Fiber bundle bundling device in spinning machine
By designing a fiber bundle bundle device in a spinning machine, using the design of crossing the introduction surface and the flow path expansion surface, the problem of fiber disorder in the spinning machine is solved, and the rapid adsorption of the fiber bundle and the stability of the yarn quality are achieved. , avoiding the reduction in flow velocity caused by vortex current.
Patent Information
- Application Number
- CN202410427189.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Priority Date
- 2023-05-31
- Filing Date
- 2024-04-10
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2044-04-10
AI Technical Summary
The fiber bundle becomes a free state after the final output roller is in the spinning machine, resulting in fiber disorder. The prior art increases the suction force by expanding the upstream end of the suction slit, but it is easy to cause vortex, reduce the airflow flow rate, and extend the fiber. The beam adsorption time cannot shorten the free state distance.
Design a fiber bundle bundle device, the suction tube is arranged on the downstream side of the final output roller, the upstream end of the suction slit is located on the curved surface of the suction tube, the introduction surface is located on the lower side of the male tangent line, the flow path expansion surface and the introduction surface Crossing to form a smaller vortex region, increasing the air flow rate and suppressing the reduction of the vortex flow rate, ensuring rapid adsorption of the fiber bundle.
Effectively shorten the distance from the fiber bundle to become a free state after output, reduce fiber bundle disorder, improve yarn quality stability, and improve suction force without increasing power consumption.
Smart Images

Figure CN119061540A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a fiber bundle bundling device in a spinning machine. Background Art
[0002] For example, as disclosed in Patent Document 1, a fiber bundle bundling device is disposed downstream of a final delivery roller pair of a drafting device of a spinning frame. The fiber bundle bundling device includes a suction pipe and an air conveyor belt.
[0003] A suction slit is formed on the suction pipe. In addition, the suction pipe is connected to the suction duct via a connecting pipe. A portion of the air-permeable conveyor belt is wound around the suction pipe. The air-permeable conveyor belt is formed of, for example, a woven fabric that can ensure moderate air permeability.
[0004] When the spinning frame is in operation, the suction from the suction duct acts on the suction pipe via the connecting pipe. Thus, the suction force generated by the suction slit acts on the fiber bundle via the air conveyor belt. As a result, the fiber bundle is adsorbed at the position of the air conveyor belt corresponding to the suction slit and is bundled and conveyed by the air conveyor belt.
[0005] Patent Document 1: Japanese Patent Application Publication No. 2012-87419
[0006] The fiber bundle is in a free state without being restrained by the rollers from the time it is discharged from the final discharge roller pair to the time it is sucked by the air conveyor belt above the suction pipe, so the fibers are easily disordered. In order to suppress the disorder of the fibers, it is preferred to shorten the distance that the fiber bundle is in a free state after it is discharged from the final discharge roller pair.
[0007] The fiber bundle is output along the common tangent line at the clamping point of the final output roller pair. Therefore, it is considered to increase the suction force generated by the suction slit by expanding the upstream end of the suction slit toward the lower roller side from the common tangent line, so that the fiber bundle is quickly adsorbed to the air conveyor belt and the distance for the fiber bundle to become free is shortened.
