Automatic test device and test method for semiconductor device
By setting AC and DC voltage test components on the periphery of the test station of the semiconductor device automation test device, the problems of slow testing speed and cumbersome operation in the prior art are solved, and multiple voltage tests are carried out in the same station, which improves the Test efficiency and simplify operational processes.
Patent Information
- Application Number
- CN202410947986.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-16
- Publication Date
- 2024-12-03
AI Technical Summary
When performing AC voltage test and DC voltage test, existing semiconductor device automation testing devices need to use two test stations respectively, resulting in slow test speed and cumbersome operation.
An automated testing device for semiconductor devices is designed. By setting the first voltage test component and the second voltage test component on the periphery of the test station, the AC voltage test and DC voltage test are respectively carried out on the same test station, and the transplantation is carried out. The mechanism and discharge structure optimize the testing process, reduce station switching, and improve testing efficiency.
It realizes AC voltage testing and DC voltage testing without switching the test station, improves test speed and efficiency, simplifies the operation process, and reduces the complexity of the test device.
Smart Images

Figure CN119056752A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of semiconductor testing technology, and more specifically, to an automatic testing device and a testing method for semiconductor devices. Background Art
[0002] The IPM module is a modular electronic device that integrates power semiconductor devices, drive circuits and protection functions. It is mainly used in power electronic applications such as motor drives, inverters, and frequency converters. When producing semiconductor devices in IPM modules, such as control chips, various quality tests need to be performed using test equipment.
[0003] In the related art, when the existing automated testing device is in use, during the voltage test of the semiconductor device, the AC voltage test and the DC voltage test are performed on two test stations respectively, which results in a slow test speed and requires two additional test stations, increasing the complexity of the test device and making the test operation more cumbersome. Summary of the invention
[0004] The object of the present invention is to provide a semiconductor device automatic testing device and a testing method to solve the above-mentioned technical problems.
[0005] The present invention solves the above-mentioned technical problems through the following technical solutions:
[0006] The present invention provides a semiconductor device automated testing device, comprising: a testing platform, a loading mechanism, a transplanting mechanism, a testing mechanism, a dynamic and static testing mechanism, an appearance inspection mechanism and a unloading mechanism, wherein the loading mechanism is arranged at the loading end of the testing platform and is used to transport the semiconductor device to the testing platform; the transplanting mechanism is arranged at the upper end of the testing platform and is used to transfer the semiconductor device;
[0007] The test mechanism is arranged in the test platform, and is used for performing electrical tests on semiconductor devices. The test mechanism comprises a test station, a first voltage test component and two second voltage test components. The test station is installed in the test platform. The first voltage test component is arranged at one end of the test station. The first voltage test component comprises a first driving cylinder, a support slide, a second driving cylinder and an AC test piece. The first driving cylinder is installed on the top surface of the test station, and its telescopic end is fixedly connected to one side of the support slide. The bottom of the support slide is slidably connected to the top surface of the test station. The second driving cylinder is vertically installed on the upper end of the support slide, and its telescopic end is fixedly connected to the AC test piece. An AC interface is installed on one side of the AC test piece. Two second voltage test components are symmetrically arranged at both ends of the top surface of the test station. The second voltage test component comprises a third driving cylinder and a DC test piece. The third driving cylinder is fixedly installed on the top surface of the test station, and its telescopic end is fixedly connected to one side of the DC test piece. The bottom of the DC test piece is slidably connected to the top surface of the test station. A DC interface is provided on the DC test piece.
[0008] The appearance inspection mechanism is arranged in the test platform, and is used for performing appearance inspection on semiconductor devices; the unloading mechanism is arranged at the unloading end of the test platform, and is used for unloading the tested semiconductor devices and stacking the semiconductor devices neatly.
[0009] As a further optimization scheme of the present invention, the unloading mechanism includes a unloading platform, a material storage structure, a material dividing structure and a material discharging structure. One side of the unloading platform is connected to the test platform. The material storage structure is arranged on one side of the unloading platform, and is used to store unused material tubes; the material dividing structure is arranged at the upper end of the unloading platform, and is used to remove the material tube from the material storage structure and place the material tube at a preset position; the material discharging structure is installed in the test platform, one end of which is connected to the material dividing structure, and the material discharging structure is used to remove the tested semiconductor device from the test platform and transport it into the material tube.
[0010] As a further optimization scheme of the present invention, the discharging structure includes a discharging station, a pushing assembly, a rotating assembly and an exporting assembly. The discharging station is installed in the test platform, and the rotating assembly is installed at the lower end of the discharging station, which is used to adjust the posture of the semiconductor device so that the semiconductor device is aligned with the exporting assembly; the pushing assembly is fixedly installed on the top surface of the discharging station, which is used to push the semiconductor device from the rotating assembly to the exporting assembly. The exporting assembly is connected to the test platform, and is used to transport the semiconductor device into the material pipe.
[0011] As a further optimization scheme of the present invention, the export assembly includes a base, a material guide conveying body and a telescopic member. The base is fixedly installed in the test platform, the material guide conveying body is rotatably installed on the top of the base, the bottom end of the telescopic member is hinged to the bottom of the base, and the top end is connected to the bottom of the material guide conveying body. The telescopic member is used to drive the material guide conveying body to flip on the base.
