Distribution network line repairing equipment and distribution network line repairing method
Through the mold components and casting components of the distribution network circuit repair equipment, the aluminum water casting and repair is carried out using drones, which solves the problems of power outages and defect deterioration in distribution network circuit maintenance, and achieves the safe operation of the line and the stability of power supply. .
Patent Information
- Application Number
- CN202411177219.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-26
- Publication Date
- 2024-12-03
AI Technical Summary
The existing distribution network line maintenance technology can easily lead to regional power outages when dealing with defects, and the deterioration of defect locations is difficult to predict, affecting the safe operation of the power system.
It provides a distribution network circuit repair equipment, including mold components and casting components. It uses a drone to carry mold components and casting components to temporarily repair them through clamps and aluminum water to avoid power outage and repair and ensure safe operation of the line.
The temporary repair of distribution network lines is realized, which avoids the deterioration of defects, ensures the safe operation of the power system, avoids the impact of temporary power outages on power supply demand, and extends the service life of the line.
Smart Images

Figure CN119070183A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power equipment maintenance, and in particular to a distribution network line repair device and a distribution network line repair method. Background Art
[0002] At present, the quality of distribution network operation in power construction has a very important impact on the normal operation of the power system. During the operation of the distribution network line, due to short-circuit accidents, single-phase grounding faults, lightning strikes, overloads, environmental corrosion and other reasons, the distribution network line will be damaged, broken strands and other problems. If such problems are not discovered and handled in time, the problems of damage and broken strands will become increasingly serious, seriously affecting the safe operation of the entire power system. The existing practice is that when defects are found in the distribution network line during inspection, the harmfulness of the defects is evaluated. If the harmfulness of the defects is small, the defective area is replaced during the regular power outage maintenance of the power system; if the harmfulness of the defects is large, the power outage maintenance method is immediately adopted to deal with it.
[0003] The existing defect handling method has the following shortcomings: when the distribution network line is immediately shut down for maintenance, it will cause regional power outages, affecting the power supply demand in the corresponding area; when the distribution network line is waiting for regular power outages for maintenance, the deterioration of the defect location is difficult to predict during the waiting time, which is a major hidden danger affecting the safe operation of the power system. Summary of the invention
[0004] The purpose of the embodiments of the present invention is to provide a distribution network line repair device and a distribution network line repair method, which can repair the distribution network line in time, avoid temporary power outages in the region and ensure the safe operation of the distribution network line.
[0005] To achieve the above object, the present invention adopts the following technical solutions:
[0006] Provided is a distribution network line repair device, comprising:
[0007] A mold assembly, the mold assembly includes a base, a first driving member and two clamping blocks, the two clamping blocks are arranged at the bottom of the base, the first driving member is connected to at least one of the clamping blocks, so that the first driving member can drive the two clamping blocks to move closer to or away from each other, and grooves are arranged on the sides of the clamping blocks facing each other, and when the two clamping blocks abut against each other, the two grooves are buckled together to form a receiving cavity for receiving a distribution network line, and a cavity wall of part of the receiving cavity is spaced from the distribution network line;
[0008] A casting assembly, wherein the casting assembly comprises a crucible for containing molten aluminum, and the crucible is used to inject the molten aluminum into the containing cavity.
[0009] Furthermore, along the length direction of the distribution network line, the end regions of the two clamping blocks clamp the distribution network line, the middle regions of the two clamping blocks are spaced from the distribution network line, and a casting gap is formed between the distribution network line and the clamping blocks.
[0010] Furthermore, along the length direction of the distribution network line, the cross section of the casting gap gradually decreases from the middle to the end.
[0011] Furthermore, at least one of the clamping blocks is provided with an air outlet, and the casting gap is connected with the outside of the accommodating cavity through the air outlet.
[0012] Furthermore, a first casting hole for injecting the molten aluminum is opened on the base, and a second casting hole is formed between the two clamping blocks. One end of the second casting hole is connected to the first casting hole, and the other end is connected to the casting gap.
