New energy delivery system scheduling method considering risk decision
Through the new energy export system scheduling method, combined with the uncertain parameters of wind power and export channels, the target output power of each generator set is solved, and the scheduling difficulties caused by inaccurate prediction of wind power output and transmission channel transmission channel are solved. The system benefits are maximized and stable operation is achieved.
Patent Information
- Application Number
- CN202411099703.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-12
- Publication Date
- 2024-12-03
AI Technical Summary
The prediction results of wind power output and transmission power transmission channels are not accurate enough, which leads to difficulty in scheduling new energy transmission system and the difficulty in effectively dealing with uncertainty in the existing technology, which leads to the transformation of the power system scheduling model from certainty to uncertainty model.
A new energy delivery system scheduling method that considers risk decisions is adopted, and by obtaining pre-constructed scheduling operation model, output constraint information of generator sets, predicted values of wind power and delivery channels, decision benchmark values and decision preference information, combined with wind power The uncertain parameters of output and transmission power of the outgoing channel are solved, and the output power target value of each generator set is solved to maximize system benefits and ensure system stability.
Taking into account the uncertainty of transmission power of wind power and transmission channels, the new energy delivery system is effectively dispatched to maximize system benefits and ensure stable operation, solving the scheduling difficulties caused by inaccurate prediction results in the prior art.
Smart Images

Figure CN119067469A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power system energy dispatching, and in particular to a new energy transmission system dispatching method taking risk decision into consideration. Background Art
[0002] Wind power generation can effectively address energy shortages and environmental pollution problems, but wind power output is greatly affected by wind speed, resulting in strong randomness and volatility, and a certain degree of uncertainty. At the same time, due to the uncertainty of the receiving grid load, the transmission power of the transmission channel is also uncertain, and the power system dispatching model has changed from a deterministic model to an uncertain model.
[0003] Pumped storage power stations have the characteristics of rapid regulation. Joint dispatch with intermittent energy sources such as wind power to achieve stable power output of power stations has become a hot topic of current research. Common uncertainty processing methods all require probability distribution, membership function, range, etc. of uncertainty factors. However, due to current technical limitations, the prediction of wind power output and transmission power of transmission channels still has great uncertainty, which is often difficult to predict, and even more difficult to determine its probability distribution. In addition, for reasons such as confidentiality, it is also difficult to obtain accurate historical data on wind power output and transmission power of transmission channels. Only power system scheduling problems with a lower degree of uncertainty can be solved. Since the prediction results of wind power output and hydropower processing are not accurate enough, the scheduling of new energy transmission systems cannot be well achieved based on the prediction results. Summary of the invention
[0004] In view of this, the present invention provides a new energy transmission system scheduling method taking risk decision into consideration to solve the problem that the prediction results of wind power output and hydropower processing are not accurate enough and the scheduling of the new energy transmission system cannot be well realized based on the prediction results.
[0005] In a first aspect, the present invention provides a method for scheduling a new energy transmission system taking risk decision into consideration, the method comprising: obtaining a pre-constructed scheduling operation model of the new energy transmission system, output constraint information of each generator set in the new energy transmission system, a predicted value of wind turbine output, a predicted value of transmission power of a transmission channel, a decision reference value of the operating income of the new energy transmission system, preset decision preference information, and a cost deviation coefficient corresponding to the preset decision preference, the scheduling operation model of the new energy transmission system is constructed with the goal of maximizing the total income of the new energy transmission system, and the scheduling operation model of the new energy transmission system is used to characterize the correlation between the output power of each generator set in the new energy transmission system and the total income of the new energy transmission system; determining the constraint information of the total income of the new energy transmission system based on the cost deviation coefficient corresponding to the preset decision preference and the decision reference value of the operating income of the new energy transmission system; Based on the preset decision preference information, the constraint information of the comprehensive uncertainty parameter is determined. The comprehensive uncertainty parameter is the sum of the wind power output fluctuation uncertainty parameter and the transmission power uncertainty parameter of the transmission channel. The wind power output fluctuation uncertainty parameter is used to characterize the degree of deviation between the predicted value and the actual value of the wind turbine output, and the transmission power uncertainty parameter of the transmission channel is used to characterize the degree of deviation between the predicted value and the actual value of the transmission power of the transmission channel; the scheduling and operation model of the new energy transmission system is solved by using the constraint information of the comprehensive uncertainty parameter, the constraint information of the total benefit of the new energy transmission system, the output constraint information of each generator set in the new energy transmission system, the predicted value of the wind turbine output and the predicted value of the transmission power of the transmission channel to obtain the target value of the output power of each generator set in the new energy transmission system; the new energy transmission system is dispatched based on the target value of the output power of each generator set.
[0006] The new energy transmission system scheduling method considering risk decision-making provided by the present invention determines the constraint information of the total revenue of the new energy transmission system based on the cost deviation coefficient corresponding to the preset decision preference and the decision reference value of the operating revenue of the new energy transmission system, and determines the constraint information of the comprehensive uncertainty parameter based on the preset decision preference information. The comprehensive uncertainty parameter is the sum of the wind power output fluctuation uncertainty parameter and the transmission power uncertainty parameter of the transmission channel. The scheduling operation model of the new energy transmission system is solved by using the constraint information of the comprehensive uncertainty parameter, the constraint information of the total revenue of the new energy transmission system, the output constraint information of each generator set in the new energy transmission system, the predicted value of the wind turbine output and the predicted value of the transmission power of the transmission channel to obtain the target value of the output power of each generator set in the new energy transmission system; and the new energy transmission system is scheduled based on the target value of the output power of each generator set. The method provided by the present invention determines the constraint information of the total revenue of the new energy transmission system by using the cost deviation coefficient corresponding to the preset decision preference and the decision reference value of the operating revenue of the new energy transmission system, determines the constraint information of the comprehensive uncertainty parameter by using the preset decision preference information, solves the scheduling and operation model of the new energy transmission system based on the constraint information of the comprehensive uncertainty parameter, the constraint information of the total revenue of the new energy transmission system, the output constraint information of each generator set in the new energy transmission system, the predicted value of the output of the wind turbine generator set and the predicted value of the transmission power of the transmission channel, and maximizes the system operation revenue under the premise of considering the uncertainty of the wind power output fluctuation corresponding to the preset decision preference and the comprehensive uncertainty, and schedules the new energy transmission system by using the target value of the output power of each generator set in the new energy transmission system, thereby effectively ensuring the stability of the system operation.