[0012] As a further optimization scheme of the present invention, the telescopic part includes a telescopic cylinder, a connecting seat, a transmission gear, a first rack and a second rack, the connecting seat is fixedly installed at the bottom of the material guiding and conveying body, the fixed end of the telescopic cylinder is hinged with the bottom of the base, and its telescopic end extends into the connecting seat; both sides of the connecting seat are provided with slide grooves, and both sides of the telescopic end of the telescopic cylinder are slidably connected with the two slide grooves correspondingly through a sliding shaft, and the transmission gear is rotatably installed in the connecting seat; one end of the first rack is fixedly connected to the telescopic end of the telescopic cylinder, and the other end of the first rack is meshed with one side of the transmission gear; one end of the second rack is slidably connected to one side of the connecting seat, and its top surface is meshed with the bottom of the transmission gear, and the other end of the second rack is rotatably installed with a pulley; a groove is provided on one side of the discharging station, and the end of the second rack away from the transmission gear slides and extends into the groove, and the pulley fits with the inner side of the groove, and a positioning contact body is fixedly installed on the top of the base, and the top of the positioning contact body fits with the bottom of the material guiding and conveying body.
[0013] As a further optimization scheme of the present invention, an auxiliary pushing member is arranged in the material guide conveying body, and the auxiliary pushing member includes a sliding body, a cam and a lifting rod. A moving groove is arranged in the material guide conveying body, and the sliding body is slidably installed in the moving groove, and two opposite inner side walls of the moving groove are provided with guide rail grooves, and one side of the guide rail groove is provided with a limit groove, and limit rods are installed on both sides of the sliding body, one end of the limit rod is slidably connected to the limit groove, and the outer side of the limit rod is rotatably sleeved with a roller, and the roller is connected to the roller inside the guide rail groove, and the cam is fixedly sleeved on the rotating shaft of the transmission gear, and the bottom end of the lifting rod is in contact with the outer side of the cam, and its top end slides upward and extends into the moving groove and in contact with the bottom of the sliding body, and the outer side of the lifting rod is sleeved with a supporting spring.
[0014] As a further optimization solution of the present invention, a swing groove is provided in the middle of the sliding body, and a rolling rod is movably provided in the swing groove.
[0015] As a further optimization scheme of the present invention, the pushing assembly includes a discharging cylinder and a discharging contact plate. The discharging cylinder is fixedly installed on the top of the discharging station, and its telescopic end is fixedly connected to one side of the discharging contact plate.
[0016] As a further optimization scheme of the present invention, the rotating assembly includes a rotating motor and a rotating material table. The rotating material table is rotatably installed on the top of the discharging station, and the rotating motor is fixedly installed on the bottom of the discharging station, and its rotating end is fixedly connected to the bottom of the rotating material table.
[0017] A method for testing a semiconductor device using the semiconductor device automated testing device comprises the following steps:
[0018] S1, the semiconductor device to be tested is transported to the loading end of the test platform by the loading mechanism, and then the semiconductor device is placed in the test mechanism in sequence by the transfer mechanism;
[0019] S2, firstly perform a DC test on the semiconductor device through the second voltage test component, and after the test is completed, perform an AC test on the semiconductor device through the first voltage test component;
[0020] S3, transporting the tested semiconductor device to a dynamic and static testing mechanism through the transfer mechanism, and performing dynamic and static tests on the semiconductor device;
[0021] S4, transporting the tested semiconductor device to an appearance inspection mechanism through the transfer mechanism, and performing appearance inspection on the semiconductor device;
[0022] S5. The material tube is removed from the discharging structure through the material dividing structure, and the material tube is placed at a preset position. The semiconductor devices that have completed the appearance inspection are transferred to the material dividing structure through the discharging structure. The semiconductor devices are transported to the material tube for storage by the material dividing structure. After the material tube is full, the material tube is stacked by the material dividing structure.
[0023] The beneficial effects of the present invention are:
[0024] In the testing mechanism provided by the present invention, by arranging a first voltage testing component and a second voltage testing component on the periphery of the testing station, an AC voltage test and a DC voltage test can be respectively performed on the semiconductor device at the testing station without switching the testing station. After the test of the second voltage testing component is completed, it can also be used to fix the semiconductor device, which is beneficial to the testing of the first voltage testing component. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a structural schematic diagram of a semiconductor device automatic testing device provided by the present invention;
[0026] Figure 2 It is a structural schematic diagram of a feeding mechanism, a testing mechanism, a transplanting mechanism, an appearance inspection mechanism, a dynamic and static inspection mechanism, and a feeding mechanism in a semiconductor device automatic testing device provided by the present invention;
[0027] Figure 3 It is a structural schematic diagram of a testing mechanism in a semiconductor device automatic testing device provided by the present invention;
[0028] Figure 4 It is a structural schematic diagram of a material unloading mechanism in a semiconductor device automatic testing device provided by the present invention;
[0029] Figure 5 It is a structural schematic diagram of a material discharging structure in a semiconductor device automatic testing device provided by the present invention;
[0030] Figure 6 It is a structural schematic diagram of a local position between a material guide and conveyor body, a telescopic member and a material discharging station in a semiconductor device automatic testing device provided by the present invention;
[0031] Figure 7 It is a structural schematic diagram of the local position of a telescopic member in a semiconductor device automatic testing device provided by the present invention;
[0032] Figure 8 It is a structural schematic diagram between a material conveying body and a connecting seat in a semiconductor device automatic testing device provided by the present invention;
[0033] Fig. 9 It is a structural schematic diagram of a telescopic member and an auxiliary pushing member in a semiconductor device automatic testing device provided by the present invention;
[0034] Fig.10 It is a cross-sectional view of a material conveying body in a semiconductor device automatic testing device provided by the present invention;
[0035] Fig.11 The present invention Fig.10 The enlarged schematic diagram of the middle A part;
[0036] Fig.12 It is a schematic diagram of the structure inside a sliding body in a semiconductor device automatic testing device provided by the present invention.
