Automatic test system for power distribution terminal

Through the design of the automatic testing system of the distribution terminal, the existing system has been solved with complex operation, single functions and difficulty in repairing and upgrading, comprehensive testing and remote maintenance of the system have been achieved, efficiency has been improved, and manpower and material resources have been saved.

CN119064706AInactive Publication Date: 2024-12-03LISHUI POWER SUPPLY COMPANY OF STATE GRID ZHEJIANG ELECTRIC POWER

Patent Information

Application Number
CN202411578121.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-07
Publication Date
2024-12-03
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing power distribution terminal testing system has complex operation, single functions, and difficult maintenance and program upgrades, resulting in slow manual investigation and repair speed, low efficiency, and a waste of manpower and material resources.

Method used

An automatic testing system for power distribution terminals is designed, including a test box and a remote control terminal. The test box is equipped with a central processor and an electromagnetic compatibility performance test unit, a remote maintenance and upgrade unit, a fault detection and processing test unit, etc., and is controlled remotely. Implement comprehensive testing, maintenance and upgrade of the system.

Benefits of technology

It realizes the comprehensive testing functions of the automatic testing system of the power distribution terminal, simple operation, can be maintained and upgraded remotely, saving manpower and material investment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119064706A_ABST
    Figure CN119064706A_ABST
Patent Text Reader

Abstract

The invention discloses a power distribution terminal automatic test system, which comprises a test box and a remote control terminal, and is characterized in that the test box comprises a central processing unit, an electromagnetic compatibility performance test unit, a remote maintenance and upgrade unit and a fault detection and processing test unit; the electromagnetic compatibility test unit comprises a radiation immunity test module, a conduction immunity test module, an electrostatic discharge test module, a surge test module, an electrical fast transient and pulse train test module, an electromagnetic emission test module and a harmonic current test module which are independently arranged and are all connected with the central processing unit; a voltage change and fluctuation and flicker emission test module; the remote maintenance and upgrade unit comprises a monitoring module, an adjustment and maintenance module and a communication module which are connected in sequence; the fault detection and processing test unit comprises an analog power supply module and a first signal generator which are connected in sequence. The test system provided by the invention has comprehensive test functions, is simple to operate, can be remotely maintained and upgraded, and saves the investment of manpower and material resources.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of electric power engineering equipment, and in particular to an automatic testing system for a power distribution terminal. Background Art

[0002] The distribution terminal plays an important role in the operation of the power grid. It is necessary to conduct comprehensive inspections on the distribution terminal regularly. The existing distribution terminal test system is complicated to operate. Professionals need to undergo certain professional training to master the test operation methods. The test function is single, generally with basic functional tests and application functional tests. When the existing distribution terminal system fails or the test system needs to be upgraded, the equipment supplier must be contacted, and the supplier will send after-sales service personnel to the site to solve the problem. Manual troubleshooting and repair are slow, inefficient, and waste a lot of manpower and material resources.

[0003] It can be seen that how to solve the problems of complex operation, single function, and difficulty in maintenance and program upgrade in the existing distribution terminal test system has become a technical problem that technical personnel in this field need to solve urgently. Summary of the invention

[0004] The present invention provides an automatic test system, device, equipment and medium for power distribution terminals to solve the technical problems of the existing power distribution terminal test system, such as complex operation, single function, and difficulty in maintenance and program upgrade, so as to achieve the effect that the automatic test system for power distribution terminals has comprehensive test functions, simple operation, and can be remotely maintained and upgraded.

[0005] In order to solve the above technical problems, an embodiment of the present invention provides an automatic test system for a power distribution terminal, the automatic test system for the power distribution terminal includes a test box and a remote control terminal, the test box includes a central processing unit and an electromagnetic compatibility performance test unit, the electromagnetic compatibility performance test unit includes a radiation immunity test module, a conducted immunity test module, an electrostatic discharge test module, a surge test module, an electrical fast transient and pulse group test module, an electromagnetic emission test module, a harmonic current test module, a voltage change and fluctuation and flicker emission test module, which are independently arranged and connected to the central processing unit; The test box also includes a remote maintenance and upgrade unit connected to the central processor and the remote control terminal; The remote maintenance and upgrade unit includes a detection module, an adjustment and maintenance module and a communication module connected in sequence; The detection module is used to determine whether the automatic test system for power distribution terminals has abnormal conditions or / and upgrade requirements based on the status data and operation data of the automatic test system for power distribution terminals acquired in real time, so as to generate a detection result; The adjustment and maintenance module is used to receive the detection result, and when the abnormal situation and / or upgrade requirement are found in the detection result, use the remote control terminal to maintain and / or upgrade the automatic test system for the power distribution terminal; The communication module is used to transmit the detection result to the remote control terminal, and transmit the instruction issued by the remote control terminal to the adjustment and maintenance module; The test box also includes a fault detection and processing test unit connected to the central processing unit; The fault detection and processing test unit comprises a simulated power module and a first signal generator connected in sequence, and a fault scenario is simulated by the simulated power module and the first signal generator to test the fault response and processing capability of the power distribution terminal; The outer side of the test box is coated with a wave absorbing pyramid layer.