[0013] Furthermore, a liquid outlet hole is provided at the bottom of the crucible, and a metal ball with a density greater than that of the molten aluminum is rolled at the bottom of the crucible, and the metal ball is used to selectively block the liquid outlet hole. A push rod is provided on the base, and when the crucible is close to the base, the push rod passes through the liquid outlet hole and pushes open the metal ball, and the molten aluminum in the crucible flows into the first casting hole through the liquid outlet hole.
[0014] Furthermore, a sleeve is provided on the top of the base, and the bottom end of the crucible can be plugged into the sleeve, so that the liquid outlet hole is directly opposite to the first casting hole.
[0015] Furthermore, the distribution network line repair equipment also includes a drone, the mold assembly and the casting assembly are both carried on the drone, and the crucible is arranged above the base.
[0016] Furthermore, the distribution network line repair equipment also includes a cooling assembly arranged on the drone, the cooling assembly includes a water tank and a spray pipe, the water tank is used to store cooling water, one end of the spray pipe is connected to the water tank, and the other end is facing the mold assembly, and the spray pipe is used to spray the cooling water onto the mold assembly.
[0017] A distribution network line repair method is also provided, which uses a distribution network line repair device to repair the damaged area of the distribution network line, comprising the following steps:
[0018] Step S1, installing the mold assembly on the distribution network line, and the first driving member drives two clamping blocks to clamp the distribution network line, and the damaged area of the distribution network line is located in the accommodating cavity surrounded by the two clamping blocks;
[0019] Step S2, injecting molten aluminum into the containing cavity by using a casting assembly, so that the molten aluminum fills the containing cavity;
[0020] Step S3, cooling the mold assembly to cool the molten aluminum injected into the accommodating cavity to solidify and fuse with the distribution network line.
[0021] The beneficial effects of the present invention are as follows: by providing a mold assembly and a casting assembly, the mold assembly is installed in the damaged area of the distribution network line, and the distribution network line is clamped by two clamps, so that a space for casting molten aluminum is formed between the distribution network line and the clamp. Then, the molten aluminum is transported to the operating area by using a crucible, and the molten aluminum is injected into the space between the distribution network line and the clamp. The solidified aluminum block is fused with the distribution network line to achieve the repair of the damaged area. Since the damaged area of the distribution network line is temporarily repaired, the damaged area of the distribution network line can be prevented from further deterioration, so that the distribution network line can continue to operate safely for a certain period of time, and can be replaced when the power system is subsequently regularly shut down for maintenance. On the one hand, this method avoids the impact of temporary power outages on regional power supply needs, and on the other hand, it can also ensure the operating safety of the distribution network line during the waiting time for maintenance. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] The present invention is further described in detail below based on the accompanying drawings and embodiments.
[0023] Figure 1 A schematic diagram of a distribution network line repair device according to an embodiment of the present invention.
[0024] Figure 2 Schematic diagram of a mold assembly according to an embodiment of the present invention.
[0025] Figure 3 The figure is a schematic diagram of the installation of the mold assembly and the distribution network line according to an embodiment of the present invention.
[0026] Figure 4 2 is a cross-sectional view of a mold assembly according to an embodiment of the present invention.
[0027] Figure 5 Schematic diagram of a crucible according to an embodiment of the present invention.
[0028] In the figure:
[0029] 1. Mold assembly; 11. Base; 110. First casting hole; 12. Clamp; 121. Groove; 122. Second casting hole; 123. Casting gap; 124. Slider; 13. First driving member; 14. Sleeve; 15. Push rod; 2. Casting assembly; 21. Shell; 22. Second driving member; 23. Crucible; 231. Liquid outlet; 24. Metal ball; 3. Cooling assembly; 31. Water tank; 32. Spray pipe; 4. UAV; 41. Bracket; 5. Distribution network line. DETAILED DESCRIPTION
[0030] In order to make the technical problems solved by the present invention, the technical solutions adopted and the technical effects achieved clearer, the technical solutions of the embodiments of the present invention will be further described in detail below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.
