Electrostatic discharge test system and test method
By designing an electrostatic discharge test system, automated electrostatic discharge test of objects such as single-phase and three-phase electric energy meters is realized, solving the problems of low manual detection efficiency and inaccurate measurement results in the existing technology, and improving the testing efficiency and safety .
Patent Information
- Application Number
- CN202411174215.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-26
- Publication Date
- 2024-11-26
AI Technical Summary
The existing electrostatic discharge testing system mainly relies on manual testing, which is low efficiency, high labor intensity, and high safety risks. It cannot guarantee the standardization and uniformity of the testing process, resulting in inaccuracy of the measurement results.
An electrostatic discharge test system was designed, including a transfer device, an electrostatic discharge device, an object power-on device, a tool power-on device and a detection device, which can realize a variety of test links of direct discharge, indirect discharge and air discharge, and is suitable for single-phase Automatic detection of objects such as three-phase electricity meters, and compatible detection of different objects is achieved by setting up different power-on equipment and fixtures.
The standardization of electrostatic discharge test has been achieved, the testing efficiency has been improved, the labor intensity of personnel has been reduced, and the credibility of the test results has been ensured, and it can be strictly implemented in accordance with the GB17626.2 standard.
Smart Images

Figure CN119024072A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of electrostatic discharge, and in particular to an electrostatic discharge test system and a test method. Background Art
[0002] Electrostatic discharge testing is to simulate the impact of human static electricity on equipment through a simulator. At present, the electrostatic discharge test systems of domestic power metering products are all manually tested, which has low detection efficiency, high labor intensity and high safety risks. At the same time, there are many existing power metering products, such as single-phase power meters, three-phase direct power meters, three-phase inductive power meters, terminals, etc., which all need to undergo electrostatic discharge testing. There are many test schemes, and manual testing cannot guarantee the standardization and uniformity of the test process, and thus cannot guarantee the accuracy of the measurement results.
[0003] The existing domestic electrostatic discharge test system tests are all manually carried out by grabbing the discharge gun head according to the GB17626.2 standard to perform electrostatic discharge tests on different positions of the power metering equipment. Some companies are also making related automation attempts for this test, mainly focusing on using industrial robots to replace people and using electrostatic discharge tools to directly discharge the surface of the power metering equipment. There is a lack of indirect discharge and air discharge links, and the discharge process is not strictly implemented according to GB17626.2, so the test results are not reliable.
[0004] The utility model with the publication number CN217981666U discloses an electrostatic discharge immunity test device, including: a workbench, an electrostatic gun, a controller, and a horizontal coupling plate, a vertical coupling plate, a moving mechanism and a gun head placement bin installed on the insulating desktop of the workbench, the horizontal coupling plate is used to place the energy meter, the vertical coupling plate is located on the side of the horizontal coupling plate, the electrostatic gun is connected to the moving mechanism, the moving mechanism drives the electrostatic gun to move and rotate the electrostatic gun within the working range, the horizontal coupling plate and the gun head placement bin are both located within the working range, the gun head placement bin is used to place the gun head and provide a placement position; the gun head placement bin, the electrostatic gun, and the moving mechanism are all connected to the controller and controlled by the controller. However, the above-mentioned electrostatic discharge immunity test device can only perform a single electrostatic discharge test on the energy meter. Summary of the invention
[0005] The purpose of the present invention is to provide an electrostatic discharge test system and a test method to solve the defects in the prior art, realize compatible detection of multiple objects, and realize multiple test links such as direct discharge, indirect discharge and air discharge.
[0006] To achieve the above-mentioned object, the present invention provides an electrostatic discharge test system, including a transport device, an electrostatic discharge device, an object power-on device, a tool power-on device, a detection device and a test bench;
[0007] The electrostatic discharge device comprises an indirect discharge device and an air discharge device, the indirect discharge device is provided with a first clamp and an indirect discharge gun, the air discharge device is provided with a second clamp and an air discharge gun, and both the first clamp and the second clamp can be connected to the transfer device;
[0008] The object positioning device comprises a first object power-on device and a second object power-on device, the first object power-on device is provided with a first object power-on tool, and the second object power-on device comprises a second object power-on tool;
[0009] The transfer device is connected with the first fixture to install the object to be tested on the first object electrical tooling device or the second object electrical tooling device, and is used to switch the position of the first object electrical tooling device between the first object electrical device and the test bench, or to switch the position of the second object electrical tooling device between the second object electrical device and the test bench;
[0010] The transfer device is cooperatively connected with the second clamp and is used to clamp the tooling power-on device to power on the first object power-on tooling or the second object power-on tooling.
