Automatic start-stop control method for pumped storage unit
By incorporating the pumping storage unit into the real-time control of provincial scheduling of the power grid, and using the encoding control of AGC and safety locking logic, the problem of the rapid start-stop, peak-to-peak frequency regulation capability of the pumping storage unit is not fully utilized, and the control effect of the power grid frequency is improved and Security.
Patent Information
- Application Number
- CN202410925818.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-11
- Publication Date
- 2024-11-26
AI Technical Summary
When the existing pumped storage power stations require power grid regulation, they dispatch the pumped storage unit through telephone scheduling, resulting in the failure to fully utilize the rapid start-stop peak-control frequency regulation capability, especially when high-power failure and low frequency, which affects the frequency recovery of the power grid. Safety.
The automatic start-stop control method of pumping accumulator is adopted to incorporate the pumping accumulator into the real-time control of provincial power grid dispatching. Through AGC, the automatic power generation control of pumping accumulator is realized. The control target is issued by encoding to ensure the safety locking logic. and operating condition conversion to maximize the utilization of peak-shaving and frequency-modulation capabilities of the pumping storage unit.
It reduces the working pressure of dispatchers, improves the grid frequency control effect, maximizes the use of the rapid start-stop, peak-modulation and frequency regulation capabilities of the pumping storage unit, and improves the safety and stability of grid frequency operation.
Abstract
Description
Technical Field
[0001] The invention belongs to the field of active power control of electric power systems. Background Art
[0002] Hydropower stations are special power sources with multiple functions such as peak regulation, valley filling, frequency regulation, phase regulation, emergency standby and black start. They are flexible in operation and quick in response, and play an important role in ensuring the safe, stable and economical operation of the power system.
[0003] The dual function of peak load shifting and valley filling of pumped storage power stations is not possessed by any other power source. Pumped storage power stations use excess cheap electricity to pump water when the load is low, and generate electricity when the load is peak, meeting the peak load demand of the power grid, thereby achieving a dynamic balance between power production and consumption. Pumped storage power stations can effectively bear the peak load of the system and play a peak load shifting role, thereby replacing peak load shifting units with high operating costs (such as oil units and gas units) to reduce system fuel consumption. When the system load is low, pumped storage power stations use the electricity generated by the idle capacity of thermal power and nuclear power units as pumped power sources, so that the waist load of this part of the thermal power units is converted into base load, allowing thermal power and nuclear power units to operate efficiently under uniform and stable loads, which not only improves the operating conditions of thermal power or nuclear power units, increases equipment utilization hours, but also reduces plant power consumption and standard coal consumption rate. In the flood season, pumped storage units and conventional hydropower units can cooperate to reasonably utilize water resources and reduce hydropower abandonment. Most of the existing pumped storage power stations participate in peak load shifting in the power grid.
[0004] Pumped storage units start quickly and increase load quickly. Even in a stationary state, they can be fully loaded within a few minutes in case of an emergency. Under pumping conditions, pumped storage power stations provide ideal emergency backup. When an accident occurs in the system, the operation of the water pump can be stopped immediately to reduce the power supply load of the system.
[0005] However, at present, pumped-storage units generally adopt the method of tracking the day-ahead plan for start and shutdown control. When grid regulation is needed, dispatchers temporarily call on pumped-storage units for peak-shaving control through telephone dispatch. The pumped-storage units' ability to quickly start and stop, regulate peak and frequency cannot be fully utilized. Especially when the grid experiences a large power loss failure or the grid frequency is seriously low, the method of telephone dispatching pumped-storage units will greatly delay the recovery of the grid frequency and affect the safe operation of the grid frequency. Summary of the invention
[0006] The purpose of the present invention is to overcome the above-mentioned deficiencies in the prior art and to provide a method for automatic start and stop control of a pumped storage unit taking into account the safety of the pumped storage unit and the safety of the power grid, so as to incorporate the pumped storage unit into the real-time control of the provincial dispatching of the grid. Through the automatic start and stop control of the pumped storage unit, the pumped storage unit can be automatically controlled according to the real-time control needs of the power grid, thereby maximizing the utilization of the peak-shaving and frequency-regulating capabilities of the pumped storage unit.