[0031] like Figures 1 to 5 As shown, a distribution network line repair device provided by the present invention is used to temporarily repair defects such as damage and broken strands on the distribution network line 5 to extend the service life of the distribution network line 5. That is, by casting molten aluminum in the damaged area of the distribution network line 5, the damaged position is filled with molten aluminum, and the position of the broken strand is fused. The distribution network line repair device includes a mold assembly 1 and a casting assembly 2. Among them, the mold assembly 1 is used to be installed in the damaged area of the distribution network line 5 to provide space for the casting of molten aluminum. The casting assembly 2 is used to store and transport molten aluminum and inject the molten aluminum into the mold assembly 1.
[0032] The mold assembly 1 includes a base 11, a clamping block 12 and a first driving member 13. The base 11 plays an integral supporting role and provides an installation position for the clamping block 12 and the first driving member 13. There are two clamping blocks 12, and the two clamping blocks 12 are arranged at the bottom of the base 11, and the two clamping blocks 12 are arranged in the horizontal direction. One of the clamping blocks 12 is fixedly connected to the base 11, and the other clamping block 12 is slidably connected to the base 11. That is, the end of the slidably connected clamping block 12 close to the base 11 has a slider 124, and correspondingly, the bottom of the base 11 is provided with a guide groove that cooperates with the slider 124, and the slider 124 is slidably connected to the guide groove. The first driving member 13 can be a cylinder, an electric telescopic member or a motor-screw mechanism, and the first driving member 13 is connected to the slidably connected clamping block 12, and the first driving member 13 can drive the corresponding clamping block 12 to approach or move away from the fixedly connected clamping block 12, so as to achieve the two clamping blocks 12 to approach or move away from each other. Of course, in some embodiments, the two clamping blocks 12 may be slidably connected to the base 11, and the first driving member 13 may be connected to the two clamping blocks 12 to drive the two clamping blocks 12 to move closer to or farther from each other. The specific mechanical structure of using the first driving member 13 to drive the two clamping blocks 12 to move closer to or farther from each other is a well-known prior art, and the specific mechanical structure will not be described in detail herein.
[0033] The mold assembly 1 has an open state and a closed state. When the first driving member 13 drives the two clamping blocks 12 to move away from each other, the two clamping blocks 12 are spaced apart, and the distribution network line 5 can pass between the two clamping blocks 12. At this time, the mold assembly 1 is in an open state; when the first driving member 13 drives the two clamping blocks 12 to approach each other, the two clamping blocks 12 abut against each other. At this time, the mold assembly 1 is in a closed state. A groove 121 is provided on the side of the clamping blocks 12 facing each other. When the mold assembly 1 is in a closed state, the two clamping blocks 12 abut against each other. At this time, the grooves 121 on the two clamping blocks 12 are buckled together to form a receiving cavity for accommodating the distribution network line 5. The cavity wall of part of the receiving cavity is spaced apart from the distribution network line 5 so that molten aluminum can be injected between the cavity wall of the receiving cavity and the distribution network line 5. It can be understood that after the molten aluminum is injected into the receiving cavity, it will fuse with the distribution network line 5 to achieve the repair of the distribution network line 5. Therefore, the shape of the receiving cavity should be matched with the shape of the distribution network line 5 and the aluminum block formed after the molten aluminum solidifies.
[0034] The casting assembly 2 includes a crucible 23 for containing molten aluminum. During the casting operation, the molten aluminum is placed in the crucible 23 and the crucible 23 is used to inject the aluminum into the receiving cavity of the mold assembly 1.
