Method for constructing railway tunnel through open excavation of deep foundation pit
The open excavation and deep foundation pit method for railway tunnels addresses the risks of arch collapse and prolonged construction by using drainage systems and layered excavation to stabilize the site, enhancing safety and efficiency.
Patent Information
- Application Number
- CN202411264717.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-10
- Publication Date
- 2024-12-03
AI Technical Summary
Constructing railway tunnels through shallow sections with complex strata like silt soil and plain fill poses risks of arch collapse and prolonged construction periods due to complex processes and high costs, necessitating a simpler and more efficient method.
A method involving open excavation and deep foundation pit construction, including steps such as intercepting ditches, constructing protection piles, excavating in layers, and using drainage systems to manage water and stabilize the site, followed by initial support and lining construction.
This method reduces the risk of tunnel collapse, simplifies construction processes, and shortens the construction period by providing independent working faces and efficient resource allocation, ensuring safety and quality.
Smart Images

Figure CN119061936A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of tunnel construction, and in particular to a method for constructing a railway tunnel through an open deep foundation pit. Background Art
[0002] Due to the terrain, in order to ensure the smoothness of the tunnel and reduce the length of the tunnel, some sections have extremely shallow tunneling. However, if these sections encounter complex and unfavorable strata such as silt soil and plain fill, there is a risk of arch collapse and construction difficulty when using tunneling. At the same time, tunneling tunnels only have working faces at both ends, and construction needs to wait until the tunnel construction reaches this section before construction can begin, which prolongs the construction period of the project. In addition, if shallow tunneling is used, complex construction processes such as surface grouting or advanced curtain pre-grouting in the tunnel, long pipe shed in the tunnel, semi-sidewall pilot tunnel method / CRD / CD are generally required, which are complex processes and high costs.
[0003] Therefore, it is necessary to study a shallow buried tunnel construction method with simpler process, shorter construction period and more controllable risks.
[0004] Application Contents
[0005] The purpose of the present application is to provide a method for constructing a railway tunnel by open excavation and deep foundation pit, so as to solve the technical problems described in the background technology.
[0006] A method for constructing a railway tunnel by open excavation of a deep foundation pit, comprising the following steps:
[0007] Step S10: construct intercepting ditches on the ground. For ground drainage, set up soil water-blocking belts along the outer edge of the excavated foundation pit according to the terrain slope. Use geomembrane and sandbags on the water-facing surface to prevent surface water from flowing into the pit. For drainage in the pit, manually excavate circular drainage ditches around the pit bottom, and construct four water collection wells at the four corners of the foundation pit. At the same time, construct precipitation wells on both sides for precipitation operations. The drainage of precipitation wells is deep groundwater. Install deep well submersible pumps in each well, and determine the design parameters of each submersible pump according to the stable water level and water production.
[0008] Step S20: construct foundation pit protection piles. The foundation pit protection piles are constructed with bored cast-in-place piles. The pile bodies are made of reinforced concrete. The protection piles are arranged outside the lining structure and are constructed with rotary drilling.
[0009] Step S30: excavate from the original ground step by step, and construct slope protection; excavate the foundation pit to the bottom of the crown beam, construct the crown beam and cross brace; continue to excavate the foundation pit to the bottom of the guide wall, construct the dark excavation side guide wall and large pipe shed; continue to excavate the foundation pit to the bottom of the waist beam, construct the waist beam and cross brace; continue to excavate the tunnel to the designed bottom elevation, and process the base;
[0010] Step S40: initial support and lining construction of the inverted arch, longitudinally burying drainage pipes before construction, vertically pre-burying perforated corrugated pipes, and using drainage pipes to drain water to the central ditch before the inverted arch filling construction;
[0011] Step S50: dismantle the lateral supports of the waist beam and the crown beam, and construct the lining of the open-cut arch of the tunnel. Use the assembled two-lining trolley as the inner mold, tie the lining steel bars on the trolley, seal the outer mold with wooden boards, and reinforce the outer back with I-beams;
[0012] Step S60: Backfilling the top of the open hole: Before backfilling, concrete interlayers are built on both sides of the arch waist, and longitudinal drainage pipes are laid on them. They are introduced into the arch drainage system through vertical pre-buried perforated corrugated pipes. A crushed stone filter layer is laid on the longitudinal drainage pipes. After the waterproof layer of the lining arch is constructed, the soil and stone are backfilled symmetrically in layers.
