are provided with the upper double skin wall just above the area between the two prefabricated slotted bottom plates, and the lower double skin wall is provided just below the area between the two prefabricated slotted bottom plates; a second connector is provided between the upper double skin wall and the lower double skin wall; the lower part of the third connector is pre-buried in the lower double skin wall, and the upper part of the third connector is used to be inserted into the upper double skin wall; A steel bar structure 1 is arranged in the prefabricated slotted bottom plate, and the steel bar structure 1 includes: a plurality of transverse steel bars 1 arranged at intervals on the left and right, and a plurality of longitudinal steel bars 1 arranged at intervals on the front and back are arranged below the plurality of transverse steel bars; the longitudinal direction is the left-right direction, and the transverse direction is the front-back direction; the longitudinal steel bars 1 are disconnected at the connection of the two prefabricated slotted bottom plates; the arrangement position of the horizontal notch in the front-back direction of the horizontal plane is staggered with the longitudinal steel bars 1; A second steel bar structure is arranged in the cast-in-place top plate, and the second steel bar structure includes: a plurality of transverse steel bars arranged at intervals on the left and right, and a plurality of longitudinal steel bars arranged at intervals on the upper sides of the plurality of transverse steel bars; the longitudinal steel bars are continuous and unbroken at the connection of the two prefabricated slotted bottom plates; The upper double wall, the lower double wall, the second connector, the third connector, two prefabricated slotted bottom plates and the first connector are formed into a connected entity with a cast-in-place top plate by cast-in-place concrete.
[0006] Preferably, the connecting member 1 is a lap steel bar 1.
[0007] Preferably, a total of 4 horizontal slots are arranged on one side of the prefabricated slotted bottom plate, and the spacing between the horizontal slots in the front-to-back direction is 100 mm; Both the transverse reinforcement 1 and the longitudinal reinforcement 1 use HRB400 with a diameter of 8mm as the stress-bearing reinforcement. The front-to-back spacing of the longitudinal reinforcement 1 adjacent to each other in a single prefabricated slotted bottom plate is 150mm; the left-right spacing of the transverse reinforcement 1 adjacent to each other at the non-horizontal notch of a single prefabricated slotted bottom plate is 150mm, and the left-right spacing of the transverse reinforcement 1 adjacent to each other at the horizontal notch of a single prefabricated slotted bottom plate is shortened to 112mm; The lap steel bar is pre-buried in the adjacent prefabricated slotted bottom plate. The length of the lap steel bar entering the horizontal slot is the anchorage length. The anchorage length is 40d, where d is the diameter of the lap steel bar. Both the transverse reinforcement 2 and the longitudinal reinforcement 2 use HRB400 with a diameter of 12 mm as the stress-bearing reinforcement; The horizontal notch is located at 1 / 2 of the area between adjacent longitudinal steel bars along the front-to-back direction. The depth of the horizontal notch is h = 40 mm, the width is a = 40 mm, and the length is n = 340 mm.
[0008] Preferably, the upper double-skin wall comprises two upper prefabricated walls arranged at intervals on the left and right, and the lower double-skin wall comprises two lower prefabricated walls arranged at intervals on the left and right, and a plurality of vertical steel bars are arranged at intervals on the upper prefabricated wall and the lower prefabricated wall, and two overlapping steel bars are connected between the vertical steel bars adjacent to each other on the left and right of the two upper prefabricated walls, and two overlapping steel bars are also connected between the vertical steel bars adjacent to each other on the left and right of the two lower prefabricated walls; The second connecting member is a circular dowel, the upper part of which is located between the two upper prefabricated walls, and the lower part of which is located between the two lower prefabricated walls; a mortar layer is provided at the upper end of the cast-in-place top slab; A notch 1 is provided in the lower part of the upper double-skin wall between the front and rear adjacent vertical steel bars; the annular dowel bar is located between the front and rear adjacent overlapping steel bars 2; The third connecting piece is an inverted U-shaped dowel. The adjacent grooves on the left and right of the two upper prefabricated walls are a group of grooves, and one group of grooves corresponds to the inverted U-shaped dowel one by one. The lower part of the inverted U-shaped dowel is pre-buried in the lower double wall, and the upper part of the inverted U-shaped dowel is used to be inserted into groove one.
[0009] Preferably, the diameter of the vertical steel bar is 12 mm, the spacing between the front and rear adjacent vertical steel bar groups in the front and rear direction is 100 mm, the diameter of the second lap steel bar is 12 mm, and the spacing between the front and rear adjacent lap steel bars in the front and rear direction is 100 mm; The annular dowel is set vertically between the upper double wall and the lower double wall. The annular dowel is 75mm wide and is located at 1 / 2 of the front-to-back direction of the adjacent lap steel bars 212. The dimensions of the slot are: 305mm high, 30mm wide, and 30mm long.
[0010] The present invention also discloses a construction method of a cross-shaped connection node between a concrete modular composite plate and a wall, comprising: Step S1: making a lower double wall; the specific production process is: firstly tie the vertical steel bars of the lower prefabricated wall and the lap steel bars between the two lower prefabricated walls, bury the inverted U-shaped dowel bars and the annular dowel bars, then cast one of the lower prefabricated walls, and cast the other lower prefabricated wall after it hardens; Step S2: making an upper double wall; the specific production process is: firstly tying the vertical steel bars of the upper prefabricated wall and the lap steel bars between the two upper prefabricated walls, then pouring one of the upper prefabricated walls, and pouring the other upper prefabricated wall after it hardens, and the upper double wall has a notch; Step S3: making two prefabricated slotted bottom plates; the specific manufacturing process of the prefabricated slotted bottom plates is: tying the steel bar structure of the prefabricated slotted bottom plates, and then pouring concrete to form the prefabricated slotted bottom plates; Step S4: assembling two lower prefabricated walls and two prefabricated slotted bottom plates on the formwork platform, and placing overlapping steel bars 1 in the horizontal slots; Step S5: After the installation of step S4 is completed, the concrete cast-in-place parts of the lower double skin wall, the prefabricated slotted bottom plate and the cast-in-place top plate are poured to form a cast-in-place top plate; Step S6: After the concrete poured in step S5 hardens, the upper double wall is installed, a group of notches of the upper double wall are installed one by one corresponding to the inverted U-shaped dowel bars of the lower double wall, and then the cast-in-place concrete part of the upper double wall is poured; Step S7: Finally, pour a two-centimeter mortar layer.
