Material life cycle tracing system and method based on intelligent label

Through intelligent label technology and automatic entry of RF scanning robots, the problems of low traceability efficiency and difficult management in traditional material management methods are solved, and efficient tracking and precise management of materials are achieved.

CN119151431AInactive Publication Date: 2024-12-17SHENZHEN ZHAOHANG LOGISTICS CO LTD

Patent Information

Application Number
CN202411176197.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-26
Publication Date
2024-12-17
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Traditional material management methods have low traceability efficiency, inaccurate information, and difficult management. Especially when the industrial Internet is marked as virtual data, it requires manual input of identification codes for data upload, and the management efficiency is low.

Method used

Using intelligent tag technology, the material encoding is obtained through the information entry subsystem, the traceability demand information is obtained by the traceability demand information is determined by the traceability result determination subsystem based on the intelligent tag technology, and the radio frequency scanning robot automatically enters the material information to improve material tracking Timeliness and management efficiency.

Benefits of technology

It improves the timeliness of material tracking and material management efficiency, reduces the workload of manual entry, and realizes accurate material tracking and full-process management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119151431A_ABST
    Figure CN119151431A_ABST
Patent Text Reader

Abstract

The invention provides a material life cycle tracing system and method based on an intelligent label, and belongs to the technical field of material management, and the system comprises an information input subsystem which is used for inputting a material code of a first target material needing to be managed; the traceability demand information acquisition subsystem is used for determining a second target material needing to be traced and acquiring traceability demand information; the tracing demand information comprises a material code of the second target material and tracing template information of the second target material; and the traceability result determination subsystem is used for determining a traceability result according to the traceability demand information and the life cycle of the second target material based on an intelligent label technology. According to the material life cycle tracing system and method based on the intelligent label, the tracing result is determined based on the intelligent label technology according to the unique material code of the second target material needing to be traced and the tracing template information of the second target material, and the timeliness of material tracing and the material management efficiency are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of material management, and in particular to a material life cycle tracing system and method based on smart labels. Background Art

[0002] With the rapid development of Internet of Things technology, the demand for full life cycle traceability of materials in the field of material management is increasing. Traditional material management methods have problems such as low traceability efficiency, inaccurate information, and difficulty in management (for example, the workload of manual inventory and data entry is large, goods are lost or misplaced, and it is difficult to inventory a large number of items in large warehouses). The full tracking and precise management of materials has important practical application value.

[0003] The invention patent with application number: 202111048719.9 discloses a material quality traceability method and system based on industrial Internet identification and blockchain. The method includes: constructing a unique identification code for materials according to industry identification coding specifications; obtaining material technical specification data, and registering identification according to the unique identification code of the materials, and constructing identification mapping data corresponding to each identification according to the technical requirement parameter name, upper limit and lower limit; uploading the identification, identification mapping data and hash value of the identification mapping data to the blockchain; performing the above-mentioned chain-up process on material production monitoring data and material quality inspection data in turn; cross-verifying the identification mapping data according to material technical specification data, material production monitoring data and material quality inspection data; and verifying the results and querying the cross-verification results through the blockchain according to the unique identification code of the materials. Compared with the prior art, the above invention realizes comprehensive, intuitive and transparent traceability of material quality, and improves the efficiency and security of data circulation.

[0004] However, the industrial Internet identifier of the above-mentioned prior art is virtual data, and uploading data to the chain through the identification code requires manual input of the identification code before uploading the data, which results in relatively low management efficiency.

[0005] In view of this, there is an urgent need for a material life cycle traceability system and method based on smart labels to at least solve the above-mentioned deficiencies. Summary of the invention

[0006] One of the purposes of the present invention is to provide a material life cycle tracing system and method based on smart labels, obtain the material code of the first target material that needs to be managed, and based on the smart label technology, determine the tracing result according to the unique material code of the second target material that needs to be traced and the tracing template information of the second target material, thereby improving the timeliness of material tracking and the efficiency of material management.

[0007] The material life cycle tracing system based on smart labels provided in the embodiment of the present invention includes:

[0008] The information input subsystem is used to input the material code of the first target material to be managed;

[0009] The traceability requirement information acquisition subsystem is used to determine the second target material that needs to be traced and obtain the traceability requirement information; the traceability requirement information includes: the material code of the second target material and the traceability template information of the second target material;

[0010] The traceability result determination subsystem is used to determine the traceability result based on the intelligent label technology, according to the traceability demand information and the life cycle of the second target material.

