Construction method for postposition of stairs in super high-rise core tube

Through the rear construction method of the stairs inside the super high-rise core cylinder, the construction in stages and the use of elevators is solved, the construction problem of small-area core cylinders in super high-rise buildings is improved, and the construction efficiency and safety are reduced, and the construction difficulty and cost are reduced.

CN119021478AInactive Publication Date: 2024-11-26SHANGHAI CONSTRUCTION NO 7 (GROUP) CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411220321.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-02
Publication Date
2024-11-26
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In super-high-rise buildings, it is difficult for traditional methods to effectively construct a small-area core cylinder, resulting in limited construction period promotion and increased construction difficulty.

Method used

The rear construction method of stairs in the super-high-rise core cylinder is adopted, including the construction of the core cylinder structure, the removal of the rack after the concrete strength reaches the design value, the installation of the elevator, and the stair construction are carried out, and the above steps are repeated until the roof elevation is completed, through phased construction and pre-burial Curtain walls and electromechanical systems improve construction efficiency and safety.

Benefits of technology

This method improves construction efficiency, reduces the difficulty of core cylinder construction, ensures construction safety and quality control, shortens construction period, and reduces costs through standardized and modular construction, improving the predictability and controllability of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021478A_ABST
    Figure CN119021478A_ABST
Patent Text Reader

Abstract

The invention relates to the field of building construction, in particular to a rear-mounted construction method for stairs in a super high-rise core tube, which comprises five steps of S1, S2, S3, S4 and S5, when the stairs in the super high-rise core tube need to be constructed, firstly, the construction of a core tube part is performed, the construction of the position of the stairs is suspended, and then when the concrete strength of the core tube reaches a design value, the construction of the core tube part is stopped; the core tube bent frame is removed, then the construction elevator is installed, then the stair is constructed, after the stair of each floor is constructed, the steps are repeated till the stair reaches the elevation position of the roof, and then the construction of the stair in the super high-rise core tube is completed. According to the construction method, the effects of improving the construction efficiency and reducing the construction difficulty of the core tube can be achieved to a certain extent under the condition that the quality technical requirements are met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of building construction, and in particular to a method for constructing a post-installed staircase in a super-high-rise core tube. Background Art

[0002] With the rapid development of my country's economy, there are more and more high-rise buildings and even super-high-rise buildings in cities. Super-high-rise buildings are generally of the structure of concrete core tube plus outer frame. During the construction process, the core tube first construction technology is basically adopted. The level of industrialized construction is improved by using climbing formwork, jacking platform inside the tube and other construction equipment. At present, a set of mature construction technology has been formed in the industry.

[0003] In related technologies, the floor structure is distributed radially from the center of the core tube. The core tube area is large and the outer facade of the tube is simple. It is relatively convenient to construct it according to the traditional construction method. However, when the core tube area is reduced, the working area is insufficient, making it difficult to construct it according to the traditional construction method, and seriously restricting the progress of the project schedule.

[0004] Therefore, how to provide a small-area core tube construction method that can improve construction efficiency while meeting quality and technical requirements and reduce the construction difficulty of the core tube is a technical problem that needs to be urgently solved by technical personnel in this field. Summary of the Invention

[0005] In order to improve construction efficiency while meeting quality and technical requirements and reduce the construction difficulty of the core tube, the present application provides a post-installed construction method for stairs in a super-high-rise core tube.

[0006] This application provides a method for constructing a rear-mounted staircase in a super-high-rise core tube, which adopts the following technical solution: A method for constructing a rear-mounted staircase in a super-high-rise core tube comprises the following steps: S1. Construction of the core tube structure, and suspension of construction of the staircase inside the tube; S2. After the core wall concrete strength reaches the design value, the core wall bents are removed; S3. Install construction hoist; S4. Carry out staircase construction; S5. Repeat the above steps S1-S4 until the roof elevation is reached.