[0011] Preferably, steps S1, S2, S3, S5, and S6 are all performed based on concrete pouring equipment, the concrete pouring equipment includes a mixing device and a concrete conveying device, the discharge port of the mixing device is connected to the feed port of the concrete conveying device, and the mixing device screens the aggregate for preparing concrete and then mixes and stirs the raw materials for preparing concrete; the mixing device includes: The outer shell has a cylindrical shell fixedly installed in the middle of the upper end of the outer shell, and the motor is fixedly installed in the cylindrical shell. The output shaft of the motor is arranged vertically downward, and the lower end of the output shaft of the motor is fixedly connected to the vertical screw, and the lower end of the vertical screw is fixedly connected to the vertical electric telescopic rod. The fixed part of the vertical electric telescopic rod is rotatably connected to the upper end of the outer shell, and the telescopic part of the vertical electric telescopic rod is located in the outer shell and is connected with blades. A sealing block is fixedly arranged at the lower end of the telescopic part of the vertical electric telescopic rod, and the peripheral side of the sealing block is in sealing contact with the peripheral side of the inner wall of the discharge port at the lower end of the outer shell. The inner sleeve is threadedly sleeved on the vertical screw, and an outer sleeve is arranged in the middle part of the inner sleeve; a hopper connected to the discharge port is arranged at the lower end of the outer shell, and the discharge port 3 of the hopper is connected to the feed port of the concrete conveying device; A plurality of groups of multifunctional filtering devices are arranged evenly spaced along the circumferential direction of the cylindrical shell, and the multifunctional filtering devices include: a feed pipe, the lower part of the feed pipe is fixedly passed through the upper end of the outer shell, a horizontal filter screen is arranged in the feed pipe, and a discharge port 2 is arranged on one side of the feed pipe, a horizontal rod 1 slides radially along the cylindrical shell and passes through the side wall of the cylindrical shell, one end of a connecting rod 1 is hinged to an end of the horizontal rod 1 located in the cylindrical shell, and the other end of the connecting rod 1 is hinged to the corresponding side wall of the outer sleeve, a collecting box is arranged on one side of the feed pipe, and the feed port of the collecting box is connected with the said discharge port 2, a push block is arranged on the other end of the connecting rod 1, and the push block passes through the corresponding side wall of the feed pipe, and the push block is used to push the aggregate on the upper end of the horizontal filter screen to the discharge port 2.
[0012] Preferably, the multifunctional filtering device further comprises: a plurality of fixing blocks, the plurality of fixing blocks are arranged at intervals on the inner side wall of the feed pipe, a spring 1 is connected between the fixing blocks and the lower end of the horizontal filter screen, a protrusion is arranged on the first side of the lower end of the horizontal filter screen; the side of the horizontal filter screen close to the cylindrical shell along the radial direction of the cylindrical shell is the first side, and the side of the horizontal filter screen away from the cylindrical shell along the radial direction of the cylindrical shell is the second side; an inclined surface is arranged on the first side of the protrusion; the height of the first side of the inclined surface is higher than the height of the second side of the inclined surface, a horizontal rod 2 is arranged parallel to the horizontal rod 1, the horizontal rod 2 passes through the side wall of the first side of the feed pipe, the second side of the horizontal rod 2 contacts the inclined surface, and the first side of the horizontal rod 2 is connected to the horizontal rod 1 through a connecting rod 2; The mixing device also includes a vibrating device, which includes: a horizontal rod three, which penetrates the left side wall of the hopper along the left and right directions, a cone is fixedly arranged at the lower end of the sealing block, a cone surface is arranged at the lower part of the cone, and the distance between the left and right sides of the upper part of the cone surface is greater than the distance between the left and right sides of the lower part of the cone surface. The left side of the horizontal rod three is connected to the ball one through the connecting rod three, and the right side of the horizontal rod three is connected to the ball two. A fixing plate is fixedly arranged at the left part of the lower end of the shell, and a spring two is connected between the fixing plate and the connecting rod three.
[0013] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments.
[0014] Compared with the prior art, the present invention has the following beneficial effects: 1. The modular prefabricated slotted base plate with horizontal slots (strip slots) eliminates the protruding steel bars of the composite plate (specifically the prefabricated slotted base plate) in the cast-in-place node area, and replaces them with horizontal slots at the end of the prefabricated slotted base plate and overlapping steel bars. It has a simple structure, simple construction, reliable connection, and is convenient for module production, transportation, installation and splicing. It can effectively improve the integrity and safety of modular buildings, shorten the construction process, and improve construction efficiency.
[0015] 2. The prefabricated walls on both sides and the cast-in-place layer form a double-skin wall connected with the slotted composite slab. The double-skin wall is stressed by the longitudinal steel bars in the prefabricated formwork, which reduces the binding of the steel cage. The structural force transmission and force mechanism are clear, which can achieve coordinated force between the formwork and the cast-in-place layer and has good seismic performance.
[0016] Compared with traditional concrete modular nodes, the slotted composite slab-wall cross node realizes the coordinated force of the formwork and the cast-in-place layer. The amount of steel used in module production is less than that of traditional nodes, and the wall thickness is reduced, which can greatly reduce the overall self-weight of the building, increase the internal space, reduce material waste and a large amount of on-site work. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings: Figure 1 It is a front view of the whole of the connection node of the present invention; Figure 2 A top view of the prefabricated slotted bottom plate of the present invention; Figure 3 It is a structural schematic diagram of the horizontal notches of the prefabricated slotted bottom plate of the present invention; Figure 4 A top view of the upper double skin wall of the present invention; Figure 5 It is a front view of the upper double skin wall of the present invention; Figure 6 A top view of the lower double skin wall of the present invention; Figure 7 It is a front view of the lower double skin wall of the present invention; Figure 8 It is a schematic diagram of the three-dimensional structure of the mixing device of the present invention; Fig. 9 is a cross-sectional view of a mixing device of the present invention; Fig.10 for Fig. 9 A schematic diagram of the enlarged structure of region A; Fig.11 for Fig. 9 Schematic diagram of the enlarged structure of area B.
[0018] In the figure: 1. slotted composite plate; 11. prefabricated slotted bottom plate; 12. horizontal notch; 13. cast-in-place top plate; 14. steel bar structure 1; 141. transverse steel bar 1; 142. longitudinal steel bar 1; 15. steel bar structure 2; 151. transverse steel bar 2; 152. longitudinal steel bar 2; 2. upper double wall; 21. upper prefabricated wall; 211. vertical steel bar; 212. lap steel bar 2; 213. notch 1; 214. inverted U-shaped dowel bar; 3. lower double wall; 31. lower prefabricated wall; 4. annular dowel bar; 5. lap steel bar 1; 6. mortar layer; 7. mixing device; 71. shell; 72. cylindrical shell; 73. motor; 74. vertical lead screw; 75. vertical electric telescopic rod; 751. vertical electric telescopic rod 752, the telescopic part of the vertical electric telescopic rod; 76, the blade; 77, the inner sleeve; 78, the outer sleeve; 79, the discharge port 1; 710, the feeding pipe; 711, the discharge port 2; 712, the horizontal rod 1; 713, the connecting rod 1; 714, the collecting box; 715, the push block; 716, the fixed block; 717, the spring 1; 718, the protrusion; 7181, the inclined plane; 719, the connecting rod 2; 720, the horizontal rod 2; 721, the sealing block; 722, the hopper; 723, the horizontal filter; 8, the vibration device; 81, the horizontal rod 3; 82, the cone; 83, the cone surface; 84, the touch ball 1; 85, the touch ball 2; 86, the spring 2; 87, the connecting rod 3; 9, the fixing plate; 10, the fixing bracket. DETAILED DESCRIPTION
[0019] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.
