Using method of large-height-difference raft foundation steel structure diagonal bracing formwork
Through the angle connection and steel pipe buckle, the vertical I-shaped steel, horizontal I-shaped steel and inclined I-shaped steel is solved, and the problem of easy loosening of the oblique support mold of the steel structure in the construction of raft slab foundations of large public buildings is achieved, and fast and firm connection is achieved. Multiple use has improved construction efficiency and quality.
Patent Information
- Application Number
- CN202411558851.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-04
- Publication Date
- 2024-12-06
AI Technical Summary
In the construction of raft foundations in large public buildings, the support mold reinforcement of the raft foundation with high and low difference is difficult, and the steel structure oblique support molds are prone to loosening, which affects the construction quality, and traditional welding connections lead to extended construction periods and waste of resources.
An angle connection piece and steel pipe buckle are used to connect vertical I-shaped steel, horizontal I-shaped steel and inclined I-shaped steel. It is fixed by bolts without welding, achieving rapid and firm connection and easy adjustment.
It improves the stability and reusability of steel structure oblique support molds, reduces construction period and resource waste, and ensures construction quality and safety.
Smart Images

Figure CN119083475A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a diagonal bracing formwork for a raft foundation steel structure, and in particular to a method for using a diagonal bracing formwork for a large height difference raft foundation steel structure. Background Art
[0002] In the current construction field, customers have more and more demands for large public buildings. Combined with urban planning and the needs of civil air defense, garages and supermarkets, the foundation and foundation engineering of these buildings usually account for a relatively important proportion in the design stage. The raft foundation of large public buildings is often designed as a raft with high and low spans for separation because the number of underground floors of the main building is inconsistent with the number of floors of the garage. Therefore, in the high and low span raft foundation, the construction is difficult due to factors such as height difference and raft thickness. The reinforcement work of the formwork is very difficult and the quality is not easy to guarantee, which has a great impact on the construction quality of the structure. The commonly used formwork is mainly composed of steel structure or steel structure combined with formwork. The steel structure as a reusable mold and its skeleton are the guarantee of efficient and excellent construction speed. The steel frame is composed of a lightweight steel pipe structure, but the stability is relatively poor. Therefore, inclined support is an indispensable structural measure. The role of inclined support for steel structure frame has the following advantages: enhancing the stability of the structure, reducing structural vibration and improving the overall strength. The use of steel structure inclined support formwork in actual use The first is to set positive and negative screw holes at both ends of the inclined support, and then adjust the angle by positive and negative screws. When pouring cement, the inclined support will be slightly shaken by the impact of cement and the vibration of the cement transporting vehicle itself, which will further cause the inclined support to loosen. In this way, local deformation of the cast wall will occur under the pressure of cement, affecting the difficulty of later wall treatment and painting. Especially in the construction of large height difference raft slab side formwork, in traditional practices, the height difference position of the raft foundation section is difficult to construct and the formwork is easy to explode. Usually, the tension screws are welded on the high-span raft slab stress reinforcement and the side formwork steel pipe is inclined to support the formwork. Because all the tension bolts are welded on the raft slab stress reinforcement, it is very easy to cause the stress reinforcement to move, and it is difficult to ensure the construction quality. In order to ensure the quality and support strength, some construction uses vertical I-beams, horizontal I-beams and inclined I-beams as steel structure diagonal bracing formwork, and the connection is welded. After use, such steel structure diagonal bracing formwork needs to be cut by a cutting machine at the weld, which makes it impossible to use it a second time, resulting in a prolonged construction period and a waste of I-beams. Summary of the invention
[0003] The purpose of the present invention is to disclose a method for using a diagonal bracing formwork for a steel structure of a large height difference raft foundation based on the deficiencies of the prior art. The vertical I-beam and the horizontal I-beam are firmly connected by means of an arranged angle connector, and the vertical I-beam and the horizontal I-beam are firmly connected by means of the vertical plates and the horizontal plates at both ends of the diagonal I-beam. The steel pipe buckle facilitates the quick and firm connection of the diagonal I-beam and the steel pipe, and no welding is required.
