Gas extraction system and method for bedding drilling gas injection displacement flow increase
By designing a gas injection and flow-injection gas pumping system for coal mines under the coal mine, the problem of low gas extraction efficiency of coal seam is solved, and efficient filtration, measurement and extraction of gas gas is achieved, and the coal seam gas is improved. The extraction efficiency and ensure underground safety.
Patent Information
- Application Number
- CN202411102303.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-12
- Publication Date
- 2024-12-06
AI Technical Summary
The gas extraction efficiency in underground coal mines is low, mainly due to the poor air permeability of the coal seam and the increase in the resistance of the pipeline network caused by the gas flow, and the increase in errors. The existing technology lacks a systematic gas injection and extraction connection system. This results in low gas extraction efficiency of coal seams.
A gas extraction system for gas injection and flow-injection and replacing the flow of the vertical drilling hole is designed, including a gas injection device and a extraction device. The gas filtering and metering is performed through a filter and a gas meter, using a booster pump and rapid The joints realize the rapid connection between gas injection and extraction, forming a complete technical system for gas injection and injection and injection drive, and the operation methods of reciprocating extraction, group injection and extraction, first injection and then extraction are adopted.
It effectively improves the efficiency of gas extraction in coal seams, reduces the separation time between the gas injection sealing pipe and the pipeline, reduces the dissipation of gas gas, protects underground safety, and realizes accurate measurement and efficient extraction of gas gas.
Smart Images

Figure CN119083958A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of underground coal mine gas extraction, and in particular relates to a gas extraction system and method for gas injection displacement and flow enhancement in layer drilling. Background Art
[0002] At present, gas extraction technology in coal mine areas is the main way to control coal seam gas disasters. Extracting gas stored in coal seams can better solve problems such as abnormal gas outburst and coal and gas outburst. However, field practice has found that poor coal seam permeability is the main reason restricting the effect of gas extraction. The problem of low permeability of coal seams can be solved by hydraulic fracturing and hydraulic cutting, but due to the large differences in coal seam storage conditions in different mines, various problems will still arise during the extraction process. And whether gas extraction meets the standards must be strictly and accurately measured. Since the extracted coal seam gas airflow often contains a certain amount of moisture, coal powder and other substances, there are problems of increasing pipeline network resistance and increasing errors.
[0003] In my country, the underground enhanced pre-extraction of coal seam gas mostly adopts gas injection to displace coal seam gas, improve the permeability of coal seams, and achieve the purpose of enhanced extraction. The underground compressed air system makes it more convenient to obtain underground compressed air, but there is currently no systematic gas injection and extraction connection system to form a complete technical system for gas injection and displacement flow increase and extraction of gas in coal seam drilling, which makes the coal seam gas extraction efficiency low. Summary of the invention
[0004] In order to solve the deficiencies in the prior art, the present invention provides a gas extraction system and method for gas injection and flow increase in coal seam drilling, forming a complete technical system for gas extraction by gas injection and flow increase in coal seam drilling, effectively solving the problem of low efficiency of existing coal seam gas extraction.
[0005] In order to solve the above technical problems, the present invention adopts the following technical scheme: a gas extraction system for gas injection and flow increase in layer drilling, comprising a set of gas injection device 3 and two sets of extraction devices located on the left and right sides of the gas injection device 3, each set of extraction devices comprising a filtering device 4 and a gas metering device 5, the gas injection port of the gas injection device 3 is connected to the gas injection hole sealing pipe 33 extending into the coal seam 55, the air inlet of the gas injection device 3 is connected to the gas injection main pipe 1 underground in the coal mine, the air inlet of the filtering device 4 is connected to the extraction hole sealing pipe 27 extending into the coal seam 55, the air outlet of the filtering device 4 is connected to the air inlet of the gas metering device 5, and the air outlets of the two gas metering devices 5 are connected to the extraction main pipe 2 in the underground tunnel of the coal mine.
[0006] The filtering device 4 includes a filter 15, a sealed water tank 17, a water tank air inlet pipe 19 and a water tank air outlet pipe 20. The inlet of the filter 15 is connected to the outlet of the extraction hole sealing pipe 27, the inlet of the water tank air inlet pipe 19 is connected to the outlet of the filter 15, an air release valve 16 is provided on the filter 15, and a drain valve 18 is provided at the bottom of the sealed water tank 17.
[0007] The gas metering device 5 includes a multi-parameter gas meter 23, a first pipeline 40, a second pipeline 28 and a gas meter 26. The inlet end of the multi-parameter gas meter 23 is connected to the water tank outlet pipe 20, the outlet end of the multi-parameter gas meter 23 is connected to one end of the first pipeline 40, the air inlet of the gas meter 26 is connected to the other end of the first pipeline 40, the air outlet of the gas meter 26 is connected to one end of the second pipeline 28, and the other end of the second pipeline 28 is connected to the extraction main pipe 2; the filtering device 4 and the gas metering device 5 are connected between the extraction hole sealing pipe 27 and the extraction main pipe 2, and then under the negative pressure of the extraction main pipe 2, the gas in the coal seam is extracted and filtered, water-gas separated and metered in turn to form an extraction circuit.
[0008] The gas injection device 3 includes a gas injection guide pipe 12, a booster pump 8, a quick connector 6 and a third pipeline 25. The upper end of the quick connector 6 is connected to the gas injection hole sealing pipe 33, and the lower end of the quick connector 6 is connected to one end of the third pipeline 25; the air inlet end of the booster pump 8 is connected to one end of the gas injection guide pipe 12, the other end of the gas injection guide pipe 12 is connected to the gas injection main pipe 1, and the air outlet end of the booster pump 8 is connected to the other end of the third pipeline 25; the gas injection device 3 is connected between the gas injection main pipe 1 and the gas injection hole sealing pipe 33, and the booster pump 8 further pressurizes the positive pressure airflow in the gas injection main pipe 1 and injects it into the coal seam through the quick connector and the gas injection hole sealing pipe 33 to form a sealed loop.
[0009] The gas extraction method of the gas extraction system for gas injection displacement and flow enhancement in layer drilling comprises the following steps:
[0010] A. Carry out fine division of gas geological grids for pre-extraction coal seams, determine the gas occurrence of coal seams, and determine the thickness, layer fluctuation and gas content of coal seams according to the on-site exploration conditions. In the pre-extraction area, drill holes shall be constructed in accordance with the requirements of the national standard GB / T-42638-2023 to determine the number, spacing, hole depth and sealing depth of the in-layer extraction holes. The hole diameter and length shall be consistent with the daily extraction holes in the mine;
[0011] B. After the drilling construction is completed, install a gas injection hole sealing pipe 33 in a gas injection borehole, install a drainage hole sealing pipe 27 in two drainage boreholes adjacent to the gas injection borehole, and measure the distances d1 and d2 between the gas injection borehole and the two adjacent drainage boreholes; install and connect the gas drainage system, turn on the filter device 4 and the gas metering device 5, use the drainage main pipe 2 in the underground tunnel of the coal mine to pre-drain the gas from the drainage borehole under negative pressure before mining, and record the drainage negative pressure p. The pre-drainage time is determined according to the gas geological characteristics of the mining area;
[0012] d1 and d2 are the minimum distances between the gas injection borehole and the two adjacent extraction boreholes. This distance is the actual effective distance between fracturing and gas injection displacement. If the distance between the borehole centers is recorded, it will lead to gross errors.
