Steam-water dual-purpose boiler system with flue gas waste heat recovery function and working method
By setting up a heat storage boiler and a gas-liquid injector in the boiler, the recovery of flue gas waste heat and the improvement of the water power safety of the boiler is achieved, and the problems of hydropower safety and thermal economy of the boiler under ultra-low load conditions are solved. , improves the operating stability and resource utilization rate of the boiler.
Patent Information
- Application Number
- CN202411171627.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-26
- Publication Date
- 2024-12-03
AI Technical Summary
Existing boilers have hydrodynamic safety problems under ultra-low load conditions, poor thermal economy, and frequent boiler rotations lead to unstable operation, making it difficult to effectively utilize the waste heat of flue gas, affecting resource utilization and carbon emission intensity.
Design a dual-purpose boiler system with flue gas waste heat recovery. By setting up a heat storage boiler in the boiler, high-temperature and high-pressure saturated water are separated for reduced pressure bubbles and then sprayed and bubbling in the flash tank. It also uses a gas-liquid injector to drive circulating flash evaporation to absorb the waste heat of the flue gas, form a combined flash evaporation up and down, and provide a stable low-pressure saturated vapor source.
Improve the hydrodynamic safety and thermal efficiency of the boiler under ultra-low load conditions, reduce the smoke exhaust temperature, improve the operating stability of the boiler and the utilization rate of the flue gas waste heat, reduce heating costs, and improve seawater desalination and sewage Economicality of thermal processes for processing, etc.
Smart Images

Figure CN119062976A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a dual-purpose steam-water boiler system with flue gas waste heat recovery, which belongs to the technical fields of flue gas waste heat recovery, three-reform linkage of thermal power units, seawater desalination, and sewage treatment. Background Art
[0002] With the rapid development of my country's social economy and industrial modernization, the demand for various energy sources is increasing, and resource shortages are becoming increasingly obvious. my country's total resources are relatively abundant, but the population density is large and the uneven spatial distribution of resources makes my country's per capita resource possession small. Therefore, improving resource utilization has become one of the important directions of scientific and technological and social development.
[0003] Especially in key industries such as electricity, chemical industry, metallurgy, and construction, boiler peak load operation has become a normalized technology. In the future, coal-fired power will transform from a main power source to a basic guarantee and system regulation power source that provides reliable capacity, peak load and frequency regulation and other auxiliary services. According to the recognition standards for energy-saving and carbon reduction transformation, flexibility transformation, and heating transformation (i.e., "three transformations and linkage") of coal-fired power units, the national coal consumption rate of coal-fired power supply will drop to 297g / (kWh) by the end of the year, but the technical difficulty of achieving this is relatively large. In particular, there are not many technical options for subcritical 300,000 kW units, subcritical 600,000 kW units, and supercritical 300,000 kW units. Most power plants have chosen the technical path of unit heating to improve the economic efficiency of power plant operation.
[0004] To achieve 20% or even lower load peaking of thermal power boiler units at home and abroad, it is necessary to improve the system efficiency and thermal economy of the boiler during long-term low-load operation, reduce the coal consumption rate and carbon emission intensity under low-load conditions, avoid frequent boiler switching, and improve the operation stability and reliability of the unit. At the same time, under deep peaking conditions, problems such as uneven flame distribution, insufficient power and low pressure in the furnace may lead to large steam temperature deviations in the water-cooled wall, which in turn causes overheating of the metal pipe wall and even pipe bursting. Ensuring the hydrodynamic safety of complex deep peaking systems is also a crucial technology. Summary of the invention
[0005] The present invention aims to provide a dual-purpose steam-water boiler system with flue gas waste heat recovery. Aiming at the problems of improving the thermal efficiency, thermal economy, and hydrodynamic safety of the unit under the ultra-low load operation of the boiler in the thermal power unit, a boiler steam-water co-supply mode is proposed, and a heat storage drum is added for hot water supply. In the case where the steam production of the boiler is greatly reduced under ultra-low load peak regulation, in order to ensure the hydrodynamic safety of the boiler and improve resource utilization, the boiler no longer produces steam alone, but separates a part of high-temperature and high-pressure saturated water from the heat storage drum, and after the resistance increase and pressure reducer is reduced and bubbled, it is sent to the flash tank for bubbling flash evaporation. The unflashed water is pressurized and circulated under the drive of the gas-liquid ejector, absorbs the waste heat of the boiler flue gas in the flue gas heat exchanger, and is heated to a near-saturated state. Spray flash evaporation is carried out in the flash tank, and the flash evaporation is combined with the bubbling flash evaporation at the bottom to form an upper and lower combined flash evaporation, thereby improving the flash evaporation efficiency and providing a stable low-pressure saturated steam source for heat-using processes such as seawater desalination and sewage treatment.
