Coating weight determination and alarm method and device, medium and electronic equipment

By calculating the coating liquid consumption and the oversteer area of ​​the strip steel, combined with the drying ratio coefficient, the coating amount of the strip steel is determined, which solves the problem of too thick or too thin coating and ensures the quality of the coating.

CN119114382APending Publication Date: 2024-12-13SHOUGANG ZHIXIN QIAN AN ELECTROMAGNETIC MATERIALS CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411165230.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-23
Publication Date
2024-12-13

AI Technical Summary

Technical Problem

Existing strip continuous coating machines are difficult to accurately determine the coating application amount, resulting in too thick or too thin coating, affecting the quality of welding and striping.

Method used

By obtaining the inner bottom area of ​​the coating liquid circulation tank, the coating liquid density, the strip speed, the strip width and the drying ratio coefficient, the coating liquid consumption and the strip steel over the steel area, and then the coating coating amount is determined. And averaged based on the data measured multiple times to reduce the impact of abnormal data.

Benefits of technology

Accurate control of the coating amount of strip steel coating is achieved, and the coating thickness is discovered and adjusted in a timely manner to ensure the coating quality and avoid the coating being too thick or too thin.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119114382A_ABST
    Figure CN119114382A_ABST
Patent Text Reader

Abstract

The invention discloses a coating weight determination and alarm method and device, a medium and electronic equipment. The determination method comprises the steps that the inner bottom area of a coating liquid circulation tank, the coating liquid density, the strip steel speed, the strip steel width, the target time period and the corresponding drying ratio coefficient when coating liquid becomes a coating after being dried through a drying furnace are obtained; determining the liquid level variation of the coating liquid circulating tank in the target time period; according to the inner bottom area, the coating liquid density and the liquid level variation, the coating liquid consumption is determined; according to the strip steel speed, the strip steel width and the target time period, the strip steel passing area is determined; and determining the coating weight of the first strip steel coating according to the coating liquid consumption, the strip steel passing area and the drying ratio coefficient. The method can determine the coating weight of the strip steel coating.
Need to check novelty before this filing date? Find Prior Art

Description

Background Art

[0002] The strip continuous coating unit mainly includes a coating machine, a coating liquid circulation tank, a circulation pump and a drying furnace, wherein the coating machine includes a coating roller, a spray beam and a liquid collecting tank, the coating machine is located above the coating liquid circulation tank, the spray beam is connected to the coating liquid circulation tank through a circulation pump, the liquid collecting tank is located below the spray beam and the coating roller, and the liquid collecting tank is connected to the coating liquid circulation tank by a pipeline, after the strip enters the coating machine, the coating liquid enters the spray beam from the coating liquid circulation tank under the action of the circulation pump, and the coating liquid is sprayed from the spray beam to the upper and lower surfaces of the strip, and then the coating roller applies the coating liquid to the strip, and the excess coating liquid falls from the upper and lower surfaces of the strip into the liquid collecting tank, and then returns to the coating liquid circulation tank through the pipeline.

[0003] If the coating amount of the steel strip is too thick, bubbles are likely to appear during welding, and the coating is likely to fall off during stripping, resulting in unqualified products. If the coating amount of the steel strip is too thin, the coating resistance and thickness are difficult to meet actual needs. Therefore, a method for determining the coating amount of the steel strip is urgently needed to detect abnormal conditions of the coating amount of the steel strip in a timely manner. Summary of the invention

[0004] The embodiments of the present application provide a coating coating amount determination and alarm method, device, medium, and electronic device, which can determine the coating coating amount of a steel strip.

[0005] Other features and advantages of the present application will become apparent from the following detailed description, or may be learned in part by the practice of the present application.

[0006] According to a first aspect of the present application, a method for determining a coating amount is provided, which is applied to a steel strip and comprises:

[0007] Obtain the inner bottom area of ​​the coating liquid circulation tank, the coating liquid density, the strip speed, the strip width, the target time period, and the drying ratio coefficient corresponding to when the coating liquid is dried in the drying furnace and becomes a coating;

[0008] Determine the change in the liquid level of the coating liquid circulation tank within the target time period;

[0009] Determining the coating liquid consumption according to the inner bottom area, the coating liquid density and the liquid level change;

[0010] Determining a strip steel passing area according to the strip steel speed, the strip steel width and the target time period;

[0011] The coating amount of the first steel strip coating is determined according to the coating liquid consumption, the steel strip passing area and the drying ratio coefficient.

