Loss resource prediction method and device for nuclear facility decommissioning, equipment and storage medium
By decomposing the target scheme information of the nuclear facility's decommissioning into sub-scheme data and automatically obtaining the execution loss resource items, combining it with the solution-level information, the problem of time and uncertainty of manual input data in the existing technology is solved, and the decommissioning of the nuclear facility is achieved Automation and high accuracy of loss resource prediction.
Patent Information
- Application Number
- CN202410878647.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-02
- Publication Date
- 2024-11-29
AI Technical Summary
In the prior art, the loss resource prediction of nuclear facilities decommissioning requires manual input of large amounts of data, which consumes a lot of manpower and is difficult to determine part of the data, affecting the accuracy of the prediction.
By decomposing the target scheme information into sub-scheme data, and automatically obtaining the execution loss resource items of the sub-scheme data, using multiple execution loss resource items to predict each sub-scheme data, and finally, based on the scheme level information and level correlation information, the Multiple target loss resource prediction data combine to realize loss resource prediction for nuclear facilities decommissioning.
It realizes the automation of nuclear facility decommissioning loss resource prediction, saves manpower, improves the accuracy and efficiency of prediction, and reduces the repetition of manual calculations.
Smart Images

Figure CN119047994A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of nuclear power plant facilities, and in particular to a method and apparatus, equipment and storage medium for predicting loss resources during decommissioning of nuclear facilities. Background Art
[0002] The decommissioning of nuclear facilities is characterized by a long implementation period, great difficulty in implementation, and many unforeseen factors. In addition, a large amount of resource loss will occur during the implementation process of nuclear facility decommissioning. Therefore, it is necessary to predict the loss resources of nuclear facility decommissioning before decommissioning the nuclear facilities, so as to adjust the operational steps of nuclear facility decommissioning according to the predicted loss resources.
[0003] In the related art, the loss resource prediction of nuclear facility decommissioning is mainly achieved by manually inputting various indicators, loss resource items and loss resource prediction algorithms involved in nuclear facility decommissioning, and then summarizing the loss resources generated by nuclear facility decommissioning step by step from bottom to top to obtain the resource loss prediction data for the entire nuclear facility decommissioning. However, the entire process requires manual input of a large amount of data, which not only consumes a lot of manpower, but also makes some data difficult to determine, affecting the accuracy of the loss resource prediction for nuclear facility decommissioning. Therefore, how to reduce manpower and accurately realize the loss resource prediction for nuclear facility decommissioning has become a technical problem that needs to be solved urgently. Summary of the invention
[0004] The main purpose of the embodiments of the present application is to propose a method and device, equipment and storage medium for predicting loss resources for decommissioning of nuclear facilities, aiming to reduce manpower and accurately realize the prediction of loss resources for decommissioning of nuclear facilities.
[0005] To achieve the above-mentioned purpose, a first aspect of an embodiment of the present application proposes a method for predicting loss resources for decommissioning a nuclear facility, the method comprising:
[0006] Obtain information on target options for decommissioning nuclear facilities;
[0007] Decomposing the target solution information to obtain a plurality of sub-solution data and solution level information and level association information of each of the sub-solution data; wherein the sub-solution data is used to characterize the minimum execution link of the decommissioning of the nuclear facility;
[0008] Obtaining a loss resource item for executing the sub-scheme data, and obtaining a plurality of execution loss resource items;
[0009] Performing resource loss prediction on each of the sub-scheme data based on the plurality of execution resource loss items to obtain target resource loss prediction data;
[0010] The target loss resource prediction data of a plurality of the sub-scheme data are combined according to the scheme level information and the level association information to obtain the total loss resource prediction data of the target scheme information.
[0011] In some embodiments, the decomposing the target solution information to obtain a plurality of sub-solution data and solution level information and level association information of each of the sub-solution data includes:
[0012] Splitting the target solution information to obtain a plurality of sub-solution data;
[0013] Acquire hierarchical relationship information between the plurality of sub-scheme data;
[0014] Determine the level association information of each of the sub-scheme data based on the hierarchical relationship information;
[0015] Obtaining the category of each sub-scheme data to obtain the sub-scheme category;
[0016] The sub-scheme data are graded according to the sub-scheme categories and the level association information to obtain the scheme level information of each sub-scheme data.
[0017] In some embodiments, the acquiring of the loss resource items of executing the sub-scheme data to obtain a plurality of execution loss resource items includes:
[0018] Obtaining the sub-scheme category of the sub-scheme data, selecting the target scheme execution-related parameters from the preset candidate scheme execution-related parameters based on the sub-scheme category, and simulating the sub-scheme data according to the target scheme execution-related parameters to obtain a plurality of the execution loss resource items; wherein the target scheme execution-related parameters are used as parameters for simulating the minimum execution link of the nuclear facility decommissioning;
[0019] or,
[0020] Based on the target scheme execution associated parameters, scheme associated parameter prompt information is generated, and parameter loss resource items fed back to the scheme associated parameter prompt information are received, and a plurality of execution loss resource items are generated based on the target scheme execution associated parameters and the parameter loss resource items.
[0021] In some embodiments, performing loss resource prediction on each of the sub-scheme data based on the plurality of execution loss resource items to obtain target loss resource prediction data includes:
[0022] Obtain sub-scheme information of the sub-scheme data;
[0023] Filtering out a selected solution resource loss prediction model from preset candidate solution resource loss prediction models according to the sub-solution information;
[0024] The target loss resource prediction data is obtained by performing loss resource prediction on the sub-scheme data through the selected scheme loss resource prediction model and the plurality of execution loss resource items.
[0025] In some embodiments, the execution loss resource items include: execution loss amount, execution correlation coefficient, execution time and execution unit price; the loss resource prediction of the sub-scheme data using the selected scheme loss resource prediction model and the plurality of execution loss resource items to obtain the target loss resource prediction data includes:
[0026] The selected solution loss resource prediction model is used to predict the execution loss amount, the execution correlation coefficient, the execution time and the execution unit price to obtain the target loss resource prediction data.
[0027] In some embodiments, after performing loss resource prediction on each of the sub-scheme data based on the plurality of execution loss resource items to obtain target loss resource prediction data, the method further includes:
[0028] extracting a correction coefficient from a preset correction database according to the sub-scheme category;
[0029] Correcting the target loss resource prediction data according to the correction coefficient to obtain updated loss resource prediction data;
[0030] The total resource loss prediction data is updated according to the updated resource loss prediction data to obtain updated resource prediction data of the target solution information.
[0031] In some embodiments, after combining the target loss resource prediction data of the plurality of sub-scheme data according to the scheme level information and the level association information to obtain the total loss resource prediction data of the target scheme information, the method includes:
[0032] Comparing the total resource loss prediction data with the preset expected resource loss data to obtain an evaluation comparison result;
[0033] If the evaluation and comparison result is that the total resource loss prediction data is greater than the expected resource loss data, the target solution information is adjusted according to the total resource loss prediction data to obtain updated solution data.
[0034] To achieve the above-mentioned purpose, a second aspect of an embodiment of the present application provides a device for predicting loss resources for decommissioning a nuclear facility, the device comprising:
[0035] A scheme acquisition module is used to obtain target scheme information for decommissioning nuclear facilities;
[0036] A decomposition module, used for decomposing the target solution information to obtain a plurality of sub-solution data and solution level information and level association information of each of the sub-solution data; wherein the sub-solution data is used to characterize the minimum execution link of the decommissioning of the nuclear facility;
[0037] A resource item acquisition module, used to acquire the loss resource items of executing the sub-scheme data, and obtain multiple execution loss resource items;
[0038] A loss resource prediction module, used for performing loss resource prediction on each of the sub-scheme data based on the plurality of execution loss resource items to obtain target loss resource prediction data;
[0039] The loss resource combination module is used to combine the target loss resource prediction data of multiple sub-scheme data according to the scheme level information and the level association information to obtain the total loss resource prediction data of the target scheme information.