[0006] Preferably, the radiation immunity test module comprises a first test antenna, a second signal generator and a first power amplifier connected in sequence, and is used to apply electromagnetic field radiation to the power distribution terminal to evaluate the anti-interference ability of the power distribution terminal in an electromagnetic field radiation environment; The conducted immunity test module includes a third signal generator, a first coupling and decoupling device, a fixed attenuator and a probe connected in sequence, and is used to simulate the conducted interference to which the power distribution terminal is subjected in an actual working environment, and to evaluate the anti-interference performance of the power distribution terminal in a conducted interference environment; The electrostatic discharge test module includes an electrostatic discharge generator, a test electrode and a discharge head connected in sequence, and is used to apply static electricity to the power distribution terminal to evaluate the anti-interference ability of the power distribution terminal in an electrostatic discharge environment; The surge test module comprises a surge signal generator, a second coupling and decoupling device, a voltage probe and a current probe connected in sequence, and is used to apply a surge voltage to the power distribution terminal to evaluate the anti-interference ability of the power distribution terminal in a surge voltage environment; The EFT and pulse group test module comprises a group pulse generator, an automatic transceiver and a coupling clamp connected in sequence, and is used to apply group pulses on the distribution terminal to evaluate the anti-interference ability of the distribution terminal in an EFT or pulse group environment.

[0007] Preferably, the electromagnetic emission test module comprises a second power amplifier, a second test antenna and a measuring device connected in sequence, for measuring and evaluating the electromagnetic waves generated by the power distribution terminal during normal operation; The harmonic current test module includes a first current acquisition circuit and a waveform analyzer connected in sequence, and is used to measure and evaluate the harmonic current generated by the power distribution terminal on the AC power line; The voltage variation, fluctuation and flicker emission test module comprises a first voltage acquisition circuit and a flicker measurement circuit connected in sequence, and is used to measure and evaluate the voltage variation, fluctuation and flicker emission caused by the power distribution terminal on the power line.

[0008] Preferably, the power distribution terminal automatic test system also includes a mechanical performance test unit, an insulation performance test unit, a function detection unit, a communication detection unit, a power supply performance test unit, a performance test unit and an environmental adaptability performance detection unit connected to the central processing unit.

[0009] Pre-selected, the mechanical performance test unit comprises a data acquisition circuit and a first data analysis module connected in sequence, for measuring and evaluating the mechanical durability of the power distribution terminal; The insulation performance testing unit includes an insulation resistance tester, a high voltage power supply, a second voltage acquisition circuit and a second current acquisition circuit which are connected in sequence and are used to measure and evaluate the insulation performance of the power distribution terminal.

[0010] Preferably, the function detection unit comprises a fourth signal generator, a third voltage acquisition circuit and a third current acquisition circuit connected in sequence, and is used to test specific functions of the power distribution terminal, wherein the specific functions at least include remote signaling, remote measurement and remote control; The communication detection unit includes a signal receiving device and a signal processing device connected in sequence, and is used to test the communication protocol and data transmission capability of the power distribution terminal.

[0011] Preferably, the power performance test unit comprises a fourth voltage acquisition circuit and a fourth current acquisition circuit connected in sequence, for evaluating the performance of the power module of the power distribution terminal; The performance testing unit comprises a second data analysis module and a first performance evaluation module connected in sequence, and is used to test the performance of the power distribution terminal under different working conditions; The environmental adaptability performance detection unit includes a third data analysis module and a second performance evaluation module, which are used to test the ability of the power distribution terminal to adapt to various environmental conditions.

[0012] Preferably, the central processing unit includes an intelligent analysis module; The intelligent analysis module is used to analyze the test data received by the central processing unit to determine the operating status of the power distribution terminal and generate an alarm signal.

[0013] Preferably, an L-shaped hollow water pipe is provided at the bottom of the test box, one end of the L-shaped hollow water pipe is through, and a filter mesh block is connected to the inner side close to the other end of the L-shaped hollow water pipe; A placement groove is provided inside the L-shaped hollow water pipe, and the interior of the placement groove is filled with condensed water; An L-shaped hollow heat dissipation pipe having the same shape as the L-shaped hollow water pipe is installed close to the outer side of the L-shaped hollow water pipe.