[0012] In some embodiments of the present application, based on the above solution, it also includes:

[0013] The second strip coating amount is determined according to at least three of the first strip coating amounts.

[0014] In some embodiments of the present application, based on the above solution, determining the second strip coating amount according to at least three first strip coating amounts includes:

[0015] Determine at least three maximum, minimum and first sum values ​​of the coating amounts of the first steel strip coating;

[0016] determining a second sum of the maximum value and the minimum value;

[0017] Determine a first difference between the first sum and the second sum and a second difference between the first strip coating amount and the corresponding quantity 2;

[0018] The coating amount of the second steel strip coating is determined according to a first quotient of the first difference and the second difference.

[0019] In some embodiments of the present application, based on the above solution, determining the coating liquid consumption according to the inner bottom area, the coating liquid density and the liquid level change includes:

[0020] The coating liquid consumption is determined according to the product of the inner bottom area, the coating liquid density and the liquid level change.

[0021] In some embodiments of the present application, based on the above solution, determining the strip passing area according to the strip speed, the strip width and the target time period includes:

[0022] Determine the single-side strip steel passing area according to the product of the strip steel speed, the strip steel width and the corresponding time length of the target time period;

[0023] The strip steel passing area is determined according to the product of the single-sided strip steel passing area and 2.

[0024] In some embodiments of the present application, based on the above scheme, determining the coating amount of the first strip steel coating according to the coating liquid consumption, the strip steel passing area and the drying ratio coefficient includes:

[0025] Determining a second quotient value based on the coating liquid consumption and the strip steel passing area;

[0026] The coating amount of the first steel strip coating is determined according to the product of the second quotient and the drying ratio coefficient.

[0027] According to a second aspect of the present application, a coating amount alarm method is provided, comprising:

[0028] Determine the coating amount of the first steel strip coating according to a coating amount determination method according to any embodiment of the first aspect of the present application;

[0029] Whether to alarm is determined according to the coating amount of the first steel strip coating and the target value.

[0030] In some embodiments of the present application, based on the above solution, determining whether to alarm according to the coating amount of the first steel strip coating and the target value includes:

[0031] Determine a first threshold and a second threshold according to the target value, wherein the first threshold is greater than the second threshold;

[0032] If the coating amount of the first strip steel coating is less than or equal to the first threshold and greater than or equal to the second threshold, no alarm is given;

[0033] If the coating amount of the first steel strip coating is greater than the first threshold or less than the second threshold, an alarm is triggered.

[0034] According to a third aspect of the present application, a coating coating amount determination device is provided, comprising:

[0035] An acquisition unit is used to acquire the inner bottom area of ​​the coating liquid circulation tank, the coating liquid density, the strip speed, the strip width, the target time period, and the drying ratio coefficient corresponding to when the coating liquid is dried in the drying furnace and becomes the coating;

[0036] A first determination unit determines a change in the liquid level of the coating liquid circulation tank within a target time period;

[0037] A second determining unit determines the coating liquid consumption according to the inner bottom area, the coating liquid density and the liquid level change;

[0038] A third determination unit determines a strip steel passing area according to the strip steel speed, the strip steel width and the target time period;

[0039] The fourth determining unit determines the coating amount of the first steel strip according to the coating liquid consumption, the steel strip passing area and the drying ratio coefficient.

[0040] According to a fourth aspect of the present application, a computer-readable storage medium is provided, on which a computer program is stored. The computer program includes executable instructions. When the executable instructions are executed by a processor, the method described in any one of the embodiments of the first aspect above is implemented.

[0041] According to the fifth aspect of the present application, an electronic device is provided, comprising: one or more processors; and a memory for storing executable instructions of the processors, wherein when the executable instructions are executed by the one or more processors, the one or more processors implement the method described in any one of the embodiments of the first aspect above.