[0006] The technical solution adopted by the present invention is: a dual-purpose steam-water boiler system with flue gas waste heat recovery, the dual-purpose steam-water boiler system consists of an upper drum, a lower drum, an economizer, a water feed pump, a gas-liquid ejector, a flue gas heat exchanger, a resistance increasing and pressure reducing device, and a flash tank. An upper heat storage drum or a lower heat storage drum is arranged in the upper drum or the lower drum for high-pressure hot water supply, and each device is connected by a pipeline; the heat storage drum is arranged in the upper drum or the lower drum to adapt to different boiler forms and water intake methods, and the internal baffle of the upper drum or the lower drum divides the upper drum or the lower drum into two chambers, separating a part of the chamber as the heat storage drum: when the heat storage drum is built into the lower drum, the internal baffle of the lower drum completely isolates the lower drum, and the lower drum is connected through the lower drum. The pipe introduces the high-pressure, high-temperature saturated water that flows into the heat storage drum from the downcomer into the lower drum header, and the water-cooled wall riser connected to the lower drum header forms the steam-water circulation of the boiler, and the high-pressure, high-temperature saturated water that enters the resistance-increasing and pressure-reducing device is led out from the lower heat storage drum in the lower drum through the lower drum lead-out pipe; when the heat storage drum is built into the upper drum, the internal baffle of the upper drum does not completely isolate the upper drum, and the internal upper drum header and the heat storage drum are connected in the steam side space. The upper drum header has the same function as the traditional boiler, and completes the steam-liquid separation and the steam-water circulation by connecting with the water-cooled wall riser, downcomer and exhaust pipe. The difference is that the upper drum connecting pipe introduces a part of the high-pressure, high-temperature saturated water into the heat storage drum, and leads the heat storage drum into the resistance-increasing and pressure-reducing device through the lead-out pipe.
[0007] The heat storage drum drains a portion of the high-pressure saturated water to the resistance increasing and pressure reducing device, reduces the pressure and bubbles to form a gas-liquid two-phase flow carrying a large number of fine bubbles, and enters the flash tank for gushing bubbling flash evaporation; the unflashed water is circulated and sprayed and flashed under the drive of the gas-liquid ejector, and the gas-liquid ejector is driven by the high-pressure steam generated by the boiler. The ejector fluid inlet is connected to the bottom of the flash tank, and the unflashed water is pressurized and then transported to the flue gas heat exchanger, where it absorbs the waste heat of the flue gas and is heated to a nearly saturated state, and is sent to the sprayer on the top of the flash tank for spray flash evaporation, which forms a top-down combined flash evaporation with the gushing bubbling flash evaporation at the bottom of the flash tank, and the low-pressure saturated steam and saturated water evaporated form a steam-water joint supply.
[0008] The steam-water dual-purpose boiler system is provided with a heat storage drum to assist the boiler in forming a steam-water circulation, thereby ensuring the safety of steam and water under ultra-low load conditions of the boiler. At the same time, the amount of water delivered to the resistance increasing and pressure reducing device can be adjusted in real time to meet the variable load operation requirements of the boiler.
