Parameter transplantation method and terminal
Through feature learning model and annealing criterion optimization, the problem of low transplant efficiency of injection molding process is solved, the transplant accuracy and consistency of process parameters are improved, and the dependence on the experience of process personnel is reduced.
Patent Information
- Application Number
- CN202411512884.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-28
- Publication Date
- 2024-12-27
- Estimated Expiration
- 2044-10-28
AI Technical Summary
The existing injection molding process has low transplant efficiency and is heavily dependent on the experience of process personnel, and ignores the use of qualified processes before transplantation, resulting in inconsistent product quality.
By obtaining the cavity pressure curves before, after the initial transplant, and after the second transplant, inputting them to the feature learning model, calculating the feature vector and distance, adjusting the solution using the annealing criterion until the iteration termination condition is reached, the second transplant is derived The process parameters afterward.
The efficiency and accuracy of the injection molding process transplantation are improved, the dependence on the experience of process personnel is reduced, and the effective transplantation of process parameters is ensured.
Smart Images

Figure CN119189237A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of parameter transplantation, and in particular to a parameter transplantation method and terminal. Background Art
[0002] In the injection molding production process of plastic products, it is often necessary to transplant the injection molding process parameters from one injection molding machine to another, such as the mold is delivered to the manufacturer after the mold manufacturer tries it out, the manufacturer replaces the old model with the new model, and the order change requires the expansion of production scale. For different models of injection molding machines, the product quality obtained with the same process parameters is inconsistent. Ideally, as long as all the equipment parameters of the original machine and the machine to be transplanted can be obtained, the transplanted process can be obtained through the conversion formula, but the degree of informatization of most domestic injection molding machine manufacturers is relatively shallow, and the acquisition of equipment parameters of foreign injection molding machines is more limited, making it difficult to establish a relatively complete machine database. Even for the same model of injection molding machine, the equipment performance will vary greatly due to screw wear, resulting in inconsistent product quality under the same process parameters. At present, the injection molding process transplantation process relies on the "trial injection"-"correction" mode, which requires process personnel to rely on their own process experience for repeated trial and error. There are problems such as high requirements for process personnel experience and low efficiency, and the use of qualified processes before transplantation is almost completely ignored. Among them, the cavity pressure curve is the "fingerprint" of the injection molding process, which can directly reflect the actual change state of the plastic melt in the cavity. Therefore, ensuring the consistency of the cavity pressure curve before and after process transplantation is an important criterion for ensuring the success of process parameter transplantation. However, there is currently no effective method to use the cavity pressure curve for injection molding process parameter transplantation. Summary of the invention
[0003] The main purpose of this application is to propose a parameter transplantation method and terminal, aiming to solve the problem that the existing injection molding process transplantation is inefficient and heavily dependent on the process experience of process personnel, effectively utilize the information of qualified processes before transplantation, and improve the efficiency and accuracy of injection molding process transplantation.
[0004] To achieve the above purpose, the parameter transplantation method proposed in this application includes: Obtaining a cavity pressure curve of a process before transplantation, a cavity pressure curve of a process after initial transplantation, and a cavity pressure curve of a process after second transplantation, and inputting them into a feature learning model respectively, and obtaining a first feature vector, a second feature vector, and a third feature vector correspondingly; Calculate the first characteristic distance between the first characteristic vector and the second characteristic vector, calculate the second characteristic distance between the first characteristic vector and the third characteristic vector, and calculate the increment between the first characteristic distance and the second characteristic distance, and accept the new solution when the increment is not greater than the threshold value, and accept the new solution according to the annealing criterion when the increment is greater than the threshold value; The steps of loop execution are to obtain the cavity pressure curve of the process before transplantation, the cavity pressure curve of the process after initial transplantation and the cavity pressure curve of the process after second transplantation, and are respectively input into the feature learning model, correspondingly obtaining the first eigenvector, the second eigenvector and the third eigenvector and the steps of calculating the first feature distance between the first eigenvector and the second eigenvector, calculating the second feature distance between the first eigenvector and the third eigenvector, and calculating the increment between the first feature distance and the second feature distance. When the increment is not greater than a threshold, the new solution is accepted. When the increment is greater than the threshold, the new solution is accepted according to the annealing criterion, until the iteration termination condition is reached, the operation ends and returns to derive the second post-transplantation process.