[0040] To achieve the above-mentioned purpose, the third aspect of an embodiment of the present application proposes a computer device, which includes a memory and a processor, the memory stores a computer program, and when the processor executes the computer program, it implements the loss resource prediction method for nuclear facility decommissioning described in the first aspect.
[0041] To achieve the above-mentioned purpose, the fourth aspect of an embodiment of the present application proposes a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the method described in the first aspect is implemented.
[0042] The loss resource prediction method, device, equipment and storage medium for decommissioning of nuclear facilities proposed in the present application decompose the target scheme information into sub-scheme data, and then automatically obtain the execution loss resource items of the sub-scheme data, so that the acquisition of the execution loss resource items is automated, without the need for manual input, thus saving manpower. At the same time, after determining the execution loss resource items, the sub-scheme data is subjected to loss resource prediction according to the execution loss resource items to obtain the target loss resource prediction data, and finally, based on the scheme level information and level association information, multiple target loss resource prediction data are combined to obtain the total loss resource prediction data of the entire target scheme information, so that the loss resource prediction of the target scheme information is simpler and more accurate, and the situation of repeated calculations in manual calculations is reduced, thereby improving the efficiency of loss resource prediction in the process of decommissioning nuclear facilities. BRIEF DESCRIPTION OF THE DRAWINGS
[0043] Figure 1 is a flow chart of a method for predicting loss resources for nuclear facility decommissioning provided in an embodiment of the present application;
[0044] Figure 2 yes Figure 1Flow chart of step S102 in FIG.
[0045] Figure 3 It is a schematic diagram of target solution information decomposition in the loss resource prediction method for nuclear facility decommissioning provided in an embodiment of the present application;
[0046] Figure 4 It is a system framework diagram of a nuclear facility decommissioning loss resource prediction system in a nuclear facility decommissioning loss resource prediction method provided in an embodiment of the present application;
[0047] Figure 5 yes Figure 1 Flow chart of step S103 in FIG.
[0048] Figure 6 yes Figure 1 Another flow chart of step S103 in FIG. 1 ;
[0049] Figure 7 yes Figure 1 Flow chart of step S104 in FIG.
[0050] Figure 8 is a flow chart of a method for predicting loss resources for nuclear facility decommissioning provided by another embodiment of the present application;
[0051] Fig. 9 is a flow chart of a method for predicting loss resources for nuclear facility decommissioning provided by another embodiment of the present application;
[0052] Fig.10 It is a schematic diagram of the structure of a loss resource prediction device for nuclear facility decommissioning provided in an embodiment of the present application;
[0053] Fig.11 It is a schematic diagram of the hardware structure of the computer device provided in the embodiment of the present application. DETAILED DESCRIPTION
[0054] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0055] It should be noted that, although the functional modules are divided in the device schematic diagram and the logical order is shown in the flowchart, in some cases, the steps shown or described may be performed in a different order than the module division in the device or the order in the flowchart. The terms "first", "second", etc. in the specification, claims and the above drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence.
[0056] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which this application belongs. The terms used herein are only for the purpose of describing the embodiments of this application and are not intended to limit this application.
[0057] First, some nouns involved in this application are analyzed:
[0058] Nuclear facility decommissioning: It is an action taken to take full account of the health and safety of workers and the public and environmental protection after a nuclear facility has expired or ceased service for other reasons. The ultimate goal of decommissioning is to achieve unrestricted opening and use of the site. There are several methods for decommissioning nuclear facilities, such as immediate demolition, delayed demolition, and on-site burial.
[0059] Source survey for nuclear facility decommissioning refers to the investigation and assessment of the various sources, factors, steps and possible impacts involved in the decommissioning process of nuclear facilities.
[0060] Demolition and dismantling: refers to the process of permanently shutting down and dismantling nuclear facilities (such as nuclear power plants, nuclear fuel processing plants, etc.).
[0061] Waste treatment during nuclear facility decommissioning: Waste treatment is particularly important during the dismantling of nuclear facilities because it may contain radioactive waste and other hazardous substances. The general steps for waste treatment during the dismantling of nuclear facilities are: 1. Identification and classification; 2. Separation and treatment; 3. Disposal; 4. Monitoring and control; 5. Recording and reporting.
[0062] Nuclear facility decommissioning has the characteristics of long cycle, high difficulty, uncertainty and many unpredictable factors, and requires a lot of manpower and funds in the decommissioning process. Therefore, before decommissioning begins, it is necessary to predict the loss resources of the nuclear facility decommissioning plan to analyze whether the current nuclear facility decommissioning plan is in line with economic benefits, and adjust the nuclear facility decommissioning plan according to the predicted loss resources, so that the nuclear facility can be decommissioned efficiently and cost-savingly in accordance with the nuclear facility decommissioning plan in the later stage.
[0063] In the related art, there is a software for evaluating nuclear facility decommissioning plans, which uses the unit factor method to predict the loss resources of nuclear facility decommissioning plans, and manually inputs various indicators involved in the nuclear facility plan, defines resource loss items and resource loss calculation formulas, and automatically generates detailed reports of various execution links in the nuclear facility plan based on the manually input resource loss calculation formulas, various indicators and resource loss items. However, for different nuclear facility decommissioning plans, it is necessary to manually input various indicators, resource loss items and resource loss calculation formulas each time. If it is necessary to make loss resource predictions for multiple nuclear facility decommissioning plans, it will take a lot of manpower. Moreover, in the prediction of loss resources for nuclear facility decommissioning, some resource loss items in some nuclear facility plans are difficult to determine, which will affect the prediction accuracy of loss resources for nuclear facility decommissioning.
[0064] Based on this, the embodiments of the present application provide a method and device, equipment and storage medium for predicting loss resources for nuclear facility decommissioning, aiming to realize the automation of loss resource prediction for nuclear facility decommissioning, save manpower, and improve the accuracy of loss resource prediction for nuclear facility decommissioning.
[0065] The loss resource prediction method, device, equipment and storage medium for nuclear facility decommissioning provided in the embodiments of the present application are specifically illustrated through the following embodiments. First, the loss resource prediction method for nuclear facility decommissioning in the embodiments of the present application is described.
[0066] The embodiments of the present application can acquire and process relevant data based on artificial intelligence technology. Among them, artificial intelligence (AI) is the theory, method, technology and application system that uses digital computers or machines controlled by digital computers to simulate, extend and expand human intelligence, perceive the environment, acquire knowledge and use knowledge to obtain the best results.
[0067] AI basic technologies generally include sensors, dedicated AI chips, cloud computing, distributed storage, big data processing technology, operation / interaction systems, mechatronics, etc. AI software technologies mainly include computer vision technology, robotics technology, biometrics technology, speech processing technology, natural language processing technology, and machine learning / deep learning.