[0011] Preferably, the information entry subsystem includes:

[0012] A coding module, used to encode the first target material and obtain the material code of the first target material;

[0013] A smart label determination module, used to obtain a smart label of a first target material;

[0014] The material code entry module is used to enter material codes based on smart labels.

[0015] Preferably, the encoding module includes:

[0016] A material type acquisition submodule is used to acquire the material type of the first target material;

[0017] A first coding position code determination submodule, for determining the first coding position code according to the material type and the first coding position determination library;

[0018] The material information acquisition submodule is used to acquire the material information of the first target material, the material information including: production date, batch number and product model;

[0019] A second coding bit code determination submodule, used to determine the second coding bit code according to the material information and the second coding bit determination template;

[0020] A management information acquisition submodule, used to acquire the management information of the first target material;

[0021] A third coding bit code determination submodule, used to determine the third coding bit code according to the management information and the third coding bit determination template;

[0022] The material code determination submodule is used to determine the material code according to the first coding bit code, the second coding bit code and the third coding bit code.

[0023] Preferably, the traceability requirement information acquisition subsystem includes:

[0024] A management information determination module, used to parse the material code of the second target material and determine the management information of the second target material;

[0025] The traceability template information determination module is used to determine the traceability template information according to the current time and the management information of the second target material.

[0026] Preferably, the tracing result determination subsystem includes:

[0027] A target entry node determination module, used to determine the target entry node of the second target material according to the current time and the life cycle of the second target material;

[0028] A tracking information acquisition module, used to obtain tracking information of a second target material according to a target entry node;

[0029] The tracking result determination module is used to determine the tracking result according to the tracking information and the tracing template information.

[0030] Preferably, the tracking information acquisition module includes:

[0031] The node type acquisition submodule is used to acquire the node type of the target input node; the node types include: manually input nodes and machine input nodes;

[0032] The tracking information first determination submodule is used to obtain the first scanning information of the manual handheld radio frequency scanning terminal when the node type is a manually entered node, and obtain the tracking information according to the first scanning information;

[0033] The second tracking information determination submodule is used to obtain the second scanning information of the radio frequency scanning robot when the node type is a machine input node, and obtain the tracking information according to the second scanning information.

[0034] Preferably, the second determination submodule of tracking information includes:

[0035] A transport arrival status information acquisition unit, used to acquire the transport arrival status information of the second target material arriving at the management area corresponding to the target entry node;

[0036] A distribution status determination unit, used to determine the distribution status of the second target material according to the transport arrival status information;

[0037] A first distance calculation unit, used for calculating a first distance between second target materials according to the distribution situation;

[0038] A distributed material cluster determining unit, configured to treat the corresponding second target materials as a distributed material cluster if the first distance between the second target materials is less than or equal to a preset first distance threshold;

[0039] The robot dispatching unit is used to dispatch the radio frequency scanning robot to the distributed material cluster to perform data entry operations.

[0040] Preferably, the robot scheduling unit comprises:

[0041] A first cluster number obtaining subunit, used to obtain the first cluster number of the distributed material cluster;

[0042] A first robot number acquisition subunit, used to acquire a first robot number of idle radio frequency scanning robots;

[0043] A first allocation subunit is used to allocate at least one radio frequency scanning robot to each distributed material cluster for data entry if the number of the first clusters is less than or equal to the number of the first robots;

[0044] A first target radio frequency scanning robot determination subunit is used to determine the radio frequency scanning robot closest to the distributed material cluster if the number of the first clusters is greater than the number of the first robots, and use the radio frequency scanning robot as the first target radio frequency scanning robot of the corresponding distributed material cluster;

[0045] A number determination subunit, used to determine whether the number of second robots of the first target radio frequency scanning robot is consistent with the number of first robots;

[0046] A second allocation subunit is used to dispatch the first target radio frequency scanning robot to go to the corresponding distributed material cluster to perform input operation if the number of the second robots is consistent with the number of the first robots;

[0047] A second cluster number calculation subunit, configured to obtain a second cluster number of the distributed material cluster corresponding to the first target radio frequency scanning robot if the second robot number is inconsistent with the first robot number;

[0048] The third allocation subunit is used for the first target radio frequency scanning robot to go to the distributed material cluster to perform input operations;

[0049] Dispatching the corresponding first target radio frequency scanning robot to the distributed material cluster to perform data entry operations;

[0050] a second target radio frequency scanning robot determining subunit, configured to use the first target radio frequency scanning robot as the second target radio frequency scanning robot if the number of the second clusters is greater than 1;

[0051] A target distributed material cluster determination subunit is used to take the distributed material cluster corresponding to the second target radio frequency scanning robot as the target distributed material cluster;