[0042] The beneficial effects of this application are as follows:

[0043] On the one hand, the coating liquid consumption is determined according to the inner bottom area, the coating liquid density and the liquid level change, and on the other hand, the strip passing area is determined according to the strip speed, the strip width and the target time period; thus, the first strip coating amount is determined according to the coating liquid consumption, the strip passing area and the drying ratio coefficient, and then whether the strip coating is too thick or too thin is determined according to the first strip coating amount, so as to control the strip coating amount and ensure the strip coating quality.

[0044] It should be understood that the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the present application. BRIEF DESCRIPTION OF THE DRAWINGS

[0045] The drawings herein are incorporated into the specification and constitute a part of the specification, showing embodiments consistent with the present application, and together with the specification, are used to explain the principles of the present application. Obviously, the drawings described below are only some embodiments of the present application, and for ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. In the drawings:

[0046] Figure 1 A schematic diagram of a strip steel continuous coating unit is shown;

[0047] Figure 2 A flow chart of a method for determining a coating amount in an embodiment of the present application is shown;

[0048] Figure 3 A block diagram of a device for determining the operating trajectory of a ring cooler in an embodiment of the present application is shown;

[0049] Figure 4 A schematic diagram showing a computer-readable storage medium in an embodiment of the present application is shown;

[0050] Figure 5 A schematic diagram showing the system structure of an electronic device in an embodiment of the present application is shown. DETAILED DESCRIPTION

[0051] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0052] In addition, described feature, structure or characteristic can be combined in one or more embodiments in any suitable manner. In the following description, many specific details are provided to provide a full understanding of the embodiments of the present application. However, those skilled in the art will appreciate that the technical scheme of the present application can be put into practice without one or more of the specific details, or other methods, components, devices, steps, etc. can be adopted. In other cases, known methods, devices, realizations or operations are not shown or described in detail to avoid blurring the various aspects of the application.

[0053] The block diagrams shown in the accompanying drawings are merely functional entities and do not necessarily correspond to physically independent entities. That is, these functional entities may be implemented in software form, or in one or more hardware modules or integrated circuits, or in different networks and / or processor devices and / or microcontroller devices.

[0054] The flowcharts shown in the accompanying drawings are only exemplary and do not necessarily include all the contents and operations / steps, nor must they be executed in the order described. For example, some operations / steps can be decomposed, and some operations / steps can be combined or partially combined, so the actual execution order may change according to actual conditions.

[0055] In the description of this application, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the feature. In the description of this application, unless otherwise specified, "plurality" means two or more.

[0056] Figure 1 shows a schematic diagram of a strip steel continuous coating unit, Figure 1 In the figure, the arrows correspond to the running direction of the strip steel, 1 is the spray beam, 2 is the coating machine, 3 is the coating roller, 4 is the drying furnace, 5 is the liquid collecting tank, 6 is the liquid level gauge, 7 is the coating liquid circulation tank, and 8 is the circulation pump. For a better understanding of the embodiments of the present application, see Figure 1 , the strip steel continuous coating unit is described:

[0057] The strip enters the coating machine, and the circulation pump transports the coating liquid in the coating liquid circulation tank to the spray beam. The spray beam allows the coating liquid to hit the upper and lower surfaces of the strip. The coating roller evenly applies the coating liquid to the upper and lower surfaces of the strip. The excess coating liquid falls into the liquid collecting tank and then flows back to the coating liquid circulation tank through the pipeline. The strip enters the drying furnace from the coating machine, and the drying furnace dries the strip. The coating liquid on the upper and lower surfaces of the strip becomes a coating.