[0020] In addition, in the present invention, the descriptions of "first", "second", etc. are only used for descriptive purposes, and do not specifically refer to the order or sequence, nor are they used to limit the present invention. They are only used to distinguish components or operations described with the same technical terms, and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the technical solutions and technical features between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in the field to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be considered that such a combination of technical solutions does not exist and is not within the scope of protection required by the present invention.
[0021] The present invention provides the following embodiments Embodiment 1, the embodiment of the present invention provides a cross-shaped connection node between a concrete modular composite panel and a wall, such as Figure 1-Figure 7 As shown, including: The slotted composite plate 1 comprises two prefabricated slotted bottom plates 11 and a cast-in-place top plate 13. The two prefabricated slotted bottom plates 11 are spliced at a certain distance from each other. A plurality of horizontal slots 12 are arranged at intervals from front to back on one side where the two prefabricated slotted bottom plates 11 are spliced with each other. A connecting piece 1 is connected in the horizontal slots 12 corresponding to the two prefabricated slotted bottom plates 11. The upper double wall 2 and the lower double wall 3 are provided. The upper end of the slotted composite board 1 is located above the area between the two prefabricated slotted bottom plates 11, and the lower double wall 3 is provided below the area between the two prefabricated slotted bottom plates 11; a second connector is provided between the upper double wall 2 and the lower double wall 3; the lower part of the third connector is pre-buried in the lower double wall 3, and the upper part of the third connector is used to be inserted into the upper double wall 2; A steel bar structure 14 is arranged in the prefabricated slotted bottom plate 11, and the steel bar structure 14 includes: a plurality of transverse steel bars 141 arranged at intervals on the left and right, and a plurality of longitudinal steel bars 142 arranged at intervals on the front and back are arranged under the plurality of transverse steel bars 141; the longitudinal direction is the left-right direction, and the transverse direction is the front-back direction; the longitudinal steel bars 142 are disconnected at the connection of the two prefabricated slotted bottom plates 11; the arrangement position of the horizontal notch 12 in the front-back direction of the horizontal plane is staggered with the longitudinal steel bars 142; A second steel bar structure 15 is arranged in the cast-in-place top plate 13, and the second steel bar structure 15 includes: a plurality of transverse steel bars 151 arranged at intervals on the left and right, and a plurality of longitudinal steel bars 152 arranged at intervals on the upper side of the plurality of transverse steel bars 151; the longitudinal steel bars 152 are continuous and unbroken at the connection of the two prefabricated slotted bottom plates 11; The upper double wall 2, the lower double wall 3, the second connector, the third connector, the two prefabricated slotted bottom plates 11 and the first connector form a connected entity with a cast-in-place top plate 13 through cast-in-place concrete.
[0022] Specifically, the connecting member 1 is a lapped steel bar 5. In particular, the lapped steel bar 5 can shorten the anchorage length by using a steel bar ring or increasing the steel bar diameter, thereby reducing the notch length.
[0023] Specifically, a total of four horizontal slots 12 are arranged on one side of the prefabricated slotted bottom plate 11, and the spacing between the horizontal slots 12 in the front-to-back direction is 100 mm; The transverse steel bars 141 and the longitudinal steel bars 142 are both HRB400 with a diameter of 8 mm as the stress-bearing steel bars. The front-to-back spacing of the longitudinal steel bars 142 adjacent to each other in a single prefabricated slotted bottom plate 11 is 150 mm. The left-right spacing of the transverse steel bars 141 adjacent to each other at the non-horizontal notches 12 in a single prefabricated slotted bottom plate 11 is 150 mm. The left-right spacing of the transverse steel bars 141 adjacent to each other at the horizontal notches 12 in a single prefabricated slotted bottom plate 11 is shortened to 112 mm. The overlapping steel bar 5 is pre-buried on the adjacent prefabricated slotted bottom plate 11, and the length of the overlapping steel bar 5 buried in the horizontal slot 12 is the anchorage length, and the anchorage length is 40d, where d is the diameter of the overlapping steel bar 5; The transverse reinforcement 151 and the longitudinal reinforcement 152 both use HRB400 with a diameter of 12 mm as the stress-bearing reinforcement; The horizontal slot 12 is located at 1 / 2 of the area between adjacent longitudinal steel bars 142 along the front-to-back direction. The depth h of the horizontal slot 12 is 40 mm, the width a is 40 mm, and the length n is 340 mm. The size of the horizontal slot 12 can be adjusted according to actual conditions.
[0024] Specifically, the upper double-skin wall 2 includes two upper prefabricated walls 21 arranged at intervals on the left and right, and the lower double-skin wall 3 includes two lower prefabricated walls 31 arranged at intervals on the left and right. The upper prefabricated walls 21 and the lower prefabricated walls 31 are both provided with a plurality of vertical steel bars 211 (stress-bearing steel bars) at intervals on the front and back. The vertical steel bars 211 adjacent to the left and right of the two upper prefabricated walls 21 are connected to the lap steel bars 212, and the vertical steel bars 211 adjacent to the left and right of the two lower prefabricated walls 31 are also connected to the lap steel bars 212; the area between the two upper prefabricated walls 21 and the area between the two lower prefabricated walls 31 is a node cast-in-place area. The second connecting member is an annular dowel 4, the upper part of which is located between the two upper prefabricated walls 21, and the lower part of which is located between the two lower prefabricated walls 31; a mortar layer 6 is provided at the upper end of the cast-in-place top plate 13; A notch 213 is provided in the lower part of the upper double-skin wall 2 between the front and rear adjacent vertical steel bars 211; the annular dowel bar 4 is located between the front and rear adjacent overlapping steel bars 212; The third connecting piece is an inverted U-shaped dowel 214. The adjacent grooves 213 on the left and right of the two upper prefabricated walls 21 form a group of grooves, and each groove group corresponds to the inverted U-shaped dowel 214 one by one. The lower part of the inverted U-shaped dowel 214 is pre-buried in the lower double wall 3, and the upper part of the inverted U-shaped dowel 214 is used to be inserted into the groove 213.
[0025] Specifically, the diameter of the vertical steel bar 211 is 12 mm, the spacing between the front and rear adjacent vertical steel bar groups in the front and rear direction is 100 mm, the diameter of the lap steel bar 212 is 12 mm, and the spacing between the front and rear adjacent lap steel bars 212 in the front and rear direction is 100 mm; to ensure the lateral stability of the prefabricated wall; The annular dowel 4 is vertically arranged between the upper double wall 2 and the lower double wall 3. The annular dowel 4 is 75 mm wide and is located at 1 / 2 of the front-to-back direction of the adjacent lap steel bars 212 to ensure that the node area is not prone to cracking. The dimensions of slot 1 213 are: 305 mm high, 30 mm wide, and 30 mm long.
[0026] The horizontal notches 12 of the left and right prefabricated slotted bottom plates 11 correspond one to one during hoisting, and the prefabricated walls on both sides of the double-skin wall (upper double-skin wall 2 and lower double-skin wall 3) are installed correspondingly at the bottom and top. After installation in place, the cast-in-place layer is cast using the formwork as a template to realize the connection structure.
