Prefabricated assembly unit connecting structure in shield tunnel

By using the connection structure between U-shaped steel insert plates and slots, insert bars and reserved blind holes in the internal prefabricated assembly unit of the shield tunnel, the error adjustment and operation and maintenance problems of bolt connection methods in the prior art are solved. , achieves rapid connection and durability improvement.

CN119021714APending Publication Date: 2024-11-26SHANGHAI MUNICIPAL ENG DESIGN INST (GRP) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411180515.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-27
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

The bolt connection method between prefabricated structural units inside existing shield tunnels has problems such as difficulty in error adjustment, frequent retightening, and cumbersome sealing inspection in construction and operation and maintenance.

Method used

The vertical and horizontal connection structure with U-shaped steel insert plates and slots, insert ribs and reserved through-hole blind holes is adopted, and the connectors are fixed with fast-condensing and fast hard materials to reduce positioning errors and improve connection stability.

Benefits of technology

It realizes a quick connection unit in the presence of positioning errors and errors, reduces the frequency of operation and maintenance inspections and maintenance, and improves the durability of the connector.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021714A_ABST
    Figure CN119021714A_ABST
Patent Text Reader

Abstract

The invention discloses a shield tunnel internal prefabricated assembly unit connecting structure which comprises a longitudinal connecting structure and a transverse connecting structure, the longitudinal connecting structure comprises a U-shaped steel inserting plate and a set of inserting grooves, and the inserting grooves are formed in the positions close to the adjacent edges of top plates of adjacent square piece units or the adjacent edges of top plates of adjacent edge block units; the two end parts of the U-shaped steel inserting plate are respectively inserted into the inserting grooves and are fixed; the transverse connecting structure comprises joint bars and brackets located on the side wall portions of the square piece units, the brackets are provided with reserved through holes, upturning structures are arranged at the positions, corresponding to the brackets, of the edge block units, the upturning structures are provided with reserved blind holes, and the joint bars are sequentially inserted into the reserved through holes and the reserved blind holes and then fixed. According to the method, a commonly-adopted bolt connection method is changed, when slab staggering exists between the segments and certain errors exist in positioning of the internal prefabricated structure units, connection can still be conducted quickly, the purpose of facilitating construction is achieved, and meanwhile inspection tour and maintenance of connecting pieces during operation and maintenance can be avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of construction of prefabricated assembly units inside a shield tunnel, and in particular relates to a connection structure of prefabricated assembly units inside a shield tunnel. Background Art

[0002] In order to meet the industrialized construction requirements put forward by national policies, the internal structure of shield tunnels is usually prefabricated and assembled. At present, the prefabricated structural units in shield tunnels are generally connected by bolts. After investigation, it was found that there are many problems in the construction and operation and maintenance of the bolt connection method, as follows: (1) Since there is more or less "misalignment" between the shield segments after assembly, and the internal prefabricated structural units inevitably have errors in positioning, the construction process needs to be constantly fine-tuned to meet the requirements of smooth bolt connection; (2) During construction, the bolts need to be tightened several times to ensure reliable connection between the prefabricated units; (3) The bolt holes need to be sealed, and during operation, it is necessary to check whether the seals fall off to ensure the durability of the bolts. Summary of the invention

[0003] In view of this, an object of the present invention is to provide a prefabricated assembly unit connection structure inside a shield tunnel to solve the deficiencies in the prior art.

[0004] In order to achieve the above object, the present invention is achieved through the following technical solutions:

[0005] Provided is a shield tunnel internal prefabricated assembly unit connection structure, the shield tunnel internal prefabricated assembly unit comprises a mouth unit located in the middle and side block units located on both sides, wherein, it comprises:

[0006] The longitudinal connection structure is suitable for the longitudinal connection between adjacent mouth-shaped unit or the longitudinal connection between adjacent side block units, and comprises a U-shaped steel insert plate and a group of slots, wherein the slots are respectively arranged near the adjacent edges of the top plates of the adjacent mouth-shaped unit or the adjacent edges of the top plates of the adjacent side block units, and the two ends of the U-shaped steel insert plate are respectively inserted into the slots and fixed;

[0007] The transverse connection structure is suitable for the transverse connection between adjacent mouth-shaped unit and side block unit, and includes an inserted bar and a corbel located at the side wall of the mouth-shaped unit, the corbel is provided with a reserved through hole, and an upward flip structure is provided at the position corresponding to the side block unit and the corbel, the upward flip structure is provided with a reserved blind hole, and the inserted bar is inserted into the reserved through hole and the reserved blind hole in sequence and then fixed.

[0008] For example, in the shield tunnel internal prefabricated assembly unit connection structure, after the front and rear two prefabricated assembly units are hoisted and positioned, quick-setting and quick-hardening material is poured into the slot, and the U-shaped steel insert is inserted into the slot before the material solidifies.