[0007] The automatic start-stop control method for pumped-storage units provided by the present invention takes into account the safety of pumped-storage units and the safety of the power grid. The provincial power grid dispatching center incorporates the pumped-storage power plant into the power grid AGC (Automatic Generation Control) for unified coordinated optimization control according to control requirements, expands the provincial power grid's peak-shaving and frequency-regulating resources, reduces the dispatcher's workload, and improves the power grid frequency control effect.
[0008] In order to achieve the above object, the present invention is implemented by adopting the following technical scheme: a method for automatically starting and stopping a pumped storage unit considering the safety of the pumped storage unit and the safety of the power grid, comprising:
[0009] When the power grid is running smoothly, the AGC master station of the power grid dispatching center performs multiple checks on the power generation plan value of the pumped storage unit. After the check passes, the power generation plan value is sent to the pumped storage unit as the control target through the control target code;
[0010] When a large power disturbance fault is detected in the power grid, the AGC master station first determines the disturbance direction and amount, then allocates the disturbance amount to the corresponding pumped storage unit, and finally sends the emergency control target to the pumped storage unit through the control target code;
[0011] The control target code length is 8 bits, and the format is AABBCDDD; AA represents the pumped-storage power plant code, starting from 01, and supports a maximum of 99 pumped-storage power plants; BB represents the internal unit code of the pumped-storage power plant, starting from 01, and a pumped-storage power plant supports a maximum of 99 pumped-storage units; C represents the operating condition conversion mode; DDD represents the control target value, and the control range is from 000 to 999.
[0012] The AGC master station of the power grid dispatching center performs multiple checks on the power generation plan value of the pumped storage unit. After the check passes, the power generation plan value is sent to the pumped storage unit as a control target through the control target code. The steps are as follows:
[0013] The AGC master station obtains the planned power generation value of the pumped storage unit and verifies the validity of the planned power generation value;
[0014] After the validity check is passed, the operating condition conversion state required is determined according to the power generation plan value and the operating condition conversion state is checked;
[0015] After the operating condition conversion status verification is passed, the permissible operating condition conversion target of the pumped storage unit is verified according to the safety interlock control logic;
[0016] After the operating condition conversion target is verified, the power generation plan value is sent to the pumped storage unit as the control target through the control target coding.
[0017] The operating condition conversion state that needs to be performed is determined based on the power generation plan value, specifically: if the power generation plan value is 0, it is necessary to enter the shutdown operating condition conversion; if the power generation plan value is a positive number, it is necessary to enter the forward power generation operating condition conversion; if the power generation plan value is a negative number, it is necessary to enter the pumping operating condition conversion.
[0018] The checking of the operating condition conversion state is specifically as follows: determining the current operating condition of the pumped storage unit according to the actual output of the pumped storage unit and the real-time operating condition sent by the pumped storage unit, and determining whether the next operating condition conversion is allowed in combination with the operating condition conversion state.
[0019] The safety lockout control logic includes:
[0020] For pumped storage units whose AGC remote controllable signals are not put into use, no control instructions will be issued;
[0021] When the AGC remote controllable signal is activated, if the pumped storage unit is in the shutdown state, it is allowed to enter the shutdown-to-power generation condition conversion only when the power generation permission signal is "yes", and it is allowed to enter the shutdown-to-pumping condition conversion only when the pumping permission state is "yes"; if the pumped storage unit is in the power generation state, it is allowed to enter the power generation-to-shutdown state only when the shutdown permission signal is "yes"; if the pumping unit is in the pumping state, it is allowed to enter the pumping-to-shutdown state only when the shutdown permission signal is "yes", and it is allowed to enter the pumping-to-pumping phase adjustment state only when the pumping phase adjustment permission state is "yes".
[0022] The implementation steps for monitoring the power grid for high power disturbance faults are as follows:
[0023] First, the AGC master station monitors the ACE and grid frequency in the grid control area in real time.
