Multifunctional integrated rack

By designing a multi-function integrated bench, the automated construction in the tunnel is achieved using arched guide rails and robotic arms, the problems of cumbersome work and low efficiency in tunnel construction are solved, and construction efficiency and safety are improved.

CN119084035APending Publication Date: 2024-12-06WUHAN ENGINEERING CO LTD OF CHINA RAILWAY SEVENTH GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411402880.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-09
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

In tunnel construction, the prior art has a cumbersome working environment and various functions of the tunnels respectively mounted on their respective engineering vehicles, resulting in cumbersome work processes, low efficiency and high risk factors.

Method used

Design a multi-functional integrated mount, including a walkable abutment, drilling assembly, spraying assembly and hydraulic clamping assembly, to automatically move and collaborate the assembly through arched rails and robotic arms, simplify construction processes and improve Work efficiency.

Benefits of technology

Automatic construction in the tunnel is realized, working efficiency is improved, process intervals are shortened, support effect is enhanced, geological disaster risk is reduced, and construction safety is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119084035A_ABST
    Figure CN119084035A_ABST
Patent Text Reader

Abstract

The invention discloses a multifunctional integrated rack, and belongs to the technical field of tunnel construction. The device comprises a base table, a drilling assembly, a guniting assembly and a hydraulic clamping assembly, the base table comprises a frame body capable of walking and an arched guide rail, and the arched guide rail is arranged opposite to a tunnel and fixedly connected with the frame body; the drilling assembly comprises a drilling unit used for drilling the tunnel wall, and the drilling unit is loaded on the frame body; the guniting assembly comprises a guniting unit used for guniting the tunnel wall, the guniting unit is loaded on the frame body, the hydraulic clamping assembly comprises a mechanical arm and a feeding unit, the feeding unit is installed on the arch-shaped guide rail and can move in a feeding mode along the arch-shaped guide rail, and the mechanical arm is installed on the feeding unit and can move along the arch-shaped guide rail. And the mechanical arm can clamp the drilling unit, the guniting unit and the steel arch frame and move relative to the drilling unit, the guniting unit and the steel arch frame. According to the device, concrete primary spraying and drilling can be automatically conducted on the tunnel wall, mounting of the steel arch is assisted, and the working efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel construction, and in particular to a multifunctional integrated stand. Background Art

[0002] In tunnels constructed by drilling and blasting and stepping methods, initial support is required to improve the stability of the surrounding rock and prevent collapse. Initial support generally uses steel arches, combined with steel mesh, anchors and shotcrete for reinforced support. At present, there are independent steel arch installation vehicles, concrete spraying vehicles and anchor drilling vehicles. The construction procedure is that the cantilever tunnel boring machine or explosives are used to break the rock, and then retreat to the rear, the concrete spraying vehicle moves to the front to spray concrete for preliminary support, and then the concrete spraying vehicle retreats to the rear, the anchor drilling vehicle moves to the front to do anchor support, and then the anchor drilling vehicle retreats to the rear, and the steel arch installation vehicle moves to the front to install the steel arch.

[0003] Due to the narrow working environment of the tunnel and the fact that each function is carried on its own engineering vehicle, each operation procedure can only be carried out once. When performing each step of the operation procedure, it is necessary to withdraw the tool vehicle of the previous step from the tunnel and push the tool vehicle of the next step into the tunnel. The work process is cumbersome, inefficient, and has a high risk factor. Summary of the invention

[0004] In view of this, it is necessary to provide a multifunctional integrated platform to solve the problems of cumbersome working process and low efficiency in existing tunnel construction.

[0005] The present invention provides a multifunctional integrated stand, comprising:

[0006] A base, the base comprising a walkable frame and an arched guide rail, the arched guide rail is arranged relative to the tunnel and fixedly connected to the frame;

[0007] A drilling assembly, the drilling assembly comprising a drilling unit for drilling a hole in a tunnel wall, the drilling unit being loaded on the frame;

[0008] A shotcrete assembly, the shotcrete assembly comprising a shotcrete unit for spraying the tunnel wall, the shotcrete unit being loaded on the frame;

[0009] A hydraulic clamping assembly, wherein the hydraulic clamping assembly comprises a mechanical arm and a feeding unit, wherein the feeding unit is mounted on the arched guide rail, and the feeding unit can feed and move along the arched guide rail, and the mechanical arm is mounted on the feeding unit, and the mechanical arm can respectively clamp the drilling unit, the spraying unit and the steel arch frame and move relative to each other.