[0013] C. Use the gas metering device 5 to monitor parameters in real time. When it is monitored that the mixed flow rate of gas extraction in the extraction borehole does not fluctuate greatly within five days and the change range is less than 10%, the pre-extraction work of the layer drilling is completed;
[0014] D. Start the gas injection device 3 and the booster pump 8 to conduct a gas injection test for 6 hours under the condition of gas injection pressure p0. In the initial stage of gas injection, as the compressed air from the gas injection source continuously displaces the coal seam gas, the gas concentration and pure amount of gas in the extraction borehole will gradually decrease; at the same time, the gas extraction system is used to monitor the pressure in the gas injection borehole and the continuous gas injection time, as well as the single-hole negative pressure, mixed flow rate and gas concentration of the extraction borehole in real time;
[0015] E. Evaluate the gas flooding effect of the gas injection boreholes in the bedding layer within 6 hours of gas injection test;
[0016] F. After the 6-hour gas injection test of the gas injection drilling in the layer, the gas injection operation shall be carried out using the corresponding gas injection method according to the evaluation results;
[0017] G. Determine whether there is a hole in the hole and take corresponding measures;
[0018] H. After the fracturing and permeability enhancement of the coal seam and the gas injection displacement, the gas injection device 3 of the gas injection hole in the layer is replaced with a filtering device 4 and a gas metering device 5, which are connected to the extraction main pipe 2 in the underground tunnel of the coal mine, and gas extraction is carried out on the gas injection holes in the layer and the extraction holes at the same time, that is, the injection-first-then-extraction mode is implemented.
[0019] The optimal selection of the gas injection pressure p0 in step D is as follows:
[0020] Open the valve on the gas injection device 3 pipeline, adjust the gas injection pressure of the booster pump 8 to p0, inject compressed air into the gas injection borehole in the layer, and start two sets of extraction devices at the same time to extract from the extraction borehole in the layer, that is, implement the long injection and short extraction mode;
[0021] Gas diffusion motion complies with Fick's law, so in the pore system, CH4 and air satisfy the diffusion motion equation:
[0022]
[0023] Where: c1, c2 represent the diffusion mass concentration of CH4 and air in the adsorption state of coal seam, Q1, Q2 are the mass sources of CH4 and air, D1, D2 are the diffusion coefficients of CH4 and air, respectively.
[0024] The amount of multi-component gas adsorbed by coal can be calculated by the adsorption equilibrium theory and expressed by the generalized Langmuir equation: the mass relationship between CH4 and air in the adsorbed state on the coal surface and CH4 and air in the free state in the fracture system is:
[0025]
[0026] Where τ is the adsorption time constant; ρ c is the density of coal; ρ1 and ρ2 are the gas component densities of CH4 and air under standard conditions; a1 and a2 are the limit adsorption capacities of CH4 and air when adsorbed alone; b1 and b2 are the adsorption equilibrium constants of CH4 and air respectively; p1 and p2 are the equilibrium partial pressures of CH4 and air respectively;
[0027] Substituting the multivariate gas adsorption equilibrium equation, seepage velocity equation, gas state and mass exchange equation into the gas seepage equation in the fracture, the coupled equation group can be obtained as follows:
[0028]
[0029] In the formula, φ is the porosity; A1 and A2 are the molar masses of the gas components CH4 and air respectively; B1 and B2 are the gas constants of the gas components CH4 and air respectively; T is the gas temperature; k is the coal permeability; μ1 and μ2 are the dynamic viscosity coefficients of the gas components CH4 and air respectively; p is the total pressure;
[0030] From the above three equations, it can be seen that the gas extraction effect of gas injection displacement is mainly affected by the injected gas flow rate, injection pressure and injection temperature. The initial injection volume is large, and the higher the injection pressure, the greater the flow rate of injected air. Since a large amount of gas is discharged from the free space of the coal seam before gas injection, the pressure of the free space is low. After air injection, these free spaces are quickly filled, and the pressure in the coal seam rises rapidly. Therefore, in the early stage of air injection, the extracted gas mixed flow rate is large;
[0031] In order to determine the influence of gas injection pressure on the gas drive flow enhancement and extraction effect, a numerical model under different gas injection pressure conditions was established for simulation analysis. The extraction negative pressure was set to 20 KPa, the spacing between gas injection and extraction holes was 1.5 m, and the gas injection pressures were set to 0.3 MPa, 0.5 MPa and 1 MPa respectively. The simulated gas injection pressures were 0.3 MPa, 0.5 MPa, and 1 MPa. The greater the gas injection pressure, the more significant the gas injection displacement flow enhancement effect. However, the gas drive effect is improved less when it is greater than 0.5 MPa, and the coal seam can bear a limited maximum gas injection pressure, which may easily cause gas overflow accidents. Therefore, the optimal gas injection pressure p0 is 0.5 MPa.
[0032] The specific process of step E is:
[0033] The recorded gas extraction mixed flow rates of the two extraction boreholes are both higher than the set first threshold value (indicating that the coal seam mixed flow rate does not change much), and the coal seam gas concentration is lower than the set second threshold value (indicating that the coal seam gas concentration does not change much). It is determined that under the conditions of gas injection pressure p0, hole spacing d1, hole spacing d2, and single hole extraction negative pressure P, the scheme has significant effects on fracturing permeability enhancement and gas injection displacement of coal seams;
[0034] The first threshold is 400% of the initial value of the gas mixed flow rate; the mixed flow rate refers to the flow rate of the CH4 and CO mixed gas in the extraction hole before gas injection; the second threshold is 30% of the initial value of gas concentration extraction; the initial value of gas concentration extraction refers to the data recorded when the gas concentration of all the in-layer extraction boreholes in this group remains stable after three consecutive monitorings at the initial stage of single negative pressure extraction;
[0035] There are pore systems 44 and fracture systems 43 in the coal seam between the gas injection hole 41 and the extraction hole 42; in the gas injection stage I, compressed air 46 is injected into the coal body from the gas injection hole 41, which increases the porosity and permeability of the coal body to a certain extent, thereby facilitating the migration of gas 45 in the coal;
[0036] Entering the gas injection II stage, the gas concentration drops significantly after the free gas in the coal body fracture channels is diluted by the injected gas, and the adsorbed gas in the pore system 44 begins to diffuse outward. Combined with the expansion and compression of the compressed air 46, the fracture system 43 is further developed, which effectively promotes the mutual interconnection of pores and the development and expansion of fractures. The compressed air 46 controls the effective stress of the fracture system 43 to prevent the fractures from closing again. The free gas 45 is continuously driven out of the coal body under the action of the pressure gradient, and the adsorbed gas 45 is continuously desorbed due to the reduction of gas partial pressure and enters the extraction pipeline.