[0011] The present invention can realize the electrostatic discharge test of objects such as single-phase electric energy meters and three-phase electric energy meters. It has a flexible structure and high flexibility. It can realize automatic detection of electrostatic discharge of various objects, standardize electrostatic discharge test, greatly improve test efficiency, and reduce labor intensity. In addition, the present invention is strictly implemented in accordance with GB17626.2, and can perform direct discharge, indirect discharge and air discharge through the device, with comprehensive detection and high credibility of test results.
[0012] Optionally, the first clamp includes a first quick-change plate, an object clamp and a positioning device clamp, the object clamp and the positioning device clamp are both connected to the first quick-change plate, and the first quick-change plate can be connected in cooperation with the transfer device.
[0013] The first quick-change plate can be connected with the connection plate provided on the transfer device to facilitate the transfer device to switch tools. The object gripper can adapt to the grasping of different objects, such as single-phase electric energy meters, three-phase electric energy meters, etc.; the positioning device gripper is used to grasp the electrical tooling on the first object or the electrical tooling on the second object.
[0014] Optionally, the first fixture further includes a first buffer device, one end of which is connected to the first quick-change disc, and the other end of which is respectively connected to the object clamping jaw and the positioning device clamping jaw.
[0015] Optionally, the second fixture includes a second quick-change disc, a clamping device and a tooling power-on device clamping jaw, the clamping device and the tooling power-on device clamping jaw are both connected to the second quick-change disc, and the second quick-change disc can be connected in cooperation with the transfer device.
[0016] The second fixture includes a second quick-change disc, which can be connected with a connecting disc provided on the transfer device to facilitate tool switching of the transfer device.
[0017] The clamping device is used to press down and fix the first object power-on device or the second object power-on device when the three-phase electric energy meter is connected to the first object power-on device, or when the single-phase electric energy meter is connected to the second object power-on device, to prevent the first object power-on device or the second object power-on device from moving when the connection is powered on.
[0018] The tooling power-on device clamp is used to clamp the tooling power-on device, connect the tooling power-on device with the first object power-on tooling / the second object power-on tooling, and complete the power-on work of the first object power-on tooling / the second object power-on tooling.
[0019] Optionally, the indirect discharge device further comprises an indirect discharge generator, and the indirect discharge generator is connected to the indirect discharge gun;
[0020] The air discharge device comprises an air discharge generator, and the air discharge generator is connected to an air discharge gun.
[0021] Optionally, the first object power-on tooling includes a first power-on seat, a first power-connecting terminal and a first limit assembly, and the first power-on seat is electrically connected to the first power-connecting terminal.
[0022] The first object power-on tooling is used for positioning and powering on a three-phase electric energy meter. The power-on end of the three-phase electric energy meter is connected to the first power-on socket, and the first power terminal is connected to the tooling power-on device to transmit power and signals to the first power-on socket. The first power-on socket directly inputs power and signals to the three-phase electric energy meter placed in the first object power-on device.
[0023] The reason why it is necessary to separately set up the first object power-on device and the second object power-on tooling is that the power-on interfaces of objects such as single-phase electric energy meters and three-phase electric energy meters are different, and corresponding special meter sockets need to be set up to cooperate with the power-on interfaces of different objects. The present invention sets up different power-on tools accordingly, sets standard power terminals and corresponding special meter sockets on the power-on tools, and there is no need to set up multiple tooling power-on devices to power on single-phase electric energy meters, three-phase electric energy meters and other objects respectively. The connectors with standard interfaces on the power-on devices can be connected to the standard power terminals on different power-on tools, and the power-on of different objects such as single-phase electric energy meters and three-phase electric energy meters can be realized.
[0024] The first limiting components are respectively arranged on the inner side walls opposite to the electrical device on the first object, and are used to limit the backward movement of the three-phase electric energy meter, complete the limiting and fixing of the three-phase electric energy meter, and realize the combined binding of the three-phase electric energy meter and the electrical device on the first object.
[0025] Optionally, the first object power-on device further includes a first positioning device, a first positioning detection component, and a plurality of first clamping blocks arranged around the first object power-on tooling.
[0026] A plurality of first clamping blocks are arranged around the first object electrical tooling, and a first positioning device is arranged at one end of the first object electrical tooling. The first clamping block cooperates with the first positioning device to achieve the position limitation of the first object electrical tooling, so as to prevent the transfer device from placing the object on the first object electrical tooling and damaging the positioning accuracy of the first object electrical tooling. The first positioning detection component can detect the presence or absence of the object or the first object electrical tooling to determine the accuracy of the workflow node.
[0027] Optionally, the second object power-on tooling includes a second power-on seat, a second power terminal and a second limit assembly, and the second power-on seat is electrically connected to the second power terminal.