[0009] For example, in the prefabricated assembly unit connection structure inside the shield tunnel, the dowel bars are sequentially inserted into the reserved through holes and the reserved blind holes, and then quick-setting and quick-hardening materials are poured in to fill them densely.

[0010] For example, in the prefabricated assembly unit connection structure inside the shield tunnel, the width of the U-shaped steel plug plate is smaller than the width of the slot, the depth of the U-shaped steel plug plate is smaller than the depth of the slot, and the inner diameter of the reserved through hole and the inner diameter of the reserved blind hole are both larger than the outer diameter of the dowel.

[0011] For example, in the prefabricated assembly unit connection structure inside the shield tunnel, there is a certain gap between the corbel and the upward flip structure.

[0012] The beneficial effects of the technical solution of the present invention are:

[0013] The commonly used bolt connection method has been changed. When there is a "misalignment" between the segments and a certain error in the positioning of the internal prefabricated structural units, the connection can still be made quickly, thereby facilitating the construction and avoiding the inspection and maintenance of the connectors during operation and maintenance. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] To further illustrate the above-mentioned objectives, structural features and effects of the present invention, the present invention will be described in detail below with reference to the accompanying drawings.

[0015] Figure 1 This is a schematic diagram of the connection structure of the prefabricated assembly units inside the shield tunnel of a preferred embodiment of the present invention;

[0016] Figure 2 for Figure 1 Sectional view along II direction;

[0017] Figure 3 for Figure 1 Middle section view along II-II direction;

[0018] Figure 4 A longitudinal cross-sectional view of the longitudinal connection structure between the port character unit and the edge block unit in a preferred embodiment of the present invention;

[0019] Figure 5 Another longitudinal cross-sectional view of the longitudinal connection structure between the port letter unit and the edge block unit in a preferred embodiment of the present invention;

[0020] Figure 6 It is a plan view of the longitudinal connection structure between the mouth piece unit and the edge block unit in a preferred embodiment of the present invention;

[0021] Figure 7 A longitudinal cross-sectional view of a transverse connection structure between a port character unit and a side block unit according to a preferred embodiment of the present invention;

[0022] Figure 8 Another longitudinal cross-sectional view of the transverse connection structure between the port character unit and the edge block unit in a preferred embodiment of the present invention;

[0023] Fig. 9 It is a plan view of the transverse connection structure between the mouth piece unit and the edge block unit in a preferred embodiment of the present invention;

[0024] In the figure: 1. Mouth-shaped component unit; 2. Edge block unit; 3. U-shaped steel plug plate; 4. Slot; 5. Insert; 6. Corbel; 7. Reserved through hole; 8. Reserved blind hole; 9. Quick-setting and quick-hardening material. DETAILED DESCRIPTION

[0025] The terms "invention", "present invention" and "the present invention" used in this specification are intended to refer broadly to all subject matter of this specification and any patent claims below. Statements containing these terms should not be understood to limit the subject matter described herein or to limit the meaning or scope of any patent claim below. In addition, this specification does not attempt to describe or limit the subject matter covered by any claim of any specific component, paragraph, statement or figure of this application. The subject matter should be understood with reference to the entire specification, all drawings and any claims below. The present invention may have other embodiments and be practiced or implemented in other ways. Moreover, it should be understood that the words and terms used herein are for illustrative purposes and should not be considered as limiting.

[0026] The details of the present invention will now be discussed with reference to the accompanying drawings which illustrate the present invention by way of example only. In the accompanying drawings, similar features or components may be marked with the same reference numerals.

[0027] The use of "including," "having," and "comprising" and variations thereof herein is meant to encompass the items listed thereafter and their equivalents and additional items. Although reference may be made to directions such as above, below, upward, downward, rearward, bottom, top, front, rear, etc., in describing the drawings, for convenience, reference is made relative to the drawings. These directions are not intended to literally accept or limit the present invention in any form. In addition, terms such as "first," "second," "third," etc., are used herein for illustrative purposes and are not intended to indicate or imply importance or significance.

[0028] Figures 1 to 9 The present invention shows a connection structure of prefabricated assembly units inside a shield tunnel, wherein the prefabricated assembly units inside the shield tunnel include a mouth unit 1 located in the middle and side block units 2 located on both sides. In a preferred embodiment, the connection structure of prefabricated assembly units inside the shield tunnel of the present invention includes a longitudinal connection structure and a transverse connection structure.

[0029] See also Figure 4 , Figure 5 and Figure 6As shown, the longitudinal connection structure is suitable for the longitudinal connection between adjacent mouth-shaped component units 1 or the longitudinal connection between adjacent side block units 2, and specifically includes a U-shaped steel plug plate 3 and a group of slots 4. The slots 4 are respectively arranged near the adjacent edges of the top plates of the adjacent mouth-shaped component units 1 or near the adjacent edges of the top plates of the adjacent side block units 2. The two ends of the U-shaped steel plug plate 3 are respectively inserted into the slots 4 and fixed, and the position of the slots 4 needs to avoid the position of the steel bars.