[0007] By adopting the above technical solution, a total of five steps S1, S2, S3, S4, and S5 are set up. This construction method is highly flexible and widely applicable. It allows staircase construction to be carried out after the core tube structure reaches the design strength, thereby effectively avoiding interference and damage to the core tube structure during construction. Construction is carried out in stages to ensure construction safety and quality control. At the same time, the use of construction elevators improves construction efficiency. The repeated construction steps of S5 can help to achieve standardization and modularization in the construction process, reduce construction costs, shorten construction period, and improve the predictability and controllability of the overall construction. To a certain extent, this application has achieved the effect of improving construction efficiency while meeting quality and technical requirements and reducing the difficulty of core tube construction.

[0008] Optionally, the S1 includes: S11. Erect the core tube frame; S12, core tube shear wall reinforcement binding; S13, core tube shear wall formwork installation; S14, laying of core tube beam and slab formwork; S15, core tube beam and slab reinforcement binding; S16. Install curtain wall and electromechanical embedded parts on the core tube floor; S17. Pour concrete in one piece.

[0009] By adopting the above technical solution, the frames are erected first, the steel bars are tied, the formwork is installed, the beams and slabs and embedded parts are laid, and then the concrete is poured as a whole. This method not only improves construction efficiency, but also facilitates subsequent construction by considering the embedding of curtain walls and mechanical and electrical systems during the floor construction stage, reducing the need for later modifications. At the same time, this method also helps to optimize resource allocation, reduce material waste, and shorten the construction period of the entire project through advance planning and synchronous construction, thereby improving construction quality and the overall economic benefits of the project.

[0010] Optionally, the steel bar binding in S12 and S15 is a mechanical connection.

[0011] By adopting the above technical solution, the strength and stability of the steel bar connection can be effectively improved, and the mechanical connection can make the structural parts have better consistency and seismic performance.

[0012] Optionally, the S17 is prestressed concrete construction.

[0013] By adopting the above technical solutions, prestressed concrete construction technology can significantly improve the bearing capacity and stiffness of concrete structures, while reducing or avoiding the occurrence of cracks.

[0014] Optionally, the S17, integral pouring of concrete, includes pouring of standard-layer core tube beams and slabs, pouring of core tube shear walls, and pouring of horizontal structures within the tube.

[0015] By adopting the above technical solution, multiple structural parts can be cast at one time, which improves construction efficiency and speed and reduces the construction period. At the same time, the overall casting also helps to ensure the integrity and continuity of the structure, thereby enhancing the stability and seismic performance of the structure.

[0016] Optionally, the S1 also includes concrete strength monitoring.

[0017] By adopting the above technical solution, real-time monitoring of concrete strength ensures that the next step of construction will not be carried out before the structure meets the design requirements, thereby ensuring the safety and reliability of the structure.

[0018] Optionally, the S4 includes: S41, stair support frame erection; S42, stair formwork laying; S43, stair reinforcement and steel bar binding; S44, pouring concrete for stairs.

[0019] By adopting the above technical solutions, orderly construction steps and strict control of details, construction efficiency is improved, construction quality is ensured, and convenient conditions are provided for subsequent construction.

[0020] Optionally, the S41 and stair support frames may be uniformly dismantled after all stair sections on all floors in the core tube are completed.

[0021] By adopting the above technical solution, the unified dismantling of the support frame reduces the frequent construction and dismantling work, thereby reducing the labor intensity and time cost during the construction process.

[0022] Optionally, in S41-S43, the elevator in S3 is used to transport the support frame, formwork and steel bars.

[0023] By adopting the above technical solutions, the efficiency of material transportation is greatly improved, the dependence on traditional lifting machinery is reduced, and the transportation time and cost are reduced.

[0024] Optionally, according to S1-S5, a BIM model is established to perform three-dimensional visual management during the construction process.