[0014] Preferably, a fan is provided inside one end of the L-shaped hollow water pipe; A temperature sensor connected to the fan signal is arranged inside the test box.

[0015] Compared with the prior art, the automatic test system for power distribution terminals disclosed in the present invention has the beneficial effect of the embodiments of the present invention in that the automatic test system for power distribution terminals has comprehensive test functions, is easy to operate, can be remotely maintained and upgraded, and saves manpower and material resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] FIG1 is a schematic diagram of the structure of an automatic test system for a power distribution terminal provided in one embodiment of the present invention; FIG2 is a three-dimensional diagram of an automatic test system for power distribution terminals provided in one embodiment of the present invention; FIG3 is a top view of a power distribution terminal automatic test system provided in one embodiment of the present invention; Reference numerals: 1. Test box; 2. Remote control terminal; 3. Electrical connection terminal; 4. Fan; 5. Filter block; 6. L-shaped hollow water pipe; 7. L-shaped hollow heat pipe; 11. Electromagnetic compatibility performance test unit; 12. Remote maintenance and upgrade unit; 13. Fault detection and processing test unit; 14 Mechanical performance test unit; 15. Insulation performance test unit; 16. Function detection unit; 17. Communication detection unit; 18. Power supply performance test unit; 19. Performance test unit; 20. Environmental adaptability performance detection unit; 21. First installation slot; 22. Second installation slot; 23. Central processing unit. DETAILED DESCRIPTION

[0017] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. The purpose of providing these embodiments is to make the disclosure of the present invention more thorough and comprehensive. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0018] In the description of this application, the terms "first", "second", "third", etc. are used for descriptive purposes only and are not to be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first", "second", "third", etc. may explicitly or implicitly include one or more of the feature. In the description of this application, unless otherwise specified, "plurality" means two or more.

[0019] In the description of the present application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be a connection between the two elements. The terms "vertical", "horizontal", "left", "right", "upper", "lower" and similar expressions used herein are only for illustrative purposes, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0020] In the description of this application, it should be noted that, unless otherwise defined, all technical and scientific terms used in the present invention have the same meaning as those commonly understood by those skilled in the art. The terms used in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood by specific circumstances.

[0021] As shown in Fig. 1 and Fig. 2, a distribution terminal automatic test system is disclosed in a preferred embodiment of the present invention, and the distribution terminal automatic test system includes a test box 1 and a remote control terminal 2. A plurality of electrical connection terminals 3 are arranged on the side of the shell of the test box 1, and a central processing unit 23 and an electromagnetic compatibility performance test unit 11 are arranged inside the test box 1. The electromagnetic compatibility performance test unit 11 includes a radiation immunity test module, a conducted immunity test module, an electrostatic discharge test module, a surge test module, an electrical fast transient and pulse group test module, an electromagnetic emission test module, a harmonic current test module, and a voltage change and fluctuation and flicker emission test module, which are independently arranged and connected to the central processing unit 23.

[0022] The radiation immunity test module includes a first test antenna, a second signal generator and a first power amplifier connected in sequence, the second signal generator is used to generate the required electromagnetic wave signal, the first power amplifier is used to enhance the power of the signal to ensure the effectiveness of the test, and the first test antenna is used to transmit and receive electromagnetic waves. Specifically, the second signal generator generates an electromagnetic wave signal within the shielding range of the shielding device, which is transmitted by the first test antenna to apply an electromagnetic field to the distribution terminal, simulate the electromagnetic field radiation received by the distribution terminal in the working environment, obtain the performance parameters of the distribution terminal and transmit them to the central processor to analyze the performance of the distribution terminal and evaluate the anti-interference ability of the distribution automation terminal in the electromagnetic field radiation environment.

[0023] The conducted immunity test module includes a third signal generator, a first coupling and decoupling device, a fixed attenuator and a probe connected in sequence. The third signal generator is used to transmit a radio frequency signal. The first coupling and decoupling device couples or decouples the radio frequency signal to simulate the conducted interference to the distribution terminal in an actual working environment, obtains the performance parameters of the distribution terminal and transmits them to the central processor to analyze the performance of the distribution terminal and evaluate the anti-interference performance of the distribution terminal in a conducted interference environment.

[0024] Electrostatic discharge test module The electrostatic discharge test module includes an electrostatic discharge generator, a test electrode and a discharge head connected in sequence. The electrostatic discharge generator is used to generate static electricity. The test electrode and the discharge head contact the distribution terminal and release the static charge. Specifically, the electrostatic discharge generator simulates the electrostatic discharge of the human body and acts on the distribution terminal, obtains the performance parameters of the distribution terminal and transmits them to the central processor to analyze the performance of the distribution terminal and evaluate the performance of the distribution terminal when subjected to electrostatic discharge.