[0008] However, if the upstream end of the suction slit is expanded toward the lower roller side more than the common tangent line, the airflow flowing along the upstream end is likely to form a vortex along the inner surface of the suction pipe. In this way, due to the generation of the vortex, the flow rate of the airflow flowing along the upstream end is slowed down. If the flow rate of the airflow near the upstream end is slowed down, the time point when the fiber bundle is adsorbed by the air conveyor belt is delayed. Therefore, regardless of whether the upstream end of the suction slit is expanded or not, the distance for the fiber bundle to become a free state does not shorten. Summary of the invention
[0009] The fiber bundle bundling device in the spinning machine for solving the above-mentioned problem comprises: a suction pipe, which is arranged on the downstream side of the final output roller pair having a lower roller and an upper roller and is provided with a suction slit; and an air-permeable conveyor belt, which is rotated while being wound on the suction pipe in a manner covering the above-mentioned suction slit to convey the fiber bundle, and the above-mentioned fiber bundle is adsorbed on the above-mentioned air-permeable conveyor belt and bundled by the air flow flowing toward the above-mentioned suction slit, and the above-mentioned fiber bundle is conveyed in the conveying direction by the above-mentioned air-permeable conveyor belt. The main purpose of the fiber bundle bundling device in the above-mentioned spinning machine is that the above-mentioned suction slit is in the above-mentioned conveying direction. The upstream end portion is arranged on the curved portion of the suction pipe facing the lower roller, and comprises: an inlet surface, which is located on the lower roller side than the common tangent line at the clamping point of the final output roller pair, and introduces the airflow into the suction slit; and a flow path expansion surface, which intersects the inlet surface and is located on the outer surface side than the inner surface of the suction pipe, and expands the flow path of the airflow compared to the flow path at the inlet surface, and the first angle between the first imaginary line along the inlet surface and the common tangent line is smaller than the second angle between the second imaginary line along the flow path expansion surface and the common tangent line.
[0010] Accordingly, the introduction surface exceeds the common tangent line and is located on the lower roller side, so the amount of airflow flowing to the suction slit can be increased compared to the case where the introduction surface exceeds the common tangent line and is located on the upper roller side. In addition, the flow path of the airflow after flowing along the introduction surface is expanded by the flow path expansion surface. Therefore, the airflow after flowing along the introduction surface is caused to flow crosswise to the common tangent line direction by the flow path expansion surface. In this way, the area where the vortex is generated between the inner surface of the suction tube and the airflow is reduced. As a result, even if the vortex is generated inside the suction tube, the reduction in the airflow velocity caused by the vortex can be suppressed. Therefore, even if the upstream end is set on the lower roller side closer to the common tangent line, the fiber bundle is quickly adsorbed on the air-permeable conveyor belt, so the distance for the fiber bundle to become a free state can be shortened.
[0011] In the fiber bundle bundling device in the spinning machine, the introduction surface may be an inclined surface forming the upstream end portion.
[0012] According to this, the airflow flows toward the suction slit along the inclined surface. Therefore, the airflow can be efficiently introduced into the suction slit through the inclined surface.
[0013] In the fiber bundle bundling device in the spinning machine, the inclined surface may be a flat surface.
[0014] According to this, the airflow can be efficiently introduced into the suction slit.
[0015] In the fiber bundle bundling device in the spinning machine, the introduction surface may extend in the common tangent line direction.
[0016] According to this, the direction of the air flow coincides with the common tangent direction, and therefore the fiber bundle can be more quickly adsorbed to the air conveyor belt.
[0017] In the fiber bundle bundling device in the spinning machine, the upstream end portion may include an intersecting surface that is orthogonal to the flow path expansion surface and extends from an inner surface of the suction pipe toward the flow path expansion surface.
[0018] According to this, when forming the flow path expansion surface in the suction pipe, the inner surface of the suction pipe is processed to form the flow path expansion surface. In this case, the flow path expansion surface can be formed while forming the intersection surface, so the flow path expansion surface can be easily formed.
[0019] The present invention can shorten the distance in which the fiber bundle becomes free after being delivered by the final delivery roller pair. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is a schematic side view of a fiber bundle bundling device, partially in section.
[0021] Figure 2 It is a perspective view showing the suction pipe.
[0022] Figure 3 This is an enlarged view showing the suction slit.
[0023] Figure 4 It is a partially enlarged cross-sectional view showing the upstream end portion.
[0024] Figure 5 Schematic diagram of the clamping point and the upstream end.
[0025] Figure 6 It is an enlarged cross-sectional view showing the upstream end portion.