[0004] In order to achieve the purpose of the invention, the present application discloses the following technical solutions: A diagonal bracing formwork for a steel structure of a large height difference raft foundation comprises a vertical I-beam, an angle connector, a horizontal I-beam, an end fixing block, an oblique I-beam and a steel pipe buckle. The lower end of the vertical I-beam is externally plugged into a convex groove A of an upper and lower structure for the angle connector, the upper inner end of the horizontal I-beam is plugged into a convex groove A of an inner and outer structure for the angle connector, the middle of the outer end of the horizontal I-beam is plugged into the groove of the end fixing block, fixing plates connected to the ground are respectively provided at the outer end and both sides of the end fixing block, the vertical plates and horizontal plates respectively provided at the upper and lower ends of the oblique I-beam are fixedly connected to the middle of the vertical I-beam and the horizontal I-beam by bolts, and a steel pipe buckle for connecting steel pipes is provided in the middle of the upper surface of the oblique I-beam.
[0005] The diagonal bracing formwork of the steel structure of the large height difference raft foundation, the corner connector is made of a steel plate welded with a convex-shaped slot A having half the structural shape of an I-beam inside, and the aforementioned one is divided into two to form two card plates A each having a convex-shaped slot A, one of which has a notch facing inward and the other has a notch facing downward; and then two reinforcement plates are welded and connected to form the corner connector.
[0006] The diagonal bracing formwork of the large height difference raft foundation steel structure is provided with screw holes in the middle of the two clamping plates A of the corner connector, and four bolts in groups of two pass through the screw holes and are fixedly connected to the lower end of the vertical I-beam and the inner end of the horizontal I-beam.
[0007] The diagonal bracing formwork of the steel structure of the large height difference raft foundation is provided with a slot in the middle of the inner end face of the end fixing block, and a convex plate is provided at the lower part of the end fixing block near the outer end, the middle upper surface of the convex plate is fixedly connected to the lower surface of the end fixing block near the outer end, and fixing holes are respectively provided on the three exposed plate bodies of the convex plate.
[0008] The diagonal bracing formwork of the large height difference raft foundation steel structure is provided with screw holes on both sides of the end fixing block, and two bolts pass through the screw holes and are pressed against the two side surfaces of the middle vertical plate of the horizontal I-beam.
[0009] The diagonal bracing formwork of the large height difference raft foundation steel structure is provided with a vertical plate at the upper end of the inclined I-beam, and oblong holes are respectively provided on the vertical plate near both sides. Two bolts pass through the oblong holes and are connected to the screw holes provided in the middle of the vertical I-beam.
[0010] The diagonal bracing formwork of the large height difference raft foundation steel structure is provided with a horizontal plate at the lower end of the inclined I-beam, and oblong holes are respectively provided near both sides of the horizontal plate. Two bolts pass through the oblong holes and are connected to the screw holes provided in the middle of the horizontal I-beam.
[0011] The diagonal bracing formwork of the steel structure of the large height difference raft foundation is characterized in that two semicircular bottom plates are arranged at intervals on the upper surface of the lower clamping plate B of the steel pipe buckle, and a convex groove B is arranged in the clamping plate B. The convex groove B is clamped in the middle of the oblique I-beam and is fastened and fixed by bolts. One side of the two semicircular bottom plates is hingedly connected to one side of the upper semicircular buckle plate through an axis, and a plane is arranged at the end of the other side of the two semicircular buckle plates, and a notch is arranged in the middle of the plane. The middle of the other side of the two semicircular bottom plates is hingedly connected to the lower end of the screw rod, and the upper part of the screw rod is in the notch, and a nut is arranged at the upper end of the screw rod.