[0024] The real-time value of ACE calculated by AGC in real time satisfies the requirements of formula (1):
[0025] ACE<-1*K*|ΔP| (1)
[0026] Where: ACE is the real-time regional control deviation of the control area, K is the correction coefficient, which is a positive number less than 1, and |ΔP is the power loss threshold;
[0027] Grid frequency deviation:
[0028] |Δf|>|Δfmax| (2)
[0029] Δf is the real-time frequency deviation of the power grid, Δf max is the frequency deviation safety threshold.
[0030] and:
[0031] Δf×ACE>0 (3)
[0032] If the above three criteria are all met, it is determined that a large power disturbance fault occurs in the power grid, and the power disturbance amount of the power grid is ACE.
[0033] The AGC master station first determines the disturbance direction and disturbance amount, then allocates the disturbance amount to the corresponding pumped storage unit, and finally sends the emergency control target to the pumped storage unit through coding. The specific implementation steps are as follows:
[0034] First determine the disturbance amount ACE and disturbance direction. If ACE is positive, the grid has excess power and needs to reduce output. If ACE is negative, the grid lacks a lot of power and the unit needs to increase output quickly.
[0035] If ACE is negative, ACE will be allocated to all units that are in pumping state and allowed to be shut down first; if there is still ACE left after allocation, the remaining part will be allocated to the pumped storage units that are currently in shutdown state and allowed to generate electricity;
[0036] If ACE is positive, ACE is allocated to the pumped storage units that are currently in power generation and allowed to shut down first; if there is still ACE left after allocation, the remaining ACE is allocated to the pumped storage units that are currently shut down and allowed to pump water;
[0037] After the ACE allocation is completed, the current output of the pumped storage unit is added to the allocated amount to obtain the emergency control target of the pumped storage unit, and then the emergency control target is sent to the pumped storage unit through coding.
[0038] It also includes establishing a pumped storage unit control model in the provincial dispatching AGC, and setting the pumped storage unit control model as follows:
[0039] Set basic parameters, including the name of the pumped-storage power plant, the name of the pumped-storage unit, the installed capacity of the pumped-storage unit, the number of the pumped-storage unit, the actual output of the pumped-storage unit, the power generation plan of the pumped-storage unit, and the remote control signal of the pumped-storage unit;
[0040] Anti-error parameters are set, including the current operating state of the pumped-storage unit, the allowed operating state conversion state of the pumped-storage unit, and the prohibited operation state of the pumped-storage unit; the current operating state of the pumped-storage unit includes shutdown, power generation, pumping, pumping phase adjustment, and power generation phase adjustment; the allowed operating state conversion state of the pumped-storage unit includes shutdown allowed, power generation allowed, pumping phase adjustment allowed, and power generation phase adjustment allowed; the prohibited operation state of the pumped-storage unit includes prohibition of increasing output and prohibition of reducing output.
[0041] Compared with the prior art, the beneficial effects of the present invention are as follows: in view of the problem that the general telephone dispatch of pumped storage units cannot fully utilize the rapid start-stop peak-shaving and frequency regulation capabilities of the pumped storage units, the present invention models the pumped storage units in the AGC application, and according to the operating characteristics and safety requirements of the start-stop operating condition conversion of the pumped storage units, the operating condition conversion locking logic and control coding that take the operating state into consideration are designed to achieve safe control of the pumped storage units, and then according to the power grid operation requirements, the control targets of the pumped storage units are automatically derived and issued, thereby maximizing the utilization of the peak-shaving and frequency regulation capabilities of the pumped storage units, while reducing the work pressure of the dispatchers and improving the safe operation level of the power grid frequency. DETAILED DESCRIPTION
[0042] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0043] The present invention aims at the problem that the pumped storage unit generally adopts telephone dispatching and cannot fully utilize the rapid start-stop peak-shaving and frequency regulation capabilities of the pumped storage unit. First, a control model of the pumped storage unit is established in the AGC application of the provincial dispatching center of the network, and the real-time operating state and the start-stop working condition conversion operating state of the pumped storage unit are connected, and the working condition conversion locking logic and control coding considering the operating state are designed to ensure the safe control of the pumped storage unit. Then, the power grid frequency control demand and the power grid safe operation need are comprehensively considered, and the control target is automatically generated according to the power generation plan of the pumped storage unit in the steady state. When a serious fault occurs in the power grid, the control target of the pumped storage unit is automatically corrected according to the power imbalance of the power grid, so as to realize the real-time closed-loop control of the pumped storage unit, and at the same time reduce the work pressure of the dispatcher and improve the level of safe operation of the power grid frequency.