[0035] In this embodiment, by setting the mold assembly 1 and the casting assembly 2, the mold assembly 1 is installed in the damaged area of the distribution network line 5, and the distribution network line 5 is clamped by two clamps 12, so that a space for casting molten aluminum is formed between the distribution network line 5 and the clamps 12. Then the molten aluminum is transported to the operating area by the crucible 23, and the molten aluminum is injected into the space between the distribution network line 5 and the clamps 12. The solidified aluminum block is fused with the distribution network line 5 to achieve the repair of the damaged area. Since the damaged area of the distribution network line 5 is temporarily repaired, the damaged area of the distribution network line 5 can be prevented from further deterioration, so that the distribution network line 5 can continue to operate safely for a certain period of time, and then be replaced when the power system is regularly shut down for maintenance. On the one hand, this method avoids the impact of temporary power outages on regional power supply needs, and on the other hand, it can also ensure the operation safety of the distribution network line 5 during the waiting time for maintenance.
[0036] Specifically, refer to Figure 4As shown, along the length direction of the distribution network line 5 (X direction in the figure), the end areas of the two clamps 12 clamp the distribution network line 5, and the middle areas of the two clamps 12 are spaced from the distribution network line 5, and a casting gap 123 is formed between the distribution network line 5 and the clamps 12. It can be understood that the size of the end of the accommodating cavity matches the diameter size of the distribution network line 5, so that the end areas of the two clamps 12 can clamp the distribution network line 5 to prevent the aluminum liquid injected into the accommodating cavity from leaking from the end of the accommodating cavity. The casting gap 123 is a part of the accommodating cavity, and the casting gap 123 is located in the middle area of the accommodating cavity, that is, the part between the distribution network line 5 and the cavity wall of the accommodating cavity. After the aluminum liquid is injected into the accommodating cavity, the aluminum liquid fills the casting gap 123. Therefore, the shape of the casting gap 123 should be the same as the shape of the aluminum block to be formed after the aluminum liquid solidifies. When installing the mold assembly 1, the damaged area on the distribution network line 5 can be located in the casting gap 123.
[0037] In order to further ensure the fusion effect of molten aluminum and the distribution network line 5 and save the amount of molten aluminum, the cross section of the casting gap 123 gradually decreases from the middle to the end along the length direction of the distribution network line 5. It can be understood that the cross section of the casting gap 123 is annular, and the entire casting gap 123 is a structure with a large middle and small ends. When installing the mold assembly 1, the damaged area of the distribution network line 5 is adjusted to the middle position of the casting gap 123 to increase the casting thickness of the damaged area and ensure the quality of the repair. At the same time, the two ends of the casting gap 123 are relatively small, and the main purpose of the two end areas of the casting gap 123 is to increase the contact surface between the solidified aluminum block and the distribution network line 5, increase the fusion area, and prevent the aluminum block from falling off. Therefore, the two end areas of the casting gap 123 can be cast thinner to save the amount of molten aluminum.
[0038] Specifically, the clamp block 12 is provided with an air outlet (not shown in the figure), and the air outlet is located at the top of the clamp block 12. The casting gap 123 is connected to the outside of the accommodating cavity through the air outlet. It can be understood that when molten aluminum is injected into the casting gap 123, the internal air can be discharged through the air outlet, so that the molten aluminum can flow smoothly into the casting gap 123. In practical applications, the position of the air outlet can be reasonably arranged according to the specific structure of the clamp block 12 and the installation form of the clamp block 12 and the base 11, and the setting position of the air outlet is not specifically limited here.
[0039] Specifically, a first casting hole 110 for injecting molten aluminum is provided on the base 11, the axis of the first casting hole 110 extends in the vertical direction, and the top of the first casting hole 110 is configured to be trumpet-shaped to facilitate the injection of molten aluminum. When the two clamps 12 abut against each other, a second casting hole 122 is formed between the two clamps 12. One end of the second casting hole 122 is connected to the first casting hole 110, and the other end is connected to the casting gap 123. During casting, the molten aluminum flows through the first casting hole 110 and the second casting hole 122 in sequence and enters the casting gap 123. It should be noted that when the mold assembly 1 is in a closed state, the second casting hole 122 is located directly below the first casting hole 110.