[0009] The steam-water dual-purpose boiler system produces low-pressure saturated steam and low-pressure saturated water in a cyclic flash evaporation mode. The system is driven by a gas-liquid ejector. The high-temperature and high-pressure steam produced by the boiler forms a vacuum at the outlet of the working nozzle inside the gas-liquid ejector, and sucks the unflashed saturated water in the flash tank for recycling. After the water is pressurized, it is transported to the flue gas heat exchanger to absorb the waste heat of the boiler flue gas, and the water is heated to a near-saturated state. The water enters the sprayer at the top of the flash tank for spray flash evaporation, and forms an upper and lower combined flash evaporation with the bubbling flash evaporation driven by the resistance increasing and pressure reducing device at the bottom of the flash tank, thereby improving the flash evaporation efficiency and controlling the flash evaporation pressure to meet the variable load operation requirements of the boiler, and flexibly adjusts the low-pressure steam pressure and flow rate under different boiler loads to meet the low-temperature heat utilization process requirements.
[0010] The beneficial effects of the present invention are as follows: a heat storage drum for dual-purpose steam and water is arranged in the boiler, which ensures the hydraulic safety of the boiler at low load and provides a large steam-water regulation margin; the boiler steam-water co-supply is realized, the heating capacity of the boiler under low load conditions is improved, the steam extraction operation of the low-load thermal power unit is avoided, and the operating stability of the thermal power unit is improved; the low-pressure steam and hot water co-supply mode recovers the boiler furnace waste heat and flue gas waste heat, reduces the exhaust temperature, improves the boiler thermal efficiency, reduces the heating cost, and improves the economy of heat-using processes such as seawater desalination, sewage treatment, heating and refrigeration, saves energy, and reduces carbon; the gas-liquid ejector is used to realize the cyclic flash evaporation without external power drive, and the flash evaporation efficiency is improved by the upper and lower combined flash evaporation mode, and the thermal efficiency of the steam-water dual-purpose boiler system is improved.
[0011] The present invention improves the hydrodynamic safety of the boiler unit under ultra-low load conditions, improves the stability and reliability of the unit's long-term low-load operation, and at the same time improves the utilization rate of boiler flue gas waste heat, reduces the boiler's exhaust heat loss, provides an ultra-clean interface for CCUS, and provides a low-cost, flexible and adjustable heat source for seawater desalination, sewage treatment, heating and refrigeration, thereby improving the thermal efficiency and heat economy of the unit. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 The device diagram of a dual-purpose steam-water boiler system with flue gas waste heat recovery and water intake from the lower drum.
[0013] Figure 2 The device diagram of a dual-purpose steam-water boiler system with water taken from the upper drum and flue gas waste heat recovery.
[0014] Figure 3 It is a structural diagram of a lower drum device with a heat storage drum.
[0015] Figure 4 It is a structural diagram of an upper drum device with a heat storage drum.
[0016] In the figure: 1. feed water pump, 2. economizer, 3. lower boiler drum, 3-1. lower boiler drum header, 3-2. lower heat storage drum, 3-3. lower boiler drum internal baffle, 3-4. lower boiler drum connecting pipe, 3-5. lower boiler drum outlet pipe, 4. upper boiler drum, 4-1. upper boiler drum header, 4-2. upper heat storage drum, 4-3. upper boiler drum internal baffle, 4-4. upper boiler drum connecting pipe, 4-5. upper boiler drum outlet pipe, 4-6. exhaust pipe, 5. resistance increasing and pressure reducing device, 6. gas-liquid ejector, 7. flue gas heat exchanger, 8. flash tank, 9. water-cooled wall riser, 10. downcomer. DETAILED DESCRIPTION
[0017] The technical solutions in the implementation of the present invention will be described clearly and completely below in conjunction with the accompanying drawings of the present invention.