[0025] By adopting the above technical solutions, the application of BIM has promoted the integration and sharing of project information, strengthened team collaboration, shortened decision-making time, reduced construction costs, and improved the management level and economic benefits of the entire project.

[0026] In summary, this application includes at least one of the following beneficial technical effects: 1. The five steps S1, S2, S3, S4, and S5 are set up. This construction method is highly flexible and widely applicable. It allows staircase construction to be carried out after the core tube structure reaches the designed strength, thereby effectively avoiding interference and damage to the core tube structure during construction. The phased construction ensures construction safety and quality control. At the same time, the use of construction hoists improves construction efficiency. To a certain extent, this application achieves the effect of improving construction efficiency while meeting quality and technical requirements and reducing the difficulty of core tube construction. 2. Set S1 to S11, S12, S13, S14, S15, S16, and S17, a total of seven steps. First, erect the bents, tie the rebar, install the formwork, lay the beams and slabs, and embedded parts, and then pour the concrete as a whole. This method not only improves construction efficiency, but also facilitates subsequent construction by considering the embedding of curtain walls and mechanical and electrical systems during the floor slab construction phase, reducing the need for later modifications. 3. S4 is set up into four steps: S41, S42, S43, and S44. The orderly construction steps and strict control of details improve construction efficiency, ensure construction quality, and also provide convenient conditions for subsequent construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 This is a construction flow chart of a method for post-installation construction of stairs within a super-high-rise core tube in an embodiment of the present application.

[0028] Figure 2 This is a detailed flow chart of a method for post-installation construction of stairs within a super-high-rise core tube in an embodiment of the present application.

[0029] Figure 3 This is a schematic diagram of the construction process of S1.1 in a method for post-installation construction of stairs in a super-high-rise core tube according to an embodiment of the present application.

[0030] Figure 4 This is a schematic diagram of the construction process of S1.2 in a method for post-installation construction of stairs in a super-high-rise core tube according to an embodiment of the present application.

[0031] Figure 5 This is a schematic diagram of the construction process of S1.3 in a method for post-installation construction of stairs in a super-high-rise core tube according to an embodiment of the present application.

[0032] Figure 6 This is a schematic diagram of the construction process of S1.4-S1.6 in a method for post-installation construction of stairs in a super-high-rise core tube in an embodiment of the present application.

[0033] Figure 7This is a schematic diagram of the construction process of S1.7 in a method for post-installation construction of stairs in a super-high-rise core tube according to an embodiment of the present application. DETAILED DESCRIPTION

[0034] The following is combined with Figure 1-7 This application is described in further detail.

[0035] The embodiment of the present application discloses a method for constructing a post-installed staircase in a super-high-rise core tube.

[0036] It should be noted that, in the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0037] Reference Figure 1 A method for post-construction of stairs in a super-high-rise core tube includes five steps, namely S1, S2, S3, S4 and S5. When constructing stairs in a super-high-rise core tube, the core tube is constructed first, and the construction of the stairs is suspended. Then, when the concrete strength of the core tube reaches the design value, the core tube frame is removed and the construction elevator is installed, and then the stairs are constructed. After the stairs are constructed on each floor, the above steps are repeated until the stairs reach the roof elevation, and the construction of the stairs in the super-high-rise core tube is completed. This application has achieved, to a certain extent, the effect of improving construction efficiency and reducing the difficulty of core tube construction while meeting quality and technical requirements.

[0038] Specifically, refer to Figure 2-7 A method for constructing a rear-mounted staircase in a super-high-rise core tube comprises the following steps: S1. Construction of the core tube structure, and suspension of construction of the staircase inside the tube.

[0039] About S1, including: S11. Erect the core tube frame; S12, core tube shear wall reinforcement binding; S13, core tube shear wall formwork installation; S14, laying of core tube beam and slab formwork; S15, core tube beam and slab reinforcement binding; S16. Install curtain wall and electromechanical embedded parts on the core tube floor; S17. Pour concrete in one piece.