[0010] Furthermore, the feeding unit includes a feeding vehicle body and guide wheels, wherein the guide wheels are rotatably connected to the feeding vehicle body, and the guide wheels are arranged in pairs on both sides of the arched guide rail, and the guide wheels can clamp the arched guide rail from both sides.

[0011] Furthermore, the frame includes a chassis frame, a first storage rack and a second storage rack, the first storage rack and the second storage rack are respectively connected to the chassis frame, the drilling unit is movably inserted in the first storage rack, and the spraying unit is movably inserted in the second storage rack.

[0012] Furthermore, the arched guide rail is fixedly connected to the chassis frame, and the first storage rack and the second storage rack are respectively arranged on both sides of the arched guide rail.

[0013] Furthermore, the shotcrete assembly also includes a delivery pump, which is fixedly connected to the chassis frame and communicated with the shotcrete unit through a pipeline to deliver concrete to the shotcrete unit.

[0014] Furthermore, it also includes a crawler moving assembly, which is installed at the bottom of the frame and can drive the base to move along the tunnel.

[0015] Furthermore, the drilling unit includes a drill and a drill bit, the drill bit is detachably connected to the drill, and one side of the drill is provided with a first clamping body for cooperating with the mechanical arm.

[0016] Furthermore, the spraying unit includes a spraying head, and one side of the spraying head is provided with a second clamping body for cooperating with the robotic arm.

[0017] Furthermore, the mechanical arm includes a rotating arm and a clamping head, the clamping head is connected to the frame through the rotating arm, and the clamping head is provided with a clamping groove for cooperating with the drilling unit and the spraying assembly.

[0018] Furthermore, it also includes a liftable workbench, the bottom of which is fixedly connected to the frame.

[0019] Compared with the prior art, the present invention has the following beneficial effects:

[0020] (1) A multifunctional integrated platform of the present invention is provided with a base, which includes a frame and an arched guide rail. The frame can move along the tunnel, drive other components to move, change the area relative to the tunnel wall, automatically expand the working range of the platform, and improve work efficiency. The arched guide rail is arranged relative to the tunnel, and the outer contour of the arched guide rail is similar to the cross-sectional contour of the inner wall of the tunnel, and a semicircular operating space is formed between the arched guide rail and the inner wall of the tunnel. The two ends of the arched guide rail are respectively fixedly connected to the frame, and the arched guide rail and the frame are connected end to end to form a closed structure, so that the arched guide rail can better withstand external pressure and improve the connection strength between the arched guide rail and the frame.

[0021] (2) A multifunctional integrated platform of the present invention is provided with a hydraulic clamping assembly, which includes a mechanical arm and a feeding unit. The feeding unit is installed on an arched guide rail, and the feeding unit can feed and move along the arched guide rail, so that the feeding unit moves around the inner wall of the tunnel with the arched guide rail as the travel trajectory, and the feeding unit can cover all the areas to be processed on the cross-section of the tunnel. The mechanical arm is installed on the feeding unit, and the feeding unit can carry the mechanical arm to move along the arched guide rail, so that the mechanical arm can cross the base and operate on both sides of the tunnel. The feeding unit and the mechanical arm cooperate to expand the working area of ​​the mechanical arm, so that the range of action of a single mechanical arm can cover the entire cross-sectional area of ​​the tunnel.

[0022] (3) A multifunctional integrated stand of the present invention, the mechanical arm can clamp the drilling unit and the spraying unit respectively to move, adjust the position of the drilling unit and the spraying unit, and perform drilling and spraying treatment on different areas of the tunnel wall. The mechanical arm uses the drilling unit and the spraying unit alternately, first clamping the spraying unit to perform initial concrete spraying on a certain area of ​​the tunnel wall, and then directly load the drilling unit onto the frame, and clamp the drilling unit in time to drill holes in the tunnel wall and install anchor rods, combining the two sets of processes into one, shortening the interval between the two processes. Initial spraying of concrete can quickly form a temporary support structure, but its strength is relatively low. The rock mass may also loosen or deform due to external forces. Timely installation of anchor rods can quickly enhance the support effect, effectively prevent the rock mass from loosening and deforming, and reduce the risk of geological disasters. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of this application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:

[0024] Figure 1 The overall structure of the present invention is shown in FIG. Figure 1 ;

[0025] Figure 2 The overall structure of the present invention is shown in FIG. Figure 2 ;

[0026] Figure 3 It is a structural schematic diagram of the hydraulic clamping assembly in the present invention;

[0027] Figure 4 It is a schematic diagram of the structure of the clamping head in the present invention;

[0028] Figure 5 It is a structural schematic diagram of the first storage rack in the present invention;

[0029] Figure 6 It is a structural schematic diagram of the drilling unit in the present invention;

[0030] Figure 7 It is a structural schematic diagram of the spray head in the present invention.