[0052] A fourth allocation subunit is used to obtain a second distance between each target distributed material cluster and the corresponding second target radio frequency scanning robot, associate the target distributed material cluster with the smallest second distance with the second target radio frequency scanning robot, and dispatch the second target radio frequency scanning robot to the associated target distributed material cluster to perform input operations;

[0053] A third target radio frequency scanning robot determination subunit is used to determine the remaining radio frequency scanning robots except the first target radio frequency scanning robot among the idle radio frequency scanning robots and use them as the third target radio frequency scanning robots;

[0054] The remaining distributed material cluster determination subunit is used to obtain the target distributed material clusters other than the target distributed material clusters associated with the second target radio frequency scanning robot, and use them as the remaining distributed material clusters;

[0055] The fifth allocation subunit is used to perform scanning operations on the remaining distributed material clusters according to the idle radio frequency scanning robots and the third target radio frequency scanning robots determined in real time.

[0056] Preferably, the robot scheduling unit further includes:

[0057] A smart tag signal penetration feature determination subunit is used to determine the smart tag signal penetration feature when the radio frequency scanning robot arrives at the distributed material cluster;

[0058] The first input subunit is used to input the second target material according to the smart tag signal penetration characteristics;

[0059] The recorded material determination subunit is used to determine the second target material that has been currently recorded by the radio frequency scanning robot;

[0060] The second input subunit is used to control the mechanical arm preset on the radio frequency scanning robot to pick up the second target materials that have been input. After picking up, the remaining second target materials continue to be input until all the second target materials on site are input.

[0061] The material life cycle tracing method based on smart labels provided in an embodiment of the present invention includes:

[0062] Step 1: Enter the material code of the first target material to be managed;

[0063] Step 2: Determine the second target material that needs to be traced and obtain traceability requirement information; the traceability requirement information includes: the material code of the second target material and the traceability template information of the second target material;

[0064] Step 3: Based on the smart label technology, determine the traceability result according to the traceability demand information and the life cycle of the second target material.

[0065] The beneficial effects of the present invention are:

[0066] The present invention obtains the material code of the first target material that needs to be managed, and based on the smart label technology, determines the tracing result according to the unique material code of the second target material that needs to be traced and the tracing template information of the second target material, thereby improving the timeliness of material tracking and the efficiency of material management.

[0067] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or understood by practicing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures specifically pointed out in the present application documents.

[0068] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0069] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0070] Figure 1 Schematic diagram of a material life cycle tracing system based on smart labels in an embodiment of the present invention;

[0071] Figure 2 Schematic diagram of a material life cycle tracing method based on smart labels in an embodiment of the present invention. DETAILED DESCRIPTION

[0072] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.

[0073] The embodiment of the present invention provides a material life cycle tracing system based on smart labels, such as Figure 1 As shown, including:

[0074] The information input subsystem 1 is used to input the material code of the first target material to be managed; wherein the first target material is: the material to be managed, such as: automobile parts; the material code is: the unique radio frequency signal identifier allocated to the first target material;

[0075] The traceability requirement information acquisition subsystem 2 is used to determine the second target material that needs to be traced and obtain the traceability requirement information; the traceability requirement information includes: the material code of the second target material and the traceability template information of the second target material; wherein the second target material is: the material that needs to be traced among the first target materials, such as: automobile tires; the material code of the second target material is: the radio frequency signal identifier of the second target material; the traceability template information is: the standard state of the second target material at each stage of the life cycle, such as: when the tire is produced, the standard state is: the location is in the tire production factory, and another example: when the tire is stored after production, the standard state is: the location is in the tire storage warehouse;

[0076] The traceability result determination subsystem 3 is used to determine the traceability result based on the intelligent label technology according to the traceability demand information and the life cycle of the second target material. The life cycle of the second target material refers to the entire process from production, storage, use to disposal of the second target material; the traceability result is the traceability conclusion or status finally determined based on the collected traceability demand information and the life cycle of the material, including information such as the source, flow and use of the second material.

[0077] The working principle and beneficial effects of the above technical solution are:

[0078] The material life cycle tracing system based on smart labels of the present invention includes smart labels, reading and writing devices, a data processing center and a user terminal. The smart label is used to identify the unique identity of the first target material, the reading and writing device is used to read and write information in the smart label, the data processing center is used to process and analyze the data read by the reading and writing device, and the user terminal is used to display the tracing results and provide an operation interface. The material code of the first target material to be managed is obtained, and based on the smart label technology, the tracing result is determined according to the unique material code of the second target material to be traced and the tracing template information of the second target material, thereby improving the timeliness of material tracking and the efficiency of material management.

