Mineral resource exploration and analysis device and analysis method thereof
By designing a mineral resource exploration and analysis device, using a motor to drive the drilling barrel and electromagnetic emitter to insert it into the soil, the problems of transmitter insertion difficulties and structural deviations are solved, and efficient and accurate mineral resource exploration and analysis are achieved.
Patent Information
- Application Number
- CN202411411186.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-10
- Publication Date
- 2024-12-17
AI Technical Summary
During the existing magnetic emission geological survey, it is difficult for the transmitter to insert the soil and the location change leads to structural deviations in the exploration and analysis, affecting the accuracy of the exploration.
A mineral resource exploration and analysis device is designed, including an exploration box, a drilling barrel and an analysis mechanism. The drilling barrel is driven by a motor to rotate and insert it into the soil, and the electromagnetic emitter is inserted into the depths of the soil. The exploration and analysis are carried out using electromagnetic waves, and different depths are collected through the sampling box. Soil samples for improved accuracy.
The electromagnetic emitter is stably inserted into the soil, improving the accuracy and efficiency of exploration and analysis, and ensuring the accuracy of exploration structure.
Smart Images

Figure CN119148236A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of mineral resource exploration, and in particular to a mineral resource exploration and analysis device and an analysis method thereof. Background Art
[0002] Mineral resource exploration is the entire geological exploration work to discover mineral deposits and determine the distribution of ore bodies, mineral types, quality, quantity, mining and utilization conditions, technical and economic evaluation and application prospects, etc., to meet the needs of construction or mining. Mineral resources are buried underground and are rare, hidden and complex. The exploration process often requires the use of geological mapping, geophysical exploration, geochemical exploration, remote sensing geology and other methods, and the application of drilling, pit exploration and other technical means. It requires measurement, cataloging, sampling, testing, experiments, reserve calculations, technical and economic evaluation and feasibility studies, etc., which requires a lot of manpower, material and financial investment.
[0003] However, in the prior art, when magnetic transmitters are used for geological surveys, the transmitter cannot be easily inserted into the soil due to geological reasons, and the survey and analysis structure may be deviated due to the replacement of the transmitter's position. Summary of the invention
[0004] In order to make up for the above deficiencies, the present invention provides a mineral resource exploration and analysis device and an analysis method thereof that overcome the above technical problems or at least partially solve the above problems.
[0005] The present invention is achieved in that: The present invention provides a mineral resource exploration and analysis device, comprising an exploration box and an analysis mechanism, wherein a movable door is movably installed on the front of the exploration box, and a controller is installed on the front of the exploration box, a support seat is installed at the bottom of the inner cavity of the exploration box, a drilling tube is provided in the inner cavity of the exploration box, and a drilling mechanism is provided in the inner cavity of the exploration box; An analysis mechanism, the analysis mechanism comprising: A mounting groove, the mounting groove being opened on the left side of the drilling tube; A first electric push rod, the first electric push rod is installed at the top of the inner cavity of the installation slot; A mounting seat, the mounting seat being mounted on a free end of the first electric push rod; An electromagnetic transmitter is installed at the bottom of the mounting base through multiple sets of connecting rods.
[0006] In a preferred embodiment, a baffle is installed in the inner cavity of the installation groove, an empty groove is opened at the bottom of the baffle, a movable plate is inserted into the inner cavity of the empty groove, a traction rope is installed in the inner cavity of the empty groove, and the bottom of the traction rope is connected to the top of the movable plate.
[0007] In a preferred embodiment, the drilling mechanism includes a motor, and the motor is installed in the inner cavity of the exploration box, a first connecting seat is installed at the output end of the motor, and a second connecting seat threadedly connected to the first connecting seat is installed at the top of the drilling barrel, a transmission rod is installed at the bottom of the first connecting seat, and a drill bit is installed at the bottom of the transmission rod, and a first discharge port is opened on the surface of the drilling barrel.