[0005] In one embodiment, the steps of establishing the feature learning model specifically include: Acquire a cavity pressure curve set, perform data alignment processing on all cavity pressure curves in the cavity pressure curve set, and obtain a cavity pressure training data set; A feature learning model is constructed based on the cavity pressure training dataset.
[0006] In one embodiment, the cavity pressure curve set is defined as follows: ; ; Among them, P is the set of cavity pressure curves, is the nth cavity pressure curve, is the pressure value corresponding to the tth sampling point in the nth cavity pressure curve.
[0007] In one embodiment, each of the cavity pressure curves includes a first sampling point, the pressure value corresponding to the first sampling point is the initial pressure value of the cavity, and the first sampling point is the data alignment starting point.
[0008] In one embodiment, the step of obtaining a set of cavity pressure curves includes: The data of each cavity pressure curve in the cavity pressure curve set is subjected to outlier filling correction and noise filtering processing.
[0009] In one embodiment, the step of performing data alignment processing on all cavity pressure curves in the cavity pressure curve set includes: The data of each cavity pressure curve in the cavity pressure curve set is normalized to obtain a cavity pressure sample data set.
[0010] In one embodiment, the normalized calculation formula is: ; ; Among them, X is the sample data set of cavity pressure, is the cavity pressure data corresponding to the i-th cavity pressure curve in the cavity pressure sample data set, is the cavity pressure value corresponding to the kth sampling point.
[0011] In one embodiment, each of the cavity pressure curves includes a second sampling point, a third sampling point, and a fourth sampling point; The pressure value corresponding to the second sampling point is the pressure value when the cavity is filled with plastic melt, the pressure value corresponding to the third sampling point is the maximum pressure value of the cavity, and the pressure value corresponding to the fourth sampling point is the pressure value when the gate solidifies; The form of any one of the first eigenvector, the second eigenvector, and the third eigenvector is: ; in, is the pressure value extracted from any one of the cavity pressure curve of the process before transplantation, the cavity pressure curve of the process after the initial transplantation, and the cavity pressure curve of the process after the second transplantation, , , They are the pressure values corresponding to the second sampling point, the third sampling point, and the fourth sampling point of any one of the cavity pressure curve of the process before transplantation, the cavity pressure curve of the process after the initial transplantation, and the cavity pressure curve of the process after the second transplantation.
[0012] In one embodiment, the calculation formula of the first characteristic distance or the second characteristic distance is: ; in, is the pressure value corresponding to the second eigenvector or the third eigenvector, is the pressure value of the first eigenvector.
[0013] The present application also proposes a terminal, comprising: Memory; and A processor, a parameter transplantation program stored in the memory and executed by the processor, wherein the parameter transplantation program implements the parameter transplantation method as described above when executed by the processor.
[0014] The technical solution of the present application proposes a parameter transplantation method, which includes: obtaining a cavity pressure curve of a process before transplantation, a cavity pressure curve of a process after initial transplantation, and a cavity pressure curve of a process after second transplantation, and inputting them into a feature learning model respectively, and obtaining a first feature vector, a second feature vector, and a third feature vector correspondingly; calculating a first feature distance between the first feature vector and the second feature vector, calculating a second feature distance between the first feature vector and the third feature vector, and calculating an increment between the first feature distance and the second feature distance, and accepting a new solution when the increment is not greater than a threshold value, and accepting the new solution according to an annealing criterion when the increment is greater than the threshold value; looping through the steps; The step is to obtain the cavity pressure curve of the process before transplantation, the cavity pressure curve of the process after the initial transplantation and the cavity pressure curve of the process after the second transplantation, and input them into the feature learning model respectively, and obtain the first eigenvector, the second eigenvector and the third eigenvector and the step is to calculate the first characteristic distance between the first eigenvector and the second eigenvector, calculate the second characteristic distance between the first eigenvector and the third eigenvector, and calculate the increment between the first characteristic distance and the second characteristic distance. When the increment is not greater than the threshold, the new solution is accepted. When the increment is greater than the threshold, the new solution is accepted according to the annealing criterion. When the iteration termination condition is reached, the operation ends and returns to derive the process after the second transplantation. The technical solution of the present application can solve the problems of low efficiency of transplantation of existing injection molding processes and heavy reliance on the process experience of process personnel, effectively utilize the information of qualified processes before transplantation, and improve the efficiency and accuracy of injection molding process transplantation. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present application and, together with the description, serve to explain the principles of the present application.