[0037] The specific process of step F is:
[0038] After a 6-hour gas injection test of the gas injection boreholes in the layer, if the recorded gas extraction mixed flow rate of the two extraction boreholes is lower than the set first threshold, it indicates that the coal seam mixed flow rate has not changed much, or the coal seam gas concentration is higher than the set second threshold, indicating that the coal seam gas concentration has not changed much, it is determined that under the conditions of gas injection pressure p0, hole spacing d1, hole spacing d2, and single hole extraction negative pressure P, the scheme has no obvious effect on the fracturing permeability enhancement and gas injection displacement of the coal seam; at this time, the gas injection pressure p0 should be increased by 50%, and the second round of gas extraction should be completed according to the method in step C; if the second round of injection and extraction still fails to achieve the expected effect, the gas injection pressure p0 will be increased by 45% again, and the gas injection flow rate will be increased by 65%, and the third round of injection and extraction will be continued, that is, the cyclic injection and extraction mode will be adopted;
[0039] The cyclic injection and extraction mode is to determine the extraction efficiency of continuous gas injection and intermittent gas injection. The experiment arranges continuous gas injection and intermittent gas injection. After the drilling construction is completed, the net is hung for extraction at the same time, and the pure gas quantity of the extraction hole is tested regularly. The drilling lengths of different drilling spacings are basically the same, and the analysis results ignore the influence of the drilling length.
[0040] Although the total extraction volume increased by intermittent gas injection competitive replacement is less than the extraction volume increased by long-term continuous gas injection energy-enhanced driving at the same gas injection pressure, the intermittent gas injection competitive adsorption replacement time is sufficient, the replacement volume is large, and the replacement efficiency is higher. Therefore, intermittent gas injection is preferred.
[0041] The specific process of step G is:
[0042] If the gas injection test of the gas injection drilling holes in the layer begins for 6 hours, and the recorded gas extraction mixed flow of the two extraction boreholes quickly exceeds the set first threshold, it is preliminarily judged that the borehole inclination angle is too large and the borehole spacing is much smaller than the measured borehole spacing, and a hole-to-hole phenomenon may occur; for further judgment, the left extraction hole is maintained to continue negative pressure extraction, the valve on the right extraction device is closed, the quick connector 6 of the gas injection device 3 is removed, and the palm is placed on the mouth of the gas injection hole sealing tube 33. If the suction generated by the negative pressure in the tube is felt, it is determined that the left extraction hole and the gas injection hole are in hole-to-hole; if the suction generated by the negative pressure in the tube is not felt, it is determined that the left extraction hole and the gas injection hole are not in hole-to-hole;
[0043] Repeat the operation content of step G to determine whether there is a hole-to-hole phenomenon between the left extraction hole and the right extraction hole and between the gas injection hole and the right extraction hole; the specific process is as follows: set the boreholes where the hole-to-hole phenomenon occurs as a group; use this group of boreholes as the gas injection hole group, drill a borehole on both sides of the gas injection hole group as a extraction hole, install the gas injection device 3 and the extraction device, and repeat the operation content of step G to determine whether the boreholes on the left and right sides have a hole-to-hole phenomenon with the gas injection hole group; if hole-to-hole phenomenon occurs, include the borehole of the hole-to-hole phenomenon into the gas injection hole group, continue to drill additional holes on the borehole side of the hole-to-hole phenomenon as extraction holes, and continue to repeat the operation content of step G until no hole-to-hole phenomenon occurs; if hole-to-hole phenomenon is not found, connect the group of gas injection holes to the gas injection device, and connect the extraction holes on the left and right sides to the filtering and extraction devices for negative pressure extraction. Open the valve of the gas injection device and conduct a 6-hour gas injection test. Stop for 6 hours after the gas injection is completed. If the recorded mixed flow rate of the two extraction boreholes is higher than the set third threshold, it indicates that the coal seam mixed flow rate has not changed much, and the coal seam gas concentration is lower than the set fourth threshold, indicating that the coal seam gas concentration has not changed much. It is judged that the compressed gas has completed fracturing development in the coal seam. If the set relevant indicators are not met, increase the gas injection flow rate by 80% at this time, continue the gas injection test for 6 hours, and stop for 6 hours after the gas injection is completed. If the gas extraction flow rate is higher than that before gas injection, the gas extraction flow rate is higher than that before gas injection. Increase by 45%, judging that the compressed gas has completed the fracturing development in the coal seam under the action of atmospheric flow; if the set relevant indicators are not met, increase the gas injection pressure by 50% and use the heating device to increase the gas injection temperature by 60%, conduct a 6-hour gas injection test, and stop for 6 hours after the gas injection is completed; if the gas extraction flow rate is increased by 45% compared with that before gas injection, it is judged that the compressed gas has completed the fracturing development in the coal seam under the combined action of high pressure, atmospheric flow and hot gas; after the fracturing development is completed, connect the gas injection hole group to the extraction main pipe for extraction to further increase gas extraction;
[0044] The third threshold value is 150% of the initial value of the gas mixed flow rate; the mixed flow rate refers to the flow rate of the CH4 and CO mixed gas in the extraction hole before gas injection; the fourth threshold value is 60% of the initial value of the gas concentration extraction; the initial value of the gas concentration extraction refers to the data recorded when the gas concentration of all the in-layer extraction boreholes in this group remains stable after three consecutive monitorings at the initial stage of single negative pressure extraction.
[0045] By adopting the above technical scheme, the present invention has outstanding substantial characteristics and significant progress compared with the prior art. Specifically, the present invention utilizes the quick connection and separation of the quick connector and the gas injection hole sealing tube to improve the speed and reliability of pipeline connection; in particular, the gas injection hole sealing tube is separated from the quick connector, thereby reducing the time for separating the gas injection sealing tube from the gas injection pipeline, thereby reducing the escape of residual gas in the tube into the working face, and protecting the lives of underground coal miners.
[0046] The present invention adopts a gas injection device to inject air into the coal seam. Of course, it is preferred to inject safe gases such as nitrogen and carbon dioxide into the coal seam to displace the gas around the coal seam gas injection holes, drive the gas into the coal seam extraction holes, and extract the gas through negative pressure suction, and then filter, separate the water and gas, and measure them in turn before collecting and extracting them through the extraction main pipe.
[0047] The present invention arranges a pre-filter and a sealed water tank at the front end of the multi-parameter gas meter and the gas meter, which solves the problem of equipment damage caused by impurities such as coal powder and condensed water in the pipeline entering the multi-parameter gas meter and the gas meter, and does not affect the resistance of the extraction system, thereby achieving the goal of increasing the accurate measurement of the gas flow.
