PSD-BPA planning scheme comparison and selection method, system, equipment, medium and program
Through automated processing and intelligent planning scheme comparison, the problem of cumbersome data maintenance when the power network changes is solved, the PSD-BPA software is quickly updated and the optimal solution selection is achieved, and the work efficiency and data accuracy are improved. .
Patent Information
- Application Number
- CN202411108615.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-13
- Publication Date
- 2024-12-06
AI Technical Summary
When faced with frequent changes in the power network and multiple solutions, existing PSD-BPA power analysis software is cumbersome in data maintenance and easy to introduce human errors, which affects work efficiency and decision-making response speed.
Provide a PSD-BPA planning scheme comparison method, through automated processing and intelligent planning scheme comparison, use BPA trend and stable data to determine alternative access solutions, obtain calculation results and compare, and select the optimal access scheme. Reduce manual intervention and improve data accuracy.
It realizes rapid update and dynamic adjustment of power equipment information, reduces the burden on staff, avoids human errors, and improves work efficiency and the scientificity and economicality of planning solutions.
Smart Images

Figure CN119090299A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of power grid and computer technology, and in particular to a PSD-BPA planning scheme comparison method, system, device, medium and program. Background Art
[0002] PSD-BPA power analysis software not only combines huge computing scale, rapid computing efficiency, excellent numerical stability and powerful functions, but also deeply reflects the accurate capture and efficient analysis of the complex dynamic behavior of the power system. However, the data management mode of PSD-BPA, especially the storage method based on fixed column width data cards, ensures the consistency and standardization of data, but in the face of frequent changes in the power network, comparison of multiple schemes and seasonal operation mode adjustments (such as the differentiated computing needs of summer peak and winter trough), the limitations of its data maintenance gradually emerge.
[0003] Specifically, whenever there is a need to add or update power equipment information, even if it is a minor change, it is necessary to manually locate the corresponding data card and carefully modify it according to the established format. This process is not only cumbersome and time-consuming, but also prone to the risk of data inconsistency due to human error. Especially when making large-scale network adjustments or optimizing operating modes, such as multiple scenario simulations of high loads in summer and low loads in winter, it is necessary to repeatedly adjust and verify the system performance under different parameter configurations. The workload of data modification has increased dramatically, seriously restricting work efficiency and decision-making response speed. In addition, the high cost of manual operation is not only reflected in the time consumption, but also in the excessive reliance on human resources, which makes it difficult to adapt to the power industry's growing demand for intelligent and automated management. Summary of the invention
[0004] In view of the problem in the prior art that when large-scale network adjustment or operation mode optimization is performed, it is necessary to manually modify or update the power equipment information, which affects work efficiency. The present invention provides a PSD-BPA planning scheme comparison method, which can realize the automatic modification of power equipment information in files, compare different planning schemes, determine the optimal planning scheme, and improve work efficiency.
[0005] In order to achieve the above object, the present invention provides the following technical solutions.
[0006] In the first aspect, a PSD-BPA planning scheme comparison method is provided, comprising:
[0007] Determine the required data for alternative access schemes based on the BPA flow and stability data of the research grid;
[0008] Modify and run the required data of the alternative access schemes to obtain calculation results of several alternative access schemes;
[0009] The calculation results of several alternative access solutions are compared to obtain the optimal access solution.
[0010] As a further improvement of the present invention, the method of determining the required data for the alternative access scheme based on the BPA flow and stability data of the research power grid includes:
[0011] According to the BPA flow and stability data of the power grid in the studied area, sort out the data required for the access plan and determine the required data for the alternative access plan;
[0012] The data required for organizing the access plan include access voltage level, number of lines, line type and length, investment cost, and implementation difficulty.
[0013] As a further improvement of the present invention, the required data of the alternative access schemes are modified and run to obtain calculation results of several alternative access schemes, including:
[0014] Based on Python, the required data of the alternative access scheme is read, and the required data of the alternative access scheme is modified to obtain the modified calculation data;
[0015] The modified calculation data is automatically run based on Python to obtain the calculation results of several alternative access solutions.
[0016] As a further improvement of the present invention, the calculation results of several alternative access solutions are compared to obtain the optimal access solution, including:
[0017] Based on Python reading the calculation results of the several alternative access schemes, the phase and voltage regulation, network loss, power grid equipment load, power flow distribution and economy are compared to obtain the best access scheme among the alternative schemes.