[0013] Furthermore, the excavation is carried out step by step with sloping and segmented excavation. The first layer is excavated to the bottom of the crown beam, and the earth and stone are excavated backwards from one side of the line to the other side, and a transportation channel is reserved on the other side; the second layer is excavated to the bottom of the waist beam, and after the pile top crown beam and the first horizontal support within the construction range are completed and the strength meets the design requirements, a small excavator in the foundation pit is used to transport the earth and stone, and a long-arm excavator is used above the construction platform to excavate; the third layer is excavated to the reserved soil layer, and the method of longitudinal segmentation and horizontal layered excavation is adopted. The small excavator in the foundation pit is used to transport the earth and stone, and the crawler electric vertical grab is used to excavate the earth and stone above the construction platform; the excavation is completed backwards to the large mileage at the junction of the light and dark ends.
[0014] Furthermore, the soil water-blocking strip is 30×30cm; the annular drainage ditch is 30×30cm with a slope of 0.3%; the water collection well is 50×50×100cm; and the water level in the well is controlled to be 0.5m below the tunnel bottom.
[0015] Furthermore, the foundation pit protection pile retaining structure adopts φ1000mm bored cast-in-place piles, the pile body adopts C35 reinforced concrete, the spacing is 1.2m, and the retaining piles adopt C-type piles, and the pile distance is 10cm from the outside of the lining structure.
[0016] Furthermore, the temporary slopes on both sides of the foundation pit adopt a slope of 1:1.5, and Φ22 mortar anchors are installed in a plum blossom shape with a spacing of 1.2m. C25 sprayed concrete is sprayed and protected with a 15cm thick anchor sprayed net. The upper permanent back slopes at both ends of the foundation pit are protected by a 1:1 skeleton slope protection with grass planted inside the skeleton, and the lower temporary slopes are protected by an anchor sprayed net.
[0017] Furthermore, the crown beam and waist beam of the foundation pit in step S30 are 1m×1m C35 reinforced concrete structures; the guide wall is made of C35 concrete, 1m thick and 1m long in the longitudinal direction; a ring of Φ108 large pipe sheds is set at 180° on the arch to pre-support the hole; the pipe shed is 30m long and has a circumferential spacing of 0.4m. Cement mortar is poured and filled densely, and Φ42 advanced small guide tubes are set between the pipe sheds; base treatment: according to the geological conditions, the foundation reinforcement can be selected by replacing Sanqi lime soil or compaction piles.
[0018] Furthermore, in step S40, a Φ100 drainage pipe is buried longitudinally before construction and drained horizontally to the ditch cable trough, a Φ50 HDPE perforated corrugated pipe is pre-buried vertically, and a Φ100 drainage pipe is used to drain water to the central ditch before the invert filling construction.
[0019] Furthermore, in step S50, the open hole arch lining is sealed with a 5 cm thick wooden board on the outer mold and reinforced with an I12 I-beam on the outer back.
[0020] Furthermore, in step S60, the top of the open hole is backfilled, and before backfilling, a C20 concrete interlayer is built on both sides of the arch waist, on which a longitudinal Φ100 drainage pipe is laid, which is introduced into the arch drainage system through a vertically pre-buried Φ50 HDPE perforated corrugated pipe, and a crushed stone filter layer is laid on the longitudinal Φ100 drainage pipe. After the waterproof layer is constructed on the lining arch, the soil and stone are backfilled symmetrically in layers.