[0068] The loss resource prediction method for decommissioning a nuclear facility provided in an embodiment of the present application relates to the technical field of nuclear facilities in nuclear power plants. The loss resource prediction method for decommissioning a nuclear facility provided in an embodiment of the present application can be applied to a terminal, can be applied to a server side, or can be software running in a terminal or a server side. In some embodiments, the terminal can be a smart phone, a tablet computer, a laptop computer, a desktop computer, etc.; the server side can be configured as an independent physical server, or can be configured as a server cluster or a distributed system composed of multiple physical servers, or can be configured as a cloud server that provides basic cloud computing services such as cloud services, cloud databases, cloud computing, cloud functions, cloud storage, network services, cloud communications, middleware services, domain name services, security services, CDN, and big data and artificial intelligence platforms; the software can be an application of the loss resource prediction method for decommissioning a nuclear facility, etc., but is not limited to the above forms.
[0069] The present application can be used in many general or special computer system environments or configurations. For example: personal computers, server computers, handheld or portable devices, tablet devices, multiprocessor systems, microprocessor-based systems, set-top boxes, programmable consumer electronics, network PCs, minicomputers, mainframe computers, distributed computing environments including any of the above systems or devices, etc. The present application can be described in the general context of computer-executable instructions executed by a computer, such as program modules. Generally, program modules include routines, programs, objects, components, data structures, etc. that perform specific tasks or implement specific abstract data types. The present application can also be practiced in distributed computing environments, in which tasks are performed by remote processing devices connected through a communication network. In a distributed computing environment, program modules can be located in local and remote computer storage media including storage devices.
[0070] Figure 1 is an optional flow chart of a method for predicting lost resources for decommissioning a nuclear facility provided in an embodiment of the present application. Figure 1 The method may include but is not limited to steps S101 to S105.
[0071] Step S101, obtaining target plan information for decommissioning a nuclear facility;
[0072] Step S102, decomposing the target solution information to obtain a plurality of sub-solution data and solution level information and level association information of each sub-solution data; wherein the sub-solution data is used to characterize the minimum execution link of the decommissioning of the nuclear facility;
[0073] Step S103, obtaining loss resource items of the execution sub-scheme data, and obtaining a plurality of execution loss resource items;
[0074] Step S104, performing resource loss prediction on each sub-scheme data based on multiple execution resource loss items to obtain target resource loss prediction data;
[0075] Step S105 , combining the target loss resource prediction data of multiple sub-scheme data according to the scheme level information and the level association information to obtain the total loss resource prediction data of the target scheme information.
[0076] In the steps S101 to S105 shown in the embodiment of the present application, the target scheme information is decomposed into multiple sub-scheme data, and the scheme level information and level association information of each sub-scheme data are determined, and the execution loss resource item is obtained by obtaining the loss resource item of the sub-scheme data, so as to predict the loss resource of each sub-scheme data according to the multiple execution loss resource items to obtain the target loss resource prediction data, and finally, the multiple target loss resource prediction data are combined into the total loss resource prediction data of the target scheme information according to the scheme level information. Among them, the sub-scheme data is used to characterize the minimum execution link of the decommissioning of nuclear facilities. Therefore, by splitting the entire target scheme of the decommissioning of the entire nuclear facility into multiple sub-scheme data, and collecting the execution loss resource items involved in each sub-scheme data, and then calculating the loss resources generated by each sub-scheme data, and then combining all the loss resources according to the level of the sub-scheme data to determine the resource data consumed by the decommissioning of the nuclear facility, the loss resource prediction of the decommissioning of the nuclear facility does not need to be manually input with a large amount of data and loss resource calculation formula, and the loss resource prediction of the decommissioning of the nuclear facility is automated and accurate, reducing the manpower of the loss resource prediction of the decommissioning of the nuclear facility, and improving the prediction accuracy of the loss resource of the decommissioning of the nuclear facility.
[0077] In step S101 of some embodiments, the target solution information records the entire operation process of nuclear facility decommissioning and the minimum execution links required for each process. Specifically, the entire operation process of nuclear facility decommissioning can be divided into stages, each stage corresponds to a different process link, and each process link will set multiple minimum execution links for nuclear facility decommissioning.
[0078] It should be noted that if Figure 4As shown, the loss resource prediction method for nuclear facility decommissioning is applied to the loss resource prediction system for nuclear facility decommissioning, and the loss resource prediction system for nuclear facility decommissioning includes a scheme editing module, a loss resource prediction module, a three-dimensional simulation system module and a database module. Among them, the database module is used to support the storage of model data such as models, tool models, and three-dimensional dose fields for the simulation of nuclear facility decommissioning scenarios. In addition, the database module also stores execution loss resource items related to the execution of nuclear facility decommissioning, as well as the evaluation formula for evaluating each sub-scheme data and the correction coefficient of the execution loss resource items. The three-dimensional simulation system module is called when the minimum execution link in the nuclear facility decommissioning is simulated, and configures the relevant configuration data required for the simulation process of the minimum execution link in the nuclear facility decommissioning.
[0079] See also Figure 2 In some embodiments, step S102 may include but is not limited to steps S201 to S205:
[0080] Step S201, splitting the target solution information to obtain multiple sub-solution data;
[0081] Step S202, obtaining hierarchical relationship information between multiple sub-scheme data;
[0082] Step S203, determining level association information of each sub-scheme data based on the hierarchical relationship information;
[0083] Step S204, obtaining the category of each sub-scheme data to obtain the sub-scheme category;
[0084] Step S205 , performing classification processing on the sub-scheme data according to the sub-scheme category and level association information to obtain the scheme level information of each sub-scheme data.
[0085] In some embodiments, in step S201 to step S202, the target plan information is split in the retirement plan editing module, that is, it is preliminarily split according to the retirement execution stage in the target plan information, and then further split according to the execution process in each stage until it is split to the smallest minimum execution link to obtain sub-plan data. In the process of splitting, the sub-plan data will record the hierarchical relationship information between each sub-plan data, so as to determine the level association information of each sub-plan data according to the hierarchical relationship information. Specifically, Figure 3As shown, the decommissioning of the target nuclear facility needs to go through four stages. The first stage includes research and development, pre-decommissioning activities, equipment closure activities, site infrastructure and operation. The second stage includes the safe storage and routine dismantling and destruction of spent fuel. The third stage includes dismantling activities, waste treatment, storage and disposal in the controlled area. The fourth stage includes additional activities and miscellaneous expenses for site restoration, safe sealing or burial. Among them, the execution process within each decommissioning execution stage can be divided into levels to divide it into the smallest execution links. In this embodiment, there are 18 minimum execution links for the decommissioning of nuclear facilities, and the 18 minimum execution links are ①, source investigation; ②, cleaning and decontamination; ③, dismantling and disintegration; ④, waste disposal; ⑤, waste preparation and transportation; ⑥, system or facility transformation; ⑦, environmental restoration; ⑧, environmental remediation; ⑨, personnel employment; ⑩, equipment procurement; Material procurement; project management; Project benefits; Preliminary work preparation; Engineering design and technical services; Supervision and final acceptance; Other engineering activities; Unforeseen activities. After the nuclear facility decommissioning plan is split into minimum execution links, it is necessary to determine the level association information between the minimum execution links, so as to determine the association between different minimum execution links based on the level association information. For example, in the pre-decommissioning activity link, the minimum execution links of the same level of association calculation include ①, ③, and ⑤, and the minimum execution link numbered ① is the source item investigation, the minimum execution link numbered ③ is the dismantling and disintegration, and the minimum execution link numbered ⑤ is the waste preparation and transportation. It can be seen that there may be multiple associated minimum execution links at the same level to implement the execution of this level in parallel.
