Online project cooperative work system and method

Through the online project collaborative working system, topological sorting algorithm and multi-module data interoperability are used to solve the problems of untimely update of information and unreasonable resource allocation in traditional project management, and the efficiency of task allocation and information timeliness are achieved.

CN119090421APending Publication Date: 2024-12-06ANHUI SYMBIOSIS PUBLIC SERVICE SUPPLY CHAIN TECH RES INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411089621.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-09
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

Traditional project management methods have problems such as untimely update of information, unreasonable resource allocation, and cumbersome assessment processes, making it difficult to effectively monitor project progress and simplify resource allocation.

Method used

Design an online project collaborative working system, adopt topological sorting algorithm for task allocation, combine project creation and management modules, project monitoring modules, task allocation modules, resource calendar modules and efficiency evaluation modules to realize automated task allocation and resource optimization, breaking information Barriers to improve information timeliness.

Benefits of technology

The rationality and efficiency of task allocation are achieved, and through multi-module data interoperability, information timeliness and real-time evaluation and adjustment of work efficiency are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119090421A_ABST
    Figure CN119090421A_ABST
Patent Text Reader

Abstract

The invention discloses an online project cooperative work system and method, and belongs to the technical field of information. The system comprises a project creation and management module which is used for creating a new project according to a project demand and performing project management according to a project list of the new project; the project monitoring module is used for checking and updating the project progress and the use state of resources in real time; the task allocation module is used for performing task allocation on the project by adopting a topological sorting algorithm according to the dependency relationship between the project level and the function point; the conflict detection and adjustment module is used for checking time conflict and overload conditions of new tasks and adjusting task allocation according to the conditions; and the resource calendar module is used for displaying the availability of the resources. According to the method, task allocation can be automatically optimized according to factors such as skills of team members, current workloads and task emergency degrees, and reasonability and high efficiency of task allocation are ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of information technology, and in particular to an online project collaborative work system and method. Background Art

[0002] In the process of project management, how to effectively monitor project progress, rationally allocate development resources, and simplify the assessment process are the keys to improving project management efficiency.

[0003] Traditional project management methods often rely on manual operations, and there are problems such as untimely information updates, unreasonable resource allocation, and cumbersome assessment processes. Therefore, it is of great significance to develop a project management system that can achieve online collaborative work, automatically monitor project progress, intelligently allocate development resources, and simplify the assessment process. Summary of the invention

[0004] The purpose of the present invention is to provide an online project collaborative work system and method, which can automatically optimize task allocation according to factors such as team members' skills, current workload, task urgency, etc., to ensure the rationality and efficiency of task allocation.

[0005] In order to achieve the above object, the present invention adopts the following technical solutions:

[0006] In a first aspect, the present invention provides an online project collaborative work system, comprising:

[0007] A project creation and management module, used to create new projects according to project requirements and perform project management according to the project list of the new projects;

[0008] Project monitoring module, used to view and update project progress and resource usage status in real time;

[0009] The task allocation module is used to allocate tasks to projects using a topological sorting algorithm based on the project level and the dependencies between function points;

[0010] Conflict detection and adjustment module, used to check the time conflict and overload of new tasks, and adjust the task allocation according to the situation;

[0011] Resource calendar module, used to display resource availability.

[0012] In combination with the first aspect, preferably, the system further includes:

[0013] Efficiency evaluation module: used to collect data to calculate and display efficiency coefficients, and to conduct performance evaluation and improvement based on the data and efficiency coefficients.

[0014] In combination with the first aspect, preferably, the system further includes:

[0015] My Workbench module, which integrates personal performance indicators and task management functions.

[0016] In combination with the first aspect, preferably, the task allocation module is further configured to:

[0017] Determine whether the function points have dependencies and adopt a parallel processing mechanism for the execution of system tasks, first executing the tasks assigned to those that have no dependencies or whose dependencies have been met.

[0018] In combination with the first aspect, preferably, the conflict detection and adjustment module is specifically configured to:

[0019] When resources are assigned to multiple tasks at the same time in a certain time period, that is, the daily work limit of the resources is exceeded, the system will continue to automatically adjust the tasks and assign them to the next appropriate time period.

