Construction method of large-span prestressed concrete double-T plate mounting structure
By using technical means such as frame beams, daughter walls, embedded steel bars and inter-slab filling in the large span prestressed concrete double T-slab installation structure, the problem of unsolid connection of double T-slabs under large span is solved, and the further development is achieved Stable installation and splicing effect.
Patent Information
- Application Number
- CN202411453790.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-17
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-10-17
AI Technical Summary
The existing dual T-board installation technology is difficult to effectively connect the dual T-board under a large span, and the assembly connection is not firm enough to meet the construction needs of the large span.
Adopt a large-span prestressed concrete double T-slab installation structure, including frame beams, daughter's walls, double T-slabs, top embedded plates, bottom embedded parts components, embedded steel bars and inter-slab connecting plates, through L-shaped notch design, The welding connection between the plate top embedded plate and the plate bottom embedded member assembly is combined with the inter-plate filling layer and embedded steel bars to ensure that the top and bottom of the double T-plate are fixed and long-term spliced.
Enhance the connection strength and stability of the double T plates, ensure the effective installation and splicing of the large-span double T plates, and achieve a more solidity through the fixation of the embedded parts and the embedded steel bars at the bottom of the plate and the sealing of the filling layer between the plates. connection.
Smart Images

Figure CN119021482A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of double T-plate installation, and in particular relates to a construction method of a large-span prestressed concrete double T-plate installation structure. Background Art
[0002] The double T-slab is different from the ordinary straight floor slab. It is more and more commonly used as a floor slab in construction due to its superior performance. As for the installation of the double T-slab, the existing construction only sets up the connection between the double T-slab and the embedded parts of the beam body. This connection can only meet the installation requirements of small spans. When the span of the double T-slab becomes larger, this connection will cause insufficient connection strength. How to ensure the effective connection of the double T-slab under large spans, and how to assemble and connect the large-span double T-slabs, etc., all require targeted design. Summary of the invention
[0003] The invention provides a construction method for a large-span prestressed concrete double T-plate installation structure, which is used to solve technical problems such as the reinforced connection between the top of the double T-plate and the parapet, the reinforced connection between the bottom and the beam body, and the long-direction splicing connection of the double T-plate.
[0004] To achieve the above object, the present invention adopts the following technical solution: The large-span prestressed concrete double T-plate installation structure comprises a frame beam, a parapet wall arranged on one side of the top of the frame beam, a double T-plate connected to the inner side of the parapet wall and connected to the top of the frame beam, a plate top embedded plate and a plate bottom embedded component assembly respectively arranged on the top and bottom surfaces of the double T-plate end, a beam top embedded plate arranged at the top of the frame beam corresponding to the plate bottom embedded component assembly at the bottom, and embedded steel bars arranged inside the parapet wall and corresponding to the connecting plate top embedded plate; Among them, the inner vertical part of the parapet and the top surface of the frame beam are set with an L-shaped gap, and a double T-plate is installed at the L-shaped gap; For the construction method of the large-span prestressed concrete double T-plate installation structure, the specific steps are as follows: Step 1: prefabricate a double T-plate of prestressed concrete, and mark the positions of the bottom embedded components and the top embedded plates to be installed on the double T-plate; Step 2: pre-embed a plate base plate with a plate through-tube at the marked position at the bottom of the double T-plate, and then weld a plate connecting plate on the plate base plate, wherein the size of the plate connecting plate is smaller than the plate base plate; pre-install a plate top embedded plate on the top of the double T-plate, and the plate top embedded plate is fixedly connected to the steel bars in the plate; Step 3: The double T-plates with large spans are spliced and connected in the length direction. The adjacent ends of the double T-plates are provided with plate top embedded plates and the adjacent plate top embedded plates are connected by plate inter-plate connecting plates; the double T-plates arranged at the ends are fixedly installed on the frame beam and the parapet through the plate bottom embedded parts assembly and the top embedded plate respectively; Step 4: When installing the double T-plate at the end, determine the position of the embedded steel bars according to the height of the double T-plate; determine the position of the embedded plate on the top of the beam according to the position of the rib plate in the double T-plate; Step 5: The embedded steel bars are shaped bars, the opening of which is set inside the parapet, and the closed arc-shaped bent end is welded to the top embedded plate of the double T plate; the beam top embedded plate is welded to the bottom embedded component of the double T plate; Step 6. A gap is set between the end of the double T-board and the inner side of the parapet. The gap is filled with an inter-board filling layer between the parapet and the top plate flange of the double T-board, thereby completing the installation of the large-span prestressed concrete double T-board.