[0040] Specifically, refer to Figure 4 and Figure 5 As shown, a liquid storage chamber for accommodating aluminum water is formed inside the crucible 23, the bottom of the liquid storage chamber is spherical, and the lowest point of the liquid storage chamber coincides with the axis of the liquid storage chamber. A metal ball 24 is arranged in the crucible 23, the density of the metal ball 24 is greater than the density of aluminum water, and the metal ball 24 can sink to the bottom of the aluminum water. A liquid outlet 231 is provided at the bottom of the crucible 23, and the liquid outlet 231 is coaxial with the liquid storage chamber. The metal ball 24 can roll freely at the bottom of the crucible 23, and under the action of its own weight, the metal ball 24 rolls to the lowest point of the liquid storage chamber, and the metal ball 24 blocks the liquid outlet 231. Of course, the end of the liquid outlet 231 close to the liquid storage chamber can also be set to a trumpet shape, so that the metal ball 24 can fit with one end of the liquid outlet 231 to stably block the liquid outlet 231. Correspondingly, a sleeve 14 and a push rod 15 are arranged on the base 11. The inner diameter of the sleeve 14 matches the outer diameter of the crucible 23, and one end of the sleeve 14 is connected to the base 11. The first casting hole 110 is connected to the inside of the sleeve 14, and the two are coaxially arranged. The push rod 15 is fixed above the first casting hole 110 by a connecting rod, and the diameter of the push rod 15 is smaller than the diameter of the liquid outlet 231. During casting, the bottom end of the crucible 23 is inserted into the sleeve 14, and the bottom of the crucible 23 is abutted against the base 11. When the bottom end of the crucible 23 is inserted into the sleeve 14, the liquid outlet 231 is opposite to the first casting hole 110. The push rod 15 passes through the liquid outlet 231 and pushes open the metal ball 24, so that the molten aluminum in the crucible 23 flows into the first casting hole 110 through the gap between the liquid outlet 231 and the push rod 15. It is understandable that, since the casting is performed at high altitude, the sleeve 14 is provided so that the crucible 23 is injected in a plug-in manner, which facilitates the fixation of the crucible 23 and promotes the alignment between the crucible 23 and the base 11. At the same time, since the aluminum liquid is in a high temperature state, it is not convenient to set up pipes and valves to transport and control the aluminum liquid. By setting the metal ball 24 to block the liquid outlet 231, it has the characteristics of simple structure and convenient operation.
[0041] Specifically, refer to Figure 1As shown, the distribution network line repair equipment also includes a drone 4 and a cooling assembly 3. The mold assembly 1, the casting assembly 2 and the cooling assembly 3 are all installed on the drone 4. The drone 4 is a prior art, which is used to transport the mold assembly 1, the casting assembly 2 and the cooling assembly 3 to the high-altitude distribution network line 5 for casting repair operations. The drone 4 includes a bracket 41, and the mold assembly 1, the casting assembly 2 and the cooling assembly 3 are all installed on the bracket 41, and the casting assembly 2 is located above the mold assembly 1. The casting assembly 2 also includes a shell 21 and a second driving member 22. The crucible 23 is installed in the shell 21, and the bottom of the shell 21 has an opening connected to the outside. The inner wall of the shell 21 is provided with a heat insulation layer, so that the shell 21 provides mechanical and heat insulation protection for the crucible 23 to prevent the aluminum liquid from being greatly cooled and solidified during transportation. The second driving member 22 is mounted on the housing 21. The second driving member 22 may be a cylinder or an electric telescopic member. The output end of the second driving member 22 is connected to the base 11 so that the second driving member 22 can drive the mold assembly 1 to move closer to or away from the housing 21. The cooling assembly 3 includes a water tank 31 and a spray pipe 32. The water tank 31 is used to store cooling water. One end of the spray pipe 32 is connected to the water tank 31, and the other end faces the mold assembly 1. The spray pipe 32 is used to spray cooling water to the mold assembly 1 so that the aluminum water in the casting gap 123 can be quickly cooled and solidified to improve the working efficiency.