[0021] Compared with the prior art, the advantages and positive effects of the present invention are: it can avoid the safety risk of tunnel top collapse in shallow buried dark-excavated tunnels with complex geological conditions such as silt fill strata, and can provide independent working face construction; it can reduce complex construction processes such as advanced curtain pre-grouting, long pipe sheds in the tunnel, semi-side wall pilot tunnel method / CRD / CD, and does not require gradual construction from one side of the dark tunnel, thus ensuring construction efficiency, effectively alleviating construction period pressure, and having good application prospects. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the background technology, the drawings required for use in the embodiments of the present application or the background technology will be described below.
[0023] Figure 1 The present invention is a schematic structural axial diagram of an embodiment of a method for constructing a railway tunnel by open excavation and deep foundation pit.
[0024] Figure 2 The present invention is a radial schematic diagram of an embodiment of a method for constructing a railway tunnel by open excavation deep foundation pit.
[0025] Figure 3 The present invention is a construction flow chart of an embodiment of a method for constructing a railway tunnel by open excavation deep foundation pit.
[0026] Figure 4The present invention is a simplified construction process diagram of an embodiment of a method for constructing a railway tunnel by open excavation deep foundation pit. DETAILED DESCRIPTION
[0027] Example embodiments will now be described more fully with reference to the accompanying drawings. However, example embodiments can be implemented in many forms and should not be construed as limited to the embodiments set forth herein; rather, these embodiments are provided so that this application will be comprehensive and complete and will fully convey the concepts of the example embodiments to those skilled in the art. The same reference numerals in the figures represent the same or similar parts, and thus their repeated description will be omitted.
[0028] The endpoints and any values of the ranges disclosed in this article are not limited to the precise ranges or values, and these ranges or values should be understood to include values close to these ranges or values. For numerical ranges, the endpoint values of each range, the endpoint values of each range and the individual point values, and the individual point values can be combined with each other to obtain one or more new numerical ranges, which should be considered as specifically disclosed in this article.
[0029] In addition, the terms "include" and "have" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but may optionally include steps or units that are not listed, or may optionally include other steps or units that are inherent to these processes, methods, products or devices.
[0030] The terms "first", "second" and the like in the specification and claims of this application and the above drawings are used to distinguish different objects rather than to describe a specific order.
[0031] The following is a clear and complete description of the technical solution of the present application in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present application.
[0032] As the instruction manual Figure 1-4 As shown:
[0033] A method for constructing a railway tunnel by open excavation of a deep foundation pit, comprising the following steps:
[0034] Step S10: construct intercepting ditches on the ground. For ground drainage, set up soil water-blocking belts along the outer edge of the excavated foundation pit according to the terrain slope. Use geomembrane and sandbags on the water-facing surface to prevent surface water from flowing into the pit. For drainage in the pit, manually excavate circular drainage ditches around the pit bottom, and construct four water collection wells at the four corners of the foundation pit. At the same time, construct precipitation wells on both sides for precipitation operations. The drainage of precipitation wells is deep groundwater. Install deep well submersible pumps in each well, and determine the design parameters of each submersible pump according to the stable water level and water production.
[0035] Step S20: construct foundation pit protection piles. The foundation pit protection piles are constructed with bored cast-in-place piles. The pile bodies are made of reinforced concrete. The protection piles are arranged outside the lining structure and are constructed with rotary drilling.
[0036] Step S30: excavate from the original ground step by step, and construct slope protection; excavate the foundation pit to the bottom of the crown beam, construct the crown beam and cross brace; continue to excavate the foundation pit to the bottom of the guide wall, construct the dark excavation side guide wall and the large pipe shed; continue to excavate the foundation pit to the bottom of the waist beam, construct the waist beam and cross brace; continue to excavate the tunnel to the designed bottom elevation, and process the base;
[0037] Step S40: initial support and lining construction of the inverted arch, longitudinally burying drainage pipes before construction, vertically pre-burying perforated corrugated pipes, and using drainage pipes to drain water to the central ditch before the inverted arch filling construction;
[0038] Step S50: dismantle the lateral supports of the waist beam and the crown beam, and construct the lining of the open-cut arch of the tunnel. Use the assembled two-lining trolley as the inner mold, tie the lining steel bars on the trolley, seal the outer mold with wooden boards, and reinforce the outer back with I-beams;
[0039] Step S60: Backfilling the top of the open hole: Before backfilling, concrete interlayers are built on both sides of the arch waist, and longitudinal drainage pipes are laid on them. They are introduced into the arch drainage system through vertical pre-buried perforated corrugated pipes. A crushed stone filter layer is laid on the longitudinal drainage pipes. After the waterproof layer of the lining arch is constructed, the soil and stone are backfilled symmetrically in layers.