[0048] To sum up, the gas injection displacement pipeline and gas extraction pipeline adopted in the present invention both adopt a quick-connect structure, which first ensures the sealing effect and also greatly improves the efficiency of disassembly and installation. The present invention forms a complete technical system for gas injection and flow increase and extraction by drilling holes in coal seams, and adopts operating modes such as cyclic reciprocating extraction, group injection and group extraction, and injection before extraction, which effectively solves the problem of low efficiency of existing coal seam gas extraction. BRIEF DESCRIPTION OF THE DRAWINGS
[0049] Figure 1 It is a structural schematic diagram of the gas extraction system of the present invention;
[0050] Figure 2 It is a schematic diagram of the process of the extraction method of the present invention;
[0051] Figure 3 These are the effects diagrams of continuous gas injection, intermittent gas injection and natural gas injection;
[0052] Figure 4 This is the principle diagram of the gas injection displacement and pumping technology in the gas injection stage I;
[0053] Figure 5 This is the principle diagram of the gas injection displacement and pumping technology in the gas injection phase II;
[0054] Figure 6 Schematic diagram of the hole-in-the-hole phenomenon. DETAILED DESCRIPTION
[0055] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0056] like Figure 1As shown, the gas extraction system for gas injection displacement and flow increase in layer drilling of the present invention comprises a set of gas injection device 3 and two sets of extraction devices located on the left and right sides of the gas injection device 3, each set of extraction devices comprises a filtering device 4 and a gas metering device 5, the gas injection port of the gas injection device 3 is connected to the gas injection hole sealing pipe 33 extending into the coal seam 55, the air inlet of the gas injection device 3 is connected to the gas injection main pipe 1 underground in the coal mine, the air inlet of the filtering device 4 is connected to the extraction hole sealing pipe 27 extending into the coal seam 55, the air outlet of the filtering device 4 is connected to the air inlet of the gas metering device 5, and the air outlets of the two gas metering devices 5 are connected to the extraction main pipe 2 in the underground tunnel of the coal mine.
[0057] The filtering device 4 includes a filter 15, a sealed water tank 17, a water tank air inlet pipe 19 and a water tank air outlet pipe 20. The inlet of the filter 15 is connected to the outlet of the extraction hole sealing pipe 27, the inlet of the water tank air inlet pipe 19 is connected to the outlet of the filter 15, an air release valve 16 is provided on the filter 15, and a drain valve 18 is provided at the bottom of the sealed water tank 17.
[0058] The gas metering device 5 includes a multi-parameter gas meter 23, a first pipeline 40, a second pipeline 28 and a gas meter 26. The inlet end of the multi-parameter gas meter 23 is connected to the water tank outlet pipe 20, the outlet end of the multi-parameter gas meter 23 is connected to one end of the first pipeline 40, the air inlet of the gas meter 26 is connected to the other end of the first pipeline 40, the air outlet of the gas meter 26 is connected to one end of the second pipeline 28, and the other end of the second pipeline 28 is connected to the extraction main pipe 2; the filtering device 4 and the gas metering device 5 are connected between the extraction hole sealing pipe 27 and the extraction main pipe 2, and then under the negative pressure of the extraction main pipe 2, the gas in the coal seam is extracted and filtered, water-gas separated and metered in turn to form an extraction circuit.
[0059] The gas injection device 3 includes a gas injection guide pipe 12, a booster pump 8, a quick connector 6 and a third pipeline 25. The upper end of the quick connector 6 is connected to the gas injection hole sealing pipe 33, and the lower end of the quick connector 6 is connected to one end of the third pipeline 25; the air inlet end of the booster pump 8 is connected to one end of the gas injection guide pipe 12, the other end of the gas injection guide pipe 12 is connected to the gas injection main pipe 1, and the air outlet end of the booster pump 8 is connected to the other end of the third pipeline 25; the gas injection device 3 is connected between the gas injection main pipe 1 and the gas injection hole sealing pipe 33, and the booster pump 8 further pressurizes the positive pressure airflow in the gas injection main pipe 1 and injects it into the coal seam through the quick connector and the gas injection hole sealing pipe 33 to form a sealed loop.
[0060] like Figure 2 As shown, a gas extraction method for a gas extraction system for gas injection displacement and flow enhancement in a layer-by-layer drilling hole comprises the following steps:
[0061] A. Carry out fine division of gas geological grids for pre-extraction coal seams, determine the gas occurrence of coal seams, and determine the thickness, layer fluctuation and gas content of coal seams according to the on-site exploration conditions. In the pre-extraction area, drill holes shall be constructed in accordance with the requirements of the national standard GB / T-42638-2023 to determine the number, spacing, hole depth and sealing depth of the in-layer extraction holes. The hole diameter and length shall be consistent with the daily extraction holes in the mine;
[0062] B. After the drilling construction is completed, install a gas injection hole sealing pipe 33 in a gas injection borehole, install a drainage hole sealing pipe 27 in two drainage boreholes adjacent to the gas injection borehole, and measure the distances d1 and d2 between the gas injection borehole and the two adjacent drainage boreholes; install and connect the gas drainage system, turn on the filter device 4 and the gas metering device 5, use the drainage main pipe 2 in the underground tunnel of the coal mine to pre-drain the gas from the drainage borehole under negative pressure before mining, and record the drainage negative pressure p. The pre-drainage time is determined according to the gas geological characteristics of the mining area;
[0063] d1 and d2 are the minimum distances between the gas injection borehole and the two adjacent extraction boreholes. This distance is the actual effective distance between fracturing and gas injection displacement. If the distance between the borehole centers is recorded, it will lead to gross errors.
[0064] C. Use the gas metering device 5 to monitor parameters in real time. When it is monitored that the mixed flow rate of gas extraction in the extraction borehole does not fluctuate greatly within five days and the change range is less than 10%, the pre-extraction work of the layer drilling is completed;
[0065] D. Start the gas injection device 3 and the booster pump 8 to conduct a gas injection test for 6 hours under the condition of gas injection pressure p0. In the initial stage of gas injection, as the compressed air from the gas injection source continuously displaces the coal seam gas, the gas concentration and pure amount of gas in the extraction borehole will gradually decrease; at the same time, the gas extraction system is used to monitor the pressure in the gas injection borehole and the continuous gas injection time, as well as the single-hole negative pressure, mixed flow rate and gas concentration of the extraction borehole in real time;
[0066] E. Evaluate the gas flooding effect of the gas injection boreholes in the bedding layer within 6 hours of gas injection test;
[0067] F. After the 6-hour gas injection test of the gas injection drilling in the layer, the gas injection operation shall be carried out using the corresponding gas injection method according to the evaluation results;
[0068] G. Determine whether there is a hole in the hole and take corresponding measures;
[0069] H. After the fracturing and permeability enhancement of the coal seam and the gas injection displacement, the gas injection device 3 of the gas injection hole in the layer is replaced with a filtering device 4 and a gas metering device 5, which are connected to the extraction main pipe 2 in the underground tunnel of the coal mine, and gas extraction is carried out on the gas injection holes in the layer and the extraction holes at the same time, that is, the injection-first-then-extraction mode is implemented.
[0070] The optimal selection of the gas injection pressure p0 in step D is as follows:
[0071] Open the valve on the gas injection device 3 pipeline, adjust the gas injection pressure of the booster pump 8 to p0, inject compressed air into the gas injection borehole in the layer, and start two sets of extraction devices at the same time to extract from the extraction borehole in the layer, that is, implement the long injection and short extraction mode;
[0072] Open the valve on the gas injection device 3 pipeline, adjust the gas injection pressure of the booster pump 8 to p0, inject compressed air into the gas injection borehole in the layer, and start two sets of extraction devices at the same time to extract from the extraction borehole in the layer, that is, implement the long injection and short extraction mode;
[0073] Gas diffusion motion complies with Fick's law, so in the pore system, CH4 and air satisfy the diffusion motion equation:
[0074]
[0075] Where: c1, c2 represent the diffusion mass concentration of CH4 and air in the adsorption state of coal seam, Q1, Q2 are the mass sources of CH4 and air, D1, D2 are the diffusion coefficients of CH4 and air, respectively.