[0008] In a preferred embodiment, a first spiral plate is installed at the bottom of the surface of the transmission rod, a second spiral plate is installed at the top of the surface of the transmission rod, a mounting ring is installed on the surface of the transmission rod, multiple groups of mounting rings are provided, and the mounting rings are located on the inner sides of the first spiral plate and the second spiral plate, and a blade is installed on the surface of the mounting ring, and a plurality of blades are provided.
[0009] In a preferred embodiment, a first fixing groove is provided on the front of the drilling tube, a first sampling box is installed in the inner cavity of the first fixing groove, a first feed port is provided on the back of the first sampling box, and a first limiting ring is installed on the surface of the drilling tube.
[0010] In a preferred solution, a second electric push rod is installed on the top of the support seat, a connecting plate is installed on the free end of the second electric push rod, a first fixing ring is installed on the surface of the motor, and the connecting plate is installed on the surface of the first fixing ring.
[0011] In a preferred solution, a second fixing ring is threadedly installed on the surface of the drilling tube, a conductive slip ring is installed on the top of the second fixing ring, and a through hole is opened in the inner cavity of the installation groove.
[0012] In a preferred solution, a tilting block is installed on the top of the support seat, side panels are installed on both sides of the tilting block, and a discharge port is opened on the left side of the exploration box.
[0013] In a preferred solution, a first fixed plate is installed on both sides of the exploration box, a second fixed plate located at the bottom of the first fixed plate is installed at the bottom of both sides of the exploration box, pressing rods are inserted on both sides of the top of the first fixed plate, a drill rod is installed at the bottom of the pressing rod, a rotating sleeve is installed on the top of the second fixed plate, and a pressing plate is rotatably installed on the top of the pressing rod.
[0014] A mineral resource exploration and analysis method, applicable to the above-mentioned mineral resource exploration and analysis device, comprises the following steps: S1: Equipment placement: First, place the survey box to a position that is convenient for survey after measurement, and press the pressing plate to drive the pressing rod and the drill rod to move downward, so that the drill rod can be inserted into the soil, and the survey box can be limited so that the survey box can be placed stably; S2: Drilling: By starting the motor, the motor drives the transmission rod and the drill bit to rotate and move downward to drill a hole in the ground, so that the electromagnetic transmitter can be inserted into the soil, and the underground mineral resources can be analyzed and judged by receiving the signal sent by the electromagnetic transmitter; S3: Sampling; when drilling the soil, the soil broken by the drill bit can enter the first sampling box, so that the soil at different depths can be sampled, which makes it easier to analyze the soil again using more accurate equipment, thereby improving the accuracy of exploration and analysis.
[0015] The invention provides a mineral resource exploration and analysis device and an analysis method thereof, and its beneficial effects include: 1. By setting up an analysis mechanism and a drilling mechanism, the soil can be drilled using the drilling mechanism, so that the analysis mechanism can be inserted deep into the soil, thereby facilitating the analysis mechanism to be moved out and inserted into the soil, thereby facilitating the transmission of electromagnetic waves, thereby facilitating the exploration and analysis of the land.
[0016] 2. By setting the first fixed groove, the first sampling box, the first feed port and the first limiting ring, the first sampling box can be installed after the first fixed groove is opened, so that the soil in the drilling tube can enter the first sampling box through the first feed port, and then the first sampling box can store part of the drilled soil, and the first limiting ring installed on the surface of the drilling tube can stably install the first sampling box in the first fixed groove.