[0028] The second object power-on device is used for positioning and powering up the single-phase electric energy meter, and includes a second frame, a second pneumatic device, a second object power-on tooling, a second positioning device, and a second positioning detection component. The second object power-on tooling is similar in structure to the first object power-on tooling, and includes a second power-on seat, a second power-connecting terminal, and a second limit component to complete the power-connecting action of the single-phase electric energy meter. The second limit component has the same structure and principle as the first limit component.
[0029] Optionally, the second object power-on device further includes a second positioning device, a second positioning detection component and a plurality of second clamping blocks arranged around the second object power-on tooling.
[0030] A plurality of second clamping blocks are arranged around the second object electrical fixture, and the second clamping blocks cooperate with the second positioning device to achieve the position limit of the second object electrical fixture, so as to prevent the transfer device from placing the object on the second object electrical fixture and damaging the positioning accuracy of the second object electrical fixture. The second positioning detection component can detect the presence or absence of the single-phase electric energy meter and the second object electrical fixture to assist in control.
[0031] The present invention also provides an electrostatic discharge testing method based on the electrostatic discharge testing system, comprising the following steps:
[0032] S1, the transfer device is connected to the first clamp;
[0033] S2, the transfer device installs the object to be tested on the electrical equipment on the first object, or on the electrical equipment on the second object, through the first fixture, and clamps the electrical equipment on the first object or the electrical equipment on the second object through the first fixture and places it on the test bench;
[0034] S3, the transfer device is replaced and connected to the second fixture;
[0035] S4, the transfer device clamps the tooling power-on device through the second fixture, and connects the tooling power-on device to the first object power-on tooling, or to the second object power-on tooling, to power on the object to be tested;
[0036] S5, the transfer device picks up the indirect discharge gun for indirect discharge and direct discharge, and picks up the air discharge gun for air discharge;
[0037] S6. The detection device records the entire process of the electrostatic discharge test and detects the state of the object to be tested in real time.
[0038] Beneficial effects:
[0039] The present invention arranges an electrostatic discharge device, an object power-on device, a tool power-on device, a detection device and a test bench within the working range of the transfer device through an overall layout. The object power-on device comprises a first object power-on device and a second object power-on device. The first object power-on device is provided with a first object power-on tool. The second object power-on device comprises a second object power-on tool. The electrostatic discharge test of objects such as single-phase electric energy meters and three-phase electric energy meters can be realized. The structure is flexible and highly flexible. Automatic detection of electrostatic discharge of various objects can be realized. The electrostatic discharge test can be standardized, the test efficiency can be greatly improved, and the labor intensity of personnel can be reduced.
[0040] The object electrification device of the present invention includes an indirect discharge device and an air discharge device. The indirect discharge device is provided with a first clamp and an indirect discharge gun, and the air discharge device is provided with a second clamp and an air discharge gun. The first clamp and the second clamp can be connected to the transfer device and can be strictly implemented according to GB17626.2. Direct discharge, indirect discharge and air discharge can be performed through the device, and the detection is comprehensive and the test results are highly reliable. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the structures shown in these drawings without paying creative work.
[0042] Figure 1 It is a structural diagram of the electrostatic discharge test system disclosed in the present invention;
[0043] Figure 2 It is a structural diagram of an indirect discharge device in the electrostatic discharge test system disclosed in the present invention;
[0044] Figure 3 It is a structural diagram of a first fixture in the electrostatic discharge test system disclosed in the present invention;
[0045] Figure 4 It is a structural diagram of an air discharge device in the electrostatic discharge test system disclosed in the present invention;
[0046] Figure 5 is a structural diagram of a second fixture in the electrostatic discharge test system disclosed in the present invention;
[0047] Figure 6 It is a structural diagram of a first object power-on device in an electrostatic discharge test system disclosed in the present invention;
[0048] Figure 7 It is a structural diagram of the first object electrical tooling in the electrostatic discharge test system disclosed in the present invention;
[0049] Figure 8 It is a structural diagram of the first limiting component in the electrostatic discharge test system disclosed in the present invention;
[0050] Fig. 9 It is a structural diagram of a second object power-on device in an electrostatic discharge test system disclosed in the present invention;
[0051] Fig.10 It is a structural diagram of the second object electrical tooling in the electrostatic discharge test system disclosed in the present invention;
[0052] Fig.11 It is a structural diagram of a tooling power-on device in an electrostatic discharge test system disclosed in the present invention;
[0053] Fig.12 It is a structural diagram of a test bench in the electrostatic discharge test system disclosed in the present invention.
[0054] Reference numerals:
[0055]
[0056]
[0057] The realization of the purpose, functional features and advantages of the present invention will be further explained in conjunction with the implementation methods and with reference to the accompanying drawings. DETAILED DESCRIPTION
[0058] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0059] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention in combination with the specific content of the technical solution.