[0012] The method for using the diagonal bracing formwork for the steel structure of the large height difference raft foundation comprises pre-installation of formwork, assembly of tension screws, installation of transverse and horizontal keels, pre-assembly of I-beams, installation and fixation of I-beams, correction and acceptance, concrete pouring and removal of formwork; A. Template pre-installation According to the size of the template components, the template assembly design is carried out in advance, and the template is assembled by the operators; sponge strips are used to seal the template joints to prevent leakage; B. Assembly of tension screws Use a drill to drill holes for the tension bolts on the assembled template; C. Transverse and horizontal keel installation After the formwork is assembled, the vertical keel needs to be arranged according to the positioning position, and then the vertical keel needs to be installed from one end to the other. In the raft slab concrete that has been poured outside the high and low span construction joints, the anti-expansion formwork structural steel bars are reserved before pouring. The tension bolts are inserted into the holes, and the operators enter the upper and lower steel bars of the raft slab and use electric welding machines to weld and fix the previously reserved anti-expansion formwork structural steel bars and tension bolts. After the vertical keel is installed and temporarily fixed, two steel pipes are used as a horizontal keel for reinforcement. Starting from the bottom of the formwork, a horizontal keel is installed upwards, and the tension bolts are fixed in the horizontal keel to start reinforcement. D. I-beam pre-assembly Insert the lower end of the vertical I-beam into the upper and lower convex grooves A of the angle connector, fix it with bolts, and adjust the steel pipe buckle to a suitable height; E. Installation and fixation of I-beam On the outside of the horizontal keel, according to the support design of the I-beam, add a vertical I-beam to reinforce the formwork. The steps for installing the vertical I-beam are the same as the vertical keel. First install it from one end to the other. After each vertical I-beam is installed, use wire to temporarily fix it to the horizontal keel; then install multiple vertical I-beams; use the same number of horizontal I-beams as the vertical I-beams to install them separately, insert the inner end of the horizontal I-beam into the inner and outer convex grooves A of the angle connector, and then use bolts to fix the angle connector to the inner end of the horizontal I-beam. According to the position of the fixing holes of the fixing plate of the end fixing block, use a drill on the concrete floor outside the post-casting belt that has been poured and settled. Punch a fixing hole, use the slot of the end fixing block to clamp it on the middle vertical plate at the outer end of the horizontal I-beam, then insert the three steel bar heads through the fixing hole and insert them into the fixing hole on the ground as anchor points to support the end of the horizontal I-beam to prevent the lateral load from impacting the horizontal I-beam and causing displacement and deformation of the template; the two oblong holes of the vertical plates at the upper and lower ends of the inclined I-beam and the two oblong holes of the horizontal plate correspond to the screw holes of the vertical I-beam and the horizontal I-beam respectively, then use four bolts to pass through the oblong holes and fix the screw holes of the vertical I-beam and the horizontal I-beam; use steel pipes to connect and fix with the steel pipe buckles of each inclined I-beam to improve the overall stability of the I-beam system; F. Correction acceptance After the overall formwork reinforcement is completed, the team leader will complete the self-inspection of various technical indicators; after the I-beam is installed, the installation quality and appearance size inspection will be carried out in a timely manner; only after all are qualified can the pouring of concrete be applied; G. Concrete pouring After acceptance, concrete pouring shall be carried out. During the pouring process, the concrete pouring of the raft foundation at the low elevation shall be carried out first, and the pouring shall be carried out from far to near in layers and sections, and vibrated during pouring. Do not touch the horizontal I-beam and inclined I-beam during the vibrating process. When the raft at the low elevation is poured to the bottom of the lateral formwork, the pouring shall be stopped. Before the concrete strength reaches the initial setting, the concrete from the high-low slope position to the high-elevation raft shall be poured. The pouring shall still be carried out in accordance with the principle of layers and sections from far to near to avoid the concentrated impact of horizontal loads and deformation of the formwork. H. Remove the template After pouring is completed and the conditions for demolding are met, the installation personnel of the carpentry team will carry out demolding. The demolding should be carried out in the order of steel pipes, inclined I-beams, vertical I-beams, horizontal I-beams, corner connectors and their end fixing blocks, horizontal purlins, and vertical purlins. Before demolding, a demolding order should be applied for and permission can only be obtained.