[0018] The steam-water dual-purpose boiler system with flue gas waste heat recovery proposed by the present invention comprises a feed water pump 1, an economizer 2, a lower drum 3, an upper drum 4, a resistance increasing and pressure reducing device 5, a gas-liquid ejector 6, a flue gas heat exchanger 7, and a flash tank 8, and each device is connected by a pipeline; the high-pressure saturated water entering the resistance increasing and pressure reducing device 5 is drawn from the lower drum 3 or the upper drum 4. When drawn from the lower drum 3, the lower drum 3 is internally provided with a lower drum header 3-1, a heat storage drum 3-2, a lower drum internal baffle 3-3, and a lower drum connecting pipe 3-4. The lower drum header 3-1 is connected to the lower heat storage drum 3-2 through the lower drum connecting pipe 3-4 at the bottom of the lower drum internal baffle 3-3. The lower drum header 3-1 is connected to the water-cooled wall riser 9, the lower heat storage drum 3-2 is connected to the downcomer 10, and the lower drum lead-out pipe 3-5 is placed at the lower part of the heat storage drum 3-2. When the high-pressure saturated water entering the resistance increasing and reducing device 5 is led from the upper drum 4, the upper drum 4 is internally equipped with an upper drum header 4-1, an upper heat storage drum 4-2, an upper drum internal baffle 4-3, and an upper drum connecting pipe 4-4. The upper drum header 4-1 is connected to the steam side space at the top of the upper heat storage drum 4-2, and the water side space at the bottom is connected through the upper drum connecting pipe 4-4 at the bottom of the upper drum internal baffle 4-3. The upper drum header 4-1 is connected to the water-cooled wall riser 9 and the downcomer 10 to form a steam-water circulation loop. After the steam and liquid are separated in the upper drum 4, the steam is led out by the exhaust pipe 4-6, and most of the unevaporated high-pressure saturated water is collected in the lower drum 3 by the downcomer 10. A part of the high-pressure saturated water is led out of the boiler through the upper drum lead-out pipe 4-5 at the bottom of the heat storage drum 4-2 and enters the resistance increasing and reducing device 5, so as to realize the dual use of high-level steam and water in the boiler.
[0019] The resistance increasing and pressure reducing device 5 plays the role of increasing resistance and reducing pressure, so that the pressure drops rapidly to below the saturation pressure, and a large number of fine bubbles are generated inside the resistance increasing and pressure reducing device 5 to form a gas-liquid two-phase flow, which enters the flash tank 8 to form a gushing bubbling flash evaporation; the unflashed water in the flash tank 8 is flashed in a cycle under the drive of the gas-liquid ejector 6, and the high-temperature and high-pressure steam generated by the boiler enters through the working nozzle inside the gas-liquid ejector 6, and the supersonic jet forms a vacuum, sucking the unflashed water into the gas-liquid ejector 6, and entering the flue gas heat exchanger 7 after the temperature and pressure are increased, and after the waste heat of the boiler flue gas is recovered, it is heated to a nearly saturated state, and then transported to the sprayer at the top of the flash tank 8 for spray flash evaporation, forming a top-down combined flash evaporation with the gushing bubbling flash evaporation at the bottom of the flash tank 8, so as to improve the flash evaporation efficiency, and control the pressure and flow of the low-pressure saturated steam output by the flash tank 8, so as to provide a flexible and controllable heat source for heat-using processes such as seawater desalination, sewage treatment, heating and cooling.
[0020] Example 1
[0021] Figure 1 The device diagram of a dual-purpose steam-water boiler system with flue gas waste heat recovery and water intake from the lower drum is shown; Figure 3 The structural diagram of the lower drum device with a heat storage drum is shown.
[0022] The system consists of a feed water pump 1, an economizer 2, a lower drum 3, an upper drum 4, a lower heat storage drum 3-2, a resistance increasing and pressure reducing device 5, a gas-liquid ejector 6, a flue gas heat exchanger 7, and a flash tank 8, and each device is connected by a pipeline; the lower heat storage drum 3-2 is built into the lower drum 3, the lower heat storage drum 3-2 is connected to the water inlet of the resistance increasing and pressure reducing device 5, the water outlet of the resistance increasing and pressure reducing device 5 is connected to the bottom of the flash tank 8, the water outlet of the flash tank 8 is connected to the induced fluid inlet of the gas-liquid ejector 6, the outlet of the gas-liquid ejector 6 is connected to the water inlet of the flue gas heat exchanger 7, and the water outlet of the flue gas heat exchanger 7 is connected to the sprayer built into the flash tank 8.