[0007] In an optional implementation, when the preset decision preference information is risk aversion decision preference information, the constraint information of the total revenue of the new energy delivery system is determined according to the first relational expression, which is:
[0008] min C≥(1-Δ1)C0
[0009] Among them, C represents the total revenue of the new energy delivery system, C0 represents the decision-making benchmark value of the operating revenue of the new energy delivery system, and Δ1 is the cost deviation coefficient corresponding to the risk aversion decision preference.
[0010] In an optional implementation, when the preset decision preference information is an opportunity seeking decision preference, the constraint information of the total revenue of the new energy delivery system is determined according to the second relational expression, which is:
[0011] max C≥(1+Δ2)C0
[0012] Among them, C represents the total revenue of the new energy delivery system, C0 represents the decision benchmark value of the operating revenue of the new energy delivery system, and Δ2 is the cost deviation coefficient corresponding to the opportunity seeking decision preference.
[0013] In an optional implementation, the new energy delivery system scheduling operation model is represented by a third relational expression, and the third relational expression is:
[0014]
[0015] Among them, C represents the total revenue of the new energy transmission system, T is the scheduling period; C e,t is the electricity price at time period t; P w,t is the wind power generation power in period t; P i,t represents the power generation of thermal power unit i in time period t; P g,t represents the power generation of the pumped storage power station in time period t; P p,t is the pumping power of the pumped storage power station in period t; N h is the number of thermal power units; u i,t ,y i,t 、z i,t is the state variable of the thermal power unit; is the power generation cost of thermal power unit i; is the startup cost of thermal power unit i; is the shutdown cost of thermal power unit i; N c The number of reversible water pumps for pumped storage power stations; is the startup cost of the pump in the pumped storage power station during period t; is the shutdown cost of the pump in the pumped storage power station during period t.
[0016] In an optional implementation, the step of determining constraint information of the comprehensive uncertainty parameter based on preset decision preference information includes:
[0017] When the preset decision preference information is risk aversion decision preference information, the constraint information of the comprehensive uncertainty parameter is determined by the fourth relational expression, which is:
[0018] maxα=α w +α l
[0019] When the preset decision preference information is the opportunity seeking decision preference, the constraint information of the comprehensive uncertainty parameter is determined by the fifth relational expression, which is:
[0020] minα=α w +α l
[0021] Among them, α represents the comprehensive uncertainty parameter, α wrepresents the uncertainty parameter of wind power output fluctuation, α l Represents the transmission power uncertainty parameter of the outgoing channel.
[0022] In an optional implementation, the decision reference value of the operating income of the new energy delivery system is determined by the following steps:
[0023] The scheduling and operation model of the new energy transmission system is solved by using the output constraint information of each generator set in the new energy transmission system, the predicted value of the wind turbine output and the predicted value of the transmission power of the transmission channel to obtain the decision-making benchmark value of the operating income of the new energy transmission system.
[0024] In a second aspect, the present invention provides a risk decision-making new energy transmission system scheduling device, the device comprising: an acquisition module, used to acquire a pre-constructed new energy transmission system scheduling operation model, output constraint information of each generator set in the new energy transmission system, a predicted value of wind turbine output, a predicted value of transmission channel transmission power, a decision benchmark value of the operating income of the new energy transmission system, preset decision preference information and a cost deviation coefficient corresponding to the preset decision preference, the new energy transmission system scheduling operation model is constructed with the goal of maximizing the total income of the new energy transmission system, and the new energy transmission system scheduling operation model is used to characterize the correlation between the output power of each generator set in the new energy transmission system and the total income of the new energy transmission system; a first determination module, used to determine the constraint information of the total income of the new energy transmission system based on the cost deviation coefficient corresponding to the preset decision preference and the decision benchmark value of the operating income of the new energy transmission system; a second determination module A block is used to determine the constraint information of the comprehensive uncertainty parameter based on the preset decision preference information. The comprehensive uncertainty parameter is the sum of the wind power output fluctuation uncertainty parameter and the transmission power uncertainty parameter of the transmission channel. The wind power output fluctuation uncertainty parameter is used to characterize the degree of deviation between the predicted value and the actual value of the wind turbine output. The transmission power uncertainty parameter of the transmission channel is used to characterize the degree of deviation between the predicted value and the actual value of the transmission power of the transmission channel; a solution module is used to solve the scheduling and operation model of the new energy transmission system by using the constraint information of the comprehensive uncertainty parameter, the constraint information of the total benefit of the new energy transmission system, the output constraint information of each generator set in the new energy transmission system, the predicted value of the wind turbine output and the predicted value of the transmission power of the transmission channel to obtain the target value of the output power of each generator set in the new energy transmission system; a scheduling module is used to schedule the new energy transmission system based on the target value of the output power of each generator set.
[0025] In a third aspect, the present invention provides a computer device, comprising: a memory and a processor, the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor executes the new energy delivery system scheduling method considering risk decision-making of the above-mentioned first aspect or any corresponding embodiment by executing the computer instructions.
[0026] In a fourth aspect, the present invention provides a computer-readable storage medium having computer instructions stored thereon, the computer instructions being used to enable a computer to execute the new energy delivery system scheduling method that takes risk decision-making into consideration according to the first aspect or any corresponding embodiment thereof.
[0027] In a fifth aspect, the present invention provides a computer program product, comprising computer instructions, the computer instructions being used to enable a computer to execute the new energy delivery system scheduling method taking risk decision-making into account according to the first aspect or any corresponding embodiment thereof. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0029] Figure 1 is a flow chart of a new energy delivery system scheduling method considering risk decision-making according to an embodiment of the present invention;
[0030] Figure 2 is a flow chart of another method for scheduling a new energy delivery system taking risk decision into consideration according to an embodiment of the present invention;
[0031] Figure 3 is a structural block diagram of a new energy delivery system scheduling device considering risk decision-making according to an embodiment of the present invention;
[0032] Figure 4 It is a schematic diagram of the hardware structure of a computer device according to an embodiment of the present invention. DETAILED DESCRIPTION
[0033] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.
[0034] In the related technologies, the commonly used uncertainty processing methods all require the probability distribution, membership function, range, etc. of the uncertainty factors. However, due to the current technical limitations, the prediction of wind power output and transmission power of the transmission channel still has great uncertainty, which is often difficult to predict, and even more difficult to determine its probability distribution. In addition, for reasons such as confidentiality, it is also difficult to obtain accurate historical data on wind power output and transmission power of the transmission channel, and can only solve the power system scheduling problem with a lower degree of uncertainty. Since the prediction results of wind power output and hydropower processing are not accurate enough, the scheduling of the new energy transmission system cannot be well realized based on the prediction results.