[0044] The automatic start-stop control method for a pumped storage unit considering the safety of the pumped storage unit and the safety of the power grid provided by the present invention includes the following contents:
[0045] (1) In response to the frequency and interconnection line power control requirements of the provincial power grid, a main control area is generally established within the AGC application of the provincial power grid dispatching center (hereinafter referred to as the provincial dispatching center), which is mainly responsible for controlling the conventional hydropower units within the dispatching range. The control target of the provincial dispatching AGC main control area can ensure that the grid frequency and interconnection line power operate near the planned values, ensure the safety of grid frequency operation, and support the safe and stable consumption of new energy in the grid.
[0046] (2) In view of the automatic closed-loop control requirements of the pumped storage unit, the control model of the pumped storage unit is first established in the provincial AGC, including:
[0047] (21) Basic model of pumped storage units, including: name of pumped storage power plant, name of pumped storage unit, installed capacity of pumped storage unit, number of pumped storage unit, actual output of pumped storage unit and power generation plan of pumped storage unit, remote control signal of pumped storage unit, etc.;
[0048] (22) The error prevention model of the pumped-storage unit includes: the current operating status of the pumped-storage unit (shutdown, power generation, pumping, pumping phase adjustment, power generation phase adjustment), the allowable operating condition conversion status of the pumped-storage unit (shutdown allowed, power generation allowed, pumping phase adjustment allowed, power generation phase adjustment allowed), and the prohibited operation status of the pumped-storage unit (output increase prohibited, output reduction prohibited).
[0049] (3) After the pumped storage unit model is established in the provincial dispatching AGC, in order to ensure the safety of the pumped storage unit control, the safety control logic of the pumped storage unit is first set:
[0050] (31) For pumped storage units whose AGC remote controllable signals are not activated, no control instructions are issued;
[0051] (32) When the AGC remote control signal is activated, if the pumped storage unit is in shutdown state, the shutdown-to-power generation mode conversion is allowed only when the power generation permission signal is "yes". The shutdown-to-pumping mode conversion is allowed only when the pumping permission state is "yes".
[0052] (33) When the AGC remote control signal is activated, if the pumping unit is in the generating state, it is allowed to enter the generating state to stop state only when the stop signal is “yes”.
[0053] (34) When the AGC remote control signal is activated, if the pumping unit is in the pumping state, the pumping to shutdown state is allowed only when the shutdown signal is "yes". The pumping to pumping phase adjustment state is allowed only when the pumping phase adjustment state is "yes".
[0054] (4) Considering the fast adjustment rate and rapid working condition conversion of the pumped storage unit, the traditional direct remote adjustment method is not used when issuing control target instructions, but a coding method with verification is adopted. The coding method is as follows:
[0055] The code length is 8 bits in total, and the format is AABBCDDD, where AA represents the power plant code. Each pumped-storage power plant has its own independent code, starting from 01, and supports a maximum of 99 pumped-storage power plants; BB represents the unit code, which represents the unit code inside the pumped-storage power plant. Starting from 01, a pumped-storage power plant supports a maximum of 99 pumped-storage units. C represents the operating condition conversion mode, and DDD represents the control target value, with a control range from 0 to 999.
[0056] For example, the power plant number of a power plant is 08, the unit number is 02, the target issued is 0, and it switches from power generation to shutdown. Then the code of C is 3, and the control target code issued is 08023000.
[0057] Through this method of sending coded control targets, the pumped-storage power plant receives and analyzes the control targets and performs safety verification on whether they are consistent with the operating conditions of the pumped-storage units, ensuring that the control targets sent by the master station are safe and reliable.