[0016] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.
[0017] Figure 1 A flow chart of an embodiment of a parameter transplantation method of the present application; Figure 2 A flow chart of another embodiment of the parameter transplantation method of the present application; Figure 3 A flow chart of another embodiment of the parameter transplantation method of the present application; Figure 4 This is a flow chart of another embodiment of the parameter transplantation method of the present application; Figure 5A flow chart of another embodiment of the parameter transplantation method of the present application; Figure 6 A schematic diagram of an embodiment of a parameter transplantation method of the present application; Figure 7 This is the cavity pressure curve diagram of this application; Figure 8 This is a schematic diagram of the circuit function modules of an embodiment of the terminal of the present application.
[0018] Description of Figure Numbers: 100. Terminal; 10. Memory; 20. Processor.
[0019] The realization of the purpose, functional features and advantages of this application will be further explained in conjunction with embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION
[0020] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments of the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0021] In the injection molding production process of plastic products, it is often necessary to transplant the injection molding process parameters from one injection molding machine to another, such as the mold is delivered to the manufacturer after the mold manufacturer tries it out, the manufacturer replaces the old model with the new model, and the order change requires the expansion of production scale. For different models of injection molding machines, the product quality obtained with the same process parameters is inconsistent. Ideally, as long as all the equipment parameters of the original machine and the machine to be transplanted can be obtained, the transplanted process can be obtained through the conversion formula, but the degree of informatization of most domestic injection molding machine manufacturers is relatively shallow, and the acquisition of equipment parameters of foreign injection molding machines is more limited, making it difficult to establish a relatively complete machine database. Even for the same model of injection molding machine, the equipment performance will vary greatly due to screw wear, resulting in inconsistent product quality under the same process parameters. At present, the injection molding process transplantation process relies on the "trial injection"-"correction" mode, which requires process personnel to rely on their own process experience for repeated trial and error. There are problems such as high requirements for process personnel experience and low efficiency, and the use of qualified processes before transplantation is almost completely ignored. Among them, the cavity pressure curve is the "fingerprint" of the injection molding process, which can directly reflect the actual change state of the plastic melt in the cavity. Therefore, ensuring the consistency of the cavity pressure curve before and after process transplantation is an important criterion for ensuring the success of process parameter transplantation. However, there is currently no effective method to use the cavity pressure curve for injection molding process parameter transplantation.
[0022] Based on this, this application proposes a parameter transplantation method, which aims to solve the problem that the existing injection molding process transplantation is inefficient and heavily relies on the process experience of process personnel. It effectively utilizes the information of qualified processes before transplantation and improves the efficiency and accuracy of injection molding process transplantation.
[0023] The parameter transplantation method of the present application can be implemented based on the terminal 100, that is, the parameter transplantation method is mainly executed on the terminal 100, and the terminal 100 is used to establish a communication connection with the injection molding machine before transplantation and the injection molding machine after transplantation via a communication component. Optionally, the terminal 100 can refer to a host computer, a mobile phone or a tablet computer, etc., which is not specifically limited here. The communication component can be a wired communication component or a wireless communication component. For example, when the communication component is a wireless communication component, the wireless communication component can specifically be a WiFi component, a Bluetooth component, or a 3G / 4G / 5G component, which is not specifically limited here.
[0024] It is understandable that, in order to improve the efficiency and accuracy of process transplantation, before the process transplantation, the terminal 100 often needs to establish a feature learning model for the transplantation of the injection molding process.
[0025] In one embodiment of the present application, refer to Figure 1 , Figure 5 and Figure 7 , Figure 1 This is a flow chart of an embodiment of the parameter transplantation method of the present application. Figure 5 This is a schematic diagram of an embodiment of the parameter transplantation method of this application. Figure 7 For the cavity pressure curve diagram of this application, the establishment of the feature learning model specifically includes the following steps: S101, obtaining a cavity pressure curve set, performing data alignment processing on all cavity pressure curves in the cavity pressure curve set, and obtaining a cavity pressure training data set; It can be understood that each injection molding process of the injection molding machine is a molding process of the plastic raw material from solid-liquid-solid. Since the plastic raw material will undergo volume expansion during the transformation from solid to liquid, and volume contraction during the transformation from liquid to solid, after the plastic melt fills the cavity, an additional volume of melt is required to fill the cavity.