[0035] In view of this, a new energy delivery system scheduling method considering risk decision-making provided in an embodiment of the present application can be applied to a server to realize energy scheduling of a new energy delivery system. The method provided by the present invention determines the constraint information of the total revenue of the new energy delivery system by using the cost deviation coefficient corresponding to the preset decision preference and the decision reference value of the operating revenue of the new energy delivery system, determines the constraint information of the comprehensive uncertainty parameter by using the preset decision preference information, solves the scheduling operation model of the new energy delivery system based on the constraint information of the comprehensive uncertainty parameter, the constraint information of the total revenue of the new energy delivery system, the output constraint information of each generator set in the new energy delivery system, the predicted value of the output of the wind turbine generator set, and the predicted value of the transmission power of the delivery channel, and the target value of the output power of each generator set in the new energy delivery system obtained by solving the target value of the output power of each generator set in the new energy delivery system maximizes the system operation revenue under the premise of considering the uncertainty of the wind power output fluctuation corresponding to the preset decision preference and the comprehensive uncertainty, and schedules the new energy delivery system by using the target value of the output power of each generator set in the new energy delivery system, effectively ensuring the stability of the system operation.
[0036] According to an embodiment of the present invention, an embodiment of a new energy delivery system scheduling method taking risk decision into consideration is provided. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described may be executed in an order different from that shown here.
[0037] In this embodiment, a new energy delivery system scheduling method considering risk decision-making is provided, which can be used for the above-mentioned server. Figure 1 is a flow chart of a new energy delivery system scheduling method considering risk decision-making according to an embodiment of the present invention. Figure 1 As shown, the process includes the following steps:
[0038] Step S101, obtaining a pre-built scheduling and operation model of a new energy transmission system, output constraint information of each generator set in the new energy transmission system, predicted value of wind turbine output, predicted value of transmission power of the transmission channel, decision reference value of the operating income of the new energy transmission system, preset decision preference information and cost deviation coefficient corresponding to the preset decision preference.
[0039] Exemplarily, the scheduling and operation model of the new energy transmission system is constructed with the goal of maximizing the total revenue of the new energy transmission system. The scheduling and operation model of the new energy transmission system is used to characterize the correlation between the output power of each generator set in the new energy transmission system and the total revenue of the new energy transmission system. The predicted value of the output of the wind turbine set and the predicted value of the transmission power of the transmission channel are predicted by a pre-constructed prediction model. In the embodiment of the present application, the generator sets in the new energy transmission system may include but are not limited to multiple wind turbine sets, thermal power units and pumped storage units.
[0040] The output constraint information of the wind turbine can be determined by the wind power processing model. There are two main factors that affect the wind power output. The first is the internal characteristics, which mainly refers to the internal structure. However, after the wind turbine is manufactured, its structure cannot be changed and has little effect on the output. The second is the external characteristic wind speed. The wind speed varies from region to region and time to time, and is relatively random. The wind speed has a greater impact on the wind power output, resulting in a more obvious volatility in the wind power output. Therefore, the research on wind speed is relatively extensive, and a variety of wind speed distribution models have been proposed, such as Weibull and Rayleigh distributions. Among them, the two-parameter Weibull distribution is the currently generally accepted wind speed probability distribution, which can more accurately represent the wind speed changes in most areas. Its probability density function and distribution function are shown in the following equations (1) and (2), respectively:
[0041]
[0042] Among them, f(v) represents the probability density function of wind speed, F(v) represents the distribution function of wind speed, v is the wind speed; c is the scale parameter; k is the shape parameter, which is generally taken as 1.5-3.0.
[0043] The input power of a wind turbine can be approximately expressed by formula (3). When the wind speed is less than the cut-in wind speed, the wind rotor cannot overcome the resistance between the internal transmission shafts to drive the generator to rotate, and the output is zero. When the wind speed is greater than the cut-out wind speed, in order to avoid damage to the unit, the wind turbine stops working and the output is also zero. When the wind speed is between the cut-in wind speed and the rated wind speed, the wind turbine works normally and the output increases with the increase of wind speed. When the wind speed is greater than the rated wind speed and less than the cut-out wind speed, the wind turbine outputs stably at the rated output.
[0044]
[0045] Among them, Pw,e is the rated power of the fan, which is mainly determined by the specifications during production; v in is the cut-in wind speed; v out is the cut-out wind speed; v e is the rated wind speed, P w is the output power of the wind turbine.
[0046] Therefore, the probability density function of wind power output can be determined by the following equations (4) and (5):
[0047]
[0048] Among them, f w (P w ) represents the probability density function of wind power output.
[0049] The output constraint information of the pumped storage unit can be obtained through the operation model of the water storage power station. Due to its own characteristics and the operation limitations of the power station, the pumped storage unit has unique constraints. The unit constraints include working condition complementarity constraints, storage capacity constraints, power constraints, etc. Compared with conventional thermal power generating units, there is no need to consider the climbing constraints of the pumped storage unit. Generally, a reversible water pump only needs about 150 seconds to complete the working condition conversion from shutdown to full load.
[0050] The output of a pumped storage power station is related to its net head, water flow and unit efficiency. The net head is related to the upper and lower heads and head loss, and the upper and lower heads are nonlinear functions of the upper and lower water flows, respectively. Therefore, the output power expression of a pumped storage power station is shown in the following equations (6) and (7):
[0051]
[0052] Where G is the acceleration due to gravity, h net,t is the net water head in time period t (m), q p and q g are the water flow rates for pumping and power generation (m 3 / s), η p ,η g is the unit efficiency when pumping water and generating electricity, It is related to the parameters of the pumped storage unit and can be obtained from the efficiency curve of the unit.
[0053] The output power constraint of the pumped storage power station can be expressed as follows:
[0054] g p,t P p,min ≤P p,t ≤g p,t P p,max (8)
[0055] gg,t P g,min ≤P g,t ≤g g,t P g,max (9)
[0056] Among them, P p,t is the pumping power of the pumped storage power station in period t; P p,max , P p,min P is the upper and lower limits of the pumping power of the pumped storage power station; g,t is the power generation capacity of the pumped storage power station in time period t; P g,max , P g,min The upper and lower limits of the power generation capacity of the pumped storage power station; g P,t , g g,t It is a state variable, which represents the operation status of the pumped-storage power station in time period t. 0 means that the pumped-storage power station is stopped, and 1 means that the pumped-storage power station is pumping water or generating electricity at this moment.
