Method for determining water and sediment series of upstream cascade reservoir

By collecting and analyzing the water and sand data of the upstream cascade reservoir and determining the appropriate water and sand series, the problem that the existing technology cannot reflect the incoming water and sand trends is solved, and the accuracy of sediment calculation in the cascade reservoir is improved, providing support for scientific scheduling.

CN119025816APending Publication Date: 2024-11-26CHINA THREE GORGES CORPORATION +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411131504.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-18
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

The existing technology cannot effectively reflect the actual trend of water and sand in the upstream cascade reservoirs and the lack of new water and sand series and determination methods suitable for upstream cascade reservoirs, resulting in the inability to scientifically dispatch and control sediment problems.

Method used

By collecting the main and tributary flow control stations and water and sand data of the upstream cascade reservoir, analyzing the change trend of incoming water and sand, combining the needs of the middle and lower reaches, a preliminary selection of the water and sand series, and through sand correction and sand blocking calculation, the final upstream cascade reservoir is determined. Water and sand series.

Benefits of technology

The accuracy of sediment calculation in cascade reservoirs has been improved, technical support is provided for scientific scheduling, and is suitable for the determination of water and sand series of other large rivers and large rivers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119025816A_ABST
    Figure CN119025816A_ABST
Patent Text Reader

Abstract

The invention relates to a method for determining water and sediment series of an upstream cascade reservoir, which comprises the following steps of: collecting water and sediment data of main and branch flow control stations, dam sites and intervals of the upstream cascade reservoir, and collecting research result data of the water and sediment series used in a design stage of each reservoir and the water and sediment series in an operation stage; the method comprises the following steps: analyzing an upstream cascade reservoir incoming water and incoming water and sediment change trend, combining existing water and sediment series research results and middle and downstream research requirements, and preliminarily selecting a proper cascade reservoir water and sediment series by taking an incoming water process as a main basis; performing comparative analysis on the sand amount of the preliminarily selected cascade reservoir water-sand series and the upstream incoming sand change characteristics, and further correcting the sand amount of the preliminarily selected cascade reservoir water-sand series; and on the basis of the reservoir entering main and branch drift sand amount of the cascade reservoir water and sediment series after sand amount correction, sand blocking calculation is carried out on reservoir entering main and branch flows, and then the final upstream cascade reservoir water and sediment series is obtained. Technical support can be provided for cascade reservoir sediment problem research and cascade reservoir scientific dispatching.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of water conservancy engineering, and more specifically, to a method for determining a water-sediment series of an upstream cascade reservoir. Background Art

[0002] One of the existing technologies is to give a typical water-sediment series for a single reservoir, and the other is to use the natural water-sediment process as a typical water-sediment series. The shortcomings of the existing technology include: the existing water-sediment series cannot reflect the current reality and future trend of upstream sediment, lack of a new water-sediment series suitable for upstream cascade reservoirs, and lack of a method for determining the new water-sediment series for cascade reservoirs. The existing technology can no longer meet the objective needs of the study of sediment problems in upstream cascade reservoirs, causing great inconvenience to the scientific dispatching research of cascade reservoirs. Summary of the invention

[0003] The purpose of the embodiment of the present application is to provide a method for determining the water-sediment series of upstream cascade reservoirs, which can solve the problem that the existing technology cannot adapt to the objective needs of studying the sediment problems of upstream cascade reservoirs.

[0004] To achieve the above objectives, this application provides the following technical solutions:

[0005] The embodiment of the present application provides a method for determining the water-sediment series of an upstream cascade reservoir, comprising the following steps:

[0006] Step 1: Collect water and sediment data of the upstream cascade reservoir main and tributary control stations, dam sites and intervals, and collect the water and sediment series used in the design stage of each reservoir and the research results of the water and sediment series in the operation stage;

[0007] Step 2: Analyze the changing trends of water and sediment in the upstream cascade reservoirs, combine the existing water and sediment series research results and the research needs of the middle and lower reaches, and preliminarily select the appropriate cascade reservoir water and sediment series based on the water inflow process;

[0008] Step 3, compare and analyze the sediment volume of the initially selected cascade reservoir water and sediment series with the upstream sediment change characteristics, and then revise the sediment volume of the initially selected cascade reservoir water and sediment series;

[0009] Step 4, based on the sediment volume of the inflowing main and tributary streams of the cascade reservoir water and sediment series after sediment volume correction, the sediment interception calculation of the inflowing main and tributary streams is performed to obtain the final upstream cascade reservoir water and sediment series.

[0010] In step 1, the hydrological stations that need to collect data include the control stations of the main and tributary streams of the cascade reservoirs and the hydrological stations along the main stream. The water and sediment data are all data since the establishment of the station; the water and sediment series include the water and sediment series used in the design stage of each reservoir, the water and sediment series used in the study of sediment problems in the reservoir operation stage, and related research results.

[0011] In step 2, the water inflow process of the water and sediment series of the preliminarily selected cascade reservoirs must include typical years of wet, medium and dry years, and must also take into account the needs of the upstream cascade reservoir scheduling and operation and the middle and lower reaches of the river management for the selected water and sediment series water inflow process, and at the same time be able to reflect the current reality and future trend of the upstream cascade reservoir water inflow.

