Monitoring and measuring method for excavation support of subsurface tunnel

By setting up support components and monitoring points in tunnel construction, using anchor drilling rigs and hot-rolled rebar monitoring and measuring rods for real-time data collection, the problem of the existing technology being unable to monitor tunnel settlement and inclination is solved, and the construction environment is realized security monitoring and potential hazard forecasts.

CN119085583APending Publication Date: 2024-12-06BEIJING URBAN CONSTRUCTION DESIGN & DEVELOPMENT GROUP CO LIMITED
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411239695.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-05
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The prior art cannot monitor the settlement value and inclination value of the structure during the construction of a hidden tunnel in real time, and cannot effectively determine the safety status of the construction environment.

Method used

By setting up multiple groups of support components and monitoring points in the tunnel structure, real-time data collection is performed using anchor drilling rigs and hot-rolled rebar monitoring and measuring rods, combined with the total station to measure the reflectors of the initial concrete surface of the tunnel, and monitor the arch The area displacement and collapse arch range, analyze and adjust the construction footprint range and support structure in real time.

Benefits of technology

Real-time safety status monitoring of the construction environment is achieved, construction safety is ensured, potential hazards are forecast in a timely manner, and the impact of construction on the surrounding environment is reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119085583A_ABST
    Figure CN119085583A_ABST
Patent Text Reader

Abstract

According to the monitoring and measuring method for excavation supporting of the subsurface tunnel, the settlement value and the inclination value of the structure are monitored in real time, the safety state of the site construction environment can be effectively determined, safe operation of site construction is ensured, deformation of the subsurface tunnel is monitored, monitoring data are analyzed and processed in time, and the safety of the subsurface tunnel is ensured. According to the method, the safety stability of a stratum and a supporting structure is judged, the influence degree of tunnel excavation construction on surrounding rock and the surrounding environment is judged, the construction safety can be controlled, the influence of underground excavation construction on the surrounding environment can be reduced, preventive measures are taken in advance, and accidents are avoided. The excavation length is equal to the distance of one grid, so that a left pilot tunnel working face is formed; and S2, after excavation is completed, a grating and a supporting assembly are erected on the working face of the left pilot tunnel, and a monitoring and measuring drill hole is drilled.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of subway construction engineering, and in particular to a monitoring and measuring method for dark tunnel excavation support. Background Art

[0002] Subway civil engineering includes the construction of the main station building and section tunnels. This is the core part of subway civil engineering, involving technologies in multiple fields such as buildings, bridges, and tunnels. During the construction of dark-cut tunnels, the displacement change of dark-cut tunnels is the focus of attention during the construction process. Whether the arch and side walls are stable reflects whether the on-site construction is in a safe state.

[0003] The existing technology cannot reflect the settlement value and tilt value of the real-time monitoring structure, and cannot effectively determine the safety status of the on-site construction environment. Summary of the invention

[0004] In view of the defects existing in the prior art, the technical problem solved by the present invention is that the prior art cannot reflect the settlement value and inclination value of the real-time monitoring structure, cannot effectively determine the safety status of the on-site construction environment, and provides a monitoring and measurement method for dark tunnel excavation support.

[0005] To achieve the above objectives, the present invention provides:

[0006] The monitoring and measuring method for dark tunnel excavation support requires the use of a tunnel structure, which is characterized in that the tunnel structure includes:

[0007] A primary support structure for a dark-excavated tunnel, wherein a plurality of support components are arranged on the inner side of the primary support structure for the dark-excavated tunnel, a collapse arch is formed on the outer side of the primary support structure for the dark-excavated tunnel, a tunnel arch secondary lining structure is arranged on the inner side of the primary support structure for the dark-excavated tunnel, and a tunnel side wall secondary lining structure is arranged on the bottom of the tunnel arch secondary lining structure;

[0008] By burying monitoring points in stable rock formations, the excavation deformation monitoring of dark tunnels can be carried out conveniently, quickly and accurately. The steps of the safety monitoring measurement method include:

[0009] S1: During construction, blasting is first carried out along the excavation contour of the left pilot tunnel. The excavation length is one grid spacing to form the left pilot tunnel working surface;

[0010] S2: After excavation is completed, grids and support components are set up on the left pilot tunnel working surface, monitoring and measurement holes are drilled, monitoring points B, D, and Fa are arranged on both sides of the arch and side walls, and initial support is completed by spraying concrete. The deformation of the arch and side walls of the primary support structure of the left pilot tunnel is monitored;

[0011] S3: After the excavation surface of the left pilot tunnel is excavated to a certain distance, the right pilot tunnel working surface is excavated;

[0012] S4: After excavating the right pilot tunnel working surface, set up grids and support components, drill monitoring and measurement holes, arrange monitoring points C, E, and Ga on both sides of the arch and side walls, spray concrete to complete the initial support, and monitor the deformation of the arch and side walls of the primary support structure of the right pilot tunnel;

[0013] S5: After the right pilot tunnel excavation surface is excavated to a certain distance, the middle pilot tunnel working surface is excavated;

[0014] S6: After the working face of the middle pilot tunnel is excavated, grids and support components are set up, monitoring and measurement holes are drilled, monitoring points A, Fb, and Gb are arranged on both sides of the arch and side walls, and initial support is completed by spraying concrete to form the initial support structure and collapse arch of the dark excavation tunnel;

[0015] S7: The three excavation faces are staggered by 15m, and excavation is carried out in layers. The above steps are repeated to complete the final excavation of the arch of the dark-cut tunnel;

[0016] S8: According to the measurement data of monitoring points A, B, and C of the arch of the dark-cut tunnel, the length and timing of the arch support assembly removal are analyzed, the arch support assembly is removed in sections and zones, the secondary lining structure of the arch of the dark-cut tunnel is removed, and deformation monitoring of the tunnel arch is continued;

[0017] S9: Excavate the lower part of the station, drill monitoring and measurement holes, arrange side wall horizontal monitoring points H and J, spray concrete to complete the initial support, and conduct real-time monitoring of the tunnel side wall stability;

[0018] S10: The secondary lining structure of the dark-excavated tunnel is completed, forming the tunnel arch secondary lining structure 10 and the tunnel side wall secondary lining structure, and the tunnel arch monitoring points A, B, and C are used to monitor the tunnel arch in real time.

[0019] Preferably, the steps in S2 include:

[0020] First, after the tunnel pilot hole is excavated, anchor drilling rigs are used to drill holes at the locations where monitoring points are set around the tunnel;

[0021] Second, after the hole is formed, the hot-rolled threaded steel bar monitoring and measuring rod is lowered into the hole. According to the position of the fracture surface of the monitoring point, the length of the free section and the fixed end position of the hot-rolled threaded steel bar monitoring and measuring rod are determined. The free section is passed through an isolation plastic pipe on the outside, and the inside of the soil is sealed with tape. The exposed end of the steel bar is tied or welded with a steel ruler, with the scale of the steel ruler facing upwards;

[0022] Third, the other end of the hot-rolled threaded steel bar monitoring and measuring rod is anchored with cement slurry, and the plastic pipe of the free section of the steel bar is reinforced by grouting to form the initial support structure of the dark excavation tunnel;

[0023] Fourth, insert a hard plastic pipe into the hole, expose the pipe from the initial support concrete surface of the tunnel, and fix the outside of the pipe with cement slurry;

[0024] Fifth, data collection is carried out by using a total station to measure the reflective sheet on the initial support concrete surface of the tunnel, and the displacement of the tunnel arch and the range of the collapsed arch are calculated based on the data changes;

[0025] Sixth, according to the design and specification requirements, monitor the arch position of the deep deformation of the dark-excavated tunnel, and according to the monitoring frequency required by the design and specifications, repeat the ae strips to set monitoring points in the middle and lower part of the initial branch of the tunnel and collect data to carry out monitoring work.