[0026] Figure 7 It is a diagram schematically showing a clamping point and an upstream end portion in a comparative example.
[0027] Figure 8 It is an enlarged cross-sectional view showing the upstream end portion of another example.
[0028] Fig. 9 It is an enlarged cross-sectional view showing an upstream end portion of still another example.
[0029] Description of Reference Numerals
[0030] θ1...the first angle; θ2...the second angle; D1...the first imaginary line; D2...the second imaginary line; F...the fiber bundle; L...the common tangent line; P1...the clamping point; R...the direction of the common tangent line; 11...the fiber bundle bundling device; 13...the final output roller pair; 13a...the front lower roller; 13b...the front upper roller; 15...the suction pipe; 15f...the curved surface; 16...the air-permeable conveyor belt; 27...the suction slit; 31...the upstream end; 31a...the intersection surface; 31b...the flow path expansion surface; 31c...the introduction surface. DETAILED DESCRIPTION
[0031] Below, according to Figure 1 to Figure 7 An embodiment in which the fiber bundle bundling device in a spinning machine is embodied as a fiber bundle bundling device in a spinning frame will be described.
[0032] <Overall structure of spinning machine>
[0033] like Figure 1 As shown, the spinning frame includes a fiber bundle bundling device 11 and a drafting device 12. The drafting device 12 includes a final output roller pair 13, and the final output roller pair 13 includes a front lower roller 13a as a lower roller and a front upper roller 13b as an upper roller. A gear portion 13c is formed on the front lower roller 13a. The fiber bundle F drafted by the drafting device 12 is output toward the fiber bundle bundling device 11 by the final output roller pair 13.
[0034] <Fiber bundle bundling device>
[0035] The fiber bundle bundling device 11 includes a suction pipe 15 , an air conveyor belt 16 , a feeding unit 14 , and a guide unit 17 .
[0036] <Output section>
[0037] The delivery section 14 includes a lower nip roller 18 a and an upper nip roller 19 .
[0038] The lower clamp roller 18a is provided so as to be rotatable integrally with the rotating shaft 18, and the rotating shaft 18 is arranged parallel to and close to the front lower roller 13a of the final output roller pair 13. In addition, the gear 22 is provided on the rotating shaft 18 so as to be rotatable integrally with the rotating shaft 18. The gear portion 13c and the gear 22 are meshed with the intermediate gear 25. The torque of the front lower roller 13a is transmitted to the rotating shaft 18 via the gear portion 13c, the intermediate gear 25 and the gear 22. As a result, the lower clamp roller 18a rotates.
[0039] The upper nip roller 19 is pressed against the lower nip roller 18a via the air conveyor belt 16. The upper nip roller 19 is supported by a weight arm (not shown) via a supporting member 20.
[0040] <Suction tube>
[0041] The spinning machine is provided with a suction duct (not shown) extending in the longitudinal direction of the machine frame. The suction pipe 15 is connected to the suction pipe via a connecting pipe 26 while extending in parallel with the suction pipe. The suction pipe 15 is provided on the downstream side of the final delivery roller pair 13 of the drafting device 12, and a suction slit 27 is formed in the suction pipe 15.
[0042] The suction pipe 15 includes a guide surface 28 formed with a suction slit 27. The air conveyor belt 16 rotates in a state where a portion of the air conveyor belt 16 is wound around the suction pipe 15 and a portion of the air conveyor belt 16 is wound around the guide portion 17 so as to cover the suction slit 27. The fiber bundle F sucked by the air conveyor belt 16 by the rotation of the air conveyor belt 16 is conveyed in the conveying direction V. The air conveyor belt 16 is formed of, for example, a woven fabric capable of ensuring appropriate air permeability.
[0043] The suction pipe 15 is provided downstream of the clamping point P1 of the final delivery roller pair 13 in the feeding direction V of the fiber bundle F. Furthermore, the suction pipe 15 is provided upstream of the clamping point P2 of the delivery section 14 in the feeding direction V of the fiber bundle F.