[0060] In the description of the present invention, the description with reference to the terms "one embodiment", "some embodiments", "illustrative embodiments", "examples", "specific examples" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0061] Embodiment 1:
[0062] See also Figure 1-12 , an electrostatic discharge test system according to an embodiment of the present invention comprises a transfer device 2, an electrostatic discharge device, an object positioning device, a tooling power-on device 7, a detection device 8 and a test bench 9;
[0063] The electrostatic discharge device includes an indirect discharge device 3 and an air discharge device 4. The indirect discharge device 3 is provided with a first clamp 32 and an indirect discharge gun 33. The air discharge device 4 is provided with a second clamp 42 and an air discharge gun 43. Both the first clamp 32 and the second clamp 42 can be connected to the transfer device 2.
[0064] The object positioning device comprises a first object power-on device 5 and a second object power-on device 6, wherein the first object power-on device 5 is provided with a first object power-on tool 53, and the second object power-on device 6 comprises a second object power-on tool 63;
[0065] The transfer device 2 is connected with the first fixture 32 to mount the object to be tested on the first object electrical fixture 53 or the second object electrical fixture 63, and is used to switch the position of the first object electrical fixture 53 between the first object electrical device 5 and the test bench 9, or to switch the position of the second object electrical fixture 63 between the second object electrical device 6 and the test bench 9;
[0066] The transfer device 2 is cooperatively connected with the second clamp 42 to clamp the tooling power-on device 7 to power on the first object power-on tooling 53 or the second object power-on tooling 63 .
[0067] Specifically, an electrostatic discharge test system further includes an electrical cabinet 10, a conveyor line 1 for conveying objects to be tested, and the conveyor line 1, the indirect discharge device 3, the air discharge device 4, the first object power-on device 5, the second object power-on device 6, the tool power-on device 7, the detection device 8 and the test bench 9 are all arranged within the working range of the transfer device 2. The first object power-on tool 53 is used for positioning and powering up a three-phase electric energy meter, and the second object power-on tool 63 is used for positioning and powering up a single-phase electric energy meter.
[0068] The conveyor line 1 conveys the object to be tested to a place near the transfer device 2; the transfer device 2 is connected to the first clamp 32; the transfer device 2 installs the object to be tested on the first object electrical fixture 53, or installs it on the second object electrical fixture 63 through the first clamp 32, and clamps the first object electrical fixture 53 or the second object electrical fixture 63 through the first clamp 32 and places it on the test bench 9; the transfer device 2 is replaced and connected to the second clamp 42; the transfer device 2 clamps the fixture electrical device 7 through the second clamp 42, and connects the fixture electrical device 7 to the first object electrical fixture 53, or to the second object electrical fixture 63; the transfer device 2 picks up the indirect discharge gun 33 for indirect discharge and direct discharge, and picks up the air discharge gun 43 for air discharge; the detection device 8 records the entire process of the electrostatic discharge test and detects the status of the object to be tested in real time.
[0069] The present invention can realize the electrostatic discharge test of objects such as single-phase electric energy meters and three-phase electric energy meters. It has a flexible structure and high flexibility. It can realize automatic detection of electrostatic discharge of various objects, standardize electrostatic discharge test, greatly improve test efficiency, and reduce labor intensity. In addition, the present invention is strictly implemented in accordance with GB17626.2, and can perform direct discharge, indirect discharge and air discharge through the device, with comprehensive detection and high credibility of test results.
[0070] The transfer device 2 is a six-axis robot. The arm lengths of the indirect discharge gun 33 and the air discharge gun 43 are both greater than or equal to 800 mm. The indirect discharge gun 33, the air discharge gun 43, the first object electrical tooling 53 and the second object electrical tooling 63 are all made of non-metallic materials, and the distance between the test bench 9 and the surrounding devices meets the requirement of no metal components within 800 mm specified in GB17626.2, which can well avoid the influence of metal structures on electrostatic discharge tests. The transfer device 1 is provided with a connecting plate, and the indirect discharge gun 33 and the air discharge gun 43 are both provided with quick-change parts that cooperate with the connecting plate, so that the transfer device 2 can quickly grab the electrostatic gun and realize tool switching. The air discharge device 4 is similar to the indirect discharge device 3, on which the air discharge gun 43 and the second fixture 42 are stored.
[0071] In this embodiment, the indirect discharge device 3 and the first object power-on device 5 are arranged on the left side of the transfer device 2, the air discharge device 4 and the second object power-on device 6 are arranged on the right side of the transfer device 2, the test bench 9 and the conveyor line 1 are arranged on the front and rear sides of the transfer device 2, and the tooling power-on device 7 and the detection device 8 are arranged above the test bench 9. Through the overall structural layout, the transfer device 2 has a flexible structure and high flexibility, which improves space utilization.