[0037] In the figure: 1. test platform; 2. feeding mechanism; 3. transplanting mechanism; 4. testing mechanism; 41. testing station; 42. first voltage testing component; 421. first driving cylinder; 422. supporting slide; 423. second driving cylinder; 424. AC test piece; 425. AC interface; 43. second voltage testing component; 431. third driving cylinder; 432. DC test piece; 433. DC interface; 5. dynamic and static testing mechanism; 6. appearance inspection mechanism; 7. unloading mechanism; 71. unloading platform; 72. material storage structure; 73. material dividing structure; 74. material discharging structure; 741. material discharging station; 742. pushing assembly; 7421. discharging cylinder; 7422. discharging contact plate; 743. rotating assembly; 7431. rotating motor ;7432, rotating material table;744, export assembly;7441, base;7442, material guide and conveying body;7443, telescopic cylinder;7444, connecting seat;7445, transmission gear;7446, first rack;7447, second rack;7448, slide groove;7449, pulley;74410, groove;74411, positioning contact body;74412, sliding body;74413, cam;74414, lifting rod;74415, moving groove;74416, guide groove;74417, limiting groove;74418, limiting rod;74419, roller;74420, supporting spring;74421, swing groove;74422, rolling rod;74423, intercepting plate;8, semiconductor device;9, material tube. DETAILED DESCRIPTION
[0038] The subject matter described herein will now be discussed with reference to example embodiments. It should be understood that the discussion of these embodiments is only to enable those skilled in the art to better understand and implement the subject matter described herein, and the functions and arrangements of the elements discussed may be changed without departing from the scope of protection of the contents of this specification. Each example may omit, replace or add various processes or components as needed. In addition, the features described relative to some examples may also be combined in other examples.
[0039] Please refer to Figure 1 and Figure 2 A semiconductor device automated testing device comprises: a testing platform 1, a loading mechanism 2, a transplanting mechanism 3, a testing mechanism 4, a dynamic and static testing mechanism 5, an appearance inspection mechanism 6 and a unloading mechanism 7, wherein the loading mechanism 2 is arranged at the loading end of the testing platform 1, and is used to transport the semiconductor device 8 into the testing platform 1; the transplanting mechanism 3 is arranged at the upper end of the testing platform 1, and is used to transfer the semiconductor device 8; the appearance inspection mechanism 6 is arranged in the testing platform 1, and is used to perform appearance inspection on the semiconductor device 8; the unloading mechanism 7 is arranged at the unloading end of the testing platform 1, and is used to unload the tested semiconductor device 8 and neatly stack the semiconductor device 8.
[0040] Please refer to Figure 3 The test mechanism 4 is arranged in the test platform 1, which is used to perform electrical tests on the semiconductor device 8. The test mechanism 4 includes a test station 41, a first voltage test component 42 and two second voltage test components 43. The test station 41 is installed in the test platform 1. The first voltage test component 42 is arranged at one end of the test station 41. The first voltage test component 42 includes a first driving cylinder 421, a supporting slide 422, a second driving cylinder 423 and an AC test piece 424. The first driving cylinder 421 is installed on the top surface of the test station 41, and its telescopic end is fixedly connected to one side of the supporting slide 422. The bottom of the supporting slide 422 is connected to the top of the test station 41. The second driving cylinder 423 is vertically installed on the upper end of the supporting slide 422, and its telescopic end is fixedly connected to the AC test piece 424, and an AC interface 425 is installed on one side of the AC test piece 424; the two second voltage test components 43 are symmetrically arranged at both ends of the top surface of the test station 41, the second voltage test component 43 includes a third driving cylinder 431 and a DC test piece 432, the third driving cylinder 431 is fixedly installed on the top surface of the test station 41, and its telescopic end is fixedly connected to one side of the DC test piece 432, the bottom of the DC test piece 432 is slidably connected to the top surface of the test station 41, and a DC interface 433 is provided on the DC test piece 432.