[0017] 3. By setting the first fixed plate, the second fixed plate, the pressing rod, the drill rod, the rotating sleeve and the pressing plate, the pressing rod can be installed after the first fixed plate is installed, so that after the pressing plate is installed, the pressing rod and the drill rod can be driven to move downward, and the drill rod and the inner cavity of the rotating sleeve slide, so that the drill rod rotates, thereby facilitating the rotation of the drill rod downward and inserting it into the soil, thereby facilitating the installation of the exploration box. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only illustrate certain embodiments of the present invention and should not be regarded as limiting the scope. For those skilled in the art, other relevant drawings can be obtained based on these drawings without creative work. Figure 1 It is an overall stereogram provided by an embodiment of the present invention; Figure 2 A schematic diagram of a three-dimensional cross-sectional structure of an investigation box provided in an embodiment of the present invention; Figure 3 A schematic diagram of the three-dimensional structure of a drilling tube provided in an embodiment of the present invention; Figure 4 The embodiments of the present invention provide Figure 3 The enlarged structural diagram at A in the middle; Figure 5 A schematic diagram of a three-dimensional side view of the structure of a drilling tube provided in an embodiment of the present invention; Figure 6 A schematic diagram of a three-dimensional cross-sectional structure of a drilling tube provided in an embodiment of the present invention; Figure 7 A schematic diagram of a drilling tube assembly structure provided in an embodiment of the present invention; Figure 8 A schematic diagram of a three-dimensional structure of a drill pipe provided in an embodiment of the present invention; In the figure: 1, exploration box; 2, movable door; 3, controller; 4, support seat; 5, drilling tube; 6, analysis mechanism; 601, mounting slot; 602, first electric push rod; 603, mounting seat; 604, electromagnetic transmitter; 605, baffle; 606, empty slot; 607, moving plate; 608, traction rope; 7, drilling mechanism; 701, motor; 702, first connecting seat; 703, second connecting seat; 704, transmission rod; 705, drill bit; 706, first discharge port; 707, first spiral plate; 708, second spiral plate; 709, mounting ring; 710, blade; 711, drilling mechanism; 712, drilling tool; 713, drilling tool; 714, drilling tool; 715, drilling tool; 716, drilling tool; 717, drilling tool; 718, drilling tool; 719, drilling tool; 720, drilling tool; 721, drilling tool; 722, drilling tool; 723, drilling tool; 724, drilling tool; 725, drilling tool; 726, drilling tool; 727, drilling tool; 728, drilling tool; 729, drilling tool; 730, drilling tool; 731, drilling tool; 732, drilling tool; 733, drilling tool; 734, drilling tool; 735, drilling tool; 736, drilling tool; 737, drilling tool; 738, drilling tool; 739, drilling tool; 740, drilling tool; 741, drilling tool; 742, drilling tool; 743, drilling tool; 744, drilling tool; 745, drilling tool; 746, drilling tool; 747, drilling tool; 748, drilling tool; 749, drilling tool; 750 1. First fixed groove; 712. First sampling box; 713. First feed port; 714. First limit ring; 8. Second electric push rod; 9. Connecting plate; 10. First fixed ring; 11. Second fixed ring; 12. Conductive slip ring; 13. Through hole; 14. Tilting block; 15. Side plate; 16. Discharge port; 17. First fixed plate; 18. Second fixed plate; 19. Pressing rod; 20. Drill rod; 21. Rotating sleeve; 22. Pressing plate; 23. Extension tube; 24. Third connecting seat; 25. Fourth connecting seat; 26. Second fixed groove; 27. Second sampling box; 28. Second limit ring. DETAILED DESCRIPTION
[0019] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0020] Reference Figure 1-Figure 8The present invention provides a technical solution: a mineral resource exploration and analysis device and an analysis method thereof, comprising an exploration box 1 and an analysis mechanism 6, a movable door 2 is movably installed on the front of the exploration box 1, and a controller 3 is installed on the front of the exploration box 1, a support seat 4 is installed at the bottom of the inner cavity of the exploration box 1, a drilling tube 5 is provided in the inner cavity of the exploration box 1, and a drilling mechanism 7 is provided in the inner cavity of the exploration box 1, and the soil can be drilled by using the drilling mechanism 7, so that the analysis mechanism 6 can enter deep into the soil, so that the analysis mechanism 6 can be moved out and inserted into the soil, and then the electromagnetic wave is transmitted, so as to facilitate the exploration and analysis of the land.