[0079] In one embodiment, the information entry subsystem includes:

[0080] A coding module, used to encode the first target material and obtain the material code of the first target material;

[0081] A smart label determination module is used to obtain a smart label of a first target material; wherein the smart label is: an RFID radio frequency label;

[0082] The material code entry module is used to enter material codes based on smart labels.

[0083] The working principle and beneficial effects of the above technical solution are:

[0084] The present invention enters the material code for encoding the first target material into the RFID radio frequency tag, thereby improving the convenience of subsequent material identification.

[0085] In one embodiment, the encoding module includes:

[0086] The material type acquisition submodule is used to acquire the material type of the first target material; wherein the material type is: the material variety of the first target material, such as: tires;

[0087] The first coding bit code determination submodule is used to determine the first coding bit code according to the material type and the first coding bit determination library; wherein the first coding bit determination library includes: a plurality of one-to-one corresponding pre-selected material types and corresponding codes, for example: "tire" corresponds to "K";

[0088] The material information acquisition submodule is used to acquire the material information of the first target material, the material information including: production date, batch number and product model;

[0089] The second coding bit code determination submodule is used to determine the second coding bit code according to the material information and the second coding bit determination template; wherein the second coding bit determination template is used to generate the code corresponding to the material information by comparing with the material information;

[0090] The management information acquisition submodule is used to acquire the management information of the first target material; wherein the management information is: the management process information of the first target material, such as: the place of production and the distribution point;

[0091] The third coding bit code determination submodule is used to determine the third coding bit code according to the management information and the third coding bit determination template; wherein the third coding bit determination template is used for the management information to generate the code corresponding to the material information;

[0092] The material code determination submodule is used to determine the material code according to the first coding bit code, the second coding bit code and the third coding bit code.

[0093] The working principle and beneficial effects of the above technical solution are:

[0094] The present invention is based on the introduced first coding position determination library, second coding position determination template and third coding position determination template, and determines the first coding position code, the second coding position code and the third coding position code respectively according to the material type, material information and management information of the first target material, and further determines the material code, thereby improving the coding suitability of the material code.

[0095] In one embodiment, the traceability requirement information acquisition subsystem includes:

[0096] A management information determination module is used to parse the material code of the second target material and determine the management information of the second target material; wherein the management information is: management process information of the second target material;

[0097] The traceability template information determination module is used to determine the traceability template information according to the current time and the management information of the second target material. When determining the traceability template information according to the current time and the management information, the management process node in the management information is located according to the current time, and the specification information corresponding to the management process node is used as the traceability template information.

[0098] The working principle and beneficial effects of the above technical solution are:

[0099] The present invention determines the traceability template information for subsequent traceability comparison according to the current time and the management information of the second target material obtained by parsing the material code, which is more reasonable.

[0100] In one embodiment, the tracing result determination subsystem includes:

[0101] The target entry node determination module is used to determine the target entry node of the second target material according to the current time and the life cycle of the second target material; wherein the current time is: the current time obtained in real time; the target entry node is: the communication node of the identification party that performs the most recent radio frequency tag identification from the current time;

[0102] A tracking information acquisition module is used to acquire tracking information of the second target material according to the target entry node; wherein the tracking information is: information of the second target material acquired by the management area corresponding to the target entry node, such as: radio frequency identification result of the second target material, and tracking video data of the second target material after identification;

[0103] The tracking result determination module is used to determine the tracking result according to the tracking information and the traceability template information. When determining the tracking result according to the tracking information and the traceability template information, the standard information corresponding to the tracking information in the traceability template information is determined and the information is compared to determine the tracking result. For example, if the incoming RFID result of warehouse A at time T does not identify the RFID ID of part B, and the standard information in the traceability template information is: the incoming RFID result of warehouse A at time T should identify the RFID ID of part B, then the tracking result is: part B is lost at time T.

[0104] The working principle and beneficial effects of the above technical solution are:

[0105] The present invention determines the target entry node of the identification party that performs radio frequency tag identification of the target entry node most recently at the current moment, obtains tracking information of the second target material through the target entry node, compares the tracking information with corresponding standard information in the traceability template information to determine the tracking result, and tracks the materials more timely.