[0026] In order to understand the changes in the pressure in the mold cavity during each injection molding process, the injection molding machine before transplantation and the injection molding machine after transplantation respectively include a pressure detection device and a control device. The pressure detection device can be implemented by a pressure sensor, and the control device can be implemented by a controller. The controllers of the injection molding machine before transplantation and the injection molding machine after transplantation respectively establish communication connections with the terminal 100. The pressure sensor is used to detect the pressure generated in the mold cavity and transmit it to the corresponding controller in the form of a signal. The controller processes the received signal and transmits it to the terminal 100. The terminal 100 displays the pressure changes in the mold cavity of the injection molding machine before transplantation or the injection molding machine after transplantation in the form of a curve, such as Figure 7 shown. Figure 7 It can represent the cavity pressure curve of the process before transplantation, and it can also represent the cavity pressure curve of the process after transplantation. Figure 7 In the figure, before 1 o'clock, it means that the plastic melt is filling in the cavity, and the melt has not yet touched the pressure sensor; 1 o'clock means that the plastic melt touches the pressure sensor, and the cavity pressure detected by the pressure sensor; the process from 1 o'clock to 2 o'clock means that the plastic melt continues to fill until the volume in the cavity is completely filled. The pressure rise in this process is the resistance that needs to be overcome during the flow of the plastic melt. The slope is related to the filling speed. The faster the speed, the higher the slope, and vice versa. 2 o'clock means that the plastic melt completely fills the cavity in terms of volume, which is the ideal pressure holding switching point. The pressure holding switching point is specifically the pressure holding switching point of the mold. When the cavity is about to be filled, the screw of the injection molding machine before or after the transplantation switches from flow rate control to pressure control. This conversion point is the pressure holding switching point. The process from 2 to 3 is that the extra volume of plastic melt is filled in the pressure holding stage, the melt density increases, and the pressure rises. 3 represents that the cavity pressure reaches the maximum value. The process from 3 to 4 is that the plastic melt shrinks significantly, while the pressure holding continues, and the cavity pressure drops slowly. 4 represents the end of pressure holding, and the gate of the cavity begins to solidify. After 4, the plastic melt shrinks rapidly until the cavity pressure returns to atmospheric pressure.
[0027] It can be seen that before the process parameters are transplanted, after the injection molding machine before transplantation undergoes multiple injection molding processes, multiple cavity pressure curves of the process before transplantation can be obtained, and a cavity pressure curve set is formed and transmitted to the terminal 100. The terminal 100 aligns the pressure data of all cavity pressure curves of the cavity pressure curve set to obtain a cavity pressure training data set.
[0028] In one embodiment of the present application, the cavity pressure training data set may be defined as follows: ; ; Among them, P is the set of cavity pressure curves, is the nth cavity pressure curve, is the pressure value corresponding to the t-th sampling point in the n-th cavity pressure curve. Specifically, t may refer to, but is not limited to, any point from 1 to 4 in the above embodiment, or any point between 1 and 4. For example, when t is point 1 in the above embodiment, is the pressure value corresponding to 1 point.
[0029] In one embodiment of the present application, each cavity pressure curve includes a first sampling point, and the pressure value corresponding to the first sampling point is set as the data alignment starting point. That is to say, the data of multiple cavity pressure curves are aligned starting from the pressure value corresponding to the first sampling point. In combination with the above embodiment, the first sampling point can be defined as point 1. This is because point 1 indicates that the plastic melt contacts the pressure sensor, and the pressure sensor begins to detect the cavity pressure. In other words, before point 1, the pressure sensor has not detected the cavity pressure, and after point 1, the pressure sensor detects the cavity pressure, and the cavity pressure is always changing. It can be seen that point 1 is the starting point for the pressure sensor to detect the cavity pressure. Taking point 1 as the first sampling point, the data obtained can fully reflect the pressure changes in the cavity, and then reflect the effect of the set process parameters on the injection molding of the plastic.
[0030] In one embodiment of the present application, refer to Figure 2 , Figure 2 This is a flow chart of another embodiment of the parameter transplantation method of the present application, wherein the step of obtaining the cavity pressure curve set includes: S1011, performing outlier filling correction and noise filtering processing on the data of each cavity pressure curve in the cavity pressure curve set.