[0044] like Figure 1 and Figure 2 As shown in FIG. 1 , the suction pipe 15 is provided with a guide surface 28 on the outer surface of the suction pipe 15. The guide surface 28 is an arc surface having a width in the conveying direction V in a manner of gently curving along the conveying direction V. The guide surface 28 is a surface extending between the clamping point P1 of the final delivery roller pair 13 and the clamping point P2 of the delivery portion 14 in a manner of connecting the two clamping points P1 and P2. Therefore, the fiber bundle F delivered from the final delivery roller pair 13 is guided from the clamping point P1 of the final delivery roller pair 13 to the clamping point P2 of the delivery portion 14 by the guide surface 28 formed via the air-permeable conveyor belt 16.
[0045] In the suction pipe 15, the guide surface forming portion 15a forming the guide surface 28 is a plate-like shape gently curved along the conveying direction V of the fiber bundle F. The suction pipe 15 includes a bottom portion 15b facing the guide surface forming portion 15a. The dimension of the bottom portion 15b in the conveying direction V is smaller than the dimension of the guide surface forming portion 15a in the conveying direction V.
[0046] The suction pipe 15 includes a first curved portion 15c that connects the downstream end of the guide surface forming portion 15a in the conveying direction V and the downstream end of the bottom portion 15b in the conveying direction V. The first curved portion 15c is curved in an arc shape along the peripheral surface of the lower clamp roller 18a. The first curved portion 15c faces the peripheral surface of the lower clamp roller 18a.
[0047] The suction pipe 15 includes a curved portion 15f continuous with the upstream end of the guide surface forming portion 15a in the conveying direction V, and includes a second curved portion 15d connecting the curved portion 15f and the upstream end of the bottom portion 15b. The second curved portion 15d is curved in an arc shape along the peripheral surface of the front bottom roller 13a. The second curved portion 15d faces the peripheral surface of the front bottom roller 13a.
[0048] The curved surface portion 15f is disposed downstream of the clamping point P1 of the final delivery roller pair 13 in the feeding direction V of the fiber bundle F. The curved surface portion 15f faces the peripheral surface of the front bottom roller 13a of the final delivery roller pair 13 in the feeding direction V.
[0049] <Suction slit>
[0050] like Figure 2 and Figure 3 As shown, the width direction of the suction slit 27 coincides with the long side direction of the suction pipe 15. The suction slit 27 includes an upstream end portion 31 extending linearly in the width direction (the width direction of the suction slit 27), a guide edge portion 29 extending from one of the two ends in the width direction of the upstream end portion 31, a side edge portion 30 extending from the other end of the upstream end portion 31, and a downstream end portion 32 connected to the guide edge portion 29 and the side edge portion 30.
[0051] The guide edge 29 is an edge for converging the fiber bundle F. The guide edge 29 includes a widened portion 29a continuous with the upstream end portion 31 and a downstream portion 29b continuous with the widened portion 29a and extending obliquely to narrow the slit width.
[0052] Here, the direction perpendicular to the longitudinal direction of the suction pipe 15 is referred to as the perpendicular direction X. The fiber bundle F delivered from the final delivery roller pair 13 travels in the vicinity of the curved surface portion 15f of the guide surface 28 along the perpendicular direction X. In addition, the downstream portion 29b of the guide edge portion 29 is inclined with respect to the perpendicular direction X. Moreover, the fiber bundle F traveling along the perpendicular direction X on the guide surface 28 is guided by the guide edge portion 29 so as to travel along the widened portion 29a and the downstream portion 29b.
[0053] The side edge portion 30 includes a straight portion 30d extending straight from the upstream end portion 31 and a downstream portion 30c continuous with the straight portion 30d. The straight portion 30d extends straight parallel to the orthogonal direction X. The downstream portion 30c is inclined with respect to the orthogonal direction X.