[0031] In the figure, 100, base; 110, frame; 111, chassis frame; 112, first storage rack; 113, second storage rack; 120, arched guide rail;

[0032] 200, drilling assembly; 210, drilling unit; 211, drilling machine; 211a, first clamping body; 212, drill bit;

[0033] 300, spraying assembly; 310, spraying unit; 311, spraying head; 311b, second clamping body; 320, delivery pump;

[0034] 400, hydraulic clamping assembly; 410, mechanical arm; 411, rotating arm; 412, clamping head; 412a, clamping groove; 420, feeding unit; 421, feeding vehicle body; 422, guide wheel;

[0035] 500, crawler moving assembly;

[0036] 600. Workbench. DETAILED DESCRIPTION

[0037] The preferred embodiments of the present invention are described in detail below in conjunction with the accompanying drawings, wherein the accompanying drawings constitute a part of this application and are used together with the embodiments of the present invention to illustrate the principles of the present invention, but are not used to limit the scope of the present invention.

[0038] A multifunctional integrated platform in the present embodiment relates to the field of tunnel construction technology. A drilling assembly 200 for drilling holes in the tunnel wall, a spraying assembly 300 for spraying cement slurry on the tunnel wall, and a hydraulic clamping assembly 400 are arranged on the platform. The hydraulic clamping assembly 400 can clamp the drilling assembly 200 and the spraying assembly 300 to operate the tunnel wall. The hydraulic clamping assembly 400 can also clamp a steel arch frame and move the steel arch frame to the tunnel wall, thereby facilitating the fixation and installation of the steel arch frame.

[0039] See also Figures 1 to 7 A multifunctional integrated stand in this embodiment includes a base 100, a drilling assembly 200, a shotcrete assembly 300 and a hydraulic clamping assembly 400. The base 100 serves as the foundation of the stand and can provide support for other components.

[0040] The base 100 includes a frame 110 and an arched guide rail 120. The frame 110 can move along the tunnel, drive other components to move, change the area relative to the tunnel wall, automatically expand the working range of the stand, and improve work efficiency. The arched guide rail 120 is set relative to the tunnel. The outer contour of the arched guide rail 120 is similar to the cross-sectional contour of the inner wall of the tunnel, and a semicircular operating space is formed between the arched guide rail 120 and the inner wall of the tunnel. The two ends of the arched guide rail 120 are fixedly connected to the frame 110 respectively, and the arched guide rail 120 and the frame 110 are connected end to end to form a closed structure, so that the arched guide rail 120 can better withstand external pressure and improve the connection strength between the arched guide rail 120 and the frame 110.

[0041] The drilling assembly 200 includes a drilling unit 210, which can act on the tunnel wall to drill holes for installing anchor rods on the tunnel wall to reinforce the tunnel wall. The drilling unit 210 is loaded on the frame 110, and the frame 110 can store the drilling unit 210 to ensure that the drilling unit 210 is relatively stable during transportation.

[0042] The spraying assembly 300 includes a spraying unit 310. The spraying unit 310 can act on the tunnel wall to spray concrete relative to the tunnel wall to fix the tunnel wall and cooperate with the steel mesh to enhance the overall strength of the tunnel wall.

[0043] The hydraulic clamping assembly 400 includes a mechanical arm 410 and a feeding unit 420. The feeding unit 420 is installed on the arched guide rail 120. The feeding unit 420 can feed and move along the arched guide rail 120, so that the feeding unit 420 moves around the inner wall of the tunnel with the arched guide rail 120 as the travel trajectory, and the feeding unit 420 can cover all the areas to be processed on the cross-section of the tunnel. The mechanical arm 410 is installed on the feeding unit 420. The feeding unit 420 can carry the mechanical arm 410 to move along the arched guide rail 120, so that the mechanical arm 410 can cross the base 100 and operate on both sides of the tunnel. The feeding unit 420 cooperates with the mechanical arm 410 to expand the workable area of ​​the mechanical arm 410, so that the range of action of a single mechanical arm 410 can cover the entire cross-sectional area of ​​the tunnel.