[0018] As a further improvement of the present invention, the phase and voltage regulation conditions, network loss conditions, grid equipment load conditions, power flow distribution conditions and economic efficiency are compared and scored to obtain the best access solution among the alternative solutions, including:
[0019] Compare and score the phase and voltage regulation, network loss, grid equipment load, power flow distribution and economy to obtain the scoring results;
[0020] According to the set evaluation criteria and weights, the scoring results are quantitatively scored to obtain the scoring results of several alternative access solutions;
[0021] Based on actual needs, find the best access solution from the scoring results of several alternative access solutions.
[0022] As a further improvement of the present invention, the comparative scoring of phase and voltage regulation, network loss, grid equipment load, power flow distribution and economy includes:
[0023] Compare and score the phase and voltage regulation results of several alternative access schemes according to the specification requirements;
[0024] Compare and score the power flow distribution, network loss, grid equipment load and short-circuit current of several alternative access schemes based on the equipment allowance of the research grid;
[0025] Compare and score several alternative access solutions in terms of implementation difficulty and economic feasibility.
[0026] In a second aspect, the present invention provides a PSD-BPA planning scheme comparison and selection system, comprising:
[0027] Data acquisition module: used to determine the required data for alternative access schemes based on the BPA flow and stability data of the research grid;
[0028] Calculation result module: used to modify and run the required data of the alternative access scheme and obtain the calculation results of several alternative access schemes;
[0029] Result comparison module: used to compare the calculation results of several alternative access solutions to obtain the optimal access solution.
[0030] In a third aspect, the present invention provides an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps of the PSD-BPA planning scheme comparison method when executing the computer program.
[0031] In a fourth aspect, the present invention provides a computer-readable storage medium, characterized in that the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the PSD-BPA planning scheme comparison method are implemented.
[0032] In a fifth aspect, the present invention provides a computer program product, characterized in that it includes computer instructions, which, when executed by a processor, implement the steps of the PSD-BPA planning scheme comparison method.
[0033] Compared with the prior art, the present invention has the following beneficial effects:
[0034] In the traditional mode, facing the complex and changeable power system network, every expansion, transformation or operation strategy adjustment requires manual intervention, which is not only time-consuming and labor-intensive, but also very easy to cause data errors due to human omissions, thereby affecting the effectiveness and reliability of the overall planning scheme. The present invention realizes the rapid update and dynamic adjustment of power equipment information through highly integrated data processing and automated calculation processes. This process does not require manual verification and modification one by one, which greatly reduces the burden on staff, while avoiding errors caused by human factors and ensuring the accuracy and timeliness of data. On this basis, the present invention further introduces an intelligent planning scheme comparison mechanism, which can automatically perform in-depth calculation and analysis on multiple alternative schemes, comprehensively consider technical feasibility, economic cost, environmental impact and other factors, and finally select the optimal access scheme. This process is not only efficient and fast, but also scientific and objective, providing decision makers with strong data support and decision-making basis. In addition, by reducing manual intervention and improving work efficiency, the present invention effectively reduces the operating costs of power companies and improves the scientificity and economy of planning schemes.
[0035] In summary, the present invention has demonstrated significant advantages and values in improving work efficiency, ensuring data accuracy, and optimizing resource allocation with its automated processing capabilities and intelligent planning scheme comparison mechanism. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] The drawings described herein are for illustrative purposes only and are not intended to limit the scope of the present disclosure in any way. In the drawings:
[0037] Figure 1 A schematic diagram of a flow chart of a PSD-BPA planning scheme comparison method of the present invention;
[0038] Figure 2 A strategy flow chart of a PSD-BPA planning scheme comparison method of the present invention;
[0039] Figure 3 It is a schematic diagram of reading and modifying in the embodiment;
[0040] Figure 4 It is a schematic diagram of voltage regulation calculation in the embodiment;
[0041] Figure 5 It is a schematic diagram of short circuit calculation in the embodiment;
[0042] Figure 6 It is a schematic diagram of the scheme comparison in the embodiment;
[0043] Figure 7 It is a structural schematic diagram of a PSD-BPA planning scheme comparison and selection system of the present invention;
[0044] Figure 8Schematic diagram of an electronic device in an embodiment of the present invention. DETAILED DESCRIPTION
[0045] In order to enable those skilled in the art to better understand the technical solutions in the present invention, the technical solutions in the present invention will be clearly and completely described below in conjunction with the drawings in the present invention. The described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in the field without creative work should fall within the scope of protection of the present invention.