[0086] In step S204 of some embodiments, the sub-scheme category of each sub-scheme data is obtained, that is, the task activity type that characterizes the execution of the sub-scheme data. It should be noted that the process of splitting the target scheme information in the retirement scheme editing module is split level by level according to the task activity type, and each level is subdivided downward into lower-level execution links according to the task activity type and level association information, until it is divided into the smallest execution link. Figure 4As shown, in the decommissioning plan editing module, the nuclear facility decommissioning plan is decomposed, first divided into first-level task A and first-level task B according to the activity task type, and then further divided, and the first-level task B is divided into the minimum execution link b, and the first-level task A can also be divided into the second-level task A1, and the second-level task A1 is further divided into the minimum execution link a and the minimum execution link c. Therefore, by dividing the target plan information into multiple minimum execution links in the decommissioning plan editing module in advance, and determining the execution level information and level association information of each minimum execution link. For example, the link level information of the minimum execution link c is level two, and the link level information of the minimum execution link b is level one. It should be noted that the link level information and level association information of each minimum execution link can be used for calculation level by level when the final resource loss combination is combined to obtain accurate total loss resource prediction data.
[0087] In steps S201 to S205 shown in this embodiment, the target scheme information is split into multiple sub-scheme data, and the scheme level information and level association information of each sub-scheme data are determined, so that the subsequent calculation of the total loss resource prediction data of the target scheme information is more convenient.
[0088] In step S103 of some embodiments, the execution loss resource item of the sub-scheme data characterizes which resource losses need to be generated during the execution of the sub-scheme data, so as to define the various resource losses generated by the sub-scheme data as execution loss resource items. It should be noted that the execution loss resource items of each sub-scheme data can be obtained by simulation or by manual input. Among them, the selection step of determining the execution loss resource items by simulation and manual input is to first obtain the calculation preference information of each sub-scheme data, and select the loss resource item calculation method in the simulation and manual input methods according to the calculation preference information. It should be noted that if the calculation preference information of the sub-scheme data is the simulation method, the simulation method is selected as the calculation method of the loss resource item; if the calculation preference information is the manual input method, the manual input method is selected as the calculation method of the loss resource item. Specifically, the simulation needs to rely on a three-dimensional simulation system module, and the three-dimensional simulation system module is equipped with simulation functions such as assembly, layout, cutting, decontamination, dismantling, preparation, sorting, transportation and lifting. The three-dimensional simulation system module can be used to simulate the resource loss that will be generated in the execution process of the sub-scheme data, that is, the resource loss that will be generated by the implementation of the minimum execution link, so as to determine the execution loss resource items.
[0089] See also Figure 5 In some embodiments, if simulation calculation is used to determine multiple execution loss resource items, step S103 may be step S501:
[0090] Step S501, obtain the sub-scheme category of the sub-scheme data, screen out the target scheme execution associated parameters from the preset candidate scheme execution associated parameters based on the sub-scheme category, and simulate the sub-scheme data according to the target scheme execution associated parameters to obtain multiple execution loss resource items; wherein the target scheme execution associated parameters are used as parameters for simulating the minimum execution link of the decommissioning of the nuclear facility.
[0091] In step S501 of some embodiments, the candidate solution execution associated parameters are simulation configuration parameters involved in the simulation of the sub-solution data, and also belong to the associated parameters of the sub-solution data execution. Specifically, the candidate solution execution associated parameters can be data such as tools, equipment, materials, and manpower involved in executing the sub-solution data. It should be noted that different sub-solution categories correspond to different candidate solution execution associated parameters, so the candidate solution execution associated parameters corresponding to the sub-solution category of the sub-solution data are used as the target solution execution associated parameters.
[0092] By inputting the target scheme execution associated parameters into the three-dimensional simulation system module, the sub-scheme data is simulated through the three-dimensional simulation system module to output the resource losses that will be generated during the execution of the sub-scheme data, so as to obtain the execution loss resource items. Specifically, the execution loss resource items of the sub-scheme data are the resource losses generated when executing the tools, equipment, materials, manpower and other data involved in the minimum execution link of the nuclear facility decommissioning process.
[0093] In step S501 shown in the present embodiment, a three-dimensional simulation system module is used to simulate the sub-scheme data based on the target scheme execution associated parameters to simulate which resource losses will be generated during the execution of the sub-scheme data to obtain execution loss resource items, thereby automating the acquisition of execution loss resource items and eliminating the need for manual input, thus saving manpower.
[0094] It should be noted that after simulation, if there are execution loss resource items that cannot be simulated, the execution loss resource items can be improved by manual input.
[0095] See also Figure 6 In some embodiments, step S103 may further include step S601:
[0096] Step S601, generating scheme-associated parameter prompt information based on target scheme execution-associated parameters, receiving parameter loss resource items fed back to the scheme-associated parameter prompt information, and generating multiple execution loss resource items based on the target scheme execution-associated parameters and the parameter loss resource items.
[0097] In step S601 of some embodiments, the scheme-associated parameter prompt information is used to display the target scheme execution-associated parameters, so that the user can know through the scheme-associated parameter prompt information that the execution loss resource items required for the implementation process of the sub-scheme data need to be manually input, that is, input the data of tools, equipment, materials, manpower, etc. involved in the minimum execution link in the process of decommissioning nuclear facilities, so as to obtain multiple execution loss resource items. The parameter loss resource item is the content input by the user according to the scheme-associated parameter prompt information, and corresponds to each input item of the target scheme execution-associated parameters, so by matching the target scheme execution-associated parameters with the corresponding parameter loss resource items, it is possible to obtain which resource data needs to be lost when executing the sub-scheme data to obtain multiple execution loss resource items.
[0098] In step S601 shown in the present embodiment, the user is prompted to manually input parameter items by using scheme-associated parameter prompt information, and the parameter loss resource items fed back by the user are received. Then, a match is made based on the parameter loss resource items and the target scheme execution-associated parameters to determine the execution loss resource items required for the execution of the sub-scheme data, thereby achieving a complete supplement of the execution loss resource items and improving the accuracy of the loss resource prediction for the decommissioning of nuclear facilities.
[0099] See also Figure 7 In some embodiments, step S104 may include but is not limited to steps S701 to S703:
[0100] Step S701, obtaining sub-scheme information of sub-scheme data;
[0101] Step S702, selecting a selected solution resource loss prediction model from preset candidate solution resource loss prediction models according to the sub-solution information;
[0102] Step S703, performing loss resource prediction on the sub-scheme data by selecting a scheme loss resource prediction model and multiple execution loss resource items to obtain target loss resource prediction data.
[0103] In step S701 to step S702 of some embodiments, the sub-scheme information represents the information of the sub-scheme data, and the sub-scheme information can be used to know which resource items are needed to complete the sub-scheme data. Figure 3As shown, there are 18 minimum execution links for the decommissioning of the target nuclear facility, that is, there are 18 sub-scheme data, namely source item investigation, cleaning and decontamination, dismantling and dismantling, waste disposal, waste preparation and transportation, system or facility transformation, environmental restoration, environmental remediation, personnel employment, equipment procurement, material procurement, project management, project benefits, preliminary work preparation, engineering design and technical services, supervision and completion acceptance, other engineering activities and unforeseen activities, and the loss resource data of each minimum execution link need to involve complex calculations of the execution loss resource items. Therefore, this embodiment selects the selected scheme loss resource prediction model from the candidate scheme loss resource prediction model based on the sub-scheme information, and the selected scheme loss resource prediction model is a model for evaluating the minimum execution link to realize the associated evaluation of the sub-scheme data. Specifically, the candidate scheme loss resource prediction model is stored in the database module, specifically a resource calculation formula, which is used to calculate the resource loss caused by the implementation of the minimum execution link.