[0031] In this embodiment, before aligning the data of multiple cavity pressure curves, the data of multiple cavity pressure curves may be subjected to abnormal value filling correction and noise filtering. This is because in the process of injection molding, both the injection molding machine before transplantation and the injection molding machine after transplantation may be abnormal, generating abnormal values and noise. Therefore, by successively performing abnormal value filling correction and noise filtering on the data of multiple cavity pressure curves, the abnormal values and noise values in each cavity pressure curve can be reduced, making the data of each cavity pressure curve more accurate, and can correctly and comprehensively reflect each injection molding situation of the injection molding machine before transplantation or the injection molding machine after transplantation.
[0032] In one embodiment of the present application, refer to Figure 3 , Figure 3 This is a flow chart of another embodiment of the parameter transplantation method of the present application, wherein the step of performing data alignment processing on all cavity pressure curves in the cavity pressure curve set includes: S1012 , normalizing the data of each cavity pressure curve in the cavity pressure curve set to obtain a cavity pressure sample data set.
[0033] In this embodiment, after the data of the plurality of cavity pressure curves are aligned, the data of the plurality of cavity pressure curves may be normalized. The minimum value and the maximum value of each cavity pressure curve are removed by the normalization process to reduce the error of each cavity pressure curve and improve the data accuracy of each cavity pressure curve.
[0034] In one embodiment of the present application, the normalized calculation formula is: ; ; Among them, X is the cavity pressure sample data set, specifically the matrix X, is the cavity pressure data corresponding to the i-th cavity pressure curve in the cavity pressure sample data set, is the cavity pressure value corresponding to the kth sampling point. It should be noted that k is less than n, which means that the number of entries in the matrix X is less than the number of entries in the matrix P, that is, after the multiple cavity pressure curves are normalized, the data are further screened to improve the data accuracy of each cavity pressure curve.
[0035] S102. Construct a feature learning model based on the cavity pressure training data set.
[0036] In this embodiment, after data alignment, the terminal 100 constructs a feature learning model based on the cavity pressure training data set. To improve the accuracy of the feature learning model, in one embodiment of the present application, the terminal 100 can construct a feature learning model based on the cavity pressure training data set that has undergone outlier filling correction, noise filtering, data alignment, and normalization processing.
[0037] In one embodiment of the present application, refer to Figure 4 , Figure 4 This is a flow chart of another embodiment of the parameter transplantation method of the present application, wherein the step of constructing a feature learning model according to the cavity pressure training data set specifically includes: S1021. Establish a sparse autoencoder model; In this embodiment, the sparse autoencoder model is a model pre-stored in the terminal 100. Specifically, the sparse autoencoder model includes an encoder and a decoder, and the encoder and the decoder are respectively implemented by a three-layer fully connected network. Among them, the encoder is used to encode the input data, and the decoder is used to decode the data encoded by the encoder and then output it, that is, the encoder is used as the input of the sparse autoencoder model, and the decoder is used as the output of the sparse autoencoder model.
[0038] S1022. Input the cavity pressure sample data set into the sparse autoencoder model for training to obtain a feature learning model.
[0039] In this embodiment, after the cavity pressure training data set is input into the sparse autoencoder training, a feature learning model can be obtained. That is to say, the cavity pressure training data set is used as the input of the sparse autoencoder model, and the feature learning model is used as the output of the sparse autoencoder model. There must be a training error between the input and output of the sparse autoencoder model. In this embodiment, the training error can be implemented using a loss function. The loss function is expressed as the sum of the reconstruction error term and the sparsity penalty term, where the reconstruction error term is calculated using the mean square error MSE, and the sparsity penalty term is calculated using the KL divergence. By using the gradient descent method to continuously reduce the loss and continuously update the parameters of the feature learning model, the training is completed after the loss is lower than the threshold, and the encoder part is saved as the feature learning model.