[0057] Considering the economic efficiency of operation, a pumped storage power station cannot pump water and generate electricity at the same time. The constraints of the state variables are shown in the following equation (10):
[0058] g g,t +g p,t ≤1 (10)
[0059] The storage capacity constraints of pumped storage power stations are shown in equations (11) and (12):
[0060] E u,min ≤E u,t ≤E u,max (11)
[0061] E d,min ≤E d,t ≤E d,max (12)
[0062] Among them, E u,t , E d,t is the water storage capacity of the upper reservoir and the lower reservoir in period t; E u,max , E u,min is the upper and lower limits of the upper reservoir capacity; E d,max , E d,min The upper and lower limits of the lower reservoir capacity.
[0063] Due to the difference between the water storage capacity of the reservoir at the next moment and the water storage capacity and water consumption of pumped power generation at the previous moment, the water storage capacity of the upper reservoir and the lower reservoir in the time period are shown in the following equations (13) and (14) respectively:
[0064]
[0065] Among them, η p , η gThe efficiency of pumping water and generating electricity for pumped storage power plants.
[0066] In order to ensure that the water level of the upper reservoir remains basically unchanged, the pumped storage power station adopts a daily power balance mode, that is, the water consumption of pumping and power generation is balanced in a day, so the power balance constraint can be shown as follows (15).
[0067]
[0068] The power balance constraint of the transmission channel of the new energy transmission system is shown in equation (16):
[0069]
[0070] Among them, P L,t is the power of the transmission channel in time period t, P w,t is the wind power generation power in period t; P i,t represents the power generation of thermal power unit i in time period t; P g,t represents the power generation of the pumped storage power station in time period t; P p,t is the pumping power of the pumped-storage power station in time period t.
[0071] The spinning reserve constraint of conventional thermal power generating units is shown in equation (17):
[0072]
[0073] Among them, SR t is the system spinning reserve capacity for period t, P i,max Indicates the maximum power generation of thermal power units, u i,t Represents a state variable of 0 or 1, u i,t =1 means that thermal power unit i is running during period t, u i,t =1 indicates that thermal power unit i is in shutdown state during period t.
[0074] The output constraint of thermal power generating units is shown in equation (18):
[0075]
[0076] in, is the minimum and maximum output power of conventional thermal power unit i.
[0077] The climbing constraint of thermal power generator set is shown in the following formula (19):
[0078]
[0079] in, It is the upper and lower climbing limit of thermal power unit i.
[0080] The start and stop time constraints of thermal power generator units are shown in formula (20):
[0081]
[0082] in, is the start and stop time of thermal power unit i.
[0083] The start-up and shutdown cost constraints of thermal power generator units are shown in formula (21):
[0084]
[0085] in, is the startup cost of thermal power unit i in period t; is the shutdown cost of thermal power unit i in period t; f i on 、f u off is the start-up and shutdown cost of thermal power unit i.
[0086] The safety constraints of the output power of thermal power units are shown in equations (22) and (23):
[0087] P l,min ≤P l,t ≤P l,max (twenty two)
[0088] U n,min ≤V n,t ≤U n,max (twenty three)
[0089] Among them, P l,max , P l,min U is the upper and lower limits of the active power allowed to be transmitted by line l; n,max , U n,min is the upper and lower limits of the voltage amplitude at node n; V n,t represents the voltage amplitude of node n in time period t.
[0090] The state variable constraints of the thermal power unit are shown in equation (24):
[0091]
[0092] Among them, y i,t 、z i,t A state variable y is either 0 or 1. i,t =1 means that thermal power unit i starts to start at time t, z i,t =1 means that thermal power unit i starts to shut down during period t, and the rest of the meanings are not repeated here.
[0093] Specifically, the decision benchmark value of the operating income of the new energy transmission system is determined through the following steps:
[0094] The scheduling and operation model of the new energy transmission system is solved by using the output constraint information of each generator set in the new energy transmission system, the predicted value of the wind turbine output and the predicted value of the transmission power of the transmission channel to obtain the decision-making benchmark value of the operating income of the new energy transmission system.
[0095] Step S102, determining constraint information of the total revenue of the new energy delivery system based on the cost deviation coefficient corresponding to the preset decision preference and the decision reference value of the operating revenue of the new energy delivery system.
[0096] Exemplarily, the cost deviation coefficient is determined according to the decision preference, and different decision preferences may correspond to different cost deviation coefficients. In the embodiment of the present application, the constraint information of the total revenue of the new energy delivery system is determined based on the cost deviation coefficient corresponding to the preset decision preference and the decision reference value.
[0097] Step S103, determining constraint information of the comprehensive uncertainty parameter based on preset decision preference information.
[0098] Exemplarily, the comprehensive uncertainty parameter is the sum of the wind power output fluctuation uncertainty parameter and the transmission power uncertainty parameter of the transmission channel. The wind power output fluctuation uncertainty parameter is used to characterize the degree of deviation between the predicted value and the actual value of the wind turbine output, and the transmission power uncertainty parameter of the transmission channel is used to characterize the degree of deviation between the predicted value and the actual value of the transmission power of the transmission channel.
[0099] Step S104, using the constraint information of the comprehensive uncertainty parameters, the constraint information of the total revenue of the new energy transmission system, the output constraint information of each generator set in the new energy transmission system, the predicted value of the wind turbine output and the predicted value of the transmission power of the transmission channel to solve the scheduling and operation model of the new energy transmission system, and obtain the target value of the output power of each generator set in the new energy transmission system.
[0100] For example, in the embodiment of the present application, the constraint information of the comprehensive uncertainty parameter, the constraint information of the total revenue of the new energy transmission system, the output constraint information of each generator set in the new energy transmission system, the predicted value of the wind turbine output and the predicted value of the transmission power of the transmission channel are used to solve the scheduling and operation model of the new energy transmission system, and the target value of the output power of each generator set can be determined. The target value is the optimal solution that meets all the constraints. Based on the target value of the output power of each generator set, the value of the comprehensive uncertainty parameter and the system operation revenue can be further calculated. The present application takes into account the uncertainty of wind power output and the transmission power of the transmission channel at the same time, and considers that the two have the same status.
[0101] Step S105, scheduling the new energy transmission system based on the target value of the output power of each generator set.
[0102] Exemplarily, the target value of the output power of each generator set in the new energy transmission system is used to schedule the new energy transmission system, effectively ensuring the stability of the system operation.