[0021] Reference Figure 1-Figure 5 In a preferred embodiment, an analysis mechanism 6 is provided, the analysis mechanism 6 includes a mounting groove 601, a first electric push rod 602, a mounting seat 603 and an electromagnetic transmitter 604, the mounting groove 601 is opened on the left side of the drilling tube 5, the first electric push rod 602 is installed on the top of the inner cavity of the mounting groove 601, the mounting seat 603 is installed on the free end of the first electric push rod 602, and the electromagnetic transmitter 604 is installed at the bottom of the mounting seat 603 through a plurality of connecting rods, so that the first electric push rod 602 can be installed after the mounting groove 601 is opened, so that the first electric push rod 602 drives the mounting seat 603 after starting. The mounting seat 603 moves downward, and the connecting rod can be flipped to the left. A guide block with an inclined top is installed at the bottom of the inner cavity of the mounting groove 601, so that the first electric push rod 602 moves the electromagnetic transmitter 604 downward, so that the guide block and the electromagnetic transmitter 604 are guided, so that the electromagnetic transmitter 604 can be offset to the left, and then the electromagnetic transmitter 604 can be inserted into the soil, so that after the electromagnetic transmitter 604 is powered on, the electromagnetic waves can be transmitted to the land, so that the electromagnetic transmitter 604 cooperates with the receiver located at other positions, so as to facilitate the exploration of mineral resources in the land.
[0022] In addition, a baffle 605 is installed in the inner cavity of the installation groove 601, and an empty groove 606 is opened at the bottom of the baffle 605. A movable plate 607 is inserted into the inner cavity of the empty groove 606, and a traction rope 608 is installed in the inner cavity of the empty groove 606, and the bottom of the traction rope 608 is connected to the top of the movable plate 607. After the baffle 605 is installed, the empty groove 606 is opened and the traction rope 608 and the movable plate 607 are installed, so that when the electromagnetic transmitter 604 and the connecting rod are rotated, the movable plate 607 is squeezed, so that the movable plate 607 moves upward, thereby facilitating the movement of the connecting rod and the electromagnetic transmitter 604, and the traction rope 608 can limit the movable plate 607 to prevent the movable plate 607 from sliding downward.
[0023] Reference Figure 7In a preferred embodiment, the drilling mechanism 7 includes a motor 701, and the motor 701 is installed in the inner cavity of the exploration box 1, the output end of the motor 701 is installed with a first connection seat 702, and the top of the drilling tube 5 is installed with a second connection seat 703 threadedly connected to the first connection seat 702, the bottom of the first connection seat 702 is installed with a transmission rod 704, and the bottom of the transmission rod 704 is installed with a drill bit 705, and the surface of the drilling tube 5 is provided with a first discharge port 706, which can enable the motor 701 to connect the first connection seat 702 to the drilling tube 5. The seat 702 is installed so that when the motor 701 drives the first connecting seat 702 to rotate, the first connecting seat 702 drives the transmission rod 704 to rotate through the second connecting seat 703, so that the transmission rod 704 drives the drill bit 705 installed at the bottom to rotate, so as to facilitate drilling, and the soil generated during drilling can be discharged from the first discharge port 706, wherein the surface of the drill bit 705 is provided with a through hole connected to the drilling tube 5, so that the soil enters the drilling tube 5, and the transmission rod 70 The first spiral plate 707 is installed at the bottom of the surface of the transmission rod 704, the second spiral plate 708 is installed at the top of the surface of the transmission rod 704, and the surface of the transmission rod 704 is installed with a mounting ring 709. The mounting ring 709 is provided with multiple groups, and the mounting ring 709 is located on the inner side of the first spiral plate 707 and the second spiral plate 708. The surface of the mounting ring 709 is installed with a blade 710, and the blade 710 is provided with a plurality of blades, which can drive the first spiral plate 707 and the second spiral plate 708 to rotate when the transmission rod 704 rotates. It is convenient to transport the soil generated during drilling, so as to facilitate the discharge of the soil. After the mounting ring 709 is installed, the blade 710 can be installed, so that multiple sets of blades 710 can cooperate to crush the soil. A tilting block 14 is installed on the top of the support seat 4, and side panels 15 are installed on both sides of the tilting block 14. A discharge port 16 is opened on the left side of the exploration box 1, which can enable the tilting block 14 and the side panel 15 to guide the discharge port 16, thereby discharging the soil generated during drilling and avoiding the accumulation of soil in the inner cavity of the exploration box 1.