[0027] The present invention also discloses a construction method of a cross-shaped connection node between a concrete modular composite plate and a wall, comprising: Step S1: making the lower double skin wall 3; the specific manufacturing process is: firstly tie the vertical steel bars 211 of the lower prefabricated wall 31 and the lap steel bars 212 between the two lower prefabricated walls 31, and bury the inverted U-shaped dowel bars 214 and the annular dowel bars 4, then cast one of the lower prefabricated walls 31, and cast the other lower prefabricated wall 31 after it hardens; Step S2: making the upper double wall 2; the specific manufacturing process is: firstly tying the vertical steel bars 211 of the upper prefabricated wall 21 and the lap steel bars 212 between the two upper prefabricated walls 21, then pouring one of the upper prefabricated walls 21, and pouring the other upper prefabricated wall 21 after it hardens, and the upper double wall 2 is provided with a notch 213; Step S3: making two prefabricated slotted bottom plates 11; the specific manufacturing process of the prefabricated slotted bottom plates 11 is: tying the steel bar structure 14 of the prefabricated slotted bottom plates 11, and then pouring concrete to form the prefabricated slotted bottom plates 11; Step S4: assembling two lower prefabricated walls 31 and two prefabricated slotted bottom plates 11 on the formwork platform, and placing overlapping steel bars 5 in the horizontal slots 12; Step S5: After the installation of step S4 is completed, the concrete cast-in-place parts of the lower double wall 3, the prefabricated slotted bottom plate 11 and the cast-in-place top plate 13 are cast to form the cast-in-place top plate 13; Step S6: After the concrete poured in step S5 hardens, the upper double wall 2 is installed, a group of notches of the upper double wall 2 is installed one-to-one with the inverted U-shaped dowel bars 214 of the lower double wall 3, and then the cast-in-place concrete part of the upper double wall 2 is poured; Step S7: Finally, pour a two-centimeter mortar layer.
[0028] The beneficial effects of the above technical solution are: 1. The modular prefabricated slotted bottom plate 11 with horizontal slots 12 (strip slots) eliminates the protruding steel bars of the composite plate (specifically the prefabricated slotted bottom plate 11) in the cast-in-place node area, and replaces them with horizontal slots 12 and overlapping steel bars at the ends of the prefabricated slotted bottom plate 11. The structure is simple, the construction is simple, the connection is reliable, and the module production, transportation, installation and splicing are convenient, which can effectively improve the integrity and safety of the modular building, shorten the construction process, and improve the construction efficiency.
[0029] 2. The prefabricated walls on both sides and the cast-in-place layer form a double-skin wall connected with the slotted composite slab. The double-skin wall is stressed by the longitudinal steel bars in the prefabricated formwork, which reduces the binding of the steel cage. The structural force transmission and force mechanism are clear, which can achieve coordinated force between the formwork and the cast-in-place layer and has good seismic performance.
[0030] Compared with traditional concrete modular nodes, the slotted composite slab-wall cross node realizes the coordinated force of the formwork and the cast-in-place layer. The amount of steel used in module production is less than that of traditional nodes, and the wall thickness is reduced, which can greatly reduce the overall self-weight of the building, increase the internal space, reduce material waste and a large amount of on-site work.
[0031] Embodiment 2, on the basis of embodiment 1, pouring concrete comprises: Step S11: Detecting the parameters of the concrete to be poured and the environmental parameters of the area to be poured. The parameters of the concrete to be poured include: the slump of the concrete to be poured, the temperature of the concrete to be poured, and the bulk density of the concrete to be poured; the environmental parameters include the ambient temperature and the ambient wind speed; Step S12: obtaining the allowable concrete force at different parts of the current area to be poured; Step S13: Obtain the flow rate information of the inlet of the concrete pouring pipe and the flow rate information of the outlet of the concrete pouring pipe in the last M consecutive monitoring time periods of the monitoring time of the pouring equipment before pouring the current area to be poured, and obtain the conveying loss coefficient of each monitoring time period. When the conveying loss coefficient of any monitoring time period is greater than the loss coefficient threshold, an alarm is given and the concrete pouring pipe is replaced before step S14 is performed; during the actual pouring process of the pouring equipment, a monitoring work of a monitoring time period is periodically performed, and the flow rate information of the inlet of the concrete pouring pipe and the flow rate information of the outlet of the concrete pouring pipe are respectively detected multiple times during the monitoring work; Step S13 obtains the flow rate information monitored for the M monitoring time periods with the latest actual monitoring time before pouring the current area to be poured;
[0032] is the transport loss coefficient of the jth monitoring time obtained before pouring the current area to be poured; is the average flow velocity at the inlet of the concrete pouring pipe obtained during the jth monitoring time before pouring the current area to be poured; The average flow rate at the outlet of the concrete pouring pipe during the jth monitoring period before pouring the current area to be poured; is the minimum flow rate at the outlet of the concrete pouring pipe obtained within the jth monitoring time before pouring the current area to be poured; e is a natural constant; Step S14: Calculate the target flow rate based on step S11, step S12, and step S13, and control the pouring equipment to pour concrete in the current area to be poured, so that the flow rate at the inlet of the concrete pouring pipe is within a preset range of the target flow rate;
[0033] is the target flow rate; is the minimum value of the force allowed to act on concrete at different parts of the current area to be poured (in Pa); is the actual detected value of the bulk density of the concrete to be poured (obtained based on the detection in step S11); The setting rate influence coefficient of the component of the concrete to be poured (obtained based on a preset table); is the total number of environmental parameters that have an impact on the setting of concrete; is the actual detected value of the i-th environmental parameter that affects the setting of concrete in the current area to be poured (obtained based on the detection in step S11); for The corresponding condensation rate influence coefficient (obtained based on a preset correlation function or correlation table); is the natural logarithm, e is the natural constant; Indicates the maximum value; is the setting rate influence coefficient (obtained based on the preset correlation function or correlation table) corresponding to the actual detection value of the slump of the concrete to be poured (obtained based on the detection in step S11); is the actual detection value of the temperature of the concrete to be poured (obtained based on the detection in step S11, in degrees Celsius). The pouring process of the first M monitoring time of the new pouring pipe does not need to execute step S13, and the corresponding target flow rate is calculated. The average value is the initial transmission loss coefficient; the above M can be greater than or equal to 3; min represents the minimum value; The 200 and 15 units are both degrees Celsius; The beneficial effects of the above technical solution are: before pouring the current area to be poured, obtain: the parameters of the concrete to be poured; the environmental parameters of the current area to be poured; the allowable concrete force at different components of the current area to be poured; the flow rate information at the inlet of the concrete pouring pipe and the flow rate information at the outlet of the concrete pouring pipe within the last (latest) continuous M monitoring time of the monitoring time of the pouring equipment to determine the target flow rate, and control the pouring equipment to make the flow rate at the inlet of the concrete pouring pipe pour the current area to be poured within the preset range of the target flow rate; ensure that the appropriate pouring flow rate is determined to adapt to the actual concrete state, environmental state, allowable stress state of the area to be poured, and transportation loss state of the pouring pipe, so as to ensure the pouring effect.
