Smoke dust purification treatment equipment for zinc oxide production

By using the combined technology of buried shell and lift partition combined with a gas-liquid mixed suction pump and spray head in the zinc oxide production factory, the problem of escape pollution during the smoke loading and unloading is solved, and efficient smoke purification and treatment is achieved. Space savings reduce energy consumption and costs.

CN119281779AActive Publication Date: 2025-01-10XINGHUA BAODA ZINC PRODUCTS FACTORY
View PDF 13 Cites 0 Cited by

Patent Information

Application Number
CN202411247665.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-06
Publication Date
2025-01-10
Estimated Expiration
2044-09-06

AI Technical Summary

Technical Problem

In zinc oxide production plants, after the underground liftable suction equipment collects smoke, a large amount of smoke escapes outward during the smoke loading and unloading process.

Method used

A smoke purification and treatment equipment for zinc oxide production is designed, including buried shells, lifting partitions, conveying pipes, infusion pipes, spray heads, waste drain pipes, collection frames, second hoses and gas-liquid mixed suction pumps , through the combination of a gas-liquid mixed suction pump and a spray head, smoke and dust are suctioned and sprayed to form wastewater mixed with powder, and treated through filtering equipment to prevent smoke and dust from escaping outward.

Benefits of technology

Without occupying the workshop space, efficient smoke and dust purification treatment is achieved, environmental pollution during the smoke loading and unloading process is avoided, smoke and dust purification efficiency is improved, and smoke and dust absorption energy consumption and treatment costs are reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119281779A_ABST
    Figure CN119281779A_ABST
Patent Text Reader

Abstract

The invention relates to the field of smoke dust purification treatment equipment, in particular to smoke dust purification treatment equipment for zinc oxide production, which comprises a buried shell, a lifting partition plate and the like. According to the smoke dust purification treatment equipment for zinc oxide production, smoke dust on the ground is sucked by the gas-liquid mixing suction pump through a vent hole structure of the lifting partition plate, after the smoke dust is sprayed, purified gas and waste water mixed with powder are pumped by the gas-liquid mixing suction pump to the direction of external filtering equipment, and the smoke dust is filtered by the gas-liquid mixing suction pump; under the condition that the floor space of a workshop is not occupied, conventional smoke dust purification treatment work is completed, the collected smoke dust is sprayed in time, in addition, the lifting partition plate can be lifted up to carry out large-range smoke dust purification treatment work, and the smoke dust purification efficiency is improved. The technical defect that after buried lifting suction equipment is used for collecting smoke dust, a large amount of smoke dust escapes outwards to pollute the environment in the smoke dust loading and unloading process is overcome.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of smoke purification equipment, in particular to smoke purification equipment for zinc oxide production. Background Art

[0002] In the workshop and storage workshop of the zinc oxide production plant, there is a lot of smoke and dust in the air. The workshop usually uses a ceiling-mounted spray mechanism to spray and settle the smoke and dust in the air. This treatment method can effectively improve the smoke and dust content in the air, but the liquid sprayed downward will also make the workshop more humid, causing the zinc oxide products placed in the workshop to easily deteriorate when exposed to water. If the method of placing smoke and dust purification devices in batches on the ground is used to replace the ceiling-mounted spray mechanism to clean the smoke and dust, a large area of ​​​​the workshop will be occupied for placing the smoke and dust purification devices. The batch of smoke purification devices leads to the waste of a large area of ​​placement space and passage space in the workshop. The Chinese patent with publication number CN111467887A discloses an underground dust removal system, which uses an underground liftable suction device to suck the smoke at ground level, which can solve the problem of zinc oxide product deterioration when exposed to water and the problem of the placement of smoke purification devices occupying a large area of ​​space in the workshop. However, after the system collects and absorbs the smoke into a waste collection room, during the loading and unloading process of the smoke collected in the waste collection room, a large amount of smoke still escapes to the outside and pollutes the environment. Summary of the invention

[0003] In order to overcome the disadvantage that in zinc oxide production, after using underground liftable suction equipment to collect smoke, a large amount of smoke escapes and pollutes the environment during the smoke loading and unloading process, the present invention provides a smoke purification treatment device for zinc oxide production.

