Reinforcing method for steel skeleton light-strength plate

By positioning and installing the steel mesh and reinforcing it with ultra-high ductile fiber concrete, the problem of the reduction of strength of the steel frame light-strength plate in later maintenance is solved, the structural performance and durability are improved, and the needs of tight construction periods and low-carbon and environmental protection are adapted to the needs of tight construction periods and low-carbon environmental protection. .

CN119062148AInactive Publication Date: 2024-12-03UNIV OF JINAN +1
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202411565053.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-05
Publication Date
2024-12-03
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The steel frame light-strength plate has problems of strength reduction and rust during later maintenance and repair, which makes it difficult to carry out reinforcement work and is time-consuming and labor-intensive to push down and reconstruction.

Method used

By measuring and positioning the position of the steel mesh, installing bidirectional steel bars and stretching bars, using ultra-high ductile fiber concrete for construction, strengthening the connection and overall strength of the steel mesh, and strengthening by spraying or applying concrete.

Benefits of technology

It significantly improves the compression, overturning and seismic resistance of the steel frame light-strength plate, extends the durability of the structure, shortens the construction cycle, is suitable for projects with tight construction periods, and saves post-maintenance and repair costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119062148A_ABST
    Figure CN119062148A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building and civil engineering, in particular to a reinforcing method for a steel framework light and strong plate. Step A, measuring and positioning the position of a reinforcing mesh II; step B, mounting a reinforcing mesh I; c, concrete construction is carried out, the first reinforcing mesh comprises two-way reinforcing steel bars and tie bars, each tie bar is an S-shaped reinforcing steel bar, the specific construction step of measuring and positioning the position of the second reinforcing mesh comprises the steps that the position of the second reinforcing mesh on the lower portion of the roof panel is detected through a reinforcing steel bar position detector, and main ribs are fixedly connected to the two sides of the two-way reinforcing steel bars. The upper portions of the tie bars and the first reinforcing mesh (the original reinforcing mesh) are tied, the lower portions of the tie bars and the reinforcing ribs newly added on the first reinforcing mesh are tied, then ultrahigh ductility concrete is sprayed or smeared, the tie bars are S-shaped steel bars and can be conveniently hung on the first reinforcing mesh and the second reinforcing mesh, and the reinforcing work effect of the steel skeleton light-strength plate is enhanced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction and civil engineering, and in particular to a reinforcement method for a steel frame light-strength plate. Background Art

[0002] The development of new materials has become an unstoppable trend. Building materials are the material basis for the development of the construction industry. The material cost alone accounts for two-thirds of the total construction cost. At present, there are many types of new building materials, and steel frame light-strength plate is one of them. The main force-bearing component of the steel frame light-strength plate is the steel frame. The frame section is adjusted according to the load size and span requirements, and the plate span can be flexibly arranged according to the column spacing. The foamed concrete perlite core material is a lightweight material containing lightweight closed pores formed by filling the casting mold with a lightweight inorganic modified cement perlite composite core material and curing naturally. Its thickness is adjusted according to energy-saving requirements, which can meet the requirements of building thermal insulation in various regions of China. Various materials ensure the realization of various functions of the steel frame light-strength plate through reasonable design and process measures; the steel frame light-strength plate has a reasonable node design, quick installation, convenient maintenance, flexible plate type, and is not restricted by fixed molds. It can be matched according to the requirements of architectural design to meet the needs of users to the maximum extent.

[0003] At present, more and more people are using steel frame light-strong panels in construction projects. Compared with ordinary cast-in-place concrete panels, steel frame light-strong panels have lower rigidity due to their light weight and high strength and lack of coarse aggregate. When the panel strength is reduced or the steel mesh and steel frame are rusted due to unreasonable structural measures, reinforcement work is difficult to carry out, and demolition and reconstruction will take a lot of time, financial and material resources, which is not convenient for the later maintenance and repair of steel frame light-strong panels. Summary of the invention

[0004] In order to facilitate the reinforcement work of the steel frame light-strong plate, the present invention provides a reinforcement method for the steel frame light-strong plate.