[0005] Furthermore, the double T-plate includes a top plate and two rib plates arranged below the top plate, and the two rib plates form a T-shape with the top plate respectively; a plate bottom embedded part assembly is arranged below each rib plate, wherein a plate through tube penetrates into the rib plate and its height is not less than half of the height of the rib plate; a plate top embedded plate is arranged at the center line position of the top plate or at the position on the top plate corresponding to the center line of the two rib plates.
[0006] Furthermore, the inner side of the parapet is not less than 250 mm away from the inner side of the frame beam, and the plate end filling layer between the parapet and the top plate is filled with fine stone concrete and the filling height is from the top surface height of the top plate to the top surface height of the frame beam.
[0007] Furthermore, the plate-base plate and the plate-through-tube are fixedly connected by welding through the plate-hole-tube weld, and the plate-hole-tube weld is arranged circumferentially along the plate-through-tube, and the weld thickness is not less than 2 mm; the plate-base plate and the plate-connecting plate are fixedly connected by the inter-plate weld, and the weld is arranged at the connecting corner between the plate-connecting plate and the plate-base plate.
[0008] Furthermore, the beam top embedded plate is a steel plate, which is pre-set on the top of the frame beam and the top surface elevation of the beam top embedded plate is flush with the top surface elevation of the frame beam; The beam top embedded plate is fully distributed over the width of the L-shaped notch, and the beam top embedded plate is respectively welded to the plate connecting plate on both sides and the outer side of the length.
[0009] Furthermore, the openings of the embedded steel bars are arranged in upper and lower vertical lines and their length is greater than the length of the plate connecting the plates. The embedded steel bars are welded to the embedded plates on the top of the plates and both sides of the embedded steel bars are fully welded.
[0010] Furthermore, the connecting plate between the plates is a thick steel plate, the connecting plate between the plates is in an inverted V shape and horizontal flanges are arranged on both sides of the opening, and the horizontal flanges are respectively connected to the embedded plates on the top of the plates.
[0011] Furthermore, inter-plate gaps are provided between adjacent double T-plates, and inter-plate filling layers are provided in the inter-plate gaps; the inter-plate filling layers are provided in an inverted trapezoidal shape and are filled by fine stone concrete grouting.
[0012] Furthermore, after the installation is completed, the exposed surface of the embedded steel bars and the exposed surface of the corresponding top embedded plate are derusted on both sides, and then coated with asphalt not less than 5mm thick. The roof is provided with a 50mm thick C20 concrete cast-in-place layer, equipped with 8@200 bidirectional steel bars, and the steel bars are anchored in the parapet or masonry wall ring beam.
[0013] The beneficial effects of the present invention are embodied in: 1) The present invention further utilizes the structural characteristics of the double T-plate by setting the bottom plate embedded component, and connects the plate through the tube to the inside of the rib plate instead of the surface, thereby strengthening the connection strength of the bottom plate and the plate; 2) The present invention facilitates fixing the top of the double T-plate by setting the embedded steel bars, thereby fixing the top and bottom of the double T-plate at the same time, thereby strengthening the fixation of the double-body plate; in addition, a plate end filling layer is provided to further seal and reinforce the connection of the end; 3) The present invention provides inter-plate connecting plates in combination with adjacent end plate top embedded plates, thereby ensuring effective connection of double T-plates at joints, and sealing and strengthening the connection at adjacent locations through inter-plate filling layers.
[0014] Other features and advantages of the present invention will be set forth in the following description, and in part will become apparent from the description, or may be understood by practicing the present invention; the main purpose and other advantages of the present invention may be realized and obtained through the solutions particularly pointed out in the description. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 This is a schematic diagram of the end installation structure of a large-span prestressed concrete double T-plate; Figure 2 It is a schematic diagram of the local structure of the end installation of a large-span prestressed concrete double T-slab; Figure 3 It is a schematic diagram of the double T-plate structure; Figure 4 It is a schematic diagram of the connection between the embedded plate on the top of the board and the embedded parts on the bottom of the board; Figure 5 This is a schematic diagram of the connection between the beam top embedded plate and the embedded steel bars; Figure 6 It is the front view of the embedded parts assembly at the bottom of the plate; Figure 7 It is the side view of the embedded parts at the bottom of the plate; Figure 8 This is a schematic diagram of the plate-through-tube connection structure; Fig. 9 This is a schematic side view of the installation of the inter-board connecting plate; Fig.10 This is the top view of the installation of the connecting plate between the boards; Fig.11 It is a schematic diagram of the board end filling layer setting.