[0024] In addition, a first fixing groove 711 is opened on the front side of the drilling tube 5, a first sampling box 712 is installed in the inner cavity of the first fixing groove 711, and a first feed port 713 is opened on the back side of the first sampling box 712, and a first limiting ring 714 is installed on the surface of the drilling tube 5, so that the first sampling box 712 can be installed after the first fixing groove 711 is opened, so that the soil in the drilling tube 5 can enter the first sampling box 712 through the first feed port 713, and then the first sampling box 712 can store part of the drilled soil, and the first limiting ring 714 installed on the surface of the drilling tube 5 can stably install the first sampling box 712 in the first fixing groove 711.
[0025] Reference Figure 2-Figure 7In a preferred embodiment, a second electric push rod 8 is installed on the top of the support seat 4, a connecting plate 9 is installed on the free end of the second electric push rod 8, a first fixing ring 10 is installed on the surface of the motor 701, and the connecting plate 9 is installed on the surface of the first fixing ring 10, so that the second electric push rod 8 can drive the first fixing ring 10 to move upward through the connecting plate 9 after startup, thereby facilitating the movement of the motor 701, and a second fixing ring 11 is threadedly installed on the surface of the drilling tube 5, a conductive slip ring 12 is installed on the top of the second fixing ring 11, and a through hole 13 is opened in the inner cavity of the installation groove 601, so that the conductive slip ring 12 can be installed after the second fixing ring 11 is installed, so that the second electric push rod 8 can be provided with power through the conductive slip ring 12, and the wires can be connected to the second electric push rod 8.
[0026] Reference Figure 1 and Figure 8 In a preferred embodiment, a first fixing plate 17 is installed on both sides of the exploration box 1, and a second fixing plate 18 located at the bottom of the first fixing plate 17 is installed at the bottom of both sides of the exploration box 1. Pressing rods 19 are inserted on both sides of the top of the first fixing plate 17, and a drill rod 20 is installed at the bottom of the pressing rod 19. A rotating sleeve 21 is installed on the top of the second fixing plate 18, and a pressing plate 22 is rotatably installed on the top of the pressing rod 19, so that the pressing rod 19 can be installed after the first fixing plate 17 is installed, so that the pressing rod 19 and the drill rod 20 can be driven to move downward after the pressing plate 22 is installed, and the drill rod 20 slides with the inner cavity of the rotating sleeve 21, so that the drill rod 20 rotates, thereby facilitating the rotation of the drill rod 20 downward and inserting it into the soil, thereby facilitating the installation of the exploration box 1.
[0027] Reference Figure 7In a preferred embodiment, an extension tube 23 is provided at the top of the drilling tube 5, and a third connection seat 24 and a fourth connection seat 25 are installed at the top and the bottom of the extension tube 23, respectively, so that the third connection seat 24 and the fourth connection seat 25 can be connected to the first connection seat 702 and the second connection seat 703, respectively, so that the extension tube 23 can be installed, and the depth of the borehole can be increased, so that the electromagnetic transmitter 604 can be deeply inserted into the soil at a sufficient depth, and the presence of more gravel in the shallow soil can be avoided to affect the insertion of the electromagnetic transmitter 604 and the transmission and reception of signals, and the extension tube 23 can be installed. A second discharge port is provided on the surface of the extension tube 23, and a second fixing groove 26 is provided on the front side of the extension tube 23. A second sampling box 27 is installed in the inner cavity of the second fixing groove 26, and a second feed port (not shown in the figure) is provided on the back side of the second sampling box 27. A second limiting ring 28 is installed on the surface of the extension tube 23, and a second discharge port (not shown in the figure) for discharging is provided on the surface of the extension tube 23, which can enable soil to enter the second sampling box 27 through the second feed port when drilling, thereby facilitating the collection of soil and facilitating a more detailed analysis of the soil after collection.