[0076] The amount of multi-component gas adsorbed by coal can be calculated by the adsorption equilibrium theory and expressed by the generalized Langmuir equation: the mass relationship between CH4 and air in the adsorbed state on the coal surface and CH4 and air in the free state in the fracture system is:
[0077]
[0078] Where τ is the adsorption time constant; ρ c is the density of coal; ρ1 and ρ2 are the gas component densities of CH4 and air under standard conditions; a1 and a2 are the limit adsorption capacities of CH4 and air when adsorbed alone; b1 and b2 are the adsorption equilibrium constants of CH4 and air respectively; p1 and p2 are the equilibrium partial pressures of CH4 and air respectively;
[0079] Substituting the multivariate gas adsorption equilibrium equation, seepage velocity equation, gas state and mass exchange equation into the gas seepage equation in the fracture, the coupled equation group can be obtained as follows:
[0080]
[0081] In the formula, φ is the porosity; A1 and A2 are the molar masses of the gas components CH4 and air respectively; B1 and B2 are the gas constants of the gas components CH4 and air respectively; T is the gas temperature; k is the coal permeability; μ1 and μ2 are the dynamic viscosity coefficients of the gas components CH4 and air respectively; p is the total pressure;
[0082] From the above three equations, it can be seen that the gas extraction effect of gas injection displacement is mainly affected by the injected gas flow rate, injection pressure and injection temperature. The initial injection volume is large, and the higher the injection pressure, the greater the flow rate of injected air. Since a large amount of gas is discharged from the free space of the coal seam before gas injection, the pressure of the free space is low. After air injection, these free spaces are quickly filled, and the pressure in the coal seam rises rapidly. Therefore, in the early stage of air injection, the extracted gas mixed flow rate is large;
[0083] In order to determine the influence of gas injection pressure on the gas drive flow enhancement and extraction effect, a numerical model under different gas injection pressure conditions was established for simulation analysis. The extraction negative pressure was set to 20 KPa, the spacing between gas injection and extraction holes was 1.5 m, and the gas injection pressures were set to 0.3 MPa, 0.5 MPa and 1 MPa respectively. The simulated gas injection pressures were 0.3 MPa, 0.5 MPa, and 1 MPa. The greater the gas injection pressure, the more significant the gas injection displacement flow enhancement effect. However, the gas drive effect is improved less when it is greater than 0.5 MPa, and the coal seam can bear a limited maximum gas injection pressure, which may easily cause gas overflow accidents. Therefore, the optimal gas injection pressure p0 is 0.5 MPa.
[0084] The specific process of step E is:
[0085] The recorded gas extraction mixed flow rates of the two extraction boreholes are both higher than the set first threshold value (indicating that the coal seam mixed flow rate does not change much), and the coal seam gas concentration is lower than the set second threshold value (indicating that the coal seam gas concentration does not change much). It is determined that under the conditions of gas injection pressure p0, hole spacing d1, hole spacing d2, and single hole extraction negative pressure P, the scheme has significant effects on fracturing permeability enhancement and gas injection displacement of coal seams;
[0086] The first threshold is 400% of the initial value of the gas mixed flow rate; the mixed flow rate refers to the flow rate of the CH4 and CO mixed gas in the extraction hole before gas injection; the second threshold is 30% of the initial value of gas concentration extraction; the initial value of gas concentration extraction refers to the data recorded when the gas concentration of all the in-layer extraction boreholes in this group remains stable after three consecutive monitorings at the initial stage of single negative pressure extraction;
[0087] like Figure 3 As shown, in this example, there are pore systems 44 and fracture systems 43 in the coal seam between the gas injection hole 41 and the extraction hole 42; in the gas injection I stage, compressed air 46 is injected into the coal body from the gas injection hole 41, which improves the porosity and permeability of the coal body to a certain extent, thereby facilitating the migration of gas 45 in the coal;
[0088] like Figure 4As shown, in this example, there are pore systems 44 and fracture systems 43 in the coal seam between the gas injection hole 41 and the extraction hole 42; in the gas injection I stage, compressed air 46 is injected into the coal body from the gas injection hole 41, which improves the porosity and permeability of the coal body to a certain extent, thereby facilitating the migration of gas 45 in the coal;
[0089] like Figure 4 As shown, when entering the gas injection II stage, the gas concentration drops sharply after the free gas in the coal body fracture channel is diluted by the injected gas, and the adsorbed gas in the pore system 44 begins to diffuse outward. In addition, the expansion and compression of the compressed air 46 leads to the further development of the fracture system 43, which effectively promotes the mutual interconnection of pores and the development and expansion of fractures. The compressed air 46 controls the effective stress of the fracture system 43 to prevent the fractures from closing again. The free gas 45 is continuously driven out of the coal body under the action of the pressure gradient, and the adsorbed gas 45 is continuously desorbed due to the reduction of the gas partial pressure and enters the extraction pipeline.
[0090] like Figure 5 As shown, when entering the gas injection II stage, the gas concentration drops sharply after the free gas in the coal body fracture channel is diluted by the injected gas, and the adsorbed gas in the pore system 44 begins to diffuse outward. In addition, the expansion and compression of the compressed air 46 leads to the further development of the fracture system 43, which effectively promotes the mutual interconnection of pores and the development and expansion of fractures. The compressed air 46 controls the effective stress of the fracture system 43 to prevent the fractures from closing again. The free gas 45 is continuously driven out of the coal body under the action of the pressure gradient, and the adsorbed gas 45 is continuously desorbed due to the reduction of the gas partial pressure and enters the extraction pipeline.
[0091] The specific process of step F is:
[0092] After a 6-hour gas injection test of the gas injection boreholes in the layer, if the recorded gas extraction mixed flow rate of the two extraction boreholes is lower than the set first threshold, it indicates that the coal seam mixed flow rate has not changed much, or the coal seam gas concentration is higher than the set second threshold, indicating that the coal seam gas concentration has not changed much, it is determined that under the conditions of gas injection pressure p0, hole spacing d1, hole spacing d2, and single hole extraction negative pressure P, the scheme has no obvious effect on the fracturing permeability enhancement and gas injection displacement of the coal seam; at this time, the gas injection pressure p0 should be increased by 50%, and the second round of gas extraction should be completed according to the method in step C; if the second round of injection and extraction still fails to achieve the expected effect, the gas injection pressure p0 will be increased by 45% again, and the gas injection flow rate will be increased by 65%, and the third round of injection and extraction will be continued, that is, the cyclic injection and extraction mode will be adopted;
[0093] The cyclic injection and extraction mode is to determine the extraction efficiency of continuous gas injection and intermittent gas injection. The experiment arranges continuous gas injection and intermittent gas injection. After the drilling construction is completed, the net is hung for extraction, and the gas quantity of the extraction hole is tested regularly. The drilling lengths of different drilling spacings are basically the same, and the analysis results ignore the influence of drilling length. The changes in the gas extraction quantity are as follows: Figure 3 As shown;
[0094] Although the total extraction volume increased by intermittent gas injection competitive replacement is less than the extraction volume increased by long-term continuous gas injection energy-enhanced driving at the same gas injection pressure, the intermittent gas injection competitive adsorption replacement time is sufficient, the replacement volume is large, and the replacement efficiency is higher. Therefore, intermittent gas injection is preferred.