[0044] The mechanical arm 410 can clamp the drilling unit 210 and the spraying unit 310 to move, adjust the positions of the drilling unit 210 and the spraying unit 310, and perform drilling and spraying treatment on different areas of the tunnel wall. The mechanical arm 410 alternately uses the drilling unit 210 and the spraying unit 310, first clamps the spraying unit 310 to spray concrete on a certain area of ​​the tunnel wall, and can directly load the drilling unit 210 onto the frame 110, and clamp the drilling unit 210 in time to drill holes in the tunnel wall and install anchor rods, combining the two sets of processes into one, shortening the interval between the two processes. The initial spraying of concrete can quickly form a temporary support structure, but its strength is low. The rock mass may also loosen or deform due to external forces. The timely installation of anchor rods can quickly enhance the support effect, effectively prevent the rock mass from loosening and deforming, and reduce the risk of geological disasters.

[0045] The mechanical arm 410 can also clamp and carry the steel mesh and the steel arch frame, and use the machine to assist workers in supporting the tunnel wall, thereby reducing labor intensity and improving work efficiency.

[0046] In some embodiments, see Figure 3 The feed unit 420 includes a feed body 421 and a guide wheel 422. The guide wheel 422 is rotatably connected to the feed body 421. The guide wheel 422 is connected to the feed body 421 through a bearing, and the guide wheel 422 can rotate freely around its own axis. The guide wheels 422 arranged in pairs are arranged on both sides of the arched guide rail 120, and can clamp the arched guide rail 120 from both sides. Ensure the stability of the feed body 421 on the guide rail. The setting of the guide wheel 422 can reduce the shaking and deviation that may occur during movement and operation, thereby improving the operational accuracy of drilling, shotcrete and steel arch installation.

[0047] As a further embodiment, two sets of arched guide rails 120 are provided and arranged at a relative interval, the feeding vehicle body 421 is arranged between the two arched guide rails 120, and a plurality of guide wheels 422 arranged in pairs act on the two arched guide rails 120 respectively. The setting of the guide wheels 422 can limit the feeding vehicle along the radial direction of the arched rails, and the two arched guide rails 120 can limit the feeding vehicle from both sides, so that the feeding vehicle is sufficiently supported and limited, and can only feed and move along the arched guide rails 120. The travel trajectory of the feeding vehicle is strictly limited to ensure the movement accuracy of the vehicle body.

[0048] It should be particularly noted that a driving unit is also provided on the feed trolley, and the driving unit includes a driving gear and a rack. The rack is fixedly connected to the arched guide rail 120, and the rack is relatively bent and has the same degree of curvature as the arched guide rail 120. The gear is connected to the feed trolley through a rotating shaft, and the rotating shaft is connected to a servo motor. The servo motor can drive the gear to rotate, thereby driving the feed trolley to move along the arched guide rail 120.

[0049] As an alternative embodiment, a driving unit is provided on the arched guide rail 120 , and the driving unit includes a sprocket chain transmission structure, a plurality of sprockets are arranged along the arched guide rail 120 , and a chain is simultaneously mounted on the plurality of sprockets, and the chain is connected to the feed trolley, and the chain can drive the feed trolley to move along the arched guide rail 120 .

[0050] In some embodiments, see Figure 2 The frame 110 includes a chassis frame 111, a first storage frame 112 and a second storage frame 113. The first storage frame 112 and the second storage frame 113 are respectively connected to the chassis frame 111. The drilling unit 210 is movably inserted in the first storage frame 112, and the spraying unit 310 is movably inserted in the second storage frame 113. The drilling unit 210 and the spraying unit 310 are respectively inserted in independent storage frames, which realizes the modularization of functions. Different functional units can be operated independently and replaced or adjusted as needed, which improves the flexibility of the equipment.

[0051] The spraying unit 310 and the drilling unit 210 are movably plug-connected to the first storage rack 112 and the second storage rack 113 respectively, so that the drilling unit 210 and the spraying unit 310 can be quickly replaced or adjusted, thereby reducing the downtime of the equipment and improving the construction efficiency.

[0052] The drilling unit 210 and the spraying unit 310 are each placed in an independent storage rack, and can perform different operations simultaneously without interfering with each other. The mechanical arm 410 can quickly insert different functional units into the rack 110 when needed, reducing the cumbersome equipment scheduling and adjustment time.