[0040] In one embodiment of the present application, refer to Figure 5 , Figure 5 This is a flow chart of another embodiment of the parameter transplantation method of the present application, and the parameter transplantation method includes: S10, obtaining a cavity pressure curve of a process before transplantation, a cavity pressure curve of a process after initial transplantation, and a cavity pressure curve of a process after second transplantation, and inputting them into a feature learning model respectively, to obtain a first feature vector, a second feature vector, and a third feature vector correspondingly; In this embodiment, after the process parameters are transplanted, the transplanted injection molding machine undergoes multiple injection molding processes, and multiple cavity pressure curves of the transplanted process can be obtained and transmitted to the terminal 100. In order to determine whether the cavity pressure curves before and after the process transplantation are consistent, the terminal 100 inputs the cavity pressure curve of a single pre-transplantation process, the cavity pressure curve of the initial post-transplantation process, and the cavity pressure curve of the second post-transplantation process into the feature learning model, respectively, and the first feature vector, the second feature vector, and the third feature vector can be obtained accordingly.
[0041] In one embodiment of the present application, each cavity pressure curve includes a second sampling point, a third sampling point, and a fourth sampling point in addition to the first sampling point. In combination with the above embodiment, the second sampling point can be defined as 2 points, the third sampling point can be defined as 3 points, and the fourth sampling point can be defined as 4 points. The second sampling point is the pressure holding switching point of the injection molding machine before transplantation or the injection molding machine after transplantation, at which time the plastic melt completely fills the cavity; the third sampling point is the maximum point of the cavity pressure of the injection molding machine before transplantation or the injection molding machine after transplantation; the fourth sampling point is the pressure holding end point of the injection molding machine before transplantation or the injection molding machine after transplantation.
[0042] The form of any one of the first eigenvector, the second eigenvector, and the third eigenvector is: ; in, is the extracted pressure value, , , The pressure values corresponding to the second sampling point, the third sampling point and the fourth sampling point of the cavity pressure curve of the process before transplantation, the process after the initial transplantation and the process after the second transplantation are shown in sequence.
[0043] For better understanding, the first eigenvector can be in the form of: ; in, is the pressure value extracted from the cavity pressure curve of the process before transplantation, is the pressure value corresponding to the second sampling point of the cavity pressure curve before transplantation, is the pressure value corresponding to the third sampling point of the cavity pressure curve of the process before transplantation, It is the pressure value corresponding to the fourth sampling point of the cavity pressure curve of the process before transplantation.
[0044] Therefore, according to the form of the first eigenvector, the second eigenvector or the form of the second eigenvector can be inferred, which will not be repeated here.
[0045] S20, calculating a first characteristic distance between the first eigenvector and the second eigenvector, calculating a second characteristic distance between the first eigenvector and the third eigenvector, and calculating an increment between the first characteristic distance and the second characteristic distance, and accepting a new solution when the increment is not greater than a threshold value, and accepting the new solution according to an annealing criterion when the increment is greater than the threshold value; In this embodiment, the terminal 100 compares the first characteristic distance with a threshold value, and the threshold value may be 0. If the first characteristic distance is close to 0, it means that the consistency between the cavity pressure curve of the process after the initial transplantation and the cavity pressure curve of the process before the transplantation is high; if the first characteristic distance is much greater than 0, it means that the consistency between the cavity pressure curve of the process after the initial transplantation and the cavity pressure curve of the process before the transplantation is high. It can be seen that the judgment of the second characteristic distance is similar to the judgment of the first characteristic distance, and no repetition is made here. In order to determine whether there is consistency between the initial transplantation and the secondary transplantation, the terminal 100 calculates the increment between the first characteristic distance and the second characteristic distance, and compares the increment with the threshold value, and the threshold value is specifically 0. When the increment between the first characteristic distance and the second characteristic distance is not greater than 0, it means that there is consistency between the initial transplantation and the secondary transplantation, and the product quality under the same process parameters can be kept consistent. The terminal 100 accepts the new solution, that is, accepts the process after the secondary transplantation, otherwise accepts the new solution according to the annealing criterion.
[0046] In one embodiment of the present application, the calculation formula of the first characteristic distance or the second characteristic distance is: ; Wherein, g is any one of the first characteristic distance and the second characteristic distance, is the pressure value corresponding to the second eigenvector or the third eigenvector, is the pressure value of the first eigenvector.
[0047] For ease of understanding, the calculation formula for the first characteristic distance can be: ; in, is the first characteristic distance, is the pressure value corresponding to the second eigenvector, is the pressure value of the first eigenvector.