[0005] The present invention provides a reinforcement method for a steel frame light-strength plate using the following technical solutions: A reinforcement method for a steel skeleton light-strength plate comprises the following steps: step A, measuring and positioning the position of a second steel mesh; step B, installing a first steel mesh; and step C, concrete construction.

[0006] By adopting the above technical solution, the steel frame light-strong plate is reinforced by steel mesh and concrete construction, which is not affected by the environment or seasons, shortens the construction period, and is particularly suitable for projects with tight construction schedules. At the same time, it adapts to the current social needs of low-carbon environmental protection, promotion of green buildings, and green construction.

[0007] Preferably, in step A, the specific construction steps of measuring and locating the position of the second steel mesh include: a steel bar position detector detects the position of the second steel mesh at the lower part of the roof panel.

[0008] By adopting the above technical solution, it is convenient to hang the steel mesh one at a later stage, and it is also convenient to confirm the length and width of the steel mesh one, so as to avoid mismatch between the steel mesh one and the steel mesh two.

[0009] Preferably, the steel mesh 1 includes bidirectional steel bars, tie bars, two main ribs and two end ribs, each of the tie bars is an S-shaped steel bar, both sides of the bidirectional steel bars are fixedly connected to the corresponding main ribs, both sides of the bidirectional steel bars are fixedly connected to the corresponding end ribs, and the steel mesh 2 is located inside the two main ribs and the two end ribs.

[0010] By adopting the above technical solution, the upper and lower parts of the S-shaped steel bars are respectively connected to the first steel mesh and the second steel mesh, and the overall strength is enhanced after the concrete is constructed.

[0011] Preferably, a plurality of reinforcing ribs in a linear array are fixedly connected inside the two main ribs along the length direction, and a plurality of reinforcing ribs in a linear array are fixedly connected inside the two main ribs along the length direction.

[0012] By adopting the above technical solution, the strength of steel mesh one is strengthened by reinforcing ribs, the connection between steel mesh two and the main rib is strengthened by reinforcing ribs, the main rib is connected to steel mesh one, and then the connection between steel mesh one and steel mesh two is strengthened.

[0013] Preferably, in step B, the specific construction steps of installing the steel mesh one include: the steel mesh one is tied to the steel mesh two by tensioning bars.

[0014] Preferably, the top end of each of the tie bars is suspended on the steel bars in the second steel mesh, wherein a portion of the reinforcing bars are suspended in the bottom of the corresponding tie bars, a portion of the bidirectional steel bars are suspended in the bottom of the corresponding tie bars, and the bottom of the reinforcing ribs is fixedly connected to the top of the second steel mesh.

[0015] By adopting the above technical solution, steel mesh 1 is hung at the lower part of the roof panel and tied to the original steel mesh 2 in the lightweight concrete of the roof panel. The connection between steel mesh 1 and steel mesh 2 is strengthened by tensioning, and steel mesh 1 is reinforced. At the same time, a large deviation of steel mesh 1 during concrete construction is avoided.

[0016] Preferably, in step C, the specific construction steps of the concrete construction include: C1, processing the lightweight concrete at the bottom of the roof panel; C2, layered concrete construction; C3, curing concrete.

[0017] By adopting the above technical solution, the steel frame light-strength plate is further reinforced with concrete, and the concrete is well maintained, which can save time for later maintenance and repair of the steel frame light-strength plate.

[0018] Preferably, in step C1, the specific construction steps of treating the lightweight concrete at the bottom of the roof panel include: stripping off the polymer mortar glass fiber layer, roughening the roof panel lightweight concrete with tools, cleaning the floating dust on the roof panel lightweight concrete, and spraying water to moisten the surface of the roof panel lightweight concrete; after the roof panel lightweight concrete is dry, evenly applying a layer of interface agent.