[0041] When testing the semiconductor device 8, the semiconductor device 8 is placed in the placement area set by the test station 41 through the transfer mechanism 3, and a DC voltage test is first performed on it. The two third driving cylinders 431 are started to drive the two DC test pieces 432 to slide close to each other on the test station 41 and connect with the two pin sides of the semiconductor device 8 respectively. At this time, the DC voltage is transmitted to the DC test piece 432 by the DC interface 433, and finally enters the semiconductor device 8. By monitoring the conduction status of the semiconductor device 8, it is determined whether the semiconductor device 8 is normal. After the DC voltage test is completed, the AC voltage test is started. At this time, the DC voltage is stopped from being supplied to the DC interface 433, and the two DC test pieces 432 continue to conduct. The semiconductor device 8 remains connected, which can fix the semiconductor device 8. Afterwards, the first driving cylinder 421 is started to drive the supporting slide 422 to slide on the test station 41, so that the AC test piece 424 moves to the top of the semiconductor device 8. Then, the AC test piece 424 is driven downward by the second driving cylinder 423, and finally connected to the top of the semiconductor device 8, and the AC voltage is transmitted to the AC interface 425. The AC voltage is transmitted to the semiconductor device 8 by the AC test piece 424, and the AC voltage test is started to monitor whether there is any abnormality inside the semiconductor device 8. After the test is completed, the semiconductor device 8 is transported to the dynamic and static test mechanism 5 through the transplanting mechanism 3 to perform the next test operation.
[0042] It should be noted that the above-mentioned feeding mechanism 2, transplanting mechanism 3, dynamic and static testing mechanism 5 and appearance inspection mechanism 6 are conventional choices in this field, and their specific structures and working principles are not disclosed here.
[0043] Please refer to Figure 4 As an embodiment of the present invention, the unloading mechanism 7 includes a unloading platform 71, a material storage structure 72, a material distribution structure 73 and a material discharge structure 74. One side of the unloading platform 71 is connected to the test platform 1. The material storage structure 72 is arranged on one side of the unloading platform 71, and is used to store unused material tubes 9; the material distribution structure 73 is arranged at the upper end of the unloading platform 71, and is used to remove the material tube 9 from the material storage structure 72 and transport the material tube 9 to the material distribution structure 73; the material discharge structure 74 is installed in the test platform 1, and one end of the material distribution structure 73 is connected to the material distribution structure 73. The material discharge structure 74 is used to remove the tested semiconductor device 8 from the test platform 1 and transport it to the material tube 9.
[0044] When the above-mentioned unloading mechanism 7 is in use, the semiconductor device 8 that has completed the test is removed from the test platform 1 through the discharging structure 74. At the same time, the unused material tube 9 is taken out from the storage structure 72 through the material dividing structure 73, and the material tube 9 is placed in the preset material tube 9 placement area thereon. After that, the semiconductor device 8 is transported to the material tube 9 through the discharging structure 74. When the material tube 9 is full of semiconductor devices 8, the filled material tube 9 is stacked in the stacking area thereon through the material dividing structure 73. After that, the unused material tube 9 is taken out from the storage structure 72 and placed in the material tube 9 placement area thereon, and the operation can be repeated in this way.
[0045] Please refer to Figures 5 to 7 As an embodiment of the present invention, the discharge structure 74 includes a discharge station 741, a pushing component 742, a rotating component 743 and a leading component 744. The discharge station 741 is installed in the test platform 1, and the rotating component 743 is installed at the lower end of the discharge station 741, which is used to adjust the posture of the semiconductor device 8. The rotating component 743 includes a rotating motor 7431 and a rotating material table 7432. The rotating material table 7432 is rotatably installed on the top of the discharge station 741, and the rotating motor 7431 is fixedly installed at the discharge station The bottom of 741, its rotating end is fixedly connected to the bottom of the rotating material table 7432; the pushing component 742 is fixedly installed on the top surface of the discharge station 741, and is used to push the semiconductor device 8 from the rotating component 743 to the export component 744, so that the semiconductor device 8 is aligned with the export component 744; the pushing component 742 includes a discharge cylinder 7421 and a discharge contact plate 7422, the discharge cylinder 7421 is fixedly installed on the top of the discharge station 741, and its telescopic end is fixedly connected to one side of the discharge contact plate 7422.
[0046] The export component 744 is connected to the test platform 1, and is used to transport the semiconductor device 8 into the material tube 9. The export component 744 includes a base 7441, a material guide conveying body 7442 and a telescopic member. The base 7441 is fixedly installed in the test platform 1, and the material guide conveying body 7442 is rotatably installed on the top of the base 7441. The bottom end of the telescopic member is hinged to the bottom of the base 7441, and the top end thereof is connected to the bottom of the material guide conveying body 7442. The telescopic member is used to drive the material guide conveying body 7442 to flip on the base 7441, and the material discharge end of the material guide conveying body 7442 is provided with an automatically retractable intercepting plate 74423.
[0047] The telescopic member includes a telescopic cylinder 7443, a connecting seat 7444, a transmission gear 7445, a first rack 7446 and a second rack 7447. The connecting seat 7444 is fixedly installed at the bottom of the material guide conveyor 7442. The fixed end of the telescopic cylinder 7443 is hinged to the bottom of the base 7441, and its telescopic end extends into the connecting seat 7444; both sides of the connecting seat 7444 are provided with slide grooves 7448, and both sides of the telescopic end of the telescopic cylinder 7443 are slidably connected to the two slide grooves 7448 through a sliding shaft, and the transmission gear 7445 is rotatably installed in the connecting seat 7444; one end of the first rack 7446 is fixed to the telescopic end of the telescopic cylinder 7443 The second rack 7447 is slidably connected to one side of the connecting seat 7444, and its top surface is meshed with the bottom of the transmission gear 7445. The other end of the second rack 7447 is rotatably installed with a pulley 7449. A groove 74410 is provided on one side of the discharging station 741, and one end of the second rack 7447 away from the transmission gear 7445 slides and extends into the groove 74410, and the pulley 7449 is fitted with the inner side of the groove 74410. A positioning contact body 74411 is fixedly installed on the top of the base 7441, and the top of the positioning contact body 74411 is fitted with the bottom of the material guiding and conveying body 7442.