[0016] Figure numbers: 1-double T-plate, 101-top plate, 102-rib plate, 2-frame beam, 3-parapet, 4-plate bottom embedded component, 41-plate base plate, 42-plate through-tube, 43-weld between plates, 44-plate connecting plate, 45-plate hole tube weld, 5-plate top embedded plate, 6-beam top embedded plate, 7-embedded steel bars, 8-plate end gap, 9-plate connecting plate, 10-plate gap, 11-filling layer between plates, 12-plate end filling layer. DETAILED DESCRIPTION
[0017] Taking an industrial park project as an example, the total height of a single building is 19.65m; its structural form is a concrete frame structure, the seismic fortification intensity is 7 degrees, the seismic level is level 2, and the design service life is 50 years. The double T-plate construction area is the top plate in the middle area of the top floor, with a total plane area of 621㎡. To ensure the effective installation of the double T-plate, such as Figures 1 to 11 As shown, through the construction method of the large-span prestressed concrete double T-plate installation structure, the large-span prestressed concrete double T-plate installation structure includes a frame beam 2, a parapet 3 arranged on one side of the top of the frame beam 2, a double T-plate 1 connected to the inner side of the parapet 3 and connected to the top of the frame beam 2, a plate top embedded plate 5 and a plate bottom embedded component assembly 4 respectively arranged on the top and bottom surfaces of the end of the double T-plate 1, a beam top embedded plate 6 located at the top of the frame beam 2 corresponding to the plate bottom embedded component assembly 4 at the bottom, and an embedded steel bar 7 arranged inside the parapet 3 and corresponding to the connecting plate top embedded plate 5; In this embodiment, the double T-plate 1 includes a top plate 101 and two ribs 102 arranged below the top plate 101, and the two ribs 102 form a T shape with the top plate 101. The double T-plate 1 component length is 19.58m, the double rib height is 540~750mm, and 8 hanging points are set in the plate. There are 8 pre-tensioned steel wire ropes at the end, 2 of which are 15.2mm and 6 of which are 12.7mm.
[0018] In this embodiment, a plate bottom embedded part assembly 4 is provided under each rib plate 102, wherein the plate through tube 42 penetrates into the rib plate 102 and its height is not less than half of the height of the rib plate 102; a plate top embedded plate 5 is provided at the center line position of the top plate 101 or at the position on the top plate 101 corresponding to the center line of two rib plates 102.
[0019] Among them, the inner vertical part of the parapet 3 and the top surface of the frame beam 2 are set in an L-shaped gap, and the double T-plate 1 is installed correspondingly at the L-shaped gap; in this embodiment, the inner side of the parapet 3 is not less than 250mm away from the inner side of the frame beam 2, and the plate end filling layer 12 between the parapet 3 and the top plate 101 is filled with C20 fine stone concrete and the filling height is from the top surface height of the top plate 101 to the top surface height of the frame beam 2.
[0020] Combination Figures 1 to 11 , further explain the construction method for the large-span prestressed concrete double T-plate installation structure, the specific steps are as follows: Step 1: prefabricate a double T-plate 1 of prestressed concrete, and mark the positions of the bottom embedded component 4 and the top embedded plate 5 to be installed on the double T-plate 1.
[0021] Step 2: pre-embed a plate base plate 41 with a plate through tube 42 at the marked position at the bottom of the double T-plate 1, and then weld a plate connecting plate 44 on the plate base plate 41, wherein the size of the plate connecting plate 44 is smaller than the plate base plate 41; pre-install a plate top embedded plate 5 on the top of the double T-plate 1, and the plate top embedded plate 5 is fixedly connected to the steel bars in the plate. The plate base plate 41 and the plate connecting plate 44 are both rectangular steel plates.
[0022] The plate-base plate 41 and the plate-through-tube 42 are fixedly connected by welding through a plate-hole-tube weld 45, and the plate-hole-tube weld 45 is circumferentially arranged along the plate-through-tube 42, and the weld thickness is not less than 2 mm; the plate-base plate 41 and the plate-connecting plate 44 are fixedly connected by an inter-plate weld 43, and the weld is arranged at the connecting inner corner between the plate-connecting plate 44 and the plate-base plate 41.
[0023] Step 3: The large-span double T-boards 1 are spliced and connected in the length direction. The ends of adjacent double T-boards 1 are provided with plate top embedded plates 5 and the adjacent plate top embedded plates 5 are connected by inter-plate connecting plates 9; the double T-boards 1 arranged at the ends are fixedly installed on the frame beam 2 and the parapet 3 respectively by the plate bottom embedded parts assembly 4 and the top embedded plate.