[0095] The specific process of step G is:
[0096] If the gas injection test of the gas injection drilling holes in the layer begins for 6 hours, and the recorded gas extraction mixed flow of the two extraction boreholes quickly exceeds the set first threshold, it is preliminarily judged that the borehole inclination angle is too large and the borehole spacing is much smaller than the measured borehole spacing, and a hole-to-hole phenomenon may occur; for further judgment, the left extraction hole is maintained to continue negative pressure extraction, the valve on the right extraction device is closed, the quick connector 6 of the gas injection device 3 is removed, and the palm is placed on the mouth of the gas injection hole sealing tube 33. If the suction generated by the negative pressure in the tube is felt, it is determined that the left extraction hole and the gas injection hole are in hole-to-hole; if the suction generated by the negative pressure in the tube is not felt, it is determined that the left extraction hole and the gas injection hole are not in hole-to-hole;
[0097] Repeat the operation content of step G to determine whether there is a cross-hole between the left extraction hole and the right extraction hole and between the gas injection hole and the right extraction hole; Figure 6As shown, the specific process is as follows: set the boreholes where the string hole phenomenon occurs as a group; use the group of boreholes as a gas injection hole group, drill a borehole on both sides of the gas injection hole group as a drainage hole, install the gas injection device 3 and the drainage device, and repeat the operation content of step G to determine whether the boreholes on the left and right sides have a string hole phenomenon with the gas injection hole group; if the string hole phenomenon occurs, include the boreholes of the string hole into the gas injection hole group, continue to drill additional holes on the side of the borehole of the string hole as drainage holes, and continue to repeat the operation content of step G until the string hole phenomenon does not occur; if the string hole phenomenon is not found, connect the group of gas injection holes to the gas injection device, and connect the drainage holes on the left and right sides to the filtering and drainage devices for negative pressure drainage. Open the valve of the gas injection device and conduct a 6-hour gas injection test. Stop for 6 hours after the gas injection is completed. If the recorded mixed flow rate of the two extraction boreholes is higher than the set third threshold, it indicates that the coal seam mixed flow rate has not changed much, and the coal seam gas concentration is lower than the set fourth threshold, indicating that the coal seam gas concentration has not changed much. It is judged that the compressed gas has completed fracturing development in the coal seam. If the set relevant indicators are not met, increase the gas injection flow rate by 80% at this time, continue the gas injection test for 6 hours, and stop for 6 hours after the gas injection is completed. If the gas extraction flow rate is higher than that before gas injection, the gas extraction flow rate is higher than that before gas injection. Increase by 45%, judging that the compressed gas has completed the fracturing development in the coal seam under the action of atmospheric flow; if the set relevant indicators are not met, increase the gas injection pressure by 50% and use the heating device to increase the gas injection temperature by 60%, conduct a 6-hour gas injection test, and stop for 6 hours after the gas injection is completed; if the gas extraction flow rate is increased by 45% compared with that before gas injection, it is judged that the compressed gas has completed the fracturing development in the coal seam under the combined action of high pressure, atmospheric flow and hot gas; after the fracturing development is completed, connect the gas injection hole group to the extraction main pipe for extraction to further increase gas extraction;
[0098] The third threshold value is 150% of the initial value of the gas mixed flow rate; the mixed flow rate refers to the flow rate of the CH4 and CO mixed gas in the extraction hole before gas injection; the fourth threshold value is 60% of the initial value of the gas concentration extraction; the initial value of the gas concentration extraction refers to the data recorded when the gas concentration of all the in-layer extraction boreholes in this group remains stable after three consecutive monitorings at the initial stage of single negative pressure extraction.
[0099] The above two embodiments do not impose any formal restrictions on the shape, material, structure, etc. of the present invention. Any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention are within the protection scope of the technical solution of the present invention.
Claims
1. A gas extraction system for gas injection and flow enhancement in layer drilling, characterized by: The invention comprises a set of gas injection devices (3) and two sets of extraction devices located on the left and right sides of the gas injection device (3), each set of extraction devices comprises a filtering device (4) and a gas metering device (5), the gas injection port of the gas injection device (3) is connected to a gas injection hole sealing pipe (33) extending into a coal seam (55), the gas inlet of the gas injection device (3) is connected to a gas injection main pipe (1) underground in a coal mine, the gas inlet of the filtering device (4) is connected to a extraction hole sealing pipe (27) extending into the coal seam (55), the gas outlet of the filtering device (4) is connected to the gas inlet of the gas metering device (5), and the gas outlets of the two gas metering devices (5) are connected to an extraction main pipe (2) in an underground tunnel of the coal mine.
2. The gas extraction system for gas injection displacement and flow enhancement in layer drilling according to claim 1, characterized in that: The filtering device (4) comprises a filter (15), a sealed water tank (17), a water tank air inlet pipe (19) and a water tank air outlet pipe (20); the inlet of the filter (15) is connected to the outlet of the extraction hole sealing pipe (27); the inlet of the water tank air inlet pipe (19) is connected to the outlet of the filter (15); an air release valve (16) is provided on the filter (15); and a water release valve (18) is provided at the bottom of the sealed water tank (17).
3. The gas extraction system for gas injection displacement and flow enhancement in layer drilling according to claim 2, characterized in that: The gas metering device (5) comprises a multi-parameter gas meter (23), a first pipeline (40), a second pipeline (28) and a gas meter (26); the inlet end of the multi-parameter gas meter (23) is connected to the water tank gas outlet pipe (20), the outlet end of the multi-parameter gas meter (23) is connected to one end of the first pipeline (40), the gas inlet of the gas meter (26) is connected to the other end of the first pipeline (40), the gas outlet of the gas meter (26) is connected to one end of the second pipeline (28), and the other end of the second pipeline (28) is connected to the extraction main pipe (2); the filtering device (4) and the gas metering device (5) are connected between the extraction hole sealing pipe (27) and the extraction main pipe (2), and then under the negative pressure of the extraction main pipe (2), the gas in the coal seam is extracted and filtered, water-gas separated and metered in sequence to form an extraction circuit.
4. The gas extraction system for gas injection displacement and flow enhancement in layer drilling according to claim 3 is characterized in that: The gas injection device (3) comprises a gas injection flow guide pipe (12), a booster pump (8), a quick connector (6) and a third pipeline (25); the upper end of the quick connector (6) is connected to the gas injection hole sealing pipe (33), and the lower end of the quick connector (6) is connected to one end of the third pipeline (25); the gas inlet end of the booster pump (8) is connected to one end of the gas injection flow guide pipe (12), the other end of the gas injection flow guide pipe (12) is connected to the gas injection main pipe (1), and the gas outlet end of the booster pump (8) is connected to the other end of the third pipeline (25); the gas injection device (3) is connected between the gas injection main pipe (1) and the gas injection hole sealing pipe (33), and the booster pump (8) further pressurizes the positive pressure gas flow in the gas injection main pipe (1) and injects it into the coal seam through the quick connector and the gas injection hole sealing pipe (33) to form a sealed loop.