[0054] From upstream to downstream in the conveying direction V, the slit width of the suction slit 27 is gradually widened by the widening portion 29a and the straight portion 30d, and then gradually narrowed by the downstream portion 29b and the straight portion 30d, and then is substantially constant due to the downstream portion 29b of the guide edge 29 and the downstream portion 30c of the side edge 30.
[0055] In addition, the ratio of the length of the widened portion 29a and the downstream portion 29b of the guide edge 29 of the suction slit 27, the ratio of the length of the straight portion 30d and the downstream portion 30c of the side edge 30, or the ratio of the length of the straight portion 30d relative to the entire side edge 30 is appropriately set according to the relationship formed with the inclination of the guide edge 29 or the required quality of the yarn to be spun, etc.
[0056] <Upstream end>
[0057] The upstream end portion 31 is formed by machining the suction pipe 15 with an end mill after forming the suction slit 27 in the suction pipe 15. Specifically, the upstream end portion 31 is formed by moving the end mill in the width direction of the suction slit 27 while bringing the end mill into contact with the upstream end portion 31.
[0058] like Figure 4 As shown, the upstream end 31 of the suction slit 27 is provided on the curved surface 15f. The upstream end 31 includes a cross surface 31a, a flow path expansion surface 31b, an introduction surface 31c, and an arcuate surface 31f. The cross surface 31a, the flow path expansion surface 31b, the introduction surface 31c, and the arcuate surface 31f extend over the entire upstream end 31 in the longitudinal direction of the suction pipe 15.
[0059] The introduction surface 31c is smoothly connected to the outer surface of the suction pipe 15 via the arcuate surface 31f. The introduction surface 31c is a flat inclined surface that slopes downward along the conveying direction V of the fiber bundle F as it goes from upstream to downstream.
[0060] like Figure 5 and Figure 6 As shown, an imaginary line passing through the introduction surface 31c and extending in the orthogonal direction X is referred to as the first imaginary line D1. The first imaginary line D1 is located on the front bottom roller 13a side of the common tangent line L at the clamping point P1. Specifically, the first imaginary line D1 is located on the bottom 15b side of the suction tube 15 closer to the common tangent line L. Here, if the extension direction of the common tangent line L is set as the common tangent line direction R, the extension direction of the first imaginary line D1 is consistent with the common tangent line direction R. Moreover, the introduction surface 31c is located closer to the front bottom roller 13a side than the common tangent line L, and therefore, the first imaginary line D1 is located away from the common tangent line L to the front bottom roller 13a side.
[0061] The angle between the first imaginary line D1 and the common tangent line L is referred to as the first angle θ1. In the present embodiment, the first angle θ1 is 0 degrees. Figure 5 and Figure 6, the first angle θ1 is not shown. As the first angle θ1 increases, the introduction surface 31c reaches the inner surface of the suction tube 15, so the flow path expansion surface 31b and the intersection surface 31a cannot be formed. Therefore, the maximum value of the first angle θ1 is set to an angle that can form the intersection surface 31a and the flow path expansion surface 31b.
[0062] In addition, as the first angle θ1 decreases, when the first angle θ1 is at a minimum value of 0 degrees, the first imaginary line D1 is parallel to the common tangent line L. When the first angle θ1 becomes 0 degrees, the direction in which the airflow flows along the introduction surface 31c coincides with the common tangent line direction R. In this way, the airflow can flow along the conveying direction V of the fiber bundle F output from the clamping point P1, which is preferable. Therefore, in the present embodiment, the first angle θ1 is 0 degrees.
[0063] The flow path expansion surface 31b is a flat surface that intersects the introduction surface 31c at an angle relative to the introduction surface 31c. In addition, the flow path expansion surface 31b is formed on the outer surface side of the inner surface of the suction pipe 15. The introduction surface 31c is located closer to the front bottom roller 13a side than the common tangent line L, so the flow path expansion surface 31b connected to the introduction surface 31c is also located closer to the front bottom roller 13a side than the common tangent line L. Moreover, the flow path expansion surface 31b extends in a manner away from the common tangent line L with the boundary between it and the introduction surface 31c as the starting point.