[0026] Preferably, the bolt drilling rig has a hole diameter of 150 mm.

[0027] Preferably, the hot-rolled threaded steel bar monitoring and measuring rod adopts 12-16 hot-rolled threaded steel bars, the isolation plastic pipe adopts medium 30 plastic pipe, and the exposed size of the steel bar is not less than 1000mm.

[0028] Preferably, the length of the anchor body at the other end of the hot-rolled threaded steel bar monitoring and measuring rod is not less than 3m, and the diameter of the drill hole is not less than 80mm.

[0029] Preferably, the length of the orifice hard plastic pipe is not less than 0.35 meters, the diameter is greater than 100 meters, and the plastic pipe is exposed outside the surface of the primary sprayed concrete by not less than 50 mm.

[0030] Preferably, through the monitoring and measurement data of the dark tunnel, the single construction advance range during tunnel excavation is adjusted to 0.5-1.5m, the diameter range of the grid steel frame steel bars used for the initial support of the arch is adjusted to 22-32mm, and the length range of the single support removal during the construction of the arch secondary lining is adjusted to 8-12m.

[0031] Compared with the prior art, the advantages of the present invention are:

[0032] The present invention can effectively determine the safety status of the on-site construction environment and ensure the safety of on-site construction by real-time monitoring of the settlement value and inclination value of the structure.

[0033] The present invention monitors the deformation of the dark-excavated tunnel, analyzes and processes the monitoring data in a timely manner, determines the safety and stability of the stratum and supporting structure, and determines the impact of the tunnel excavation construction on the surrounding rock and the surrounding environment. It can control construction safety and reduce the impact of the dark-excavation construction on the surrounding environment, and provide timely and accurate forecasts of potential hazards or accidents that may endanger the environment and the safety of the construction itself, so as to take preventive measures in advance and avoid accidents. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 This is a schematic diagram of the monitoring method during construction;

[0035] Figure 2This is a schematic diagram of the monitoring method during operation;

[0036] Figure 3a-3f The schematic diagram of the monitoring and measurement point layout process of the dark tunnel is shown;

[0037] Figure 4 It is a plan view of the construction sequence of the dark tunnel;

[0038] Figure 5 This is a schematic diagram of buried measuring points in dark tunnels;

[0039] Figure 6 Side view of the measuring rod for monitoring measurement.

[0040] In the figure: 1. Hot-rolled threaded steel bar monitoring and measuring rod; 2. Isolation plastic pipe; 3. Anchor body; 4. Anchor body; 5. Initial support structure of dark-cut tunnel; 6. Hard plastic pipe; 7. Tunnel initial support concrete surface; 8. Initial support structure of dark-cut tunnel; 9. Collapse arch; 10. Secondary lining structure of tunnel arch top; 11. Secondary lining structure of tunnel side wall; 12. Support assembly. DETAILED DESCRIPTION

[0041] The embodiments of the present invention are further described in detail below with reference to the accompanying drawings.

[0042] See also Figure 1-6 As shown, a monitoring and measuring method for dark tunnel excavation support includes a monitoring and measuring method for dark tunnel excavation support, which requires the use of a tunnel structure, characterized in that the tunnel structure includes:

[0043] A primary support structure 8 for a dark-excavated tunnel, wherein a plurality of support components 12 are arranged on the inner side of the primary support structure 8 for the dark-excavated tunnel, a collapse arch 9 is formed on the outer side of the primary support structure 8 for the dark-excavated tunnel, a tunnel arch secondary lining structure 10 is arranged on the inner side of the primary support structure 8 for the dark-excavated tunnel, and a tunnel side wall secondary lining structure 11 is arranged at the bottom of the tunnel arch secondary lining structure 10;