[0058] Figure 2 A flow chart showing a method for determining a coating amount in an embodiment of the present application is shown, see Figure 2 , provides a coating amount determination method, applied to strip steel, including at least S1 to S5,:

[0059] In step S1, the inner bottom area of ​​the coating liquid circulation tank, the coating liquid density, the strip speed, the strip width, the target time period, and the drying ratio coefficient corresponding to the coating liquid after being dried in the drying furnace are obtained. The coating liquid circulation tank is used to store the coating liquid. The inner bottom area of ​​the coating liquid circulation tank refers to the bottom area of ​​the inner wall of the coating liquid circulation tank. The product of the inner bottom area and the height of the inner wall of the coating liquid circulation tank is the volume of the inner wall of the coating liquid circulation tank, that is, the volume of the coating liquid that can be stored in the coating liquid circulation tank. The coating liquid density refers to the density of the coating liquid. The strip speed refers to the speed of the strip passing through the coating machine. The strip width refers to the width of the strip perpendicular to the running direction of the strip. The target time period refers to the corresponding time period for determining the coating coating amount. The drying ratio coefficient refers to the ratio of the first mass of the coating liquid after being dried in the drying furnace to the second mass of the coating liquid before being dried in the drying furnace.

[0060] In some embodiments, obtaining the strip speed includes: obtaining the strip speed according to a rotary encoder of a tension roller, wherein the coating machine is located between the tension roller and a drying furnace, that is, the tension roller is located in front of the coating machine, and the drying furnace is located behind the coating machine.

[0061] In some embodiments, when obtaining the inner bottom area, it can be obtained through the parameters of the coating liquid circulation tank, or it can be obtained by measurement; when obtaining the coating liquid density, it can be obtained through the coating liquid parameters, or it can be obtained by measurement, such as by measuring the mass of the coating liquid per unit volume to measure the density of the coating liquid; when obtaining the strip width, it can be obtained through the strip parameters, or it can be obtained by measurement, such as by measuring with a tape measure; when obtaining the target time period, it can be set according to experience, or it can be set according to the strip speed, for example, the faster the strip speed, the shorter the target time period, so that the strip coating amount can be determined in time, or the target time period can be set to a fixed value.

[0062] In step S2, the amount of change in the liquid level of the coating liquid circulation tank within the target time period is determined. The target time period refers to the time period between the first time and the second time, wherein the first time is before the second time, and the amount of change in the liquid level refers to the amount of change in the liquid level of the coating liquid circulation tank corresponding to the second time relative to the liquid level of the coating liquid circulation tank corresponding to the first time, for example, if the liquid level of the coating liquid circulation tank corresponding to the second time is 60 cm and the liquid level of the coating liquid circulation tank corresponding to the first time is 62 cm, then the amount of change in the liquid level is 2 cm.

[0063] In some embodiments, the determination of the liquid level change of the coating liquid circulation tank within the target time period includes: using a liquid level detection device to detect a first liquid level of the coating liquid circulation tank at the start time point of the target time period and a second liquid level of the coating liquid circulation tank at the end time point of the target time period, that is, using a liquid level detection device to detect a first liquid level of the coating liquid circulation tank at a first time and a second liquid level of the coating liquid circulation tank at a second time; and determining the liquid level change according to the first liquid level and the second liquid level. The first time corresponds to the first liquid level, and the second time corresponds to the second liquid level.

[0064] In step S3, the coating liquid consumption is determined according to the inner bottom area, the coating liquid density and the liquid level change. The coating liquid consumption refers to the consumption of the coating liquid within the target time period.

[0065] In step S4, the strip passing area is determined according to the strip speed, the strip width and the target time period. The strip passing area refers to the area of ​​the strip passing through the coating machine within the target time period.

[0066] In step S5, the first strip coating amount is determined according to the coating liquid consumption, the strip passing area and the drying ratio coefficient. The first strip coating amount refers to the coating amount per unit area of ​​the strip within the target time period.

[0067] In some embodiments, the method further includes: determining a second steel strip coating amount according to at least three of the first steel strip coating amounts. The at least three first steel strip coating amounts may be first steel strip coating amounts corresponding to at least three consecutive target time periods. Determining the second steel strip coating amount according to multiple first steel strip coating amounts can reduce the impact of abnormal data on the coating amount, and the coating amount can be determined with higher accuracy.