[0053] Placing the drilling unit 210 and the shotcrete unit 310 in the first and second storage racks 113 respectively can effectively utilize the space and make the overall design of the equipment more compact. The independent storage rack design reduces the occupied area of ​​a single device, especially in a narrow tunnel environment, which not only saves the working space in the tunnel, but also makes the equipment easier to operate and maintain.

[0054] The chassis frame 111 serves as the foundation of the frame body 110 and provides a stable support to ensure that the entire device remains stable during operation. The first storage rack 112 and the second storage rack 113 respectively fix the drilling unit 210 and the spraying unit 310, making it difficult for them to shake or move during operation, thereby improving the operational stability of the device.

[0055] In some embodiments, see Figure 1 and Figure 2The arched guide rail 120 is fixedly connected to the chassis frame 111, which ensures the stability of the entire equipment structure. The chassis frame 111 provides a stable basic support, and the fixed connection of the arched guide rail 120 further enhances the overall stability of the equipment, avoiding operational problems caused by movement or loosening of the guide rail.

[0056] The first storage rack 112 and the second storage rack 113 are respectively disposed on both sides of the arched guide rail 120. The first storage rack 112 and the second storage rack 113 are separated from each other relative to the arched guide rail 120. The mechanical arm 410 disposed at the arched guide rail 120 can rotate relatively to clamp the drilling unit 210 and the spraying unit 310 in the first storage rack 112 and the second storage rack 113 respectively.

[0057] The first storage rack 112 and the second storage rack 113 are respectively arranged on both sides of the arched guide rail 120, which fully utilizes the space of the arched guide rail 120, making the limited tunnel space more compact and improving space utilization.

[0058] Distributing different functional units on both sides of the arched guide rail 120 can achieve a reasonable layout, avoid interference between functional units, and improve the flexibility and efficiency of equipment operation.

[0059] The first storage rack 112 and the second storage rack 113 are respectively arranged on both sides of the arched guide rail 120, so that the drilling unit 210 and the spraying unit 310 can be operated from both sides, reducing the limitation of single-direction operation and improving the operational flexibility. The double-sided layout allows different functional units to be easily inserted and removed from their respective storage racks, achieving rapid switching and improving the working efficiency of the equipment.

[0060] In particular, please refer to Figure 5 The first storage rack 112 includes an external frame and a limiting ring. The limiting ring is arranged inside the external frame and is fixedly connected to the external frame through an elastic member. The elastic member is a flexible plastic or rubber. The elastic member can fix and buffer the limiting ring to reduce the influence and damage of external vibration on the limiting ring. The drilling unit 210 can be inserted into the limiting ring. The limiting ring can not only store the drilling unit 210, but also protect the drilling unit 210 from the influence of external vibration.

[0061] The structure and shape of the second storage rack 113 are consistent with those of the first storage rack 112 , and the limiting ring of the second storage rack 113 can be adjusted according to the size of the spraying unit 310 , so that the second storage rack 113 can store and protect the spraying unit 310 .

[0062] In some embodiments, see Figure 2The shotcrete assembly 300 further includes a delivery pump 320, which is fixedly connected to the chassis frame 111. The delivery pump 320 is connected to the shotcrete unit 310 through a pipeline. The delivery pump 320 can continuously deliver concrete to the shotcrete unit 310 to achieve continuous shotcrete operation. Compared with the traditional intermittent feeding method, the use of the delivery pump 320 enables the shotcrete unit 310 to work continuously and efficiently, avoiding the inefficiency caused by frequent feeding and improving the overall construction progress.

[0063] In addition, by controlling the flow rate of the delivery pump 320, the supply of cement slurry can be accurately adjusted, so that the spraying unit 310 can spray according to actual needs, avoiding excessive or insufficient conditions and improving construction quality.

[0064] In some embodiments, see Figure 1 and Figure 2 A multifunctional integrated platform also includes a crawler moving assembly 500, which is installed at the bottom of the frame 110. The crawler moving assembly 500 has strong passability and can move smoothly on various complex terrains in the tunnel. Compared with the wheeled moving assembly, the crawler can better adapt to complex environments such as uneven ground, gravel and mud, thereby improving the overall adaptability of the equipment.