[0012] In the step 3, according to the principle that the underlying surface conditions of water and sediment production and transportation in the basin where the cascade reservoirs are located are as new as possible and the principle of selecting measured natural values ​​as much as possible rather than predicted calculated values ​​as much as possible, the sediment inflow of the main and tributary rivers of the cascade reservoirs of the water and sediment series preliminarily selected in step 2 is corrected. The method for selecting the corrected sediment value is to give priority to the median value among the three averages of the annual average sediment volume of the water and sediment series selected in step 2, the annual average sediment volume before the construction of each reservoir, and the recent annual average sediment volume. When the median value is close to the maximum value or the minimum value and the future sediment production has a decreasing trend, the minimum value is selected. The method for selecting the sediment volume series must meet the principle of being as safe as possible and reflecting the overall decreasing trend of the upstream sediment production and transportation in the future as much as possible.

[0013] In step 4, based on the sediment volume of the upstream cascade reservoirs entering the main and tributary streams obtained in step 3, the sediment interception effect of the cascade reservoirs entering the main and tributary streams is considered, and the balanced slope method is used to calculate the sediment interception of the main and tributary streams entering the cascade reservoirs, thereby obtaining the final water and sediment series of the upstream cascade reservoirs.

[0014] Compared with the prior art, the present invention has the following beneficial effects:

[0015] The present invention can obtain a water-sediment series of upstream cascade reservoirs, improve the accuracy of sediment calculation of cascade reservoirs, and provide technical support for scientific scheduling of cascade reservoirs. The method of the present invention is also applicable to the determination of water-sediment series of cascade reservoirs on other major rivers. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments of the present application will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0017] Figure 1 The figure is a flow chart of a method according to an embodiment of the present invention. DETAILED DESCRIPTION

[0018] The technical solutions in the embodiments of the present application will be described below in conjunction with the drawings in the embodiments of the present application. It should be noted that similar reference numerals and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in the subsequent drawings.

[0019] The terms "comprises," "comprising," or any other variation thereof are intended to encompass non-exclusive inclusion, such that a process, method, article, or apparatus that includes a list of elements includes not only those elements, but also other elements not explicitly listed, or elements inherent to such process, method, article, or apparatus. In the absence of further limitations, an element defined by the phrase "comprising a ..." does not exclude the presence of additional identical elements in the process, method, article, or apparatus that includes the element.

[0020] The terms "first", "second", etc. are only used to distinguish one entity or operation from another entity or operation, and should not be understood as indicating or implying relative importance, nor should they be understood as requiring or implying any such actual relationship or order between these entities or operations.

[0021] like Figure 1 As shown, a method for determining the water-sediment series of an upstream cascade reservoir comprises the following steps:

[0022] Step 1: Collect water and sediment data of the upstream cascade reservoir main and tributary control stations, dam sites and intervals, and collect the water and sediment series used in the design stage of each reservoir and the research results of the water and sediment series in the operation stage;

[0023] Step 2: Analyze the changing trends of water and sediment in the upstream cascade reservoirs, combine the existing water and sediment series research results and the research needs of the middle and lower reaches, and preliminarily select the appropriate cascade reservoir water and sediment series based on the water inflow process;

[0024] Step 3, compare and analyze the sediment volume of the initially selected cascade reservoir water and sediment series with the upstream sediment change characteristics, and then revise the sediment volume of the initially selected cascade reservoir water and sediment series;

[0025] Step 4, based on the sediment volume of the inflowing main and tributary streams of the cascade reservoir water and sediment series after sediment volume correction, the sediment interception calculation of the inflowing main and tributary streams is performed to obtain the final upstream cascade reservoir water and sediment series.

[0026] Embodiment 1:

[0027] Collect water and sediment data of the main and tributary control stations, dam sites and intervals of the WDD-BHT-XLD-XJB-SX cascade reservoirs in the upper reaches of the C River, collect water and sediment series used in the design stage of each reservoir and research results of water and sediment series in the operation stage, etc.;

[0028] The changing trends of water and sediment in the cascade reservoirs in the upper reaches of the C River were analyzed. Based on the existing research results on water and sediment series and the research needs of the middle and lower reaches of the C River, the natural water and sediment series from 1991 to 2000 was preliminarily selected as the water and sediment series of the cascade reservoirs in the upper reaches of the C River based on the water inflow process.

[0029] Comparing and analyzing the sediment amount of the water-sediment series of the initially selected cascade reservoirs and the characteristics of sediment changes in the upper reaches of the C River, it is found that compared with the current actual and future trends, the total sediment amount of the natural water-sediment series in the middle and lower reaches of the JS River and some hydrological stations from 1991 to 2000 is still too large, so the sediment amount of the natural water-sediment series of the initially selected cascade reservoir water-sediment series from 1991 to 2000 is revised to reduce the sediment amount of the new water-sediment series;

[0030] Based on the sediment amount correction of the water and sediment series of the upper reaches of the C River cascade reservoirs, the sediment interception calculations of the cascade reservoirs for the inflowing main and tributary rivers such as the middle reaches of the JS River cascade, the YL River cascade, the M River cascade, the JL River cascade, and the W River cascade were carried out, and then the final "Sediment Amount Correction Series of the Upper C River Cascade Reservoirs from 1991 to 2000" applicable to the upper reaches of the C River cascade reservoirs was obtained.