[0058] When the power grid is running smoothly, control instructions are issued based on the power generation plan of the pumped storage unit. The control steps are to first obtain the power generation plan value of the pumped storage unit, and then verify the validity of the power generation plan value of the unit, including data quality bit verification and data rationality verification; then determine the required operating condition conversion state based on the power generation plan value of the unit and verify the operating condition conversion state. If the operating condition conversion target verification passes, the pumped storage unit's allowed operating condition conversion target verification will continue. If the verification passes, the power generation plan control target of the pumped storage unit is allowed to be issued.
[0059] (5) After the pumped storage unit model is established in the AGC, the AGC periodically (for example, once a minute) obtains the planned power generation value of the pumped storage unit, and performs safety verification and status judgment on the power generation plan based on the planned power generation value of the pumped storage unit. The process is as follows:
[0060] (51) First, obtain the power generation plan value of the pumped storage unit;
[0061] (52) The power generation plan value of the unit is then verified for validity, including data quality bit verification and data rationality verification; if the data quality bit is abnormal or the data exceeds a reasonable range, the planned value will be judged to be abnormal.
[0062] (53) The operating state conversion state to be performed is determined according to the power generation plan value of the unit. For example, if the power generation plan value is 0, then the shutdown operating state conversion is to be performed. If the power generation plan value is a positive number, then the forward power generation operating state conversion is to be performed. If the power generation plan value is a negative number, then the pumping operating state conversion is to be performed.
[0063] (6) After completing the verification of the power generation plan and the operating condition conversion status of the pumped storage unit, continue to verify the operating condition conversion status:
[0064] (61) Determine the current operating condition of the pumped storage unit, which is determined by the actual output of the pumped storage unit and the real-time operating condition of the pumped storage unit. For example, if the actual output of the pumped storage unit is greater than 0, and the operating condition of the pumped storage unit is power generation, then the master station determines that the unit is currently in the power generation condition;
[0065] (62) Determine whether to allow the next operating condition conversion in combination with the operating condition conversion target of the power generation plan. For example, if the pumped storage unit is currently in the power generation condition, and if the operating condition conversion of the power generation plan is to pump water, then the operating condition conversion command will be invalid, and the control target will be refused to be executed;
[0066] (63) If the operating condition conversion target verification is passed, the pumped storage unit's permitted operating condition conversion status verification will be continued. If the verification is passed, the power generation plan control target of the pumped storage unit will be allowed to be issued.
[0067] (7) If the power generation plan control target of the pumped storage unit is normal and the safety check in step (6) is passed, the control target code of the pumped storage unit can be issued.
[0068] (8) When the power grid is operating normally, the AGC uses steps (5) to (7) to periodically send the power generation plan control target to the pumped storage power plant. When a large power disturbance event such as a DC fault lockout occurs in the power grid, the current power generation plan target value can be directly corrected and converted to a frequency emergency control target.
[0069] When a large power disturbance event such as a DC fault lockout occurs in the power grid, the direction and amount of the disturbance fault in the power grid are first determined using equations (1 to (3), and then the disturbance amount is allocated to the corresponding pumped storage unit according to step (9). Finally, the emergency control target is sent to the pumped storage unit through coding for execution.
[0070] (81) First, the AGC monitors the ACE and grid frequency of the grid control area in real time.
[0071] The real-time value of ACE calculated by AGC in real time satisfies the requirement of formula (1:
[0072] ACE<-1*K*|ΔP|(1wherein: ACE is the real-time regional control deviation of the control area, K is the correction coefficient, which is a positive number less than 1, and |ΔP is the power loss threshold.
[0073] Grid frequency deviation:
[0074] |Δf|>|Δfmax|(2
[0075] Δf is the real-time frequency deviation of the power grid, Δf max is the frequency deviation safety threshold.
[0076] and:
[0077] Δf×ACE>0(3If all the above three criteria are met, it is determined that a large power disturbance fault occurs in the power grid, and the power disturbance amount of the power grid is ACE.