[0023] After the boiler feed water is pressurized by the feed water pump 1, it is heated by the economizer 2 and enters the lower drum 3. After forming a steam-water cycle with the upper drum 4, part of the high-pressure, high-temperature saturated water is drawn out from the lower heat storage drum 3-2. The high-pressure, high-temperature saturated water transported to the resistance increasing and pressure reducing device 5 is drawn out from the lower drum 3. The heat storage drum (3-2) is placed in the lower drum 3. The lower drum 3 has a lower drum header 3-1, a heat storage drum 3-2, a lower drum internal baffle 3-3, and a lower drum connecting pipe 3-4. The lower drum internal baffle 3-3 divides the lower drum into two chambers, namely the lower drum header 3-1 and the heat storage drum 3-2, which are connected at the bottom by the lower drum connecting pipe 3-4. The lower drum header 3-1 is connected to the water-cooled wall riser 9, and the heat storage drum 3-2 is connected to the downcomer 10, forming a steam-water circulation loop. The boiler feed water is pressurized by the feed water pump 1 and pumped to the economizer 2, enters the lower drum 3 through the lower drum header 3-1, mixes with the high-pressure and high-temperature saturated water led out of the heat storage drum 3-2 through the lower drum connecting pipe 3-4, enters the water-cooled wall riser 9 to absorb the heat of the furnace, and then enters the upper drum 4; the high-pressure and high-temperature saturated water that has not evaporated in the upper drum 4 is collected by the downcomer 10 to the heat storage drum 3-2, most of which enters the lower drum header 3-1 to participate in the boiler steam-water circulation, and a part of it is led out of the boiler through the lower drum lead-out pipe 3-5 and enters the resistance increasing and pressure reducing device 5, so as to realize the dual use of high-level steam and water in the boiler.
[0024] After being transported to the resistance increasing and pressure reducing device 5 for decompression and bubbling, a gas-liquid two-phase flow with a large number of fine bubbles is formed, which enters the bottom of the flash tank 8 to form gushing bubbling flash evaporation. The unflashed water is driven by the high-pressure steam generated by the boiler and is sucked and pressurized by the gas-liquid ejector 6 to form a circulating flash evaporation. The pressurized water at the outlet of the gas-liquid ejector 6 absorbs the waste heat of the boiler flue gas in the flue gas heat exchanger 7, and is heated to a nearly saturated state and then transported to the top of the flash tank 8 for spray flash evaporation, forming a top-down combined flash evaporation with the gushing bubbling flash evaporation at the bottom of the flash tank 8, thereby realizing the low-level steam and water co-supply.
[0025] Example 2
[0026] Figure 2 The device diagram of a dual-purpose steam-water boiler system with flue gas waste heat recovery and water intake from the upper drum is shown; Figure 4 The structural diagram of the upper drum device with a heat storage drum is shown.
[0027] The system consists of a feed water pump 1, an economizer 2, a lower drum 3, an upper drum 4, an upper heat storage drum 4-2, a resistance increasing and pressure reducing device 5, a gas-liquid ejector 6, a flue gas heat exchanger 7, and a flash tank 8, and the various devices are connected by pipelines; the upper heat storage drum 4-2 is built into the upper drum 4, the upper heat storage drum 4-2 is connected to the water inlet of the resistance increasing and pressure reducing device 5, the water outlet of the resistance increasing and pressure reducing device 5 is connected to the bottom of the flash tank 8, the water outlet of the flash tank 8 is connected to the induced fluid inlet of the gas-liquid ejector 6, the outlet of the gas-liquid ejector 6 is connected to the water inlet of the flue gas heat exchanger 7, and the water outlet of the flue gas heat exchanger 7 is connected to the sprayer built into the flash tank 8.