[0048] When the above-mentioned discharge structure 74 is in use, the transfer mechanism 3 places the tested semiconductor device 8 on the rotating material table 7432, and drives the rotating material table 7432 to rotate horizontally by ninety degrees on the discharge station 741 through the rotating motor 7431, so that it is aligned with the material guide conveying body 7442, and then, the discharge cylinder 7421 is extended to drive the discharge contact plate 7422 to move to the rotating discharge table, and after contacting one end of the semiconductor device 8, the semiconductor device 8 is pushed from the rotating material table 7432 to the material guide conveying body 7442, and the operation is repeated until the material guide conveying body 7442 reaches the maximum storage capacity. At this time, the sliding shaft connected to the telescopic end of the telescopic cylinder 7443 can slide along the slide groove 7448, and the first rack 7446 7444, and the second rack 7447 starts to slide horizontally toward the inside of the connecting seat 7444 under the driving action of the transmission gear 7445, and the other end of the second rack 7447 gradually moves away from the groove 74410. The pulley 7449 rolls in the groove 74410 following the second rack 7447. Due to the limiting effect of the second rack 7447, the material guide conveying body 7442 can maintain a stable state before the sliding shaft reaches the other end of the sliding groove 7448. When the sliding shaft is about to reach the other end of the sliding groove 7448, the pulley 7449 is completely separated from the groove 74410. When the sliding shaft contacts the other end in the sliding groove 7448, as the telescopic cylinder 7443 continues to extend, the material guide conveying body 7442 can be driven to move upward synchronously and drive the transmission gear 7445 to rotate in the connecting seat 7444. The feeding body 7442 is turned upward on the base 7441, so that it gradually turns from a horizontal state to an inclined state, and the intercepting action of the material blocking plate can prevent the semiconductor device 8 from escaping from the material guiding and conveying body 7442. When the material guiding and conveying body 7442 is turned over to a preset position, its discharge end is just aligned with the port of the material pipe 9 on the material dividing structure 73. At this time, the material blocking plate is opened, and under the action of gravity, the semiconductor devices 8 enter the material pipe 9 from the material guiding and conveying body 7442 in turn. After that, the material guiding and conveying body 7442 can be driven to turn downward and reset by contracting the telescopic cylinder 7443. When the bottom of the material guiding and conveying body 7442 turns over to contact with the top of the positioning contact body 74411, the material guiding and conveying body 7442 no longer follows the movement of the telescopic cylinder 7443. The telescopic cylinder 7443 continues to contract, which can drive the sliding shaft and move in the sliding groove 7448, and the first rack 7446 moves synchronously, which can drive the transmission gear 7445 to rotate. The second rack 7447 is driven by the transmission gear 7445 and gradually moves toward the groove 74410. When the pulley 7449 contacts the end of the groove 74410, if the material guide conveying body 7442 is in a standard state aligned with the rotating material table 7432, the pulley 7449 is also aligned with the end of the groove 74410. At this time, the pulley 7449 can directly enter the groove 74410. If the position of the pulley 7449 at this time is not aligned with the groove 74410, when the pulley 7449 moves to the inside of the groove 74410,Under the extrusion of the inclined groove at the corresponding position, the top of the positioning contact body 74411 has a certain elastic expansion, so that the material guide conveying body 7442 can move with the second rack 7447, so that the pulley 7449 can finally enter the groove 74410 smoothly. At this time, the material guide conveying body 7442 is driven by the pulley 7449 and moves to the standard state aligned with the rotating material table 7432. In this way, the automatic position correction function of the material guide conveying body 7442 is realized.
[0049] In the export assembly 744 provided in the present invention, a telescopic member is provided, which is used, on the one hand, to drive the material guide conveying body 7442 to perform a flipping action so that it can convey the semiconductor device 8 out; on the other hand, when the material guide conveying body 7442 is flipped and reset, the longitudinal force generated by the active contact between the telescopic member and the discharge station 741 can be used to synchronously squeeze the material guide conveying body 7442 that has reached the initial stop position, so as to realize the position correction function of the material guide conveying body 7442 after the reset, which is beneficial for keeping the material guide conveying body 7442 and the rotating material table 7432 in a standard alignment state, so that the subsequent semiconductor device 8 can smoothly enter the material guide conveying body 7442. The telescopic member changes the traditional direct hinged connection method of the telescopic cylinder 7443 and the material guide conveying body 7442, and improves the problem that when the telescopic cylinder 7443 is repeatedly extended and retracted for a long time and its extension amount deviates, the position of the material guide conveying body 7442 when driving the reset is not completely aligned with the rotating material table 7432.