[0024] The inter-plate connecting plate 9 is an 8mm thick steel plate with a width of 90mm. The inter-plate connecting plate 9 is inverted V-shaped and has horizontal flanges on both sides of the opening, which are respectively connected to the top embedded plate 5. An inter-plate gap 10 is provided between adjacent double T plates 1, and an inter-plate filling layer 11 is provided in the inter-plate gap 10; the inter-plate filling layer 11 is set in an inverted trapezoidal shape and is filled with C20 fine stone concrete grouting.
[0025] Step 4: When installing the double T-plate 1 at the end, determine the position of the embedded steel bars 7 according to the height of the double T-plate 1 ; determine the position of the embedded plate on the top of the beam according to the position of the rib 102 in the double T-plate 1 .
[0026] The beam top embedded plate 6 is a steel plate, which is pre-set on the top of the frame beam 2 and the top surface elevation of the beam top embedded plate 6 is flush with the top surface elevation of the frame beam 2; the beam top embedded plate 6 is fully distributed over the width of the L-shaped notch, and the beam top embedded plate 6 is welded to the plate connecting plate 44 on both sides and the outside of the length direction.
[0027] Step 5: The embedded steel bars 7 are shaped bars, the opening of which is arranged inside the parapet 3 , and the closed arc-shaped bent ends are welded to the top embedded plate 5 on the top of the double T-plate 1 ; the beam top embedded plate is welded to the bottom embedded component 4 on the bottom of the double T-plate 1 .
[0028] The opening of the embedded steel bar 7 is arranged in an upper and lower vertical line and its length is greater than the length of the plate connecting plate 44. The embedded steel bar 7 is welded to the embedded plate 5 on the top of the plate and both sides of the embedded steel bar 7 are fully welded.
[0029] Step six, a plate end gap 8 is set between the plate end of the double T plate 1 and the inner side of the parapet 3; the plate end gap 8 is filled with an inter-plate filling layer 11 between the parapet 3 and the flange of the top plate 101 of the double T plate 1, thereby completing the installation of the large-span prestressed concrete double T plate 1.
[0030] After the installation is completed, the exposed surface of the embedded steel bar 7 and the exposed surface of the corresponding top embedded plate are derusted on both sides, and then coated with asphalt not less than 5mm thick. The roof is provided with a 50mm thick C20 concrete pouring layer, with 8@200 bidirectional steel bars inside, and the steel bars are anchored in the parapet 3 or the masonry wall ring beam.
[0031] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that a technician familiar with the technical field can think of within the technical scope disclosed in the present invention should be covered within the protection scope of the present invention.
Claims
1. A construction method for a large-span prestressed concrete double T-plate installation structure, characterized in that: The large-span prestressed concrete double T-plate installation structure comprises a frame beam (2), a parapet wall (3) arranged on one side of the top of the frame beam (2), a double T-plate (1) connected to the inner side of the parapet wall (3) and connected to the top of the frame beam (2), a plate top embedded plate (5) and a plate bottom embedded component assembly (4) respectively arranged on the top and bottom surfaces of the end of the double T-plate (1), a beam top embedded plate (6) located at the top of the frame beam (2) and arranged corresponding to the plate bottom embedded component assembly (4) at the bottom, and embedded steel bars (7) arranged inside the parapet wall (3) and corresponding to the connecting plate top embedded plate (5); The inner vertical portion of the parapet wall (3) and the top surface of the frame beam (2) are provided with an L-shaped notch, and a double T-plate (1) is installed corresponding to the L-shaped notch; For the construction method of the large-span prestressed concrete double T-plate installation structure, the specific steps are as follows: Step 1: prefabricate a double T-plate (1) of prestressed concrete, and mark the positions of the bottom embedded component assembly (4) and the top embedded plate (5) to be installed on the double T-plate (1); Step 2: pre-embed a plate base plate (41) with a plate through tube (42) at a marked position at the bottom of the double T-plate (1), and then weld a plate connecting plate (44) on the plate base plate (41), wherein the size of the plate connecting plate (44) is smaller than that of the plate base plate (41); pre-install a plate top pre-embedded plate (5) on the top of the double T-plate (1), and the plate top pre-embedded plate (5) is fixedly connected to the steel bars in the plate; Step 3: The double T-plates (1) with a large span are spliced and connected in the length direction. The ends of the adjacent double T-plates (1) are provided with plate top embedded plates (5), and the adjacent plate top embedded plates (5) are connected by an inter-plate connecting plate (9); the double T-plates (1) arranged at the ends are fixedly installed on the frame beam (2) and the parapet (3) by means of the plate bottom embedded component assembly (4) and the top embedded plate respectively; Step 4: When installing the double T-plate (1) at the end, determine the position of the embedded steel bars (7) according to the height of the double T-plate (1); determine the position of the embedded plate on the top of the beam according to the position of the rib plate (102) in the double T-plate (1); Step 5: The embedded steel bars (7) are shaped bars, the opening of which is arranged inside the parapet (3), and the closed arc-shaped bent end is welded to the top embedded plate (5) at the top of the double T plate (1); the beam top embedded plate is welded to the bottom embedded component assembly (4) at the bottom of the double T plate (1); Step 6: A plate end gap (8) is provided between the plate end of the double T plate (1) and the inner side of the parapet (3); the plate end gap (8) is filled with an inter-plate filling layer (11) between the parapet (3) and the flange of the top plate (101) of the double T plate (1), thereby completing the installation of the large-span prestressed concrete double T plate (1).