[0104] In some embodiments, when the target loss resource prediction data of the sub-scheme data is determined as fixed evaluation data according to the sub-scheme information, it is not necessary to perform resource loss prediction on the sub-scheme data by selecting a scheme loss resource prediction model.
[0105] In step S703 of some embodiments, resource loss prediction is performed on the sub-scheme data by selecting a scheme loss resource prediction model and multiple loss resource items. Specifically, based on the unknowns in the selected scheme loss resource prediction model, and the resource data items include resource loss categories and resource loss values, the resource loss values corresponding to each resource loss category are substituted into the unknowns in the selected scheme loss resource prediction model to obtain the target loss resource prediction data of the sub-scheme data, so that the calculation of the target loss resource prediction data is simple.
[0106] That is, in some embodiments, the execution loss resource items include: execution loss amount, execution correlation coefficient, execution time and execution unit price; by selecting a solution loss resource prediction model and multiple execution loss resource items, the sub-solution data is subjected to loss resource prediction to obtain the target loss resource prediction data, including:
[0107] By selecting a solution loss resource prediction model, the execution loss amount, execution correlation coefficient, execution time and execution unit price are predicted to obtain the target loss resource prediction data.
[0108] It should be noted that the resource loss prediction model for the selected scheme is a resource loss calculation model corresponding to each sub-scheme data, that is, a cost calculation model for the execution of the minimum execution link. During the execution of the minimum execution link, the execution loss resource items involved are the equipment, manpower, materials, etc. consumed in the execution process of the minimum execution link, so the loss resource items include the execution loss amount, execution correlation coefficient, execution time and execution unit price. The execution loss amount is the material consumed when executing the minimum execution link, the execution correlation coefficient is the coefficient involved in the execution process, the execution time is the time consumed when executing the minimum execution link, and the execution unit price is the unit price of the consumed equipment, manpower and materials, etc.
[0109] Specifically, the sub-scheme data is the minimum execution link of the nuclear facility decommissioning process. If the minimum execution link is the source item survey, then the target loss resource prediction data is the source item survey fee, and the calculation of the source item survey fee can be to find out the fixed quotation of the source item survey in the pre-set fixed quotation table. In addition, the association calculation can be used, and the scheme loss resource prediction model selected in the association calculation is the calculation formula of the source item survey fee, and the calculation formula of the source item survey fee is source item survey fee = (source item survey working hours × labor unit price DIM × first time coefficient DIM × radiation protection coefficient DIM) + (equipment use time × second time coefficient DIM × rental unit price DIM) + (consumables × consumables unit price DIM). Among them, the source item survey working hours, labor unit price DIM, first time coefficient DIM, radiation protection coefficient DIM, equipment use time, second time coefficient DIM, rental unit price DIM, consumables, and consumables unit price DIM are multiple execution loss resources, that is, execution loss amount, execution correlation coefficient, execution time and execution unit price. Specifically, if the minimum execution link is the source item survey, the execution unit price is the labor unit price during the source item survey, the first time coefficient is the coefficient of the labor time spent on the source item survey, the radiation protection coefficient is the coefficient corresponding to the use of radiation protection equipment or protective clothing in the source item survey, the equipment use time is the time when the equipment is needed during the source item survey, the second time coefficient is the coefficient of the time when the equipment is used during the source item survey, the rental unit price is the unit price of equipment rental, the consumables are the amount of material consumption required in the source item survey process, and the consumables unit price is the unit price of consumables. Among them, the equipment and personnel selected for the source item survey are simulated by the three-dimensional simulation system module. Therefore, the execution loss resource items obtained by each simulation are input into the calculation formula of the source item survey fee to obtain the source item survey fee, so that the calculation operation of the source item survey fee is simple.
[0110] If the minimum execution link is dismantling, then the target loss resource prediction data is the dismantling cost, and the calculation of the dismantling cost can be done by finding the fixed quotation of dismantling in a pre-set fixed quotation table. In addition, an associated calculation can be used, in which the selected scheme loss resource prediction model is the calculation formula of the dismantling cost, and the calculation formula of the dismantling cost is dismantling cost = (dismantling man-hours × labor unit price DIM × first time coefficient DIM × radiation protection coefficient DIM) + (equipment use time × second time coefficient × rental unit price DIM) + (consumables × consumables unit price DIM). Among them, dismantling man-hours, labor unit price DIM, time coefficient DIM, radiation protection coefficient DIM, equipment use time, time coefficient DIM, rental unit price DIM, consumables, and unit price DIM are multiple execution loss resource items, and are obtained by simulating the equipment and personnel selected during dismantling through the three-dimensional simulation system module. Specifically, if the minimum execution link is dismantling and disintegration, the labor unit price is the labor unit price during dismantling and disintegration, the first time coefficient is the coefficient of the labor time spent on dismantling and disintegration, the radiation protection coefficient is the coefficient corresponding to the use of radiation protection equipment or protective clothing for dismantling and disintegration, the equipment use time is the time required for the equipment to be used during dismantling and disintegration, the second time coefficient is the coefficient of the time used for the equipment during dismantling and disintegration, the rental unit price is the unit price of equipment rental, the consumables are the amount of materials needed for the dismantling and disintegration process, and the consumables unit price is the unit price of consumables. Among them, compared with non-nuclear contaminated projects, nuclear contaminated projects need to consider the subsequent packaging and treatment of waste, so some parts have certain requirements for the demolition volume and size, and the impact of the working hours of the radiation environment operation team needs to be considered. The equipment use time and rental unit price are only for the case of renting equipment. If equipment is purchased, the relevant expenses will be included in the equipment procurement fee.
[0111] If the minimum execution link is waste treatment preparation, then the target loss resource prediction data is the waste treatment preparation fee, and the calculation of the waste treatment preparation fee can be to find out the fixed quotation of dismantling and dismantling in the pre-set fixed quotation table. In addition, the association calculation can be used, and the loss resource prediction model of the selected scheme in the association calculation is the calculation formula of the waste treatment preparation fee, and the calculation formula of the waste treatment preparation fee is waste treatment preparation fee = (dismantling operation hours × labor unit price DIM × first time coefficient DIM × radiation protection coefficient DIM) + (equipment use time × second time coefficient × rental unit price DIM) + [consumables (cement, additives) × consumables unit price DIM] + (number of various packaging containers × packaging unit price DIM). Among them, dismantling operation hours, labor unit price DIM, time coefficient DIM, radiation protection coefficient DIM, equipment use time, time coefficient DIM, rental unit price DIM, consumables, unit price DIM, and the number of various packaging containers are multiple execution loss resource items, and the processing and packaging costs of radioactive waste are closely related to the treatment process and methods. Therefore, the simulation system module is used to simulate the equipment, personnel, main material consumption (cement, additives, etc.) selected during waste treatment and preparation and the task execution process. Specifically, if the minimum execution link is waste treatment preparation, the labor unit price is the labor unit price during waste treatment preparation, the first time coefficient is the coefficient of the labor time spent during waste treatment preparation, the radiation protection coefficient is the coefficient corresponding to the use of radiation protection equipment or protective clothing for waste treatment preparation, the equipment use time is the time required for equipment to be used during waste treatment preparation, the second time coefficient is the coefficient of the time equipment is used during waste treatment preparation, the rental unit price is the unit price of equipment rental, the consumables are the amount of materials consumed during the dismantling process, specifically the amount of cement or additives consumed, the consumables unit price is the unit price of consumables, and the number of various packaging containers is the number of containers for waste treatment packaging. Among them, the equipment use time and rental unit price are only for the case of renting equipment. If the equipment is purchased, the relevant expenses will be included in the equipment procurement fee.