[0064] An imaginary line passing through the flow path expansion surface 31b and extending in the orthogonal direction X is referred to as a second imaginary line D2. The extension direction of the second imaginary line D2 intersects with the common tangent direction R. The angle between the second imaginary line D2 and the common tangent line L is referred to as a second angle θ2. The magnitude of the second angle θ2 is greater than the magnitude of the first angle θ1. In other words, the magnitude of the first angle θ1 is smaller than the magnitude of the second angle θ2.
[0065] As the second angle θ2 decreases, the intersection surface 31a cannot be formed, so the minimum value of the second angle θ2 is the angle at which the intersection surface 31a can be formed. As the second angle θ2 increases, the intersection surface 31a approaches the outer surface side of the suction pipe 15, so a portion that is recessed toward the outer surface side of the suction pipe 15 is formed between the flow path expansion surface 31b and the intersection surface 31a. This is not preferred because eddy currents are likely to be generated in the recessed portion. Therefore, it is preferred that the second angle θ2 be set so that the intersection surface 31a is orthogonal to the flow path expansion surface 31b.
[0066] The intersection surface 31a is a surface that intersects with the inner surface of the suction pipe 15. The intersection surface 31a is a flat surface that is orthogonal to the flow path expansion surface 31b. Therefore, the intersection surface 31a is orthogonal to the flow path expansion surface 31b and extends from the inner surface of the suction pipe 15 toward the flow path expansion surface 31b. In addition, a step is formed on the inner surface of the curved surface portion 15f of the suction pipe 15 by the intersection surface 31a and the flow path expansion surface 31b.
[0067] <Effects of implementation methods>
[0068] When the spinning frame is in operation, the fiber bundle F is drawn by the drawing device 12 and then delivered from the final delivery roller pair 13 toward the fiber bundle collecting device 11. Figure 5 As shown, the fiber bundle F is delivered from the final delivery roller pair 13 along the common tangent line L. Furthermore, the fiber bundle F is sucked by the air conveyor belt 16 due to the suction of the suction pipe 15, so that the fiber bundle F moves from the clamping point P1 of the final delivery roller pair 13 to the clamping point P2 of the delivery part 14. Thereafter, the fiber bundle F is guided by the guide surface 28 via the air conveyor belt 16, and is delivered in the delivery direction V by the air conveyor belt 16.
[0069] <Comparative Example>
[0070] Here, the upstream end portion 71 of the comparative example will be described.
[0071] like Figure 7 As shown by the arrow Y, due to the suction action of the suction duct, an airflow is generated that flows toward the upstream end 71 of the suction slit 27. The upstream end 71 of the comparative example has a plane 71a extending from the outer surface of the suction pipe 15 to the inner surface. The plane 71a of the upstream end 71 exceeds the common tangent line L and is located on the front lower roller 13a side, but does not have a flow path expansion surface 31b and a cross surface 31a. Therefore, at the upstream end 71 of the comparative example, the airflow flows along the plane 71a as it flows in the common tangent direction R. In this way, a vortex is generated in the area W between the inner surface of the suction pipe 15 and the airflow. In the comparative example, due to the vortex, the flow velocity of the airflow near the inner surface of the suction pipe 15 is reduced. Moreover, in the comparative example, the fiber bundle F output from the final output roller pair 13 is adsorbed by the air conveyor belt 16 on the front upper roller 13b side than the common tangent line L.
[0072] Next, the operation of the upstream end portion 31 according to the embodiment will be described in comparison with a comparative example.