[0103] The new energy transmission system scheduling method considering risk decision-making provided in this embodiment determines the constraint information of the total revenue of the new energy transmission system by using the cost deviation coefficient corresponding to the preset decision preference and the decision reference value of the operating revenue of the new energy transmission system, determines the constraint information of the comprehensive uncertainty parameter by using the preset decision preference information, solves the scheduling operation model of the new energy transmission system based on the constraint information of the comprehensive uncertainty parameter, the constraint information of the total revenue of the new energy transmission system, the output constraint information of each generator set in the new energy transmission system, the predicted value of the output of the wind turbine generator set and the predicted value of the transmission power of the transmission channel, and maximizes the system operation revenue under the premise of considering the uncertainty of the wind power output fluctuation corresponding to the preset decision preference and the comprehensive uncertainty, and schedules the new energy transmission system by using the target value of the output power of each generator set in the new energy transmission system, thereby effectively ensuring the stability of the system operation.
[0104] In this embodiment, a new energy delivery system scheduling method considering risk decision-making is provided, which can be used for the above-mentioned server. Figure 2 is a flow chart of a new energy delivery system scheduling method considering risk decision-making according to an embodiment of the present invention. Figure 2 As shown, the process includes the following steps:
[0105] Step S201, obtain the pre-built new energy transmission system scheduling operation model, the output constraint information of each generator set in the new energy transmission system, the predicted value of wind turbine output, the predicted value of transmission channel transmission power, the decision benchmark value of the new energy transmission system operation income, the preset decision preference information and the cost deviation coefficient corresponding to the preset decision preference. The new energy transmission system scheduling operation model is constructed with the goal of maximizing the total income of the new energy transmission system. The new energy transmission system scheduling operation model is used to characterize the correlation between the output power of each generator set in the new energy transmission system and the total income of the new energy transmission system. For details, please see Figure 1 Step S101 of the illustrated embodiment will not be described in detail here.
[0106] In some optional implementations, the new energy delivery system scheduling operation model is represented by a third relational expression, which is shown in the following equation (25):
[0107]
[0108] Among them, C represents the total revenue of the new energy transmission system, T is the scheduling period; C e,tis the electricity price at time period t; P w,t is the wind power generation power in period t; P i,t represents the power generation of thermal power unit i in time period t; P g,t represents the power generation of the pumped storage power station in time period t; P p,t is the pumping power of the pumped storage power station in period t; N h is the number of thermal power units; u i,t ,y i,t 、z i,t is the state variable of the thermal power unit, the value of this state variable is 0 or 1, u i,t =1 means that thermal power unit i is running during period t, y i,t =1 means that thermal power unit i starts to start at time t, z i,t =1 means that thermal power unit i starts to shut down in period t, and the rest of the meanings are not repeated here; is the power generation cost of thermal power unit i; is the startup cost of thermal power unit i; is the shutdown cost of thermal power unit i; N c The number of reversible water pumps for pumped storage power stations; is the startup cost of the pump in the pumped storage power station during period t; W t off is the shutdown cost of the pump in the pumped storage power station during period t. is a quadratic function of the output power of conventional thermal power units, as shown in the following equation (26):
[0109]
[0110] Among them, a i , b i 、c i Represents the characteristic parameters of thermal power unit i.
[0111] Step S202, determining constraint information of the total revenue of the new energy delivery system based on the cost deviation coefficient corresponding to the preset decision preference and the decision reference value of the operating revenue of the new energy delivery system.
[0112] In some optional implementations, when the preset decision preference information is risk aversion decision preference information, the constraint information of the total revenue of the new energy delivery system is determined according to the first relationship, and the first relationship is shown in the following formula (27):
[0113] min C≥(1-Δ1)C0 (27)
[0114] Among them, C represents the total revenue of the new energy delivery system, C0 represents the decision-making benchmark value of the operating revenue of the new energy delivery system, and Δ1 is the cost deviation coefficient corresponding to the risk aversion decision preference.
[0115] In some optional implementations, when the preset decision preference information is an opportunity seeking decision preference, the constraint information of the total revenue of the new energy delivery system is determined according to the second relationship, which is shown in the following formula (28):
[0116] max C≥(1+Δ2)C0 (28)
[0117] Among them, C represents the total revenue of the new energy delivery system, C0 represents the decision benchmark value of the operating revenue of the new energy delivery system, and Δ2 is the cost deviation coefficient corresponding to the opportunity seeking decision preference.
[0118] Step S203, based on the preset decision preference information, the constraint information of the comprehensive uncertainty parameter is determined, the comprehensive uncertainty parameter is the sum of the wind power output fluctuation uncertainty parameter and the transmission power uncertainty parameter of the transmission channel, the wind power output fluctuation uncertainty parameter is used to characterize the degree of deviation between the predicted value and the actual value of the wind turbine output, and the transmission power uncertainty parameter of the transmission channel is used to characterize the degree of deviation between the predicted value and the actual value of the transmission power of the transmission channel.
[0119] Specifically, the above step S203 includes:
[0120] Step S2031, when the preset decision preference information is risk aversion decision preference information, the constraint information of the comprehensive uncertainty parameter is determined by the fourth relational expression, and the fourth relational expression is shown in the following equation (29):
[0121] maxα=α w +α l (29)
[0122] Step S2032: When the preset decision preference information is the opportunity seeking decision preference, the constraint information of the comprehensive uncertainty parameter is determined by the fifth relational expression, which is shown in the following equation (30):
[0123] min α=α w +α l (30)
[0124] Among them, α represents the comprehensive uncertainty parameter, α w represents the uncertainty parameter of wind power output fluctuation, α l Represents the transmission power uncertainty parameter of the outgoing channel.
[0125] Exemplarily, in the embodiment of the present application, an electric output uncertainty set model is constructed as shown in the following formula (31):
[0126]
[0127] Among them, α wis the amplitude of wind power output fluctuation, which is related to the wind power output prediction error; is the actual value of wind turbine output; is the predicted value of wind turbine output.
[0128] The transmission power uncertainty set model of the outbound transmission channel is constructed as shown in the following equation (32):
[0129]
[0130] Among them, α l Transmission power uncertainty for the outgoing channel; is the actual value of the transmission power of the outgoing channel; It is the predicted value of the transmission power of the outgoing channel.