[0019] By adopting the above technical solution, ultra-high ductility fiber concrete can be constructed conveniently and evenly.

[0020] Preferably, in step C2, the specific construction steps of the layered concrete construction include: spraying concrete onto the first steel mesh, pressing and smearing the latter layer of concrete within two hours after the pressing and smearing of the previous layer of concrete, leveling the other layers of concrete, and leveling and finishing the surface of the last layer of concrete; applying concrete to the first steel mesh, pressing and smearing the latter layer of concrete within two hours after the pressing and smearing of the previous layer of concrete, leveling the other layers of concrete, and leveling and finishing the surface of the last layer of concrete.

[0021] By adopting the above technical solution, through applying or spraying ultra-high ductility concrete, two concrete construction methods are adapted to different construction environments, and both construction methods are easy to use, economical and applicable, and easy to promote.

[0022] Preferably, in step C3, the specific construction steps of curing the concrete include: regularly performing moisture-maintaining curing after the concrete has finally set, and the curing time is not less than seven days.

[0023] By adopting the above technical solution, the strength of concrete is enhanced through concrete curing, and the steel frame light-strong panels are stored under suitable temperature and humidity conditions to avoid strength reduction, cracking or warping of the light-strong panels.

[0024] In summary, the present invention has the following beneficial technical effects: 1. The present invention hangs a second steel mesh at the bottom of the roof panel and connects it with the first steel mesh (original steel mesh) in the lightweight concrete of the roof panel, that is, the upper part of the tie bar is connected with the first steel mesh (original steel mesh), and the lower part of the tie bar is connected with the reinforcing bar newly added on the first steel mesh, and then spraying or applying ultra-high ductility concrete, and the connection between the first steel mesh and the second steel mesh is reinforced by the tie bar. The tie bar is an S-shaped steel bar, which is convenient to hang on the first steel mesh and the second steel mesh, which is conducive to the reinforcement of the steel skeleton light strong plate; 2. The present invention facilitates the reinforcement of the steel frame light-strong plate through the construction of ultra-high ductility fiber concrete, strengthens the connection between the steel mesh 1 and the steel mesh 2, and can reinforce the house at the same time, improve the bearing capacity of the steel mesh 1 and the steel mesh 2, and significantly improve the compression resistance, anti-overturning and seismic performance of the house. Its crack dispersion ability can improve the structural impermeability and improve the durability of the structure. At the same time, the ultra-high ductility fiber concrete can be well maintained, which can save the later maintenance and repair of the steel frame light-strong plate, and reduce the time and financial and material resources spent on the maintenance and repair of the steel frame light-strong plate; 3. The concrete construction of the present invention can be carried out by spraying or smearing concrete. According to the specific conditions of the roof panel and local conditions, the method of spraying, rotary spraying or smearing can be flexibly adopted to carry out the construction of ultra-high ductility concrete. The construction is simple and fast, not affected by the season, greatly improving the construction efficiency and shortening the construction period. It is especially suitable for projects with tight construction period. In addition, the technology is easy to construct, economical and applicable, and easy to promote. At the same time, it meets the current social needs of low-carbon environmental protection, promotion of green buildings and green construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 The present invention is a structural schematic diagram of the bottom surface of a roof panel in a reinforcement method for a steel frame light-strength panel.

[0026] Figure 2 is along Figure 1 Sectional view along line AA; Figure 3 is along Figure 1 Sectional view of the mid-CC line; Figure 4 yes Figure 3 Schematic diagram of the structure of the middle main rib; Figure 5 yes Figure 2 Schematic diagram of the structure of the middle rib; Figure 6 yes Figure 2 Schematic diagram of the structure of the middle reinforcement rib; Figure 7 The present invention is a structural schematic diagram of a reinforcement method for a steel skeleton light-strength plate.