[0013] Through the above invention content, the beneficial effects of the present invention are: The method for using the diagonal bracing formwork for the large height difference raft foundation described in the present invention utilizes the two convex grooves A of the angle connector to respectively connect the lower end of the vertical I-beam and the inner end of the horizontal I-beam, and then further reinforces them with bolts, thereby obtaining a firm connection between the vertical I-beam and the horizontal I-beam; the present invention respectively arranges a vertical plate and a horizontal plate at both ends of the inclined I-beam, so that the two ends of the inclined I-beam can be firmly connected to the vertical I-beam and the horizontal I-beam by bolts; the steel pipe buckle of the present invention can be conveniently connected to the inclined I-beam, and the position adjustment is realized, and the connection is fast and firm; the present invention uses connectors for all connections, and there is no need to spend time on welding connections, thereby achieving lossless multiple uses of all components. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a step diagram of the method of using the present invention; Figure 2 It is a three-dimensional structural schematic diagram of the present invention; Figure 3 It is a schematic diagram of the three-dimensional structure of the I-beam of the present invention; Figure 4 It is a schematic diagram of the three-dimensional structure of the end fixing block of the present invention; Figure 5 It is a schematic diagram of the card slot structure of the end fixing block of the present invention; Figure 6 It is a schematic diagram of the three-dimensional structure of the corner connector of the present invention; Figure 7 It is a schematic diagram of the three-dimensional structure of the steel pipe buckle of the present invention; In the figure: 1. vertical I-beam; 2. oblique I-beam; 3. steel pipe; 4. steel pipe buckle; 5. horizontal I-beam; 6. end fixing block; 7. corner connector; 8. vertical plate; 9. oblong hole; 10. horizontal plate; 11. slot; 12. screw hole; 13. fixing hole; 14. fixing plate; 15. convex slot A; 16. clamping plate A; 17. reinforcement plate; 18. screw; 19. nut; 20. shaft; 21. semicircular bottom plate; 22. clamping plate B; 23. convex slot B. DETAILED DESCRIPTION
[0015] The preferred embodiments of the present invention will be described in detail below in conjunction with the accompanying drawings so as to more clearly understand the purpose, features and advantages of the present invention. It should be understood that the embodiments shown in the accompanying drawings are not intended to limit the scope of the present invention, but are only intended to explain that the technical solution of the present invention is not limited to one implementation method.
[0016] Combined with Figures 2 to 7The diagonal bracing formwork of the steel structure of the large height difference raft foundation described in the invention comprises a vertical I-beam 1, an angle connector 7, a horizontal I-beam 5, an end fixing block 6, an oblique I-beam 2 and a steel pipe buckle 4. The lower end of the vertical I-beam 1 is externally plugged into the angle connector 7 to form a convex groove A15 of an upper and lower structure. The upper inner end of the horizontal I-beam 5 is plugged into the angle connector 7 to form a convex groove A15 of an inner and outer structure. The middle of the outer end of the horizontal I-beam 5 is inserted into the groove 11 of the end fixing block 6. Fixed plates 14 connected to the ground are respectively provided at the outer end and both sides of the end fixing block 6. The vertical plates 8 and the horizontal plates 10 respectively provided at the upper and lower ends of the oblique I-beam 2 are fixedly connected to the middle of the vertical I-beam 1 and the horizontal I-beam 5 by bolts. A steel pipe buckle 4 connecting the steel pipe 3 is provided in the middle of the upper surface of the oblique I-beam 2.
[0017] Combined with Figure 2 Or 6, the corner connector 7 is welded with a convex groove A15 having half the structure of an I-beam inside the steel plate, and the aforementioned one is divided into two or three, two of which form two clamping plates A16 each having a convex groove A15, one of which has a notch facing inward and the other has a notch facing downward; then two triangular reinforcing plates 17 are welded and connected to form the corner connector 7; screw holes are respectively provided in the middle of the two clamping plates A16 of the corner connector 7, and four bolts in groups of two are respectively passed through the screw holes and fixedly connected to the lower end of the vertical I-beam 1 and the inner end of the horizontal I-beam 5.
[0018] Combined with Figure 2 , 4 Or 5, a card slot 11 is provided in the middle of the inner end face of the end fixing block 6, a convex plate is provided at the lower part of the end fixing block 6 near the outer end, the middle upper face of the convex plate is fixedly connected to the lower face of the end fixing block 6 near the outer end, and fixing holes 13 are respectively provided on the three exposed plate bodies of the convex plate; screw holes 12 are respectively provided on both sides of the end fixing block 6, and two bolts are respectively passed through the screw holes 12 and then pressed against the two side faces of the middle vertical plate of the horizontal I-beam 5.