[0072] The detection device 8 is a visual detection device, and the test bench 9 includes a horizontal plate 91, a vertical plate 92 and a limit bar 93 arranged on the horizontal plate 91, and the limit bar 93 is used to limit the position of the electrical tooling 53 on the first object or the electrical tooling 63 on the second object during the test.
[0073] See also Figure 2 and 3 In some embodiments of the present invention, the first clamp 32 includes a first quick-change disk 324, an object clamp 321 and a positioning device clamp 322, and the object clamp 321 and the positioning device clamp 322 are both connected to the first quick-change disk 324, and the first quick-change disk 324 can be connected to the transfer device 2.
[0074] The first quick-change disk 324 can be connected with the connection disk provided on the transfer device 2 to facilitate the transfer device 2 to switch tools. The first clamp 32 is equipped with an object clamp 321 and a positioning device clamp 322. The object clamp 321 is used to grasp objects, and the object clamp 321 can adapt to the grasping of different objects, such as single-phase electric energy meters, three-phase electric energy meters, etc.; the positioning device clamp 322 is used to grasp the electrical tooling 53 on the first object or the electrical tooling 63 on the second object. When the clamp only needs to grasp two or less types of electric energy metering devices, a pneumatic clamp drive is used. When more than two metering devices need to be grasped, the drive device can be driven by a linear motor or an electric cylinder.
[0075] In this embodiment, the first clamp 32 also includes a first buffer device 323, which is a spring assembly. The upper end of the first buffer device 323 is connected to the first quick-change disk 324, and the lower end is respectively connected to the object clamp 321 and the positioning device clamp 322. When the transfer device 2 drives the first clamp 32 close to the desktop to grasp an object, the first object on the electrical tool 53 or the second object on the electrical tool 63, it can buffer the force of the transfer device 2 to prevent the transfer device 2 from moving too fast and causing damage to the clamping parts, and can achieve accurate grasping and placement of objects.
[0076] See also Figure 4 and 5In some embodiments of the present invention, the second clamp 42 includes a second quick-change disc 424, a clamping device 421 and a tooling power-on device clamp 422, the clamping device 421 and the tooling power-on device clamp 422 are both connected to the second quick-change disc 424, and the second quick-change disc 424 can be connected in cooperation with the transfer device 2.
[0077] The second fixture 4 includes a second quick-change disc 424 , which can be connected with a connecting disc provided on the transfer device 2 to facilitate tool switching of the transfer device 2 .
[0078] The clamping device 421 is used to press down and fix the first object power-on device 5 or the second object power-on device 6 when the three-phase electric energy meter is connected to the first object power-on device 5, or when the single-phase electric energy meter is connected to the second object power-on device 6, to prevent the first object power-on device 5 or the second object power-on device 6 from moving when the connection is powered on.
[0079] The tooling power-on device clamping jaw 422 is used to clamp the tooling power-on device 7, so that the tooling power-on device 7 is connected to the first object power-on tool 53 / the second object power-on tool 63, and the power-on work of the first object power-on tool 53 / the second object power-on tool 63 is completed. The tooling power-on device clamping jaw 422 is L-shaped, and a protrusion 4221 is provided on it, and a groove 73 is provided corresponding to the tooling power-on device 7, so as to facilitate the positioning of the tooling power-on device clamping jaw 422 and the tooling power-on device 7.
[0080] In this embodiment, the second clamp 42 also includes a second buffer device 423, which is also a spring assembly. The upper end of the second buffer device 423 is connected to the second quick-change disk 424, and the lower end is respectively connected to the clamping device 421 and the tooling power-on device clamp 422. The function of the second buffer device 423 is similar to that of the first buffer device 323, which prevents the transfer device 2 from moving too fast and causing damage to the clamped parts, thereby achieving accurate grasping and placement of objects.
[0081] See also Figure 2 and 4 In some embodiments of the present invention, the indirect discharge device 3 also includes an indirect discharge generator 31, which is connected to an indirect discharge gun 33, and the air discharge device 4 includes an air discharge generator 41, which is connected to an air discharge gun 43.
[0082] The indirect discharge generator 31 is used to provide the electric energy required by the indirect discharge gun 33 , and the air discharge generator 41 is used to provide the electric energy required by the air discharge gun 43 .
[0083] See also Figure 6-811. In some embodiments of the present invention, the first object power-on tooling 53 includes a first upper power seat 531, a first power terminal 532 and a first limiting component 533, and the first upper power seat 531 is electrically connected to the first power terminal 532.