[0028] After the boiler feed water is pressurized by the feed water pump 1, it is heated by the economizer 2 and enters the lower drum 3. After forming a steam-water circulation with the upper drum 4, the high-pressure and high-temperature saturated water transported to the resistance increasing and pressure reducing device 5 is led out from the upper drum 4. The heat storage drum 4-2 is placed in the upper drum 4. The upper drum 4 has an upper drum header 4-1, a heat storage drum 4-2, an upper drum internal baffle 4-3, and an upper drum connecting pipe 4-4 built in. The upper drum internal baffle 4-3 divides the upper drum into two chambers, namely the upper drum header 4-1 and the heat storage drum 4-2, the bottom of which is connected by the upper drum connecting pipe 4-4. The top of the upper drum internal baffle 4-3 is not connected to the inner wall of the upper drum 4, that is, the steam side space of the upper drum header 4-1 and the top of the heat storage drum 4-2 is connected; the upper drum header 4-1 is connected to the water-cooled wall riser 9 and the downcomer 10 to form a steam-water circulation loop. The boiler feed water enters the water-cooled wall riser 9 to absorb the heat from the furnace and then enters the upper drum 4. After the steam and liquid are separated in the upper drum 4, the steam is led out by the exhaust pipe 4-6. Most of the unevaporated high-pressure and high-temperature saturated water is collected by the downcomer 10 to the lower drum 3 to participate in the boiler steam-water circulation. A part of the high-pressure and high-temperature saturated water enters the heat storage drum 4-2 through the upper drum connecting pipe 4-4, is led out of the boiler through the upper drum lead-out pipe 4-5, and enters the resistance increasing and pressure reducing device 5, so as to realize the dual use of high-level steam and water in the boiler.
[0029] The high-temperature and high-pressure saturated water is first subjected to resistance-increasing and pressure-reducing treatment by using the resistance-increasing and pressure-reducing device 5 to enhance the flash evaporation effect. The fluid entering the bottom of the flash tank 8 through the resistance-increasing and pressure-reducing device 5 is a gas-liquid two-phase flow with a large number of fine bubbles, which forms a gushing bubbling flash at the bottom of the flash tank 8, thereby forming a top-to-bottom combined flash with the spray flash at the top of the flash tank 8. The circulating flash water driven by the gas-liquid ejector 6 is subjected to heat exchange treatment by the flue gas heat exchanger 7 to reduce the boiler exhaust temperature, thereby achieving energy saving and emission reduction.
Claims
1. A steam-water dual-purpose boiler system with flue gas waste heat recovery, wherein a water pump (1) is connected to a lower drum (3) via an economizer (2), the lower drum (3) is connected to an upper drum (4) via a water-cooled wall riser (9), and the upper drum (4) is connected to the lower drum (3) via a downcomer (10); characterized in that: The upper heat storage drum (4-2) is built into the upper drum (4), the lower heat storage drum (3-2) is built into the lower drum (3), the upper heat storage drum (4-2) or the lower heat storage drum (3-2) is connected to the water inlet of the resistance increasing and pressure reducing device (5), the water outlet of the resistance increasing and pressure reducing device (5) is connected to the bottom of the flash tank (8), the water outlet of the flash tank (8) is connected to the injection fluid inlet of the gas-liquid ejector (6), the outlet of the gas-liquid ejector (6) is connected to the water inlet of the flue gas heat exchanger (7), and the water outlet of the flue gas heat exchanger (7) is connected to the sprayer built into the flash tank (8); The lower drum (3) is divided into two chambers by a lower drum internal baffle (3-3): a lower drum header (3-1) and a lower heat storage drum (3-2), the bottoms of which are connected by a lower drum connecting pipe (3-4); the lower drum header (3-1) is connected to a water-cooled wall riser (9), and the upper portion of the lower heat storage drum (3-2) is connected to a downcomer (10) to form a steam-water circulation loop; the lower portion of the lower heat storage drum (3-2) is connected to a resistance increasing and pressure reducing device (5) by a lower drum outlet pipe (3-5); The upper drum (4) is divided into two chambers by an upper drum internal baffle (4-3): an upper drum header (4-1) and an upper heat storage drum (4-2), the bottoms of which are connected by an upper drum connecting pipe (4-4); the top of the upper drum internal baffle (4-3) is not connected to the inner wall of the upper drum (4), that is, the steam side space of the upper drum header (4-1) and the top of the upper heat storage drum (4-2) is connected; the upper drum header (4-1) is connected to the water-cooled wall riser (9) and downcomer (10) to form a steam-water circulation loop; an exhaust pipe (4-6) is provided at the top of the upper drum (4), and the bottom of the upper heat storage drum (4-2) is connected to the resistance increasing and pressure reducing device (5) through the upper drum outlet pipe (4-5).