[0040] Steps S11 to S17 demonstrate a high degree of organization and systematicity. The advantage of this method lies in its phased and orderly construction process, which ensures the stability and safety of the core tube structure. By first setting up the racks, tying the steel bars, installing the formwork, laying the beams and slabs and embedded parts, and then pouring the concrete as a whole, this method not only improves construction efficiency, but also facilitates subsequent construction by considering the pre-embedding of curtain walls and electromechanical systems during the floor slab construction phase, reducing the need for later modifications. In addition, this method also helps to optimize resource allocation, reduce material waste, and shorten the construction period of the entire project through advance planning and synchronous construction, thereby improving construction quality and the overall economic benefits of the project.

[0041] Furthermore, the steel bar tying in S12 and S15 is a mechanical connection.

[0042] The construction method of using mechanical connection for rebar tying, as in steps S12 and S15, offers significant advantages. This technique can improve the efficiency and speed of rebar connection, reduce the time and labor intensity of manual tying, and ensure the consistency and reliability of the connection. Mechanically connected rebar has higher connection strength and better seismic performance, which helps to improve the safety and durability of the overall structure. In addition, mechanical connection allows for more flexible rebar arrangement and adjustment, adapting to the design requirements of complex structures, thereby optimizing the construction process, improving construction quality, and accelerating the construction schedule, ultimately achieving a dual improvement in cost-effectiveness and project quality.

[0043] Furthermore, S17 is prestressed concrete construction.

[0044] S17 uses prestressed concrete construction, a method that significantly improves the bearing capacity and rigidity of concrete structures while reducing or avoiding cracks. Prestressing technology applies prestressing force before the concrete hardens, optimizing the stress state of the structure under load, thereby extending the service life of the structure and reducing maintenance costs. In addition, prestressed concrete construction allows for the design of thinner components, reducing the deadweight of the structure, saving space and materials for high-rise buildings, and improving construction efficiency. The application of prestressing also helps achieve larger spans and more elegant architectural forms, providing greater flexibility in architectural design.

[0045] At the same time, S17, the overall concrete pouring, including the pouring of standard layer core tube beams and slabs, the pouring of core tube shear walls and the pouring of horizontal structures inside the tube.

[0046] The monolithic casting construction method of prestressed concrete, which includes the casting of standard-layer core tube beams and slabs, core tube shear walls, and horizontal structures within the tube, offers a range of significant advantages. This method improves construction efficiency and speed by completing multiple structural parts in one go, reducing the construction period. Monolithic casting also helps ensure the integrity and continuity of the structure, thereby enhancing its stability and seismic resistance. In addition, this method can reduce construction joints, lower the risk of leakage, and improve the sealing and durability of the structure. The application of prestressed concrete technology further enhances the bearing capacity of concrete structures, allowing for thinner components to be designed, reducing the deadweight of the structure, saving space and materials for high-rise buildings, and improving construction quality and the overall economic benefits of the project.

[0047] Furthermore, S1 also includes concrete strength monitoring.

[0048] Adding concrete strength monitoring to step S1 brings the following advantages to the post-construction method of stairs in the core tube of the entire super-high-rise building: First, real-time monitoring of concrete strength ensures that the next step of construction will not be carried out before the structure meets the design requirements, thereby ensuring the safety and reliability of the structure; second, through data-driven decision-making, the construction schedule can be arranged more accurately, avoiding the risks and cost waste caused by dismantling the racks too early or too late; in addition, accurate monitoring of concrete strength helps to optimize material use, reduce over-design, and thus reduce project costs; finally, this monitoring also provides valuable data support for the construction team, which helps to continuously improve construction techniques and methods, and enhance the quality and efficiency of the entire construction process.

[0049] S2. After the core tube concrete strength reaches the design value, the core tube frames are removed.

[0050] S3. Install construction hoist.

[0051] S4. Carry out stair construction.