[0004] The technical implementation scheme of the present invention is: a smoke purification and treatment equipment for zinc oxide production, including an underground shell, a lifting partition, a delivery pipe, a liquid infusion pipe, a first hose, a spray head, a waste pipe, a collection frame, a second hose and a gas-liquid mixing suction pump; a lifting partition is slidably connected in the underground shell; the lifting partition is provided with a plurality of vent structures; the lifting partition is provided with a plurality of ventilation vertical slot structures connected to the vent structures, and the ventilation vertical slot structures are located below the vent structures; no less than two electric push rods are installed in the underground shell; the electric push rods are provided with a plurality of ventilation vertical slot structures connected to the ventilation vertical slot structures, and the ventilation vertical slot structures are located below the ventilation vertical slot ... The telescopic end of the movable push rod is fixedly connected to the lifting partition; the delivery pipe and the waste pipe are fixedly connected in sequence in the underground shell; the infusion pipe is fixedly connected in the lifting partition; the infusion pipe and the delivery pipe are commonly connected with a first hose; the infusion pipe is connected with a plurality of sprinkler heads; the lifting partition is fixedly connected with a collecting frame, and the collecting frame is located below the infusion pipe; the collecting frame and the waste pipe are commonly connected with a plurality of second hoses; a gas-liquid mixing suction pump is installed in the underground shell; the inlet end of the gas-liquid mixing suction pump is connected with the waste pipe; the outlet end of the gas-liquid mixing suction pump is connected with a discharge pipe.

[0005] Preferably, a sealing ring is installed on the buried shell; the sealing ring is wrapped around the outer surface of the lifting partition, and the sealing ring is located between the ventilation hole and the ventilation vertical groove of the lifting partition.

[0006] Preferably, a plurality of photosensitive sensors are installed on the lifting partition.

[0007] Preferably, an electric control valve for controlling the spray flow rate is installed on the spray head.

[0008] Preferably, a plurality of smoke sensors are installed on the lifting partition.

[0009] Preferably, a plurality of air guide tubes are installed on the collection frame; and an exhaust fan is installed in the air guide tube.

[0010] Preferably, the air guide cylinder is configured as a bucket-shaped structure that contracts downward toward the adjacent second hose.

[0011] Preferably, the air guide tube is connected to two air extraction scoops; the air extraction scoops are provided with air extraction hole structures; the air extraction hole structures of the air extraction scoops are aligned with the air vent structures of the lifting partition.

[0012] Preferably, the discharge pipe of the gas-liquid mixing suction pump is connected to an air supply pipe; the air supply pipe is connected to a diversion pipe, and the diversion pipe is provided with no less than two outlet ends; the outlet end of the diversion pipe is connected to an underground exhaust box; the underground exhaust box is provided with an air outlet structure.

[0013] Preferably, the air outlet structure of the underground exhaust box faces the lifting partition.