[0044] By burying monitoring points in stable rock formations, the excavation deformation monitoring of dark tunnels can be carried out conveniently, quickly and accurately. The steps of the safety monitoring measurement method include:

[0045] S1: During construction, blasting is first carried out along the excavation contour of the left pilot tunnel. The excavation length is one grid spacing to form the left pilot tunnel working surface;

[0046] S2: After excavation is completed, grids and support components 12 are set up on the left pilot tunnel working surface, monitoring and measurement holes are drilled, monitoring points B, D, and Fa are arranged on both sides of the arch and side walls, and initial support is completed by spraying concrete. The deformation of the arch and side walls of the primary support structure of the left pilot tunnel is monitored;

[0047] S3: After the excavation surface of the left pilot tunnel is excavated to a certain distance, the right pilot tunnel working surface is excavated;

[0048] S4: After the right pilot tunnel working surface is excavated, the grid and support assembly 12 are set up, monitoring and measurement holes are drilled, and monitoring points C, E, and Ga are arranged on both sides of the arch and side walls respectively. The initial support is completed by spraying concrete, and the deformation of the arch and side walls of the primary support structure of the right pilot tunnel is monitored;

[0049] S5: After the right pilot tunnel excavation surface is excavated to a certain distance, the middle pilot tunnel working surface is excavated;

[0050] S6: After the working face of the middle pilot tunnel is excavated, the grid and the support assembly 12 are set up, monitoring and measuring holes are drilled, and monitoring points A, Fb, and Gb are arranged on both sides of the arch and the side walls respectively. The initial support is completed by spraying concrete to form the initial support structure 8 and the collapse arch 9 of the dark excavation tunnel;

[0051] S7: The three excavation faces are staggered by 15m, and excavation is carried out in layers. The above steps are repeated to complete the final excavation of the arch of the dark-cut tunnel;

[0052] S8: According to the measurement data of the monitoring points A, B, and C of the arch of the dark-cut tunnel, the dismantling length and dismantling timing of the arch support assembly 12 are analyzed, the arch support assembly is dismantled in sections and zones, the secondary lining structure of the arch of the dark-cut tunnel is dismantled, and the deformation monitoring of the tunnel arch is continued;

[0053] S9: Excavate the lower part of the station, drill monitoring and measurement holes, arrange side wall horizontal monitoring points H and J, spray concrete to complete the initial support, and conduct real-time monitoring of the tunnel side wall stability;

[0054] S10: The secondary lining structure of the dark-excavated tunnel is completed, forming a tunnel arch secondary lining structure 10 and a tunnel side wall secondary lining structure 11, and the tunnel arch monitoring points A, B, and C are used to monitor the tunnel arch in real time.

[0055] Embodiment 2

[0056] The monitoring and measuring method for dark tunnel excavation support comprises the following steps:

[0057] First, after the tunnel pilot hole is excavated, anchor drilling rigs are used to drill holes at the locations where monitoring points are set around the tunnel;

[0058] Second, after the hole is formed, the hot-rolled threaded steel bar monitoring and measuring rod 1 is lowered into the hole. According to the position of the fracture surface of the monitoring point, the length of the free section and the fixed end position of the hot-rolled threaded steel bar monitoring and measuring rod 1 are determined. The free section is passed through an isolation plastic pipe 2, and the inner side of the soil is sealed with tape. The exposed end of the steel bar is tied or welded with a steel ruler 3, with the scale surface of the steel ruler facing upwards;

[0059] Third, the other end of the hot-rolled threaded steel bar monitoring and measuring rod 1 is formed with cement slurry to form an anchor body 4, and the free section of the steel bar is reinforced by grouting outside the plastic pipe to form an initial support structure 5 for the dark excavation tunnel;

[0060] Fourth, insert a hard plastic pipe 6 into the hole, the pipe is exposed from the tunnel primary support concrete surface 7, and the outside of the pipe is fixed with cement slurry;

[0061] Fifth, data collection is carried out by using a total station to measure the reflective sheet on the initial support concrete surface of the tunnel, and the displacement of the tunnel arch and the range of the collapsed arch are calculated based on the data changes;

[0062] Sixth, according to the design and specification requirements, monitor the arch position of the deep deformation of the dark-excavated tunnel, and according to the monitoring frequency required by the design and specifications, repeat the ae strips to set monitoring points in the middle and lower part of the initial branch of the tunnel and collect data to carry out monitoring work.