[0068] In some embodiments, the determining of the second steel strip coating amount according to at least three of the first steel strip coating amounts includes: determining the maximum value, the minimum value and the first sum of at least three of the first steel strip coating amounts; determining the second sum of the maximum value and the minimum value; determining the first difference between the first sum and the second sum and the second difference between the corresponding number of the first steel strip coating amount and 2; determining the second steel strip coating amount according to the first quotient of the first difference and the second difference. Remove the maximum value and the minimum value of the at least three first steel strip coating amounts, and then determine the average value of the remaining first steel strip coating amounts, so as to determine the second steel strip coating amount. Removing the maximum value and the minimum value can be understood as removing abnormal data, so as to determine the coating amount with higher accuracy.

[0069] In some embodiments, determining the coating liquid consumption according to the inner bottom area, the coating liquid density and the liquid level change includes: determining the coating liquid consumption according to the product of the inner bottom area, the coating liquid density and the liquid level change. The product of the inner bottom area and the liquid level change is the volume of the consumed coating liquid, and the coating liquid consumption is the product of the volume of the consumed coating liquid and the coating liquid density, that is, the mass of the consumed coating liquid.

[0070] In some embodiments, the determining of the strip passing area according to the strip speed, the strip width and the target time period includes: determining the single-sided strip passing area according to the product of the strip speed, the strip width and the corresponding time length of the target time period; determining the strip passing area according to the product of the single-sided strip passing area and 2. The single-sided strip passing area refers to the area of ​​the upper surface of the strip or the lower surface of the strip passing the coating machine. Since the area of ​​the upper surface of the strip passing the coating machine is the same as the area of ​​the lower surface of the strip passing the coating machine, the single-sided strip passing area multiplied by 2 is the strip passing area.

[0071] In some embodiments, determining the first strip coating amount based on the coating liquid consumption, the strip passing area and the drying ratio coefficient includes: determining a second quotient based on the coating liquid consumption and the strip passing area; determining the first strip coating amount based on the product of the second quotient and the drying ratio coefficient.

[0072] In some embodiments, the formula for determining the coating amount of the first strip coating is as follows: T = k*(ρ*S*Δh) / (2*v*Δt*W), wherein T is the coating amount of the first strip coating, ρ is the coating liquid density, S is the inner bottom area, Δh is the change in the strip liquid level, v is the strip speed, Δt is the duration corresponding to the target time period, and W is the strip width.

[0073] In some embodiments, the unit of k is %, the unit of T is g / m3, the unit of ρ is g / cm3, and the unit of S is m 2 , Δh is in m, v is in m / min, Δt is in s, and W is in mm, the formula for determining the coating amount of the first strip steel is as follows: T = k*6*10 10 *(ρ*S*Δh) / (2*v*Δt*W).

[0074] According to a second aspect of the present application, a coating amount alarm method is provided, comprising:

[0075] Determine the coating amount of the first steel strip coating according to a coating amount determination method according to any embodiment of the first aspect of the present application;

[0076] Whether to alarm is determined according to the coating amount of the first steel strip coating and the target value.

[0077] In some embodiments, determining whether to alarm based on the first steel strip coating amount and the target value includes: determining a first threshold value and a second threshold value based on the target value, wherein the first threshold value is greater than the second threshold value; if the first steel strip coating amount is less than or equal to the first threshold value and greater than or equal to the second threshold value, no alarm is issued; if the first steel strip coating amount is greater than the first threshold value or less than the second threshold value, an alarm is issued.

[0078] In some embodiments, determining whether to alarm based on the coating amount of the second steel strip and the target value includes: determining a first threshold and a second threshold based on the target value, wherein the first threshold is greater than the second threshold; if the coating amount of the second steel strip is less than or equal to the first threshold and greater than or equal to the second threshold, no alarm is issued; if the coating amount of the second steel strip is greater than the first threshold or less than the second threshold, an alarm is issued.

[0079] When the first coating amount or the second coating amount is not between the first threshold and the second threshold, an alarm is given, that is, the strip coating amount does not meet the requirements and needs to be adjusted. When the strip coating amount is too little, that is, the strip coating is too thin, the coating roller pressure can be reduced, and when the strip coating amount is too much, that is, the strip coating is too thick, the coating roller pressure can be increased.