[0106] In one embodiment, the tracking information acquisition module includes:

[0107] The node type acquisition submodule is used to acquire the node type of the target entry node; the node types include: manual entry node and machine entry node; wherein the manual entry node is: the communication node of the manager who performs radio frequency tag scanning; the machine entry node is: the communication node of the scanning robot that performs radio frequency tag scanning;

[0108] The tracking information first determination submodule is used to obtain the first scanning information of the manual handheld radio frequency scanning terminal when the node type is a manually entered node, and obtain the tracking information according to the first scanning information; wherein the radio frequency scanning terminal is: an RFID reader; the first scanning information is: a radio frequency signal recognition result of the radio frequency scanning terminal;

[0109] The second tracking information determination submodule is used to obtain the second scanning information of the radio frequency scanning robot when the node type is a machine input node, and obtain the tracking information according to the second scanning information. The radio frequency scanning robot is: an intelligent robot equipped with an RFID identification device; the second scanning information is: the radio frequency signal identification result of the radio frequency scanning robot.

[0110] The working principle and beneficial effects of the above technical solution are:

[0111] This application introduces two ways to obtain tracking information. The first way is to obtain tracking information based on the first scanning information entered manually; the second way is to obtain tracking information based on the second scanning information entered by the robot. Introducing two ways to identify tag information is more comprehensive and intelligent.

[0112] In one embodiment, the tracking information second determination submodule includes:

[0113] The transport arrival status information acquisition unit is used to acquire the transport arrival status information of the second target material arriving at the management area corresponding to the target entry node; wherein the management area corresponding to the target entry node is: the material storage area after the second target material is completed at the target entry node; the transport arrival status information is: the video data before the second target material is entered at the target entry node;

[0114] A distribution determination unit is used to determine the distribution of the second target material according to the transport arrival status information; wherein the distribution of the second target material is: the point distribution of the second target material on the transport device;

[0115] A first distance calculation unit is used to calculate the first distance between the second target materials according to the distribution situation; wherein the first distance is: the distance between two of the second target materials;

[0116] A distributed material cluster determination unit, configured to treat the corresponding second target materials as a distributed material cluster if the first distance between the second target materials is less than or equal to a preset first distance threshold; wherein the first distance threshold is manually preset, such as 0.9 m;

[0117] The robot dispatching unit is used to dispatch the radio frequency scanning robot to the distributed material cluster for data entry. The distributed material cluster is: the position corresponding to the average position coordinate of the second target material in the distributed material cluster.

[0118] The working principle and beneficial effects of the above technical solution are:

[0119] During the life cycle of materials, there is a possibility of loss when materials are transferred from one location to another. Therefore, when the second target material arrives at the management area corresponding to the target entry node, it is necessary to enter information, check for missing materials, and pick up the second target material on the transport device through an automated RF scanning robot. Since the second target material may be in large quantity, it is necessary to coordinate the scheduling of RF scanning robots to determine the distribution of the second target materials based on the video data before the second target material is entered into the target entry node. Distance measurement is performed based on the distribution to determine the first distance between the second target materials. When the first distance is less than or equal to the first distance threshold, the corresponding second target material is divided into a distributed material cluster, and the RF scanning robots are dispatched to the distributed material clusters to perform material entry operations, so that the information entry of stored materials is automated and more intelligent.

[0120] In one embodiment, the robot scheduling unit comprises:

[0121] The first cluster number acquisition subunit is used to acquire the first cluster number of the distributed material cluster; wherein the first cluster number is: the number of clusters of the distributed material cluster;

[0122] The first robot number acquisition subunit is used to acquire the first robot number of idle radio frequency scanning robots; wherein the first robot number is: the idle radio frequency scanning robots in the management area when the second target material arrives at the management area;

[0123] A first allocation subunit is configured to allocate at least one radio frequency scanning robot to each distributed material cluster for data entry if the number of the first clusters is less than or equal to the number of the first robots; wherein when at least one radio frequency scanning robot is allocated to each distributed material cluster for data entry, the nearest radio frequency scanning robot corresponding to each distributed material cluster is determined as the allocated robot;

[0124] A first target radio frequency scanning robot determination subunit is used to determine the radio frequency scanning robot closest to the distributed material cluster if the number of the first clusters is greater than the number of the first robots, and use the radio frequency scanning robot as the first target radio frequency scanning robot of the corresponding distributed material cluster;

[0125] The number determination subunit is used to determine whether the number of the second robots of the first target radio frequency scanning robot is consistent with the number of the first robots; wherein the number of the second robots is: the number of the robots of the first target radio frequency scanning robot;

[0126] A second allocation subunit is used to dispatch the first target radio frequency scanning robot to go to the corresponding distributed material cluster to perform input operation if the number of the second robots is consistent with the number of the first robots;