[0131] When the preset decision preference information is risk aversion decision preference information, the constraints required to solve the scheduling and operation model of the new energy delivery system can be determined by the robust scheduling model of the risk aversion decision maker. The robust scheduling model can be shown as follows (33):
[0132]
[0133] When the preset decision preference information is the opportunity seeking decision preference, the constraints required to solve the scheduling operation model of the new energy delivery system can be determined by the opportunity scheduling model of the opportunity seeking decision maker. The opportunity scheduling model can be shown as follows (34):
[0134]
[0135] Since the scheduling model based on information gap decision theory belongs to a two-level planning model, it needs to be converted into a single-level planning model. The lower-level goal of the robust scheduling model is that when the actual wind power output and the transmission power of the transmission channel fluctuate within the uncertainty set, the total system operation revenue is not less than the expected revenue, and the upper layer represents the maximum value of uncertainty when the lower layer is established. Since the cost of wind power generation is very low and can be ignored, the lower-level target revenue is the lowest when the wind power output reaches the minimum value; at the same time, when the power required by the transmission system is less, the output of each unit is less, and the resulting revenue is also reduced. Therefore, the robust scheduling model shown in the above formula (33) can be converted into a single-level optimization model, as shown in the following formula (35):
[0136]
[0137] Similarly, the lower level target of the opportunity scheduling model is that when the actual wind power output and the transmission power of the transmission channel fluctuate within the uncertainty set, the total operating benefit of the system is higher than the expected cost, and the upper level represents the minimum value of uncertainty when the lower level is established. When the wind power output is greater and the power required by the transmission channel is greater, the total system benefit is greater, so the opportunity scheduling model shown in the above formula (34) can be converted into a single-layer optimization model, as shown in the following formula (36):
[0138]
[0139] Step S204, using the constraint information of the comprehensive uncertainty parameters, the constraint information of the total revenue of the new energy transmission system, the output constraint information of each generator set in the new energy transmission system, the predicted value of the wind turbine output and the predicted value of the transmission power of the transmission channel to solve the scheduling and operation model of the new energy transmission system, and obtain the target value of the output power of each generator set in the new energy transmission system.
[0140] Step S205: scheduling the new energy transmission system based on the target value of the output power of each generator set.
[0141] In the embodiment of the present application, when solving the scheduling operation model of the new energy transmission system, the wind power output prediction value is firstly And the transmission power prediction value of the outgoing channel The optimal value C0 of the objective function is obtained by bringing it into the model for solution, and this is used as the benchmark value for subsequent decision making. Then, the cost deviation coefficients Δ1 and Δ2 are set. The expected cost of the risk-averse decision maker is (1-Δ1)C0, and the expected cost of the opportunity-seeking decision maker is (1+Δ2)C0. The actual value of wind power output is and the actual value of the transmission power of the outgoing channel Instead of solving the model with the predicted value, according to the risk preference of the decision maker, the risk-averse decision maker selects the robust scheduling model, and the opportunity-seeking decision maker selects the opportunity scheduling model, and the uncertainty, the operating income of the transmission system and the output of each unit are solved.
[0142] In this embodiment, a new energy delivery system scheduling device for risk decision-making is also provided, which is used to implement the above-mentioned embodiments and preferred implementation modes, and will not be repeated hereafter. As used below, the term "module" can implement a combination of software and / or hardware for a predetermined function. Although the devices described in the following embodiments are preferably implemented in software, the implementation of hardware, or a combination of software and hardware, is also possible and conceivable.
[0143] This embodiment provides a new energy delivery system scheduling device for risk decision making, such as Figure 3 As shown, including:
[0144] The acquisition module 301 is used to acquire a pre-built new energy transmission system scheduling and operation model, output constraint information of each generator set in the new energy transmission system, predicted value of wind turbine output, predicted value of transmission power of the transmission channel, decision reference value of the operation benefit of the new energy transmission system, preset decision preference information and cost deviation coefficient corresponding to the preset decision preference. The new energy transmission system scheduling and operation model is constructed with the goal of maximizing the total benefit of the new energy transmission system. The new energy transmission system scheduling and operation model is used to characterize the correlation between the output power of each generator set in the new energy transmission system and the total benefit of the new energy transmission system;
[0145] A first determination module 302 is used to determine the constraint information of the total revenue of the new energy delivery system based on the cost deviation coefficient corresponding to the preset decision preference and the decision reference value of the operating revenue of the new energy delivery system;
[0146] The second determination module 303 is used to determine the constraint information of the comprehensive uncertainty parameter based on the preset decision preference information, the comprehensive uncertainty parameter is the sum of the wind power output fluctuation uncertainty parameter and the transmission power uncertainty parameter of the external transmission channel, the wind power output fluctuation uncertainty parameter is used to characterize the deviation degree between the predicted value and the actual value of the wind turbine output, and the transmission power uncertainty parameter of the external transmission channel is used to characterize the deviation degree between the predicted value and the actual value of the transmission power of the external transmission channel;
[0147] The solution module 304 is used to solve the scheduling and operation model of the new energy transmission system by using the constraint information of the comprehensive uncertainty parameters, the constraint information of the total revenue of the new energy transmission system, the output constraint information of each generator set in the new energy transmission system, the predicted value of the output of the wind turbine set and the predicted value of the transmission power of the transmission channel to obtain the target value of the output power of each generator set in the new energy transmission system;
[0148] The scheduling module 305 is used to schedule the new energy transmission system based on the target value of the output power of each generator set.
[0149] In some optional implementations, when the preset decision preference information is risk aversion decision preference information, the constraint information of the total revenue of the new energy delivery system is determined according to the first relationship, which is:
[0150] min C≥(1-Δ1)C0
[0151] Among them, C represents the total revenue of the new energy delivery system, C0 represents the decision-making benchmark value of the operating revenue of the new energy delivery system, and Δ1 is the cost deviation coefficient corresponding to the risk aversion decision preference.
[0152] In some optional implementations, when the preset decision preference information is an opportunity seeking decision preference, the constraint information of the total revenue of the new energy delivery system is determined according to the second relational expression, which is:
[0153] max C≥(1+Δ2)C0
[0154] Among them, C represents the total revenue of the new energy delivery system, C0 represents the decision benchmark value of the operating revenue of the new energy delivery system, and Δ2 is the cost deviation coefficient corresponding to the opportunity seeking decision preference.