[0065] The crawler moving assembly 500 includes at least two sets of crawler wheels, which are respectively connected to the bottom of the frame 110. The crawler wheels have a large contact area and a relatively evenly distributed pressure, and can maintain good stability on soft ground or slopes, reducing the risk of equipment tipping over. The crawler wheel assembly can drive the base 100 to move quickly to a designated position, realize rapid switching between different construction positions, reduce equipment scheduling time, and improve construction efficiency. The crawler wheel assembly can move the stand integrated with different components as a whole, without the need to adjust the positions of each unit separately, simplifying the construction process and further improving work efficiency.

[0066] The crawler moving assembly 500 can realize automatic movement through a remote control or automatic control system, reducing the labor intensity and repeated operations of the operator, and improving the convenience and safety of equipment operation. Through the crawler moving assembly 500, the equipment can move by itself without manual handling, reducing the labor burden of construction workers and improving the comfort of the working environment.

[0067] In some embodiments, see Figure 6The drilling unit 210 includes a drill rig 211 and a drill bit 212. The drill bit 212 is detachably connected to the drill rig 211, so that the drill bit 212 can be quickly replaced according to different construction requirements, adapting to drilling operations of different types and sizes, thereby improving the operational flexibility of the equipment. By replacing different types of drill bits 212, the drill rig 211 can be applied to a variety of operating scenarios, such as drilling and coring rocks of different materials, thus expanding the application range of the equipment.

[0068] A first clamping body 211a for cooperating with the mechanical arm 410 is provided on one side of the drilling machine 211. The first clamping body 211a can cooperate with the mechanical arm 410. The mechanical arm 410 cooperates with the first clamping body 211a to accurately locate the position of the drilling machine 211, providing a stable clamping force, ensuring the stability of the drilling machine 211 during operation, ensuring the accuracy of the drilling operation, and improving the construction quality. Through automated clamping and operation, errors caused by manual positioning can be avoided.

[0069] In some embodiments, see Figure 7 The spraying unit 310 includes a spraying head 311. A second clamping body 311b for cooperating with the mechanical arm 410 is provided on one side of the spraying head 311. The spraying head 311 cooperates with the mechanical arm 410 through the second clamping body 311b. The spraying head 311 can be quickly disassembled and replaced to meet different spraying requirements. The operator can flexibly adjust the spraying head 311 according to specific construction requirements to improve the operational flexibility of the equipment. By replacing different types of spraying heads 311, the spraying unit 310 can be suitable for spraying operations of different materials, such as cement slurry, concrete slurry, etc., which expands the application range of the equipment.

[0070] The cooperation between the mechanical arm 410 and the second clamping body 311b reduces the need for the operator to directly contact the spray head 311, reduces the risk of safety accidents caused by contacting the spray head 311, and improves the safety of operation. The second clamping body 311b provides a stable clamping force to ensure the stability of the spray head 311 during operation and reduces the safety hazards caused by the shaking of the equipment.

[0071] In the specific implementation process, the mechanical arm 410 cooperates with the second clamping body 311b to accurately locate the position of the spraying head 311, ensure the accuracy of the spraying operation, and improve the construction quality. Through automated clamping and operation, errors caused by manual positioning can be avoided.

[0072] In some embodiments, see Figure 1 and Figure 4The mechanical arm 410 includes a rotating arm 411 and a clamping head 412. The clamping head 412 is connected to the frame 110 through the rotating arm 411. The rotating arm 411 enables the clamping head 412 to rotate and position freely at multiple angles, thereby enhancing the operational flexibility of the mechanical arm 410 in narrow and complex environments and being able to flexibly respond to different construction requirements. The clamping head 412 is provided with a clamping groove 412a for cooperating with the drilling unit 210 and the spraying assembly 300. The setting of the clamping groove 412a enables the clamping head 412 to quickly cooperate and replace with different functional units (such as the drilling unit 210 and the spraying unit 310), thereby enhancing the versatility and adaptability of the equipment.

[0073] In the specific implementation process, the clamping groove 412a of the clamping head 412 can be embedded in the first clamping body 211a of the drilling machine 211 or the second clamping body 311b of the shotcrete head 311, so that the clamping head 412 can quickly grab and replace the drilling unit 210 and the shotcrete assembly 300, reducing the tool replacement time and improving the overall construction efficiency. The operator can quickly switch between different operation steps and reduce downtime.

[0074] In addition, the coordinated arrangement of the clamping groove 412a and the clamping body can not only improve the connection strength between the clamping head 412 and the drilling rig 211 or the spraying head 311, but also enable the clamping head 412 to be connected to the drilling rig 211 or the spraying head 311 at a certain angle, thereby ensuring the position accuracy of the drilling rig 211 or the spraying head 311.