2. The working method of a dual-purpose steam-water boiler system with flue gas waste heat recovery according to claim 1 is characterized in that: After the boiler feed water is pressurized by the feed water pump (1), it is heated by the economizer (2) and enters the lower drum (3). After forming a steam-water cycle with the upper drum (4), part of the high-pressure and high-temperature saturated water is drawn out from the upper heat storage drum (4-2) or the lower heat storage drum (3-2) and transported to the resistance increasing and reducing pressure device (5) for pressure reduction and bubbling to form a gas-liquid two-phase flow with a large number of fine bubbles and enter the bottom of the flash tank (8) to form a bubbling flash. The unflashed water is driven by the high-pressure steam generated by the boiler and is sucked and pressurized by the gas-liquid ejector (6) to form a circulating flash. The pressurized water at the outlet of the gas-liquid ejector (6) absorbs the waste heat of the boiler flue gas in the flue gas heat exchanger (7), is heated to a nearly saturated state, and is transported to the top of the flash tank (8) for spray flash, forming a top-to-bottom combined flash with the bubbling flash at the bottom of the flash tank (8). When the high-pressure, high-temperature saturated water delivered to the resistance increasing and pressure reducing device (5) is led out from the lower drum (3): The lower heat storage drum (3-2) is placed in the lower drum (3); the boiler feed water is pressurized by the feed water pump (1) and then pumped to the economizer (2); the feed water enters the lower drum (3) from the lower drum header (3-1); after mixing with the high-pressure and high-temperature saturated water led out of the lower heat storage drum (3-2) through the lower drum connecting pipe (3-4), the feed water enters the water-cooled wall riser (9) to absorb the heat of the furnace, and then enters the upper drum (4); the high-pressure and high-temperature saturated water that has not evaporated in the upper drum (4) is collected by the downcomer (10) to the lower heat storage drum (3-2); part of the water enters the lower drum header (3-1) to participate in the boiler steam-water circulation; part of the water is led out of the boiler through the lower drum lead-out pipe (3-5) and enters the resistance increasing and pressure reducing device (5), thereby realizing the dual use of boiler high-level steam and water; When the high-pressure, high-temperature saturated water delivered to the resistance increasing and pressure reducing device (5) is led out from the upper boiler drum (4): The upper heat storage drum (4-2) is placed in the upper drum (4). The boiler feed water enters the water-cooled wall riser (9) to absorb the heat from the furnace and then enters the upper drum (4). After the steam and liquid are separated in the upper drum (4), the steam is led out through the exhaust pipe (4-6). A part of the high-pressure and high-temperature saturated water that has not evaporated is collected in the lower drum (3) through the downcomer (10) to participate in the boiler steam-water circulation. A part of the high-pressure and high-temperature saturated water enters the upper heat storage drum (4-2) through the upper drum connecting pipe (4-4), is led out of the boiler through the upper drum lead-out pipe (4-5), and enters the resistance increasing and pressure reducing device (5), thereby realizing the dual use of boiler high-level steam and water.