[0127] A second cluster number calculation subunit, configured to obtain a second cluster number of the distributed material cluster corresponding to the first target radio frequency scanning robot if the second robot number is inconsistent with the first robot number;

[0128] A third allocation subunit is used to dispatch the corresponding first target radio frequency scanning robot to the distributed material cluster for input operation if the number of the second clusters is equal to 1;

[0129] a second target radio frequency scanning robot determining subunit, configured to use the first target radio frequency scanning robot as the second target radio frequency scanning robot if the number of the second clusters is greater than 1;

[0130] A target distributed material cluster determination subunit is used to take the distributed material cluster corresponding to the second target radio frequency scanning robot as the target distributed material cluster;

[0131] A fourth allocation subunit is used to obtain a second distance between each target distributed material cluster and the corresponding second target radio frequency scanning robot, associate the target distributed material cluster with the smallest second distance with the second target radio frequency scanning robot, and dispatch the second target radio frequency scanning robot to the associated target distributed material cluster to perform input operations;

[0132] A third target radio frequency scanning robot determination subunit is used to determine the remaining radio frequency scanning robots except the first target radio frequency scanning robot among the idle radio frequency scanning robots and use them as the third target radio frequency scanning robots;

[0133] The remaining distributed material cluster determination subunit is used to obtain the target distributed material clusters other than the target distributed material clusters associated with the second target radio frequency scanning robot, and use them as the remaining distributed material clusters;

[0134] The fifth allocation subunit is used to perform scanning operations on the remaining distributed material clusters according to the idle radio frequency scanning robots and the third target radio frequency scanning robots determined in real time.

[0135] The working principle and beneficial effects of the above technical solution are:

[0136] When dispatching RF scanning robots to distributed material clusters for data entry, there are many situations, such as: there are a large number of idle RF scanning robots, and each distributed material cluster can find a corresponding RF scanning robot for data entry; another example: there are a small number of idle RF scanning robots, and it is necessary to first enter data for some distributed material clusters, and then enter data for some distributed material clusters. Therefore, the first cluster number of distributed material clusters is compared with the first robot number of idle RF scanning robots. When the first cluster number is less than or equal to the first robot number, it means that each distributed material cluster can be assigned to at least one RF scanning robot; when the first cluster number is greater than the first robot number, relay data entry is required.

[0137] When relaying data entry, first determine the first target RF scanning robot closest to each distributed material cluster. Since the number of robots is less than the number of distributed material clusters, at least one first target RF scanning robot corresponds to more than one distributed material cluster. Obtain the number of second robots of the first target RF scanning robot, and determine whether the number of second robots of the first target RF scanning robot is consistent with the number of first robots, so as to measure whether each target RF scanning robot participates in the data entry operation. If they are consistent, it means that all RF scanning robots participate in the data entry operation, and dispatch the first target RF scanning robot to the corresponding distributed material cluster for data entry. The correspondence here means that the distance between the distributed material cluster and the first target RF scanning robot is greater than the distance with other RF scanning robots. If there is inconsistency, it means that the RF scanning robot resources are not allocated reasonably. The second cluster number of the distributed material cluster corresponding to the first target RF scanning robot is obtained. If the second cluster number is equal to 1, it means that the first target RF scanning robot corresponds to entering a distributed material cluster. The first target RF scanning robot is dispatched to that distributed material cluster to perform the entry operation. If the second cluster number is greater than 1, it means that the second target RF scanning robot corresponds to multiple distributed material clusters. The second distance between the target distributed material cluster and the corresponding second target RF scanning robot is calculated, and the target distributed material cluster with the smallest second distance is associated with the second target RF scanning robot and the second target RF scanning robot is dispatched to enter. The third target RF scanning robot with the remaining unassigned tasks is dispatched to the remaining distributed material clusters in the target distributed material cluster to perform scanning operations, thereby improving the work efficiency of automated scanning operations.

[0138] In one embodiment, the robot scheduling unit further includes:

[0139] The smart tag signal penetration feature determination subunit is used to determine the smart tag signal penetration feature when the RF scanning robot arrives at the distributed material cluster; wherein the smart tag signal penetration feature is: the identified RF signal emission point and the material code corresponding to the RF signal;

[0140] The first input subunit is used to input the second target material according to the smart tag signal penetration feature; wherein inputting the second target material according to the smart tag signal penetration feature includes: inputting the material code corresponding to the radio frequency signal;

[0141] The recorded material determination subunit is used to determine the second target material that has been currently recorded by the radio frequency scanning robot;

[0142] The second input subunit is used to control the mechanical arm preset on the radio frequency scanning robot to pick up the second target materials that have been input, and after picking up, continue to input the remaining second target materials until all the second target materials on site are input. When picking up the second target materials that have been input, the second target materials that have been input are determined according to the emission point of the radio frequency signal and the mechanical arm is controlled to take them, and continuing to input the remaining second target materials means continuing radio frequency identification and picking up until there is no second target material left at the distributed material cluster.