[0075] The integrated platform also includes a liftable workbench 600, the bottom of which is fixedly connected to the frame 110. The liftable workbench 600 can adjust its height according to different construction requirements and on-site environments, so that workers can operate various tools and equipment to work at an optimal height, thereby improving the flexibility and adaptability of construction.

[0076] In the specific implementation process, the workbench 600 is a workbench 600 controlled by a hydraulic mechanism. The workbench 600 can move in the vertical direction and the horizontal direction, and always maintains a suitable distance from the tunnel wall. Construction workers can stand on the workbench 600 to construct the tunnel wall.

[0077] The lifting function of the workbench 600 can adapt to different working height requirements and support a variety of construction operations such as drilling, spraying and mounting brackets, increasing the versatility of the equipment.

[0078] The liftable workbench 600 can quickly adjust the working height of equipment and tools, reducing the adjustment time due to inappropriate height and improving construction efficiency.

[0079] The height adjustment function of the workbench 600 makes switching between different work steps faster, reduces equipment scheduling time, and improves the overall construction progress.

[0080] Reduced operator fatigue: The height of the Elevating Workbench 600 can be adjusted according to the operator's height and work needs, allowing the operator to work in a comfortable posture, reducing fatigue, improving work efficiency and operator satisfaction.

[0081] The height adjustment function of the workbench 600 allows operators to more easily access and operate tools and equipment, improving the convenience and safety of operation.

[0082] Workflow:

[0083] 1. Preparation stage:

[0084] Equipment inspection: Before construction begins, the operator needs to inspect the various components of the multifunctional integrated stand, including the drilling unit 210, the shotcrete unit 310, the robotic arm 410, the workbench 600, the crawler moving assembly 500, etc., to ensure that each part is functioning properly.

[0085] 2. Shotcrete operation:

[0086] Positioning of the robot arm 410: The robot arm 410 is moved to the spraying position by means of the feeding unit 420. Through the cooperation of the rotating arm 411 and the clamping head 412, the robot arm 410 can be accurately positioned to the position where spraying is required.

[0087] Clamping the spraying head 311: The second clamping body 311b on the clamping head 412 firmly clamps the spraying head 311 through the clamping groove 412a, ensuring the stability of the spraying head 311 during the spraying process.

[0088] Start the delivery pump 320: Start the delivery pump 320 in the spray assembly 300 to deliver cement slurry to the spray head 311 through the pipeline.

[0089] Shotcrete operation: The shotcrete unit 310 is started, and the shotcrete head 311 starts to spray the tunnel wall with concrete. The robot arm 410 can adjust the angle and position of the shotcrete as needed to ensure the uniformity and coverage of the shotcrete.

[0090] Shotcrete spraying is completed: After the spraying is completed, the robot arm 410 returns the spraying head 311 to the second storage rack 113, ready for the next operation.

[0091] 3. Drilling operation:

[0092] Positioning of the robot arm 410: The robot arm 410 is moved to the drilling position by means of the feeding unit 420. Through the cooperation of the rotating arm 411 and the clamping head 412, the robot arm 410 can be accurately positioned to the position where the drilling is required.

[0093] Clamping the drill 211: The first clamping body 211a on the clamping head 412 firmly clamps the drill 211 through the clamping groove 412a, ensuring the stability of the drill 211 during the drilling process.

[0094] Drilling operation: The drilling unit 210 is started, and the drill 211 starts drilling. The mechanical arm 410 can adjust the drilling angle and position as needed to ensure the accuracy and quality of the drilling.

[0095] Drilling is completed: After drilling is completed, the robot arm 410 returns the drill 211 to the first storage rack 112, ready for the next operation.

[0096] 4. Anchor support:

[0097] Worker preparation: The construction worker moves the anchor rod to be installed onto the workbench 600 and puts it in place on the workbench 600.

[0098] Set height: According to the height of the tunnel and construction requirements, adjust the height of the liftable workbench 600 to make it suitable for the current working environment.

[0099] Anchor rod installation: Construction workers install anchor rods into the drilled anchor holes on the workbench 600.

[0100] 5. Install the steel arch:

[0101] Positioning of the mechanical arm 410: Move the mechanical arm 410 to the steel arch installation position. Through the cooperation of the rotating arm 411 and the clamping head 412, the mechanical arm 410 can be accurately positioned to the position where the steel arch needs to be installed.