[0020] In combination with the first aspect, preferably, the project creation and management module includes:

[0021] A new unit is created on the project interface to receive user input of project name, project manager, customer, project attributes and project level;

[0022] The project allocation table generation unit is used to create a project allocation table based on project requirements and to clarify the responsibilities and tasks of each member.

[0023] In combination with the first aspect, preferably, the project creation interface unit is further configured to:

[0024] Receive key project time nodes input by the user, where the key project time nodes include project establishment time nodes, plan demand review time nodes, plan design review time nodes, plan launch review time nodes, and plan acceptance time nodes.

[0025] In combination with the first aspect, preferably, the project progress includes at least: the development progress status of each task, the progress ratio and the statistics of overtime delay days.

[0026] In a second aspect, the present invention provides an online project collaborative work method, the method comprising the following steps:

[0027] Project creation and management: creating new projects according to project requirements and managing projects according to the project list of the new projects;

[0028] Project monitoring and task allocation: real-time viewing and updating of project progress and resource usage status; using topological sorting algorithms to allocate tasks to projects based on project levels and dependencies between function points;

[0029] Conflict detection and adjustment: check the time conflicts and overloads of new tasks and adjust the task allocation accordingly;

[0030] Resource management and efficiency evaluation, dynamically adjust task allocation according to resource availability and project needs, collect data to calculate and display efficiency coefficients, and conduct performance evaluation and improvement based on data and efficiency coefficients.

[0031] In conjunction with the second aspect, preferably, the project creation and management specifically includes the following steps:

[0032] A new project interface receives the project name, project manager, customer, project attributes and project level input by the user, as well as the key project time nodes input by the user, wherein the key project time nodes include the project establishment time node, the planned demand review time node, the planned design review time node, the planned online review time node and the planned acceptance time node;

[0033] Generate a project allocation table, create a project allocation table based on project requirements, and clarify the responsibilities and tasks of each member.

[0034] Compared with the prior art, the present invention has the following beneficial effects:

[0035] 1. The present invention introduces an intelligent task allocation algorithm, namely a topological sorting algorithm, which can automatically optimize task allocation according to factors such as team members' skills, current workload, and task urgency, thereby ensuring the rationality and efficiency of task allocation.

[0036] 2. The present invention realizes data interoperability through multiple modules such as project creation and management module, project monitoring module, task allocation module, resource calendar module, etc., breaking down the information barriers between different departments or teams, allowing team members to obtain all project-related information in one stop, thereby improving the timeliness of information.

[0037] 3. The present invention can obtain its own work efficiency in real time and intuitively through the efficiency evaluation module and the my workbench module, which is conducive to adjusting its own working status. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 The figure is a schematic diagram of the system structure in an embodiment of the present invention;

[0039] Figure 2 The figure is a schematic diagram of a project creation and management module in an embodiment of the present invention;

[0040] Figure 3 Shown is a schematic diagram of a process in an embodiment of the present invention; DETAILED DESCRIPTION

[0041] The present invention will be further described below in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and cannot be used to limit the protection scope of the present invention.

[0042] Example 1

[0043] refer to Figures 1 to 3 The present invention provides an online project collaborative work system, comprising:

[0044] A project creation and management module, used to create new projects according to project requirements and perform project management according to the project list of the new projects;

[0045] Project monitoring module, used to view and update project progress and resource usage status in real time;

[0046] The task allocation module is used to allocate tasks to projects using a topological sorting algorithm based on the project level and the dependencies between function points;

[0047] Conflict detection and adjustment module, used to check the time conflict and overload of new tasks, and adjust the task allocation according to the situation;

[0048] Resource calendar module, used to display resource availability;

[0049] Efficiency evaluation module: used to collect data to calculate and display efficiency coefficients, and to conduct performance evaluation and improvement based on data and efficiency coefficients;

[0050] My Workbench module, which integrates personal performance indicators and task management functions.