[0040] The method of constructing a railway tunnel through an open-cut deep foundation pit in this embodiment can avoid the safety risk of tunnel top collapse in shallow buried dark-cut tunnels with complex geological conditions such as silt fill strata, and can provide independent working face construction; it reduces complex construction techniques such as advance curtain pre-grouting, long pipe sheds in the tunnel, and semi-side wall pilot tunnel method / CRD / CD, and does not require step-by-step construction from one side of the dark tunnel, thereby ensuring construction efficiency, effectively alleviating construction period pressure, and having good application prospects.
[0041] Specifically, in step S30, the excavation is carried out step by step, and the excavation is carried out in layers and sections. The first layer is excavated to the bottom of the crown beam, and the earth and stone are excavated backward from one side of the line to the other side of the line, and a transportation channel is reserved on the other side; the second layer is excavated to the bottom of the waist beam, and after the pile top crown beam and the first lateral support within the construction range are completed and the strength meets the design requirements, a small excavator in the foundation pit is used to reverse the transportation, and a long-arm excavator is used above the construction platform to excavate; the third layer is excavated to the reserved soil layer position, and the longitudinal segmentation and horizontal layering excavation method is adopted, and the small excavator in the foundation pit is reversed, and the crawler electric vertical grab is used to excavate above the construction platform; the excavation is completed backward from the bright and dark junction to the large mileage. Thereby further reducing the unstable factors of the slope, reducing the risk of landslide and collapse, ensuring construction safety and quality; through reasonable planning of construction steps and resource allocation, reasonable allocation of construction resources and manpower, more effectively controlling construction costs and improving construction efficiency; reducing interference with the surrounding environment, including reducing noise and vibration, and protecting surrounding buildings and facilities.
[0042] Specifically, in step S10, the soil water blocking belt is 30×30 cm; the annular drainage ditch is 30×30 cm with a slope of 0.3%; the water collection well is 50×50×100 cm; and the water level in the well is controlled to be 0.5 m below the tunnel bottom.
[0043] Specifically, in step S20, the foundation pit protection pile retaining structure adopts φ1000mm bored cast-in-place piles, the pile body adopts C35 reinforced concrete, the spacing is 1.2m, and the retaining piles adopt C-type piles, and the pile distance is 10cm outside the lining structure.
[0044] Specifically, in step S20, the temporary slopes on both sides of the foundation pit adopt a slope of 1:1.5, Φ22 mortar anchors are installed in a plum blossom shape with a spacing of 1.2m, C25 sprayed concrete is sprayed, and a 15cm thick anchor sprayed net is used for protection. The upper permanent back slopes at both ends of the foundation pit are protected by a 1:1 skeleton slope protection, grass is planted inside the skeleton, and the lower temporary slopes are protected by an anchor sprayed net.
[0045] Specifically, the crown beam and waist beam of the foundation pit in step S30 are 1m×1m C35 reinforced concrete structures; the guide wall is made of C35 concrete, 1m thick and 1m long in the longitudinal direction; a ring of Φ108 large pipe sheds is set at 180° on the arch to pre-support the hole; the pipe shed is 30m long and has a circumferential spacing of 0.4m. Cement mortar is poured to fill the hole tightly, and Φ42 advanced small guide tubes are set between the pipe sheds; base treatment: according to the geological conditions, the foundation reinforcement can be carried out by replacing the 37 ash soil or compaction piles.