[0019] Combined with Figure 2 , 3and 7, a vertical plate 8 is provided at the upper end of the inclined I-beam 2, and oblong holes 9 are respectively provided on the vertical plate 8 near both sides, and two bolts are respectively passed through the oblong holes 9 and connected to the screw holes set in the middle of the vertical I-beam 1; a horizontal plate 10 is provided at the lower end of the inclined I-beam 2, and oblong holes 9 are respectively provided on both sides of the horizontal plate 10, and two bolts are respectively passed through the oblong holes 9 and connected to the screw holes set in the middle of the horizontal I-beam 5; further, after making one of the vertical plate 8 and the horizontal plate 10, the inclined I-beam 2, First, put the convex groove B23 of the steel pipe buckle 4 clamping plate B22 on the inclined I-beam 2, and then make another vertical plate 8 or horizontal plate 10; the method of making the vertical plate 8 and the horizontal plate 10 is to use gas cutting to leave enough length for the vertical plate 8 and the horizontal plate 10 at the upper and lower ends of the inclined I-beam 2 and then cut the inclined connecting surface. Another steel plate can also be used to obtain the vertical plate 8 and the horizontal plate 10 by welding after cutting the inclined surfaces at both ends; then turn the oblong hole 9 on the vertical plate 8 and the horizontal plate 10.
[0020] Combined with Figure 2 Or 7, two semicircular bottom plates 21 are arranged at intervals on the upper surface of the lower clamping plate B22 of the steel pipe buckle 4, and a convex groove B23 is arranged in the clamping plate B22. The convex groove B23 is clamped in the middle of the inclined I-beam 2 and fixed by bolts. One side of the two semicircular bottom plates 21 is hingedly connected to one side of the upper semicircular buckle plate through an axis 20, and a plane is arranged at the end of the other side of the two semicircular buckle plates, and a notch is arranged in the middle of the plane. The middle of the other side of the two semicircular bottom plates 21 is hingedly connected to the lower end of the screw 18, and the upper part of the screw 18 is in the notch, and a nut 19 is arranged at the upper end of the screw 18; the above structure can be divided using a steel pipe connecting cross fastener, and then the connecting surfaces of the two fasteners are obtained after gas cutting and leveling.
[0021] Combined with Figures 1 to 7 The method for using the diagonal bracing formwork of the steel structure of the large height difference raft foundation of the present invention comprises pre-installation of formwork, assembly of tension screw rods, installation of transverse and horizontal keels, pre-assembly of I-beams, installation and fixation of I-beams, correction and acceptance, concrete pouring and removal of formwork; A. Template pre-installation According to the size of the formwork components, the formwork assembly design is carried out in advance. The principle of using complete formwork for large areas is followed. The principle of cutting is adopted for the detailed nodes. The formwork is assembled by the operators. Sponge strips are used to seal the joints between the formwork to prevent leakage. B. Assembly of tension screws On the assembled formwork, use a drill to drill holes for the tension bolts, with horizontal and vertical spacings ranging from 400mm to 450mm; C. Transverse and horizontal keel installation After the template is assembled, the vertical keel layout position shall be located using a marker pen, and then the vertical keel shall be installed from one end to the other. The horizontal spacing of the vertical keel is 150mm, and the horizontal distance from the free end on the outside of the template shall not be greater than 100mm; in the raft slab concrete that has been poured outside the high and low span construction joints, anti-expansion formwork structural steel bars shall be reserved before pouring, and the anti-expansion formwork steel bars are not the raft slab force-bearing steel bars; φ14 tension bolts shall be inserted into the holes, and the operating personnel shall enter the upper and lower steel bars of the raft slab and use an electric welder to weld and fix the previously reserved anti-expansion formwork structural steel bars and tension bolts; after the vertical keel is installed and temporarily fixed, two φ48*2.5 steel pipes are used as a horizontal keel for reinforcement; starting from 200mm from the bottom end of the template, a horizontal keel shall be installed every 450mm upwards, and the tension bolts shall be fixed in the horizontal keel to start reinforcement; D. I-beam pre-assembly Insert the lower end of the vertical I-beam 1 into the upper and lower convex grooves A15 of the angle connector 7, fix it with bolts, and adjust the steel pipe buckle 4 to a suitable height; E. Installation