[0143] The working principle and beneficial effects of the above technical solution are:

[0144] The present invention introduces a smart tag signal penetration feature, and enters the second target material according to the smart tag signal penetration feature and controls the robotic arm to pick up the second target material that has been entered. After picking up, the remaining second target materials continue to be entered until all the second target materials on site are entered. The second target materials are identified in batches, which improves the entry efficiency. The secondary verification and identification of radio frequency identification also avoids the omission of second target materials caused by inaccurate radio frequency signal identification due to obstructions such as packaging.

[0145] The embodiment of the present invention provides a material life cycle tracing method based on smart labels, such as Figure 2 As shown, including:

[0146] Step 1: Enter the material code of the first target material to be managed;

[0147] Step 2: Determine the second target material that needs to be traced and obtain traceability requirement information; the traceability requirement information includes: the material code of the second target material and the traceability template information of the second target material;

[0148] Step 3: Based on the smart label technology, determine the traceability result according to the traceability demand information and the life cycle of the second target material.

[0149] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. The material life cycle traceability system based on smart labels is characterized by: include: The information input subsystem is used to input the material code of the first target material to be managed; The traceability requirement information acquisition subsystem is used to determine the second target material that needs to be traced and obtain the traceability requirement information; The traceability requirement information includes: the material code of the second target material and the traceability template information of the second target material; The traceability result determination subsystem is used to determine the traceability result based on the intelligent label technology, according to the traceability demand information and the life cycle of the second target material.

2. The material life cycle tracing system based on smart labels as claimed in claim 1, characterized in that: Information entry subsystem, including: A coding module, used to encode the first target material and obtain the material code of the first target material; A smart label determination module, used to obtain a smart label of a first target material; The material code entry module is used to enter material codes based on smart labels.

3. The material life cycle tracing system based on smart labels as claimed in claim 2 is characterized in that: Coding module, including: A material type acquisition submodule is used to acquire the material type of the first target material; A first coding position code determination submodule, for determining the first coding position code according to the material type and the first coding position determination library; The material information acquisition submodule is used to acquire the material information of the first target material, the material information including: production date, batch number and product model; A second coding bit code determination submodule, used to determine the second coding bit code according to the material information and the second coding bit determination template; A management information acquisition submodule, used to acquire the management information of the first target material; A third coding bit code determination submodule, used to determine the third coding bit code according to the management information and the third coding bit determination template; The material code determination submodule is used to determine the material code according to the first coding bit code, the second coding bit code and the third coding bit code.

4. The material life cycle tracing system based on smart labels as claimed in claim 1, characterized in that: The traceability requirement information acquisition subsystem includes: A management information determination module, used to parse the material code of the second target material and determine the management information of the second target material; The traceability template information determination module is used to determine the traceability template information according to the current time and the management information of the second target material.

5. The material life cycle tracing system based on smart labels as claimed in claim 1, characterized in that: The traceability result determination subsystem includes: A target entry node determination module, used to determine the target entry node of the second target material according to the current time and the life cycle of the second target material; A tracking information acquisition module, used to obtain tracking information of a second target material according to a target entry node; The tracking result determination module is used to determine the tracking result according to the tracking information and the tracing template information.

6. The material life cycle tracing system based on smart labels as claimed in claim 5, characterized in that: Tracking information acquisition module, including: The node type acquisition submodule is used to acquire the node type of the target input node; the node types include: manually input nodes and machine input nodes; The tracking information first determination submodule is used to obtain the first scanning information of the manual handheld radio frequency scanning terminal when the node type is a manually entered node, and obtain the tracking information according to the first scanning information; The second tracking information determination submodule is used to obtain the second scanning information of the radio frequency scanning robot when the node type is a machine input node, and obtain the tracking information according to the second scanning information.