[0073] like Figure 6As shown by the arrow Y, due to the suction action of the suction duct, an airflow is generated to flow toward the upstream end 31 of the suction slit 27. Since the introduction surface 31c of the upstream end 31 exceeds the common tangent line L and is located on the front bottom roller 13a side, the amount of airflow flowing toward the suction slit 27 can be increased compared to the case where the introduction surface 31c exceeds the common tangent line L and is located on the front top roller 13b side.
[0074] In addition, the flow path of the airflow after flowing along the introduction surface 31c is expanded by the flow path expansion surface 31b. Therefore, the airflow after flowing along the introduction surface 31c is caused to flow away from the common tangent line L by the flow path expansion surface 31b. In other words, the flow path of the airflow after flowing along the introduction surface 31c is expanded. Moreover, although a vortex is generated between the airflow after the flow path expansion and the inner surface of the suction pipe 15, the area W where the vortex is generated is smaller than that of the comparative example. As a result, even if a vortex is generated inside the suction pipe 15, the decrease in the airflow velocity caused by the vortex can be suppressed. Therefore, the fiber bundle F output from the final output roller pair 13 is adsorbed by the air conveyor belt 16 near the intersection between the common tangent line L and the second imaginary line D2. As a result, compared with the case where the fiber bundle F output from the final output roller pair 13 is adsorbed by the air conveyor belt 16 on the front upper roller 13b side of the common tangent line L as in the comparative example, it is possible to quickly adsorb the fiber bundle F output from the final output roller pair 13 to the air conveyor belt 16. As a result, the distance in which the fiber bundle F becomes free after being delivered from the final delivery roller pair 13 can be shortened.
[0075] According to the above-described embodiment, the following effects can be obtained.
[0076] (1) The amount of airflow flowing into the suction slit 27 can be increased by the introduction surface 31c located closer to the front bottom roller 13a than the common tangent line L. In addition, the area W of the eddy current generated along the inner surface of the suction pipe 15 can be reduced by the flow path expansion surface 31b. As a result, the amount of airflow sucked into the suction slit 27 can be increased by the upstream end portion 31, and the decrease in flow velocity due to the eddy current can be suppressed, so that the fiber bundle F can be quickly adsorbed to the air conveyor belt 16. Therefore, the state in which the fiber bundle F becomes free from the time of being delivered by the final delivery roller pair 13 to the time of being adsorbed by the air conveyor belt 16 can be shortened, so that the fiber turbulence of the fiber bundle F can be suppressed.
[0077] (2) The introduction surface 31c allows the airflow flowing in the common tangent direction R to be introduced as it is so as to be sucked into the suction slit 27. Compared with the case where the introduction surface 31c is not formed, the amount of airflow flowing into the suction slit 27 can be increased. As a result, the fiber bundle F can be adsorbed to the air-permeable conveyor belt 16 more quickly than in the case where the introduction surface 31c is not formed, and the fiber bundle F can be easily bundled. In addition, the flow path expansion surface 31b can reduce the area W where the vortex is generated. According to the above, the fiber bundle F can be quickly adsorbed and the suction force that can be bundled can be generated without increasing power consumption.
[0078] (3) The fiber bundle F delivered from the final delivery roller pair 13 can be quickly adsorbed to the air conveyor belt 16 by the upstream end portion 31. Thus, the quality of the yarn produced from the fiber bundle F can be stabilized.
[0079] (4) In order to quickly adsorb the fiber bundle F discharged from the final delivery roller pair 13 to the air conveyor belt 16, it is conceivable to bring the suction pipe 15 close to the front bottom roller 13a. However, in order to suppress clogging when the fiber bundle F is wound around the front bottom roller 13a, there is a limit to the degree to which the suction pipe 15 can be brought close to the front bottom roller 13a. However, by forming the introduction surface 31c and the flow path expansion surface 31b at the upstream end 31, the fiber bundle F discharged from the final delivery roller pair 13 can be quickly adsorbed to the air conveyor belt 16 without bringing the suction pipe 15 close to the front bottom roller 13a.