[0155] In some optional implementations, the new energy delivery system scheduling operation model is represented by a third relational expression, and the third relational expression is:
[0156]
[0157] Among them, C represents the total revenue of the new energy transmission system, T is the scheduling period; C e,t is the electricity price at time period t; P w,t is the wind power generation power in period t; P i,t represents the power generation of thermal power unit i in time period t; P g,t represents the power generation of the pumped storage power station in time period t; P p,t is the pumping power of the pumped storage power station in period t; N h is the number of thermal power units; u i,t ,y i,t 、z i,t is a 0-1 state variable, u i,t =1 means that thermal power unit i is running during period t, y i,t =1 means that thermal power unit i starts to start at time t, z i,t =1 means that thermal power unit i starts to shut down during period t; is the power generation cost of thermal power unit i; is the startup cost of thermal power unit i; is the shutdown cost of thermal power unit i; N c The number of reversible water pumps for pumped storage power stations; is the startup cost of the pump in the pumped storage power station during period t; is the shutdown cost of the pump in the pumped storage power station during period t.
[0158] In some optional implementations, the second determining module 303 includes:
[0159] When the preset decision preference information is risk aversion decision preference information, the constraint information of the comprehensive uncertainty parameter is determined by the fourth relational expression, which is:
[0160] maxα=α w +αl
[0161] When the preset decision preference information is the opportunity seeking decision preference, the constraint information of the comprehensive uncertainty parameter is determined by the fifth relational expression, which is:
[0162] minα=α w +α l
[0163] Among them, α represents the comprehensive uncertainty parameter, α w represents the uncertainty parameter of wind power output fluctuation, α l Represents the transmission power uncertainty parameter of the outgoing channel.
[0164] In some optional implementations, the decision reference value of the operating income of the new energy transmission system is determined by the following steps: the new energy transmission system scheduling operation model is solved using the output constraint information of each generator set in the new energy transmission system, the predicted value of the wind turbine output and the predicted value of the transmission power of the transmission channel to obtain the decision reference value of the operating income of the new energy transmission system.
[0165] The further functional description of each of the above modules and units is the same as that of the above corresponding embodiments and will not be repeated here.
[0166] The risk decision-making new energy delivery system scheduling device in this embodiment is presented in the form of a functional unit, where the unit refers to an ASIC (Application Specific Integrated Circuit) circuit, a processor and memory that executes one or more software or fixed programs, and / or other devices that can provide the above functions.
[0167] The embodiment of the present invention also provides a computer device having the above Figure 3 The risk decision-making scheduling device of the new energy transmission system is shown.
[0168] See also Figure 4 , Figure 4 is a schematic diagram of the structure of a computer device provided by an optional embodiment of the present invention, such as Figure 4As shown, the computer device includes: one or more processors 10, a memory 20, and interfaces for connecting various components, including high-speed interfaces and low-speed interfaces. Various components are connected to each other using different buses for communication, and can be installed on a common mainboard or installed in other ways as needed. The processor can process the instructions executed in the computer device, including instructions stored in or on the memory to display the graphical information of the GUI on an external input / output device (such as, a display device coupled to the interface). In some optional embodiments, if necessary, multiple processors and / or multiple buses can be used together with multiple memories and multiple memories. Similarly, multiple computer devices can be connected, and each device provides some necessary operations (for example, as a server array, a group of blade servers, or a multi-processor system). Figure 4 A processor 10 is taken as an example.
[0169] The processor 10 may be a central processing unit, a network processor or a combination thereof. The processor 10 may further include a hardware chip. The hardware chip may be a dedicated integrated circuit, a programmable logic device or a combination thereof. The programmable logic device may be a complex programmable logic device, a field programmable gate array, a general purpose array logic or any combination thereof.
[0170] The memory 20 stores instructions executable by at least one processor 10, so that the at least one processor 10 executes the method shown in the above embodiment.
[0171] The memory 20 may include a program storage area and a data storage area, wherein the program storage area may store an operating system, an application required for at least one function; the data storage area may store data created according to the use of the computer device, etc. In addition, the memory 20 may include a high-speed random access memory, and may also include a non-transient memory, such as at least one disk storage device, a flash memory device, or other non-transient solid-state storage device. In some optional embodiments, the memory 20 may optionally include a memory remotely arranged relative to the processor 10, and these remote memories may be connected to the computer device via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.
[0172] The memory 20 may include a volatile memory, such as a random access memory; the memory may also include a non-volatile memory, such as a flash memory, a hard disk or a solid state drive; the memory 20 may also include a combination of the above types of memory.
[0173] The computer device further comprises a communication interface 30 for the computer device to communicate with other devices or a communication network.
[0174] The embodiment of the present invention also provides a computer-readable storage medium. The method according to the embodiment of the present invention can be implemented in hardware, firmware, or can be implemented as a computer code that can be recorded in a storage medium, or can be implemented as a computer code that is originally stored in a remote storage medium or a non-temporary machine-readable storage medium and will be stored in a local storage medium through a network download, so that the method described herein can be stored in such software processing on a storage medium using a general-purpose computer, a dedicated processor, or programmable or dedicated hardware. Among them, the storage medium can be a magnetic disk, an optical disk, a read-only storage memory, a random access memory, a flash memory, a hard disk or a solid-state hard disk, etc.; further, the storage medium can also include a combination of the above types of memories. It can be understood that a computer, a processor, a microprocessor controller, or programmable hardware includes a storage component that can store or receive software or computer code. When the software or computer code is accessed and executed by a computer, a processor, or hardware, the method shown in the above embodiment is implemented.
[0175] A part of the present invention may be applied as a computer program product, such as a computer program instruction, which, when executed by a computer, can call or provide the method and / or technical solution according to the present invention through the operation of the computer. Those skilled in the art should understand that the existence of the computer program instruction in a computer-readable medium includes, but is not limited to, a source file, an executable file, an installation package file, etc., and accordingly, the way in which the computer program instruction is executed by the computer includes, but is not limited to: the computer directly executes the instruction, or the computer compiles the instruction and then executes the corresponding compiled program, or the computer reads and executes the instruction, or the computer reads and installs the instruction and then executes the corresponding installed program. Here, the computer-readable medium may be any available computer-readable storage medium or communication medium accessible to the computer.
[0176] Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.