[0112] If the minimum execution link is waste disposal, then the target loss resource prediction data is the waste disposal fee, and the calculation of the waste disposal fee can be done by finding the fixed quotation of dismantling and disintegration in the pre-fixed quotation table. In addition, the associated calculation can be used, and the selected scheme loss resource prediction model in the associated calculation is the calculation formula of the waste disposal fee, and the calculation formula of the waste disposal fee is waste disposal fee = (number of waste packages × disposal site acceptance unit price DIM). Among them, the number of waste packages and the disposal site acceptance unit price DIM are multiple execution loss resource items, and the processing and packaging costs of radioactive waste are closely related to the processing technology and method. Therefore, the number and type of waste packages generated after preparation are simulated through the simulation system module, and the disposal cost calculation is carried out to obtain multiple execution loss resource items. Specifically, the number of waste packages is the number of waste packages generated during the waste disposal process, and the external site acceptance unit price is the unit price of each waste package received by the external site. It should be noted that the disposal cost of medium and low-level waste is estimated according to the waste acceptance unit price of the waste disposal site; the disposal cost of high-level waste is estimated with reference to historical experience. The disposal unit quotation is added when setting the basic properties of the waste container and can be modified when calculating the cost.
[0113] If the minimum execution link is project management, engineering design, supervision of completion acceptance and other management-related costs, such minimum execution link costs can be given based on the preset fixed quotation. In addition, the management cost = human input working hours × labor unit price DIM can be used for calculation.
[0114] If the minimum execution link is an unforeseeable link, then the target loss resource prediction data is an unforeseeable fee, and the calculation of the waste treatment preparation fee can be to find out the fixed quotation of the unforeseeable link in the pre-set fixed quotation table. The fixed unforeseeable fee is usually calculated according to 25% of the pre-set total cost of nuclear facility decommissioning in the early stage of the decommissioning project. In addition, the association calculation can be used, and the loss resource prediction model of the selected scheme in the association calculation is the calculation formula of the unforeseeable fee, and the unforeseeable fee is to use the Monte Carlo method and other methods to perform uncertainty analysis on the unforeseeable cost of the decommissioning project, which is not specifically described in this embodiment.
[0115] In steps S701 to S703 shown in this embodiment, a selected solution loss resource prediction model that meets the minimum execution link is selected, and the minimum execution link is evaluated through the selected solution loss resource prediction model and multiple execution loss resource items. This makes the evaluation operation of the minimum execution link automated, eliminates the need for manual calculations, and can efficiently output target loss resource prediction data.
[0116] In step S105 of some embodiments, the target loss resource prediction data of multiple sub-scheme data are combined according to the scheme level information and the level association information to obtain the total loss resource prediction data. Specifically, the target loss resource prediction data are combined level by level according to the scheme level information and the level association information. For example, Figure 4 As shown, the sub-scheme data a corresponding to the secondary task A1 and the target loss resource prediction data corresponding to the minimum execution link c are first combined into the secondary loss resource prediction data corresponding to the secondary task A1, and then the secondary loss resource prediction data and the target loss resource prediction data corresponding to the minimum execution link b are combined to form the total loss resource prediction data of the target scheme information. Therefore, the calculation operation of the total loss resource prediction data is simple, and the loss resource prediction data of tasks at different levels can be clearly understood, and it can be analyzed in detail which level of task has the greatest impact on the loss resource prediction data through the minimum execution link.
[0117] See also Figure 8 In some embodiments, after step S105, the method for predicting loss resources for decommissioning a nuclear facility may further include but is not limited to steps S801 to S803:
[0118] Step S801, extracting a correction coefficient from a preset correction database according to the sub-scheme category;
[0119] Step S802, correcting the target loss resource prediction data according to the correction coefficient to obtain updated loss resource prediction data;
[0120] Step S803, updating the total loss resource prediction data according to the updated loss resource prediction data to obtain updated resource prediction data of the target solution information.
[0121] It should be noted that when the three-dimensional simulation system module performs simulation, there may be errors in the output of multiple execution loss resource items, which makes it difficult to accurately characterize the resource losses of each sub-scheme data. Therefore, after completing the evaluation of the target scheme information, the total loss resource prediction data needs to be corrected to obtain more accurate total loss resource prediction data.
[0122] In step S801 of some embodiments, the correction database is set in the database module, and multiple correction coefficients are stored in the correction database, and the correction coefficients are correction coefficients involving multiple resource items in the sub-scheme data, and are stored in the correction database according to the sub-scheme category. Therefore, by extracting the coefficients matching the sub-scheme category from the correction database as the correction coefficients, the correction coefficients can be easily extracted.
[0123] In step S802 of some embodiments, after extracting the correction coefficient, the correction coefficient can be called to correct the target loss resource prediction data of the sub-scheme data to obtain more accurate link evaluation data as updated loss resource prediction data. Specifically, if the correction coefficient is a time correction coefficient, and the time correction coefficient represents the proportional coefficient between the actual time consumed by the sub-scheme data and the simulation time obtained by the three-dimensional simulation system module, when calculating the target loss resource prediction data, the simulation time obtained by the simulation is corrected according to the time correction coefficient to obtain the correction time, and the updated loss resource prediction data is calculated according to the correction time. It should be noted that if the sub-scheme data involves multiple resource items, multiple correction coefficients can be obtained to correct the target loss resource prediction data one by one through multiple correction coefficients. For example, if the sub-scheme data is a source item survey, the correction coefficient can be a time correction coefficient and a radiation protection correction coefficient, and the target loss resource prediction data of the source item survey is corrected according to the time correction coefficient and the radiation protection correction coefficient.
[0124] In step S803 of some embodiments, when the target loss resource prediction data of the sub-scheme data is updated, the total loss resource prediction data can be further corrected based on the updated loss resource prediction data to obtain more accurate updated resource prediction data, thereby making the resource loss prediction of the target scheme information more accurate.
[0125] In steps S801 to S803 shown in this embodiment, the correction coefficient associated with the sub-scheme data is found out, and the target loss resource prediction data of the sub-scheme data is corrected according to the correction coefficient, so as to obtain more accurate updated loss resource prediction data, so as to achieve more accurate resource loss prediction for nuclear facility decommissioning.
[0126] See also Fig. 9 In some embodiments, after step S105, the method for predicting loss resources for decommissioning a nuclear facility may further include, but is not limited to, steps S901 to S902:
[0127] Step S901, comparing the total resource loss prediction data with the preset expected resource loss data to obtain an evaluation comparison result;
[0128] Step S902: If the evaluation and comparison result is that the total resource loss prediction data is greater than the expected resource loss data, the target solution information is adjusted according to the total resource loss prediction data to obtain updated solution data.
[0129] In step S901 of some embodiments, the expected loss resource data is the loss resource data preset by the user, which is used as the expected loss resource for the decommissioning of the nuclear facility. Therefore, the evaluation comparison result is obtained by comparing the total loss resource prediction data with the preset expected loss resource data. It should be noted that if the evaluation comparison result is that the total loss resource prediction data is less than or equal to the expected loss resource data, it is determined that the implementation of the nuclear facility decommissioning plan meets the preset expected loss resources. If the evaluation comparison result is that the total loss resource prediction data is greater than the expected loss resource data, it indicates that the implementation of the nuclear facility decommissioning plan will exceed the preset expected loss resources. Specifically, if the total loss resource prediction data is the predicted decommissioning cost of the nuclear facility decommissioning, and the expected loss resource data is the preset decommissioning preparation cost, if the decommissioning prediction cost exceeds the decommissioning preparation cost, it indicates that it is difficult to implement the nuclear facility decommissioning plan.