5. The gas extraction method of the gas extraction system for gas injection displacement and flow enhancement in layer drilling according to claim 4, characterized in that: The following steps are involved: A. Carry out fine division of gas geological grids for pre-extraction coal seams, determine the gas occurrence of coal seams, and determine the thickness, layer fluctuation and gas content of coal seams according to the on-site exploration conditions. In the pre-extraction area, drill holes shall be constructed in accordance with the requirements of the national standard GB / T-42638-2023 to determine the number, spacing, hole depth and sealing depth of the in-layer extraction holes. The hole diameter and length shall be consistent with the daily extraction holes in the mine; B. After the drilling construction is completed, a gas injection hole sealing pipe (33) is installed in a gas injection hole, and a drainage hole sealing pipe (27) is installed in two drainage holes adjacent to the gas injection hole, and the distances d1 and d2 between the gas injection hole and the two adjacent drainage holes are measured respectively; the gas drainage system is installed and connected, the filtering device (4) and the gas metering device (5) are turned on, and the drainage main pipe (2) in the underground tunnel of the coal mine is used to pre-drain the gas from the drainage hole with negative pressure before extraction, and the drainage negative pressure p is recorded. The pre-drainage time is determined according to the gas geological characteristics of the mining area; d1 and d2 are the minimum distances between the gas injection borehole and the two adjacent extraction boreholes. This distance is the actual effective distance between fracturing and gas injection displacement. If the distance between the borehole centers is recorded, it will lead to gross errors. C. Using the gas metering device (5) to monitor parameters in real time, when it is monitored that the mixed flow rate of gas extraction from the extraction borehole does not fluctuate significantly within five days (the fluctuation range is less than 10%), the pre-extraction work of the in-layer drilling hole is completed; D. Start the gas injection device (3), and the booster pump (8) conducts a gas injection test for 6 hours under the condition of gas injection pressure p0. In the initial stage of gas injection, as the compressed air of the gas injection source continuously displaces the coal seam gas, the gas concentration and the pure amount of gas in the extraction borehole will gradually decrease; at the same time, the gas extraction system is used to monitor the pressure in the gas injection borehole and the continuous gas injection time, as well as the single hole negative pressure, mixed flow rate and gas concentration of the extraction borehole in real time; E. Evaluate the gas flooding effect of the gas injection boreholes in the bedding layer within 6 hours of gas injection test; F. After the 6-hour gas injection test of the gas injection drilling in the layer, the gas injection operation shall be carried out using the corresponding gas injection method according to the evaluation results; G. Determine whether there is a hole in the hole and take corresponding measures; H. After the fracturing and permeability enhancement of the coal seam and the gas injection displacement, the gas injection device (3) of the gas injection hole in the layer is replaced with a filtering device (4) and a gas metering device (5), which are connected to the extraction main pipe (2) in the underground tunnel of the coal mine, and gas extraction is carried out on the gas injection hole in the layer and the extraction hole at the same time, that is, the injection-first-then-extraction mode is implemented.
6. The gas extraction method for gas extraction system for gas injection displacement and flow enhancement in layer drilling according to claim 5, characterized in that: The optimal selection of the gas injection pressure p0 in step D is as follows: Open the valve on the gas injection device (3) pipeline, adjust the gas injection pressure of the booster pump (8) to p0, inject compressed air into the in-layer gas injection borehole, and simultaneously start two sets of extraction devices to extract air from the in-layer extraction borehole, that is, implement a long injection and short extraction mode; Gas diffusion motion complies with Fick's law, so in the pore system, CH4 and air satisfy the diffusion motion equation: Where: c1, c2 represent the diffusion mass concentration of CH4 and air in the adsorption state of coal seam, Q1, Q2 are the mass sources of CH4 and air, D1, D2 are the diffusion coefficients of CH4 and air, respectively. The amount of multi-component gas adsorbed by coal can be calculated by the adsorption equilibrium theory and expressed by the generalized Langmuir equation: the mass relationship between CH4 and air in the adsorbed state on the coal surface and CH4 and air in the free state in the fracture system is: Where τ is the adsorption time constant; ρ c is the density of coal; ρ1 and ρ2 are the gas component densities of CH4 and air under standard conditions; a1 and a2 are the limit adsorption capacities of CH4 and air when adsorbed alone; b1 and b2 are the adsorption equilibrium constants of CH4 and air respectively; p1 and p2 are the equilibrium partial pressures of CH4 and air respectively; Substituting the multivariate gas adsorption equilibrium equation, seepage velocity equation, gas state and mass exchange equation into the gas seepage equation in the fracture, the coupled equation group can be obtained as follows: In the formula, φ is the porosity; A1 and A2 are the molar masses of the gas components CH4 and air respectively; B1 and B2 are the gas constants of the gas components CH4 and air respectively; T is the gas temperature; k is the coal permeability; μ1 and μ2 are the dynamic viscosity coefficients of the gas components CH4 and air respectively; p is the total pressure; From the above three equations, it can be seen that the gas extraction effect of gas injection displacement is mainly affected by the injected gas flow rate, injection pressure and injection temperature. The initial injection volume is large, and the higher the injection pressure, the greater the flow rate of injected air. Since a large amount of gas is discharged from the free space of the coal seam before gas injection, the pressure of the free space is low. After air injection, these free spaces are quickly filled, and the pressure in the coal seam rises rapidly. Therefore, in the early stage of air injection, the extracted gas mixed flow rate is large; In order to determine the influence of gas injection pressure on the gas drive flow enhancement and extraction effect, a numerical model under different gas injection pressure conditions was established for simulation analysis. The extraction negative pressure was set to 20 KPa, the spacing between gas injection and extraction holes was 1.5 m, and the gas injection pressures were set to 0.3 MPa, 0.5 MPa and 1 MPa respectively. The simulated gas injection pressures were 0.3 MPa, 0.5 MPa, and 1 MPa. The greater the gas injection pressure, the more significant the gas injection displacement flow enhancement effect. However, the gas drive effect is improved less when it is greater than 0.5 MPa, and the coal seam can bear a limited maximum gas injection pressure, which may easily cause gas overflow accidents. Therefore, the optimal gas injection pressure p0 is 0.5 MPa.