[0042] During the repair operation, firstly, aluminum blocks are added to the crucible 23 on the ground and heated to form aluminum liquid. Then the crucible 23 is installed in the housing 21, and the mold assembly 1, the casting assembly 2 and the cooling assembly 3 are transported to the damaged area of the distribution network line 5 by the drone 4. The drone 4 descends to a certain height, so that the distribution network line 5 enters the accommodating cavity between the two clamping blocks 12 from the bottom of the mold assembly 1. The first driving member 13 drives the two clamping blocks 12 to clamp the distribution network line 5, and the damaged area of the distribution network line 5 is located in the casting gap 123. The second driving member 22 drives the mold assembly 1 and the casting assembly 2 to move closer, and the drone 4 descends at the same time. At this time, the crucible 23 is inserted into the sleeve 14, and the push rod 15 pushes the metal ball 24 away, and the aluminum liquid enters the casting gap 123 from the crucible 23 through the liquid outlet 231, the first casting hole 110 and the second casting hole 122 in sequence. Finally, the cooling assembly 3 sprays cooling water onto the mold assembly 1 to rapidly cool down and solidify the molten aluminum to complete the repair.
[0043] like Figure 1 and Figure 4 As shown, a distribution network line repair method is also provided, using a distribution network line repair device to repair the damaged area of the distribution network line 5. The repair method includes the following steps:
[0044] Step S1, install the mold assembly 1 on the distribution network line 5, and the first driving member 13 drives the two clamps 12 to clamp the distribution network line 5, and the damaged area of the distribution network line 5 is located in the accommodating cavity surrounded by the two clamps 12. Specifically, the mold assembly 1 and the casting assembly 2 are carried by the drone 4 to the damaged area of the distribution network line 5. The distribution network line 5 is inserted into the accommodating cavity from the bottom of the mold assembly 1, that is, the gap between the two clamps 12. The first driving member 13 drives the two clamps 12 to clamp the distribution network line 5.
[0045] Step S2, using the casting assembly 2 to inject molten aluminum into the accommodating cavity of the mold assembly 1, so that the molten aluminum fills the accommodating cavity. Specifically, after the distribution network line 5 is clamped in the accommodating cavity, along the length direction of the distribution network line 5, the two ends of the accommodating cavity are pressed against the distribution network line 5, and the middle area of the accommodating cavity is spaced from the distribution network line 5 to form a casting gap 123. The molten aluminum in the crucible 23 is injected into the casting gap 123 through the first casting hole 110 and the second casting hole 122 in sequence, and the molten aluminum fills the entire casting gap 123, so that the molten aluminum can cover the entire damaged area.
[0046] Step S3, cooling the mold assembly 1 so that the aluminum water injected into the accommodating cavity is cooled and solidified, and fused with the distribution network line. Specifically, the drone 4 is also equipped with a cooling assembly 3, through which cooling water is sprayed on the outer surface of the mold assembly 1 to quickly cool it down, promote the solidification of the aluminum water, reduce the waiting time for the aluminum water to solidify, and improve the repair efficiency. In other embodiments, the drone 4 may not be equipped with a cooling assembly 3, and the mold assembly 1 is naturally cooled in the air.
[0047] The beneficial effects of the present invention are as follows: by setting the mold assembly 1 and the casting assembly 2, the mold assembly 1 is installed in the damaged area of the distribution network line 5, and the distribution network line 5 is clamped by two clamps 12, so that a space for casting molten aluminum is formed between the distribution network line 5 and the clamps 12. Then, the molten aluminum is transported to the operating area by using the crucible 23, and the molten aluminum is injected into the space between the distribution network line 5 and the clamps 12, and the solidified aluminum block is fused with the distribution network line 5 to achieve the repair of the damaged area. Since the damaged area of the distribution network line 5 is temporarily repaired, the damaged area of the distribution network line 5 can be prevented from further deteriorating, so that the distribution network line 5 can continue to operate safely for a certain period of time, and then be replaced when the power system is regularly shut down for maintenance. On the one hand, this method avoids the impact of temporary power outages on regional power supply needs, and on the other hand, it can also ensure the operating safety of the distribution network line 5 during the waiting time for maintenance.