[0063] In this embodiment, the anchor drilling rig drills a hole with a diameter of 150 mm.

[0064] In this embodiment, the hot-rolled threaded steel bar monitoring and measuring rod 1 adopts 12-16 hot-rolled threaded steel bars, the isolation plastic pipe 2 adopts a medium 30 plastic pipe, and the exposed size of the steel bar is not less than 1000mm.

[0065] In this embodiment, the length of the anchor body 4 at the other end of the steel bar is not less than 3m, and the diameter of the drill hole is not less than 80mm.

[0066] In this embodiment, the length of the orifice hard plastic pipe 6 is not less than 0.35 meters, the diameter is greater than 100 meters, and the plastic pipe is exposed outside the primary sprayed concrete surface 7 by not less than 50 mm.

[0067] In this embodiment, through the monitoring and measurement data of the dark tunnel, the single construction advance range during tunnel excavation is adjusted to 0.5-1.5m, the diameter range of the grid steel frame steel bars used for the initial support of the arch is adjusted to 22-32mm, and the length range of the single support removal during the construction of the arch secondary lining is adjusted to 8-12m.

[0068] The present invention is not limited to the above-mentioned optimal implementation mode. Anyone can derive other various forms of products under the inspiration of the present invention. However, no matter what changes are made in the shape or structure, all technical solutions that are the same or similar to the present invention are within the scope of protection.

Claims

1. A monitoring and measuring method for dark tunnel excavation support requires the use of a tunnel structure, characterized in that: The tunnel structure comprises: A primary support structure (8) for a dark-excavated tunnel, wherein a plurality of support components (12) are arranged on the inner side of the primary support structure (8), a collapse arch (9) is formed on the outer side of the primary support structure (8), a tunnel arch secondary lining structure (10) is arranged on the inner side of the primary support structure (8), and a tunnel side wall secondary lining structure (11) is arranged at the bottom of the tunnel arch secondary lining structure (10); The steps of the safety monitoring measurement method include: S1: During construction, blasting is first carried out along the excavation contour of the left pilot tunnel. The excavation length is one grid spacing to form the left pilot tunnel working surface; S2: After excavation is completed, grids and support components (12) are set up on the left pilot tunnel working surface, monitoring and measurement holes are drilled, monitoring points B, D, and Fa are arranged on both sides of the arch and side walls, and initial support is completed by spraying concrete. The deformation of the arch and side walls of the primary support structure of the left pilot tunnel is monitored; S3: After the excavation surface of the left pilot tunnel is excavated to a certain distance, the right pilot tunnel working surface is excavated; S4: After the right pilot tunnel working surface is excavated, grids and support components (12) are set up, monitoring and measurement holes are drilled, monitoring points C, E, and Ga are arranged on both sides of the arch and side walls, and initial support is completed by spraying concrete. The deformation of the arch and side walls of the primary support structure of the right pilot tunnel is monitored; S5: After the right pilot tunnel excavation surface is excavated to a certain distance, the middle pilot tunnel working surface is excavated; S6: After the working face of the middle pilot tunnel is excavated, grids and support components (12) are set up, monitoring and measurement holes are drilled, monitoring points A, Fb, and Gb are arranged on both sides of the arch and side walls, and initial support is completed by spraying concrete to form the initial support structure (8) and the collapse arch (9) of the dark tunnel; S7: The three excavation faces are staggered by 15m, and excavation is carried out in layers. The above steps are repeated to complete the final excavation of the arch of the dark-cut tunnel; S8: Analyze the dismantling length and dismantling timing of the arch support assembly (12) based on the measurement data of the monitoring points A, B, and C of the dark-cut tunnel arch, dismantle the arch support assembly in sections and zones, dismantle the secondary lining structure of the dark-cut tunnel arch, and continue to monitor the deformation of the tunnel arch; S9: Excavate the lower part of the station, drill monitoring and measurement holes, arrange side wall horizontal monitoring points H and J, spray concrete to complete the initial support, and conduct real-time monitoring of the tunnel side wall stability; S10: The secondary lining structure of the dark-excavated tunnel is completed, forming a tunnel arch secondary lining structure (10) and a tunnel side wall secondary lining structure (11), and the tunnel arch is monitored in real time through the tunnel arch monitoring points A, B, and C.