[0048] S30, loop execution steps to obtain the cavity pressure curve of the process before transplantation, the cavity pressure curve of the process after initial transplantation and the cavity pressure curve of the process after second transplantation, and input them into the feature learning model respectively, correspondingly obtaining the first eigenvector, the second eigenvector and the third eigenvector and steps to calculate the first feature distance between the first eigenvector and the second eigenvector, calculate the second feature distance between the first eigenvector and the third eigenvector, and calculate the increment between the first feature distance and the second feature distance. When the increment is not greater than the threshold, the new solution is accepted. When the increment is greater than the threshold, the new solution is accepted according to the annealing criterion, until the iteration termination condition is reached, the operation ends and returns to derive the second post-transplantation process.
[0049] In this embodiment, the terminal 100 executes S10 and S20 in a loop and determines whether the iteration termination condition is reached. If the iteration number is reached, it means that the iteration termination condition has been reached, and the operation ends and returns to derive the second post-transplantation process. If the iteration number is reached, it means that the iteration termination condition has not been reached, and then returns to execute S10 and S20 until the iteration termination condition is reached and the output is output.
[0050] The technical solution of the present application proposes a parameter transplantation method, which includes: obtaining a cavity pressure curve of a process before transplantation, a cavity pressure curve of a process after initial transplantation, and a cavity pressure curve of a process after second transplantation, and inputting them into a feature learning model respectively, and obtaining a first feature vector, a second feature vector, and a third feature vector correspondingly; calculating a first feature distance between the first feature vector and the second feature vector, calculating a second feature distance between the first feature vector and the third feature vector, and calculating an increment between the first feature distance and the second feature distance, and accepting a new solution when the increment is not greater than a threshold value, and accepting the new solution according to an annealing criterion when the increment is greater than the threshold value; looping through the steps; The step is to obtain the cavity pressure curve of the process before transplantation, the cavity pressure curve of the process after the initial transplantation and the cavity pressure curve of the process after the second transplantation, and input them into the feature learning model respectively, and obtain the first eigenvector, the second eigenvector and the third eigenvector and the step is to calculate the first characteristic distance between the first eigenvector and the second eigenvector, calculate the second characteristic distance between the first eigenvector and the third eigenvector, and calculate the increment between the first characteristic distance and the second characteristic distance. When the increment is not greater than the threshold, the new solution is accepted. When the increment is greater than the threshold, the new solution is accepted according to the annealing criterion. When the iteration termination condition is reached, the operation ends and returns to derive the process after the second transplantation. The technical solution of the present application can solve the problems of low efficiency of transplantation of existing injection molding processes and heavy reliance on the process experience of process personnel, effectively utilize the information of qualified processes before transplantation, and improve the efficiency and accuracy of injection molding process transplantation.
[0051] The present application also proposes a terminal 100, see Figure 8 The terminal 100 includes a memory 10, a processor 20, and a parameter transplantation program stored in the memory 10 and executable on the processor 20, wherein the parameter transplantation program is configured to implement the steps of the parameter transplantation method.
[0052] The terminal 100 provided by the present application adopts the parameter transplantation method in the above embodiment, which can solve the problem that the transplantation efficiency of the existing injection molding process is low and it is heavily dependent on the process experience of the process personnel, effectively utilizes the information of the qualified process before transplantation, and improves the efficiency and accuracy of the injection molding process transplantation. Compared with the prior art, the beneficial effects of the terminal 100 provided by the present application are the same as the beneficial effects of the parameter transplantation method provided by the above embodiment, and the other technical features in the terminal 100 are the same as the features disclosed in the above embodiment method, which will not be repeated here.
[0053] The above description is only a preferred embodiment of the present application, and does not limit the patent scope of the present application. All equivalent structural changes made by using the contents of the present application specification and drawings under the inventive concept of the present application, or directly / indirectly applied in other related technical fields are included in the patent protection scope of the present application.