7. The material life cycle tracing system based on smart labels as claimed in claim 6, characterized in that: The second determination submodule of the tracking information includes: A transport arrival status information acquisition unit, used to acquire the transport arrival status information of the second target material arriving at the management area corresponding to the target entry node; A distribution status determination unit, used to determine the distribution status of the second target material according to the transport arrival status information; A first distance calculation unit, used for calculating a first distance between second target materials according to the distribution situation; A distributed material cluster determining unit, configured to treat the corresponding second target materials as a distributed material cluster if the first distance between the second target materials is less than or equal to a preset first distance threshold; The robot dispatching unit is used to dispatch the radio frequency scanning robot to the distributed material cluster to perform data entry operations.

8. The material life cycle tracing system based on smart labels as claimed in claim 7, characterized in that: Robot dispatch unit, including: A first cluster number obtaining subunit, used to obtain the first cluster number of the distributed material cluster; A first robot number acquisition subunit, used to acquire a first robot number of idle radio frequency scanning robots; A first allocation subunit, configured to allocate at least one radio frequency scanning robot to each distributed material cluster for data entry if the number of the first clusters is less than or equal to the number of the first robots; A first target radio frequency scanning robot determination subunit is used to determine the radio frequency scanning robot closest to the distributed material cluster if the number of the first clusters is greater than the number of the first robots, and use the radio frequency scanning robot as the first target radio frequency scanning robot of the corresponding distributed material cluster; A number determination subunit, used to determine whether the number of second robots of the first target radio frequency scanning robot is consistent with the number of first robots; A second allocation subunit is used to dispatch the first target radio frequency scanning robot to go to the corresponding distributed material cluster to perform input operation if the number of the second robots is consistent with the number of the first robots; A second cluster number calculation subunit, configured to obtain a second cluster number of the distributed material cluster corresponding to the first target radio frequency scanning robot if the second robot number is inconsistent with the first robot number; A third allocation subunit is used to dispatch the corresponding first target radio frequency scanning robot to the distributed material cluster for input operation if the number of the second clusters is equal to 1; a second target radio frequency scanning robot determining subunit, configured to use the first target radio frequency scanning robot as the second target radio frequency scanning robot if the number of the second clusters is greater than 1; A target distributed material cluster determination subunit is used to take the distributed material cluster corresponding to the second target radio frequency scanning robot as the target distributed material cluster; A fourth allocation subunit is used to obtain a second distance between each target distributed material cluster and the corresponding second target radio frequency scanning robot, associate the target distributed material cluster with the smallest second distance with the second target radio frequency scanning robot, and dispatch the second target radio frequency scanning robot to the associated target distributed material cluster to perform input operations; A third target radio frequency scanning robot determination subunit is used to determine the remaining radio frequency scanning robots except the first target radio frequency scanning robot among the idle radio frequency scanning robots and use them as the third target radio frequency scanning robots; The remaining distributed material cluster determination subunit is used to obtain the target distributed material clusters other than the target distributed material clusters associated with the second target radio frequency scanning robot, and use them as the remaining distributed material clusters; The fifth allocation subunit is used to perform scanning operations on the remaining distributed material clusters according to the idle radio frequency scanning robots and the third target radio frequency scanning robots determined in real time.

9. The material life cycle tracing system based on smart labels as claimed in claim 7, characterized in that: The robot dispatching unit also includes: A smart tag signal penetration feature determination subunit is used to determine the smart tag signal penetration feature when the radio frequency scanning robot arrives at the distributed material cluster; The first input subunit is used to input the second target material according to the smart tag signal penetration characteristics; The recorded material determination subunit is used to determine the second target material that has been currently recorded by the radio frequency scanning robot; The second input subunit is used to control the mechanical arm preset on the radio frequency scanning robot to pick up the second target materials that have been input. After picking up, the remaining second target materials continue to be input until all the second target materials on site are input.

10. The material life cycle tracing method based on smart labels is characterized by: include: Step 1: Enter the material code of the first target material to be managed; Step 2: Determine the second target material that needs to be traced and obtain the traceability requirement information; The traceability requirement information includes: the material code of the second target material and the traceability template information of the second target material; Step 3: Based on the smart label technology, determine the traceability result according to the traceability demand information and the life cycle of the second target material.

Citation Information

Patent Citations

  • Warehouse material life-cycle management method and system

    CN106778952A

  • Automobile accessory transaction and full-life-cycle tracing system and method

    CN108470200A

  • Internet of Things based RFID intelligent stocktaking robot system

    CN110587630A

  • Robot cluster task allocation method, system and device and storage medium

    CN113269424A

  • Intelligent checking method and device based on RFID and electronic equipment

    CN117764100A

Cited By

  • Inventory chain node authentication method and device, electronic equipment and storage medium

    CN121544180A

  • Customer bar code tracing management method and system based on block chain

    CN122089346A