[0034] Embodiment 3, on the basis of embodiment 1 or 2, as Figure 8-Figure 11 As shown, steps S1, S2, S3, S5, and S6 are all performed based on a concrete pouring device, and the concrete pouring device includes a mixing device 7 and a concrete conveying device. The discharge port of the mixing device 7 is connected to the feed port of the concrete conveying device (which may be an existing concrete conveying pump, such as the conveying pump disclosed in CN 216031572 U, and the conveying pump is connected to the pouring pipe through a hose). The mixing device 7 screens the aggregate for preparing concrete and then mixes and stirs the raw materials for preparing concrete; the mixing device 7 includes: The outer shell 71 has a cylindrical shell 72 fixedly installed in the middle of the upper end of the outer shell 71, and a motor 73 is fixedly installed in the cylindrical shell 72. The output shaft of the motor 73 is vertically downwardly arranged, and the lower end of the output shaft of the motor 73 is fixedly connected to the vertical lead screw 74, and the lower end of the vertical lead screw 74 is fixedly connected to the vertical electric telescopic rod 75. The fixed part 751 of the vertical electric telescopic rod is rotatably connected to the upper end of the outer shell 71, and the telescopic part 752 of the vertical electric telescopic rod is located in the outer shell 71 and is connected to the blade 76. The lower end of the telescopic part 752 of the vertical electric telescopic rod is fixedly provided with a sealing block 721, and the peripheral side of the sealing block 721 is connected to the outer shell The inner wall of the discharge port 1 79 at the lower end of 71 is in sealed contact, the inner sleeve 77 is threadedly sleeved on the vertical screw 74 (wherein, a screw nut can be embedded in the inner sleeve 77, and the screw nut cooperates with the vertical screw 74), and the outer sleeve 77 is sleeved with an outer sleeve 78 at the middle part of the outer sleeve 77 (the outer sleeve 78 can be rotatably sleeved or fixedly sleeved with the inner sleeve 77); the lower end of the outer shell 71 is provided with a hopper 722 connected with the discharge port 1 79, and the discharge port 3 of the hopper 722 is connected with the feed port of the concrete conveying device; wherein, the lower end of the outer shell 71 can be provided with a fixed bracket 10 for supporting the placement surface of the mixing device (such as the ground); A plurality of groups of multifunctional filtering devices are evenly spaced along the circumferential direction of the cylindrical shell 72. The multifunctional filtering devices include: a feed pipe 710, the lower part of the feed pipe 710 is fixedly passed through the upper end of the shell 71, a horizontal filter screen 723 is arranged in the feed pipe 710, a discharge port 2 711 is arranged on one side of the feed pipe 710, a horizontal rod 1 712 slides radially along the cylindrical shell 72 and passes through the side wall of the cylindrical shell 72, and one end of the connecting rod 1 713 is connected to the water pipe 710. One end of the flat rod 712 located in the cylindrical shell 72 is hinged, and the other end of the connecting rod 713 is hinged to the corresponding side wall of the outer sleeve 78. A collecting box 714 is set on one side of the feed pipe 710, and the feed port of the collecting box 714 is connected to the said discharge port 2 711. A push block 715 is set at the other end of the connecting rod 713. The push block 715 penetrates the corresponding side wall of the feed pipe 710. The push block 715 is used to push the aggregate at the upper end of the horizontal filter 723 to the discharge port 2 711.
[0035] Specifically, the multifunctional filtering device also includes: a plurality of fixed blocks 716, the plurality of fixed blocks 716 are arranged at intervals on the inner side wall of the feed pipe 710, a spring 717 is connected between the fixed block 716 and the lower end of the horizontal filter screen 723, a protrusion 718 is arranged on the first side of the lower end of the horizontal filter screen 723; the side of the horizontal filter screen 723 close to the cylindrical shell 72 along the radial direction of the cylindrical shell 72 is the first side, and the side of the horizontal filter screen 723 away from the cylindrical shell 72 along the radial direction of the cylindrical shell 72 is the second side; a slope 7181 is arranged on the first side of the protrusion 718; the height of the first side of the slope 7181 is higher than the height of the second side of the slope 7181, the horizontal rod 720 is arranged parallel to the horizontal rod 712, the horizontal rod 720 passes through the side wall of the first side of the feed pipe 710, the second side of the horizontal rod 720 is in contact with the slope 7181, and the first side of the horizontal rod 720 is connected to the horizontal rod 712 through the connecting rod 2 719; The mixing device 7 also includes a vibration device 8, which includes: a horizontal rod three 81, the horizontal rod three 81 penetrates the left side wall of the hopper 722 along the left-right direction, a cone 82 is fixedly arranged at the lower end of the sealing block 721, a cone surface 83 is arranged at the lower part of the cone 82, and the distance between the left and right sides of the upper part of the cone surface 83 is greater than the distance between the left and right sides of the lower part of the cone surface 83. The left side of the horizontal rod three 81 is connected to the ball one 84 through the connecting rod three 87, and the right side of the horizontal rod three 81 is connected to the ball two 85. A fixing plate 9 is fixedly arranged on the left part of the lower end of the outer shell 71, and a spring two 86 is connected between the fixing plate 9 and the connecting rod three 87.
[0036] The horizontal filter 723 is used to screen the aggregates whose particle size needs to be controlled in the raw materials for preparing concrete. Different aggregates to be screened are screened through horizontal filter screens 723 with different apertures in different feed pipes 710, so as to ensure that the particle size of the aggregates for preparing concrete meets the use requirements and ensure the quality of the concrete finally prepared; the collecting box 714 is also provided with a weighing device for real-time weighing of the aggregates therein. After the push block 715 pushes the aggregates on the horizontal filter screen 723 that cannot pass through the horizontal filter screen 723 to the collecting box 714, the weight of the aggregates mixed in the outer shell 71 can be obtained according to the detection value of the weighing device and the weight of the aggregates added to the feed pipe 710, so as to ensure a suitable aggregate mixing ratio.
[0037] The working principle and beneficial effects of the above technical solution are: 1. When mixing the raw materials for preparing concrete: (1) In the initial state, the second side of the horizontal rod 720 contacts the upper end of the inclined surface 7181, and the aggregate to be screened enters the feed pipe 710 and is screened through the horizontal filter screen 723. First, the motor 73 is controlled to rotate forward to drive the vertical screw 74 to rotate, and the inner sleeve 77 is driven to move downward through the cooperation between the inner sleeve 77 and the vertical screw 74, so that the horizontal rod 1 712 is pushed away from each other through the connecting rod 1 713. The horizontal rod 1 712 drives the horizontal rod 2 720 to move through the connecting rod 2 719. Through the cooperation between the horizontal rod 2 720 and the inclined surface 7181, the horizontal filter screen 723 and the protrusion 718 are moved upward as a whole to the position shown in FIG. Fig.11 As shown in the position Fig.11 When the motor 73 rotates in the reverse direction, the horizontal filter screen 723 moves downward under the action of the spring 717, thereby realizing the up and down movement of the horizontal filter screen 723 to accelerate the screening of aggregates; and when the raw materials for preparing concrete are mixed, the sealing block 721 is in the position as shown in FIG. Figure 8 The position shown prevents unmixed materials from being discharged, and the rotation of the motor 73 can drive the blades 76 to rotate to mix the raw materials for preparing concrete; (2) When Fig.11 By continuing to control the motor 73 to rotate forward based on the position, the horizontal rod 1 712 can be pushed further away from each other through the connecting rod 1 713, and the push block 715 moves on the upper end of the horizontal filter screen 723. The push block 715 pushes the aggregate that cannot pass through the horizontal filter screen 723 to the collection box 714 through the discharge port 2 711, thereby automatically discharging the aggregate that cannot pass through the horizontal filter screen 723 and ensuring the screening efficiency of the horizontal filter screen 723.