[0027] Description of reference numerals: 1. Steel mesh 1; 11. Bidirectional steel bars; 12. Tie bars; 2. Steel mesh 2; 3. Main rib; 4. Reinforcement rib; 5. Reinforcing ribs; 6. End ribs; 7. Sprayed or applied ultra-high ductility fiber concrete. DETAILED DESCRIPTION

[0028] The following is combined with Figure 1-Figure 7 The present invention is described in further detail.

[0029] Steel frame light-strength panels are mainly suitable for various industrial plants, large warehouses, supermarkets, public buildings, stadiums, schools, house additions (mezzanines), trestle walkways and other industrial and civil buildings. They can be used in conjunction with concrete structures, steel structures and large-span space structures.

[0030] Attached Figure 1-Figure 7 In the figure, L and B represent the length and width of the steel skeleton light-strength plate, respectively, and HZ and BZ represent the height and width of the main rib 3, respectively.

[0031] The embodiment of the present invention discloses a reinforcement method for a steel frame light-strength plate.

[0032] Reference Figure 1 , Figure 2 , Figure 5 , including the following steps; step A, measuring and locating the position of steel mesh 2, steel mesh 2 is the original steel mesh in the house; step B, installing steel mesh 1, steel mesh 1 is a new steel mesh newly added as a reinforcement support; step C, concrete construction, using ultra-high ductility concrete (UHDC), during construction, the ambient temperature should not be lower than 5°C, without disturbing steel mesh 1 and steel mesh 2, by applying or spraying UHDC surface layer on the outer wall of steel mesh 1, the bearing capacity of the original structure can be improved, the durability can be improved, and the quality of the steel skeleton light-strong plate can be avoided to be directly affected by concrete construction.

[0033] Reference Figure 1 In step A, the specific construction steps of measuring and locating the position of the steel mesh 2 include: using a steel bar position detector to detect the position of the steel mesh 2 at the lower part of the roof panel, and using the steel bar position detector to detect the steel mesh 2 (original steel mesh) to determine the specific position.

[0034] Reference Figure 1 , Figure 2 , Figure 3 , Figure 5 , Figure 6 The steel mesh 1 includes bidirectional steel bars 11, tie bars 12, two main ribs 3 and two end ribs 6. Each tie bar 12 is an S-shaped steel bar. Both sides of the bidirectional steel bars 11 are fixedly connected to the corresponding main ribs 3. Both sides of the bidirectional steel bars 11 are fixedly connected to the corresponding end ribs 6. The steel mesh 2 is located inside the two main ribs 3 and the two end ribs 6. The main ribs 3 and the end ribs 6 protect the bidirectional steel bars 11 and the steel mesh 2 around. The steel mesh 1 is also connected to the steel mesh 2 through the main ribs 3 and the end ribs 6.

[0035] Reference Figure 1 , Figure 2A plurality of reinforcing ribs 4 in a linear array are fixedly connected to the inside of the two main ribs 3 along the length direction. The reinforcing ribs 4 strengthen the connection between the steel mesh 1 and the main rib 3. The reinforcing ribs 4 and the steel mesh 2 are spot welded. The two ends of the reinforcing ribs 4 are respectively welded to the inside of the two main ribs 3. A plurality of reinforcing ribs 5 in a linear array are fixedly connected to the inside of the two main ribs 3 along the length direction. The reinforcing ribs 5 are spot welded to the top of the steel mesh 2 to strengthen the connection between the main rib 3 and the steel mesh 2.

[0036] Reference Figure 1 , Figure 2 , Figure 4 , Figure 5 , Figure 6 In step B, the specific construction steps of installing the steel mesh 1 include: the steel mesh 1 is tied to the steel mesh 2 through the tie rod 12, the upper part of the tie rod 12 is tied to the steel mesh 2 (the original steel mesh), and the lower part of the tie rod 12 is tied to the reinforcing bar 4 newly added on the steel mesh 1, and the bidirectional steel bar 11 should be close to the roof surface, and then the tie rod 12 is used to tie and suspend the bidirectional steel bar 11.