[0084] The first object electrification device 5 comprises a first frame 51 , a first pneumatic device 52 arranged on a side wall of the first frame 51 , a first object electrification tool 53 arranged on the first frame 51 , a first positioning device 54 and a first positioning detection assembly 55 .
[0085] In this embodiment, the first object power-on tool 53 is used for positioning and powering up the three-phase energy meter, the first power-on seat 531 is a dedicated three-phase energy meter seat, and the first power connection terminal 532 is a standard power connection terminal, which is used to cooperate with the connector 71 using a standard interface. The power-on end of the three-phase energy meter is connected to the first power-on seat 531, and the first power connection terminal 532 is connected to the tool power-on device 7, so that the power supply and signal are transmitted to the first power-on seat 531, and the first power-on seat 531 directly inputs the power supply and signal to the three-phase energy meter placed in the first object power-on device 5.
[0086] The reason why the first object power-on device 5 and the second object power-on tooling 63 need to be separately set is that the power-on interfaces of objects such as single-phase electric energy meters and three-phase electric energy meters are different, and corresponding special meter sockets need to be set to cooperate with the power-on interfaces of different objects. The present invention sets different power-on tools accordingly, sets standard power terminals and corresponding special meter sockets on the power-on tools, and there is no need to set multiple tooling power-on devices 7 to power on single-phase electric energy meters, three-phase electric energy meters and other objects respectively. The connector 71 with a standard interface on the power-on device 7 can be connected to the standard power terminals on different power-on tools, and the power-on of different objects such as single-phase electric energy meters and three-phase electric energy meters can be realized.
[0087] The first limiting assembly 533 is respectively arranged on the inner side wall opposite to the first object electrical device 5, and is used to limit the backward movement of the three-phase electric energy meter, complete the limiting and fixing of the three-phase electric energy meter, and realize the combined binding of the three-phase electric energy meter and the first object electrical device 5. The first limiting assembly 533 includes a fixing seat 5331, a reset spring 5332 and a limiting block 5333. When the three-phase electric energy meter needs to be limited, the limiting block 5333 is pressed down to make it contact with the end of the three-phase electric energy meter away from the first upper electrical seat 531 to prevent it from escaping from the first upper electrical seat 531. Under the downward pressure of the external force, the limiting block 5333 rotates upward under the action of the reset spring 5332 to realize the release of the limiting, and release the binding of the three-phase electric energy meter and the first object electrical tooling 53.
[0088] The tooling power-on device 7 is provided with a connector 71, which adopts a standard interface and can realize the power-on of different tooling such as single-phase, three-phase, and terminal. Guide pin holes 72 are provided at both ends of the connector 71, and guide columns are provided at corresponding positions on the first power terminal 532 or the second power terminal 632. Through the cooperation of the guide pin holes 72 and the guide columns, the connector 71 can be accurately connected to the first power terminal 532 to achieve precise guiding and positioning.
[0089] See also Figure 6 In some embodiments of the present invention, the first object power-on device 5 further includes a first positioning device 54 , a first positioning detection component 55 and a plurality of first clamping blocks 56 arranged around the first object power-on tooling 53 .
[0090] A plurality of first clamping blocks 56 are arranged around the first object electrical fixture 53, and a first positioning device 54 is arranged at one end of the first object electrical fixture 53. The first clamping block 56 cooperates with the first positioning device 54 to limit the first object electrical fixture 53, thereby preventing the transfer device 2 from damaging the positioning accuracy of the first object electrical fixture 53 during the process of placing the object on the first object electrical fixture 53. The first positioning detection component 55 can detect the presence or absence of the object or the first object electrical fixture 53, and determine the accuracy of the workflow node.
[0091] See also Fig. 9 and 10 In some embodiments of the present invention, the second object power-on tooling 63 includes a second upper power seat 631 , a second power terminal 632 , and a second limit assembly 633 , and the second upper power seat 631 is electrically connected to the second power terminal 632 .
[0092] The second object power-on device 6 is used for positioning and powering up the single-phase electric energy meter, and includes a second frame 61, a second pneumatic device 62, a second object power-on tool 63, a second positioning device 64, and a second positioning detection component 65. The second object power-on tool 63 is similar in structure to the first object power-on tool 53, and includes a second power-on seat 631, a second power terminal 632, and a second limit component 633, to complete the power-on action of the single-phase electric energy meter. The second limit component 633 has the same structure and principle as the first limit component 533.
[0093] In this embodiment, the movements of the object clamping jaw 321 , the positioning device clamping jaw 322 , the pressing device 421 , and the tooling power-on device clamping jaw 422 are all driven by the second pneumatic device 62 or by the first pneumatic device 52 .