[0080] In some embodiments, determining the first threshold and the second threshold based on the target value includes: obtaining a threshold percentage; determining a threshold product of the target value and the threshold percentage; determining the first threshold based on the sum of the target value and the threshold product; determining the second threshold based on the difference between the target value and the threshold product.

[0081] In the present application, on the one hand, the coating liquid consumption is determined according to the inner bottom area, the coating liquid density and the liquid level change, and on the other hand, the strip passing area is determined according to the strip speed, the strip width and the target time period; thereby, the first strip coating amount is determined according to the coating liquid consumption, the strip passing area and the drying ratio coefficient, and then according to the first strip coating amount, it is determined whether the strip coating is too thick or too thin, so as to control the strip coating amount and ensure the strip coating quality.

[0082] Figure 3 A block diagram of a device for determining the operating trajectory of a ring cooler in an embodiment of the present application is shown, see Figure 3 According to a third aspect of the present application, a coating coating amount determination device 100 is provided, comprising:

[0083] An acquisition unit 101 acquires the inner bottom area of ​​the coating liquid circulation tank, the coating liquid density, the strip speed, the strip width, the target time period, and the drying ratio coefficient corresponding to the coating after the coating liquid is dried in the drying furnace;

[0084] A first determining unit 102 determines a change in the liquid level of the coating liquid circulation tank within a target time period;

[0085] A second determining unit 103 determines the coating liquid consumption according to the inner bottom area, the coating liquid density and the liquid level change;

[0086] A third determining unit 104 determines a strip passing area according to the strip speed, the strip width and the target time period;

[0087] The fourth determining unit 105 determines the coating amount of the first steel strip coating according to the coating liquid consumption, the steel strip passing area and the drying ratio coefficient.

[0088] Based on the same inventive concept, as a fourth aspect, the present application also provides a computer-readable storage medium on which is stored a program product capable of implementing the above-mentioned method for determining the coating amount of the present specification. In some possible implementations, various aspects of the present application can also be implemented in the form of a program product, which includes a program code, and when the program product is run on a terminal device, the program code is used to enable the terminal device to execute the steps according to various exemplary implementations of the present application described in the above-mentioned "Exemplary Method" section of the present specification.

[0089] refer to Figure 4 As shown, a program product 200 for implementing the above method according to an embodiment of the present application is described, which can adopt a portable compact disk read-only memory (CD-ROM) and include program code, and can be run on a terminal device, such as a personal computer. However, the program product of the present application is not limited thereto. In this document, a readable storage medium can be any tangible medium containing or storing a program, which can be used by or in combination with an instruction execution system, an apparatus or a device.

[0090] The program product may use any combination of one or more readable media. The readable medium may be a readable signal medium or a readable storage medium. The readable storage medium may be, for example, but not limited to, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device or device, or any combination of the above. More specific examples (non-exhaustive list) of readable storage media include: an electrical connection with one or more wires, a portable disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above.

[0091] Computer readable signal media may include data signals propagated in baseband or as part of a carrier wave, in which readable program code is carried. Such propagated data signals may take a variety of forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination of the above. Readable signal media may also be any readable medium other than a readable storage medium, which may send, propagate, or transmit a program for use by or in conjunction with an instruction execution system, apparatus, or device.

[0092] The program code embodied on the readable medium may be transmitted using any appropriate medium, including but not limited to wireless, wired, optical cable, RF, etc., or any suitable combination of the foregoing.

[0093] Program code for performing the operations of the present application may be written in any combination of one or more programming languages, including object-oriented programming languages ​​such as Java, C++, etc., and conventional procedural programming languages ​​such as "C" or similar programming languages. The program code may be executed entirely on the user computing device, partially on the user device, as a separate software package, partially on the user computing device and partially on a remote computing device, or entirely on a remote computing device or server. In the case of a remote computing device, the remote computing device may be connected to the user computing device through any type of network, including a local area network (LAN) or a wide area network (WAN), or may be connected to an external computing device (e.g., using an Internet service provider to connect through the Internet).