[0037] Reference Figure 2 , Figure 4 , Figure 5 , Figure 6 , Figure 7 The top of each tie bar 12 is suspended on the steel bars in the steel mesh 2, a portion of the reinforcing bars 4 are suspended in the bottom of the corresponding tie bars 12, a portion of the bidirectional steel bars 11 are suspended in the bottom of the corresponding tie bars 12, the bottom of the reinforcing rib 5 is fixedly connected to the top of the steel mesh 2, and the height and width of the main rib 3 and the end rib 6 are used to limit the concrete coating area.

[0038] Reference Figure 2 , Figure 3 In step C, the specific construction steps of concrete construction include: C1, processing the lightweight concrete at the bottom of the roof panel; C2, layered concrete construction, layered processing when using shotcrete or plastering construction, refer to Figure 3 For the location of the ultra-high ductility fiber concrete 7 sprayed or applied, the thickness of each layer should not exceed 15mm. When indoor ultra-high ductility fiber concrete construction is carried out in a high temperature, windy and dry environment, doors and windows should be closed to avoid being affected during concrete construction. Ultra-high ductility fiber concrete materials should be used as soon as they are mixed. The interval time of each layer construction should be controlled and avoid direct sunlight; C3, curing concrete.

[0039] Reference Figure 2In step C1, the specific construction steps for processing the lightweight concrete at the bottom of the roof panel include: stripping off the 3mm thick polymer mortar glass fiber layer, roughening the surface with a low-power electric drill, cleaning the floating dust on the lightweight concrete of the roof panel, and spraying water to moisten the surface of the lightweight concrete of the roof panel; after the lightweight concrete of the roof panel is dry, evenly apply a layer of interface agent.

[0040] Reference Figure 3 In step C2, the specific construction steps of the layered concrete construction include: spraying concrete onto the steel mesh 1, pressing and smearing the latter layer of concrete is carried out within two hours after the pressing and smearing of the previous layer of concrete, the other layers of concrete are leveled, the surface of the last layer of concrete is leveled and polished, the surface of all the inner layers of ultra-high ductility fiber concrete is leveled, and the other layers are the concrete layers remaining after removing the last layer, and the last layer is also polished; applying concrete to the steel mesh 1, pressing and smearing the latter layer of concrete is carried out within two hours after the pressing and smearing of the previous layer of concrete, the other layers of concrete are leveled, and the last The surface of the last layer of concrete is flattened and polished. By reinforcing the house with ultra-high ductility concrete, the house's compression resistance, overturning resistance and seismic resistance can be significantly improved. Its crack dispersion ability can improve the structure's anti-seepage ability and improve the durability of the structure. During construction, according to the specific conditions of the house panel, that is, according to the actual conditions of the steel frame light roof panels and floor slabs of steel trusses and grid structure buildings, it is possible to adapt to local conditions and flexibly adopt the method of spraying, rotary spraying and smearing to carry out the construction of ultra-high ductility concrete, which greatly improves the construction efficiency. In addition, this technology is easy to construct, economical and applicable, and easy to promote.

[0041] In step C3, the specific construction steps of curing concrete include: regular moisture maintenance, i.e., watering maintenance, after the final setting of the concrete, the curing time is not less than seven days, the concrete surface layer of the steel mesh 1 should be watered and cured, and it should be prevented from being exposed to the sun on a daily basis. Anti-freeze measures should be taken in winter, and attention should be paid to the concrete curing link of the steel skeleton light-strong plate to avoid storing the steel skeleton light-strong plate under inappropriate temperature and humidity conditions to avoid the reduction of strength, cracking or warping of the steel skeleton light-strong plate.

[0042] The above are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A reinforcement method for a steel frame light-strength plate, characterized in that: The following steps are included: Step A, measuring and locating the position of the second steel mesh (2); Step B, installing a steel mesh (1); Step C, concrete construction.