[0051] 1. Project creation and management module

[0052] Among them, the project creation and management modules include:

[0053] 1. Create a new unit in the project interface to receive other basic information such as project name, project manager, customer, project attributes, project level, etc. entered by the user.

[0054] The project creation interface unit is further configured to:

[0055] Receive key project time nodes input by the user, where the key project time nodes include project establishment time nodes, plan demand review time nodes, plan design review time nodes, plan launch review time nodes, and plan acceptance time nodes.

[0056] 2. Project allocation table generation unit, used to create a project allocation table based on project requirements and clarify the responsibilities and tasks of each member.

[0057] 3. Project List

[0058] After creating a new project, the system displays a list of all maintained projects, where users can manage projects. The specific operations are as follows:

[0059] 3.1 The user enters the project list interface and views information such as project name, level, stage, DingTalk number, number of function points, total man-days, unused man-days, customers, project managers, members, and project progress.

[0060] 3.2 Users can select specific projects, view project details, modify project information, perform task assignment and progress management, and perform acceptance and other operations.

[0061] 4. Project details

[0062] Furthermore, the system interface also displays project details. On this interface, users can view and manage detailed project information. The specific functions are as follows:

[0063] 4.1 Displays basic information such as project name, project manager, project allocation plan, development phase function points, function point dependencies and task arrangements.

[0064] 4.2 Provide progress management function and support the export of task breakdown table.

[0065] Among them, the explanations of function points and function point dependencies are as follows.

[0066] Function point: A project development task consists of multiple function points, and each function point can have multiple sub-function points.

[0067] Function point dependency: Function point dependency means that a function point needs to wait for one or more other function points to be completed before entering the development phase. You can maintain multiple other function point dependencies in a function point. If you maintain a parent function point, you need to wait for all child function points under the parent to complete the task.

[0068] 2. Project Monitoring Module

[0069] 1. The project monitoring module is used to view and update the project progress and resource usage status in real time. The specific operations are as follows:

[0070] 1.1 Display the development progress status, progress ratio and overtime delay days of each task.

[0071] 1.2 Display the task execution status of each project member, including normal progress, unprocessed, delayed start, delayed end, timeout, not started and other status.

[0072] 1.3 If there are changes in the task schedule, the project manager can cancel the assignment and then re-assign it.

[0073] 3. Task Assignment Module

[0074] The task allocation module uses a specific task allocation algorithm to allocate tasks to the project according to the project level and the dependency relationship of the function points. In this embodiment, a topological sorting algorithm is used. The specific operation is as follows:

[0075] 1. Integrate the calendar information of project personnel for the next two weeks, mark each person's working days, rest days, statutory holidays and assigned project work tasks. Among them, statutory holidays are pre-included in the resource calendar and are automatically regarded as unassignable time.

[0076] 2. Task type definition: prototype design, front-end, back-end, testing, and other task types, and set the basic working hours for each task type (optional working hours are 0.25 days, 0.5 days, 0.75 days, and 1 day).

[0077] 3. Each project staff has entered their corresponding skills mastery level in the system (design, front-end development, back-end development, testing, etc.)

[0078] The task allocation module is further configured to:

[0079] 1. Determine whether the function points have dependencies and adopt a parallel processing mechanism for the execution of system tasks, first executing the tasks assigned to those that have no dependencies or whose dependencies have been met.

[0080] 2. The system should have an automatic check function to ensure that new tasks can be accommodated in the selected time period after the task type and personnel availability date selected by the project manager, without exceeding the limit of 1 day per day.

[0081] 3. Prioritize the best match between task type and personnel skills.

[0082] 4. If the task can be assigned, it will be automatically inserted into the earliest and appropriate time period according to the scheduled basic working hours of the task, and the personnel's resource calendar and workbench tasks will be updated at the same time.

[0083] 5. The system will automatically skip statutory holidays and scheduled task times.

[0084] 4. Conflict Detection and Adjustment Module

[0085] The conflict detection and adjustment module is used to check the time conflict and overload of new tasks, that is, to check whether the new tasks will cause time conflict or overload, and adjust the task allocation according to the situation. The specific situation is as follows:

[0086] 1. If a resource has been assigned too many tasks within a certain time period, exceeding its daily work limit, it will automatically search for the next most suitable free time period.