[0028] A mineral resource exploration and analysis method, applicable to the above-mentioned mineral resource exploration and analysis device, comprises the following steps: S1: Equipment placement; first, the survey box 1 is placed at a position convenient for survey after measurement, and the pressing plate 22 is pressed so that the pressing plate 22 drives the pressing rod 19 and the drill rod 20 to move downward, so that the drill rod 20 can be inserted into the soil, and the survey box 1 can be limited so that the survey box 1 can be stably placed; S2: Drilling; by starting the motor 701, the motor 701 drives the transmission rod 704 and the drill bit 705 to rotate downward to drill a hole in the ground, so that the electromagnetic transmitter 604 can be inserted into the soil, and the underground mineral resources can be analyzed and determined by receiving the signal sent by the electromagnetic transmitter 604; S3: Sampling; when drilling the soil, the soil broken by the drill bit 705 can enter the first sampling box 712, so that the soil at different depths can be sampled, which makes it easier to analyze the soil again using more accurate equipment, thereby improving the accuracy of exploration and analysis.
[0029] Specifically, the working process or working principle of the mineral resource exploration and analysis device and the analysis method thereof is as follows: when in use, the exploration box 1 is first placed at a position suitable for drilling for mineral resource analysis, and the pressing plate 22 is pressed downward, so that the pressing plate 22 drives the pressing rod 19 and the drill hole to move downward, thereby facilitating the insertion of the drill rod 20 into the soil, and then the exploration box 1 can be limited, and then the motor 701 is started, so that the motor 701 drives the transmission rod 704 and the drill bit 705 to rotate, so that the drill bit 705 drills the ground, and the drilling tube 5 can be inserted into the ground, so that the soil can enter the drilling tube 5, which can The soil can be transported through the first spiral plate 707 and the second spiral plate 708, so that part of the soil can enter the first sampling box 712 when the soil is transported upward, and most of the soil can be discharged. When the motor 701 is started, the first electric push rod 602 is started at the same time, so that the first electric push rod 602 drives the motor 701 to move downward through the connecting plate 9 and the first fixing ring 10, so as to facilitate the drill bit 705 to drill downward. Since the soil is continuously transported upward, the first sampling box 712 can collect soil of different depths, and the drilling depth of the drill bit 705 can be extended by assembling the extension tube 23.
[0030] After the drill bit 705 drills to a sufficient depth, the second electric push rod 8 is started, so that the second electric push rod 8 drives the electromagnetic transmitter 604 to move downward, and then the electromagnetic transmitter 604 can be inserted into the soil, so that the signal emitted by the electromagnetic transmitter 604 can be received by the receiver, thereby facilitating the exploration and analysis of resources in the land, and also by analyzing the soil in the first sampling box 712, the accuracy of the analysis can be improved, making the exploration structure more accurate.
Claims
1. A mineral resource exploration and analysis device, comprising an exploration box (1) and an analysis mechanism (6), characterized in that; The front of the exploration box (1) is movably provided with a movable door (2), and the front of the exploration box (1) is provided with a controller (3), the bottom of the inner cavity of the exploration box (1) is provided with a support seat (4), the inner cavity of the exploration box (1) is provided with a drilling tube (5), and the inner cavity of the exploration box (1) is provided with a drilling mechanism (7); An analysis mechanism (6), wherein the analysis mechanism (6) comprises: A mounting groove (601), wherein the mounting groove (601) is provided on the left side of the drilling tube (5); A first electric push rod (602), the first electric push rod (602) being installed at the top of the inner cavity of the installation slot (601); A mounting seat (603), wherein the mounting seat (603) is mounted on the free end of the first electric push rod (602); An electromagnetic transmitter (604) is installed at the bottom of the mounting seat (603) via a plurality of sets of connecting rods.
2. A mineral resource exploration and analysis device according to claim 1, characterized in that: A baffle (605) is installed in the inner cavity of the installation groove (601), a hollow groove (606) is provided at the bottom of the baffle (605), a movable plate (607) is inserted into the inner cavity of the hollow groove (606), a traction rope (608) is installed in the inner cavity of the hollow groove (606), and the bottom of the traction rope (608) is connected to the top of the movable plate (607).