[0025] The surge test module includes a surge signal generator, a second coupling and decoupling device, a voltage probe and a current probe connected in sequence, which are used to apply a surge voltage to the distribution terminal and evaluate the anti-interference ability of the distribution terminal in a surge voltage environment. Specifically, the surge signal generator generates a surge signal waveform and applies it to the distribution terminal to simulate a voltage surge caused by a lightning strike or a power grid failure, obtain the performance parameters of the distribution terminal and transmit them to the central processor to analyze the performance of the distribution terminal and evaluate the anti-interference ability of the distribution terminal in a surge voltage environment.

[0026] The EFT and pulse group test module includes a group pulse generator, an automatic transceiver and a coupling clamp connected in sequence. The group pulse generator is used to generate an EFT pulse group signal that meets the standard requirements, the automatic transceiver is used to receive the EFT pulse group signal from the group pulse generator, and the coupling clamp is used to couple the EFT pulse group signal generated by the group pulse generator to the distribution terminal. Specifically, the group pulse generator generates an EFT pulse group signal, the automatic transceiver receives the EFT pulse group signal, and the coupling clamp couples the EFT pulse group signal to the distribution terminal. The fast transient pulse group signal is applied to the distribution terminal to simulate the transient interference caused by the power switch operation, analyze the performance of the distribution terminal, and evaluate the anti-interference ability of the distribution terminal in the EFT or pulse group environment.

[0027] The electromagnetic emission test module includes a second power amplifier, a second test antenna and a measuring device connected in sequence, and is used to measure and evaluate the electromagnetic waves generated by the power distribution terminal during normal operation. Specifically, the second test antenna receives the electromagnetic waves generated by the power distribution terminal during normal operation, the second power amplifier performs amplification processing, and the measuring device measures the electromagnetic waves and evaluates whether it will cause interference to other electronic equipment. If it is likely to cause interference to other electronic equipment, relevant repairs and upgrades are performed to ensure that it will not cause interference to other electronic equipment.

[0028] The harmonic current test module includes a first current acquisition circuit and a waveform analyzer connected in sequence, which are used to measure and evaluate the harmonic current generated by the distribution terminal on the AC power line. Specifically, the first current acquisition circuit acquires the harmonic current generated by the distribution terminal on the AC power line, and evaluates whether it meets the relevant electromagnetic compatibility standards. If it does not meet the relevant electromagnetic compatibility standards, relevant maintenance and upgrades are performed to ensure that it meets the relevant electromagnetic compatibility standards.

[0029] The voltage change and fluctuation and flicker emission test module includes a first voltage acquisition circuit and a flicker measurement circuit connected in sequence, which are used to measure and evaluate the voltage change, fluctuation and flicker emission caused by the distribution terminal on the power line. Specifically, the first voltage acquisition circuit acquires the voltage change and fluctuation caused by the distribution terminal on the power line, and the flicker measurement circuit measures the flicker emission caused by the distribution terminal on the power line, and evaluates whether it meets the relevant electromagnetic compatibility standards. If it does not meet the relevant electromagnetic compatibility standards, relevant maintenance and upgrades are performed to ensure that it meets the relevant electromagnetic compatibility standards.

[0030] The test box 1 also includes a remote maintenance and upgrade unit 12 connected to the central processor 23 and the remote control terminal 2. The remote maintenance and upgrade unit 12 includes a detection module, an adjustment and maintenance module, a communication module and a storage module which are connected in sequence.

[0031] The detection module is used to determine whether there are abnormal conditions or / and upgrade requirements in the automatic test system of the distribution terminal according to the status data and operation data of the automatic test system of the distribution terminal acquired in real time, so as to generate the detection results. Specifically, the status data and operation data of the automatic test system of the distribution terminal are detected in real time, the abnormal conditions are quickly discovered and recorded, and it is determined whether the system needs to be upgraded, and the detection results are sent to the adjustment and maintenance module. The adjustment and maintenance module is used to receive the detection results, and when there are abnormal conditions and / or upgrade requirements in the detection results, the automatic test system of the distribution terminal is maintained and / or upgraded using the remote control terminal 2. Specifically, the detection module is started to perform a comprehensive detection on the automatic test system of the distribution terminal; the detection results are sent to the adjustment and maintenance module to analyze and determine whether an upgrade and / or maintenance is required; if an upgrade is required, the communication module establishes a connection with the central processor, prepares for data transmission, receives and downloads a new upgrade package and stores it in the data storage module; the central processor 23 receives the upgrade instruction of the remote control terminal 2 and extracts the new upgrade package from the data storage module. The central processor 23 executes the new upgrade package to upgrade the automatic test system of the power distribution terminal; after the upgrade is completed, the detection module detects the new test system to ensure the upgrade effect; the maintenance and adjustment module makes necessary system adjustments based on the detection results; all operations and results are recorded in the data storage module.