[0031] The sediment load at the main hydrological stations in the upper reaches of the river C in the sediment load correction series from 1991 to 2000 is shown in Table 1, and the sediment load in the upper reaches of the river C in the sediment load correction series from 1991 to 2000 is shown in Table 2.

[0032] Table 1 1991-2000 Sediment Quantity Correction Series C Sediment Quantity Statistics of Main Hydrological Stations in the Upper Reaches of the River Unit: billion tons

[0033]

[0034] Note: (1) The sediment discharge of the YL River before 2000 was the sum of the XDS and WT stations, and after 2000 it was the TZL station; (2) The sediment discharge of the mainstream control station is the sum of the sediment discharge of the upstream main and tributary rivers, without considering the impact of river scouring and siltation, so it is marked with brackets ()

[0035] Table 2 1991-2000 Sediment Quantity Correction Series C Sediment Quantity Statistics for the Upper Reaches of the Yangtze River Unit: billion tons Note: (1) PZH+TZL-HT, the sediment transport of YL River was the sum of XDS and WT stations before 2000, and after 2000 it was TZL station; (2) It is assumed that the sediment transport in the interval below XJB is equal to the sand mining in the river and they offset each other, so the value is zero.

[0036] The above description is only an embodiment of the present application and is not intended to limit the protection scope of the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A method for determining the water-sediment series of upstream cascade reservoirs, It is characterized in that The following steps are involved: Step 1: Collect water and sediment data of upstream cascade reservoir main and tributary control stations, dam sites and intervals, and collect water and sediment series used in the design stage of each reservoir and research results of water and sediment series in the operation stage; Step 2: Analyze the changing trends of water and sediment in the upstream cascade reservoirs, combine the existing water and sediment series research results and the research needs of the middle and lower reaches, and preliminarily select the appropriate cascade reservoir water and sediment series based on the water inflow process; Step 3, compare and analyze the sediment volume of the initially selected cascade reservoir water and sediment series with the upstream sediment change characteristics, and then revise the sediment volume of the initially selected cascade reservoir water and sediment series; Step 4, based on the sediment volume of the inflowing main and tributary streams of the cascade reservoir water and sediment series after sediment volume correction, the sediment interception calculation of the inflowing main and tributary streams is performed to obtain the final upstream cascade reservoir water and sediment series.

2. A method for determining the water-sediment series of an upstream cascade reservoir according to claim 1, It is characterized in that In step 1, the hydrological stations that need to collect data include the control stations of the main and tributary streams of the cascade reservoirs and the hydrological stations along the main stream. The water and sediment data are all data since the establishment of the station; the water and sediment series include the water and sediment series used in the design stage of each reservoir, the water and sediment series used in the study of sediment problems in the reservoir operation stage, and related research results.

3. A method for determining the water-sediment series of an upstream cascade reservoir according to claim 1, It is characterized in that In step 2, the water inflow process of the water and sediment series of the preliminarily selected cascade reservoirs must include typical years of wet, medium and dry years, and must also take into account the needs of the upstream cascade reservoir scheduling and operation and the middle and lower reaches of the river management for the selected water and sediment series water inflow process, and at the same time be able to reflect the current reality and future trend of the upstream cascade reservoir water inflow.

4. A method for determining the water-sediment series of an upstream cascade reservoir according to claim 3, It is characterized in that In the step 3, according to the principle that the underlying surface conditions of water and sediment production and transportation in the basin where the cascade reservoirs are located are as new as possible and the principle of selecting measured natural values ​​as much as possible rather than predicted calculated values ​​as much as possible, the sediment inflow of the main and tributary rivers of the cascade reservoirs of the water and sediment series preliminarily selected in step 2 is corrected. The method for selecting the corrected sediment value is to give priority to the median value among the three averages of the annual average sediment volume of the water and sediment series selected in step 2, the annual average sediment volume before the construction of each reservoir, and the recent annual average sediment volume. When the median value is close to the maximum value or the minimum value and the future sediment production has a decreasing trend, the minimum value is selected. The method for selecting the sediment volume series must meet the principle of being as safe as possible and reflecting the overall decreasing trend of the upstream sediment production and transportation in the future as much as possible.

5. A method for determining the water-sediment series of an upstream cascade reservoir according to claim 4, It is characterized in that In step 4, based on the sediment volume of the upstream cascade reservoirs entering the main and tributary streams obtained in step 3, the sediment interception effect of the cascade reservoirs entering the main and tributary streams is considered, and the balanced slope method is used to calculate the sediment interception of the main and tributary streams entering the cascade reservoirs, thereby obtaining the final water and sediment series of the upstream cascade reservoirs.