[0038] (3) A motor 73 realizes three functions: first, it drives the blades 76 to mix the raw materials for preparing concrete; second, it realizes the up and down movement of multiple horizontal filters 723 to accelerate the screening of aggregates; third, it realizes the discharge of aggregates that cannot pass through the horizontal filters 723 on the multiple horizontal filters 723, which is easy to control; 2. When discharging mixed concrete: (1) In Figure 8On the basis of the invention, the vertical electric telescopic rod 75 is controlled to extend downward, so that the sealing block 721 moves downward to open the discharge port 1 79, so that the mixed concrete in the shell 71 enters the hopper 722, enters the concrete conveying device through the hopper 722, and is conveyed and poured by the concrete conveying device, and the sealing block 721 moves downward to drive the cone 82 to move downward, and the cooperation between the touch ball 2 85 and the cone surface 83 makes the touch ball 2 85 and the horizontal rod 3 81 move to the left as a whole, so that the touch ball 2 85 can collide with the hopper 722, and accelerate the discharge of the hopper 722; then the vertical electric telescopic rod 75 can be controlled to shorten upward, so that the horizontal rod 3 81 moves to the right under the action of the spring 2 86, so that the touch ball 1 84 can collide with the hopper 722, and accelerate the discharge of the hopper 722, and the discharge efficiency of the present invention can be guaranteed by the alternating action of the touch ball 1 84 and the touch ball 2 85; and the up and down movement of the telescopic part 752 of the vertical electric telescopic rod can avoid the blockage of the discharge port 1 79; (2) The vertical electric telescopic rod 75 realizes four functions: first, the up and down movement of the telescopic portion 752 of the vertical electric telescopic rod can avoid blockage of the discharge port 79; second, the discharge port 79 can be opened or closed; third, the collision ball 84 and the collision ball 85 can be driven to collide with the hopper 722, thereby accelerating the discharge of the hopper 722; fourth, the up and down movement of the telescopic portion 752 of the vertical electric telescopic rod and the rotation of the motor 73 can cause the blades 76 connected to the vertical electric telescopic rod 75 to stir different parts of the outer shell 71, and the cone 82 to stir different positions in the hopper 722.
[0039] Embodiment 4, based on any one of Embodiments 1-3, further comprises: The process of making the lower double skin wall 3 in step S1 includes: Step S101: Obtaining material parameters of concrete of the lower prefabricated wall 31, dimensions of the lower prefabricated wall 31, and material parameters and dimensions of the inverted U-shaped dowel 214; Step S102: obtaining the actual historical front-to-back arrangement spacing of the inverted U-shaped dowel bars 214 in the same type of lower prefabricated wall 31 that has been poured and qualified, and the angle between the side surface of the inverted U-shaped dowel bars 214 and the top surface of the lower prefabricated wall 31; Step S03: Calculate the depth of the inverted U-shaped dowel bar 214 inserted into the lower prefabricated wall 31 based on steps S101 and S102;
[0040] is the diameter of the inverted U-shaped dowel 214, is the elastic modulus of the concrete in the lower precast wall 31; is the elastic modulus of the inverted U-shaped dowel 214; B is the bending inertia moment of the inverted U-shaped dowel 214; is a constant, with a value of 0.0025 and a unit of 1 / mm; L is the average value of the actual historical front-to-back arrangement spacing obtained in step S102; is the depth of the inverted U-shaped dowel bar 214 embedded in the lower prefabricated wall 31; is the compressive strength of the concrete in the lower precast wall 31; is the compressive strength of the inverted U-shaped dowel 214; is the shear force that the lower double skin wall 3 can withstand; is the natural logarithm, e is the natural constant; is the unit diameter; G is the spacing correction coefficient; is the height of the concrete in the lower precast wall 31; is the height of the inverted U-shaped dowel 214 (in this embodiment, the height direction ( Figure 1 The middle up-down direction) is the direction in which the inverted U-shaped dowel 214 is inserted into the lower prefabricated wall 31); is the angle between the side surface of the inverted U-shaped dowel 214 obtained in step S102 and the top surface of the lower prefabricated wall 31; sin is the sine; and S is the cross-sectional area of the U-shaped dowel 214.
[0041] The beneficial effects of the above technical solution are as follows: based on: the material parameters of the concrete of the lower prefabricated wall 31, the size of the lower prefabricated wall 31; the material parameters of the inverted U-shaped dowel 214, the size of the inverted U-shaped dowel 214; the position information of the inverted U-shaped dowel 214 in the same type of lower prefabricated wall 31 that has been cast and qualified; the depth of the inverted U-shaped dowel 214 inserted into the lower prefabricated wall 31 is calculated, and the calculation is reliable; In practice, the inverted U-shaped dowel 214 is inserted into the lower prefabricated wall 31 at the depth H before the lower prefabricated wall 31 is cast, thereby ensuring the connection strength between the inverted U-shaped dowel 214 and the lower prefabricated wall.
[0042] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.
Claims
1. A cross-shaped connection node between a concrete modular composite panel and a wall, characterized in that: include: The slotted composite plate (1) comprises two prefabricated slotted bottom plates (11) and a cast-in-place top plate (13), wherein the two prefabricated slotted bottom plates (11) are spliced at a certain distance from each other, and a plurality of horizontal slots (12) are arranged at intervals from front to back on one side of the two prefabricated slotted bottom plates (11) spliced together, and a connecting piece is connected in the corresponding horizontal slots (12) of the two prefabricated slotted bottom plates (11); An upper double-skin wall (2) and a lower double-skin wall (3); the upper end of the slotted composite board (1) is located directly above the area between the two prefabricated slotted bottom plates (11) to arrange the upper double-skin wall (2); the lower end of the slotted composite board (1) is located directly below the area between the two prefabricated slotted bottom plates (11) to arrange the lower double-skin wall (3); a second connector is arranged between the upper double-skin wall (2) and the lower double-skin wall (3); the lower portion of the third connector is pre-buried in the lower double-skin wall (3), and the upper portion of the third connector is used to be inserted into the upper double-skin wall (2); A steel bar structure (14) is arranged in the prefabricated slotted bottom plate (11), and the steel bar structure (14) includes: a plurality of transverse steel bars (141) arranged at intervals in the left and right, and a plurality of longitudinal steel bars (142) arranged at intervals in the front and back are arranged under the plurality of transverse steel bars (141); the longitudinal direction is the left-right direction, and the transverse direction is the front-back direction; the longitudinal steel bars (142) are disconnected at the connection of the two prefabricated slotted bottom plates (11); the arrangement position of the horizontal notch (12) in the front-back direction of the horizontal plane is staggered with the longitudinal steel bars (142); A second steel bar structure (15) is arranged in the cast-in-place top plate (13), and the second steel bar structure (15) includes: a plurality of second transverse steel bars (151) arranged at intervals on the left and right, and a plurality of second longitudinal steel bars (152) arranged at intervals on the upper side of the plurality of second transverse steel bars (151); the second longitudinal steel bars (152) are continuous and unbroken at the connection of the two prefabricated slotted bottom plates (11); The upper double wall (2), the lower double wall (3), the second connector, the third connector, the two prefabricated slotted bottom plates (11), and the first connector form a connected whole with a cast-in-place top plate (13) by cast-in-place concrete.