[0014] The present invention has the following advantages: the present invention is a smoke purification treatment equipment for zinc oxide production, wherein the buried shell and the lower side of the lifting partition are buried under the ground, and the smoke on the ground is sucked by the gas-liquid mixed suction pump through the vent structure of the lifting partition, and the smoke sucked into the lifting partition is sprayed by the infusion pipe through the spray head, and the smoke and the spray liquid together form wastewater mixed with powder, and the gas sucked into the lifting partition with the smoke completes the smoke purification treatment, and the purified gas and the wastewater mixed with powder are mixed by gas and liquid The suction pump pumps toward the external filtering equipment, completes the routine smoke purification work without occupying the floor space of the workshop, and sprays the collected smoke in time, avoiding environmental pollution during the later loading and unloading of smoke. When the smoke sensor recognizes that the smoke concentration in the workshop increases, the electric push rod brakes and pushes the lifting partition upward. At the same time, the gas-liquid mixed suction pump uses higher suction power through the vent structure and ventilation vertical slot structure of the lifting partition to perform large-scale smoke purification in the workshop, thereby improving the purification efficiency of smoke. The smoke purification treatment equipment for zinc oxide production of the present invention overcomes the technical disadvantage that after collecting the smoke with underground liftable suction equipment, a large amount of smoke escapes and pollutes the environment during the smoke loading and unloading process. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 A schematic diagram for describing the structure of the present invention; Figure 2 A cross-sectional view of the buried shell structure for describing the present invention; Figure 3 A schematic diagram of the structure of the electric push rod and the lifting partition of the present invention is provided; Figure 4 A schematic diagram of the local structure of the lifting partition of the present invention is provided; Figure 5 A cross-sectional view of the local structure of the lifting partition of the present invention is provided; Figure 6 A schematic diagram of the partial structure of the liquid infusion tube and the shower head of the present invention is provided; Figure 7 A cross-sectional view of the local structure of the collection frame of the present invention is provided; Figure 8 A cross-sectional view of the collecting frame and the air guide tube structure of the present invention is described; Fig. 9 A schematic diagram of the structure of the shunt pipe and the buried exhaust box of the present invention is provided; Fig.10 A schematic diagram of the exhaust pipe and gas pipe structure of the present invention is provided; Fig.11 This is an enlarged view of the F region structure for describing the present invention.

[0016] The markings of the components in the accompanying drawings are as follows: 1-underground shell, 11-sealing ring, 2-lifting partition, 201-vent, 202-vent vertical slot, 21-electric push rod, 22-photosensitive sensor, 23-smoke sensor, 3-delivery pipe, 31-liquid infusion pipe, 32-first hose, 33-sprinkler head, 34-electric control valve, 4-waste discharge pipe, 41-collection frame, 42-second hose, 43-gas-liquid mixing suction pump, 431-discharge pipe, 51-air guide tube, 52-exhaust fan, 53-exhaust bucket, 530-exhaust hole, 61-gas supply pipe, 62-diversion pipe, 63-underground exhaust box, 630-air outlet. DETAILED DESCRIPTION

[0017] In order to make the purpose, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings. It is hereby stated that the directional terms such as up, down, left, right, front, back, inside, outside, etc. that appear or will appear in the text of the present invention are only based on the accompanying drawings of the present invention, and are not specific limitations of the present invention.

[0018] Example 1 A smoke purification and treatment equipment for zinc oxide production, such as Figure 1-Figure 8 As shown, it includes an underground shell 1, a lifting baffle 2, a photosensitive sensor 22, a delivery pipe 3, a liquid infusion pipe 31, a first hose 32, a spray head 33, a waste pipe 4, a collection frame 41, a second hose 42 and a gas-liquid mixing suction pump 43; the lifting baffle 2 is slidably connected to the buried shell 1, and the lower sides of the buried shell 1 and the lifting baffle 2 are buried below the ground; a number of photosensitive sensors 22 are installed on the lifting baffle 2; a number of vent holes 201 structures are respectively opened on the front upper side and the rear upper side of the lifting baffle 2; a number of ventilation vertical grooves 202 structures connected to the ventilation hole 201 structures are respectively opened on the front side and the rear side of the lifting baffle 2, and the ventilation vertical grooves 202 structures are located below the ventilation hole 201 structures; two electric push rods 21 are installed in the buried shell 1; the telescopic ends of the two electric push rods 21 are fixedly connected together A lifting partition 2; a delivery pipe 3 and a waste pipe 4 are fixedly connected in sequence in the buried shell 1; a liquid infusion pipe 31 is fixedly connected in the lifting partition 2; two first hoses 32 are commonly connected between the liquid infusion pipe 31 and the delivery pipe 3; a plurality of spray heads 33 are connected to the liquid infusion pipe 31; the delivery pipe 3 is externally connected to a spray liquid circulation and delivery device; a collecting frame 41 is fixedly connected in the lifting partition 2, and the collecting frame 41 is located below the liquid infusion pipe 31; a plurality of second hoses 42 are commonly connected between the collecting frame 41 and the waste pipe 4; a gas-liquid mixing suction pump 43 is installed in the buried shell 1; the inlet end of the gas-liquid mixing suction pump 43 is connected to the waste pipe 4; the outlet end of the gas-liquid mixing suction pump 43 is connected to a discharge pipe 431; the discharge pipe 431 is externally connected to a filtering device; the drain outlet of the external filtering device is connected to the water inlet of the external spray liquid circulation and delivery device.