and fixation of I-beam On the outside of the horizontal keel, according to the support design of the I-beam, add a vertical I-beam 1 every 1m to reinforce the formwork. The steps for installing the vertical I-beam 1 are the same as those for the vertical keel. First install it from one end to the other end. The horizontal distance between the first vertical I-beam 1 and the edge of the formwork shall not exceed 10 cm. After each vertical I-beam 1 is installed, use 20# iron wire to temporarily fix it to the horizontal keel; then install a vertical I-beam 1 every 1m; use the same number of horizontal I-beams 5 as the vertical I-beams 1 to install them separately, insert the inner end of the horizontal I-beam 5 into the inner and outer convex grooves A15 of the angle connector 7, and then use bolts to fix the angle connector 7 to the inner end of the horizontal I-beam 5, and use a φ20 drill bit to drill a hole 1 meter deep on the concrete floor outside the post-casting belt after the settlement has been poured according to the position of the fixing hole 13 of the fixing plate 14 of the end fixing block 6. 00mm fixing hole, use the card slot 11 of the end fixing block 6 to clamp on the middle vertical plate at the outer end of the horizontal I-beam 5, then insert 3 250mmφ20 steel bar heads through the fixing hole 13 and insert them into the fixing hole on the ground as anchor points to support the end of the horizontal I-beam 5 to prevent the lateral load from impacting the horizontal I-beam 5 and causing displacement and deformation of the template; the two oblong holes 9 of the vertical plates 8 at the upper and lower ends of the inclined I-beam 2 and the two oblong holes 9 of the horizontal plate 10 correspond to the screw holes of the vertical I-beam 1 and the horizontal I-beam 5 respectively, and then use four bolts to pass through the oblong holes 9 and fix the screw holes of the vertical I-beam 1 and the horizontal I-beam 5 respectively; use φ48*2.5 specification steel pipe 3 to connect and fix with the steel pipe buckle 4 of each inclined I-beam 2 to improve the overall stability of the I-beam system; the spacing of the steel pipe 3 on the inclined I-beam 2 is 500mm; F. Correction acceptance After the overall formwork reinforcement is completed, the team leader completes the self-inspection and reports to the project department for inspection; the project department quality inspectors and professional construction workers arrive at the site to check the technical indicators such as the thickness of the protective layer, verticality, flatness, formwork joints, axis deviation, embedded parts position and quantity according to the drawing dimensions; after the I-beam is installed, the installation quality and appearance size inspection shall be carried out in a timely manner; after all inspections meet the requirements, the supervision unit shall be reported for inspection and acceptance, and only after all are qualified can the pouring of concrete be applied; G. Concrete pouring After acceptance, concrete pouring is carried out; during the pouring process, the concrete pouring of the raft foundation at the low elevation should be carried out first, and the pouring should be carried out from far to near in layers and sections, and each layer of concrete should not exceed 300mm. Vibration should be carried out while pouring, and the horizontal I-beam 5 and the inclined I-beam 2 should not be touched during the vibration process; when the raft at the low elevation is poured to the bottom of the lateral formwork, the pouring is suspended, and before the concrete strength reaches the initial setting, the concrete from the high-low slope position to the high-elevation raft is continued. The pouring should still be carried out in accordance with the principle of layers and sections from far to near to avoid the concentrated impact of horizontal loads and deformation of the formwork; H. Remove the template After pouring is completed and the conditions for demolding are met, the installation personnel of the carpentry team will remove the mold. The demolding should be carried out in the order of steel pipe 3, inclined I-beam 2, vertical I-beam 1, horizontal I-beam 5, corner connector 7 and its end fixing block 6, horizontal keel, and vertical keel; a demolding order should be applied for before demolding, and it can only be carried out after permission is obtained.
[0022] The preferred embodiments of the present invention have been described in detail above, but it should be understood that after reading the above teachings of the present invention, those skilled in the art may make various changes or modifications within the scope of protection of the present invention. These equivalent forms also fall within the scope defined by the claims attached to this application.
[0023] Parts of the present invention not described in detail are prior art.