2. The cross-shaped connection node between a concrete modular composite panel and a wall according to claim 1, characterized in that: The connecting member 1 is a lap steel bar 1 (5).
3. The cross-shaped connection node between a concrete modular composite panel and a wall according to claim 2, characterized in that: A total of four horizontal slots (12) are arranged on one side of the prefabricated slotted bottom plate (11), and the spacing between the horizontal slots (12) in the front-to-back direction is 100 mm; The transverse steel bars (141) and the longitudinal steel bars (142) are both made of HRB400 steel with a diameter of 8 mm as the stress-bearing steel bars. The longitudinal steel bars (142) adjacent to each other in the front and rear direction in a single prefabricated slotted bottom plate (11) are spaced 150 mm in the front and rear direction. The transverse steel bars (141) adjacent to each other in the non-horizontal notches (12) in the single prefabricated slotted bottom plate (11) are spaced 150 mm in the left and right direction. The transverse steel bars (141) adjacent to each other in the horizontal notches (12) in the single prefabricated slotted bottom plate (11) are spaced 112 mm in the left and right direction. The overlapping steel bar (5) is pre-buried on the adjacent prefabricated slotted bottom plate (11), and the length of the overlapping steel bar (5) buried in the horizontal slot (12) is the anchoring length, and the anchoring length is 40d, where d is the diameter of the overlapping steel bar (5); The second transverse steel bar (151) and the second longitudinal steel bar (152) are both made of HRB400 with a diameter of 12 mm as the stress-bearing steel bars; The horizontal notch (12) is located at 1 / 2 of the area between adjacent longitudinal steel bars (142) along the front-to-back direction. The horizontal notch (12) has a depth of h=40 mm, a width of a=40 mm, and a length of n=340 mm.
4. The cross-shaped connection node between a concrete modular composite panel and a wall according to claim 1, characterized in that: The upper double-skin wall (2) comprises two upper prefabricated walls (21) arranged at intervals on the left and right, and the lower double-skin wall (3) comprises two lower prefabricated walls (31) arranged at intervals on the left and right. The upper prefabricated walls (21) and the lower prefabricated walls (31) are both provided with a plurality of vertical steel bars (211) arranged at intervals on the front and back. The two upper prefabricated walls (21) are connected to each other by a second overlapping steel bar (212), and the two lower prefabricated walls (31) are also connected to each other by a second overlapping steel bar (212). The second connecting member is an annular dowel (4), the upper part of the annular dowel (4) is located between the two upper prefabricated walls (21), and the lower part of the annular dowel (4) is located between the two lower prefabricated walls (31); a mortar layer (6) is provided at the upper end of the cast-in-place top plate (13); A notch 1 (213) is provided in the lower part of the upper double-skin wall (2) between the front and rear adjacent vertical steel bars (211); the annular dowel bar (4) is located between the front and rear adjacent overlapping steel bars 2 (212); The third connecting member is an inverted U-shaped dowel bar (214), and the adjacent notches (213) of the two upper prefabricated walls (21) form a group of notches, and the notches of the group correspond to the inverted U-shaped dowel bars (214) one by one. The lower part of the inverted U-shaped dowel bar (214) is pre-buried in the lower double-skin wall (3), and the upper part of the inverted U-shaped dowel bar (214) is used to be inserted into the notch (213).
5. The cross-shaped connection node between a concrete modular composite panel and a wall according to claim 4, characterized in that: The diameter of the vertical steel bar (211) is 12 mm, and the distance between the front and rear adjacent vertical steel bar groups in the front and rear direction is 100 mm. The diameter of the second overlapping steel bar (212) is 12 mm, and the distance between the front and rear adjacent overlapping steel bars (212) in the front and rear direction is 100 mm. The annular dowel bar (4) is vertically arranged between the upper double wall (2) and the lower double wall (3), the annular dowel bar (4) is 75 mm wide, and the annular dowel bar (4) is located at the half of the front-to-back direction of the adjacent lap steel bars 2 (212); The dimensions of slot one (213) are: 305 mm in height, 30 mm in width, and 30 mm in length.
6. The construction method of a cross-shaped connection node between a concrete modular composite slab and a wall according to any one of claims 1 to 5, characterized in that: include: Step S1: manufacturing the lower double-skin wall (3); the specific manufacturing process is: firstly tying the vertical steel bars (211) of the lower prefabricated wall (31) and the lap steel bars (212) between the two lower prefabricated walls (31), burying the inverted U-shaped dowel bars (214) and the annular dowel bars (4), then casting one of the lower prefabricated walls (31), and after it hardens, casting the other lower prefabricated wall (31); Step S2: making an upper double-skin wall (2); the specific manufacturing process is: firstly tying the vertical steel bars (211) of the upper prefabricated wall (21) and the lap steel bars (212) between the two upper prefabricated walls (21), then casting one of the upper prefabricated walls (21), and after it hardens, casting the other upper prefabricated wall (21), and the upper double-skin wall (2) is provided with a notch (213); Step S3: manufacturing two prefabricated slotted bottom plates (11); the specific manufacturing process of the prefabricated slotted bottom plates (11) is: tying the steel bar structure 1 (14) of the prefabricated slotted bottom plates (11), and then pouring concrete to form the prefabricated slotted bottom plates (11); Step S4: assembling two lower prefabricated walls (31) and two prefabricated slotted bottom plates (11) on the formwork platform, and placing overlapping steel bars (5) in the horizontal slots (12); Step S5: After the installation of step S4 is completed, the concrete cast-in-place parts of the lower double wall (3), the prefabricated slotted bottom plate (11) and the cast-in-place top plate (13) are cast to form the cast-in-place top plate (13); Step S6: After the concrete poured in step S5 hardens, the upper double wall (2) is installed, a group of notches of the upper double wall (2) is installed one-to-one with the inverted U-shaped dowel bars (214) of the lower double wall (3), and then the cast-in-place concrete part of the upper double wall (2) is poured; Step S7: Finally, pour a two-centimeter mortar layer.