[0032] The test box 1 also includes a fault detection and processing test unit 13 connected to the central processor 23. The fault detection and processing test unit 13 includes a simulated power supply module and a first signal generator connected in sequence. The fault scenario is simulated by the simulated power supply module and the first signal generator, and the performance parameters of the distribution terminal are obtained and transmitted to the central processor 23 to evaluate the performance of the distribution terminal and test the fault response and processing capabilities of the distribution terminal.

[0033] In a preferred embodiment of the present invention, the automatic testing system for distribution terminals also includes a mechanical performance testing unit 14, an insulation performance testing unit 15, a function detection unit 16, a communication detection unit 17, a power supply performance testing unit 18, a performance testing unit 19 and an environmental adaptability performance detection unit 20 connected to a central processor 23.

[0034] The mechanical performance test unit 14 includes a data acquisition circuit and a first data analysis module connected in sequence, which are used to measure and evaluate the mechanical durability of the distribution terminal. The mechanical durability test mainly focuses on the service life and performance stability of the distribution terminal under conditions such as mechanical stress, vibration and impact. Among them, the most commonly used method for mechanical durability evaluation is the stress-strain analysis method. The first data analysis module analyzes the stress and strain of the distribution terminal under different loads and working conditions collected by the data acquisition circuit to evaluate its load-bearing capacity and fatigue life.

[0035] The insulation performance test unit 15 includes an insulation resistance tester, a high-voltage power supply, a second voltage acquisition circuit and a second current acquisition circuit connected in sequence. The high-voltage power supply is used to provide a stable high-voltage output to simulate the high-voltage conditions of the distribution terminal in the actual working environment. The insulation resistance tester is used to measure the insulation resistance value of the distribution terminal to evaluate its insulation performance. Specifically, the high-voltage power supply outputs high voltage to act on the distribution terminal, the first voltage acquisition circuit and the second current acquisition circuit acquire the voltage and current during the test, and the insulation resistance tester tests the insulation. Insulation performance is the key to the safe operation of the distribution terminal, ensuring the safe operation of the distribution terminal in a high-voltage environment.

[0036] The function detection unit 16 is connected in sequence to a fourth signal generator, a third voltage acquisition circuit, and a third current acquisition circuit, which are used to test specific functions of the distribution terminal, and the specific functions include at least telesignaling, telemetering, and remote control. The telesignaling test content is whether the signal received by the distribution terminal can be sent to the main station normally. The main station judges the operation status of the on-site power equipment through the telesignaling signal sent by the distribution terminal. The telemetering distribution terminal collects the on-site voltage and current, and calculates the active and reactive status of the distribution terminal through the line loss module. The telemetering test calculates the telemetering pass rate by continuously monitoring the telemetering data of key parameters such as voltage, current, and power. The remote control test reflects the responsiveness of the distribution terminal to the remote control command by testing the success rate of sending and receiving the remote control command.

[0037] The communication detection unit 17 includes a signal receiving device and a signal processing device connected in sequence, which are used to test the communication protocol and data transmission capability of the power distribution terminal to ensure effective communication with the master station. Specifically, the signal receiving device receives the signal, the signal processing device demodulates the signal, and transmits the demodulated signal to the central processor 23 for analysis to test the communication protocol and data transmission capability of the power distribution terminal.

[0038] The power supply performance test unit 18 includes a fourth voltage acquisition circuit and a fourth current acquisition circuit connected in sequence, and the fourth voltage acquisition circuit and the fourth current acquisition circuit are respectively used to collect the voltage and current of the power supply, and transmit the collected voltage and current to the central processor 23 for analysis to evaluate the performance of the power supply module of the distribution terminal, including power switching and power quality.

[0039] The performance testing unit 19 includes a second data analysis module and a first performance evaluation module which are connected in sequence. The second data analysis module is used to analyze the operating data under different working conditions, and the first performance evaluation module is used to evaluate the analysis results to obtain the performance of the distribution terminal under different working conditions.

[0040] The environmental adaptability performance detection unit 20 includes a third data analysis module and a second performance evaluation module. Specifically, the third data analysis module simulates high temperature, low temperature, and humid heat environments, and analyzes the operating data under various environments. The second performance evaluation module is used to evaluate the analysis results to test the ability of the distribution terminal to adapt to various environmental conditions.