[0019] like Figure 3 As shown, a sealing ring 11 is installed on the buried shell 1; the sealing ring 11 is wrapped around the outer surface of the lifting partition 2, and the sealing ring 11 is initially located between the vent hole 201 and the ventilation vertical groove 202 of the lifting partition 2.

[0020] like Figure 3 and Figure 6 As shown, each spray head 33 is equipped with an electric control valve 34 for controlling the spray flow rate; and a plurality of smoke sensors 23 are installed on the lifting partition 2.

[0021] The conventional fume purification process of the fume purification equipment for zinc oxide production of the present invention is as follows.

[0022] The lower sides of the buried shell 1 and the lifting partition 2 are initially buried below the ground, and only the vent hole 201 structure area of ​​the lifting partition 2 is above the ground, while the upper surface of the lifting partition 2 is an upwardly arched trapezoidal structure. This concealed buried design not only does not occupy the placement space and passage space in the workshop, but the trapezoidal structure on the upper surface of the lifting partition 2 can also be used as a ground speed bump for transport vehicles and pedestrians in the workshop to pass. At the same time, the gas-liquid mixing suction pump 43 operates in a low-power state through the exhaust pipe 4 and the second hose 42 in the lifting partition 2 to perform suction work, so that the smoke and dust in the external gas can pass through the vent hole 201 structure of the lifting partition 2 and enter the interior of the lifting partition 2. At the same time, the external spray liquid circulation conveying equipment conveys the spray liquid to the infusion pipe 31 through the conveying pipe 3. Spray liquid, under the flow control of the electric control valve 34, the spray head 33 initially sprays the spray liquid downward at a low flow state, and the spray liquid sprays the smoke sucked into the lifting partition 2. The smoke and the spray liquid together form wastewater mixed with powder, so that the gas sucked into the lifting partition 2 can complete the smoke purification treatment. At the same time, under the suction of the gas-liquid mixing suction pump 43, the purified gas and the wastewater mixed with powder are pumped toward the external filtering device along the collecting frame 41, the second hose 42 and the waste discharge pipe 4. After the filtering device filters the wastewater mixed with powder into clean spray liquid, the spray liquid flows back to the external spray liquid circulation and conveying equipment for circulating spraying, and the purified gas entering the filtering device is directly discharged to the outside.

[0023] The steps of large-scale smoke purification treatment of smoke purification treatment equipment for zinc oxide production of the present invention are as follows.

[0024] In conventional smoke purification work, if the smoke concentration in the workshop suddenly increases, the smoke concentration sucked into the lifting partition 2 will also increase. At this time, the spray liquid sprayed downward at a low flow rate cannot completely spray and treat the smoke. Therefore, when high-concentration smoke flows through the smoke sensor 23, the smoke sensor 23 will be triggered. The smoke sensor 23 immediately sends a signal to switch to high-power operation to the gas-liquid mixing suction pump 43 through the circuit system to increase the suction power of the smoke. At the same time, the smoke sensor 23 also immediately sends a start signal to the electric push rod 21 through the circuit system, and the electric push rod 21 pushes the lifting partition 2. The partition 2 rises upward, allowing the ventilation vertical groove 202 of the lifting partition 2 to leave the sealing ring 11 upward and be exposed above the ground, so as to perform large-scale suction work on the smoke in the workshop, and promptly suck the smoke in the workshop into the lifting partition 2. At the same time, the smoke sensor 23 immediately sends a signal to switch to high-flow control to the electric control valve 34 aligned in the upward and downward directions through the circuit system, so that the spray head 33 entering the corresponding area with high-concentration smoke can spray the spray liquid downward at a high-flow state, so that the high-concentration smoke can be sprayed in time, and the air in the area with high-concentration smoke can be purified in time without wasting the spray liquid.