[0046] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those generally understood by those skilled in the art of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.
[0047] In view of the problem in the prior art that when large-scale network adjustment or operation mode optimization is performed, it is necessary to manually modify or update the power equipment information, which affects the work efficiency. The present invention provides a PSD-BPA planning scheme comparison method, such as Figure 1 As shown, the method includes:
[0048] S101: Determine the required data for alternative access solutions based on the BPA flow and stability data of the research power grid;
[0049] S201: modifying and running the required data of the alternative access schemes to obtain calculation results of several alternative access schemes;
[0050] S301: Compare calculation results of several candidate access solutions to obtain an optimal access solution.
[0051] The present invention can realize automatic modification of power equipment information in files, compare and select different planning schemes, determine the optimal planning scheme, and improve work efficiency.
[0052] The present invention is further explained below in conjunction with the specific drawings.
[0053] The present invention provides a PSD-BPA planning scheme comparison method based on Python, such as Figure 2 As shown, the method specifically comprises the following steps:
[0054] S1: Receive the power flow and stability files dat and swi of the power grid in the studied area; create a new scheme data table and list the relevant data of the alternative access schemes;
[0055] S2: Based on Python, read the relevant data of the alternative access solutions through the third-party library xlrd, and modify the dat and swi files of different solutions;
[0056] S3: Based on Python, the modified dat and swi files are automatically executed through the third-party library win32api;
[0057] S4: Read the pfo file for power flow calculation, the swx file for stability calculation, and the lis (sce) file for short-circuit current calculation results based on Python, and save the calculation results through the third-party library xlwt;
[0058] S5: Comprehensively compare and select the best solution based on the calculation results to recommend the best solution.
[0059] The present invention is further explained below in conjunction with specific embodiments.
[0060] Example
[0061] like Figure 2 As shown, a flowchart of a PSD-BPA planning scheme comparison method based on Python optimization of the present invention is shown, and the specific operation steps of the method are as follows:
[0062] S1: Receive the dat and swi files of the power grid in the studied area; create a new scheme data table and list the data related to the alternative access schemes;
[0063] The specific data table of the new construction plan is shown in Table 1, including the access voltage level, number of lines, type and length, investment cost, implementation difficulty, etc.
[0064] The table content only needs to list the content related to the alternative access plan, including the addition and deletion of line data.
[0065] Table 1 Access system alternative access plan 1
[0066]
[0067]
[0068] S2: Read relevant data through the third-party library xlrd based on Python, and modify the dat and swi files of different alternative access solutions;
[0069] Based on Python, the third-party library xlrd is used to read the relevant data of the new plan table and modify the corresponding parts of the dat and swi files.
[0070] Based on Python, the third-party library xlwt is used to read the relevant bus voltages, relevant line flow data, network loss conditions and grid equipment load conditions in the pfo files of the power flow calculation results of different schemes;
[0071] Based on Python, the third-party library xlwt is used to read the overvoltage, sub-supply current data, etc. in the stable calculation results swx file of different schemes;
[0072] Based on Python, the third-party library xlwt is used to read the short-circuit current calculation results of different schemes and the relevant bus short-circuit current data in the LIS (SCE) file.
[0073] Specific data reading and modification include: reading the content of the new scheme data table, modifying the dat and swi file data, such as Figure 3 shown.
[0074] S3: Based on Python, the modified dat and swi files are automatically executed through the third-party library win32api;
[0075] The specific calculation of alternative access solutions includes: based on the dat and swi files of different solutions, Python calls the flow and stability kernel program through the third-party library win32api to automatically run the alternative access solution, including phase adjustment and voltage regulation calculation, stability calculation, short-circuit current calculation, etc. Figure 4 and Figure 5 shown.
[0076] Phase modulation and voltage regulation calculations mainly focus on maintaining the grid voltage within a reasonable range and improving the power factor of the power system by adjusting the output of generators or reactive compensation equipment. The results directly affect the voltage stability and power quality of the grid.