[0041] The mechanical performance test unit 14, the insulation performance test unit 15, the fault detection and processing test unit 13, the remote maintenance and upgrade unit 12, the function detection unit 16, the communication detection unit 17, the power supply performance test unit 18, the performance test unit 19 and the environmental adaptability performance detection unit 20, as well as the radiation immunity test module, the conducted immunity test module, the electrostatic discharge test module, the surge test module, the electrical fast transient and pulse group test module, the electromagnetic emission test module, the harmonic current test module, the voltage change and fluctuation and the flicker emission test module of the electromagnetic compatibility performance test unit 11 all transmit the detected test data to the central controller through the connecting cables. The central processing unit includes an intelligent analysis module, which is used to analyze the test data to judge the operating status of the distribution terminal and generate a corresponding alarm signal. Specifically, the intelligent analysis module analyzes various types of test data and compares them with preset thresholds, and generates alarm signals based on the comparison results to achieve automatic testing and abnormal warning of distribution terminals. At the same time, it can also monitor the operating status and functions of the distribution terminal automatic test system itself, providing a basis for remote automatic maintenance and upgrading of the distribution terminal automatic detection system.

[0042] As shown in Figure 1, a first installation slot 21 and a second installation slot 22 are provided at the bottom of the test box. The first installation slot 21 is provided with a mechanical performance test unit 14, an insulation performance test unit 15, an electromagnetic compatibility performance test unit 11, a remote maintenance and upgrade unit 12 and a fault detection and processing test unit 13, and the second installation slot 22 is provided with a function detection unit 16, a communication detection unit 17, a power supply performance test unit 18, a performance test unit 19 and an environmental adaptability performance detection unit 20.

[0043] Furthermore, as shown in FIG3 , in order to prevent the working environment temperature of the automatic test system of the power distribution terminal from being too high and affecting the performance of the automatic test system of the power distribution terminal, an L-shaped hollow water pipe 6 is arranged at the bottom of the test box 1, one end of the L-shaped hollow water pipe 6 is passed through, and a filter block 5 is connected to the inner side near the other end of the L-shaped hollow water pipe 6. A placement groove is provided inside the L-shaped hollow water pipe 6, and the inside of the placement groove is filled with condensed water. An L-shaped hollow heat dissipation pipe 7 of the same shape as the L-shaped hollow water pipe 6 is installed close to the outside of the L-shaped hollow water pipe 6. A fan 4 is arranged inside the end through which the L-shaped hollow water pipe 6 passes, and a temperature sensor connected to the signal of the fan 4 is arranged inside the test box 1. When the temperature sensor senses that the temperature inside the test box 1 is too high, the fan 4 is driven to draw the air outside the test box 1 into the L-shaped hollow water pipe 6 through the fan 4, and the temperature of the incoming air is absorbed by the condensed water inside the L-shaped hollow water pipe 6, and then the air enters each test unit and module inside the test box 1, and the air inside the test box 1 flows out through the heat dissipation holes, thereby achieving rapid heat dissipation. The setting of the L-shaped hollow heat dissipation pipe 7 further enhances the heat dissipation effect.

[0044] The environment in which the distribution terminal is located is relatively complex. The existing automatic test system for distribution terminals is easily interfered by electromagnetic radiation and has relatively strict requirements on the test environment, resulting in low accuracy of the test results. In order to improve the adaptability of the automatic test system for distribution terminals to the environment and improve the accuracy of the test, an absorbing cone layer is coated on the outside of the test box 1.

[0045] The absorbing pyramid layer is a structural layer composed of a pyramid absorbing material. This material has a special geometric shape and electromagnetic properties and can effectively absorb or reflect radio frequency energy. It has the following characteristics: 1. The thickness is large. The pyramid absorbing layer usually has a large thickness, which helps to increase the number of reflections of electromagnetic waves inside the material, thereby improving the absorption efficiency. Good flexibility. The material has a certain flexibility and can adapt to different shapes and curved surfaces. The absorption rate is large. The pyramid absorbing layer has a high absorption rate for electromagnetic waves and can effectively reduce the reflection and transmission of electromagnetic waves. Good stability. The pyramid absorbing layer maintains stable absorbing performance in a wide temperature range (-50°C~150°C). Therefore, in the preferred embodiment of the present invention, the absorbing pyramid layer is coated on the outside of the test box 1 to significantly reduce the impact of external electromagnetic interference on the automatic test system of the distribution terminal, improve the accuracy and stability of the test, and enable the automatic test system of the distribution terminal disclosed in the present invention to be applicable to various occasions with high-precision testing requirements.