[0130] In step S902 of some embodiments, when the evaluation and comparison result is that the total loss resource prediction data is greater than the expected loss resource data, it indicates that it is difficult to implement the nuclear facility decommissioning plan, and the nuclear facility decommissioning plan needs to be adjusted to obtain an updated nuclear facility decommissioning plan. It should be noted that in the process of adjusting the target plan information, that is, adjusting the target plan information according to the total loss resource prediction data, that is, adjusting the nuclear facility decommissioning plan. Among them, the adjustment process will re-predict the loss resources for the adjusted nuclear facility decommissioning plan until the updated loss resource data is less than or equal to the expected loss resource data, and then the adjusted nuclear facility decommissioning plan will be used as the updated nuclear facility decommissioning plan.
[0131] Specifically, this embodiment adjusts the target plan information based on the total loss resource prediction data, that is, adjusts the specific operation steps of the nuclear facility decommissioning plan to optimize the decommissioning operation of the nuclear facility decommissioning plan so that the decommissioning operation of the nuclear facility can save resource loss.
[0132] In steps S901 to S902 shown in this embodiment, the difficulty of implementing the nuclear facility decommissioning plan is determined by comparing the total loss resource prediction data with the expected loss resource data, and when the total loss resource prediction data is greater than the expected loss resource data, the target plan information is adjusted according to the total loss resource prediction data to obtain an updated plan that can implement the decommissioning of the nuclear facility, thereby facilitating the decommissioning operation of the nuclear facility.
[0133] In the embodiments of the present disclosure, Figure 4As shown, the cost estimation of the target scheme information is taken as an example. The nuclear facility decommissioning scheme is hierarchically divided in the scheme editing module to obtain multiple minimum execution links. When it is necessary to perform cost estimation on each minimum execution link, the relevant execution parameters required for the sub-scheme data to be implemented are first extracted from the database module to obtain the target scheme execution associated parameters. Specifically, the target scheme execution associated parameters are the tools, equipment, materials, manpower and other data involved in the execution of the sub-scheme data, and then the three-dimensional simulation system module simulates each minimum execution link based on the target scheme execution associated parameters to output which resource items will be consumed during the implementation of the minimum execution link as the execution loss resource items. The loss resource prediction module performs detailed cost estimation on each minimum execution link based on multiple execution loss resource items to output the cost estimation value of each sub-scheme data. Finally, according to the level information of the minimum execution link in the scheme editing module, multiple cost estimation values are superimposed and calculated step by step to obtain the decommissioning cost of the nuclear facility decommissioning scheme, so that the decommissioning cost calculation of the nuclear facility decommissioning scheme is accurate and does not require manual input of the resource loss of each resource item. It only needs to be realized through simulation, saving a lot of manpower.
[0134] See also Fig.10 The embodiment of the present application further provides a device for predicting loss resources for decommissioning a nuclear facility, which can implement the above-mentioned method for predicting loss resources for decommissioning a nuclear facility. The device includes:
[0135] A plan acquisition module 1001 is used to acquire target plan information for decommissioning a nuclear facility;
[0136] The decomposition module 1002 is used to decompose the target solution information to obtain a plurality of sub-solution data and solution level information and level association information of each sub-solution data; wherein the sub-solution data is used to represent the minimum execution link of the decommissioning of the nuclear facility;
[0137] A resource item acquisition module 1003 is used to acquire the loss resource items of the execution sub-scheme data, and obtain multiple execution loss resource items;
[0138] The loss resource prediction module 1004 is used to perform loss resource prediction on each sub-scheme data based on multiple execution loss resource items to obtain target loss resource prediction data;
[0139] The loss resource combination module 1005 is used to combine the target loss resource prediction data of multiple sub-scheme data according to the scheme level information and level association information to obtain the total loss resource prediction data of the target scheme information.
[0140] The specific implementation of the device for predicting loss resources during decommissioning of a nuclear facility is substantially the same as the specific implementation of the method for predicting loss resources during decommissioning of a nuclear facility described above, and will not be described in detail herein.
[0141] The embodiment of the present application also provides a computer device, the computer device includes a memory and a processor, the memory stores a computer program, and the processor implements the above-mentioned method for predicting the loss resources of nuclear facility decommissioning when executing the computer program. The computer device can be any intelligent terminal including a tablet computer, a car computer, etc.
[0142] See also Fig.11 , Fig.11 The hardware structure of a computer device according to another embodiment is shown, and the computer device includes:
[0143] The processor 1101 may be implemented by a general-purpose CPU (Central Processing Unit), a microprocessor, an application-specific integrated circuit (ASIC), or one or more integrated circuits, and is used to execute relevant programs to implement the technical solutions provided in the embodiments of the present application;
[0144] The memory 1102 may be implemented in the form of a read-only memory (ROM), a static storage device, a dynamic storage device, or a random access memory (RAM). The memory 1102 may store an operating system and other application programs. When the technical solution provided in the embodiments of this specification is implemented by software or firmware, the relevant program code is stored in the memory 1102, and the processor 1101 calls and executes the loss resource prediction method for decommissioning a nuclear facility in the embodiments of this application;
[0145] Input / output interface 1103, used to implement information input and output;
[0146] The communication interface 1104 is used to realize the communication interaction between the device and other devices. The communication can be realized through a wired manner (such as USB, network cable, etc.) or a wireless manner (such as mobile network, WI FI, Bluetooth, etc.);
[0147] A bus 1105 that transmits information between various components of the device (e.g., the processor 1101, the memory 1102, the input / output interface 1103, and the communication interface 1104);
[0148] The processor 1101 , the memory 1102 , the input / output interface 1103 and the communication interface 1104 are connected to each other in communication within the device via the bus 1105 .
[0149] An embodiment of the present application also provides a computer-readable storage medium, which stores a computer program. When the computer program is executed by a processor, it implements the above-mentioned method for predicting loss resources for decommissioning of nuclear facilities.
[0150] The memory, as a non-transient computer-readable storage medium, can be used to store non-transient software programs and non-transient computer executable programs. In addition, the memory may include a high-speed random access memory, and may also include a non-transient memory, such as at least one disk storage device, a flash memory device, or other non-transient solid-state storage device. In some embodiments, the memory may optionally include a memory remotely disposed relative to the processor, and these remote memories may be connected to the processor via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.
[0151] The loss resource prediction method, device, equipment and storage medium for nuclear facility decommissioning provided in the embodiments of the present application decompose the target scheme information into sub-scheme data, and then automatically determine which resource consumption will be generated during the execution of each sub-scheme data as the execution loss resource item, and perform loss resource prediction on each sub-scheme data according to multiple execution loss resource items to obtain target loss resource prediction data, and then combine multiple target loss resource prediction data based on scheme level information and level association information to obtain total loss resource prediction data of the target scheme information. Therefore, by dividing the nuclear facility decommissioning scheme into multiple minimum execution links, and then calculating the resource items that will be lost when each minimum execution link is implemented, the loss resources that will be generated by the implementation of the minimum execution link can be predicted based on multiple loss resource data, and finally the loss resources of multiple minimum execution links are summarized as the total loss resources for nuclear facility decommissioning, so that the loss resource prediction operation for nuclear facility decommissioning is automated and accurate.
[0152] The embodiments described in the embodiments of the present application are intended to more clearly illustrate the technical solutions of the embodiments of the present application and do not constitute a limitation on the technical solutions provided in the embodiments of the present application. Those skilled in the art will appreciate that with the evolution of technology and the emergence of new application scenarios, the technical solutions provided in the embodiments of the present application are also applicable to similar technical problems.