[0080] (5) The introduction surface 31c is an inclined surface intersecting the flow path expansion surface 31b. Therefore, the airflow can be efficiently introduced into the suction slit 27 through the introduction surface 31c.
[0081] (6) The introduction surface 31c is a flat inclined surface. For example, compared with a case where the introduction surface 31c is a curved inclined surface, the airflow can be introduced into the suction slit 27 more efficiently.
[0082] This embodiment can be implemented with modifications as follows. This embodiment and the following modifications can be implemented in combination with each other within a range that does not technically conflict.
[0083] The shape of the upstream end portion 31 of the suction slit 27 is not limited to a shape extending linearly along the longitudinal direction of the suction pipe 15, and may be a shape extending obliquely with respect to the orthogonal direction X, for example.
[0084] Instead of forming the air conveyor belt 16 from a woven fabric or a knitted fabric, the air conveyor belt 16 may be formed by opening a plurality of holes in a belt body made of rubber or an elastic resin.
[0085] ○ If Figure 8As shown, the introduction surface 31c may be formed by defining the inner surface of a through hole 33 that penetrates the curved surface portion 15f in the thickness direction.
[0086] ○ If Fig. 9 As shown, the first angle θ1 formed between the common tangent line L and the first imaginary line D1 may be larger than 0 degrees as long as it is smaller than the second angle θ2.
[0087] The magnitude of the second angle θ2 may be appropriately changed as long as it is larger than the first angle θ1.
[0088] The upstream end portion 31 may not include the intersecting surface 31 a intersecting the inner surface of the suction pipe 15 . In this case, the flow path expansion surface 31 b is formed along the inner surface of the suction pipe 15 .
[0089] The flow path expansion surface 31b and the intersection surface 31a do not need to be orthogonal as long as they intersect.
Claims
1. A fiber bundle bundling device in a spinning machine, comprising: a suction pipe provided on the downstream side of a final delivery roller pair including a bottom roller and a top roller and having a suction slit; and a permeable conveyor belt which conveys the fiber bundle by rotating while being wound around the suction pipe so as to cover the suction slit, The airflow flowing toward the suction slit causes the fiber bundle to be adsorbed on the air-permeable conveyor belt and the fiber bundle is bundled, and the fiber bundle is conveyed in a conveying direction by the air-permeable conveyor belt. The fiber bundle bundling device in the spinning machine is characterized in that: For the upstream end of the suction slit in the conveying direction, The device is provided on a curved portion of the suction pipe facing the bottom roller and comprises: an introduction surface which is located closer to the bottom roller than a common tangent line at a clamping point of the final delivery roller pair and which introduces the airflow into the suction slit; and a flow path expansion surface intersecting the introduction surface and located closer to the outer surface than the inner surface of the suction pipe, and expanding the flow path of the airflow than the flow path at the introduction surface, A first angle between a first imaginary line along the introduction surface and the common tangent line is smaller than a second angle between a second imaginary line along the flow path expansion surface and the common tangent line.
2. The fiber bundle bundling device in the spinning machine according to claim 1, It is characterized in that The introduction surface is an inclined surface forming the upstream end portion.
3. The fiber bundle bundling device in the spinning machine according to claim 2, It is characterized in that The inclined surface is a flat surface.
4. The fiber bundle bundling device in a spinning machine according to claim 1 or 2, It is characterized in that The introduction surface extends along a common tangent direction.
5. The fiber bundle bundling device in a spinning machine according to claim 1 or 2, It is characterized in that The upstream end portion includes an intersecting surface that is orthogonal to the flow path expansion surface and extends from the inner surface of the suction pipe toward the flow path expansion surface.
Citation Information
Patent Citations
Fiber bundle-gathering device used for spinning machine
CN102660818A
Drawing frame of a ring spinning machine
CN112352068A
Air fine spinning device
JP1995070833A
Spinning machine
JP2008202175A
Fiber bundle-gathering device in spinning machine
JP2012087419A