[0048] The above contents are only preferred embodiments of the present invention. For ordinary technicians in this field, according to the concept of the present invention, there will be changes in the specific implementation methods and application scopes. The content of this specification should not be understood as limiting the present invention.
Claims
1. A distribution network line repair device, characterized in that: include: A mold assembly, the mold assembly includes a base, a first driving member and two clamping blocks, the two clamping blocks are arranged at the bottom of the base, the first driving member is connected to at least one of the clamping blocks, so that the first driving member can drive the two clamping blocks to move closer to or away from each other, and grooves are arranged on the sides of the clamping blocks facing each other, and when the two clamping blocks abut against each other, the two grooves are buckled together to form a receiving cavity for receiving a distribution network line, and a cavity wall of part of the receiving cavity is spaced from the distribution network line; A casting assembly, wherein the casting assembly comprises a crucible for containing molten aluminum, and the crucible is used to inject the molten aluminum into the containing cavity.
2. The distribution network line repair equipment according to claim 1, characterized in that: Along the length direction of the distribution network line, the end regions of the two clamping blocks clamp the distribution network line, the middle regions of the two clamping blocks are spaced from the distribution network line, and a casting gap is formed between the distribution network line and the clamping blocks.
3. The distribution network line repair equipment according to claim 2, characterized in that: Along the length direction of the distribution network line, the cross section of the casting gap gradually decreases from the middle to the end.
4. The distribution network line repair equipment according to claim 2, characterized in that: At least one of the clamping blocks is provided with an air outlet hole, and the casting gap is communicated with the outside of the accommodating cavity through the air outlet hole.
5. The distribution network line repair equipment according to claim 2, characterized in that: The base is provided with a first casting hole for injecting the molten aluminum, and a second casting hole is formed between the two clamping blocks. One end of the second casting hole is connected to the first casting hole, and the other end is connected to the casting gap.
6. The distribution network line repair equipment according to claim 5, characterized in that: A liquid outlet hole is provided at the bottom of the crucible, and a metal ball with a density greater than that of the molten aluminum is rolled at the bottom of the crucible, and the metal ball is used to selectively block the liquid outlet hole. A push rod is provided on the base, and when the crucible is close to the base, the push rod passes through the liquid outlet hole and pushes open the metal ball, and the molten aluminum in the crucible flows into the first casting hole through the liquid outlet hole.
7. The distribution network line repair equipment according to claim 6, characterized in that: A sleeve is arranged on the top of the base, and the bottom end of the crucible can be plugged into the sleeve, so that the liquid outlet hole is directly opposite to the first casting hole.
8. The distribution network line repair device according to any one of claims 1 to 7, characterized in that: The distribution network line repair equipment also includes a drone, the mold assembly and the casting assembly are both carried on the drone, and the crucible is arranged above the base.
9. The distribution network line repair equipment according to claim 8, characterized in that: The distribution network line repair equipment also includes a cooling assembly arranged on the drone, and the cooling assembly includes a water tank and a spray pipe. The water tank is used to store cooling water, one end of the spray pipe is connected to the water tank, and the other end is directed toward the mold assembly. The spray pipe is used to spray the cooling water onto the mold assembly.
10. A distribution network line repair method, characterized in that: Repairing the damaged area of the distribution network line using the distribution network line repair device according to any one of claims 1 to 9 comprises the following steps: Step S1, installing the mold assembly on the distribution network line, and the first driving member drives two clamping blocks to clamp the distribution network line, and the damaged area of the distribution network line is located in the accommodating cavity surrounded by the two clamping blocks; Step S2, injecting molten aluminum into the containing cavity by using a casting assembly, so that the molten aluminum fills the containing cavity; Step S3, cooling the mold assembly to cool the molten aluminum injected into the accommodating cavity to solidify and fuse with the distribution network line.