[0094] As another aspect, the present application also provides an electronic device capable of implementing the above method.

[0095] Those skilled in the art will appreciate that various aspects of the present application may be implemented as a system, method or program product. Therefore, various aspects of the present application may be specifically implemented in the following forms, namely: a complete hardware implementation, a complete software implementation (including firmware, microcode, etc.), or a combination of hardware and software, which may be collectively referred to as "circuit", "module" or "system" herein.

[0096] Refer to the following Figure 5 The electronic device 300 according to this embodiment of the present application is described. Figure 5 The electronic device 300 shown is merely an example and should not bring any limitation to the functions and scope of use of the embodiments of the present application.

[0097] like Figure 5 As shown, the electronic device 300 is in the form of a general computing device. The components of the electronic device 300 may include but are not limited to: at least one processing unit 310, at least one storage unit 320, and a bus 330 connecting different system components (including the storage unit 320 and the processing unit 310).

[0098] The storage unit stores program codes, which can be executed by the processing unit 310, so that the processing unit 310 executes the steps described in the above “Example Method” section of this specification according to various exemplary implementations of the present application.

[0099] The storage unit 320 may include a readable medium in the form of a volatile storage unit, such as a random access memory unit (RAM) 321 and / or a cache memory unit 322 , and may further include a read-only memory unit (ROM) 323 .

[0100] The storage unit 320 may also include a program / utility 324 having a set (at least one) of program modules 325, such program modules 325 including but not limited to: an operating system, one or more application programs, other program modules, and program data, each of which or some combination may include an implementation of a network environment.

[0101] Bus 330 may represent one or more of several types of bus structures, including a memory unit bus or memory unit controller, a peripheral bus, an accelerated graphics port, a processing unit, or a local bus using any of a variety of bus architectures.

[0102] The electronic device 300 may also communicate with one or more external devices 400 (e.g., keyboards, pointing devices, Bluetooth devices, etc.), one or more devices that enable a user to interact with the electronic device 300, and / or any device that enables the electronic device 300 to communicate with one or more other computing devices (e.g., routers, modems, etc.). Such communication may be performed through an input / output (I / O) interface 350. Furthermore, the electronic device 300 may also communicate with one or more networks (e.g., a local area network (LAN), a wide area network (WAN), and / or a public network, such as the Internet) through a network adapter 360. Figure 5 As shown, the network adapter 360 communicates with other modules of the electronic device 300 via the bus 330. It should be understood that, although not shown in the figure, other hardware and / or software modules can be used in conjunction with the electronic device 300, including but not limited to: microcode, device drivers, redundant processing units, external disk drive arrays, RAID systems, tape drives, and data backup storage systems.

[0103] The functions described herein may be implemented in hardware, software executed by a processor, firmware, or any combination thereof. If implemented in software executed by a processor, the functions may be stored as one or more instructions or codes on a computer-readable medium or transmitted via a computer-readable medium. Other examples and implementations are within the scope and spirit of the present application and the appended claims. For example, due to the nature of software, the functions described above may be implemented using software executed by a processor, hardware, firmware, hard wiring, or a combination of any of these. In addition, each functional unit may be integrated into a processing unit, each unit may exist physically separately, or two or more units may be integrated into one unit.

[0104] In the several embodiments provided in this application, it should be understood that the disclosed technical content can be implemented in other ways. Among them, the device embodiments described above are only schematic. For example, the division of the units can be a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of units or modules, which can be electrical or other forms.

[0105] The units described as separate components may or may not be physically separated, and the components of the control device may or may not be physical units, that is, they may be located in one place or distributed in multiple units. Some or all of the units may be selected according to actual needs to achieve the purpose of the present embodiment.

[0106] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application can be essentially or partly or all or partly embodied in the form of a software product that contributes to the prior art. The computer software product is stored in a storage medium, including several instructions for a computer device (which can be a personal computer, server or network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present application. The aforementioned storage medium includes: U disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), mobile hard disk, disk or optical disk, etc., which can store program code.

[0107] The above description is only an embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent substitution, improvement, etc. made within the spirit and principle of the present application shall be included in the scope of the claims of the present application.