[0052] Specifically, S4 includes: S41, stair support frame erection; S42, stair formwork laying; S43, stair reinforcement and steel bar binding; S44, pouring concrete for stairs.

[0053] The staircase construction method described in S4, through a detailed, phased construction process, demonstrates the following advantages: First, the staircase support frame erection in S41 provides a stable construction foundation for the staircase structure, ensuring safety during construction. Second, the staircase formwork laying in S42 provides precise shapes and dimensions for concrete pouring, helping to improve the geometric accuracy of the staircase. Third, the staircase reinforcement and steel binding in S43 ensure the staircase's load-bearing capacity and durability. Through the rational arrangement and binding of steel bars, the staircase's crack resistance and earthquake resistance are enhanced. Finally, the staircase concrete pouring in S44 is a critical step in achieving the structural integrity of the staircase. By carefully controlling the quality of the concrete and the pouring process, the uniformity and density of the staircase can be ensured, thereby improving the service life and performance of the entire staircase. Overall, this method improves construction efficiency and ensures construction quality through orderly construction steps and strict control of details, while also facilitating subsequent construction.

[0054] Furthermore, S41 and the stair support frame can be uniformly dismantled after all the stair sections on each floor in the core tube are completed.

[0055] The construction method of setting up the stair support frame in S41 and uniformly dismantling it after all the stair sections on all floors in the core tube are completed has the following advantages: first, the uniform dismantling of the support frame reduces the frequent erection and dismantling work, thereby reducing the labor intensity and time cost during the construction process; second, this method allows stair construction to be carried out simultaneously on different floors, improving construction efficiency and flexibility in schedule control; in addition, the centralized dismantling of the support frame can also reduce interference with the construction site, reduce construction noise and dust, and improve the construction site environment; finally, by uniformly dismantling all the stair sections after completion, the stability of the stair structure during construction can be ensured, and the risk of structural damage caused by improper dismantling of the support frame can be reduced, thereby improving the safety of construction and the reliability of the stair structure.

[0056] At the same time, in S41-S43, the elevator in S3 is used to transport the support frame, formwork and steel bars.

[0057] In steps S41 to S43, the support frame, formwork, and steel bars are vertically transported using the construction elevator installed in step S3. This method has the following advantages: first, it greatly improves the efficiency of material transportation, reduces dependence on traditional lifting machinery, and reduces transportation time and costs; second, the use of the elevator reduces the risk of vertical movement of construction workers in high-rise buildings, improving operational safety; in addition, the centralized vertical transportation system helps reduce chaos in the construction area and makes on-site management more orderly; at the same time, this method can also reduce interference with other construction activities within the building, ensuring the continuity and stability of the construction progress. In general, this method improves construction efficiency and safety by optimizing the logistics process, which helps to achieve more efficient and economical construction operations.

[0058] S5. Repeat the above steps S1-S4 until the roof elevation is reached.

[0059] Furthermore, according to S1-S5, a BIM model is established to carry out three-dimensional visual management during the construction process.

[0060] By establishing a BIM model and applying it to the construction process of S1 to S5, the following advantages are achieved: First, the BIM model provides a three-dimensional visualization platform, allowing the project team to have an intuitive understanding of the entire project before construction, thereby better planning the construction process and resource allocation; second, BIM technology can achieve real-time monitoring and management during the construction process, promptly discover and solve problems during construction, and improve construction quality and safety; in addition, the BIM model also supports collision detection and construction simulation, which helps to optimize design plans, reduce conflicts and rework during construction, and improve construction efficiency; finally, the application of BIM promotes the integration and sharing of project information, strengthens team collaboration, shortens decision-making time, reduces construction costs, and improves the management level and economic benefits of the entire project.