[0153] Those skilled in the art will appreciate that the technical solutions shown in the figures do not constitute a limitation on the embodiments of the present application, and may include more or fewer steps than shown in the figures, or a combination of certain steps, or different steps.
[0154] The device embodiments described above are merely illustrative, and the units described as separate components may or may not be physically separated, that is, they may be located in one place or distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0155] Those skilled in the art will appreciate that all or some of the steps in the methods disclosed above, and the functional modules / units in the systems and devices may be implemented as software, firmware, hardware, or a suitable combination thereof.
[0156] The terms "first", "second", "third", "fourth", etc. (if any) in the specification of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchangeable where appropriate, so that the embodiments of the present application described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0157] It should be understood that in the present application, "at least one (item)" means one or more, and "plurality" means two or more. "And / or" is used to describe the association relationship of associated objects, indicating that three relationships may exist. For example, "A and / or B" can mean: only A exists, only B exists, and A and B exist at the same time, where A and B can be singular or plural. The character " / " generally indicates that the objects associated before and after are in an "or" relationship. "At least one of the following" or similar expressions refers to any combination of these items, including any combination of single or plural items. For example, at least one of a, b or c can mean: a, b, c, "a and b", "a and c", "b and c", or "a and b and c", where a, b, c can be single or multiple.
[0158] In the several embodiments provided in the present application, it should be understood that the disclosed devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the above units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.
[0159] The units described above as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0160] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.
[0161] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application is essentially or the part that contributes to the prior art or all or part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including multiple instructions to enable a computer device (which can be a personal computer, server, or network device, etc.) to execute all or part of the steps of the methods of various embodiments of the present application. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (Read-Only Memory, referred to as ROM), random access memory (RandomAccess Memory, referred to as RAM), disk or optical disk and other media that can store programs.
[0162] The preferred embodiments of the present invention are described above with reference to the accompanying drawings, but the scope of the rights of the present invention is not limited thereto. Any modification, equivalent substitution and improvement made by a person skilled in the art without departing from the scope and essence of the present invention should be within the scope of the rights of the present invention.
Claims
1. A method for predicting loss resources for decommissioning of nuclear facilities. It is characterized in that The method comprises: Obtain information on target options for decommissioning nuclear facilities; Decomposing the target solution information to obtain a plurality of sub-solution data and solution level information and level association information of each of the sub-solution data; wherein the sub-solution data is used to characterize the minimum execution link of the decommissioning of the nuclear facility; Obtaining a loss resource item for executing the sub-scheme data, and obtaining a plurality of execution loss resource items; Performing resource loss prediction on each of the sub-scheme data based on the plurality of execution resource loss items to obtain target resource loss prediction data; The target loss resource prediction data of a plurality of the sub-scheme data are combined according to the scheme level information and the level association information to obtain the total loss resource prediction data of the target scheme information.
2. The method according to claim 1, It is characterized in that The step of decomposing the target solution information to obtain a plurality of sub-solution data and solution level information and level association information of each sub-solution data includes: Splitting the target solution information to obtain a plurality of sub-solution data; Acquire hierarchical relationship information between the plurality of sub-scheme data; Determine the level association information of each of the sub-scheme data based on the hierarchical relationship information; Obtaining the category of each sub-scheme data to obtain the sub-scheme category; The sub-scheme data are graded according to the sub-scheme categories and the level association information to obtain the scheme level information of each sub-scheme data.
3. The method according to claim 1, It is characterized in that The acquiring of the loss resource items for executing the sub-scheme data obtains a plurality of execution loss resource items, including: Obtaining the sub-scheme category of the sub-scheme data, selecting the target scheme execution-related parameters from the preset candidate scheme execution-related parameters based on the sub-scheme category, and simulating the sub-scheme data according to the target scheme execution-related parameters to obtain a plurality of the execution loss resource items; wherein the target scheme execution-related parameters are used as parameters for simulating the minimum execution link of the nuclear facility decommissioning; or, Based on the target scheme execution associated parameters, scheme associated parameter prompt information is generated, and parameter loss resource items fed back to the scheme associated parameter prompt information are received, and a plurality of execution loss resource items are generated based on the target scheme execution associated parameters and the parameter loss resource items.
4. The method according to claim 1, It is characterized in that The performing resource loss prediction on each of the sub-scheme data based on the plurality of execution resource loss items to obtain target resource loss prediction data includes: Obtain sub-scheme information of the sub-scheme data; Filtering out a selected solution resource loss prediction model from preset candidate solution resource loss prediction models according to the sub-solution information; The target loss resource prediction data is obtained by performing loss resource prediction on the sub-scheme data through the selected scheme loss resource prediction model and the plurality of execution loss resource items.
5. The method according to claim 4, It is characterized in that The execution loss resource items include: execution loss amount, execution correlation coefficient, execution time and execution unit price; the loss resource prediction of the sub-scheme data is performed through the selected scheme loss resource prediction model and the plurality of execution loss resource items to obtain the target loss resource prediction data, including: The selected solution loss resource prediction model is used to predict the execution loss amount, the execution correlation coefficient, the execution time and the execution unit price to obtain the target loss resource prediction data.
6. The method according to claim 2, It is characterized in that After performing resource loss prediction on each of the sub-scheme data based on the plurality of execution resource loss items to obtain target resource loss prediction data, the method further includes: extracting a correction coefficient from a preset correction database according to the sub-scheme category; Correcting the target loss resource prediction data according to the correction coefficient to obtain updated loss resource prediction data; The total resource loss prediction data is updated according to the updated resource loss prediction data to obtain updated resource prediction data of the target solution information.
7. The method according to any one of claims 1 to 6, It is characterized in that After combining the target loss resource prediction data of the plurality of sub-scheme data according to the scheme level information and the level association information to obtain the total loss resource prediction data of the target scheme information, the method includes: Comparing the total resource loss prediction data with the preset expected resource loss data to obtain an evaluation comparison result; If the evaluation and comparison result is that the total resource loss prediction data is greater than the expected resource loss data, the target solution information is adjusted according to the total resource loss prediction data to obtain updated solution data.
8. A device for predicting loss resources for decommissioning nuclear facilities, It is characterized in that The device comprises: A scheme acquisition module is used to obtain target scheme information for decommissioning nuclear facilities; A decomposition module, used for decomposing the target scheme information to obtain a plurality of sub-scheme data and scheme level information and level association information of each sub-scheme data; wherein the sub-scheme data is used to characterize the minimum execution link of nuclear facility decommissioning; A resource item acquisition module, used to acquire the loss resource items of executing the sub-scheme data, and obtain multiple execution loss resource items; A loss resource prediction module, used for performing loss resource prediction on each of the sub-scheme data based on the plurality of execution loss resource items to obtain target loss resource prediction data; The loss resource combination module is used to combine the target loss resource prediction data of multiple sub-scheme data according to the scheme level information and the level association information to obtain the total loss resource prediction data of the target scheme information.
9. A computer device, It is characterized in that The computer device includes a memory and a processor, the memory stores a computer program, and the processor implements the method for predicting loss resources for decommissioning of nuclear facilities as described in any one of claims 1 to 7 when executing the computer program.
10. A computer-readable storage medium storing a computer program. It is characterized in that When the computer program is executed by a processor, the method for predicting lost resources for decommissioning a nuclear facility according to any one of claims 1 to 7 is implemented.
Citation Information
Cited By
Method and apparatus for consumed-resource prediction in nuclear facility decommissioning, and device and storage medium
WO2026007336A1