[0078] (9) After a large power disturbance fault occurs in the power grid through step (8), the automatic control function of the AGC pumped storage unit is immediately started, and the control steps are as follows:
[0079] (91) First determine the disturbance amount and disturbance direction. If ACE is positive, the grid has excess power and needs to reduce output. If ACE is negative, the grid lacks a lot of power and the unit needs to increase output quickly.
[0080] (92) If ACE is negative, all the units that are in the pumping state and allowed to be shut down are counted first, and then the regulation demand (ACE) is allocated to these units first; if there is still a surplus of ACE, the pumped storage units that are currently in the shutdown state and allowed to generate electricity are counted again, and the surplus is allocated to these units;
[0081] (93) If ACE is positive, the pumped storage units that are currently in power generation and allowed to shut down are counted first, and then the regulation demand (ACE) is allocated to these units first; if there is still ACE left after the allocation, the pumped storage units that are currently shut down and allowed to pump water are counted again, and the remaining part is allocated to these units;
[0082] (10) After the regulation demand is allocated in step (9), the current output of the pumped storage unit plus the allocated amount can be used to obtain the frequency emergency control target of the pumped storage unit, and then the emergency control target is sent to the pumped storage unit through coding.
[0083] The present invention has been described according to the preferred embodiments. It should be understood that the above embodiments do not limit the present invention in any form. Any technical solutions obtained by equivalent replacement or equivalent transformation fall within the protection scope of the present invention.
Claims
1. A method for automatically starting and stopping a pumped storage unit, characterized in that: include: When the power grid is running smoothly, the AGC master station of the power grid dispatching center verifies the power generation plan value of the pumped storage unit. After the verification is passed, the power generation plan value is sent to the pumped storage unit as the control target through the control target code; When a large power disturbance fault is detected in the power grid, the AGC master station first determines the disturbance direction and amount, then allocates the disturbance amount to the corresponding pumped storage unit, and finally sends the emergency control target to the pumped storage unit through the control target code; The control target code length is 8 bits, and the format is AABBCDDD; AA represents the pumped-storage power plant code, starting from 01, and supports a maximum of 99 pumped-storage power plants; BB represents the internal unit code of the pumped-storage power plant, starting from 01, and a pumped-storage power plant supports a maximum of 99 pumped-storage units; C represents the operating condition conversion mode; DDD represents the control target value, and the control range is from 000 to 999.
2. The automatic start-stop control method of a pumped storage unit according to claim 1, characterized in that: The AGC master station of the power grid dispatching center verifies the power generation plan value of the pumped storage unit. After the verification is passed, the power generation plan value is sent to the pumped storage unit as a control target through the control target code. The steps are as follows: The AGC master station obtains the planned power generation value of the pumped storage unit and verifies the validity of the planned power generation value; After the validity check is passed, the operating condition conversion state required is determined according to the power generation plan value and the operating condition conversion state is checked; After the operating condition conversion status verification is passed, the operating condition conversion target allowed by the pumped storage unit is verified according to the safety interlock control logic; After the operating condition conversion target is verified, the power generation plan value is sent to the pumped storage unit as the control target through the control target coding.
3. The automatic start-stop control method of a pumped storage unit according to claim 2, characterized in that: The operating condition conversion state that needs to be performed is determined based on the power generation plan value, specifically: if the power generation plan value is 0, it is necessary to enter the shutdown operating condition conversion; if the power generation plan value is a positive number, it is necessary to enter the forward power generation operating condition conversion; if the power generation plan value is a negative number, it is necessary to enter the pumping operating condition conversion.
4. The automatic start-stop control method of a pumped storage unit according to claim 2, characterized in that: The checking of the operating condition conversion state is specifically as follows: determining the current operating condition of the pumped storage unit according to the actual output of the pumped storage unit and the real-time operating condition sent by the pumped storage unit, and determining whether the next operating condition conversion is allowed in combination with the operating condition conversion state.