Claims
1. A diagonal bracing formwork for a steel structure of a large height difference raft foundation, comprising a vertical I-beam (1), an angle connector (7), a horizontal I-beam (5), an end fixing block (6), an oblique I-beam (2) and a steel pipe buckle (4), wherein: The lower end of the vertical I-beam (1) is externally plugged into the angle connector (7) to form a convex groove A (15) of an upper and lower structure, and the upper inner end of the horizontal I-beam (5) is plugged into the angle connector (7) to form a convex groove A (15) of an inner and outer structure. The middle of the outer end of the horizontal I-beam (5) is inserted into the groove (11) of the end fixing block (6), and fixing plates (14) connected to the ground are respectively provided at the outer end and both sides of the end fixing block (6). The vertical plate (8) and the horizontal plate (10) respectively provided at the upper and lower ends of the inclined I-beam (2) are fixedly connected to the middle of the vertical I-beam (1) and the horizontal I-beam (5) by bolts, and a steel pipe buckle (4) for connecting the steel pipe (3) is provided in the middle of the upper surface of the inclined I-beam (2).
2. The large height difference raft foundation steel structure diagonal bracing formwork according to claim 1 is characterized by: The corner connector (7) is welded from a steel plate to form a convex groove A (15) having a half structural shape of an I-beam. The steel plate is divided into two to form two clamping plates A (16) each having a convex groove A (15), wherein one clamping plate A (16) has a groove facing inwards and the other clamping plate A (16) has a groove facing downwards. The two reinforcement plates (17) are then welded together to form the corner connector (7).
3. The large height difference raft foundation steel structure diagonal bracing formwork according to claim 2 is characterized by: Screw holes are respectively provided in the middle of the two clamping plates A (16) of the corner connector (7), and four bolts in groups of two are respectively passed through the screw holes and fixedly connected to the lower end of the vertical I-beam (1) and the inner end of the horizontal I-beam (5).
4. The large height difference raft foundation steel structure diagonal bracing formwork according to claim 1 is characterized by: A slot (11) is provided in the middle of the inner end surface of the end fixing block (6), and a convex plate is provided at the lower part of the end fixing block (6) near the outer end. The middle upper surface of the convex plate is fixedly connected to the lower surface of the end fixing block (6) near the outer end, and fixing holes (13) are respectively provided on three exposed plate bodies of the convex plate.
5. The large height difference raft foundation steel structure diagonal bracing formwork according to claim 4 is characterized by: Screw holes (12) are respectively provided on both sides of the end fixing block (6), and two bolts are respectively passed through the screw holes (12) and then pressed against the two side surfaces of the middle vertical plate of the horizontal I-beam (5).
6. The large height difference raft foundation steel structure diagonal bracing formwork according to claim 1 is characterized in that: A vertical plate (8) is arranged at the upper end of the inclined I-beam (2), and oblong holes (9) are respectively arranged on the vertical plate (8) near both sides, and two bolts are respectively passed through the oblong holes (9) and connected to the screw holes arranged in the middle of the vertical I-beam (1).
7. The large height difference raft foundation steel structure diagonal bracing formwork according to claim 1 is characterized in that: A horizontal plate (10) is provided at the lower end of the inclined I-beam (2). Long round holes (9) are respectively provided near two sides of the horizontal plate (10). Two bolts pass through the long round holes (9) and are connected to screw holes provided in the middle of the horizontal I-beam (5).
8. The large height difference raft foundation steel structure diagonal bracing formwork according to claim 1 is characterized by: Two semicircular bottom plates (21) are arranged at intervals on the upper surface of the lower clamping plate B (22) of the steel pipe buckle (4). A convex-shaped clamping groove B (23) is arranged in the clamping plate B (22). The convex-shaped clamping groove B (23) is clamped in the middle of the inclined I-beam (2) and is fixed by bolts. One side of the two semicircular bottom plates (21) is hingedly connected to one side of the upper semicircular buckle plate through a shaft (20). The other end of the two semicircular buckle plates is provided with a plane, and the middle of the plane is provided with a notch. The middle of the other side of the two semicircular bottom plates (21) is hingedly connected to the lower end of the screw rod (18), and the upper part of the screw rod (18) is located in the notch. The upper end of the screw rod (18) is provided with a nut (19).