[0094] See also Fig. 9 In some embodiments of the present invention, the second object power-on device 6 further includes a second positioning device 64 , a second positioning detection component 65 and a plurality of second clamping blocks 66 arranged around the second object power-on tooling 63 .
[0095] A plurality of second clamping blocks 66 are arranged around the second object electrical fixture 63. The second clamping blocks 66 cooperate with the second positioning device 64 to limit the position of the second object electrical fixture 63, thereby preventing the transfer device 2 from damaging the positioning accuracy of the second object electrical fixture 63 during the process of placing the object on the second object electrical fixture 63. The second positioning detection component 65 can detect the presence or absence of the single-phase electric energy meter and the second object electrical fixture 63 to assist in control.
[0096] Embodiment 2:
[0097] The present invention also provides an electrostatic discharge testing method based on the electrostatic discharge testing system, comprising the following steps:
[0098] S1, the transfer device 2 is connected to the first clamp 32;
[0099] S2, the transfer device 2 installs the object to be tested on the first object electrical tooling 53, or on the second object electrical tooling 63, through the first fixture 32, and clamps the first object electrical tooling 53 or the second object electrical tooling 63 through the first fixture 32 and places it on the test bench 9;
[0100] S3, the transfer device 2 is replaced and connected to the second clamp 42;
[0101] S4, the transfer device 2 clamps the tooling power-on device 7 through the second clamp 42, and connects the tooling power-on device 7 to the first object power-on tooling 53, or to the second object power-on tooling 63, to power on the object to be tested;
[0102] S5, the transfer device 2 picks up the indirect discharge gun 33 to perform indirect discharge and direct discharge, and picks up the air discharge gun 43 to perform air discharge;
[0103] S6. The detection device 8 records the entire process of the electrostatic discharge test and detects the state of the object to be tested in real time.
[0104] See also Figure 1-12 Taking a three-phase electric energy meter as an example, the working process of the present invention is as follows:
[0105] The three-phase electric energy meter is transported to the side adjacent to the transfer device 2 through the conveyor line 1 , and after being stopped and lifted to position, the first clamp 32 is picked up by the transfer device 2 .
[0106] After the transfer device 2 picks up the first clamp 32 , it clamps the three-phase electric energy meter to be tested through the object clamping claws 321 and places it on the first object electrical equipment 53 .
[0107] The transfer device 2 pushes the three-phase electric energy meter to be tested toward the first upper electric seat 531, and limits the position through the first limit assembly 533, so that the three-phase electric energy meter is clamped in the first object upper electric tooling 53, thereby completing the combination of the three-phase electric energy meter and the first object upper electric tooling 53. The transfer device 2 places the first object upper electric tooling 53 on the test bench 9 through the first fixture 32.
[0108] The transfer device 2 is replaced with the second clamp 42, which clamps the tooling power-on device 7 and inserts it into the first power terminal 532 provided on the first object power-on tooling 53, so as to power on the first object power-on tooling 53 and the three-phase electric energy meter.
[0109] According to the national standard GB17626.2, the transfer device 2 uses an indirect discharge gun 33 for indirect discharge and direct discharge, and replaces it with an air discharge gun 43 for air discharge. A wireless electrostatic gun can be used here, and a thread tightening machine or a plug-in device can be used to replace the gun head to achieve different electrostatic discharge requirements.
[0110] During the test, the detection device 8 records the entire test process and detects the status of the three-phase electric energy meter in real time.
[0111] After the test is completed, the transfer device 2 is replaced with the first clamp 32, and the first object on the test table 9 is grabbed and put on the electrical tool 53, rotated 90 degrees, and tested again.
[0112] After completing the electrostatic discharge test of the electric energy meter in strict accordance with the national standard, the transfer device 2 is replaced with the second fixture 42 to take out the tooling power-on device 7 .
[0113] Then the transfer device 2 uses the first fixture 32 to place the electric energy meter and the first object electrical tooling 53 on the first object electrical device 5. After being positioned by the first positioning device 54, the transfer device 2 presses down the limit block 5333 on the first limit assembly 533, grabs the three-phase electric energy meter and unloads it to the conveyor line 1 to complete the test.
[0114] For the test process of single-phase electric energy meter, in addition to replacing the first object power-on tool 53 with the second object power-on tool 63 in the second object power-on device 6, the corresponding power-on tool is replaced for the terminal or other metering device, and the test can be performed according to the same process as the three-phase electric energy meter.
[0115] The above are only preferred embodiments of the present invention, and are not intended to limit the patent scope of the present invention. All equivalent structural changes made using the contents of the present invention's specification and drawings under the inventive concept of the present invention, or directly / indirectly applied in other related technical fields, are included in the patent protection scope of the present invention.