[0030] See also Figure 7 , Figure 8 and Fig. 9 As shown, the transverse connection structure is suitable for the transverse connection between adjacent mouth-shaped component units 1 and side block units 2, including dowel bars 5 (i.e., steel bars) and corbels 6 located at the side wall of the mouth-shaped component unit 1, the corbels 6 are provided with reserved through holes 7, the side block units 2 are provided with an upward-flipping structure at the corresponding positions of the corbels 6, the upward-flipping structure is provided with reserved blind holes 8, and the dowel bars 5 are inserted into the reserved through holes 7 and the reserved blind holes 8 in sequence and then fixed.

[0031] Further, referring to the figure, in the longitudinal connection structure, after the front and rear prefabricated assembly units are hoisted and positioned, the quick-setting and quick-hardening material 9 is poured into the slot 4, and the U-shaped steel plug plate 3 is inserted into the slot 4 before the material solidifies. After the material solidifies and reaches strength, the U-shaped steel plug plate 3 can serve the purpose of longitudinally connecting the two adjacent units. The width of the U-shaped steel plug plate 3 is smaller than the width of the slot 4, and the depth of the U-shaped steel plug plate 3 is smaller than the depth of the slot 4. The purpose is to take into account the positioning error of the prefabricated structural unit and the misalignment in the assembly of the shield segment, so as to facilitate the insertion of the U-shaped steel plug plate 3.

[0032] In the transverse connection structure, after the dowel 5 is inserted into the reserved through hole 7 and the reserved blind hole 8 in sequence, the quick-setting and quick-hardening material 9 is poured in for dense filling. After the material solidifies and reaches strength, the dowel 5 can serve the purpose of horizontally connecting the middle mouth unit 1 with the side block units 2 on both sides. During the operation and maintenance stage, the dowel 5 as a connector is wrapped and covered with the quick-setting and quick-hardening material 9, which improves the durability of the connector and facilitates operation and maintenance. The inner diameter of the reserved through hole 7 and the inner diameter of the reserved blind hole 8 are both larger than the outer diameter of the dowel 5. The size of the reserved hole can accommodate the positioning error and a certain amount of misalignment of the prefabricated structural unit, and is also for the convenience of construction.

[0033] Furthermore, there is a certain gap between the corbel 6 and the upward-turned structure, and the gap is filled with a quick-setting and quick-hardening material 9 .

[0034] The present invention changes the commonly used bolt connection method. When there is "misalignment" between the pipe segments and a certain error in the positioning of the internal prefabricated structural units, the connection can still be quickly carried out, thereby achieving the purpose of facilitating construction and avoiding the inspection and maintenance of the connecting parts during operation and maintenance.

[0035] The above are only preferred embodiments of the present invention, and are not intended to limit the implementation methods and protection scope of the present invention. Those skilled in the art should be aware that all solutions obtained by equivalent substitutions and obvious changes made using the description and illustrations of the present invention should be included in the protection scope of the present invention.

Claims

1. A shield tunnel internal prefabricated assembly unit connection structure, the shield tunnel internal prefabricated assembly unit includes a mouth unit located in the middle and side block units located on both sides, It is characterized in that include: The longitudinal connection structure is suitable for the longitudinal connection between adjacent mouth-shaped unit or the longitudinal connection between adjacent side block units, and comprises a U-shaped steel insert plate and a group of slots, wherein the slots are respectively arranged near the adjacent edges of the top plates of the adjacent mouth-shaped unit or the adjacent edges of the top plates of the adjacent side block units, and the two ends of the U-shaped steel insert plate are respectively inserted into the slots and fixed; The transverse connection structure is suitable for the transverse connection between adjacent mouth-shaped unit and side block unit, and includes an inserted bar and a corbel located at the side wall of the mouth-shaped unit, the corbel is provided with a reserved through hole, and an upward flip structure is provided at the position corresponding to the side block unit and the corbel, the upward flip structure is provided with a reserved blind hole, and the inserted bar is inserted into the reserved through hole and the reserved blind hole in sequence and then fixed.

2. The prefabricated assembly unit connection structure inside the shield tunnel as claimed in claim 1, It is characterized in that After the front and rear prefabricated assembly units are hoisted and positioned, quick-setting and quick-hardening material is poured into the slot, and the U-shaped steel insert is inserted into the slot before the material solidifies.

3. The prefabricated assembly unit connection structure inside the shield tunnel as claimed in claim 1, It is characterized in that After the inserted bars are sequentially inserted into the reserved through holes and the reserved blind holes, quick-setting and quick-hardening materials are poured in to fill them densely.

4. The prefabricated assembly unit connection structure inside the shield tunnel as claimed in claim 1, It is characterized in that The width of the U-shaped steel insert plate is smaller than the width of the slot, the depth of the U-shaped steel insert plate is smaller than the depth of the slot, and the inner diameter of the reserved through hole and the inner diameter of the reserved blind hole are both larger than the outer diameter of the dowel.