Claims

1. A method for determining the amount of coating applied to a steel strip, characterized in that: include: Obtain the inner bottom area of ​​the coating liquid circulation tank, the coating liquid density, the strip speed, the strip width, the target time period, and the drying ratio coefficient corresponding to when the coating liquid is dried in the drying furnace and becomes a coating; Determine the change in the liquid level of the coating liquid circulation tank within the target time period; Determining the coating liquid consumption according to the inner bottom area, the coating liquid density and the liquid level change; Determining a strip steel passing area according to the strip steel speed, the strip steel width and the target time period; The coating amount of the first steel strip coating is determined according to the coating liquid consumption, the steel strip passing area and the drying ratio coefficient.

2. A method for determining a coating amount according to claim 1, characterized in that: Also includes: The second strip coating amount is determined according to at least three of the first strip coating amounts.

3. A method for determining a coating amount according to claim 2, characterized in that: The determining the second strip coating amount according to at least three of the first strip coating amounts comprises: Determine at least three maximum, minimum and first sum values ​​of the coating amounts of the first steel strip coating; determining a second sum of the maximum value and the minimum value; Determine a first difference between the first sum and the second sum and a second difference between the first strip coating amount and the corresponding quantity 2; The coating amount of the second steel strip coating is determined according to a first quotient of the first difference and the second difference.

4. A method for determining a coating amount according to claim 1, characterized in that: Determining the coating liquid consumption according to the inner bottom area, the coating liquid density and the liquid level change includes: The coating liquid consumption is determined according to the product of the inner bottom area, the coating liquid density and the liquid level change.

5. A method for determining a coating amount according to claim 1, characterized in that: Determining the strip passing area according to the strip speed, the strip width and the target time period includes: Determine the single-side strip steel passing area according to the product of the strip steel speed, the strip steel width and the corresponding time length of the target time period; The strip steel passing area is determined according to the product of the single-sided strip steel passing area and 2.

6. A method for determining a coating amount according to claim 1, characterized in that: Determining the coating amount of the first steel strip coating according to the coating liquid consumption, the steel strip passing area and the drying ratio coefficient includes: Determining a second quotient value based on the coating liquid consumption and the strip steel passing area; The coating amount of the first steel strip coating is determined according to the product of the second quotient and the drying ratio coefficient.

7. A coating coating amount alarm method, characterized in that: include: According to a coating coating amount determination method according to any one of claims 1 to 6, determining the coating amount of the first steel strip coating; Whether to alarm is determined according to the coating amount of the first steel strip coating and the target value.

8. A coating coating amount alarm method according to claim 7, characterized in that: The determining whether to alarm according to the coating amount of the first steel strip coating and the target value comprises: Determine a first threshold and a second threshold according to the target value, wherein the first threshold is greater than the second threshold; If the coating amount of the first strip steel coating is less than or equal to the first threshold and greater than or equal to the second threshold, no alarm is given; If the coating amount of the first steel strip coating is greater than the first threshold or less than the second threshold, an alarm is triggered.

9. A coating coating amount determination device, characterized in that: include: An acquisition unit is used to acquire the inner bottom area of ​​the coating liquid circulation tank, the coating liquid density, the strip speed, the strip width, the target time period, and the drying ratio coefficient corresponding to when the coating liquid is dried in the drying furnace and becomes the coating; A first determination unit determines a change in the liquid level of the coating liquid circulation tank within a target time period; A second determining unit determines the coating liquid consumption according to the inner bottom area, the coating liquid density and the liquid level change; A third determination unit determines a strip steel passing area according to the strip steel speed, the strip steel width and the target time period; The fourth determining unit determines the coating amount of the first steel strip according to the coating liquid consumption, the steel strip passing area and the drying ratio coefficient.

10. A computer-readable storage medium having a computer program stored thereon, characterized in that: The computer program includes executable instructions, and when the executable instructions are executed by a processor, the method described in any one of claims 1 to 6 is implemented.

Citation Information

Cited By

  • Gas consumption monitoring method, device and equipment and storage medium

    CN120734520A