7. The construction method of the cross-shaped connection node between the concrete modular composite slab and the wall according to claim 6, characterized in that: Pouring concrete includes: Step S11: Detecting the parameters of the concrete to be poured and the environmental parameters of the area to be poured. The parameters of the concrete to be poured include: the slump of the concrete to be poured, the temperature of the concrete to be poured, and the bulk density of the concrete to be poured; the environmental parameters include the ambient temperature and the ambient wind speed; Step S12: obtaining the allowable concrete force at different parts of the current area to be poured; Step S13: obtaining the flow rate information of the inlet of the concrete pouring pipe and the flow rate information of the outlet of the concrete pouring pipe in the last M consecutive monitoring time periods of the pouring equipment before pouring the current area to be poured, and obtaining the transmission loss coefficient for each monitoring time period; ; is the transport loss coefficient of the jth monitoring time obtained before pouring the current area to be poured; is the average flow velocity at the inlet of the concrete pouring pipe obtained during the jth monitoring time before pouring the current area to be poured; The average flow rate at the outlet of the concrete pouring pipe during the jth monitoring period before pouring the current area to be poured; is the minimum flow rate at the outlet of the concrete pouring pipe obtained within the jth monitoring time before pouring the current area to be poured; e is a natural constant; Step S14: Calculate the target flow rate based on step S11, step S12, and step S13, and control the pouring equipment to pour concrete in the current area to be poured, so that the flow rate at the inlet of the concrete pouring pipe is within a preset range of the target flow rate; ; is the target flow rate; is the minimum value of the force allowed to concrete at different parts of the current area to be poured; The actual test value of the bulk density of the concrete to be poured; is the setting rate influence coefficient of the component of the concrete to be poured; is the total number of environmental parameters that have an impact on the setting of concrete; is the actual detected value of the i-th environmental parameter that affects the setting of concrete in the current area to be poured; for The corresponding condensation rate influence coefficient; is the natural logarithm, e is the natural constant; Indicates the maximum value; is the setting rate influence coefficient corresponding to the actual detection value of the slump of the concrete to be poured; It is the actual detected value of the temperature of the concrete to be poured; min represents the minimum value.
8. The construction method of the cross-shaped connection node between the concrete modular composite slab and the wall according to claim 6, characterized in that: Steps S1, S2, S3, S5 and S6 are all performed based on a concrete pouring device. The concrete pouring device comprises a mixing device (7) and a concrete conveying device. The discharge port of the mixing device (7) is connected to the feed port of the concrete conveying device. The mixing device (7) screens the aggregate for preparing concrete and then mixes and stirs the raw materials for preparing concrete. The mixing device (7) comprises: The outer shell (71) is provided with a cylindrical shell (72) fixedly mounted in the middle of the upper end of the outer shell (71), and a motor (73) is fixedly mounted in the cylindrical shell (72). The output shaft of the motor (73) is arranged vertically downward, and the lower end of the output shaft of the motor (73) is fixedly connected to a vertical lead screw (74), and the lower end of the vertical lead screw (74) is fixedly connected to a vertical electric telescopic rod (75). The fixed part (751) of the vertical electric telescopic rod is rotatably connected to the upper end of the outer shell (71), and the telescopic part (752) of the vertical electric telescopic rod is located in the outer shell (71) and connected to the outer shell (71). A blade (76) is provided, a sealing block (721) is fixedly arranged at the lower end of the telescopic part (752) of the vertical electric telescopic rod, the peripheral side of the sealing block (721) is in sealing contact with the peripheral side of the inner wall of the discharge port 1 (79) at the lower end of the housing (71), the inner sleeve (77) is threadedly sleeved on the vertical lead screw (74), and an outer sleeve (78) is sleeved on the middle part of the inner sleeve (77); a hopper (722) connected to the discharge port 1 (79) is arranged at the lower end of the housing (71), and the discharge port 3 of the hopper (722) is connected to the feed port of the concrete conveying device; A plurality of groups of multifunctional filtering devices are arranged evenly spaced along the circumferential direction of the cylindrical shell (72), and the multifunctional filtering devices include: a feed pipe (710), the lower part of the feed pipe (710) is fixedly passed through the upper end of the shell (71), a horizontal filter screen (723) is arranged in the feed pipe (710), a discharge port 2 (711) is arranged on one side of the feed pipe (710), a horizontal rod 1 (712) slides radially along the cylindrical shell (72) and passes through the side wall of the cylindrical shell (72), and one end of a connecting rod 1 (713) is connected to the horizontal rod 1 One end of the connecting rod (712) located in the cylindrical shell (72) is hinged, and the other end of the connecting rod (713) is hinged to the corresponding side wall of the outer sleeve (78). A collecting box (714) is arranged on one side of the feed pipe (710), and the feed port of the collecting box (714) is connected to the said discharge port 2 (711). A pushing block (715) is arranged on the other end of the connecting rod (713), and the pushing block (715) passes through the corresponding side wall of the feed pipe (710). The pushing block (715) is used to push the aggregate at the upper end of the horizontal filter (723) to the discharge port 2 (711).
9. The construction method of the cross-shaped connection node between the concrete modular composite slab and the wall according to claim 8, characterized in that: The multifunctional filtering device further comprises: a plurality of fixing blocks (716), the plurality of fixing blocks (716) being arranged at intervals on the inner side wall of the feed pipe (710), a spring (717) being connected between the fixing blocks (716) and the lower end of the horizontal filter screen (723), a protrusion (718) being arranged on the first side of the lower end of the horizontal filter screen (723); a side of the horizontal filter screen (723) close to the cylindrical shell (72) along the radial direction of the cylindrical shell (72) being the first side, and a side of the horizontal filter screen (723) away from the cylindrical shell (72) along the radial direction of the cylindrical shell (72) being the second side. ) is the second side; a slope (7181) is provided on the first side of the protrusion (718); the height of the first side of the slope (7181) is higher than the height of the second side of the slope (7181); the second horizontal rod (720) is provided parallel to the first horizontal rod (712); the second horizontal rod (720) passes through the side wall of the first side of the feeding pipe (710); the second side of the second horizontal rod (720) contacts the slope (7181); and the first side of the second horizontal rod (720) is connected to the first horizontal rod (712) via the second connecting rod (719); The mixing device (7) also includes a vibrating device (8), which includes: a horizontal rod three (81), the horizontal rod three (81) penetrates the left side wall of the hopper (722) along the left-right direction, a cone (82) is fixedly arranged at the lower end of the sealing block (721), a cone surface (83) is arranged at the lower part of the cone (82), the distance between the left and right sides of the upper part of the cone surface (83) is greater than the distance between the left and right sides of the lower part of the cone surface (83), the left side of the horizontal rod three (81) is connected to the first ball (84) through the connecting rod three (87), and the right side of the horizontal rod three (81) is connected to the second ball (85), and a fixed plate (9) is fixedly arranged at the left part of the lower end of the shell (71), and a spring two (86) is connected between the fixed plate (9) and the connecting rod three (87).
Citation Information
Patent Citations
Energy-saving building structural system suitable for industrialized production
CN101575872A
Integrated concrete stirring device
CN108858746A
Concrete pouring side station supervision method based on artificial intelligence
CN111582188A
Assembled double-leaf cavity laminated wall system and construction method thereof
CN113389304A
Groove type prefabricated laminated slab without extending out of slab bottom steel bars
CN217782521U