[0061] The implementation principle of the method for post-installation of stairs in the core tube of a super-high-rise building in accordance with an embodiment of the present application is as follows: a total of five steps, namely, S1, S2, S3, S4, and S5, are set up. The core tube structure is constructed first, and the staircase part in the core tube is not constructed first. After the concrete strength at the core tube reaches the design value, the core tube frame is removed and a construction elevator is installed. The stairs of one floor are constructed, and the above construction steps are repeated until the stairs are constructed to the roof elevation. This construction method is highly flexible and widely applicable. It allows the staircase construction to be carried out after the core tube structure reaches the design strength, thereby effectively avoiding interference and damage to the core tube structure during construction. The phased construction ensures construction safety and quality control. At the same time, the use of the construction elevator improves construction efficiency. The repeated construction step of S5 can help to achieve standardization and modularization in the construction process, reduce construction costs, shorten construction period, and improve the predictability and controllability of the overall construction. To a certain extent, this application has achieved the effect of improving construction efficiency and reducing the difficulty of core tube construction while meeting quality and technical requirements.

[0062] The above are all preferred embodiments of the present application, and are not intended to limit the scope of protection of the present application. Therefore, any equivalent changes made based on the structure, shape, and principle of the present application should be included in the scope of protection of the present application.

Claims

1. A method for post-installation construction of stairs in a super high-rise core tube, characterized in that: The following steps are involved: S1. Construction of the core tube structure, and suspension of construction of the staircase inside the tube; S2. After the core tube concrete strength reaches the design value, the core tube racks are removed; S3. Install construction hoist; S4, carry out staircase construction; S5. Repeat the above steps S1-S4 until the roof elevation is reached.

2. The method for post-installation construction of stairs in a super-high-rise core tube according to claim 1 is characterized in that: The S1 includes: S11. Erect the core tube rack; S12, reinforcement binding of core tube shear wall; S13, core tube shear wall formwork installation; S14, laying of core tube beam and slab formwork; S15, reinforcement binding of core tube beams and slabs; S16. Install curtain wall and electromechanical embedded parts on the core tube floor; S17, pour concrete as a whole.

3. The method for post-installation construction of stairs in a super-high-rise core tube according to claim 2 is characterized in that: The steel bar binding in S12 and S15 is a mechanical connection.

4. The method for post-installation construction of stairs in a super-high-rise core tube according to claim 2 is characterized in that: The S17 is prestressed concrete construction.

5. The method for post-installation construction of stairs in a super high-rise core tube according to claim 2 is characterized in that: The S17, integral pouring of concrete, includes pouring of standard-layer core tube beams and slabs, pouring of core tube shear walls, and pouring of horizontal structures within the tube.

6. The method for post-installation construction of stairs in a super high-rise core tube according to claim 2 is characterized in that: The S1 also includes concrete strength monitoring.

7. The method for post-installation construction of stairs in a super high-rise core tube according to claim 1 is characterized in that: The S4 includes: S41, erection of stair support frame; S42, stair formwork laying; S43, stair reinforcement and steel bar binding; S44, pouring of concrete for stairs.

8. The method for post-installation construction of stairs in a super high-rise core tube according to claim 7 is characterized in that: The S41 and stair support frames can be uniformly dismantled after all the stair sections on all floors in the core tube are completed.

9. The method for post-installation construction of stairs in a super high-rise core tube according to claim 7 is characterized in that: In S41-S43, the elevator in S3 is used to transport the support frame, formwork and steel bars.

10. The method for post-installation construction of stairs in a super high-rise core tube according to claim 1, characterized in that: According to S1-S5, a BIM model is established to perform three-dimensional visual management during the construction process.

Citation Information

Patent Citations

  • Evacuation escape channel of steel platform mould frame system and construction method for evacuation escape channel

    CN105401737A

  • BIM (Building Information Modeling)-based super-high-rise super-thick mass concrete one-time pouring construction method in hot weather

    CN111368361A

  • Frame-core tube construction method

    CN113982115A

  • Super high-rise core tube and steel structure leveling construction method and temporary supporting frame

    CN115726462A

  • Construction method for RC structured high rise building

    KR100685147B1