[0077] Stability calculation in the power system is mainly to simulate and calculate the possible fault problems in the power system according to the national power engineering planning and design requirements, analyze the problems and propose solutions to ensure that the power system can operate stably after the project construction is completed. It includes network loss, power grid equipment load, and power flow distribution.
[0078] Flow distribution is the basis of power system stability analysis. The stability of the power system depends largely on whether the flow distribution is reasonable. If the flow distribution is uneven, it may cause some equipment to be overloaded, thus causing system instability. Therefore, the flow distribution must be considered when performing stability calculations.
[0079] The load of power grid equipment is also an important factor affecting the stability of the power system. Excessive load rate of equipment may cause equipment overheating, damage, or even cause system failure. When performing stability calculations, it is necessary to consider the load capacity of power grid equipment to ensure that it can operate safely under various working conditions.
[0080] Although network loss is closely related to the economic efficiency of the power system, it does not directly affect the stability of the system. However, excessive network loss may lead to reduced system efficiency and increased operating costs, which will indirectly affect the long-term stable operation of the system.
[0081] Short-circuit current calculation is used to evaluate the current level of the power grid during a short-circuit fault, and is an important basis for power grid protection design and equipment selection.
[0082] S4: Read the pfo file for power flow calculation, the swx file for stability calculation, and the lis (sce) file for short-circuit current calculation results based on Python, and save the calculation results through the third-party library xlwt;
[0083] The specific scheme comparison includes: reading the calculation results of the alternative access schemes for comprehensive comparison, including phase and voltage regulation, network loss, grid equipment load, power flow distribution, economy, etc., to obtain the best access scheme among the alternative access schemes, such as Figure 6 shown.
[0084] Reading the calculation results of the alternative access schemes for comprehensive comparison is a comprehensive comparison of the phase and voltage regulation, power flow distribution, short-circuit current, implementation difficulty and economy of different alternative access schemes, including.
[0085] The phase and voltage regulation results of different alternative access schemes are scored according to the specification requirements;
[0086] Good phase modulation and voltage regulation can optimize power flow distribution, reduce voltage deviation and power loss, and thus improve the economy and reliability of the power grid.
[0087] The power flow distribution, network loss, grid equipment load and short-circuit current of different alternative access schemes are scored according to the equipment allowance of the research grid;
[0088] Reasonable phase-modulation and voltage-regulation strategies can reduce the current impact during short circuits and protect grid equipment from damage.
[0089] Score the implementation difficulty and economic feasibility of different alternative access solutions.
[0090] The configuration and operation and maintenance costs of phase-shifting and voltage-regulating equipment will affect the economic feasibility of the solution, while the difficulty of equipment installation and commissioning is related to the difficulty of implementation.
[0091] S5: Comprehensively compare and select the best solution based on the calculation results to recommend the best solution.
[0092] S5.1: Clarify the evaluation criteria and weights of various evaluation indicators, namely phase and voltage regulation, power flow distribution, short-circuit current, implementation difficulty, and economy.
[0093] These criteria and weights should be determined based on the specific needs, technical requirements, economic benefits, etc. of the project. For example, for projects that pay special attention to system stability, the weights of phase regulation, voltage regulation and short-circuit current will be higher; while for cost-sensitive projects, the weight of economy will be higher.
[0094] S5.2: Based on the scores in S4, collect the specific calculation results and data of each alternative access scheme under the evaluation indicators in S5.1. These data may include the effect evaluation of phase and voltage regulation, power flow distribution diagram, short-circuit current calculation results, implementation difficulty assessment report and economic analysis report, etc.
[0095] S5.3: Quantitatively score each alternative access scheme based on the set evaluation criteria and weights. For technical indicators such as phase and voltage regulation, power flow distribution, and short-circuit current, scores can be given based on specific data and regulatory requirements; for non-technical indicators such as implementation difficulty and economic efficiency, scores can be obtained through expert review, questionnaires, etc.
[0096] S5.4: The scores of each alternative access solution under each evaluation indicator are weighted and summed to obtain the comprehensive score of each solution. As shown in Table 2, the comprehensive score reflects the comprehensive performance of the solution in multiple dimensions.
[0097] S5.5: Compare the alternative access solutions based on their comprehensive scores. The solution with the highest comprehensive score is usually considered the best solution. However, before making a final recommendation, other non-quantitative factors need to be considered, such as technical feasibility, policy restrictions, and environmental impact.