[0046] Specifically, in step S40, a Φ100 drainage pipe is buried longitudinally before construction and drained horizontally to the ditch cable trough, a Φ50 HDPE perforated corrugated pipe is pre-buried vertically, and a Φ100 drainage pipe is used to drain water to the central ditch before the invert filling construction.
[0047] Specifically, in step S50, the open hole arch lining is sealed with a 5 cm thick wooden board on the outer mold, and reinforced with an I12 I-beam on the outside.
[0048] Specifically, in step S60, the top of the open hole is backfilled, and before backfilling, a C20 concrete interlayer is built on both sides of the arch waist, on which a longitudinal Φ100 drainage pipe is laid, and introduced into the arch drainage system through a vertical pre-buried Φ50 HDPE perforated corrugated pipe, a crushed stone filter layer is laid on the longitudinal Φ100 drainage pipe, and after the waterproof layer of the lining arch is constructed, the soil and stone are symmetrically backfilled in layers.
[0049] In this embodiment, through a large number of engineering tests, explorations and verifications, the dimensions and specific structures of structures such as water-blocking strips, drainage ditches, foundation pit protection pile retaining structures, temporary slopes, foundation pit crown beams and waist beams, and open-cut arch lining outer formwork were confirmed, which improved the safety of the method of constructing railway tunnels in open deep foundation pits and consolidated the construction quality of open foundation pits.
[0050] In the description of this specification, specific features, structures, materials or characteristics may be combined in an appropriate manner in any one or more embodiments or examples.
[0051] The above are only specific implementations of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
Claims
1. A method for constructing a railway tunnel by excavating a deep foundation pit, characterized in that the steps include: Step S10: construct intercepting ditches on the ground. For ground drainage, set up soil water-blocking belts along the outer edge of the excavated foundation pit according to the terrain slope. Use geomembrane and sandbags on the water-facing surface to prevent surface water from flowing into the pit. For drainage in the pit, manually excavate circular drainage ditches around the pit bottom, and construct four water collection wells at the four corners of the foundation pit. At the same time, construct precipitation wells on both sides for precipitation operations. The drainage of precipitation wells is deep groundwater. Install deep well submersible pumps in each well, and determine the design parameters of each submersible pump according to the stable water level and water production. Step S20: construct foundation pit protection piles. The foundation pit protection piles are constructed with bored cast-in-place piles. The pile bodies are made of reinforced concrete. The protection piles are arranged outside the lining structure and are constructed with rotary drilling. Step S30: excavate from the original ground step by step, and construct slope protection; excavate the foundation pit to the bottom of the crown beam, construct the crown beam and cross brace; continue to excavate the foundation pit to the bottom of the guide wall, construct the dark excavation side guide wall and the large pipe shed; continue to excavate the foundation pit to the bottom of the waist beam, construct the waist beam and cross brace; continue to excavate the tunnel to the designed bottom elevation, and process the base; Step S40: initial support and lining construction of the inverted arch, longitudinally burying drainage pipes before construction, vertically pre-burying perforated corrugated pipes, and using drainage pipes to drain water to the central ditch before the inverted arch filling construction; Step S50: dismantle the lateral supports of the waist beam and the crown beam, and construct the lining of the open-cut arch of the tunnel. Use the assembled two-lining trolley as the inner mold, tie the lining steel bars on the trolley, seal the outer mold with wooden boards, and reinforce the outer back with I-beams; Step S60: Backfilling the top of the open hole: Before backfilling, concrete interlayers are built on both sides of the arch waist, and longitudinal drainage pipes are laid on them. They are introduced into the arch drainage system through vertical pre-buried perforated corrugated pipes. A crushed stone filter layer is laid on the longitudinal drainage pipes. After the waterproof layer of the lining arch is constructed, the soil and stone are backfilled symmetrically in layers.