2. The construction method of a large-span prestressed concrete double T-plate installation structure according to claim 1, characterized in that: The double T-plate (1) comprises a top plate (101) and two rib plates (102) arranged below the top plate (101), wherein the two rib plates (102) respectively form a T-shape with the top plate (101); a plate bottom embedded component assembly (4) is arranged below each rib plate (102), wherein a plate through tube (42) penetrates into the rib plate (102) and its height is not less than half the height of the rib plate (102); and a plate top embedded plate (5) is arranged at a midline position of the top plate (101) or at a position on the top plate (101) corresponding to the midlines of the two rib plates (102).
3. The construction method of a large-span prestressed concrete double T-plate installation structure according to claim 2, characterized in that: The inner side of the parapet wall (3) is not less than 250 mm from the inner side of the frame beam (2); the plate end filling layer (12) between the parapet wall (3) and the top plate (101) is filled with fine stone concrete and the filling height is from the top surface height of the top plate (101) to the top surface height of the frame beam (2).
4. The construction method of a large-span prestressed concrete double T-plate installation structure according to claim 1, characterized in that: The plate-base plate (41) and the plate-through tube (42) are fixedly connected by welding via a plate-hole-tube weld (45), and the plate-hole-tube weld (45) is circumferentially arranged along the plate-through tube (42), and the weld thickness is not less than 2 mm; the plate-base plate (41) and the plate-connecting plate (44) are fixedly connected via an inter-plate weld (43), and the weld is arranged at a connecting inner corner between the plate-connecting plate (44) and the plate-base plate (41).
5. The construction method of a large-span prestressed concrete double T-plate installation structure according to claim 1, characterized in that: The beam top embedded plate (6) is a steel plate, and the beam top embedded plate (6) is pre-arranged on the top of the frame beam (2), and the top surface elevation of the beam top embedded plate (6) is arranged flush with the top surface elevation of the frame beam (2); The beam top embedded plate (6) is fully distributed over the width of the L-shaped notch, and the beam top embedded plate (6) is welded to the plate connecting plate (44) on both sides and the outer side in the length direction.
6. The construction method of a large-span prestressed concrete double T-plate installation structure according to claim 1, characterized in that: The opening of the embedded steel bar (7) is arranged in an upper and lower vertical line and has a length greater than the length of the plate connecting plate (44). The embedded steel bar (7) is welded to the embedded plate (5) at the top of the plate and both sides of the embedded steel bar (7) are fully welded.
7. The construction method of a large-span prestressed concrete double T-plate installation structure according to claim 1, characterized in that: The inter-plate connecting plate (9) is a thick steel plate, is in an inverted V shape, and is provided with horizontal flanges on both sides of the opening, and the horizontal flanges are respectively connected to the plate top embedded plates (5).
8. The construction method of a large-span prestressed concrete double T-plate installation structure according to claim 7, characterized in that: An inter-plate gap (10) is provided between adjacent double T-plates (1), and an inter-plate filling layer (11) is provided in the inter-plate gap (10); the inter-plate filling layer (11) is provided in an inverted trapezoidal shape and is filled with fine stone concrete grouting.
9. The construction method of a large-span prestressed concrete double T-plate installation structure according to claim 1, characterized in that: After installation, the exposed surface of the embedded steel bar (7) and the exposed surface of the corresponding top embedded plate are derusted on both sides, and then coated with asphalt not less than 5 mm thick. The roof is provided with a 50 mm thick C20 concrete pouring layer, which is equipped with 8@200 bidirectional steel bars. The steel bars are anchored in the parapet (3) or the masonry wall ring beam.
Citation Information
Patent Citations
Connection structure and method of prestressed double T-plate floor slab and prefabricated beam
CN109707086A
Prefabricated concrete building structure
CN203961014U
Novel prefabricated concrete building structure
CN204098215U
Connection structure between double T board edge of a wing
CN207892100U
The long-span slab system
KR101541454B1