[0087] 2. If multiple tasks depend on the same resource at the same time, but the resources cannot be processed at the same time, prioritize or reallocate them.

[0088] 3. If automatic adjustment cannot meet all conditions, the project manager is prompted to make manual adjustments.

[0089] After the work tasks are assigned, the system will display the assignment results to the project manager in a visual way. The display content includes the assigned personnel, task name, task type, assigned time, expected completion time and other information of each task.

[0090] If you find that there is a problem or unreasonableness in the allocation of a task, you can manually adjust it or cancel the allocation. The allocation can only be canceled before the task is completed.

[0091] After assignment, the project manager can manually adjust the task schedule or assign it to other people, limited to unfinished tasks.

[0092] 5. Resource Calendar Module

[0093] The resource calendar module is used to display the availability of resources, that is, to display the work arrangements of team members, including the planned workload for the month, the daily resource arrangement list and other information. The specific operations include the following:

[0094] Departments, personnel, planned work content and project names (allocated work days, free man-days) are displayed on a daily basis.

[0095] The daily resource arrangement list uses different colors to distinguish whether the project team members are free, whether the work execution is normal, etc.

[0096] 6. Efficiency Evaluation Module

[0097] The efficiency evaluation module is designed to collect data to calculate and display the efficiency coefficient, that is, to display information such as the function points, workload, efficiency coefficient, etc. of all personnel in different assessment months. It supports exporting lists and viewing details, and then conducts performance evaluation and improvement based on the data and efficiency coefficient.

[0098] 7. My Workbench Module

[0099] My Workbench module is used to integrate personal performance indicators and task management functions. You can receive planned tasks in the task list, click Complete Task when the task is completed, and enter the actual start time and actual completion time. If there is a function point dependency, you need to wait until the dependent function point is completed before you can operate and receive the task.

[0100] The specific operations are: displaying information such as function points, workload, efficiency coefficient, etc. of all personnel in different assessment months, and supporting exporting lists and viewing details.

[0101] It should be noted that in addition to the modules mentioned above, the system can also have a demand creation module, a demand list module, a product maintenance module, an organization module, etc. These modules respectively implement the functions of demand management, product information management, organization and personnel account maintenance, etc. The specific operations and processes are similar to the above modules, and corresponding creation, editing, viewing and export operations can be performed according to actual needs.

[0102] Specifically, the command operations for creating the requirement module, requirement list module, product maintenance module, and organization module are as follows:

[0103] Create a demand module: maintain demand content, including demand title, product, customer and other information.

[0104] Requirements list module: displays all registered requirements, supports historical requirements import, requirements association / removal of projects and other functions.

[0105] Product maintenance module: maintain product information, including product name, product manager, product description and other information.

[0106] Organizational structure module: Maintenance of organizational structure and personnel accounts, including organization name, user name, department, and other information.

[0107] Example 2

[0108] refer to Figures 1 to 3 Based on Example 1, this embodiment of the present invention provides an online project collaborative work method, the method comprising the following steps:

[0109] Step 1: Project creation and management, creating a new project according to project requirements, and managing the project according to the project list of the new project;

[0110] Step 2: Project monitoring and task allocation: Check and update the project progress and resource usage status in real time, and use the topological sorting algorithm to allocate tasks to the project based on the project level and the dependency of function points;

[0111] Step 3: Conflict detection and adjustment, check the time conflict and overload of the new task, and adjust the task allocation according to the situation;

[0112] Step 4: Resource management and efficiency assessment, dynamically adjust task allocation according to resource availability and project needs, collect data to calculate and display efficiency coefficients, and conduct performance evaluation and improvement based on data and efficiency coefficients.

[0113] Among them, in step 1, the project creation and management specifically includes the following steps:

[0114] Step 11: Create a new project interface, receive the project name, project manager, customer, project attributes and project level input by the user, and receive the key time nodes of the project input by the user, wherein the key time nodes of the project include the project establishment time node, the plan demand review time node, the plan design review time node, the plan launch review time node and the plan acceptance time node;

[0115] Step 12: Generate a project allocation table. Create a project allocation table based on project requirements and clarify the responsibilities and tasks of each member.