3. A mineral resource exploration and analysis device according to claim 1, characterized in that: The drilling mechanism (7) comprises a motor (701), and the motor (701) is installed in the inner cavity of the exploration box (1); a first connecting seat (702) is installed at the output end of the motor (701); a second connecting seat (703) threadedly connected to the first connecting seat (702) is installed at the top of the drilling tube (5); a transmission rod (704) is installed at the bottom of the first connecting seat (702); a drill bit (705) is installed at the bottom of the transmission rod (704); and a first discharge port (706) is opened on the surface of the drilling tube (5).
4. A mineral resource exploration and analysis device according to claim 3, characterized in that: A first spiral plate (707) is installed at the bottom of the surface of the transmission rod (704), a second spiral plate (708) is installed at the top of the surface of the transmission rod (704), a mounting ring (709) is installed on the surface of the transmission rod (704), a plurality of mounting rings (709) are provided, and the mounting rings (709) are located on the inner sides of the first spiral plate (707) and the second spiral plate (708), and a plurality of blades (710) are installed on the surface of the mounting ring (709).
5. A mineral resource exploration and analysis device according to claim 4, characterized in that: The front side of the drilling tube (5) is provided with a first fixing groove (711), the inner cavity of the first fixing groove (711) is provided with a first sampling box (712), and the back side of the first sampling box (712) is provided with a first feed port (713), and the surface of the drilling tube (5) is provided with a first limiting ring (714).
6. A mineral resource exploration and analysis device according to claim 3, characterized in that: A second electric push rod (8) is mounted on the top of the support seat (4), a connecting plate (9) is mounted on the free end of the second electric push rod (8), a first fixing ring (10) is mounted on the surface of the motor (701), and the connecting plate (9) is mounted on the surface of the first fixing ring (10).
7. A mineral resource exploration and analysis device according to claim 1, characterized in that: A second fixing ring (11) is threadedly mounted on the surface of the drilling tube (5), a conductive slip ring (12) is mounted on the top of the second fixing ring (11), and a through hole (13) is formed in the inner cavity of the mounting groove (601).
8. The mineral resource exploration and analysis device according to claim 1, characterized in that: A tilting block (14) is installed on the top of the support seat (4), side panels (15) are installed on both sides of the tilting block (14), and a discharge port (16) is opened on the left side of the investigation box (1).
9. A mineral resource exploration and analysis device according to claim 1, characterized in that: First fixing plates (17) are installed on both sides of the survey box (1), second fixing plates (18) located at the bottom of the first fixing plates (17) are installed at the bottom of both sides of the survey box (1), pressing rods (19) are inserted on both sides of the top of the first fixing plate (17), a drill rod (20) is installed at the bottom of the pressing rod (19), a rotating sleeve (21) is installed on the top of the second fixing plate (18), and a pressing plate (22) is rotatably installed on the top of the pressing rod (19).
10. A method for mineral resource exploration and analysis, applicable to a mineral resource exploration and analysis device as claimed in any one of claims 1 to 9, characterized in that: The steps include: S1: equipment placement; first, the survey box (1) is placed at a position that is convenient for survey after measurement, and the pressing plate (22) is pressed so that the pressing plate (22) drives the pressing rod (19) and the drill rod (20) to move downward, so that the drill rod (20) can be inserted into the soil, and the survey box (1) can be limited so that the survey box (1) can be stably placed; S2: Drilling; by starting the motor (701), the motor (701) drives the transmission rod (704) and the drill bit (705) to rotate and move downward to drill a hole in the ground, so that the electromagnetic transmitter (604) can be inserted into the soil, and the underground mineral resources can be analyzed and determined by receiving the signal sent by the electromagnetic transmitter (604); S3: Sampling; when drilling the soil, the soil crushed by the drill bit (705) can enter the first sampling box (712), so that the soil at different depths can be sampled, which makes it easier to analyze the soil again using more accurate equipment, thereby improving the accuracy of exploration and analysis.
Citation Information
Cited By
Alloy drilling system special for underground exploration