9. The method for using the diagonal bracing formwork for the large height difference raft foundation steel structure according to any one of claims 1 to 8 is characterized by: Including formwork pre-installation, assembly of tension screws, installation of transverse and horizontal keels, pre-assembly of I-beams, installation and fixation of I-beams, correction and acceptance, concrete pouring and formwork removal; A. Template pre-installation According to the size of the template components, the template assembly design is carried out in advance, and the template is assembled by the operators; sponge strips are used to seal the template joints to prevent leakage; B. Assembly of tension screws Use a drill to drill holes for the tension bolts on the assembled template; C. Transverse and horizontal keel installation After the formwork is assembled, the vertical keel needs to be arranged according to the positioning position, and then the vertical keel needs to be installed from one end to the other. In the raft slab concrete that has been poured outside the high and low span construction joints, the anti-expansion formwork structural steel bars are reserved before pouring. The tension bolts are inserted into the holes, and the operators enter the upper and lower steel bars of the raft slab and use electric welding machines to weld and fix the previously reserved anti-expansion formwork structural steel bars and tension bolts. After the vertical keel is installed and temporarily fixed, two steel pipes are used as a horizontal keel for reinforcement. Starting from the bottom of the formwork, a horizontal keel is installed upwards, and the tension bolts are fixed in the horizontal keel to start reinforcement. D. I-beam pre-assembly Insert the lower end of the vertical I-beam (1) into the upper and lower convex grooves A (15) of the angle connector (7), fix it with bolts, and adjust the steel pipe buckle (4) to a suitable height; E. Installation and fixation of I-beam On the outside of the horizontal keel, according to the support design of the I-beam, multiple vertical I-beams (1) are added to reinforce the formwork. The steps for installing the vertical I-beams (1) are the same as those for the vertical keel. First, install from one end to the other end. After each vertical I-beam (1) is installed, it is temporarily fixed to the horizontal keel with iron wire; then install multiple vertical I-beams (1); use the same number of horizontal I-beams (5) as the vertical I-beams (1) to install them respectively, insert the inner end of the horizontal I-beam (5) into the inner and outer convex grooves A (15) of the angle connector (7), and then use bolts to fix the angle connector (7) to the inner end of the horizontal I-beam (5). According to the position of the fixing hole (13) of the fixing plate (14) of the end fixing block (6), use a drill to drill fixing holes on the concrete floor outside the post-casting strip after the settlement has been poured. , use the slot (11) of the end fixing block (6) to clamp on the middle vertical plate at the outer end of the horizontal I-beam (5), then insert the three steel bar heads through the fixing holes (13) and into the fixing holes on the ground as anchor points to support the end of the horizontal I-beam (5) to prevent the lateral load from impacting the horizontal I-beam (5) and causing displacement and deformation of the template; the two oblong holes (9) of the vertical plates (8) at the upper and lower ends of the inclined I-beam (2) and the two oblong holes (9) of the horizontal plate (10) correspond to the screw holes of the vertical I-beam (1) and the horizontal I-beam (5), and then use four bolts to pass through the oblong holes (9) and fix the screw holes of the vertical I-beam (1) and the horizontal I-beam (5); use the steel pipe (3) to connect and fix with the steel pipe buckle (4) of each inclined I-beam (2) to improve the overall stability of the I-beam system; F. Correction acceptance After the overall formwork reinforcement is completed, the team leader will complete the self-inspection of various technical indicators; after the I-beam is installed, the installation quality and appearance size inspection will be carried out in a timely manner; only after all are qualified can the pouring of concrete be applied; G. Concrete pouring After acceptance, concrete pouring is carried out. During the pouring process, the concrete of the raft foundation at the lower elevation should be poured first, and the pouring should be carried out in layers and sections from far to near, and vibrating should be carried out while pouring. During the vibrating process, the horizontal I-beam (5) and the inclined I-beam (2) should not be touched. When the raft at the lower elevation is poured to the bottom of the lateral formwork, the pouring is stopped. Before the concrete strength reaches the initial setting, the concrete at the slope position with a high elevation difference is poured. The pouring should still be carried out in layers and sections from far to near to avoid the impact of horizontal load concentration and deformation of the formwork. H. Remove the template After pouring is completed and the conditions for demolding are met, the installation personnel of the carpentry team shall remove the molds in the order of steel pipes (3), inclined I-beams (2), vertical I-beams (1), horizontal I-beams (5), corner connectors (7) and their end fixing blocks (6), horizontal keels, and vertical keels. Before demolding, a demolding order shall be applied for and the demolding may only be carried out after obtaining permission.