[0102] Clamping the steel arch frame: The clamping head 412 firmly clamps the steel arch frame to ensure the stability of the steel arch frame during the installation process.

[0103] Installation operation: The mechanical arm 410 moves the steel arch frame to the designated position and installs it. The mechanical arm 410 can adjust the angle and position of the steel arch frame as needed to ensure the accuracy and stability of the installation.

[0104] Installation completed: After the steel arch installation is completed, the robot arm 410 is retracted to prepare for the next operation or repeat the previous steps.

[0105] 5. Move and adjust:

[0106] Track movement: The operator can control the multifunctional integrated platform to move to the next work point along the tunnel through the track movement assembly 500. The track movement assembly 500 ensures the smooth movement of the equipment in the tunnel.

[0107] Adjusting the workbench 600: According to the height requirement of the new working point, adjust the height of the liftable workbench 600 to adapt it to the new working environment.

[0108] 6. Operation cycle:

[0109] Repeat operation: Repeat the above steps according to the construction plan to carry out the next round of drilling, spraying and steel arch installation operations.

[0110] On-site adjustment: During the operation, according to the actual construction situation, the operator can adjust the working parameters of the robot arm 410, the workbench 600 and each functional unit at any time to ensure smooth construction.

[0111] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily conceived by any technician familiar with the technical field within the technical scope disclosed in the present invention should be covered by the present invention.

Claims

1. A multifunctional integrated stand, characterized in that: include: A base, the base comprising a walkable frame and an arched guide rail, the arched guide rail is arranged relative to the tunnel and fixedly connected to the frame; A drilling assembly, the drilling assembly comprising a drilling unit for drilling a hole in a tunnel wall, the drilling unit being loaded on the frame; A shotcrete assembly, the shotcrete assembly comprising a shotcrete unit for spraying the tunnel wall, the shotcrete unit being loaded on the frame; A hydraulic clamping assembly, wherein the hydraulic clamping assembly comprises a mechanical arm and a feeding unit, wherein the feeding unit is mounted on the arched guide rail, and the feeding unit can feed and move along the arched guide rail, and the mechanical arm is mounted on the feeding unit, and the mechanical arm can respectively clamp the drilling unit, the spraying unit and the steel arch frame and move relative to each other.

2. A multifunctional integrated stand according to claim 1, characterized in that: The feeding unit includes a feeding vehicle body and guide wheels, wherein the guide wheels are rotatably connected to the feeding vehicle body, and the guide wheels arranged in pairs are arranged on both sides of the arched guide rail, and the guide wheels can clamp the arched guide rail from both sides.

3. The multifunctional integrated stand according to claim 1, characterized in that: The frame body includes a chassis frame, a first storage rack and a second storage rack, the first storage rack and the second storage rack are respectively connected to the chassis frame, the drilling unit is movably inserted in the first storage rack, and the spraying unit is movably inserted in the second storage rack.

4. The multifunctional integrated stand according to claim 3, characterized in that: The arched guide rail is fixedly connected to the chassis frame, and the first storage rack and the second storage rack are respectively arranged on both sides of the arched guide rail.

5. The multifunctional integrated stand according to claim 4, characterized in that: The shotcrete assembly further comprises a delivery pump, which is fixedly connected to the chassis frame and communicated with the shotcrete unit through a pipeline so as to deliver concrete to the shotcrete unit.

6. The multifunctional integrated stand according to claim 1, characterized in that: It also includes a crawler moving assembly, which is installed at the bottom of the frame and can drive the base to move along the tunnel.

7. The multifunctional integrated stand according to claim 1, characterized in that: The drilling unit comprises a drill and a drill bit, wherein the drill bit is detachably connected to the drill, and a first clamping body for cooperating with the mechanical arm is provided on one side of the drill.

8. The multifunctional integrated stand according to claim 1, characterized in that: The spraying unit comprises a spraying head, and a second clamping body for cooperating with the mechanical arm is provided on one side of the spraying head.

9. A multifunctional integrated stand according to claim 1, 7 or 8, characterized in that: The mechanical arm comprises a rotating arm and a clamping head, wherein the clamping head is connected to the frame through the rotating arm, and the clamping head is provided with a clamping groove for cooperating with the drilling unit and the spraying assembly.

10. The multifunctional integrated stand according to claim 1, characterized in that: It also includes a liftable workbench, the bottom of which is fixedly connected to the frame.