[0098] Table 2 Results of alternative access scheme 1 for access system
[0099]
[0100]
[0101] In summary, the present invention provides a PSD-BPA planning scheme comparison method based on Python optimization, which can be used to compare different access schemes and determine the optimal access scheme. It uses the computer's data processing capabilities and Python's ability to easily develop automated programs to replace manual modification and operation, thereby avoiding duplication of work, reducing workload, and improving work efficiency and accuracy.
[0102] The second object of the present invention is to propose a PSD-BPA planning scheme comparison system, such as Figure 7 As shown, including:
[0103] The data acquisition module 102 is used to determine the required data of the alternative access scheme according to the BPA flow and stability data of the research power grid;
[0104] Calculation result module 202: used to modify and run the required data of the alternative access scheme, and obtain the calculation results of several alternative access schemes;
[0105] The result comparison module 302 is used to compare the calculation results of several candidate access solutions to obtain the optimal access solution.
[0106] like Figure 8 As shown, the third object of the present invention is to provide an electronic device,
[0107] The electronic device includes: a processor 501, a memory 502 and a display screen 503. The memory 502 and the display screen 503 are both connected to the processor 501, such as through a bus 504. Optionally, the electronic device may further include a transceiver 505. It should be noted that in actual applications, the transceiver 505 is not limited to one, and the structure of the electronic device does not constitute a limitation on the embodiments of the present application.
[0108] Processor 501 may be a CPU (Central Processing Unit), a general purpose processor, a DSP (Digital Signal Processor), an ASIC (Application Specific Integrated Circuit), an FPGA (Field Programmable Gate Array) or other programmable logic devices, transistor logic devices, hardware components or any combination thereof. It may implement or execute various exemplary logic blocks, modules and circuits described in conjunction with the disclosure of this application. Processor 501 may also be a combination that implements computing functions, such as a combination of one or more microprocessors, a combination of a DSP and a microprocessor, etc.
[0109] The bus 504 may include a path to transmit information between the above components. The bus 504 may be a PCI (Peripheral Component Interconnect) bus or an EISA (Extended Industry Standard Architecture) bus, etc. The bus 504 may be divided into an address bus, a data bus, a control bus, etc.
[0110] The memory 502 may be a ROM (Read Only Memory) or other types of static storage devices that can store static information and instructions, a RAM (Random Access Memory) or other types of dynamic storage devices that can store information and instructions, or an EEPROM (Electrically Erasable Programmable Read Only Memory), a CD-ROM (Compact Disc Read Only Memory) or other optical disk storage, optical disk storage (including compressed optical disk, laser disk, optical disk, digital versatile disk, Blu-ray disk, etc.), a magnetic disk storage medium or other magnetic storage device, or any other medium that can be used to carry or store the desired program code in the form of instructions or data structures and can be accessed by a computer, but is not limited to these.
[0111] The memory 502 is used to store application code for executing the solution of the present application, and the execution is controlled by the processor 501. The processor 501 is used to execute the application code stored in the memory 502 to implement the contents shown in the above method embodiment.
[0112] Figure 8 The electronic device shown is merely an example and should not bring any limitation to the functions and scope of use of the embodiments of the present application.
[0113] The fourth object of the present invention is to provide a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, wherein the computer program is stored thereon, and when the program is executed by a processor, the aforementioned Figure 1 and Figure 2 The various processes of the method embodiment shown in the figure include, for example, a memory including instructions, and the instructions can be executed by a processor of an electronic device to complete the method.
[0114] A computer-readable storage medium may be a tangible device that holds and stores instructions used by an instruction execution device. A computer-readable storage medium may be, but is not limited to, an electrical storage device, a magnetic storage device, an optical storage device, an electromagnetic storage device, a semiconductor storage device, or any combination thereof. Specifically, a computer-readable storage medium may be a portable computer disk, a hard disk, a USB flash drive, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), a podium random access memory (SRAM), a portable compact disk read-only memory (CD-ROM), a digital versatile disk (DVD), a memory stick, a floppy disk, an optical disk, a magnetic disk, a mechanical encoding device, and any combination thereof.
[0115] A fifth object of the present invention is to provide a computer program product, comprising computer instructions, which, when executed by a processor, implement the above Figure 1 and Figure 2 The various processes of the method embodiment shown can achieve the same technical effect, and will not be described again here to avoid repetition.