[0116] In summary, the present invention provides an online project collaborative work system and method, which can automatically optimize task allocation according to factors such as team member skills, current workload, and task urgency by introducing an intelligent task allocation algorithm, namely a topological sorting algorithm, to ensure the rationality and efficiency of task allocation. Specifically, data intercommunication is achieved through multiple modules such as project creation and management modules, project monitoring modules, task allocation modules, and resource calendar modules, breaking down information barriers between different departments or teams, so that team members can obtain all project-related information in one stop, thereby improving the timeliness of information.

[0117] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. An online project collaborative work system, characterized in that: include: A project creation and management module, used to create new projects according to project requirements and perform project management according to the project list of the new projects; Project monitoring module, used to view and update project progress and resource usage status in real time; The task allocation module is used to allocate tasks to projects using a topological sorting algorithm based on the project level and the dependencies between function points; Conflict detection and adjustment module, used to check the time conflict and overload of new tasks, and adjust the task allocation according to the situation; Resource calendar module, used to display resource availability.

2. The online project collaborative work system according to claim 1, characterized in that: Also includes: Efficiency evaluation module: used to collect data to calculate and display efficiency coefficients, and to conduct performance evaluation and improvement based on the data and efficiency coefficients.

3. The online project collaborative work system according to claim 1, characterized in that: Also includes: My Workbench module, which integrates personal performance indicators and task management functions.

4. The online project collaborative work system according to claim 1, characterized in that: The task allocation module is further configured to: Determine whether the function points have dependencies and adopt a parallel processing mechanism for the execution of system tasks, first executing the tasks assigned to those that have no dependencies or whose dependencies have been met.

5. The online project collaborative work system according to claim 1, characterized in that: The conflict detection and adjustment module is specifically configured to: When resources are assigned to multiple tasks at the same time in a certain time period, exceeding the daily work limit of the resources, the system will continue to automatically adjust the tasks and assign them to the next appropriate space time period.

6. The online project collaborative work system according to claim 1, characterized in that: The project creation and management module includes: A new unit is created on the project interface to receive user input of project name, project manager, customer, project attributes and project level; The project allocation table generation unit is used to create a project allocation table based on project requirements and to clarify the responsibilities and tasks of each member.

7. The online project collaborative work system according to claim 6, characterized in that: The project creation interface unit is further configured to: Receive key project time nodes input by the user, where the key project time nodes include project establishment time nodes, plan demand review time nodes, plan design review time nodes, plan launch review time nodes, and plan acceptance time nodes.

8. The online project collaborative work system according to claim 1, characterized in that: The project progress includes at least: the development progress status of each task, the progress ratio and the statistics of overtime delay days.

9. An online project collaborative working method, characterized in that: Based on the online project collaborative work system according to any one of claims 1 to 8, the method comprises the following steps: Step 1: Project creation and management: create a new project according to project requirements, and manage the project according to the project list of the new project; Step 2: Project monitoring and task allocation: Check and update the project progress and resource usage status in real time, and use the topological sorting algorithm to allocate tasks to the project based on the project level and the dependency of function points; Step 3: Conflict detection and adjustment: check the time conflict and overload of the new task, and adjust the task allocation according to the situation; Step 4: Resource calendar and efficiency evaluation, dynamically adjust task assignments based on resource availability and project requirements, collect data to calculate and display efficiency coefficients, and conduct performance evaluation and improvement based on data and efficiency coefficients.

10. The online project collaborative working method according to claim 9, characterized in that: The project creation and management specifically include the following steps: Step 11: Create a new project interface, receive the project name, project manager, customer, project attributes and project level input by the user, and receive the key time nodes of the project input by the user, wherein the key time nodes of the project include the project establishment time node, the planned demand review time node, the planned design review time node, the planned online review time node and the planned acceptance time node; Step 12: Generate a project allocation table. Create a project allocation table based on project requirements and clarify the responsibilities and tasks of each member.