[0046] Stability is one of the important indicators of the power distribution terminal. The power distribution terminal automatic test system of the present invention can perform a long-term stability test on the power distribution terminal to evaluate its stability and reliability during long-term operation.

[0047] The power distribution terminal automatic test system provided in the embodiment of the present invention is used to solve the technical problems of the existing power distribution terminal test system, such as complex operation, single function, and difficulty in maintenance and program upgrade. The automatic test system for distribution terminals provided by the present invention comprises a test box and a remote control terminal, wherein the test box comprises a central processing unit and an electromagnetic compatibility performance test unit, wherein the electromagnetic compatibility performance test unit comprises a radiation immunity test module, a conducted immunity test module, an electrostatic discharge test module, a surge test module, an electrical fast transient and pulse group test module, an electromagnetic emission test module, a harmonic current test module, a voltage change and fluctuation and flicker emission test module which are independently arranged and connected to the central processing unit; the test box also comprises a remote maintenance and upgrade unit connected to the central processing unit and the remote control terminal; the remote maintenance and upgrade unit comprises a detection module, an adjustment and maintenance module and a communication module which are connected in sequence; the detection module is used to determine whether the automatic test system for distribution terminals has abnormal conditions or / and upgrade requirements according to the status data and operation data of the automatic test system for distribution terminals acquired in real time, so as to generate a detection result; the adjustment and maintenance module is used to receive the detection result, and when there is an abnormal condition and / or upgrade requirement in the detection result, the automatic test system for distribution terminals is maintained and / or upgraded by using the remote control terminal; the communication module is used to transmit the detection result to the remote control terminal, and transmit the instructions issued by the remote control terminal to the adjustment and maintenance module. The test box also includes a fault detection and processing test unit connected to the central processing unit; the fault detection and processing test unit includes a simulated power module and a first signal generator connected in sequence, and the simulated power module and the first signal generator are used to simulate the fault scenario and test the fault response and processing capability of the power distribution terminal. The power distribution terminal automatic test system provided by the present invention has comprehensive test functions, simple operation, and can be remotely maintained and upgraded, saving manpower and material resources.

[0048] The above-described embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the present invention. It should be pointed out that, for a person of ordinary skill in the art, several modifications and improvements can be made without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the attached claims.

Claims

1. An automatic test system for power distribution terminals, characterized in that: The automatic test system for power distribution terminals includes a test box and a remote control terminal. The test box includes a central processing unit and an electromagnetic compatibility performance test unit. The electromagnetic compatibility performance test unit includes a radiation immunity test module, a conducted immunity test module, an electrostatic discharge test module, a surge test module, an electrical fast transient and pulse group test module, an electromagnetic emission test module, a harmonic current test module, and a voltage change and fluctuation and flicker emission test module, which are independently arranged and connected to the central processing unit. The test box also includes a remote maintenance and upgrade unit connected to the central processor and the remote control terminal; The remote maintenance and upgrade unit includes a detection module, an adjustment and maintenance module and a communication module connected in sequence; The detection module is used to determine whether the automatic test system for power distribution terminals has abnormal conditions or / and upgrade requirements based on the status data and operation data of the automatic test system for power distribution terminals acquired in real time, so as to generate a detection result; The adjustment and maintenance module is used to receive the detection result, and when the abnormal situation and / or upgrade requirement are found in the detection result, use the remote control terminal to maintain and / or upgrade the automatic test system for the power distribution terminal; The communication module is used to transmit the detection result to the remote control terminal, and transmit the instruction issued by the remote control terminal to the adjustment and maintenance module; The test box also includes a fault detection and processing test unit connected to the central processing unit; The fault detection and processing test unit comprises a simulated power module and a first signal generator connected in sequence, and a fault scenario is simulated by the simulated power module and the first signal generator to test the fault response and processing capability of the power distribution terminal; The outer side of the test box is coated with a wave absorbing pyramid layer.

2. The automatic test system for power distribution terminals according to claim 1, characterized in that: The radiation immunity test module includes a first test antenna, a second signal generator and a first power amplifier connected in sequence, and is used to apply electromagnetic field radiation to the power distribution terminal to evaluate the anti-interference ability of the power distribution terminal in an electromagnetic field radiation environment; The conducted immunity test module includes a third signal generator, a first coupling and decoupling device, a fixed attenuator and a probe connected in sequence, and is used to simulate the conducted interference to which the power distribution terminal is subjected in an actual working environment, and to evaluate the anti-interference performance of the power distribution terminal in a conducted interference environment; The electrostatic discharge test module includes an electrostatic discharge generator, a test electrode and a discharge head connected in sequence, and is used to apply static electricity to the power distribution terminal to evaluate the anti-interference ability of the power distribution terminal in an electrostatic discharge environment; The surge test module comprises a surge signal generator, a second coupling and decoupling device, a voltage probe and a current probe connected in sequence, and is used to apply a surge voltage to the power distribution terminal to evaluate the anti-interference ability of the power distribution terminal in a surge voltage environment; The EFT and pulse group test module comprises a group pulse generator, an automatic transceiver and a coupling clamp connected in sequence, and is used to apply group pulses to the distribution terminal to evaluate the anti-interference ability of the distribution terminal in an EFT or pulse group environment.