2. A reinforcement method for a steel skeleton light-weight plate according to claim 1, characterized in that: In step A, the specific construction steps of measuring and locating the position of the second steel mesh (2) include: The steel bar position detector detects the position of the second steel bar mesh (2) at the bottom of the roof panel.

3. A reinforcement method for a steel skeleton light-weight plate according to claim 2, characterized in that: The steel mesh one (1) comprises bidirectional steel bars (11), tie bars (12), two main ribs (3) and two end ribs (6), each tie bar (12) is an S-shaped steel bar, both sides of the bidirectional steel bars (11) are fixedly connected to the corresponding main ribs (3), both sides of the bidirectional steel bars (11) are fixedly connected to the corresponding end ribs (6), and the steel mesh two (2) is located inside the two main ribs (3) and the two end ribs (6).

4. A reinforcement method for a steel skeleton light-weight plate according to claim 3, characterized in that: A plurality of reinforcing ribs (4) in a linear array are fixedly connected inside the two main ribs (3) along the length direction, and a plurality of reinforcing ribs (5) in a linear array are fixedly connected inside the two main ribs (3) along the length direction.

5. A reinforcement method for a steel skeleton light-strength plate according to claim 4, characterized in that: In step B, the specific construction steps of installing the steel mesh 1 (1) include: The steel mesh 1 (1) is connected to the steel mesh 2 (2) via the tie rods (12).

6. A reinforcement method for a steel skeleton light-strength plate according to claim 5, characterized in that: The top end of each tie bar (12) is suspended on the steel bar in the second steel mesh (2), a portion of the reinforcing bars (4) are suspended in the bottom of the corresponding tie bar (12), a portion of the bidirectional steel bars (11) are suspended in the bottom of the corresponding tie bar (12), and the bottom of the reinforcing rib (5) is fixedly connected to the top of the second steel mesh (2).

7. A reinforcement method for a steel skeleton light-strength plate according to claim 6, characterized in that: In step C, the specific construction steps of the concrete construction include: C1, lightweight concrete treatment at the bottom of the roof slab; C2, concrete layered construction; C3, curing concrete.

8. A reinforcement method for a steel skeleton light-weight plate according to claim 7, characterized in that: In step C1, the specific construction steps of processing the lightweight concrete at the bottom of the roof panel include: Remove the polymer mortar glass fiber layer, use tools to roughen it, clean the floating dust on the lightweight concrete of the roof panel, and spray water to moisten the surface of the lightweight concrete of the roof panel; After the lightweight concrete of the roof panel is dry, apply a layer of interface agent evenly.

9. A reinforcement method for a steel skeleton light-weight plate according to claim 8, characterized in that: In step C2, the specific construction steps of the concrete layered construction include: Spray concrete onto the steel mesh (1). The pressing and troweling of the next layer of concrete shall be carried out within two hours after the pressing and troweling of the previous layer of concrete. The surface of the other layers of concrete shall be smoothed and the surface of the last layer of concrete shall be smoothed and polished. Apply concrete to the steel mesh (1). The last layer of concrete should be applied within two hours after the previous layer of concrete is applied. The other layers of concrete should be smoothed and the surface of the last layer of concrete should be smoothed and polished.

10. A reinforcement method for a steel skeleton light-weight plate according to claim 9, characterized in that: In step C3, the specific construction steps of curing concrete include: After the concrete has finally set, regular moisturizing maintenance should be carried out, and the maintenance time should not be less than seven days.

Citation Information

Patent Citations

  • Assembled steel encircling framework light heat preservation and energy conservation roof panel and manufacturing and assembling process thereof

    CN102888948A

  • Method for reinforcing pre-stressed concrete core unit by using bar-mat reinforcement fine aggregate concrete

    CN103046764A

  • Lightweight concrete plate and manufacturing method

    CN112609897A

  • Existing building masonry load bearing wall reinforcing structure and construction method thereof

    CN113216678A

  • High ductility fibre concrete strengthening roof beam

    CN206128673U