2. The method for constructing a railway tunnel by open excavation deep foundation pit according to claim 1, characterized in that: The step-by-step slope excavation in step S30 is carried out in layers and sections. The first layer is excavated to the bottom of the crown beam, and the earth and stone are excavated backward from one side of the line to the other side of the line, and a transportation channel is reserved on the other side; the second layer is excavated to the bottom of the waist beam, and after the pile top crown beam and the first lateral support within the construction range are completed and the strength meets the design requirements, a small excavator in the foundation pit is used to transport the earth and stone, and a long-arm excavator is used above the construction platform to excavate; the third layer is excavated to the reserved soil layer position, and a longitudinal segmented and horizontal layered excavation method is adopted. A small excavator in the foundation pit is used to transport the earth and stone, and a crawler-type electric vertical grab is used to excavate the earth and stone above the construction platform; the excavation is completed backward from the bright and dark boundary to the large mileage.
3. The method for constructing a railway tunnel through an open-cut deep foundation pit according to any one of claims 1 to 2, characterized in that: In step S10, the soil water blocking strip is 30×30 cm; the annular drainage ditch is 30×30 cm with a slope of 0.3%; the water collection well is 50×50×100 cm; and the water level in the well is controlled to be 0.5 m below the tunnel bottom.
4. The method for constructing a railway tunnel through an open-cut deep foundation pit according to any one of claims 1 to 2, characterized in that: In step S20, the foundation pit protection pile retaining structure adopts φ1000mm bored cast-in-place piles, the pile body adopts C35 reinforced concrete, the spacing is 1.2m, and the retaining piles adopt C-type piles, and the pile distance is 10cm from the outside of the lining structure.
5. The method for constructing a railway tunnel in an open-cut deep foundation pit according to any one of claims 1-2, characterized in that: In step S20, the temporary slopes on both sides of the foundation pit adopt a slope of 1:1.5, Φ22 mortar anchors are installed in a plum blossom shape with a spacing of 1.2m, C25 sprayed concrete is sprayed, and 15cm thick anchor sprayed nets are used for protection. The upper permanent back slopes at both ends of the foundation pit are protected by a 1:1 skeleton slope protection, grass is planted inside the skeleton, and the lower temporary slopes are protected by anchor sprayed nets.
6. The method for constructing a railway tunnel through an open-cut deep foundation pit according to any one of claims 1 to 2, characterized in that: The top beam and waist beam of the foundation pit in step S30 are 1m×1m C35 reinforced concrete structures; the guide wall is made of C35 concrete, 1m thick and 1m long in the longitudinal direction; a ring of Φ108 large pipe sheds is set at 180° on the arch to pre-support the hole; the pipe shed is 30m long and 0.4m apart in the annular direction; cement mortar is poured to fill the hole tightly, and Φ42 advanced small guide tubes are set between the pipe sheds; base treatment: according to the geological conditions, the foundation reinforcement can be carried out by replacing the 37 ash soil or compaction piles.
7. The method for constructing a railway tunnel in an open-cut deep foundation pit according to any one of claims 1 to 2, characterized in that: In the step S40, a Φ100 drainage pipe is buried longitudinally before construction and drained horizontally to the ditch cable trough, a Φ50 HDPE perforated corrugated pipe is pre-buried vertically, and a Φ100 drainage pipe is used to drain water to the central ditch before the invert filling construction.
8. The method for constructing a railway tunnel through an open-cut deep foundation pit according to any one of claims 1 to 2, characterized in that: In the step S50, the open hole arch lining is sealed with a 5 cm thick wooden board on the outer mold and reinforced with an I12 I-beam on the outer back.
9. The method for constructing a railway tunnel through an open-cut deep foundation pit according to any one of claims 1 to 2, characterized in that: In the step S60, the top of the open hole is backfilled, and before backfilling, a C20 concrete interlayer is built on both sides of the arch waist, on which a longitudinal Φ100 drainage pipe is laid, which is introduced into the inverted arch drainage system through a vertically pre-buried Φ50 HDPE perforated corrugated pipe, and a crushed stone filter layer is laid on the longitudinal Φ100 drainage pipe.