5. The automatic start-stop control method of a pumped storage unit according to claim 2, characterized in that: The safety lockout control logic includes: For pumped storage units whose AGC remote controllable signals are not put into use, no control instructions will be issued; When the AGC remote controllable signal is activated, if the pumped storage unit is in the shutdown state, the shutdown-to-power generation condition conversion is allowed only when the power generation permission signal is "yes", and the shutdown-to-pumping condition conversion is allowed only when the pumping permission state is "yes"; if the pumped storage unit is in the power generation state, the power generation-to-shutdown state is allowed only when the shutdown permission signal is "yes"; if the pumping unit is in the pumping state, the pumping-to-shutdown state is allowed only when the shutdown permission signal is "yes", and the pumping-to-pumping phase adjustment state is allowed only when the pumping phase adjustment state is "yes".
6. The automatic start-stop control method of a pumped storage unit according to claim 1, characterized in that: The implementation steps for monitoring the power grid for high power disturbance faults are as follows: First, the AGC master station monitors the ACE and grid frequency in the grid control area in real time. The real-time value of ACE calculated by AGC in real time satisfies the requirements of formula (1): ACE<-1*K*|ΔP| (1) Where: ACE is the real-time regional control deviation of the control area, K is the correction coefficient, which is a positive number less than 1, and |ΔP is the power loss threshold; Grid frequency deviation: |Δf|>|Δf max | (2)Δf is the real-time frequency deviation of the power grid, Δf max is the frequency deviation safety threshold. and: Δf×ACE>0 (3) If the above three criteria are all met, it is determined that a large power disturbance fault occurs in the power grid, and the power disturbance amount of the power grid is ACE.
7. The automatic start-stop control method of a pumped storage unit according to claim 6, characterized in that: The AGC master station first determines the disturbance direction and disturbance amount, then allocates the disturbance amount to the corresponding pumped storage unit, and finally sends the emergency control target to the pumped storage unit through coding. The specific implementation steps are as follows: First determine the disturbance amount ACE and disturbance direction. If ACE is positive, the grid has excess power and needs to reduce output. If ACE is negative, the grid lacks a lot of power and the unit needs to increase output quickly. If ACE is negative, ACE will be allocated to all units that are in pumping state and allowed to be shut down first; if there is still ACE left after allocation, the remaining part will be allocated to the pumped storage units that are currently in shutdown state and allowed to generate electricity; If ACE is positive, ACE is allocated to the pumped storage units that are currently in power generation and allowed to shut down first; if there is still ACE left after allocation, the remaining ACE is allocated to the pumped storage units that are currently shut down and allowed to pump water; After the ACE allocation is completed, the current output of the pumped storage unit is added to the allocated amount to obtain the emergency control target of the pumped storage unit, and then the emergency control target is sent to the pumped storage unit through coding.
8. The automatic start-stop control method of a pumped storage unit according to claim 1, characterized in that: It also includes establishing a pumped storage unit control model in the provincial dispatching AGC, and setting the pumped storage unit control model as follows: Set basic parameters, including the name of the pumped-storage power plant, the name of the pumped-storage unit, the installed capacity of the pumped-storage unit, the number of the pumped-storage unit, the actual output of the pumped-storage unit, the power generation plan of the pumped-storage unit, and the remote control signal of the pumped-storage unit; Anti-error parameters are set, including the current operating state of the pumped-storage unit, the allowed operating state conversion state of the pumped-storage unit, and the prohibited operation state of the pumped-storage unit; the current operating state of the pumped-storage unit includes shutdown, power generation, pumping, pumping phase adjustment, and power generation phase adjustment; the allowed operating state conversion state of the pumped-storage unit includes shutdown allowed, power generation allowed, pumping phase adjustment allowed, and power generation phase adjustment allowed; the prohibited operation state of the pumped-storage unit includes prohibition of increasing output and prohibition of reducing output.
9. An electronic device, characterized in that: The invention comprises a memory, a processor and a computer program stored in the memory and executable on the processor. When the processor executes the computer program, the automatic start-stop control method for a pumped storage unit as described in any one of claims 1 to 8 is implemented.
10. A non-transitory computer-readable storage medium having a computer program stored thereon, wherein when the computer program is executed by a processor, the method for automatically starting and stopping a pumped storage unit according to any one of claims 1 to 8 is implemented.