[0050] As a further optimization of the above solution, please refer to Figures 8 to 11As an embodiment of the present invention, an auxiliary pushing member is arranged in the material guide conveying body 7442, and the auxiliary pushing member includes a sliding body 74412, a cam 74413 and a lifting rod 74414. A moving groove 74415 is arranged in the material guide conveying body 7442, and the sliding body 74412 is slidably installed in the moving groove 74415. The two opposite inner side walls of the moving groove 74415 are provided with a guide groove 74416, and a limiting groove 74417 is arranged on one side of the guide groove 74416. Limiting rods 74418 are installed on both sides of the sliding body 74412, and one end of the limiting rod 74418 is slidably connected to the limiting groove 74417, and the outer rotating sleeve of the limiting rod 74418 is provided. Roller 74419, roller 74419 is connected to the inner roller 74419 of the guide groove 74416, the cam 74413 is fixedly mounted on the rotating shaft of the transmission gear 7445, the bottom end of the lifting rod 74414 is fitted with the outer side of the cam 74413, and its top end slides upward and extends into the movable groove 74415, and fits with the bottom of the sliding body 74412, and the outer side of the lifting rod 74414 is provided with a support spring 74420; the guide groove 74416 includes a vertical section and an inclined section, when the sliding body 74412 is in a retracted state, the roller 74419 is just at the bottom end of the vertical section, and when the sliding body 74412 is unfolded, it is at the end of the inclined section.
[0051] When the telescopic cylinder 7443 is extended, the first rack 7446 drives the transmission gear 7445 to rotate, and the cam 74413 rotates with the transmission gear 7445. The rotating cam 74413 generates an upward thrust on the bottom end of the lifting rod 74414, causing it to extend into the moving groove 74415 and squeeze the support spring 74420 to contract. The sliding body 74412 is pushed by the lifting rod 74414 and moves upward in the moving groove 74415 synchronously. , the roller 74419 follows the sliding body 74412 to move in the guide groove 74416. When the transmission gear 7445 stops rotating, the sliding body 74412 just extends to the upper end of the material guide conveying body 7442. Afterwards, when the material guide conveying body 7442 turns over, under the action of gravity, the sliding body 74412 starts to slide along the moving groove 74415. During its movement, due to the sliding limit action of the limit rod 74418 and the guide groove 74416, , so that the sliding body 74412 can maintain a vertical moving state, and the roller 74419 rolls in the guide groove 74416 at the same time, and the sliding body 74412 slides on the material conveying body 7442, and the gravity of the semiconductor device 8 can be used to push the semiconductor device 8 to slide downward, thereby accelerating the moving speed of the semiconductor device 8. When the material conveying body 7442 flips to a preset angle, the sliding body 74412 just moves to the other end of the moving groove 74415. When the telescopic cylinder 7443 shrinks and resets, the material conveying body 7442 flips and resets, and the cam 74413 of the sliding body 74412 follows the transmission gear 7445 to rotate in the opposite direction, and the lifting rod 74414 moves downward and resets under the elastic force of the support spring 74420. When the material conveying body 7442 is in a horizontal state, due to the inclined setting of the inclined section, the sliding body 74412 automatically slides to the vertical section under the action of gravity, and finally moves to a contracted state;
[0052] The present invention further arranges the auxiliary pushing member in the material conveying body 7442, and utilizes its gravity to generate a downward thrust on the semiconductor device 8 in the material conveying body 7442, thereby accelerating the moving speed of the semiconductor device 8 and improving the problem of the semiconductor device 8 being stuck in the material conveying body 7442, thereby ensuring the smooth transportation of the semiconductor device 8. The auxiliary pushing member is used in conjunction with the telescopic member, and utilizes the telescopic driving force of the telescopic member as its own extension driving source. It can synchronously complete the extension action before the material conveying body 7442 is flipped, thereby realizing the function of synchronous adaptation and adjustment of the use state of the auxiliary pushing member and the material conveying body 7442, without the need to separately set up a driving source and a control system, which is more convenient in use; the auxiliary pushing member has an automatic retraction function, and when in the retracted state, it will not affect the normal activity of the semiconductor device 8, and can automatically move and reset after use, and can well adapt to the state change of the material conveying body 7442 without manual control.
[0053] As a further optimization method for the above solution, please refer to Fig.12 As an embodiment of the present invention, a swing groove 74421 is provided in the middle of the sliding body 74412 . The swing groove 74421 is in a semicircular shape. A rolling rod 74422 is movably provided in the swing groove 74421 .
[0054] When the material conveying body 7442 is in a tilted state, under the action of gravity, the rolling body rolls to the downward end of the swing groove 74421. At this time, the gravity of the sliding body 74412 is offset downward. At this time, the gravity effect of the sliding body 74412 is increased, which can reduce the resistance of the sliding body 74412, making it smoother when sliding, and has a stronger driving force on the semiconductor device 8, thereby better solving the blockage problem.