[0116] Many embodiments and many applications beyond the examples provided will be apparent to those skilled in the art upon reading the above description. Therefore, the scope of the present teachings should not be determined with reference to the above description, but rather with reference to the preceding claims and the full scope of equivalents to which such claims are entitled. For the purpose of comprehensiveness, all articles and references, including disclosures of patent applications and publications, are incorporated herein by reference. The omission of any aspect of the subject matter disclosed herein in the preceding claims is not intended to be a disclaimer of such subject matter, nor should it be considered that the applicants did not consider such subject matter to be part of the disclosed inventive subject matter.
[0117] The above content is a further detailed description of the present invention. It cannot be determined that the specific implementation methods of the present invention are limited to these. For ordinary technicians in the technical field to which the present invention belongs, without departing from the concept of the present invention, they can also make several simple deductions or substitutions, which should be regarded as belonging to the protection scope of the present invention determined by the submitted claims.
Claims
1. A PSD-BPA planning scheme comparison method, characterized in that: include: Determine the required data for alternative access schemes based on the BPA flow and stability data of the research grid; Modify and run the required data of the alternative access schemes to obtain calculation results of several alternative access schemes; The calculation results of several alternative access solutions are compared to obtain the optimal access solution.
2. A PSD-BPA planning scheme comparison method according to claim 1, characterized in that: The required data for determining the alternative access scheme based on the BPA flow and stability data of the research power grid include: According to the BPA flow and stability data of the power grid in the studied area, sort out the data required for the access plan and determine the required data for the alternative access plan; The data required for organizing the access plan include access voltage level, number of lines, line type and length, investment cost, and implementation difficulty.
3. A PSD-BPA planning scheme comparison method according to claim 1, characterized in that: The required data of the alternative access scheme is modified and run to obtain calculation results of several alternative access schemes, including: Based on Python, the required data of the alternative access scheme is read, and the required data of the alternative access scheme is modified to obtain the modified calculation data; The modified calculation data is automatically run based on Python to obtain the calculation results of several alternative access solutions.
4. A PSD-BPA planning scheme comparison method according to claim 1, characterized in that: The calculation results of the plurality of alternative access solutions are compared to obtain the optimal access solution, including: Based on Python reading the calculation results of the several alternative access schemes, the phase and voltage regulation, network loss, power grid equipment load, power flow distribution and economy are compared to obtain the best access scheme among the alternative schemes.
5. A PSD-BPA planning scheme comparison method according to claim 4, characterized in that: The phase and voltage regulation, network loss, grid equipment load, power flow distribution and economy are compared and scored to obtain the best access solution among the alternative solutions, including: Compare and score the phase and voltage regulation, network loss, grid equipment load, power flow distribution and economy to obtain the scoring results; According to the set evaluation criteria and weights, the scoring results are quantitatively scored to obtain the scoring results of several alternative access solutions; Based on actual needs, find the best access solution from the scoring results of several alternative access solutions.
6. A PSD-BPA planning scheme comparison method according to claim 5, characterized in that: The comparative scoring of phase and voltage regulation, network loss, grid equipment load, power flow distribution and economy includes: Compare and score the phase and voltage regulation results of several alternative access schemes according to the specification requirements; Compare and score the power flow distribution, network loss, grid equipment load and short-circuit current of several alternative access schemes based on the equipment allowance of the research grid; Compare and score several alternative access solutions in terms of implementation difficulty and economic feasibility.
7. A PSD-BPA planning scheme comparison and selection system, characterized in that: include: Data acquisition module: used to determine the required data for alternative access schemes based on the BPA flow and stability data of the research grid; Calculation result module: used to modify and run the required data of the alternative access scheme and obtain the calculation results of several alternative access schemes; Result comparison module: used to compare the calculation results of several alternative access solutions to obtain the optimal access solution.
8. An electronic device, characterized in that: The method comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps of a PSD-BPA planning scheme comparison method as described in any one of claims 1 to 6 when executing the computer program.
9. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of a PSD-BPA planning scheme comparison method according to any one of claims 1 to 6 are implemented.
10. A computer program product, characterized in that It includes computer instructions, which, when executed by a processor, implement the steps of a PSD-BPA planning scheme comparison method as described in any one of claims 1 to 6.