7. The gas extraction method for gas extraction system for gas injection displacement and flow enhancement in layer drilling according to claim 6, characterized in that: The specific process of step E is: The recorded gas extraction mixed flow rates of the two extraction boreholes are both higher than the set first threshold value (indicating that the coal seam mixed flow rate does not change much), and the coal seam gas concentration is lower than the set second threshold value (indicating that the coal seam gas concentration does not change much). It is determined that under the conditions of gas injection pressure p0, hole spacing d1, hole spacing d2, and single hole extraction negative pressure P, the scheme has significant effects on fracturing permeability enhancement and gas injection displacement of coal seams; The first threshold is 400% of the initial value of the gas mixed flow rate; the mixed flow rate refers to the flow rate of the CH4 and CO mixed gas in the extraction hole before gas injection; the second threshold is 30% of the initial value of gas concentration extraction; the initial value of gas concentration extraction refers to the data recorded when the gas concentration of all the in-layer extraction boreholes in this group remains stable after three consecutive monitorings at the initial stage of single negative pressure extraction; A pore system (44) and a fracture system (43) exist in the coal seam between the gas injection hole (41) and the extraction hole (42); in the gas injection I stage, compressed air (46) is injected into the coal body through the gas injection hole (41), which increases the porosity and permeability of the coal body to a certain extent, thereby facilitating the migration of gas (45) in the coal; Entering the gas injection II stage, the free gas in the coal body fracture channel is diluted by the injected gas, and the gas concentration drops significantly. The adsorbed gas in the pore system (44) begins to diffuse outward, and the expansion and compression of the compressed air (46) leads to the further development of the fracture system (43), which effectively promotes the interconnection of pores and the development and expansion of fractures. The compressed air (46) controls the effective stress of the fracture system (43) to prevent the fractures from closing again. The free gas (45) is continuously driven out of the coal body under the action of the pressure gradient, and the adsorbed gas (45) is continuously desorbed due to the reduction of gas partial pressure and enters the extraction pipeline.
8. The gas extraction method for gas extraction system for gas injection displacement and flow enhancement in layer drilling according to claim 7, characterized in that: The specific process of step F is: After a 6-hour gas injection test of the gas injection boreholes in the layer, if the recorded gas extraction mixed flow rate of the two extraction boreholes is lower than the set first threshold, it indicates that the coal seam mixed flow rate has not changed much, or the coal seam gas concentration is higher than the set second threshold, indicating that the coal seam gas concentration has not changed much, it is determined that under the conditions of gas injection pressure p0, hole spacing d1, hole spacing d2, and single hole extraction negative pressure P, the scheme has no obvious effect on the fracturing permeability enhancement and gas injection displacement of the coal seam; at this time, the gas injection pressure p0 should be increased by 50%, and the second round of gas extraction should be completed according to the method in step C; if the second round of injection and extraction still fails to achieve the expected effect, the gas injection pressure p0 will be increased by 45% again, and the gas injection flow rate will be increased by 65%, and the third round of injection and extraction will be continued, that is, the cyclic injection and extraction mode will be adopted; The cyclic injection and extraction mode is to determine the extraction efficiency of continuous gas injection and intermittent gas injection. The experiment arranges continuous gas injection and intermittent gas injection. After the drilling construction is completed, the net is hung for extraction at the same time, and the pure gas quantity of the extraction hole is tested regularly. The drilling lengths of different drilling spacings are basically the same, and the analysis results ignore the influence of the drilling length. Although the total extraction volume increased by intermittent gas injection competitive replacement is less than the extraction volume increased by long-term continuous gas injection energy-enhanced driving at the same gas injection pressure, the intermittent gas injection competitive adsorption replacement time is sufficient, the replacement volume is large, and the replacement efficiency is higher. Therefore, intermittent gas injection is preferred.
9. The gas extraction method for gas extraction system for gas injection displacement and flow enhancement in layer drilling according to claim 8, characterized in that: The specific process of step G is: If the recorded gas extraction mixed flow rate of the two extraction boreholes rapidly exceeds the set first threshold value when the gas injection test of the in-layer gas injection drilling is started for 6 hours, it is preliminarily judged that the borehole inclination angle is too large and the borehole spacing is much smaller than the measured borehole spacing, and a hole-to-hole phenomenon may occur; for further judgment, the left extraction hole is maintained to continue negative pressure extraction, the valve on the right extraction device is closed, the quick connector (6) of the gas injection device (3) is removed, and the palm is placed on the mouth of the gas injection hole sealing tube (33). If the suction force generated by the negative pressure in the tube is felt, it is determined that the left extraction hole and the gas injection hole are in hole-to-hole; if the suction force generated by the negative pressure in the tube is not felt, it is determined that the left extraction hole and the gas injection hole are not in hole-to-hole.
10. The gas extraction method of the gas extraction system for gas injection displacement and flow enhancement in layer drilling according to claim 9, characterized in that: Repeat the operation content of step G to determine whether there is a hole-to-hole phenomenon between the left extraction hole and the right extraction hole and between the gas injection hole and the right extraction hole. The specific process is as follows: set the boreholes where the hole-to-hole phenomenon occurs as a group; use the group of boreholes as the gas injection hole group, drill a borehole on both sides of the gas injection hole group as a extraction hole, install a gas injection device (3) and an extraction device, and repeat the operation content of step G to determine whether the boreholes on the left and right sides have a hole-to-hole phenomenon with the gas injection hole group; if a hole-to-hole phenomenon occurs, include the borehole of the hole-to-hole phenomenon into the gas injection hole group, continue to drill additional holes on the side of the borehole of the hole-to-hole phenomenon as extraction holes, and continue to repeat the operation content of step G until no hole-to-hole phenomenon occurs; if no hole-to-hole phenomenon is found, connect the group of gas injection holes to the gas injection device, and connect the extraction holes on the left and right sides to the filtering and extraction devices for negative pressure extraction. Open the valve of the gas injection device and conduct a 6-hour gas injection test. Stop for 6 hours after the gas injection is completed. If the recorded mixed flow rate of the two extraction boreholes is higher than the set third threshold, it indicates that the coal seam mixed flow rate has not changed much, and the coal seam gas concentration is lower than the set fourth threshold, indicating that the coal seam gas concentration has not changed much. It is judged that the compressed gas has completed fracturing development in the coal seam. If the set relevant indicators are not met, increase the gas injection flow rate by 80% at this time, continue the gas injection test for 6 hours, and stop for 6 hours after the gas injection is completed. If the gas extraction flow rate is higher than that before gas injection, the gas extraction flow rate is higher than that before gas injection. Increase by 45%, judging that the compressed gas has completed the fracturing development in the coal seam under the action of atmospheric flow; if the set relevant indicators are not met, increase the gas injection pressure by 50% and use the heating device to increase the gas injection temperature by 60%, conduct a 6-hour gas injection test, and stop for 6 hours after the gas injection is completed; if the gas extraction flow rate is increased by 45% compared with that before gas injection, it is judged that the compressed gas has completed the fracturing development in the coal seam under the combined action of high pressure, atmospheric flow and hot gas; after the fracturing development is completed, connect the gas injection hole group to the extraction main pipe for extraction to further increase gas extraction; The third threshold value is 150% of the initial value of the gas mixed flow rate; the mixed flow rate refers to the flow rate of the CH4 and CO mixed gas in the extraction hole before gas injection; the fourth threshold value is 60% of the initial value of the gas concentration extraction; the initial value of the gas concentration extraction refers to the data recorded when the gas concentration of all the in-layer extraction boreholes in this group remains stable after three consecutive monitorings at the initial stage of single negative pressure extraction.
Citation Information
Cited By
Hole sealing system and method for high-concentration gas extraction caused by mixed gas injection
CN120331731A
Coal seam gas extraction method based on synergistic interaction of horizontal hydraulic slotting and gas injection displacement
CN122485529A