[0025] During the process of the electric push rod 21 pushing the lifting partition 2 upward, when the photosensor 22 on the lifting partition 2 is blocked by the passing or stopping transport vehicles and pedestrians, the electric push rod 21 will not push the lifting partition 2 upward. Only when the passing or stopping transport vehicles and pedestrians leave the top of the lifting partition 2 without blocking the photosensor 22, the electric push rod 21 will resume pushing the lifting partition 2 upward, to prevent the rising lifting partition 2 from lifting the passing or stopping transport vehicles and pedestrians upward and causing damage.

[0026] Example 2 On the basis of Example 1, Figure 1-Figure 8 As shown, a plurality of air guide tubes 51 are installed on the collection frame 41 of the present embodiment; an exhaust fan 52 is installed in each air guide tube 51; the lower end of each air guide tube 51 is configured as a bucket-shaped structure that contracts downward toward the adjacent second hose 42; two front and rear exhaust scoops 53 are connected to the air inlet of the air guide tube 51; the two exhaust scoops 53 are each provided with a plurality of exhaust holes 530 structures; the exhaust holes 530 structures of the two exhaust scoops 53 are respectively aligned with the ventilation holes 201 structures on the front and rear sides of the lifting partition 2.

[0027] In conventional smoke purification work, the gas-liquid mixed suction pump 43 does not need to perform suction work, and only the exhaust fans 52 in each air guide tube 51 perform suction work downward together, so that all the exhaust fans 52 can pass through the exhaust hole 530 structure of the exhaust hopper 53, and respectively close to the vent hole 201 structure in each area of ​​the lifting partition 2 to perform smoke suction work synchronously. This can not only make the vent hole 201 structure in each area of ​​the lifting partition 2 have a uniform smoke suction force, but also improve the smoke suction effect in different areas. In this process, since the working power of the exhaust fan 52 is much smaller than the working power of the gas-liquid mixed suction pump 43, it can also greatly reduce the smoke suction energy consumption consumed in conventional smoke purification work and reduce the cost of smoke purification work.

[0028] Example 3 On the basis of Example 1, Figure 1-Figure 11 As shown, the discharge pipe 431 of the gas-liquid mixing suction pump 43 of the present embodiment is connected to the air supply pipe 61; the air supply pipe 61 is connected to the diverter pipe 62, and the diverter pipe 62 is provided with six outlet ends; the six outlet ends of the diverter pipe 62 are respectively connected to an underground exhaust box 63, and the underground exhaust box 63 is installed on the ground, and the air supply pipe 61 and the diverter pipe 62 are both buried under the ground; the six underground exhaust boxes 63 are all provided with a plurality of air outlet holes 630 structures; the air outlet holes 630 structures of the six underground exhaust boxes 63 are all facing the lifting partition 2.

[0029] During the process that the gas-liquid mixing suction pump 43 continuously conveys the purified gas and wastewater mixed with powders to the external filtering equipment, when the purified gas and wastewater mixed with powders flow through the discharge pipe 431, the wastewater mixed with powders will directly flow to the external filtering equipment for filtering and purification. Since the purified gas will encounter greater flow resistance when flowing to the filtering equipment, the purified gas will preferentially choose to flow along the gas transmission pipe 61 through the diversion pipe 62, and then be discharged from the air outlet 630 structure of each buried exhaust box 63 toward the lifting baffle 2. During the period when the purified gas flows along the ground to the lifting baffle 2, the smoke and dust settled on the ground away from the lifting baffle 2 can be blown toward the air vent 201 of the lifting baffle 2, thereby improving the suction effect of the lifting baffle 2 on the smoke and dust settled on the ground at a long distance.