Claims
1. A parameter transplantation method, characterized in that: include: Obtaining a cavity pressure curve of a process before transplantation, a cavity pressure curve of a process after initial transplantation, and a cavity pressure curve of a process after second transplantation, and inputting them into a feature learning model respectively, and obtaining a first feature vector, a second feature vector, and a third feature vector correspondingly; Calculate the first characteristic distance between the first characteristic vector and the second characteristic vector, calculate the second characteristic distance between the first characteristic vector and the third characteristic vector, and calculate the increment between the first characteristic distance and the second characteristic distance, and accept the new solution when the increment is not greater than the threshold value, and accept the new solution according to the annealing criterion when the increment is greater than the threshold value; The steps of loop execution are to obtain the cavity pressure curve of the process before transplantation, the cavity pressure curve of the process after initial transplantation and the cavity pressure curve of the process after second transplantation, and are respectively input into the feature learning model, correspondingly obtaining the first eigenvector, the second eigenvector and the third eigenvector and the steps of calculating the first feature distance between the first eigenvector and the second eigenvector, calculating the second feature distance between the first eigenvector and the third eigenvector, and calculating the increment between the first feature distance and the second feature distance. When the increment is not greater than a threshold, the new solution is accepted. When the increment is greater than the threshold, the new solution is accepted according to the annealing criterion, until the iteration termination condition is reached, the operation ends and returns to derive the second post-transplantation process.
2. The parameter transplantation method according to claim 1, characterized in that: The steps of establishing the feature learning model specifically include: Acquire a cavity pressure curve set, perform data alignment processing on all cavity pressure curves in the cavity pressure curve set, and obtain a cavity pressure training data set; A feature learning model is constructed based on the cavity pressure training dataset.
3. The parameter transplantation method according to claim 2, characterized in that: The definition of the cavity pressure curve set is as follows: ; ; Among them, P is the set of cavity pressure curves, is the nth cavity pressure curve, is the pressure value corresponding to the tth sampling point in the nth cavity pressure curve.
4. The parameter transplantation method according to claim 2, characterized in that: Each of the cavity pressure curves includes a first sampling point, a pressure value corresponding to the first sampling point is an initial pressure value of the cavity, and the first sampling point is a data alignment starting point.
5. The parameter transplantation method according to claim 2, characterized in that: The step of obtaining a set of cavity pressure curves includes: The data of each cavity pressure curve in the cavity pressure curve set is subjected to outlier filling correction and noise filtering processing.
6. The parameter transplantation method according to claim 2, characterized in that: After the step of performing data alignment processing on all cavity pressure curves in the cavity pressure curve set, the following steps are included: The data of each cavity pressure curve in the cavity pressure curve set is normalized to obtain a cavity pressure sample data set.
7. The parameter transplantation method according to claim 6, characterized in that: The normalized calculation formula is: ; ; Among them, X is the sample data set of cavity pressure, is the cavity pressure data corresponding to the i-th cavity pressure curve in the cavity pressure sample data set, is the cavity pressure value corresponding to the kth sampling point.
8. The parameter transplantation method according to claim 2, characterized in that: Each of the cavity pressure curves includes a second sampling point, a third sampling point and a fourth sampling point; The pressure value corresponding to the second sampling point is the pressure value when the cavity is filled with plastic melt, the pressure value corresponding to the third sampling point is the maximum pressure value of the cavity, and the pressure value corresponding to the fourth sampling point is the pressure value when the gate solidifies; The form of any one of the first eigenvector, the second eigenvector, and the third eigenvector is: ; in, is the pressure value extracted from any one of the cavity pressure curve of the process before transplantation, the cavity pressure curve of the process after the initial transplantation, and the cavity pressure curve of the process after the second transplantation, , , They are the pressure values corresponding to the second sampling point, the third sampling point, and the fourth sampling point of any one of the cavity pressure curve of the process before transplantation, the cavity pressure curve of the process after the initial transplantation, and the cavity pressure curve of the process after the second transplantation.
9. The parameter transplantation method according to claim 8, characterized in that: The calculation formula of the first characteristic distance or the second characteristic distance is: ; in, is the pressure value corresponding to the second eigenvector or the third eigenvector, is the pressure value of the first eigenvector.
10. A terminal, characterized in that: include: Memory; as well as A processor, a parameter transplantation program stored in the memory and executed by the processor, wherein the parameter transplantation program, when executed by the processor, implements the parameter transplantation method according to any one of claims 1 to 9.
Citation Information
Patent Citations
Methods for determining real molding compound fronts and for comparing simulations
AT523127A1
Injection molding machine debugging method and device, injection molding machine, electronic equipment and storage medium
CN117227122A
Injection molding machine product quality prediction method, device and equipment and storage medium
CN117952311A
Model predictive control apparatus and methods for motion and / or pressure control of injection molding machines
US20030080452A1
State determination device and state determination method
US20230367304A1