3. The automatic test system for power distribution terminals according to claim 1, characterized in that: The electromagnetic emission test module includes a second power amplifier, a second test antenna and a measuring device connected in sequence, and is used to measure and evaluate the electromagnetic waves generated by the power distribution terminal during normal operation; The harmonic current test module includes a first current acquisition circuit and a waveform analyzer connected in sequence, and is used to measure and evaluate the harmonic current generated by the power distribution terminal on the AC power line; The voltage variation, fluctuation and flicker emission test module comprises a first voltage acquisition circuit and a flicker measurement circuit connected in sequence, and is used to measure and evaluate the voltage variation, fluctuation and flicker emission caused by the power distribution terminal on the power line.

4. The automatic test system for power distribution terminals according to claim 1, characterized in that: The power distribution terminal automatic test system also includes a mechanical performance test unit, an insulation performance test unit, a function detection unit, a communication detection unit, a power performance test unit, a performance test unit and an environmental adaptability performance detection unit connected to the central processing unit.

5. The automatic test system for power distribution terminals according to claim 4, characterized in that: The mechanical performance testing unit includes a data acquisition circuit and a first data analysis module connected in sequence, and is used to measure and evaluate the mechanical durability of the power distribution terminal; The insulation performance testing unit includes an insulation resistance tester, a high voltage power supply, a second voltage acquisition circuit and a second current acquisition circuit which are connected in sequence and are used to measure and evaluate the insulation performance of the power distribution terminal.

6. The automatic test system for power distribution terminals according to claim 4, characterized in that: The function detection unit includes a fourth signal generator, a third voltage acquisition circuit and a third current acquisition circuit connected in sequence, and is used to test the specific functions of the power distribution terminal, and the specific functions include at least remote signaling, remote measurement and remote control; The communication detection unit includes a signal receiving device and a signal processing device connected in sequence, and is used to test the communication protocol and data transmission capability of the power distribution terminal.

7. The automatic test system for power distribution terminals according to claim 4, characterized in that: The power performance testing unit comprises a fourth voltage acquisition circuit and a fourth current acquisition circuit connected in sequence, and is used to evaluate the power module performance of the power distribution terminal; The performance testing unit comprises a second data analysis module and a first performance evaluation module connected in sequence, and is used to test the performance of the power distribution terminal under different working conditions; The environmental adaptability performance detection unit includes a third data analysis module and a second performance evaluation module, which are used to test the ability of the power distribution terminal to adapt to various environmental conditions.

8. The automatic test system for power distribution terminals according to claim 1, characterized in that: The central processing unit includes an intelligent analysis module; The intelligent analysis module is used to analyze the test data received by the central processing unit to determine the operating status of the power distribution terminal and generate an alarm signal.

9. The automatic test system for power distribution terminals according to claim 1, characterized in that: An L-shaped hollow water pipe is provided at the bottom of the test box, one end of the L-shaped hollow water pipe is through, and a filter block is connected to the inner side of the other end of the L-shaped hollow water pipe; A placement groove is provided inside the L-shaped hollow water pipe, and the interior of the placement groove is filled with condensed water; An L-shaped hollow heat dissipation pipe having the same shape as the L-shaped hollow water pipe is installed close to the outer side of the L-shaped hollow water pipe.

10. The automatic test system for power distribution terminals according to claim 9, characterized in that: A fan is arranged inside one end of the L-shaped hollow water pipe; A temperature sensor connected to the fan signal is arranged inside the test box.

Citation Information

Patent Citations

  • Large-scale medical equipment onsite test system and test method

    CN104880633A

  • Power distribution cabinet test system based on Internet of things

    CN110794230A

  • Distribution network automatic on-line test system

    CN117155825A

  • Distributor product intelligent test system

    CN118688558A

Cited By

  • Simulation test device for elevator electrical power distribution system

    CN120539524A

  • An elevator electrical power distribution system simulation test device

    CN120539524B

  • Power distribution automation remote terminal intelligent debugging system and process

    CN121499933A