[0030] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A smoke purification and treatment device for zinc oxide production, comprising: an underground shell (1); Its characteristics are: It also includes a lifting partition (2); A lifting partition (2) is slidably connected in the buried shell (1); the lifting partition (2) is provided with a plurality of ventilation holes (201) structures; the lifting partition (2) is provided with a plurality of ventilation vertical slots (202) structures connected to the ventilation holes (201) structures, and the ventilation vertical slots (202) structures are located below the ventilation holes (201) structures; at least two electric push rods (21) are installed in the buried shell (1); the telescopic ends of the electric push rods (21) are fixedly connected to the lifting partition (2); a conveying pipe (3) and a waste discharge pipe (4) are fixedly connected in sequence in the buried shell (1); a liquid infusion pipe (3) is fixedly connected in the lifting partition (2) 1); a first hose (32) is commonly connected between the infusion tube (31) and the delivery tube (3); a plurality of spray heads (33) are connected to the infusion tube (31); a collection frame (41) is fixedly connected inside the lifting partition (2), and the collection frame (41) is located below the infusion tube (31); a plurality of second hoses (42) are commonly connected between the collection frame (41) and the waste discharge pipe (4); a gas-liquid mixing suction pump (43) is installed inside the buried shell (1); an inlet end of the gas-liquid mixing suction pump (43) is connected to the waste discharge pipe (4); and an outlet end of the gas-liquid mixing suction pump (43) is connected to the discharge pipe (431).

2. A smoke purification treatment equipment for zinc oxide production according to claim 1, characterized in that: A sealing ring (11) is installed on the buried shell (1); the sealing ring (11) is wrapped around the outer surface of the lifting baffle (2), and the sealing ring (11) is located between the vent hole (201) and the ventilation vertical groove (202) of the lifting baffle (2).

3. A smoke purification treatment equipment for zinc oxide production according to claim 1, characterized in that: A plurality of photosensitive sensors (22) are mounted on the lifting partition (2).

4. A smoke purification treatment equipment for zinc oxide production according to claim 1, characterized in that: An electric control valve (34) for controlling the spray flow rate is installed on the spray head (33).

5. A smoke purification treatment equipment for zinc oxide production according to claim 1, characterized in that: A plurality of smoke sensors (23) are mounted on the lifting partition (2).

6. A smoke purification treatment equipment for zinc oxide production according to claim 1, characterized in that: A plurality of air guide tubes (51) are installed on the collection frame (41); an exhaust fan (52) is installed in the air guide tube (51).

7. A smoke purification treatment equipment for zinc oxide production according to claim 6, characterized in that: The air guide cylinder (51) is configured as a bucket-shaped structure that contracts downwardly toward the adjacent second hose (42).

8. A smoke purification treatment equipment for zinc oxide production according to claim 6, characterized in that: The air guide tube (51) is connected to two air extraction hoppers (53); the air extraction hoppers (53) are provided with air extraction holes (530) structures; the air extraction holes (530) structures of the air extraction hoppers (53) are aligned with the air vents (201) structures of the lifting partition (2).

9. A smoke purification treatment equipment for zinc oxide production according to any one of claims 1 to 8, characterized in that: The discharge pipe (431) of the gas-liquid mixing suction pump (43) is connected to an air supply pipe (61); the air supply pipe (61) is connected to a flow distribution pipe (62), and the flow distribution pipe (62) is provided with at least two outlet ends; the outlet end of the flow distribution pipe (62) is connected to an underground exhaust box (63); and the underground exhaust box (63) is provided with an air outlet hole (630) structure.

10. A smoke purification treatment equipment for zinc oxide production according to claim 9, characterized in that: The air outlet hole (630) of the underground exhaust box (63) is structured to face the lifting partition (2).

Citation Information

Patent Citations

  • Buried dust removal system

    CN111467887A

  • Dust conveying device for metallurgical machinery

    CN112122992A

  • Hidden lifting dust removal mechanism for flywheel shell machining workshop

    CN113798265A

  • Energy-saving and environment-friendly dust removal and recovery system for concrete mixing plant

    CN116352888A

  • Intelligent environment-friendly assembly type fence device based on BIM and installation method