Claims
1. A new energy delivery system scheduling method considering risk decision-making, characterized in that: The method comprises: Obtaining a pre-built new energy transmission system scheduling and operation model, output constraint information of each generator set in the new energy transmission system, predicted value of wind turbine output, predicted value of transmission power of the transmission channel, decision reference value of the operating income of the new energy transmission system, preset decision preference information, and cost deviation coefficient corresponding to the preset decision preference, wherein the new energy transmission system scheduling and operation model is constructed with the goal of maximizing the total income of the new energy transmission system, and the new energy transmission system scheduling and operation model is used to characterize the correlation between the output power of each generator set in the new energy transmission system and the total income of the new energy transmission system; Determining constraint information of the total revenue of the new energy delivery system based on the cost deviation coefficient corresponding to the preset decision preference and the decision reference value of the operating revenue of the new energy delivery system; Based on the preset decision preference information, the constraint information of the comprehensive uncertainty parameter is determined. The comprehensive uncertainty parameter is the sum of the wind power output fluctuation uncertainty parameter and the transmission power uncertainty parameter of the transmission channel. The wind power output fluctuation uncertainty parameter is used to characterize the degree of deviation between the predicted value and the actual value of the wind turbine output. The transmission power uncertainty parameter of the transmission channel is used to characterize the degree of deviation between the predicted value and the actual value of the transmission power of the transmission channel. The scheduling and operation model of the new energy transmission system is solved by using the constraint information of the comprehensive uncertainty parameters, the constraint information of the total revenue of the new energy transmission system, the output constraint information of each generator set in the new energy transmission system, the predicted value of the output of the wind turbine set, and the predicted value of the transmission power of the transmission channel to obtain the target value of the output power of each generator set in the new energy transmission system; The new energy transmission system is scheduled based on the target value of the output power of each generator set.
2. The method according to claim 1, characterized in that: When the preset decision preference information is risk aversion decision preference information, the constraint information of the total revenue of the new energy delivery system is determined according to a first relational expression, and the first relational expression is: min C≥(1-Δ1)C0 Among them, C represents the total revenue of the new energy delivery system, C0 represents the decision-making benchmark value of the operating revenue of the new energy delivery system, and Δ1 is the cost deviation coefficient corresponding to the risk aversion decision preference.
3. The method according to claim 2, characterized in that When the preset decision preference information is an opportunity seeking decision preference, the constraint information of the total revenue of the new energy delivery system is determined according to the second relational expression, which is: max C≥(1+Δ2)C0 Among them, C represents the total revenue of the new energy delivery system, C0 represents the decision benchmark value of the operating revenue of the new energy delivery system, and Δ2 is the cost deviation coefficient corresponding to the opportunity seeking decision preference.
4. The method according to claim 1, characterized in that: The scheduling and operation model of the new energy delivery system is represented by the third relational expression, which is: Among them, C represents the total revenue of the new energy transmission system, T is the scheduling period; C e,t is the electricity price at time period t; P w,t P is the wind power generation power in period t; i,t represents the power generation of thermal power unit i in time period t; P g,t represents the power generation of the pumped storage power station in time period t; P p,t is the pumping power of the pumped storage power station in period t; N h is the number of thermal power units; u i,t ,y i,t 、z i,t is the state variable of the thermal power unit; is the power generation cost of thermal power unit i; is the startup cost of thermal power unit i; is the shutdown cost of thermal power unit i; N c The number of reversible water pumps for pumped storage power stations; is the startup cost of the pump in the pumped storage power station during period t; W t off is the shutdown cost of the pump in the pumped storage power station during period t.
5. The method according to claim 3, characterized in that: The step of determining constraint information of the comprehensive uncertainty parameter based on preset decision preference information includes: When the preset decision preference information is risk aversion decision preference information, the constraint information of the comprehensive uncertainty parameter is determined by the fourth relational expression, and the fourth relational expression is: maxα=α w +a l When the preset decision preference information is an opportunity seeking decision preference, the constraint information of the comprehensive uncertainty parameter is determined by the fifth relational expression, and the fifth relational expression is: minα=a w +a l Among them, α represents the comprehensive uncertainty parameter, α w represents the uncertainty parameter of wind power output fluctuation, α l Represents the transmission power uncertainty parameter of the outgoing channel.
6. The method according to claim 1, characterized in that The decision benchmark value of the operating income of the new energy transmission system is determined through the following steps: The output constraint information of each generator set in the new energy transmission system, the predicted value of the wind turbine output and the predicted value of the transmission power of the transmission channel are used to solve the scheduling and operation model of the new energy transmission system to obtain the decision-making benchmark value of the operating income of the new energy transmission system.
7. A risk-based decision-making new energy delivery system scheduling device, characterized in that: The device comprises: An acquisition module is used to acquire a pre-built new energy transmission system scheduling and operation model, output constraint information of each generator set in the new energy transmission system, predicted values of wind turbine output, predicted values of transmission power of transmission channels, decision reference values of operating benefits of the new energy transmission system, preset decision preference information, and cost deviation coefficients corresponding to preset decision preferences. The new energy transmission system scheduling and operation model is constructed with the goal of maximizing the total benefits of the new energy transmission system, and is used to characterize the correlation between the output power of each generator set in the new energy transmission system and the total benefits of the new energy transmission system; A first determination module is used to determine the constraint information of the total revenue of the new energy delivery system based on the cost deviation coefficient corresponding to the preset decision preference and the decision reference value of the operating revenue of the new energy delivery system; The second determination module is used to determine the constraint information of the comprehensive uncertainty parameter based on the preset decision preference information. The comprehensive uncertainty parameter is the sum of the wind power output fluctuation uncertainty parameter and the transmission power uncertainty parameter of the external transmission channel. The wind power output fluctuation uncertainty parameter is used to characterize the degree of deviation between the predicted value and the actual value of the wind turbine output. The transmission power uncertainty parameter of the external transmission channel is used to characterize the degree of deviation between the predicted value and the actual value of the transmission power of the external transmission channel. A solution module is used to solve the scheduling and operation model of the new energy transmission system by using the constraint information of the comprehensive uncertainty parameters, the constraint information of the total revenue of the new energy transmission system, the output constraint information of each generator set in the new energy transmission system, the predicted value of the output of the wind turbine set and the predicted value of the transmission power of the transmission channel to obtain the target value of the output power of each generator set in the new energy transmission system; A scheduling module is used to schedule the new energy transmission system based on the target value of the output power of each generator set.
8. A computer device, characterized in that: include: A memory and a processor, wherein the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor executes the new energy delivery system scheduling method considering risk decision-making as described in any one of claims 1 to 6 by executing the computer instructions.
9. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a computer to execute the new energy delivery system scheduling method considering risk decision-making as described in any one of claims 1 to 6.
10. A computer program product, characterized in that The method comprises computer instructions for causing a computer to execute the new energy delivery system scheduling method considering risk decision-making as described in any one of claims 1 to 6.