2. The monitoring and measuring method for dark tunnel excavation support according to claim 1 is characterized in that: The steps in S2 include: First, after the tunnel pilot hole is excavated, anchor drilling rigs are used to drill holes at the locations where monitoring points are set around the tunnel; Second, after the hole is formed, a hot-rolled threaded steel bar monitoring and measuring rod (1) is lowered into the hole. According to the position of the fracture surface of the monitoring point, the length of the free section and the position of the fixed end of the hot-rolled threaded steel bar monitoring and measuring rod (1) are determined. The free section is passed through an isolation plastic pipe (2) on the outside, and the inside of the soil is sealed with tape. The exposed end of the steel bar is tied or welded with a steel ruler (3), with the scale surface of the steel ruler facing upwards; Third, the other end of the hot-rolled threaded steel bar monitoring and measuring rod (1) is formed into an anchor body (4) with cement slurry, and the free section of the steel bar is reinforced by grouting outside the plastic pipe to form an initial support structure (5) for the dark excavation tunnel; Fourth, a hard plastic pipe (6) is inserted into the hole, the pipe is exposed above the tunnel primary support concrete surface (7), and the outside of the pipe is fixed with cement slurry; Fifth, data collection is carried out by using a total station to measure the reflective sheet on the initial support concrete surface of the tunnel, and the displacement of the tunnel arch and the range of the collapsed arch are calculated based on the data changes; Sixth, according to the design and specification requirements, monitor the arch position of the deep deformation of the dark-excavated tunnel, and according to the monitoring frequency required by the design and specifications, repeat the ae strips to set monitoring points in the middle and lower part of the initial branch of the tunnel and collect data to carry out monitoring work.

3. The monitoring and measuring method for dark tunnel excavation support according to claim 2 is characterized in that: The anchor drilling rig has a hole diameter of 150 mm.

4. The monitoring and measuring method for dark tunnel excavation support according to claim 2 is characterized in that: The steel bars (1) are 12-16 hot-rolled threaded steel bars, the isolation plastic pipe (2) is a medium 30 plastic pipe, and the exposed size of the steel bars is not less than 1000 mm.

5. The monitoring and measuring method for dark tunnel excavation support according to claim 2 is characterized in that: The anchor body (4) at the other end of the steel bar has a length of not less than 3m and a borehole diameter of not less than 80mm.

6. The monitoring and measuring method for dark tunnel excavation support according to claim 2 is characterized in that: The length of the orifice hard plastic pipe (6) is not less than 0.35 meters, the diameter is greater than 100 meters, and the plastic pipe is exposed outside the primary sprayed concrete surface (7) by not less than 50 mm.

7. The monitoring and measuring method for dark tunnel excavation support according to claim 2 is characterized in that: Through the monitoring and measurement data of the dark tunnel, the single construction advance range during tunnel excavation was adjusted to 0.5-1.5m, the diameter of the grid steel frame steel bars used for the initial support of the arch was adjusted to 22-32mm, and the length of the single support removed during the construction of the secondary lining of the arch was adjusted to 8-12m.