[0055] Second embodiment
[0056] As a second embodiment of the present invention, the present invention further provides a method for testing a semiconductor device using a semiconductor device automated testing apparatus, comprising the following steps:
[0057] S1, the semiconductor device 8 to be tested is transported to the loading end of the test platform 1 by the loading mechanism 2, and then the semiconductor device 8 is placed in the test mechanism 4 in sequence by the transfer mechanism 3;
[0058] S2, firstly perform a DC test on the semiconductor device 8 through the second voltage test component 43, and after the test is completed, perform an AC test on the semiconductor device 8 through the first voltage test component 42;
[0059] S3, transporting the tested semiconductor device 8 to the dynamic and static testing mechanism 5 through the transfer mechanism 3, and performing dynamic and static tests on the semiconductor device 8;
[0060] S4, transporting the tested semiconductor device 8 to the appearance inspection mechanism 6 through the transfer mechanism 3, and performing appearance inspection on the semiconductor device 8;
[0061] S5. Remove the material tube 9 from the discharging structure 74 through the material dividing structure 73, and place the material tube 9 at a preset position. Transfer the semiconductor device 8 that has completed the appearance inspection to the material dividing structure 73 through the discharging structure 74. The semiconductor device 8 is transported to the material tube 9 by the material dividing structure 73 for storage. After the material tube 9 is full, the material dividing structure 73 will stack the material tubes 9.
[0062] An example of the present specific implementation mode is described above, but the present embodiment is not limited to the above-mentioned specific implementation mode, which is merely illustrative and not restrictive. A person skilled in the art may make many forms inspired by the present embodiment, all of which are protected by the present embodiment.
Claims
1. A semiconductor device automated testing device, comprising: A test platform (1), a loading mechanism (2), a transplanting mechanism (3), a test mechanism (4), a dynamic and static test mechanism (5), an appearance inspection mechanism (6) and a unloading mechanism (7), characterized in that the loading mechanism (2) is arranged at the loading end of the test platform (1) and is used to transport the semiconductor device (8) into the test platform (1); the transplanting mechanism (3) is arranged at the upper end of the test platform (1) and is used to transfer the semiconductor device (8); The test mechanism (4) is arranged in the test platform (1) and is used to perform electrical tests on the semiconductor device (8). The test mechanism (4) comprises a test station (41), a first voltage test component (42) and two second voltage test components (43). The test station (41) is installed in the test platform (1). The first voltage test component (42) is arranged at one end of the test station (41). The first voltage test component (42) comprises a first drive cylinder (421), a support slide (422), a second drive cylinder (423) and an AC test piece (424). The first drive cylinder (421) is installed on the top surface of the test station (41). The telescopic end of the first drive cylinder (421) is fixedly connected to one side of the support slide (422). The bottom of the support slide (422) is connected to the test station (41). The second driving cylinder (423) is vertically mounted on the upper end of the supporting slide (422), and its telescopic end is fixedly connected to the AC test piece (424), and an AC interface (425) is installed on one side of the AC test piece (424); two second voltage test components are symmetrically arranged at two ends of the top surface of the test station (41), and the second voltage test component (43) includes a third driving cylinder (431) and a DC test piece (432), and the third driving cylinder (431) is fixedly mounted on the top surface of the test station (41), and its telescopic end is fixedly connected to one side of the DC test piece (432), and the bottom of the DC test piece (432) is slidably connected to the top surface of the test station (41), and a DC interface (433) is provided on the DC test piece (432); The appearance inspection mechanism (6) is arranged in the test platform (1) and is used to perform appearance inspection on the semiconductor device (8); the unloading mechanism (7) is arranged at the unloading end of the test platform (1) and is used to unload the semiconductor device (8) after the test and to neatly stack the semiconductor devices (8).
2. A semiconductor device automatic testing device according to claim 1, characterized in that: The material unloading mechanism (7) comprises a material unloading platform (71), a material storage structure (72), a material distribution structure (73) and a material discharge structure (74); one side of the material unloading platform (71) is connected to the test platform (1); the material storage structure (72) is arranged on one side of the material unloading platform (71) and is used to store unused material tubes (9); the material distribution structure (73) is arranged at the upper end of the material unloading platform (71) and is used to remove the material tube (9) from the material storage structure (72) and place the material tube (9) at a preset position; the material discharge structure (74) is installed in the test platform (1) and one end of the material distribution structure (73) is connected to the material distribution structure (73); the material discharge structure (74) is used to remove the tested semiconductor device (8) from the test platform (1) and transport it into the material tube (9).
3. A semiconductor device automatic testing device according to claim 2, characterized in that: The discharge structure (74) comprises a discharge station (741), a pushing component (742), a rotating component (743) and an exporting component (744); the discharge station (741) is installed in the test platform (1); the rotating component (743) is installed at the lower end of the discharge station (741) and is used to adjust the posture of the semiconductor device (8) so that the semiconductor device (8) is aligned with the exporting component (744); the pushing component (742) is fixedly installed on the top surface of the discharge station (741) and is used to push the semiconductor device (8) from the rotating component (743) to the exporting component (744); the exporting component (744) is connected to the test platform (1) and is used to transport the semiconductor device (8) to the material pipe (9).
4. The semiconductor device automatic testing device according to claim 3, characterized in that: The export assembly (744) comprises a base (7441), a material guide and conveying body (7442) and a telescopic member, wherein the base (7441) is fixedly mounted in the test platform (1), the material guide and conveying body (7442) is rotatably mounted on the top of the base (7441), the bottom end of the telescopic member is hinged to the bottom of the base (7441), and the top end is connected to the bottom of the material guide and conveying body (7442), and the telescopic member is used to drive the material guide and conveying body (7442) to perform a flipping action on the base (7441).