Claims
1. An electrostatic discharge test system, characterized in that: It comprises a transfer device (2), an electrostatic discharge device, an object power-on device, a tool power-on device (7), a detection device (8) and a test bench (9); The electrostatic discharge device comprises an indirect discharge device (3) and an air discharge device (4); the indirect discharge device (3) is provided with a first clamp (32) and an indirect discharge gun (33); the air discharge device (4) is provided with a second clamp (42) and an air discharge gun (43); the first clamp (32), the indirect discharge gun (33), the second clamp (42) and the air discharge gun (43) can all be connected to the transfer device (2); The object power-on device comprises a first object power-on device (5) and a second object power-on device (6), the first object power-on device (5) is provided with a first object power-on tool (53), and the second object power-on device (6) is provided with a second object power-on tool (63); The transfer device (2) is connected in cooperation with the first fixture (32) for mounting the object to be tested on the first object electrical tooling (53) or the second object electrical tooling (63), and for switching the position of the first object electrical tooling (53) between the first object electrical device (5) and the test bench (9), or switching the position of the second object electrical tooling (63) between the second object electrical device (6) and the test bench (9); The transfer device (2) is cooperatively connected with the second clamp (42) and is used to clamp the tooling power-on device (7) to power on the first object power-on tooling (53) or the second object power-on tooling (63).
2. The electrostatic discharge test system according to claim 1, characterized in that: The first clamp (32) comprises a first quick-change disc (323), an object clamp (321) and a positioning device clamp (322); the object clamp (321) and the positioning device clamp (322) are both connected to the first quick-change disc (323); and the first quick-change disc (323) can be connected in cooperation with the transfer device (2).
3. The electrostatic discharge test system according to claim 2, characterized in that: The first clamp (32) further comprises a first buffer device (324), one end of the first buffer device (324) is connected to the first quick-change disk (323), and the other end is respectively connected to the object clamping jaw (321) and the positioning device clamping jaw (322).
4. The electrostatic discharge test system according to claim 1, characterized in that: The second clamp (42) comprises a second quick-change disc (423), a clamping device (421) and a tooling power-on device clamping jaw (422); the clamping device (421) and the tooling power-on device clamping jaw (422) are both connected to the second quick-change disc (423); and the second quick-change disc (423) can be connected in cooperation with the transfer device (2).
5. The electrostatic discharge test system according to claim 1, characterized in that: The indirect discharge device (3) further comprises an indirect discharge generator (31), wherein the indirect discharge generator (31) is connected to an indirect discharge gun (33); The air discharge device (4) comprises an air discharge generator (41), and the air discharge generator (41) is connected to an air discharge gun (43).
6. The electrostatic discharge test system according to claim 1, characterized in that: The first object power-on tool (53) comprises a first power-on seat (531), a first power-connecting terminal (532) and a first limit assembly (533), and the first power-on seat (531) is electrically connected to the first power-connecting terminal (532).
7. The electrostatic discharge test system according to claim 6, characterized in that: The first object power-on device (5) further comprises a first positioning device (54), a first positioning detection component (55) and a plurality of first clamping blocks (56) arranged around the first object power-on tooling (53).
8. The electrostatic discharge test system according to claim 1, characterized in that: The second object power-on tooling (63) comprises a second power-on seat (631), a second power-connecting terminal (632) and a second limit assembly (633), and the second power-on seat (631) is electrically connected to the second power-connecting terminal (632).
9. The electrostatic discharge test system according to claim 8, characterized in that: The second object power-on device (6) further comprises a second positioning device (64), a second positioning detection component (65) and a plurality of second clamping blocks (66) arranged around the second object power-on tooling (63).
10. An electrostatic discharge test method based on the electrostatic discharge test system according to any one of claims 1 to 9, characterized in that: The steps include: S1, the transfer device (2) is connected to the first clamp (32); S2, the transfer device (2) installs the object to be tested on the first object electrical tool (53) or the second object electrical tool (63) through the first clamp (32), and clamps the first object electrical tool (53) or the second object electrical tool (63) through the first clamp (32) and places it on the test bench (9); S3, the transfer device (2) is replaced and connected to the second clamp (42); S4, the transfer device (2) clamps the tooling power-on device (7) through the second clamp (42), and connects the tooling power-on device (7) to the first object power-on tooling (53), or to the second object power-on tooling (63), so as to power on the object to be tested; S5, the transfer device (2) picks up the indirect discharge gun (33) to perform indirect discharge and direct discharge, and picks up the air discharge gun (43) to perform air discharge; S6. The detection device (8) records the entire process of the electrostatic discharge test and detects the state of the object to be tested in real time.