5. The semiconductor device automatic testing device according to claim 4, characterized in that: The telescopic member comprises a telescopic cylinder (7443), a connecting seat (7444), a transmission gear (7445), a first rack (7446) and a second rack (7447); the connecting seat (7444) is fixedly mounted on the bottom of the material guide and conveying body (7442); the fixed end of the telescopic cylinder (7443) is hinged to the bottom of the base (7441), and the telescopic end thereof extends into the connecting seat (7444); both sides of the connecting seat (7444) are provided with sliding grooves (7448); both sides of the telescopic end of the telescopic cylinder (7443) are slidably connected to the two sliding grooves (7448) via sliding shafts; the transmission gear (7445) is rotatably mounted in the connecting seat (7444); one end of the first rack (7446) is fixedly mounted to the telescopic end of the telescopic cylinder (7443); The second rack (7447) is fixedly connected to the connecting seat (7444), and the other end thereof meshes with one side of the transmission gear (7445); one end of the second rack (7447) is slidably connected to one side of the connecting seat (7444), and the top surface thereof meshes with the bottom of the transmission gear (7445); the other end of the second rack (7447) is rotatably mounted with a pulley (7449); a groove (74410) is provided on one side of the discharging station (741), and one end of the second rack (7447) away from the transmission gear (7445) slides and extends into the groove (74410), and the pulley (7449) fits with the inner side of the groove (74410); a positioning contact body (74411) is fixedly mounted on the top of the base (7441), and the top end of the positioning contact body (74411) fits with the bottom of the material guide and conveying body (7442).
6. The semiconductor device automatic testing device according to claim 5, characterized in that: An auxiliary pusher is arranged in the material guide and conveying body (7442), and the auxiliary pusher comprises a sliding body (74412), a cam (74413) and a lifting rod (74414). A moving groove (74415) is arranged in the material guide and conveying body (7442). The sliding body (74412) is slidably installed in the moving groove (74415). Two opposite inner side walls of the moving groove (74415) are provided with guide grooves (74416). One side of the guide groove (74416) is provided with a limiting groove (74417). Limiting rods (74418) are installed on both sides of the sliding body (74412). The limiting rods (74419) are provided with a plurality of guide grooves (74411). One end of the limit rod (74418) is slidably connected to the limit groove (74417), the outer side of the limit rod (74418) is rotatably sleeved with a roller (74419), and the roller (74419) is connected to the inner roller (74419) of the guide groove (74416), the cam (74413) is fixedly sleeved on the rotating shaft of the transmission gear (7445), the bottom end of the lifting rod (74414) is fitted with the outer side of the cam (74413), and the top end thereof slides upward and extends into the movable groove (74415) and is fitted with the bottom of the sliding body (74412), and the outer side of the lifting rod (74414) is sleeved with a support spring (74420).
7. The semiconductor device automatic testing device according to claim 6, characterized in that: A swing groove (74421) is provided in the middle of the sliding body (74412), and a rolling rod (74422) is movably provided in the swing groove (74421).
8. The semiconductor device automatic testing device according to claim 7, characterized in that: The pushing assembly (742) comprises a discharging cylinder (7421) and a discharging contact plate (7422); the discharging cylinder (7421) is fixedly mounted on the top of the discharging station (741), and a telescopic end thereof is fixedly connected to one side of the discharging contact plate (7422).
9. The semiconductor device automatic testing device according to claim 8, characterized in that: The rotating assembly (743) comprises a rotating motor (7431) and a rotating material table (7432); the rotating material table (7432) is rotatably mounted on the top of the material discharging station (741); the rotating motor (7431) is fixedly mounted on the bottom of the material discharging station (741), and its rotating end is fixedly connected to the bottom of the rotating material table (7432).
10. A method for testing a semiconductor device using the semiconductor device automated testing device according to any one of claims 1 to 9, characterized in that: The steps include: S1, transporting the semiconductor device (8) to be tested to the loading end of the test platform (1) by means of a loading mechanism (2), and then placing the semiconductor device (8) in sequence in the test mechanism (4) by means of a transfer mechanism (3); S2, firstly performing a DC test on the semiconductor device (8) through the second voltage test component (43), and after the test is completed, performing an AC test on the semiconductor device (8) through the first voltage test component (42); S3, transporting the tested semiconductor device (8) to the dynamic and static testing mechanism (5) through the transfer mechanism (3), and performing dynamic and static tests on the semiconductor device (8); S4, transporting the tested semiconductor device (8) to the appearance inspection mechanism (6) through the transfer mechanism (3), and performing appearance inspection on the semiconductor device (8); S5. The material tube (9) is removed from the discharge structure (74) by the material dividing structure (73), and the material tube (9) is placed at a preset position. The semiconductor device (8) that has completed the appearance inspection is transferred to the material dividing structure (73) by the discharge structure (74). The semiconductor device (8) is transported to the material tube (9) by the material dividing structure (73) for storage. After the material tube (9) is full, the material tube (9) is stacked by the material dividing structure (73).